+ All Categories
Home > Documents > Bells Line of Road Corridor Study - Transport for NSW

Bells Line of Road Corridor Study - Transport for NSW

Date post: 05-Feb-2022
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
20
Bells Line of Road Corridor study SUMMARY NOVEMBER 2005
Transcript

Bells Line of RoadCorridor study

SUMMARY

NOVEMBER 2005

Foreword

The NSW and Australian governments have committed funding to investigate the feasibility of upgrading the Bells Line of Road to become a major freight routebetween Lithgow and north-western Sydney.

The existing crossings of the Blue Mountains include the Great Western

Highway (primary route), Bells Line of Road (secondary route) and the Main

Western Rail Line.All have major limitations to their use as significant transport

corridors across the Blue Mountains.

The two road options are limited by very steep grades, tight curves and limited

overtaking opportunities. Rail use is also constrained by freight and passenger

rail having to share the same track.This, along with the steep grades, tight track

curvature and limited opportunities for commuter trains to overtake freight

trains, constrains rail in substantially increasing the amount of freight it is able to

transport across the Blue Mountains.

The Bells Line of Road Corridor Study concluded that:

The Main Western Rail Line over the Blue Mountains could be upgraded but

any upgrade would be unlikely to deliver significant benefits without major

upgrades east of Penrith and west of Lithgow.

All of the road upgrade options examined are feasible from an engineering

perspective.

None of the four-lane, B-Double road upgrade options examined appear feasible

from an economic or financial perspective for a range of growth assumptions.

All of the four-lane B-Double capable upgrade options would require the

full regional and economic development growth potential of the Central

West region to be realised over the next 30 years for the project to

progress towards being justified economically.

It is highly unlikely that private investment would be forthcoming to progress

this project without significant government funding.

All of the four-lane, B-Double road upgrade options, including the preferred

option would have significant environmental and social impacts.

Reserving a road corridor to enable future upgrade works along the Bells

Line of Road is complex and is likely to result in the need for detailed and

comprehensive environmental assessment and approval from the

Commonwealth and State governments. It is also likely to require funding

for property acquisition of approximately $230 million in 2004 dollars.

This Summary provides an overview of the Bells Line of Road Corridor Study.

INTRODUCTION 03

STRATEGIC CONTEXT 04

OPTIONS CONSIDERED 07

KEY CONSTRAINTS 09

SELECTION OF THE PREFERRED OPTION 13

NEED AND JUSTIFICATION 15

Contents

ADDENDUM: A typographical error was corrected in June

2008 in the table at the bottom of page 12. The dollar

value estimates for the Eastern to Richmond Road and

Western precincts had been inadvertently transposed.

NOTE: This version of the summary has been amended

to incorporate changes to the Environmental Planning &

Assessment Act 1979 that became active in August 2005.

Bells Line of Road corridor study Summary 3

Sydney

Newcastle

Wollongong

GoulburnYass

Denman

Dubbo

Parkes

Cowra

Bathurst

Lithgow

West Wyalong

Young

Cootamundra

Orange

0 25

Kilometres

50

LEGEND

B-Double Route

After a number of strategic studies during the 1990s,

the NSW Government committed $360 million to the

upgrade of the Great Western Highway and the Mitchell

Highway between Penrith and Orange over a 12-year period.

The Australian Government also contributed $100 million to

enable works in the Blue Mountains to be accelerated.These

works are expected to result in significant improvements to

the primary Blue Mountains crossing.

Some stakeholders in NSW’s Central West are of the opinion

that the lack of an efficient freight route across the Blue

Mountains is constraining regional growth. They are also

concerned that there is B-Double vehicle access to the Sydney

area from the north and south but not from the west.They are

of the view that this represents inequitable access to regional

markets and a major constraint to growth.

Introduction

The NSW and Australian governments have committed funding to investigate the feasibility of upgrading the Bells Line of Road, between Lithgow and north-western Sydney, to B-Double (greater than 19m long) standard.The NSW Roads and Traffic Authority (RTA), in partnership withthe Federal Department of Transport and Regional Services (DOTARS), is managing the study.

B-Double (greater than 19m long) approved routes

As a result, the RTA has engaged Sinclair Knight Merz to

undertake a Corridor Study to:

Review existing options to provide a link

between Lithgow and the Westlink M7

(formerly known as the Western Sydney Orbital).

Identify the option that best meets the needs

of heavy vehicle access between Sydney and

the Central West of NSW.

Assess the feasibility of a high standard road

across the Blue Mountains along the Bells Line

of Road corridor.

Develop a concept design for the best of

the four-lane options, to meet B-Double

standards.

N

Bells Line of Road corridor study Summary

HISTORY OF THE ROUTE

Bells Line of Road is rich in history reaching back to the early

days of British settlement of the then young colony of New

South Wales. At that time, the Blue Mountains constituted a

visible and real boundary to the pioneers who were confined

to the relatively narrow coastal plain.

A route to the south of the Grose River, clinging to the ridges,

was finally established with the aid of Aboriginal people in

1813.The current alignment of the Great Western Highway

essentially follows this route.A separate route to the north of

the Grose River did not reach the Bathurst Plains until 1823

when Archibald Bell (Junior) established its viability in a series

of three journeys in that year.

Despite some initial enthusiasm for Bell's more direct route,

the Great Western Highway remained the dominant route.

As a result very little public money was expended on

improving the dangerous pinches on the Bells Line of Road,

which remained primarily a stock route until well into the

twentieth century.

EXISTING ROLE

Bells Line of Road provides a secondary crossing of the Blue

Mountains supporting the Great Western Highway.This role

is clear when looking at the comparison of the daily traffic

volumes in the diagram opposite on p5.

In addition to its supplementary role

Bells Line of Road also provides:

Access to properties along the route.

Local access for Bilpin and Kurrajong areas.

Recreation and tourism access.

Firebreak and emergency access.

EXISTING CONDITION

Adjacent land uses

The major land uses in the vicinity of Bells Line of Road

are conservation and recreation, and rural production.

In terms of land use, the study area can essentially be divided

into four sections:

The eastern section, east of the Blue Mountains

escarpment at Kurrajong Heights, which includes the

Cumberland Plain, was a mix of urban and village areas,

urban fringe areas and rural production, and scattered,

generally isolated conservation areas.

The mid-eastern section, from Kurrajong Heights to

Mt Tomah, which includes generally rural uses following

the ridgeline adjacent to the road.

The mid-western section, which includes predominantly

conservation related land uses within National Parks,

World Heritage Areas and Wilderness Areas between

Mt Tomah and Newnes Junction.

The western section, between Newnes Junction and

Lithgow, which includes a mix of forestry and open

grazing land, resource mining and the city of Lithgow.

Strategic context

Bells Line of Road has been investigated as a freight route across the Blue Mountains since the earliest days of European settlement.With the competing local and through-traffic demands along the Great Western Highway some stakeholders in NSW’s Central West have been promoting an upgraded Bells Line of Road as a strategic regional development link between that region and the Sydney metropolitan area.

4

St Davids Anglican church on Bells Line of Road at Kurrajong Heights.

Bells Line of Road corridor study Summary5

The listing of the Blue Mountains World Heritage Area, the

identification of Bilpin as an ecological gateway and the high

biodiversity value adjacent to much of the route limit the

range of land uses able to be pursued and also place

constraints on existing land uses.

Traffic flows

As can be seen in the diagram on the right, traffic volumes

vary significantly along the route. Traffic flows increase

significantly at either end of the route with approximately

8,000 vehicles per day (vpd) in the west (influenced by

Lithgow) and approximately 12,000 vpd in the east (influenced

by Richmond). This compares with about 3,000 vpd in the

central area.

Weekend traffic along Bells Line of Road is approximately 60%

higher than weekday traffic indicating its tourist value.

Traffic volumes have remained similar since the mid 1970s for

much of the route.The exception to this is the eastern section

where Sydney’s growth to the west and north-west has seen

a steady increase in traffic using Bells Line of Road.

Travel times

Travel over the Blue Mountains along the existing Bells Line of

Road is generally faster, from end to end (as seen in the table

below), than the slightly longer journey via the Great Western

Highway.

Travel speeds are lower on weekends when weekend tourist

traffic increases. The sections of Bells Line of Road around

Bellbird Hill and Mt Tomah that are steep and winding slow

travels speeds significantly in these areas.The travel speed in

the vicinity of North Richmond is also slow due to intersection

performance and additional traffic.

Road safety

Bells Line of Road has a high accident rate, particularly in

the areas around Lithgow and towards Kurrajong, where

features of the existing road have contributed to accidents

in a number of cases.The accident rate is higher on Bells

Line of Road than the State average and higher than the

Great Western Highway.

Over 120 serious injury accidents occur each year on

Bells Line of Road. Investigation of the accident data

indicated that:

There were 564 accidents recorded between 1994-1998

and 545 between 1998-2002 indicating that the accident

rate has remained fairly constant, but nevertheless

is too high.

In more remote areas along the route most accidents

involved vehicles leaving the road.

The highest proportion of accidents involving heavy-goods

vehicles was between Kurrajong Heights and Newnes

Junction, many of these were vehicles leaving the road

and steep grades were attributable in a number of cases.

Eleven of the 13 fatal accidents recorded occurred

between Kurrajong Heights and Newnes Junction.

8000

3000

Bells Line Road

SECTION 1

Lithgow

Katoomba Glenbrook

RichmondSECTION 2SECTION 3

12,000

34,00022,000

14,000

Existing traffic volumes of Blue Mountains crossings

AVERAGE TRAVEL TIMES BETWEEN LITHGOW AND THE M7

ROUTE DISTANCE (KM FROM LITHGOW TO M7) AVERAGE TRAVEL TIME (TO NEAREST 5 MINUTES)

WESTBOUND EASTBOUND

TRUCKS CARS TRUCKS CARS

BELLS LINE OF ROAD 81 90 65 85 70

GREAT WESTERN HIGHWAY 89 100 85 95 85

Bells Line of Road corridor study Summary6

Travel patterns

The results from a truck origin /destination survey for both

Bells Line of Road and the Great Western Highway are

described below.The predominant trip end region is Western

NSW, which accounts for the majority of origins and

destinations for westbound trips.The main points to note from

the survey are that:

Bathurst, Orange and Oberon account for almost 80%

of origins and destinations in that region.

Orange produces a significant amount of manufactured

goods and receives a large amount petroleum to support

these industries.

Bathurst attracts a high proportion of building material

freight to the region due to its continuing residential

growth.

Approximately 50% of eastbound truck traffic travelling

to Sydney is destined east of the Westlink M7.

Almost all building materials and consumables are carried

on the Great Western Highway. One-third of trucks on

Bells Line of Road travel empty.The route also carries a

significant amount of farming and forestry cargo.

The typical journey length is between three and five hours

which corresponds to the approximate time taken for the

journey between Sydney and Lithgow/Bathurst.

Road design

Due to the mountainous terrain, the road has a high degree

of curvature resulting in at least 35% of the 81km from

Richmond to Lithgow is subject to advisory speeds of less than

100km/hr.

Steep gradients are common. Six percent of the route has

grades in excess of 10% (13% maximum) and 34% has grades

between 4% and 10%.With most fully-laden trucks travelling

at speeds of less than 50km/hr when sustained uphill grades

exceed 4% to 6%, Bells Line of Road, in its current condition,

would not be suitable as a designated truck route and would

not be able to cater for B-Double vehicles.

A further limitation to B-Doubles using Bells Line of Road is

that the tight curves result in the swept path of long vehicles

exceeding existing lane widths.This means that long vehicles

are sometimes forced to cross the centreline or have wheels

running outside the edge of the pavement which are both

unsatisfactory from a road safety perspective.

OTHER INVESTIGATIONS

A number of strategic studies and policies have been

developed that are relevant to this investigation.These include:

Central West Transport Study, 1996 by SMEC on behalf of

Central Regional Organisation of Councils (CENTROC),

the former NSW Department of Transport, the RTA and

other State agencies.

NSW Regional Study (The Central West),

1997 by NRMA.

Action for Transport 2010, 1998

by the NSW Government.

Penrith to Orange Transport Corridor Study,

1998 by Sinclair Knight Merz on behalf of the RTA.

The Regional Economics Research Unit Study (RERU),

1999 by Charles Sturt University on behalf of CENTROC.

The Bells Line of Road Development Study, 2000 by

Maunsell McIntyre on behalf of the RTA.

The Great Western Highway was the focus of the first four

studies while Bells Line of Road was the focus of the last two.

The Charles Sturt University study identified a number of

economic and regional benefits of upgrading Bells Line of Road

to a four-lane motorway standard. However, the study also

noted that the costs were likely to outweigh the proposed

benefits.

The study by Maunsell McIntyre concluded that:

Medium to long-term traffic demand across the Blue

Mountains justified the development of only one primary

route and a supplementary route.

The Great Western Highway is already the more

developed route and is designated as part of the

Australian Government’s AusLink National Network.

Bells Line of Road would be very expensive to

develop to a significantly higher standard because

of the severe terrain.

Continued investment in the Great Western Highway

should remain the priority, with periodic but limited

improvements to Bells Line of Road as the

supplementary route.

Bells Line of Road corridor study Summary 7

RAIL

No major rail improvements are currently planned for

the Main Western Rail Line.There are unlikely to be service

improvements needed over the next 15 years or so for the

rail passenger demand expected west of Penrith.

Currently, rail has a 64% share of the total freight tonnes

moved across the mountains and a 74% share of interstate

freight tonnage. Most of this rail traffic is coal to Port Kembla.

Growth in freight rail volumes in the corridor is expected to

be largely accommodated by the existing rail infrastructure and

services. However, after about 2011, without major track

capacity improvements and improved access and train paths

to the Sydney rail network, rail is likely to begin to lose market

share to road, especially for general freight.

Enhancement of the Main Western Rail Line would be difficult,

but feasible, from an engineering perspective but is unlikely to

deliver the significant transport and access benefits desired

without further capacity enhancements east of Penrith and

west of Lithgow.

ROAD OPTIONS

Five possible improvement options were developed as part of

The Bells Line of Road Development Study.A brief description

of the options investigated is as follows:

OPTION 1 High standard 100-110 km/hr design speed route

with four lanes and gradient generally less than 7%.Would be

suitable for all vehicles including B-Doubles.

OPTION 2 Medium standard 70 – 100km/hr design speed,

four-lane road on existing alignment as far as practical, with

improvements for truck use and easing of tight curves.Would

be suitable for all vehicles including B-Doubles.

OPTION 3 Upgrade two-lane road for truck use by adding

passing/climbing lanes from Newnes Junction via Bell to Mt

Victoria, and new bypass road around Lithgow between

Marangaroo and Newnes Junction. There would be no

substantial road works east of Bell.Would be suitable for all

vehicles including B-Doubles.

OPTION 4 Upgrade existing Bells Line of Road between

Richmond and Bell, add passing/climbing lanes and other

incremental improvements where feasible on the current

alignment. Not suitable for B-Doubles over 19m.

OPTION 5 Maintenance and progressive local safety

improvements. Not suitable for B-Doubles over 19m.

These options did not include connections into the Sydney

road network and specifically to the Westlink M7.

The potential transport solutions were assessed against

the project objectives developed for this corridor study,

which were:

Review the options for upgrading the Bells Line of

Road corridor investigated in The Bells Line of Road

Development Study (2000) to identify the option that

best meets the needs of heavy vehicle access between

Sydney and NSW’s Central West.

Develop the design and fully assess the best of

the four-lane B Double capable options.

The five options described above were assessed against the

project objectives. Only two of the options satisfied the project

objectives.The other three were not pursued in detail, even

though some had merit when combined with other transport

enhancements along the Great Western Highway corridor.

For the purposes of options assessment the route was divided

into three precincts and the options re-named. The three

precincts can be seen on the adjacent map along with the

options:

Western Precinct.

Central Precinct.

Eastern Precinct.

The options in each of the precincts are described in the table

opposite and illustrated in the map on page 13.

Options considered

Five road upgrade options were developed in The Bells Line of Road Development Study (2000).These were further assessed and refined as part of this corridor study.The potential to addressfreight issues through the enhancement of the Main Western Rail Line was also considered.

OPTION DESCRIPTION

Western Precinct

Option WPNth1 High standard 100-110 kph design speed northern Lithgow bypass route with four lanes and

gradient generally less than 7%.This would be a new road between Marangaroo and Bell.Would

be suitable for all vehicles including B-Doubles.

Option WPSth1 High standard 100-110 kph design speed southern Lithgow bypass route with four lanes and

gradient generally less than 7%.This would be a new road between Marangaroo and Bell.Would

be suitable for all vehicles including B-Doubles.

Option WPNth2 Medium standard 70 – 100 kph design speed northern Lithgow bypass route with four lanes.

Would be suitable for all vehicles including B-Doubles but at lower standard to reduce footprint.

Option WPSth2 Medium standard 70 – 100 kph design speed southern Lithgow bypass route with four lanes.

Would be suitable for all vehicles including B-Doubles but at lower standard to reduce footprint.

Option WP3 Medium standard 70 – 100 kph design speed to upgrade two- lane road for truck use adding

passing/climbing lanes from Newnes Junction via Bell to Mt Victoria, and new bypass road north

of Lithgow (the southern bypass) between Marangaroo and Newnes Junction.There would be

no substantial road works east of Bell.Would be suitable for all vehicles including B-Doubles.

Central Precinct

Option CP1 High standard 100-110 kph design speed with four lanes and gradient generally less than 7%

between Bell and Kurrajong Heights.Would involve the straightening of numerous curves

and a tunnel under Mt Tomah.Would be suitable for all vehicles including B-Doubles.There

would be prohibitions on vehicles carrying dangerous goods using the tunnel.

Option CP2 Medium standard 70 – 100 kph design speed with four lanes. Many tight curves would remain

and would remain at-grade at Mt Tomah.Would be suitable for all vehicles including B-Doubles

but at lower standard to reduce footprint.

Option CP1A Exactly the same as CP1 except that the upgrade would remain at-grade at Mt Tomah.

Eastern Precinct

Option EPNth1 High standard 100-110 kph design speed with four lanes and gradient generally less than 7%.

This would involve a bypass of Bellbird Hill. It would also require a bypass of Richmond.

Would be suitable for all vehicles including B-Doubles.

Option EPSth1 High standard 100-110 kph design speed with four lanes and gradient generally less than 7%.

This would involve a new road bypassing Kurrajong Heights to Agnes Banks. It would also

require an extension of the M2 corridor to Blacktown.Would be suitable for all vehicles

including B-Doubles.

Option EPNth2 Medium standard 70 – 100 kph design speed with four lanes.This would stay as close as

possible to the existing alignment. It would also require a bypass of Richmond.Would be

suitable for all vehicles including B-Doubles.

Bells Line of Road corridor study Summary8

Bells Line of Road corridor study Summary 9

CONSTRAINTS CONSIDERED

A wide range of constraints were considered in the

investigations carried out for this corridor study including:

Land use and statutory planning.

Biological.

Indigenous heritage.

Non-Indigenous heritage.

Noise and vibration.

Hydrology and hydraulics.

Air quality.

Engineering feasibility.

Cost/Affordability.

Many of these issues provide constraints to the project either

along its length or in one or more of the three precincts.

Information in this booklet focuses on the key constraints that

either assist in differentiating options or have the potential to

significantly affect the viability of the project.

NON-INDIGENOUS HERITAGE

Items of Non-indigenous heritage would be impacted by

the options in all precincts. However, items of State heritage

significance are able to be avoided.

INDIGENOUS HERITAGE

A number of indigenous heritage items occur in the vicinity of

the existing road, mainly in the central and western precincts.

This assessment is based on known archaeological sites. A

major issue is that there is little known for this area because of

the lack of field survey data, resulting in an increase in risk that

unknown sites and artefacts are likely to be discovered during

detailed investigations.

NOISE AND VIBRATION

Noise and vibration will be an important issue for the amenity

of communities along Bells Line of Road.There is already a high

proportion of heavy vehicle traffic using the road. This will

increase substantially with an upgraded four-lane designated

freight route.

Many of the houses directly adjacent to the existing road

would be within the footprint of the new road and would

therefore require acquisition. While this would negate the

noise issue for those residences, the properties with partial

acquisition would be the most significantly impacted.

There are a number of schools along Bells Line of Road that

would require specific noise treatment. Solutions to bypass

centres along the route would assist in alleviating potentially

severe noise amenity impacts for areas such as Bilpin, Kurmond

and Kurrajong.

HYDROLOGY AND HYDRAULICS

Flooding is only a major issue in the Eastern Precinct. It

is unlikely that flood-free bridges would be warranted

across this flood plain for the Probable Maximum Flood

(PMF) level, but design may be possible for medium to large

flood events.

Both the northern and southern options face significant

problems in crossing the Hawkesbury/Nepean River

floodplain.

AIR QUALITY

The key air quality issue is the effect of introducing a major

new traffic/emissions source in north-western Sydney (the

Sydney airshed) and the Lithgow airshed.This is an issue for

the project as a whole rather than any particular option.This

would need to be addressed during Environmental Impact

Statement (EIS) investigations.

Generally, options that result in less steep grades will be better

from an air quality perspective.Additionally, towns that can be

bypassed along the route would have an air quality advantage.

The other key air quality issue was associated with Option

CP1 which includes a 1.3km tunnel under Mt Tomah that

would require ventilation.The tunnel would result in exposure

to less emissions than with a surface road option, but a

ventilation stack, if needed, in a largely undisturbed area

bounded by National Park and a World Heritage area is

likely to attract significant community and environmental

stakeholder opposition.The tunnel option is also significantly

more expensive than the surface road option.

Key constraints

There are a range of environmental, engineering and economic constraints that have the potentialto affect the proposed route options. Effects range from issues that should be avoided if practica-ble to constraints that could prevent from the project proceeding.

Bells Line of Road corridor study Summary10

Lithgow

Western Precinct Central Precinct Eastern Precinct

BLUE MOUNTAINS NATIONAL PARK

BLUE MOUNTAINS NATIONAL PARK

Bell

Berambing

Bilpin

Windsor

Hazelbrook

Hartley

Marrangaroo

Mount Tomah

Blaxland

Richmond

Penrith

Kurrajong

Katoomba

Blackheath

Kurrajong Heights

Kurmond

Agnes Banks

Marsden Park

Dean Park

Bowen Mountain

Grose Vale

Springwood

Newnes Junction

Wentworth Falls

WOLLEMI NATIONAL PARK

Mount Victoria

0 5

Kilometres

10

The remaining constraints have the potential to prevent the

project from proceeding.

LAND USE AND STATUTORY PLANNING

Land affected by the proposed Bells Line of Road upgrade

options has statutory planning controls at Commonwealth and

State.This is the case irrespective of the option considered.This

will result in a complex statutory approval process at both

levels of government.

Approval of the proposal would be required under the

recently introduced Part 3A of the Environmental Planning &

Assessment Act, 1979 (EP&A Act).The proposal would be the

subject of an environmental assessment which would examine

the potential impacts of the preferred route. If a decision was

made to proceed with the proposal, the refined design and

assessment would be displayed for community comment prior

to assessment of the proposal by the Department of Planning

and consideration by the Minister for Planning.

In most areas, the National Park boundaries mirror those of

the Blue Mountains World Heritage area.These are significant

statutory constraints. As can be seen by the possible cross

sections on the following page, the encroachment into these

valuable ecological areas will be significant.

To impact on the National Parks, legislation would need to

be changed to amend Park boundaries.This would require

the concurrence of National Parks and Wildlife Service

(now Depar tment of Environment and Conservation

[DEC]), which will require strong justification for the

project and assurance that there are no feasible

alternatives

Under the Commonwealth Environment Protection and

Biodiversity Conservation Act, 1999 (EPBC Act), actions which

may have a significant impact on matters of ‘national

environmental significance’ are taken to be ‘controlled actions’.

This means that they come under the control of the EPBC

Act, and are subject to the assessment and approval processes

it establishes.

The matters of national environmental significance, as stated in

the EPBC Act are:

World Heritage properties.

Ramsar wetlands.

Nationally threatened species and communities.

Migratory species protected under

international agreements.

The Commonwealth marine environment.

Nuclear actions.

LEGEND

NPWS Estate Boundary

M7 West Link (WSO)

Network Connection

Road

Rail

DESIGN OPTIONS

EP Nth 1

CP 2

CP 1

EP Nth 2

EP Sth 1

WP Sth

WP Nth1

WP 3

N

Options for Bells Line of Road

Bells Line of Road corridor study Summary 11

Due to the impact of options on the Blue Mountains World

Heritage area, the project would trigger the EPBC Act

provisions. It may also trigger those applicable to nationally

threatened species and communities and migratory species

protected under international agreements.

Western Precinct

WPNth and WPSth options avoid all National Parks,World

Heritage areas and wilderness areas. WP3 encroaches on a

small area of Blue Mountains National Park and the associated

World Heritage area.There is potential for this to be avoided

with the steepening of batters.

Central Precinct

Both CP1 and CP2 would have significant incursions into Blue

Mountains National Park and minor incursions into Wollemi

National Park. CP2 would have marginally less effect.

Eastern Precinct

EPNth1 would impact on a small area of National Park as part

of the Bellbird Hill deviation. EPNth2 would impact on a small

area of National Park and World Heritage area to the north-

west of Kurrajong Heights.This impacts likely to be negated in the

refinement of the concept design. EPSth1 would have significant

incursions into National Park and World Heritage area.

BIOLOGICAL

Options in all precincts would result in extensive clearing of

native vegetation. It is likely that threatened flora and fauna

species would be impacted, requiring the need for a SIS.

Western Precinct

The WPNth options would result in greater clearing of native

vegetation and greater risk of discovering threatened flora and

fauna species that were not known to occur, simply because of

the historic lack of field investigations in the area. It should be

noted that WPSth options will also have a significant impact on

the clearing of native vegetation.

Central Precinct

CP2 would result in marginally less native vegetation clearing

than CP1. Both would be in areas of National Park and World

Heritage.

Eastern Precinct

WPSth1 has the potential to impact on significant areas of

core habitat and support for core habitat as seen on the

adjacent map. It would result in extensive clearing of native

vegetation, including portions of four endangered ecological

communities.This represents a significant constraint for EPSth1.

ENGINEERING FEASIBILITY

From an engineering feasibility perspective, the two key areas

of engineering risk are the Mt Tomah Tunnel as part of option

CP1 and the route of EPSth1 at Bowen Mountain.The tunnel

presents a range of geotechnical uncertainties that all have the

potential to significantly increase the project costs.

While the EPNth options intersect with the Kurrajong Fault,

seismic events would not be damaging, but could cause

rockfalls in vulnerable locations, such as deep cuttings.

Traffic Lane 3.50 Traffic Lane 3.50Traffic Lane 3.50 Traffic Lane 3.50Shoulder 2.00 Shoulder 2.00Median 5.00

Shou

lder

1.0

0

Shou

lder

1.0

0

Traffic Lane 3.50 Traffic Lane 3.50Traffic Lane 3.50 Traffic Lane 3.50Shoulder 2.00 Shoulder 2.00Median 11.00

Shou

lder

1.0

0

Shou

lder

1.0

0

Possible cross sections

Bells Line of Road corridor study Summary12

EPSth1 would involve the construction of 17km of new road,

traversing an area of the greatest geological complexity along

the Bells Line of Road corridor.At least three major bridges –

across the Hawkesbury, Grose River and Devils Hole Creek –

would be required, plus many creek-spanning structures.

Several deep cuttings (30-60m) would be needed to achieve

satisfactory grades as the road ascends the Lapstone

Monocline escarpment north of Bowen Mountain.

It is expected that the geotechnical conditions will be as severe

as any previously encountered in the Sydney region, and would

add greatly to construction costs.

COST/AFFORDABILITY

Based on preliminary cost estimates the construction costs of

the project between Marangaroo and the Westlink M7 at

Dean Park would be $3.015 billion.

Due to the geotechnical issues in some parts of the route and

the likelihood of the need for substantial structures across the

Hawkesbury/Nepean floodplain, this cost estimate could

increase.

The issue of cost and affordability is a major constraint for

Government.The amount of money required for this project

is very large, with benefits that fall short of breaking even with

costs. It would be difficult to justify such expenditure on a

marginal project.

Grose Vale

Kurrajong

Kurmond

Agnes Banks

Londonderry

Marsden Park

Quakers Hill

Richmond

Cornwallis

Windsor

Vineyard

Riverstone

Pitt Town

Cattai

Glossodia

Wilberforce

Dean Park

Kurrajong Heights

Bowen Mountain

BLUE MOUNTAINS

0 2

Kilometres

4

N

LEGEND

Flora

Fauna

M7 West Link (WSO)

Network Connection

NPWS CORE HABITAT

Core Habitat

Support to Core Habitat

DESIGN OPTIONS

EP Nth 1

CP 2

CP 1

EP Nth 2

EP Sth 1

Effects of Eastern Precinct options on core habitat.

PRELIMINARY ESTIMATED PROJECT COSTS

PRECINCT ESTIMATED PROJECT COSTS – $M

EASTERN TO RICHMOND ROAD 727*

CENTRAL 1,174

WESTERN 1,114*

TOTAL COSTS 3,015

Note: Tunnel costs would make up approximately $170 to 200 million of the central precinct concept.*A typographical error had the dollar value estimates for the Eastern to Richmond Road and Western precincts transposed.This was corrected in June 2008.

Bells Line of Road corridor study Summary 13

ROUTE SELECTION PROCESS

After the constraints were identified, assessment of the four-

lane options required a consistent set of criteria against which

each option could be evaluated. These criteria needed to

ensure the major issues associated with the routes and their

impacts were adequately addressed.The criteria used were:

Environmental and social impacts.

Engineering factors, such as constructability.

Transport issues, such as corridor requirements.

Construction issues.

Regional development and economic

returns to the community.

Financial returns to a private developer.

Options were considered against the criteria and additional

sub-criteria, under a Multi-Criteria Analysis (MCA) framework

to assist in deciding on a preferred option.The MCA approach

allowed a systematic comparison of a range of options with a

view to selecting a preferred option. The MCA process,

combined with specialist investigations, enabled more objective

assessment of options and a more robust process.

To enable the process to be more robust, sets of weights

(the importance of one criteria in comparison with another)

were developed. Weighting sets were developed to reflect

emphasis on:

Environmental issues.

Transport efficiency.

Regional development.

The break-up of the weight scenarios can be seen in the table

at the bottom of the page.

PREFERRED OPTION

The preferred option can be seen in the map over the page.

Western Precinct

In the Western Precinct, the preferred option involves a high-

speed road link bypassing Lithgow to the north (Option

WPNth1).

WPNth1 was the preferred option under all three

weighting scenarios.

This option had less steep grades, only minor creek

crossings and would integrate more effectively with

any proposals for an airport at Newnes Plateau.

However, there will be significant impacts on native

vegetation with a likely follow-on impact on habitat

of threatened species.These issues would need to

be addressed through the EIS process.

Selection of the preferred option

The options were considered against the project objectives, taking into account the key constraintsand benefits. A structured approach was used to assist in the decision making process.This and otheranalyses resulted in the identification of a preferred four-lane upgrade option.

WEIGHT SCENARIOS

TRANSPORT/TECHNICAL ENVIRONMENTAL REGIONAL DEVELOPMENTCATEGORY / CRITERIA WEIGHTS WEIGHTS WEIGHTS

ENGINEERING AND TECHNICAL 25 10 10

TRANSPORT ISSUES 20 20 40

ENVIRONMENT AND SOCIAL IMPACTS 20 30 5

CONSTRUCTION ISSUES 20 15 30

REGIONAL DEVELOPMENT AND ECONOMIC RETURNS TO COMMUNITY 10 20 30

FINANCIAL RETURNS TO DEVELOPER 5 5 5

Bells Line of Road corridor study Summary14

Lithgow

Western Precinct Central Precinct Eastern Precinct

BLUE MOUNTAINS NATIONAL PARK

WOLLEMI NATIONAL PARK

Bell

Mount Victoria

Bilpin

Windsor

Hazelbrook

HartleyMount Tomah

Blaxland

Richmond

Penrith

Kurrajong

Katoomba

Kurrajong Heights

Kurmond

Agnes Banks

Marsden Park

Bowen Mountain

Grose Vale

Springwood

Wentworth Falls

BLUE MOUNTAINS NATIONAL PARK

Berambing

Marrangaroo

Blackheath

Dean Park

Newnes Junction

0 5

Kilometres

10

Central Precinct

In the Central Precinct, the preferred option involves a high-

speed road link with lower speed sections including Mt Tomah

(Option CP1A).

Much of the Central Precinct has an existing alignment

that enables 100km/hr travel.There are some key areas

and communities that require a much lower travel speed.

For this precinct, it was preferred to adopt the design

principle of designing the upgrade to the high-speed

standard for as much of the route as practicable

and adopting a lower standard where there are

significant constraints.

A cost benefit analysis was done on the provision

of a tunnel at Mt Tomah.As similar diversion of traffic

from Great Western Highway would be achieved

with or without the tunnel and there was the risk

of cost over-run associated with the tunnel, the cost

benefit analysis indicated that it was not worth pursuing

this option.This would result in a steep section of

four-lane road at Mt Tomah but this was not expected

to significantly affect the attractiveness of the road.

It should also be noted that the environmental impacts

in this precinct might present an insurmountable blockage

to the approval of this significant upgrade. Both CP1

and CP2 would require substantial incursion into

National Parks and World Heritage areas.With marginal

project justification, it will be difficult to demonstrate

that the regional development benefits of the project

outweigh the environmental costs.

The preferred option includes bypasses of towns

such as Berambing and Bilpin.

Eastern Precinct

In the Eastern Precinct, the lower-speed option (EPNth2)

generally along the existing alignment would be preferred.

This enables better servicing of existing local traffic needs

and enables effective integration with the likely future

expansion of residential development in the area.

A bypass of Richmond and North Richmond is required

and this would connect with any Richmond Road upgrade.

LEGEND

NPWS Estate Boundary

M7 West Link (WSO)

Network Connection

Road

Rail

DESIGN OPTIONS

CP 1

EP Nth 2

WP Nth1N

Preferred option

Bells Line of Road corridor study Summary 15

REGIONAL GROWTH ISSUES

Transport demand is linked to changes in economic activity in

a region. One of the key perceived needs for this project is

that the Central West region (and beyond) is constrained in

reaching its growth potential by the lack of suitable freight

transport access across the Blue Mountains.

Traditional road user cost benefit analysis focuses on the

transport user costs and benefits (i.e what time savings,

operating cost savings and accident savings are gained from the

project development relative to the baseline scenario (i.e

comparing the project and the ‘do nothing’ scenarios). This

approach is designed for choosing between options or routes

once the level of demand has been determined.

Under this approach benefits from regional development are

usually analysed in two ways:

Shifting existing traffic flows onto the improved access

corridor to generate user benefits.

Adding a component for ‘induced’ demand (that is trips

that currently do not take place).

Many transport projects either urban, or regional / rural often

have wider strategic reasons as part of their justification. In

regard to regional development, the level of demand may be

currently constrained significantly by the lack of transport

access.

Addressing the constraint can improve the overall economic

activity (e.g. the lowering of transport costs could lead to the

export/import of products in a region for which trade is

currently not cost effective).

From a regional development perspective, this needs to be

assessed ‘up front’ in the economic assessment. Consideration

of these wider impacts then leads to an improved two-stage

process of assessment:

Determination of the overall level of demand at the macro

level, including inclusion of regional development.

Use of cost benefit analysis to select between route

options at this determined level of demand.

Determining the wider impacts, such as regional economic

development effects, may be important in determining the

overall level of demand for a transport corridor. Evidence from

the development of regional areas in the USA, involving

transport access across the Rockies, indicates that improved

transport access was a important common factor in facilitating

these regions’ growth.

On this basis, adequate transport access is a necessary

condition for improved regional development but other

conditions also need to be present for improved regional

growth to occur and be sustained once a transport constraint

is overcome. Key factors include resource endowment,

diversification of the regional economy, labour costs and

availability and the size of markets.

GROWTH SCENARIOS

The regional benefits to the Central West of providing an

upgraded four-lane road across the Blue Mountains along the

Bells Line of Road alignment has been taken into account by

the consideration of a range of potential regional growth:

Based on current growth trends.

Assuming higher levels of regional development could

take place as a result of improved transport provision.

Need and justification

Due to the high cost of constructing a four-lane Bells Line of Road upgrade and the existing lowtravel demand for that route, communities in the Central West are of the opinion that traditionaleconomic analysis carried out on major transport infrastructure does not provide an accurateassessment of the perceived regional development needs for the project. As part of this study,the regional development benefits were considered in a wider economic assessment.

Existing Bells Line of Road

Bells Line of Road corridor study Summary16

The assumed growth in the region was based on a review

of development by region and sub-region and by industry

sector. The growth in car trips was related to population and

employment increases and growth in road freight to GDP

growth using historical data.

The key growth and traffic assumptions for the two scenarios

are shown in the following two tables.

The trend growth scenario is based upon emerging trends for

the Central West noting that:

There is evidence that provision of adequate road

infrastructure allows trend growth to improve.

Department of Planning forecasts do not allow for the

effects in infrastructure developments on growth.

The high growth scenario requires that the Central West

becomes a significant centre of economic growth

amongst the regions in NSW.This could occur for

the following reasons:

– Overspill economic impacts from the Sydney Basin.

As the Sydney Basin becomes more congested and the

cost of land use for development purposes rises further,

adjacent regions, such as the Central West take up a

share of this development.This has occurred on the

Central Coast and Hunter regions in particular, and

under this scenario the Central West benefits as it is

another ‘adjacent region’ given the existence of suitable

conditions for increased growth.

– Overspill impacts would first occur in the eastern part

of the Central West region (Orange-Bathurst-Blayney-

Oberon-Lithgow) as this sub region is closest to the

Sydney basin.

– Initial overspill effects would be one of the initial catalysts

in creating internally generated regional growth as

employment and resident population increase above

‘critical mass’ levels.

– Other industries such as tourism are assumed to play

a key role in the region’s economic development under

this scenario.

It should be emphasised that the high growth scenario would

be very difficult to achieve even with an upgraded transport

link. It would require a doubling of the region’s population

over the next 30 years, in contrast to the existing levels of

economic and population growth.

‘TREND’ GROWTH SCENARIO ASSUMPTIONS

PERCENT PER ANNUM AVERAGE POPULATION REGIONAL GDP GROWTH PER ANNUM GROWTH1 PER ANNUM CROSS MOUNTAIN TRIPS GROWTH

CARS TRUCK RAIL

2003-11 1% 2% 3% 3% 3%

2011-21 1% 2% 2% 4% 2%

2021-31 1% 1.5% 2% 4% 1%

2031-41 0.5% 1% 1% 3% 0%(1) Growth for Central West Region including adjustment for Sydney Basin growth impacts 2. It is assumed that no major investment will take place on the Main Western Rail Line over the study period. Rail freightwould continue, assisted by minor capacity improvements. Rail freight growth after 2020 will fall and road will increase its mode share as a result, particularly for general freight

HIGH GROWTH SCENARIO ASSUMPTIONS

PERCENT PER ANNUM AVERAGE POPULATION REGIONAL GDP CROSS MOUNTAIN TRIPS GROWTHGROWTH PER ANNUM GROWTH2 PER ANNUM

CARS TRUCK RAIL

2003-11 1% 2% 3% 3% 3%

2011-21 3% 5% 8% 7% 2%

2021-31 3% 4% 6% 7% 1%

2031-41 1% 2% 3% 6% 0%(2) Growth for Central West Region including adjustment for Sydney Basin growth impacts

Bells Line of Road corridor study Summary 17

ECONOMIC ANALYSIS RESULTS

The two growth scenarios were applied to the preferred

upgrade option.

Using a 30-year evaluation period following the completion of

construction (assumed to be in 2011), the preliminary results

of the Road User Cost Benefit Analysis (RUCBA) are shown in

the table below.

ECONOMIC FINDINGS

The conclusions of the regional economic analysis were:

None of the four-lane, B-Double capable options are

justifiable in terms of the road user net benefit analysis.

The lower design speed options perform marginally better

economically than the higher design speed option and are

slightly more affordable.

The project could become marginally economically justified

if the Central West Region becomes a major growth centre

in NSW (with population and employment doubling in the

next 30 years) and additional significant regional benefits

could be achieved and included as benefit of the project.

Other lower cost options which allow B-Double access

across the mountains and which also allow for an

improved Great Western Highway are likely to be more

justified economically than the options assessed to date.

For the project to ‘break-even’ in terms of quantified net

benefits, the Central West would have to attract additional

regional benefits that would result in:

Trend growth scenario – an extra 270% of measured

road user benefits for the preferred concept.

High growth scenario – an extra 140% of measured

road user benefits for the preferred concept.

A preliminary financial analysis was undertaken to determine

the potential for private investment in the project.The analysis

indicated that the project is highly unlikely to be self-funding

from toll revenues that are acceptable to road users. For

instance, in the trend growth scenario, it is estimated that toll

levels of over $150 for cars ($300 for trucks) per trip would

be required to achieve a 7% real rate of return on the

preferred option.To enable tolls of $20 for cars and $40 for

trucks the Government would need to contribute $1.75-$2.22

billion, depending on the regional growth scenario.

The clear conclusion is that the preferred four-lane, B-Double

capable option is not justified on economic or regional

development grounds.

RESULTS OF THE PRELIMINARY ROAD USER COST BENEFIT ANALYSIS (RUCBA)

TREND GROWTH HIGH GROWTH

PREFERRED CONCEPT PREFERRED CONCEPT

CAPITAL COST ($ MILL) 3,015 3,015

INCREMENTAL PRESENT VALUES ($M AT 7% DISCOUNT RATE)

CAPITAL COST 2,238 2,238

RESIDUAL VALUE - 63 - 63

RECURRENT COSTS 249 249

TOTAL COST 2,424 2,424

VEHICLE OPERATING COST SAVINGS 179 264

TRAVEL TIME SAVINGS 371 569

ACCIDENT COST SAVINGS 132 204

TOTAL SAVINGS 682 1,037

NPV1 ($M) -1,741 -1,387

BCR2 0.3 0.4

FYRR3 (%) 2 2

NPV/I4 - 0.8 - 0.6

(1) Net Present Value (may not correspond to the difference between total savings and total cost due to rounding) (2) Benefit Cost Ratio (3) First Year Rate of Return (4) Ratio of NPV over Capital Cost

Bells Line of Road corridor study Summary18

The Bells Line of Road corridor study concluded that:

The Main Western Rail Line over the Blue Mountains

could be upgraded but any upgrade would be unlikely

to deliver significant benefits without major upgrades

east of Penrith and west of Lithgow.

All of the road upgrade options examined are feasible

from an engineering perspective.

None of the four-lane, B-Double road upgrade options

examined appear feasible from an economic or financial

perspective for a range of growth assumptions.

All of the four-lane B-Double capable upgrade options

would require the full regional and economic

development growth potential of the Central West

region to be realised over the next 30 years for the

project to progress towards being justified economically.

It is highly unlikely that private investment would be

forthcoming to progress this project without significant

government funding.

All of the four-lane, B-Double road upgrade options,

including the preferred option would have significant

environmental, social impacts.

Reserving a road corridor to enable future upgrade

works along BloR is complex and is likely to result in

the need for detailed and comprehensive environmental

assessment and approval from the Commonwealth and

State governments. It is also likely to required funding

for property acquisition of approximately $230 million

in 2004 dollars.

Conclusions

RTA/Pub. 05.283 ISBN 1920-907556


Recommended