26
CONTENTS SL.NO. DESCRIPTION 01. COLD START UP 02. INTEGRATED START UP PROCEDURE – COLD START UP 03. HOT AND WARM START UPS. 04. INTEGRATED START UP PROCEDURE – WARM START UP 05. INTEGRATED START UP PROCEDURE – HOT START UP. 06. START UP BY CURVES FOR ABSOLUTE COLD START WITH HP/LP BYPASS SYSTEM. 07. START UP CURVES AFTER 48 HOURS SHAT DOWN WITH HP/LP BYPASS SYSTEM. 08. START UP PROCEDURE AFTER 8 HOURS SHUT DOWN WITH HP/LP BYPASS SYSTEM. 09. TECHNICAL DATA LIMIT CURVES FOR TURBINE VALVES WALL OF THE CASING – SHAFTS. 10. WARMING – UP AND STARTING THE TURBINE – TEMPERATURE CRITERIA. 11. TECHNICAL DATA – REACTIVE CAPACITY CURVE FOR TURBO GENERATORS. COLD START UP (With Aux Steam available) A cold start up is by definition, one of which the maximum of HP casing and HP shaft is less than 150 0 C. This normally means that the unit is shut down from the maximum load for more than five days. If machine is started from ambient temperature (HPC/HP shaft temp approx. 40 0 C), heating up of casting is required. This is accomplished by soaking the machine at 360 rpm at warming up steam parameters (40kg/cm 2 , 360 0 C), till the TSE margin are satisfactory. The rifle construction of the water wall combined with the boiler circulating water pumps permits very high rate of pressure rising of boiler. An upper limit of 200 0 C/hr saturation temperature gradient can be allowed, i.e. approximately the boiler pressure can be brought to 20 kg/cm 2 within an hour of cold start up. But actual temperature gradient is limited by the thick walled Y piece provided in the main steam and HRH lines. A main steam line heating is to be started as early as possible (at approx. 4 kg/cm 2 ) as maximum differential temperature allowed between inner (98%) and mid wall temperature (50%) is 40 0 C. So boiler loading is accordingly regulated. It may be preferably to start only two CC pumps in order to minimise flashing in down comers (and subsequent vibration) when the boiler water is in range of 85 0 C to 125 0 C. The third pump should be started before drum pressure reaches 7 kg/cm 2 to minimise the temperature transients experienced by the pump casing (this is to avoid fast load out back on the boiler in the event of any CC pump tripping). To get the rolling parameters, normally two elevation oil guns are taken with approx. 70 to 80t/hr flow through HPLP bypass. At that time M.S. parameters would be 40 kg/cm 2 and 360 0 C, HRH parameters would be 12 kg/cm 2 and 360 0 C. As soon as the turbine loading has started, HP/LP bypass closes and gets completely closed as the turbine reaches the boiler load. First mill is put into operation around 10% of generator load. Second mill is put into operation around 25% while third mill is at 40% of generator load. Fourth and fifth mills are put into operation at 60% and 80% of generator load respectively. Sixth mill is taken to reach full generator load. During loading the RH outlet steam temperature has to be kept as close as possible to SH outlet steam temperature Burner tilt, SH spray, RH spray controls has to be adjusted accordingly. The turbineloading rate is decided by a selection circuit which compares the external load gradient, TSE margin and time dependant gradient (set internally) and frequency influence.
Transcript
  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 1/26

    CONTENTS

    SL.NO.DESCRIPTION

    01. COLDSTARTUP

    02. INTEGRATEDSTARTUPPROCEDURECOLDSTARTUP

    03. HOTANDWARMSTARTUPS.

    04. INTEGRATEDSTARTUPPROCEDUREWARMSTARTUP

    05. INTEGRATEDSTARTUPPROCEDUREHOTSTARTUP.

    06. START UP BY CURVES FOR ABSOLUTE COLD START WITH HP/LP BYPASSSYSTEM.

    07. START UP CURVES AFTER 48 HOURS SHAT DOWN WITH HP/LP BYPASSSYSTEM.

    08. START UP PROCEDURE AFTER 8 HOURS SHUT DOWN WITH HP/LP BYPASSSYSTEM.

    09. TECHNICAL DATA LIMIT CURVES FOR TURBINE VALVES WALL OF THECASINGSHAFTS.

    10. WARMINGUPANDSTARTINGTHETURBINETEMPERATURECRITERIA.

    11. TECHNICALDATAREACTIVECAPACITYCURVEFORTURBOGENERATORS.

    COLDSTARTUP

    (WithAuxSteamavailable)Acoldstartupisbydefinition,oneofwhichthemaximumofHPcasingandHPshaftislessthan1500C.Thisnormallymeansthattheunitisshutdownfromthemaximumloadformorethanfivedays.Ifmachineisstartedfromambienttemperature(HPC/HPshafttempapprox.400C),heatingupofcastingisrequired.Thisisaccomplishedbysoakingthemachineat360rpmatwarmingupsteamparameters(40kg/cm2,3600C),tilltheTSEmarginaresatisfactory.Therifleconstructionofthewaterwallcombinedwiththeboilercirculatingwaterpumpspermitsveryhighrateofpressurerisingofboiler.Anupperlimitof2000C/hrsaturationtemperaturegradientcanbeallowed,i.e.approximatelytheboilerpressurecanbebroughtto20kg/cm2withinanhourofcoldstartup.ButactualtemperaturegradientislimitedbythethickwalledYpieceprovidedinthemainsteamandHRHlines.Amainsteamlineheatingistobestartedasearlyaspossible(atapprox.4kg/cm2)asmaximumdifferentialtemperatureallowedbetweeninner(98%)andmidwalltemperature(50%)is400C.Soboilerloadingisaccordinglyregulated.ItmaybepreferablytostartonlytwoCCpumpsinordertominimiseflashingindowncomers(andsubsequentvibration)whentheboilerwaterisinrangeof850Cto1250C.Thethirdpumpshouldbestartedbeforedrumpressurereaches7kg/cm2tominimisethetemperaturetransientsexperiencedbythepumpcasing(thisistoavoidfastloadoutbackontheboilerintheeventofanyCCpumptripping).Togettherollingparameters,normallytwoelevationoilgunsaretakenwithapprox.70to80t/hrflowthroughHPLPbypass.AtthattimeM.S.parameterswouldbe40kg/cm2and3600C,HRHparameterswouldbe12kg/cm2and3600C.Assoonastheturbineloadinghasstarted,HP/LPbypassclosesandgetscompletelyclosedastheturbinereachestheboilerload.Firstmillisputintooperationaround10%ofgeneratorload.Secondmillisputintooperationaround25%whilethirdmillisat40%ofgeneratorload.Fourthandfifthmillsareputintooperationat60%and80%ofgeneratorloadrespectively.Sixthmillistakentoreachfullgeneratorload.DuringloadingtheRHoutletsteamtemperaturehastobekeptascloseaspossibletoSHoutletsteamtemperatureBurnertilt,SHspray,RHspraycontrolshastobeadjustedaccordingly.Theturbineloadingrateisdecidedbyaselectioncircuitwhichcomparestheexternalloadgradient,TSEmarginandtimedependantgradient(setinternally)andfrequencyinfluence.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 2/26

    INTEGRATEDSTARTUPPROCEDURE

    COLDSTARTUP

    (AUXILIARYSTEAMAVAILABLE)

    REF.DRGNO.20BPE691

    STEP TIME UNITCONDITION OPERATION NOTES

    0 .. Boilerpr.0kg/cm2(g)

    andAmbienttemperature

    ChargeAux.Steamheader16ata,2600C,fromexistingunits.

    Chargesteamtofueloilpumphouse,atomisingsteamandtracingsteamdeaeratorwarmingup.

    Allthesteamtracinglinesandelectricaltracingsinpumphouse&boilertobecharged.

    StarttankheatingofLSHSoil.

    StartoneLSHSpumponrecirculationassoonasthesufficientoiltemperatureatinletisachieved.

    ChargeLSHStoboilerfrontandkeepitonlongrecirculation,withheaterscontrolsetonAutotomaintain1101290C.

    Fillwaterindrumupto+200mm.

    EnsurethatthesuctionanddischargevalvesofalltheCCpumpsareopenandthepumpsuctionanddischargelinesarevented.

    StartBearingcoolingwatersystempumpsforBoiler,TurbineandTGauxiliaries.

    Checkallcircuitshavesufficientflow.Beforestartingthepumps,theemergencycoolingwatertankleveltobecheckedandmadenormal.

    StartinstrumentaircompressorandcheckthatallthelinestoBoilerandTGarecharged.

    Checkthatallcircuitshavesufficientairpressure.

    StartserviceaircompressorandfilltheairreceivertanksofSRAPH&PRAPHarefilled.

    EnsurethatpurgeairtoHEAisopeninallcorners.

    LineupAirandfluegascircuitsforstartup.Checkdampersandgatesregisterposition.

    ESPreadyinallrespects.

    Furnacebottomashsystemandsealthroughlinedup.

    FSSSpanelreadyinallrespects.

    EASTpanelreadyinallrespects.

    Excitationpanelreadyinallrespects.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 3/26

    Generatorprotectionpanelreadyinallrespects.

    GeneratorH2gaspressureis

    4kg/cm2CheckpurityofH2gasisnormal.

    Generatorstatorwatersystemreadyinallrespects.Checkpurityofgeneratorstatorwaterisnormal.

    H2coolingwatersystemreadyinallrespectswithSLCon.

    LP&HPchemicaldozingsystemisready.

    CheckforlevelinHydrazine,Ammoniaandphosphatepreparationtanks.

    SADCpanelreadiness. Checkforairpressureinallthecornersandelevations.

    PowersupplyforallthevalvesanddampersareON.EnsureAux.airdampersandmodulating.

    SupplyforallauxiliariesofSG,TurbineandGeneratorisensured.

    ReadinessofHPbypasspanelinallrespects.

    Ensuretheoilunitisrunningandallthebypassandsprayvalvesareclosed.

    StartoneoftheCCpumps.Ensuredrumlevelis+200mm,andthedrumairventsareclosed.

    StartthesecondCCpump. Ensuredrumlevelisnormal. Startscannerairfan.

    Startboththesecondaryairpreheaters.

    Ensurethatalltheinletandoutletairgasdampersareopen.

    Startboththeprimaryairpreheaters.Ensurethatthegasdampersareclosed.

    StartonesetofIDandFDfans.

    Adjust30%airflow,andfurnacedraftminus5to10mmWCL.

    ChargesteamcoilpreheaterconcernedwiththerunningFDfans.

    InitiateBoilerPurge(duration5minutes).

    AfterpurgecompletionBoilertripvalveswillgetreset.

    Also,afterpurge,adjustthewindboxdamperstoget3040mmWCL.Windboxdp.

    Luboilsystemstopped. Startonevapourextractionfan,keepotherfanstandby. CheckoillevelinMOT.

    LineupluboilcoolerandthrustbearingfilterStartoneAOP.

    PutonSLCsforotherAOPandEOP.

    CheckoutautostartofAOPandEOP.

    Putluboiltemperaturecontrolleron.

    StartoneJOP. PutonSLCsforotherJOPandDCJOP.

    CheckoutautostartofJOP

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 4/26

    andDCJOP.

    PutoffSLCsJOP1,2&3.StoprunningJOP.

    Opengatevalvegearing. SwitchonSLCgatevalvegearing.

    StartoneJOPandswitchonSLCsforJOPs.

    M/c.comesonbarring.MOTlevel50mmoiltemp.450CJOPheaderpr.140kg/cm2speed80100rpm.

    ThesequentialoperationnarratedaboveonLuboilsystemstoppedisachievedbySGCmode.

    Iftheprogrammegetsinterrupted,thestepandcriteriatobecheckedandtobefulfilledfortheprogrammetoproceedfurther.

    M/conbarring. Startcentrifugewithbothheaters

    FRFsysteminstoppedcondition. CheckFRFtanklevel. +200mm.

    LineupFRFcoolerandduplexfiltersin32barsystemstartoneCEP.CheckautostartofstandbyCEP.

    Establishcontrolfluidsupplytovariousservices. FRFtanklevelO(normal).

    StartoneVEF.

    StartonerecirculationpumpandincludeoneFiltersearthandultrafine.

    SwitchonFRFheaterandkeepSLCONfortemperaturecontrol,andcontrolfluidpumps.

    FRFtemperature550C.

    SwitchONcontrolfluidSGC.

    FRFsystem,SGCison.

    ThesequentialoperationnarratedaboveinFRFsystemstoppedconditionisachievedbySGCFRFsystemonstartingprogrammemode.

    Iftheprogrammegetsinterruptedthestepandcriteriatobecheckedandfulfilledfortheprogrammetoproceedfurther.

    01 ooBoilerreadyforlightupandTurbineonTurninggear.

    Start4burnersinABelevationwithLSHS.

    CheckthatSH&RHventsareopen.

    SH&RHdrainsareopen.

    MSVsclosedanddrainsbeforeMSVopen.

    Regulateoilpressureto810kg/cm2.

    Ensureatomisingsteampressureabout6kg/cm2.

    After30minutes,takeadditionalburners,soastoensureadrummetaltemperatureraiseofabout20C/min.

    Insertfurnaceprobeandensurethatthetemperatureisbelow5350C.

    Checkdrumlevelandgiveblowdown.

    KeepopentheEco.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 5/26

    recirculationvalvewhenthereisnofeedingtodrum.

    Startmotordrivenfeedpumponrecirculation. Checkdeaeratorlevel.

    Chargethefeedlineuptofeedcontrolstation.

    ChargeheatingsteamtodeaeratorfromAux.PRDS.

    Startcondensatepumpsandfeedtodeaeratorasandwhenrequired.

    Checkhotwelllevel.

    Starthotwellmakeuppumpsandfeedhotwellasandwhenrequired.

    Aux.PRDSsteam15kg/cm2

    (g)2600C

    CWsystemischarged.

    CWboxestoensureventilatingofwaterboxes.

    Startoneglandsteamexhausterfan.

    LineupvacuumpumpsandstartonebyoneGraduallyadmitglandsteamwhencondenservacuumreaches0.2kg/cm2(g).

    Ensureglandsteamadmissiontemperatureisalwaysabove2000C.

    VacuumbuildingcanbedonethroughSGCvacuumonstartingprogrammemode,glandsteamexhausterhastobestartedmanually.

    Vacuum09kg/cm2(g).Openalldrainsconnectedtoflashtanksandflashboxesconnectedtocondenser.

    OpenHPBPwarmupvalves. SwitchonSLCdrains.

    02 60' Boilerpressure2kg/cm2 CloseSH&RHheadervents.

    CloseSH&RHheaderdrains.

    OpenMSVbypasslines. MS,HRH,&CRHlineswillgetwarmedup.

    03 100 Boilerpressure5kg/cm2.SwitchonautomaticcontrolinterfaceofLPbypass.

    Assoonasthefixedsetpointreaches12kg/cm2,itseizes.

    OpenMainsteamvalves.

    Automaticcontrolinterfacegetsswitchedoffwhenthehotreheatsteampressurereaches13kg/cm2i.e.aftersynchronisation.

    OpenHPbypass.

    StartthirdC.C.pumpwhenboilerpressurereaches9kg/cm2.

    TakeadditionalgunsinCD&EFelevation.Airheatersootblowingtobecarriedout.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 6/26

    CloseHPBPwarmupvalves.

    AROLLINGTHROUGHHYDRAULICGOVERNOR

    04 150

    Boilerpressure:15kg/cm2

    Temperature:1802000C

    HRHPressure:812Kg/cm2

    OpenHPESVs&IPESVsforwarmingupbyoperatingstartingdevicetoapproximately42%.

    Checkandensurethatspeedsetpointiszeroandspeedergearis0%position.

    EnsureTSEinfluenceisswitchedonandavailablemarginsaregreaterthan=300K.

    05 300

    M.S.Pr.50kg/cm2

    M.S.temp.3500C

    H.R.H.Pr.12kg/cm2

    HRHtemp.:3500C

    RaisethespeedsetpointofEHCto3200rpm

    IftheoilsystemofEHCisisolatedatspeedGov.rack,speedsetpointneednotberaised.

    Graduallyraisethestartingdevicetobringthespeedto360rpm

    Startingdevicepositionapproximately56%.

    TurbinereadyforRolling. Holdthespeedat360rpmforabout35to40mts.

    Ensureclosureofgatevalvegearingat240rpm.Monitorbearingvibrations,shaftvibrations,TSEmargins,bearingtemperature&Turbosupervisoryreadingsat360rpm.

    06 360M.S.Pr.50kg/cm2/3500C.Turbinerunningat360rpm.

    Raisethespeedupto2400rpmthroughstartingdeviceattherateof600rpm.

    EnsuretrippingofJOPat540rpm.

    Raisefurtherspeedupto3000rpmthroughspeedergear.

    Startingdevicewillbeat90%.

    Monitoringbearingtemperatureandvibrations,shaftvibrations,TSEmarginsandTurbovisoryreadings,Sealoil,Primarywaterandgastemperatures&Generatorwindingtemperature.

    EnsuretrippinfofAOPat2950rpm.

    Speedergearpositionwillbeapproximatelyat50to60%.

    07 370

    MSPr.50kg/cm2.Temperature:3500CTurbinerunningat3000rpm.

    PutAVRonAuto.

    Closefieldbreaker.

    Setmanuallythegeneratorvoltagetogridvoltage.

    Synchronisethegeneratorwithgrid.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 7/26

    Pickup50MWloadbyoperatingspeedergear.

    IncreaseHPBPsetpoint.EnsureclosureofHPBPsteamvalves&sprayvalves.

    Closeotherdrains,M.S.HRH,keepingSLCdrainson.

    DrainpotdrainsofMS,CRH&HRHandextractionsteamlineswilloperateaspertheactuationoflevelswitches.

    BROLLINGTHROUGHEHC.

    04 150'

    MSPr.:15kg/cm2.Temperature:1802000CHRHPressure:8to12kg/cm2.

    OpenHPESVs&IPESVsforwarmingupbyoperatingstartingdevicetoapproximately42%.

    CheckandensurethatTSEinfluencesisswitchedonandavailablemarginsaregreaterthan300K.

    Checkandensurethatspeedsetpointiszeroandspeedergearis0%position.

    05 300'

    MSPressure:50kg/cm2

    MSTemperature:3500C

    HRHPressure:12kg/cm2

    HRHTemperature:3500C.

    TurbineReadyforrolling

    Raisethestartingdevicetoabout70%.

    CheckandensureopeningofvalvesinHP/IPsecondaryfluidlinestoEHCatspeedcontrolrack.

    Raisethespeedsetpointto360rpmandwatchtheactualspeed.

    IftrackingdeviceisswitchedON,startingdevicepositionwillautomaticallytracktheEHCposition

    Raisethespeedergearto100%

    Holdthespeedat360rpmforabout35to40mts.Ensureclosureofgatevalvegearingat240rpm.

    Monitoringbearingvibrations,bearingtemperatures,shaftvibrations,TSEmarginsandTurbovisoryreadings.

    06 360'MSPressure:50kg/cm2

    MSTemperature:3500C

    Raisethespeedsetpointto3000rpm.

    Ensuretrippingofjackingoilpumpat540rpm.

    Turbinespeed:360rpm. Therateofaccelerationwillbe600to850rpm.

    Monitorbearingvibrationandtemperatures,shaftvibrations,TurbovisoryreadingsandTSEmargins

    Monitorandcontrol,SEALoiltemperatures,Primarywatertemp.Hydrogengastemperatureandwindingtemperature.

    EnsuretrippingofAOPat2950rpm.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 8/26

    07 370'

    MSPressure:50kg/cm2

    MSTemperature:3500C

    Turbinespeed:3000rpm.

    PutAVRonauto,CloseFieldBreaker.

    Setmanuallygeneratorvoltagetogridvoltage.

    Synchronisethegeneratorwithgrid.

    Speedsetpointwillraiseautomaticallyby8rpmandloadwillbepickedupto20MW.

    Raisethespeedsetpointandpickuptheloadto50MW.

    IncreaseHPBPsetpoint.EnsureclosureofHPBPsteamvalves&sprayvalves.

    CloseotherdrainsofMS,CRH,HRH,keepingSLCdrains'ON'.

    DrainpotdrainsofMS,CRH,HRHandextractionsteamlineswilloperateaspertheactuationoflevelswitches.

    CROLLINGTHROUGHSGCTURBINE.

    04 150'

    MSPressure:15kg/cm2

    MSTemp.:1802000C

    HRHPressure:12kg/cm2

    SwitchonthestartupprogrammeofSGCTurbine.

    EnsureTSEinfluenceisswitchedon.

    Iftheprogrammeinterruptstheparticularstepandcriteriatobecheckedandcorrectedfortheprogrammetoproceedfurther.

    AlloperationsasexplainedunderEHCrollingwillbecarriedoutbySHCTurbineprogrammesequentially.

    05 300'

    MSPressure:50kg/cm2

    MSTemperature:3500C

    HRHPressure:12kg/cm2

    HRHTemp.:3500C.

    TurbineReadyforrolling

    Turbinespeedwillberaisedto360rpmthroughSGCProgramme.

    Ensureclosureofgatevalvegearingat240rpm.

    Monitorbearingvibration,bearingtemperature,shaftvibration,TSEmarginsandTurbovisoryreadings.

    Toachievetheprogrammeasperthestartingcurve,themainsteamtemperatureshouldbemaintainedsteadilytillloadingupto50MW.

    06 360'

    MSPressure:50kg/cm2

    MSTemperature:3500CTurbinespeedwillberaisedupto3000rpmthroughSGCprogramme.

    EnsuretrippingofJOPat540rpm.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 9/26

    Turbinerunningat360rpm.

    EnsuretrippingofAOPat2950rpm.

    Monitorbearingtempandvibrations,shaftvibrations,TSEmarginsandturbovisoryreadingssealoil,primarywater,HydrogengasandGeneratorwindingtemperatures.

    07 370'

    MSPressure:50kg/cm2

    MSTemperature:3500C

    Turbinespeed:3000rpm.

    SGCprogrammewillswitchONfieldbreaker,putAVRonauto,synchroniseandpickuploadupto20MW.

    EnsureSGCstartupprogrammeiscompleted.

    Raisethespeedsetpointandpickuptheloadupto50MW.

    IncreaseHPBPsetpoint.EnsureclosureofHPBPsteamvalvesandsprayvalves.

    CloseotherdrainsofM.S.CRHandHRH,keepingSLCdrainsON.

    DrainpotdrainsofMS,CRH,HRHextractionsteamlineswilloperateaspertheactuationoflevelswitches.

    08 390'

    Load:55MW

    M.S.:54kg/cm2/3500C

    HRH:12kg/cm2/3400C

    StartsealairfanandPAfanandtakefirstmillinservice.

    BeforestartingP.A.fan,ensurethatairandgasdampersofPrimaryAirPreheatersareopen.

    ChargeESPfields EnsureAshhandlingsystemisready.

    StartthesecondsetofID&FDfans.MakereadySH&RHspraysystems.

    CutinL.P.heaters2&3. Ensureswitchingonofloadcontrollerabove60MW.

    CutoutheatingsteamfromAux.P.R.D.S.toDeaerator.

    PegDeaeratorfromCRHsteamgraduallyupto2kg/cm2.

    Cutinautocontrollers.

    Load:55MW

    M.S.:54kg/cm2/3500C

    HRH:12kg/cm2/3400C

    ChargeAux.PRDSstationfromCRH.Cutinsprayandmaintainatemperatureof2500C.

    Ensureenergizingofsolenoidintrimmingdeviceatandabove100MWload.

    PegDeaeratorgraduallyto4kg/cm2.

    RaisethepressuresetpointofDeaeratorpressurecontrollergradually.

    CutinIIndmillandcutinautocontrollers.

    Startwithdrawingoilsupportgradually.Ensurefireballscannerhealthiness

    Controlmainsteamandreheatsteamtemperaturesbyusingsprayifrequired.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 10/26

    10 440'

    Load:160MW

    M.S.:90kg/cm2/3800C

    HRH:20kg/cm2/3800C

    Steamflow:580t/hr.

    Increasethewindboxtofurnacedifferentialpressureto100mmW.C.byadjustingSADC.

    ChargeH.P.heaters5A,5B,6Aand6B.

    Putcontrollersonauto.

    StartfirstTDBFP&secondCEP.

    ChargeDeareatorpeggingsteamflowCRHtoExtractionaround200MWload.

    EnsureDeareatorPressurecontrollerremainsasauto.

    11 480'

    Load:250MW

    M.S.:120kg/cm2/4200C

    HRH:26kg/cm2/3400C

    Steamflow:820t/hr.

    CutinIIIrdmillandcutinautocontrollers.

    StartsecondP.A.Fan.BeforestartingP.A.fanensurethatairandgasdampersofPAPHsareopen.

    12 510'

    Load:320MW

    M.S.:125kg/cm2/3500C

    HRH:2830kg/cm2/3400C

    Steamflow:1040t/hr.

    CutinIVthmillandcutinautocontrollers.

    Cutofoilsupportcompletely.Ensurehealthinessoffireballscanners.

    13 550'

    Load:405MW

    M.S.:145kg/cm2/4600C

    HRH:33kg/cm2/4600C

    Steamflow:1310t/hr.

    CutinVthmillandcutinautocontrollers.

    CutinsecondTDBFPandswitchoffmotordrivenBFP.

    14 590'

    Load:500MW

    M.S.:170kg/cm2/4750C

    HRH:40.5kg/cm2/4750C

    IffullloadisnotreachedcutinVIthmillalongwithitscontrollers.IncreasethesetpointofSH&RHspraycontrollerssuchthatratedparametesareachievedgradually.

    15 670'

    Load:405MW

    M.S.:145kg/cm2/4600C

    HRH:33kg/cm2/4600C

    Steamflow:1310t/hr.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 11/26

    WARMANDHOTSTARTUPS

    (WithAux.SteamAvailable).

    Awarmstartupis,bydefinition,onewhichthemaximumofHPcasing/HPshafttemperatureis

    between1500Cand3500C.Thisnormallymeansthattheunitisshutdownfromthemaximumloadforone

    to fourdays.Dependingupon theabsolute temperatureofHPcasingandHPshaft, steamparametersare

    derived.AhotstartupisbydefinitiononewhichthemaximumofHPcasing/shafttemperatureismorethan

    3500C.InthiscasetogettherollingparameterstwomillsaretakenintoservicekeepingHP,LPbypassin

    operation. (Again the flowrate is restrictedby the Ypiecesconstraints i.e.,400C). Inboth the cases,

    curves are given to derive the rolling parameters. In case when machine is rolled through EAST, curve

    generators,calculateandgivepermissiveforrolling.

    INTEGRATEDSTARTUPPROCEDURE

    WARMSTARTUP(AFTER48HOURSSHUTDOWN).

    STEP TIMEINMINUTES UNITCONDITION OPERATION NOTES.

    OneCCpumpinoperationandscannerfaninoperation.

    MotoroperatedBFPisrunasandwhenrequiredtomaintainthedrumlevel.

    BothSAPHsandPAPHsinoperation.

    TurbineonbearinggearwithAOP,JOPandsealoilpumpsinoperation.

    Controlfluidsystemreadyinallrespects.Onecirculatingpumpinoperationwithoneearthfilterandultrafinefilterincircuit.

    Generatorgassystem,sealoilsystemandprimarywatersysteminoperation.

    Bearingcoolingwatersysteminoperation.

    HTandLTauxiliariespowersupplyavailable.

    HPbypasssystemreadyinallrespects.

    ESPreadyinallrespects.

    EASTpanelsreadyinallrespects.

    Furnacebottomashsystemandsealtroughlinedup.

    Vacuumpumpslinedupandreadyforoperation.

    Glandsteamandleaksteamcontrollersarelinedupandreadyforoperation.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 12/26

    Generatorprotectionpanelandexciterpanelsreadyinallrespects.

    Boilerdrumpressure=0kg/cm2.SHtemperaturebetween1300Cand1500C.

    1.Chargeauxiliarysteamheaderfromexistingunits.Pr.16atatemp.2600C.

    2.Chargesteamtofueloilpumphouse,atomisingsteamandtracingsteam.

    3.StarttankheatingofLSHSoil.

    4.StartoneLSHSpumponrecirculationassoonassufficientoiltemp.atinletisachieved.

    StartinstrumentoilcompressorandserviceaircompressorsandcheckthatalllinestoboilerandTGarecharged.

    ChargeLSHSpumptoboilerfrontandkeepitonlongrecirculationwithheaterscontrolsetonautotomaintain1200C.

    Startcirculatingwaterpumpforcondenseranddeaeratethecondenserwaterboxes.

    StartsecondCCPump.EnsurerunningofmotordrivenBFPcontinuouslyformaintainingdrumlevel.

    StartonesetofIDandFDfans.

    Initiateboilerpurge.

    StartoneCEPandkeepthehotwellmakeupinservice.

    Startoneofthecontrolfluidpumpsandkeepthesecondasautostandby.

    Keepthecontrolfluidtemperaturecontrolonauto.

    Lineupmainsteam,CRHandHRHsteamlinesforchargingbyopeningrespectivelinedrains.

    LineupFSSSpanelsinallrespects

    ChargeheatingsteamlinetoDeaeratorfromAux.PRDS.

    01 ooBoilerreadyforlightupandturbineonturninggear.

    Start4burnersinABelevationwithLSHS.

    CheckthatSH&RHventsareopen.

    SH&RHdrainsareopen.

    MSVsclosedanddrainsbeforeMSVopen.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 13/26

    Ensureatomisingsteampressureofabout6kg/cm2

    EnsuremotoroperatedBFPisinservice.

    StartGlandsteamExhauster.

    Startonebyonevacuumpumps.

    Admitglandsteamwhenvacuumreaches0.2kg/cm2.

    Ensureglandsteamadmissiontemperatureisalwaysabove2000C.

    VacuumbuildingcanbedonethroughSGCvacuumonstartingprogrammemode.Glandsteamexhausterhastobestartedmanually.

    Openalldrainsconnectedtoflashtanksandflashboxesconnectedtocondenser.

    Ensurecondenservacuumof0.8kg/cm2.

    SwitchonSLCdrains.

    CloseSH&RHheaderventsanddrains.Ensureboilerpressureis2kg/cm2.

    OpenHPBPwarmingupvalves.

    OpenMSVbypasslines.

    SwitchAutomaticcontrolinterfaceofLPbypass.

    Assoonasthefixedsetpointreaches12kg/cm2,itseizes.

    Automaticcontrolinterfacegetsswitchedoffwhenthehotreheatsteampressurereaches13kg/cm2(i.e.)aftersynchronisation.

    OpenMainsteamstopvalves.EnsureMS,CRH&HRHlinesgetwarmedup.

    OpenHPbypassandclosetheHPBPwarmupvalves.EnsureBoilerpressureis5kg/cm2.

    StartthirdCCpump. EnsureBoilerpressureis9kg/cm2.

    PutHPbypasscontrolleronautoandvarythesetpointaccordingtothegradientofpipelinetemperatures.

    EnsureBoilerpressureis10kg/cm2

    PutHPbypassspraycontrolonauto.

    Takeadditionalgunsaccordingtotherequirement.

    Airheatersootblowingtobecarriedout.

    AROLLINGTHROUGHHYDRAULICGOVERNOR.

    02 180'

    MS:50kg/cm2/3650C

    HRH:12kg/cm2/3250C

    Bypasssteamflow:170t/hr.

    OpenHPESVandIPESVforwarmingupbyoperatingstartingdevicetoapprox.42%

    Checkandensurethatspeedsetpointiszeroandspeedergearis0%.

    EnsureTSEinfluenceis

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 14/26

    switchedonandavailablemarginsaregreaterthan300K.

    03 210'

    MS:60kg/cm2/4000C

    HRH:12kg/cm2/3500C

    Bypasssteamflow:200t/hr.

    RaisethespeedsetpointofEHCto3200rpm.

    IftheoilsystemofEHCisisolatedatspeedGov.rack,speedsetpointneednotberaised.

    Graduallyrisethestartingdevicetobringthespeedto360rpm.

    Startingdevicepositionapproximately56%.

    Holdthespeedat360rpmforabout5minutes.Ensureclosureofgatevalvegearingat240rpm.

    Monitorbearingvibrations,shaftvibrations,TDEmargins,bearingtemp.&Turbovisoryreadingsat360rpm.

    04 215' Turbinerunningat360rpm.

    Raisethespeedupto2400rpmthroughstartingdeviceattherateof600rpm.

    EnsuretrippingofJOPat540rpm.

    Raisefurtherspeedupto3000rpmthroughspeedergear.

    Startingdevicewillbeat90%.

    Monitorbearingtemp&vibrations,shaftvibrations,TSEmarginsandTurbovisoryreadings.Sealoil,Primarywaterandgastemperatures&Generatorwindingtemperature.

    EnsuretrippingofAOPat2950rpm.

    Speedergearpositionwillbeapprox.at50to60%.

    05 220' Turbinerunningat3000rpm PutAVRonauto.

    Closefieldbreaker.

    Setmanuallythegeneratorvoltagetogridvoltage.

    Synchronisethegeneratorwithgrid.Pickup50MWloadbyoperatingspeedergear.

    IncreaseHPBPsetpoint.EnsureclosureofHPBPsteamvalves&sprayvalves.

    Closeotherdrains,M.S.HRH,keepingSLCdrainson.

    DrainpotdrainsofMS,CRH,andHRHandextractionsteamlineswilloperateaspertheactuationoflevelswitches.

    Furtherloadraisingwillbedonebyoperatingthespeedergearaccordingtothestartupcurve.

    BROLLINGTHROUGHEHCMS:50kg/cm2/3650C

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 15/26

    02 180'HRH:12kg/cm2/3250C

    Bypasssteamflow:170t/hr.

    OpenHPESVsandIPESVsforwarmingupbyoperatingstartingdevicetoapprox.42%.

    CheckandensurethatTSEinfluenceisswitchedonandavailablemarginsaregreaterthan300K.

    Checkandensurethatspeedsetpointiszeroandspeedergearis0%.

    03 210'

    MS:60kg/cm2/4000C

    HRH:12kg/cm2/3500C

    Bypasssteamflow:200t/hr.

    Turbinereadyforrolling.

    Raisethestartingdevicetoabout70%.

    CheckandensureopeningofvalvesinHP/IPsecondaryfluidlinestoEHCatspeedcontrolrack.

    Raisethespeedsetpointto360rpmandwatchtheactualspeed.

    IftrackingdeviceisswitchedonstartingdevicepositionwillautomaticallytracktheEHCposition

    Raisethespeedergearto100%.Ensureclosureofgatevalvegearingat240rpm.

    Holdthespeedat360rpmforabout5minutes.

    Monitorbearingvibrationsbearingtemperatures,shaftvibrations,TSEmargins&turbovisoryreadings.

    04 215' Turbinerunningat360rpm. Raisethespeedsetpointto3000rpm.EnsuretrippingofJackingoilpumpat340rpm.

    Monitorbearingvibrationsandtemps,shaftvibration,turbovisoryreadingsandTSEmargins.

    EnsuretrippingofAOPat2950rpm.

    05 225' Turbinespeed:3000rpm. PutAVRonautocloseFieldbreaker.

    Setmanuallygeneratorvoltagetogridvoltage.

    Synchronisethegeneratorwithgrid.

    Speedsetpointwillberaiseautomaticallybyabout8rpm&loadwillbepickedupto20MW.

    Raisethespeedsetpointandpickuptheloadto50MW.

    IncreaseHPBPsetpoints.EnsureclosureofHPBPsteamvalvesandsprayvalves.

    CloseotherdrainsofMS,CRH,andHRHkeepingSLCdrainsON.

    DrainpotdrainsofMS,CRH,HRHandextractionsteamlineswilloperateaspertheactuationoflevelswitches.

    CROLLINGTHROUGHSGCTURBINE.

    02 180'

    MS:50kg/cm2/3650C

    HRH:12kg/cm2/3250C

    Bypasssteamflow:

    SwitchonthestartupprogrammeofSGCTurbine.

    EnsureTSEinfluenceisswitchedon.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 16/26

    170t/hr.

    Iftheprogrammeinterruptstheparticularstepandcriteriatobecheckedandcorrectedfortheprogrammetoproceedfurther.

    AlloperationsasexplainedunderEHCrollingwillbecarriedoutbySGCTurbineprogrammesequentially.

    03 210'

    MS:50kg/cm2/3650C

    HRH:12kg/cm2/3250C

    Bypasssteamflow:170t/hr.

    Turbinereadyforrolling.

    Turbinespeedwillberaisedto360rpmthroughSGCProgramme.

    Ensureclosureofgatevalvegearingat240rpm.

    Monitorbearingvibration,bearingtemp,shaftvibration,TSEmarginsandTurbovisoryreadings.

    Toachievetheprogrammeasperthestartingcurve,themainsteamtemperatureshouldbemaintainedsteadilytillloadingupto50MW.

    04 215'

    MS:60kg/cm2/4000C

    Turbinerunningat360rpm.

    Turbinespeedwillberaisedupto3000rpmthroughSGCProgramme.

    EnsuretrippingofJOPat540rpm.EnsuretrippingofA.O.P.at2950rpm.

    Monitorbearingtemp&vibrations,shaftvibrations,TSEmarginandturbovisoryreadings,sealoil,primarywater,HydrogengasandGeneratorwindingtemperatures.

    05 225'

    MS:60kg/cm2/4000C

    Turbinespeed:3000rpm.

    SGCprogrammewillswitchONfieldbreaker,putAVRonauto,synchroniseandpickuploadupto20MW.

    EnsureSGCStartupprogrammeiscompleted.

    Raisethespeedsetpointandpickuploadupto50MW.

    IncreaseHPBPsetpointEnsureclosureofHPBPsteamvalvesandsprayvalves.

    CloseotherdrainsofM.S.,CRHandHRH,keepingSLCdrainsON.

    DrainpotdrainsofM.S.,CRH,HRHandExtractionsteamlineswilloperateaspertheactuatoroflevelswitches.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 17/26

    06 230'

    Load:60MW

    MS:60kg/cm2/4100C

    HRH:14kg/cm2/3600C

    CutinL.P.heaters2and3. Ensureswitchingonofloadcontrollerat60MW.

    CutoutheatingsteamfromAux.PRDStoDeaerator.

    PegDeaeratorfromCRHsteamgraduallyupto2kg/cm2.

    Cutinallautocontrollers.

    StartsealairfanandP.A.fan

    BeforestartingP.A.fan,ensurethatairandgasdampersofPrimaryAirPreheatersareopen.

    Cutinfurtheroilgunsforraisingparameters.

    07 245'

    Load:110MW

    MS:80kg/cm2/4200C

    HRH:19kg/cm2/3800C

    Mainsteamflow:470t/hr.

    TrimmingdeviceisinOFF.

    Cutin1stcoalmillandcutinAutocontrollers.

    MakereadySH&RHspraysystem.

    ChargeESPFields. EnsureAshhandlingsystemisready.

    ChargeAux.PRDSstationfromCRH.Cutinsprayandmaintainatemperatureof2500C.

    PegDeaeratorgraduallyupto4kg/cm2.

    RaisethepressuresetpointofDeaeratorpressurecontrollergradually

    CutinH.P.heatersandputthelevelcontrolsonauto.

    StartfirstTDBFPandsecondCEParoundaloadof170MW.

    Increasethewindboxtofurnacediff.pressureto100mm.W.C.byadjustingSADC.

    08 270'

    Load:200MW

    MS:100kg/cm2/4350C

    HRH:19kg/cm2/4000C

    Mainsteamflow:750t/hr.

    CutinIIndmillandcutinautocontrollers.

    Startwithdrawingoilsupportgradually.Ensurehealthinessoffireballscanners.

    Controlmainsteamandreheatsteamtemperaturebyusingsprayifrequired.

    ChangeDeaeratorpeggingsteamfromCRHto EnsureDeaeratorpressure

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 18/26

    Extractionsteam. controllerremainsonauto.

    CutinIIIrdmillandcutinautocontrollers.

    StartsecondP.A.fan.

    BeforestartingP.A.fanensurethatairandgasdampersofPAPHareopen.

    09 300'

    Load:320MW

    MS:125kg/cm2/4500C

    HRH:30kg/cm2/4300C

    Mainsteamflow:1080t/hr.

    CutinIVthmillandcutinautocontrollers.

    Cutoffoilsupportcompletely.Ensurehealthinessoffireballscanners.

    CutinVthcoalmillandcutinautocontrollers.

    StartsecondTDBFPandswitchoffmotordrivenBFP.

    CutinVIthcoalmillandcutinautocontrollers.

    10 340'

    Load:500MW

    MS:170kg/cm2/4800C

    HRH:40.5kg/cm2/4800C

    Mainsteamflow:1620t/hr.

    Checkallparametersatfullloadandensurethemwithinlimits.

    IncreasethesetpointofSH&RHspraycontrollerssuchthatratedparametersareachieved.

    11 420'

    Load:500MW

    MS:170kg/cm2/5350C

    HRH:40.5kg/cm2/5350C

    Mainsteamflow:1570t/hr.

    INTEGRATEDSTARTUPPROCEDURE

    HOTSTARTUP(AFTER8HOURSSHUTDOWN)

    STEP TIMEINMINUTES. UNITCONDITION OPERATION NOTES.

    TwoCCpumpsinoperationandscannerfaninoperation.

    MotoroperatedBFPisrunasandwhenrequiredtomaintainthedrumlevel.IfnecessaryBFPshouldbekeptrunningcontinuously.

    BothSAPHsandPAPHsinoperation.

    Turbineonbarringgear

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 19/26

    withAOP,JOPandsealoilpumpsinoperation.

    Controlfluidpumpinoperation.Onecirculatingpumpinoperationwithoneearthfilterandultrafinefilterincircuit.

    Generatorgassystem,sealoilsystemandprimarywatersysteminoperation.

    Bearingcoolingwatersysteminoperation.

    Condensercirculatingwatersysteminoperation.

    Serviceairandinstrumentaircompressorsinoperation.

    Onecondensatepumpinoperationandhotwellmakeupinservice.

    Aux.steamheaderchargedfromexistingunits(16ata2600C).

    LSHSpumpinoperationonlongrecirculationuptoboilerfrontwithheaterscontrolseton

    HPbypasssystemreadyinallrespects.

    LP&HPandchemicaldosingsystemready.

    ESPpanelsreadyinallrespects.

    EASTpanelsreadyinallrespects.

    Furnacebottomashsystemandsealtroughlinedup.

    Vacuumpumpslinedupandreadyforoperation.

    Glandsteamandleaksteamcontrollersarelinedupandreadyforoperation.

    Generatorprotectionpanelandexciterpanelsreadyinallrespects.

    FSSSpanelreadyinallrespects.

    BoilerdrumPr.75kg/cm2

    SH.Temp.between4150Cand4300C.

    Lineupmainsteam,CRHandHRHsteamlinesforchargingbyopeningrespectivelinedrains.

    EnsureMSVisclosed.

    Startoneglandsteamexhauster.

    Startonebyonevacuumpumps.

    Admitglandsteamwhenvacuumreaches0.2

    Ensureglandsteamadmissiontemperatureis

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 20/26

    kg/cm2. alwaysabove2000C.

    VacuumbuildingcanbedonethroughSGCvacuumonstartingprogrammemode.Glandsteamexhausterhastobestartedmanually.

    Openalldrainsconnectedtoflashtanksandflashboxesconnectedtocondenser.

    Ensurecondenservacuumof0.8kg/cm2.

    Ensurecondenservacuumof0.8kg/cm2.

    OpenHPBPwarmingupvalves.

    SwitchAutomaticcontrolinterfaceofLPbypass.

    Assoonasthefixedsetpointreaches12kg/cm2,itseizes.

    Automaticcontrolinterfacegetsswitchedoffwhenthehotreheatsteampressurereaches13kg/cm2(i.e.)aftersynchronisation.

    StartthirdCCpump. Ensuredifferentialtemp.iswithinpermissiblelimits.

    EnsurerunningofmotordrivenBFPcontinuouslyformaintainingdrumlevel.

    StartbothID&FDfans Initiateboilerpurge.

    ChargeheatingsteamlinetoDeaeratorfromAux.PRDS.

    01 ooBoilerreadyforlightupandturbineonturninggear.

    Start4burnersinABelevationwithLSHS.

    Ensureatomisingsteampressureofabout6kg/cm2.

    DrumPr.75kg/cm2

    SH.Temp.4150Cand4300C.

    EnsuremotoroperatedBFPisinservice.

    OpendrainsbeforeMSV. OpenMSVbypasslines.

    OpenMainsteamstopvalves.EnsureMS,CRH,HRHlinesgotwarmedup.

    OpenHPbypassandclosetheHPBPwarmupvalves.

    PutHPbypasscontrollersonautoandvarythesetpointaccordingtothegradientofpipelinetemperatures.

    PutHPbypassspraycontrolonauto.

    Takeadditionalgunsaccordingtotherequirement.

    Airheatersootblowingtobecarriedout.

    StartbothP.A.fansandsealairfans.

    BeforestartingP.A.FansensurethatairandgasdampersofPrimaryair

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 21/26

    preheatersareopen.

    Lineupmillingsystemforstarting.

    AROLLINGTHROUGHHYDRAULICGOVERNOR

    02 40'

    MS:85kg/cm2/4850C

    HRH:12kg/cm2/4400C

    Bypasssteamflow:280t/hr.

    Cutinfirstcoalmill&cutinautocontrollers.

    MakereadySHandRHspraysystem.

    ChargeESPfields. EnsureAshhandlingsystemisready.

    Increasethewindboxtofurnacediff.Pressureto100mmW.C.byadjustingS.A.D.C.

    Cutinsecondmillandcutinautocontrollers.

    PegthedeaeratorfromCRHgraduallyupto2kg/cm2.

    OpenHPESVsandIPESVsforwarmingupbyoperatingstartingdevicetoapproximately42%.

    Checkandensurethatspeedsetpointiszeroandspeedergearisat0%.

    EnsureTSEinfluenceisswitchedonandavailablemarginsaregreaterthan300K.

    03 50'

    MSPressure:85kg/cm2

    MSTemperature:5000C

    HRHPressure:12kg/cm2

    HRHTemperature:4500C.

    Bypasssteamflow:360t/hr.

    TurbineReadyforrolling

    RaisethespeedsetpointofEHCto3200rpm.

    IftheoilofEHCisisolatedatspeedGov.rack,speedsetpointneednotberaised.

    Graduallyraisethestartingdevicetobringthespeedto360rpm

    Startingdevicepositionapproximately56%.

    Ensureclosureofgatevalvegearingat240rpm.

    Monitoringbearingvibrations,shaftvibrations,TSEmargins,bearingtemp&Turbovisoryreadingsat360rpm.

    04 52' Turbinerunningat360rpm.Raisespeedupto2400rpmthroughstartingdeviceattherateof600rpm.

    EnsuretrippingofJOPat540rpm.

    Raisefurtherspeedupto300rpmthroughspeedergear.

    Startingdevicewillbeat90%.

    Monitorbearingtempandvibrations,shaft

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 22/26

    vibrations,TSEmarginsandturbovisoryreadings.SealoilPrimarywaterandgastemperaturesandGeneratorwindingtemperature.

    EnsuretrippingofAOPat2950rpm.

    Speedergearpositionwillbeapproximatelyat50to60%.

    05 56' Turbinerunningat3000rpm PutAVRonauto.

    Closefieldbreaker.

    Setmanuallythegeneratorvoltagetogridvoltage.

    SynchronisetheGeneratorwithgrid.Pickup50MWloadbyoperatingspeedergear.

    IncreaseHPBPsetpoint.EnsureclosureofHPBPsteamvalves&sprayvalves.

    Closeotherdrains,M.S.CRH,HRH,keepingSLCdrainson.

    DrainpotdrainsofMS,CRH,andHRHandextractionsteamlineswilloperateaspertheactuationoflevelswitches.

    Furtherloadraisingwillbedonebyoperatingthespeedergearaccordingtothestartupcurve.

    BROLLINGTHROUGHEHC

    02 40'

    MSPressure:85kg/cm2

    MSTemperature:4850C

    HRHPressure:12kg/cm2

    HRHTemperature:4400C.

    Bypasssteamflow:280t/hr.

    Cutinfirstcoalmill&cutinautocontrollers.

    MakereadySH&RHspraysystems.

    ChargeESPfields. EnsureAshhandlingsystemisready.

    Increasethewindboxtofurnacediff.Pressureto100mmW.C.byadjustingS.A.D.C.

    Cutinsecondmillandcutinautocontrollers.

    PegthedeareatorfromCRHgraduallyupto2kg/cm2.

    OpenHPESVsandIPESVsforwarmingupbyoperatingstartingdevicetoapproximately42%.

    Checkandensurethatspeedsetpointiszeroandspeedergearisat0%.

    EnsureTSEinfluenceisswitchedonandavailablemarginsaregreaterthan

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 23/26

    300K.

    03 50'

    MSPressure:85kg/cm2

    MSTemperature:5000C

    HRHPressure:12kg/cm2

    HRHTemperature:4500C.

    TurbineReadyforrolling.Bypasssteamflow:360t/hr.

    Raisethestartingdevicetoabout70%.

    CheckandensureopeningofvalvesinHP/IPsecondaryfluidlinestoEHCatspeedcontrolrack.

    Raisethespeedsetpointto360rpmandwatchtheactualspeed.

    IftrackingdeviceisswitchedonstartingdevicepositionwillautomaticallytracktheEHCposition.

    Raisethespeedergearto100%.Ensureclosureofgatevalvegearingat240rpm.

    Holdthespeedat360rpmforabout5minutes.

    Monitorbearingvibrations,bearingtemperatures,shaftvibrations,TSEmarginsandturbovisoryreadings.

    04 52' Turbinereadingat360rpm.Raisethespeedsetpointto300rpm.

    EnsuretrippingofJackingoilpumpat540rpm.

    Therateofaccelerationwillbe600to800rpm2.

    Monitorbearingvibrationsandtemperatures,shaftvibration,turbovisoryreadingsandTSEmargins.

    Monitorandcontrol,sealoiltemperatures,primarywatertemperature.Hydrogengastemperatureandwindingtemperature.

    EnsuretrippingofAOPat2950rpm.

    05 56' Turbinespeed:3000rpm. PutAVRonautoClosefieldbreaker.

    SetManuallygeneratorvoltagetogridvoltage.

    Synchronisethegeneratorwithgrid.

    Speedsetpointwillberaisedautomaticallybyabout8rpmandloadwillbepickedupto20MW.

    Synchronisethegeneratorwithgrid.

    IncreaseHPBPsetpoint.EnsureclosureofHPBPsteamvalvesandsprayvalves.

    CloseotherdrainsofMS.CRHandHRH,keepingSLCdrainsON.

    DrainpotdrainsofMS,CRH,HRHandextractionsteamlineswilloperateaspertheactuationoflevelswitches.

    CROLLINGTHROUGHSGCTURBINE.MS:85kg/cm2/4850C

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 24/26

    02 40' HRH:12kg/cm2.

    Bypasssteamflow:280t/hr.

    Cutinfirstcoalmill&cutinautocontrollers.

    MakereadySH&RHspraysystems.

    ChargeESPfields. EnsureAshhandlingsystemisready.

    Increasethewindboxtofurnacediff.Pressureto100mmW.C.byadjustingS.A.D.C.

    Cutinsecondmillandcutinautocontrollers.

    PegthedeaeratorfromCRHgraduallyupto2kg/cm2.

    SwitchonthestartupprogrammeofSGCTurbine.EnsureTSEinfluenceisswitchedON.

    Iftheprogrammeinterrupts,theparticularstepandcriteriatobecheckedandcorrectedfortheprogrammetoproceedfurther.

    AlloperationsasexplainedunderEHCrollingwillbecarriedoutbySGCTurbineprogrammesequentially.

    03 50'

    Turbinereadyforrolling.

    MS:85kg/cm2/5000C

    HRH:12kg/cm2/4500C

    Bypasssteamflow:360t/hr.

    Turbinespeedwillberaisedto360rpmthroughSGCprogramme.

    Ensureclosureofgatevalvegearingat240rpm.

    Monitorbearingvibration,bearingtemperature,shaftvibration,TSEmarginsandTurbovisoryreadings.

    Toachievetheprogrammeasperthestartupcurve,themainsteamtemperatureshouldbemaintainedsteadilytillloadingof50MW.

    04 52' Turbinereadingat360rpm.

    Turbinespeedwillberaisedupto3000rpmthroughSGCprogramme.

    EnsuretrippingofJOPat540rpm.

    EnsuretrippingofAOPat2950rpm.

    Monitorbearingtemperatureandvibrations,shaftvibrations,TSEmargins,Turbovisoryreadings,sealoil,primarywater,HydrogengasandGeneratorwindingtemperatures.

    Turbinespeed:3000rpm.

    MS:85kg/cm2/5000C SGCProgrammewillswitch

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 25/26

    05 56' HRH:12kg/cm2/4500C

    Bypasssteamflow:360t/hr.

    ONfieldbreaker,putAVRonautosynchroniseandpickuploadupto20MW.

    EnsureSGCstartupprogrammeiscompleted.

    Raisethespeedsetpointandpickuploadupto50MW.

    IncreaseHPBPsetpoint.EnsureclosureofHPBPsteamvalves&sprayvalves.

    CloseotherdrainsofM.S,CRHandHRH,keepingSLCdrainsON.

    DrainpotdrainsofMS,CRH,HRHandExtractionsteamlineswilloperateaspertheactuationoflevelswitches.

    06 60'

    LOAD:60MW.

    MS:85kg/cm2/5000C

    HRH:16kg/cm2/4700C

    CutinL.P.heaters2and3. Ensureswitchingonofloadcontrollerat60MW.

    CutoutheatingsteamfromAux.PRDStoDeaerator.

    Raisethegeneratorpressurefrom2kg/cm2to4kg/cm2.

    RaisethepressuresetpointofDeaeratorpressurecontroller.

    Cutinautocontroller.

    Startwithdrawingoilsupportgradually.Ensurehealthinessoffireballscanners.

    07 65'

    LOAD:150MW.

    MS:100kg/cm2/5000C

    HRH:20kg/cm2/4800C

    Mainsteamflow:1620t/hr.

    TrimmingdeviceisinOFF.

    ChargeAux.PRDSstationfromCRH.Cutinsprayandmaintainatemperatureof2500C.

    CutinH.P.heatersandputthelevelcontrolsonauto.

    StartfirstTDBFPandsecondCEParoundaloadof170MW.

    Controlmainsteamandreheatsteamtemperaturebyusingsprayifrequired.

    ChangedeaeratorpeggingsteamfromCRHtoExtractionsteam.

    EnsureDeaeatorpressurecontrollerremainsonauto.

    CutinIIIrdmillandcutinautocontrollers.

    08 70'

    LOAD:230MW.

    MS:120kg/cm2/5000C

    HRH:20kg/cm2/4950C

    Mainsteamflow:820t/hr.

    CutinIVthmillandcutinautocontrollers.

  • 7/15/2015 TechnicalServices

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm 26/26

    Cutoffoilsupportcompletely.

    Ensurehealthinessoffireballscanners.

    CutinVthcoalmillandcutinautocontrollers.

    StartsecondTDBFPandswitchoffmotordrivenBFP.

    CutinVIthcoalmillandcutinautocontrollers.

    09 86'

    LOAD:500MW.

    MS:170kg/cm2/5000C

    HRH:40.5kg/cm2/5000C

    Mainsteamflow:1620t/hr.

    Checkallparametersatfullloadandensurethemwithinlimits.

    IncreasethesetpointofSH&RHspraycontrollerssuchthatratedparametersareachieved.

    10 135'

    LOAD:500MW.

    MS:170kg/cm2/5000C

    HRH:40.5kg/cm2/4800C

    Mainsteamflow:1570t/hr.

    ********************


Recommended