Date post: | 16-Nov-2015 |
Category: |
Documents |
Upload: | prasanna-kumar-subudhi |
View: | 28 times |
Download: | 1 times |
F-ING-002 Cartula de documentos de Ingeniera Word
BIB-11-GHA-MCD-ISX-001Page:2Of:11
Rev.:0
CLIENT:BANGLADESH POWER DEVELOPMENT BOARD
PROJECT:BIBIYANA SOUTH 400 MW COMBINED CYCLE POWER PLANT
SERVICE WATER SYSTEM CALCULATION REPORT
BIB-11-GHA-MRS-ISX-001Page:1
Of:11
CLIENT:BANGLADESH POWER DEVELOPMENT BOARD
PROJECT:BIBIYANA SOUTH 400 MW COMBINED CYCLE POWER PLANT
SERVICE WATER SYSTEM FUNCTIONAL DESCRIPTION
SERVICE WATER SYSTEM FUNCTIONAL DESCRIPTION
003/11/2014FOR INFORMATION PKSVTBTS
REVDATEPURPOSE OF REVISIONAUTHORREVISEDAPPROVED
TABLE OF CONTENTS
31.PURPOSE
42.GENERAL DESCRIPTION
42.1. System functions
42.1.1. Functions of main control valves
52.2. Equipment list and system limits
52.3. Description
52.3.1. General
62.3.2. Service Water Pumping Group and associated lines
62.4. Emergency and transients
83.SYSTEM INTERFACES
83.1. General
83.2. Support systems
83.3. Dependent systems
94.OPERATION
94.1. General
94.2. Start-up
94.3. Normal operation
104.4. Shutdown
104.5. Emergency stop. Plant trip
104.5.1. Plant trip without auxiliaries voltage loss
104.5.2. Plant trip with auxiliaries voltage loss
115.CONTROL DESCRIPTION
115.1. Analogue and regulation control loop
115.2. Automation and protective logic
125.2.1. Control of service water pumping group (10GHU21/22AP001)
136.EVENTS AND SET POINTS LIST
147.RELATED DOCUMENTS
147.1. Piping and instrumentation diagrams
147.2. Mechanicals
147.3. Instrumentation and control
1. AIMThe aim of this document is to describe the function and physical layout of the Service Water System for the Bibiyana South 400MW CCPP Also, it is defined the system instrumentation and the control and the interfaces with other systems.
2. GENERAL DESCRIPTION2.1. System functions
The Service Water System function is the supply of service water to all the hose points placed throughout the plant, as well as to supply water at Water Treatment Plant for different process purposes.The systems, buildings and equipment in the distribution net that require service water are:
Water Treatment plant Area Electrical Building
Air Compressors Building
Fire Water pump House
Water Pre-Treatment Area
H2 Generation Plant
Fuel gas Compressor Area
ETP Area
Cooling tower Chemical Dosing
Work Shop Building
Ware House Building
ST Area
GT Area
HRSG Area
2.2. Equipment list and system limits
The following equipment is included in this system. For detailed data for each equipment will be provided later, in equipment data sheet.
Two (2) 2x100% Service Water Distribution Pumps
The following equipment is related with the Service Water System but they belong to other system and will be described in the corresponding functional descriptions.
Clarified Water Storage Tank (belongs to the Clarified Water System)
2.3. Description
2.3.1. GeneralThe Service Water Distribution Pump receives water from the Clarified Water System by means of the pipe.This Pump supplies the service water to all the consumption points by means of the main distribution lines all of them in 1 diameter.The main distribution line distributes service water to the above mentioned building or areas.2.3.2. Service Water Distribution Pump and associated linesThe system has two pumps, 2X110% capacity. These pumps belong to a Pressure group with an accumulator tank. The pressure group has a filter in the common suction pipe. Both of the pumps have isolation valves in the suction line as well as the check valve and isolation valve discharge line.
The normal operation is explained in the point 4.3 of this specification. 2.4. Emergency and transients
The events that cause emergencies or transients in the system are identified below:
Loss of automatic system of service water distribution pump. Low low level in Clarified Water Storage Tank. Any trip from the MCC pumping group.3. SYSTEM INTERFACES 3.1. General
In this section it is described the interfaces of the system with other systems or relevant equipment. The interfaces are classified in those that are necessary for the system operation (support systems) and those that are provided by the system and necessary for other systems operation (dependent systems).3.2. Support systems
Mechanical systems
Clarified Water System Electric system for the pumps operation
Distributed control system (DCS)
3.3. Dependent systems
The following equipment / systems are dependents of the correct operation of the system:
Mechanical systems
Water Treatment Plant
All the hose points where service water is required (see point 2.1)
4. OPERATION4.1. General
For the Service Water System operations, the following operational requirements shall be achieved:
All the Drains and Vent valves shall be closed
All the root valves must be opened and the instrumentation available for operation.
MCCs and required electrical devices are energized.
All equipment and instruments properly installed and calibrated.
The Distributed Control System (DCS) is operational
All the alarms and anomalies must be recognized and the equipment qualified in safe condition to operate.
Clarified Water System working properly.4.2. Start-upIf the level in the Clarified Water Storage Tank is below Low level, the Service Water Distribution Pump will not be able to start.
Service Water Distribution pump will start automatically when there is low pressure in line main distribution line due to a service water demand in the service water net.
4.3. Normal operation
Normal operation shall be accomplished by means of the accumulator tank in the Service Water Distribution. During normal operation, one of the pumps shall be working and the other one shall remain on standby mode. The accumulator tank keeps the pressure in the system so that when any of the consumption points require service water it can be supply without starting up the pumps. When there is low pressure after pumps, the pump that is not on standby mode is started.4.4. Shutdown
In the Service Water System shutdown, when there is no demand of service water, the Service Water Distribution Pump can be stopped.4.5. Emergency stop. Plant trip4.5.1. Plant trip without auxiliaries voltage loss
In the event of a Plant trip without auxiliaries voltage loss, Service Water distribution Pump will be completely stopped. Therefore the system is left out of service.4.5.2. Plant trip with auxiliaries voltage loss
In the event of black out, Service Water Distribution Pump will be completely stopped. Therefore the system is left out of service.
5. CONTROL DESCRIPTION The sizing of the main pipes has been developed considering the maximum allowable velocities indicated in the document BIB-10-YM_-MRD-ISX-001 Mechanical Design Criteria.
LinesService Water Main Distribution Line
Pipe spec.1A1
MaterialCarbon Steel
Pipe size1 1/2
Outside diameter(mm)48.3
Thickness (mm)5.08
Inner diameter(mm)38.14
Water Flow4.16 m3/hr
Operation ConditionsCalculated velocity (m/s)Maximum Allowable velocity (m/s)Compliance
Design point1.013ok
LinesConsumption points lines
Pipe spec.1A1
MaterialCarbon Steel
Pipe size3/4
Outside diameter(mm)26.7
Thickness (mm)3.91
Inner diameter(mm)18.88
Water Flow1.2 m3/hr
Operation ConditionsCalculated velocity (m/s)Maximum Allowable velocity (m/s)Compliance
Design point1.193ok
6. SERVICE WATER DISTRIBUTION PUMP
6.1. Principal characteristics
Quantity:2x100%
Place:Near Clarified Water Storage TankType:Horizontal pumpsFluid:Clarified Water6.2. Design point
The service water is produced in the Water Treatment Plant (WTP) .It is filtered water, with the characteristics indicated in the WTP Technical specification.Service water is used for hose connections for the following services:
Water Treatment plant Area Electrical Building
Air Compressors Building
Fire Water pump House
Water Pre-Treatment Area
H2 Generation Plant
Fuel gas Compressor Area
ETP Area
Cooling tower Chemical Dosing
Work Shop Building
Ware House Building
ST Area
GT Area
HRSG Area
For the consumption point design, it has been considered 1.2 m3/h per hose according to the Water Balance Calculation Report and the peak consumption has been determined considering a simultaneity factor of 0,2, also according to the mentioned report. Thus:
Design flow (100%): 4.16 m3/hr6.3. Suction Pump Line
It has been considered the effect on the pressure loss of the piping route with its specialties as valves, elbows and filter according P&ID and Lay Out.
Velocity at suction line (less than)
1.5 m/s 6.4. Pumps Discharge Line
It has been considered the effect on the pressure loss of the piping route with its specialties as valves, elbows etc. according P&ID and Lay Out.
Total pressure drop in pipes
0.982 bar
PAGE