Klaasjaap Buijs Engineering Manager BELWIND Offshore Wind Farm - 9 March 2010 -
Transcript
Page 1: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Klaasjaap BuijsEngineering Manager

BELWINDOffshore Wind Farm

- 9 March 2010 -

Page 2: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

BELWIND Wind Farm

Outline:• Scope of Works• Project Organization • Design of foundations• Fabrication and transport of foundations (MP+TP) • Storage Yard Zeebrugge• Transport and Installation of foundations (MP+TP) • Production and installation Infield cables • Design and construction of OHVS and Booster Station• Production and installation Export cable

Page 3: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Scope of Work

Location: • 55 km offshore Zeebrugge• 18-33m water depth

• 55 WTG Foundations • 55 Wind Turbines • Scour Protection• Electrical Infrastructure

• 1 OHVS• 55 Infield Cables• 1 Export Cable • 3 km Onshore Cable• Grid connection

Execution Period:• Contract award July 2009• Completion November 2010

Zeebrugge

BELWIND Wind Farm

‘Scheur’

Contract Value 280M Euro

Page 4: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Wind Turbine Generators:52m / 250tVestas V90 3MW

Transition Pieces:25m / 160t

Monopiles:40m – 65m / 250t – 500t

Scope of Work

Page 5: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Project Organization

Van Oord (BOP Contractor)

Nexans Parker Scanrope

Ballast Nedam

CEI-de Meyer

OffshoreInstallationMonopiles

Dredging Trench across

‘de Scheur’

Infield Cables

Fabrication

Export Cable

Supply & Installation

Transition Pieces &

OHVS

MonopilesFabrication

Van Oord

Belwind

Vestas

Van Oord

Scour Protection

OffshoreInstallationTransition Pieces and

WTG’s

THV Seawind

OHVS and Grid

connection

Supply WTG

BladtEEW

Page 6: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Project Organization

Work ForceOffice Staff: ±40Vessels & Local: ±150

Page 7: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Design foundations

- Soil investigation

- Design primary steel

- Design Secondary steel

- Scour protection

- Certification

Page 8: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Fabrication Monopiles

MONOPILES:

Ready for Load Out 1.8m

Page 9: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Transport Monopilesto Zeebrugge

MONOPILES:

Load Out in Progress

Page 10: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Transport Monopilesto Zeebrugge

3 Monopiles

en route to Zeebrugge

Page 11: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Fabrication Transition Pieces

TRANSITION PIECES

Ready for Load Out

Page 12: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Transport Transition Piecesto Zeebrugge

TRANSITION PIECES

4 Transition Pieces

en route to Zeebrugge

1.8m

Page 13: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Storage and Handling Yardin Zeebrugge Port

Storage:- 20 Monopiles- 20 Transition Pieces- Auxiliary Pieces

AssemblingPlatforms TP

Load Out of MP and TP

Storage Area:

175m x 285m

Albert-II

Dock

Page 14: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Storage and Handling Yardin Zeebrugge Port

BEFORE

Page 15: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Storage and Handling Yardin Zeebrugge Port

AFTER

Page 16: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Float Out / Launch of Monopiles

Launching First Monopile 02/09/09

Upper PlugBottom Plug

Page 17: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Tow Out of Monopiles

Monopiles

en route to Offshore Site

Page 18: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Installation of Monopiles

Docking of Monopile

IHC Hydro Hammer

IHC Up-Ending Tool

Page 19: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Installation of Monopiles by HVL Svanen

Page 20: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Transport and Installation of Transition Pieces by JB-114

JB-114 ready to load TP’s

Monopile

Page 21: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Load Out of Transition Pieces

Page 22: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Installation of Transition Pieces

Page 23: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Installation of Transition Pieces

Page 24: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Construction OHVS Transition piece

Page 25: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

OHVS Transition piece

Page 26: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

OHVS Transition piece

Page 27: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Today’s Progress Installation of MP’s and TP’s

56

56

Page 28: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Scour Protection (2010)

Picture from Q7 / Princes Amalia wind farm

Page 29: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Delivery Infield Cables

Page 30: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Picture from Q7 /

Princes Amaliawind farm

Installation Infield Cables (2010)

Page 31: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Design and Construction OHVS

THV Seawind

Fabricom

HSS

Pauwels

IEMANTS

OHVS:20m x 20m x 20m1100 ton

Page 32: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Dredging of Trench across ‘de Scheur’ (2010)

Working Area at Crossing Location

To Zeebrugge

Page 33: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Installation Export Cable (2010)

Skagerrak

Page 34: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

Pictures JB-109Installation WTG (2010)

Page 35: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

THE END

Page 36: BELWIND Offshore Wind Farm - Central Dredging Association · BELWIND Wind Farm Outline: • Scope of Works • Project Organization • Design of foundations • Fabrication and transport

THE END 2010?