Works 3: Remediation works of NMK-KIE Page 1 BIDDING DOCUMENTS Under NATIONAL COMPETITIVE BIDDING (NCB) For Procurement of Remediation works of Noor Mohammed Kunta (NMK), Kattedan Industrial Estate (KIE), Ranga Reddy Dist, Telangana State, India NCB No. 003/TSPCB/CBIPMP/NMK Works/2016 Project: Capacity Building for Industrial Pollution Management Project (CBIPMP) Employer: Telangana State Pollution Control Board (TSPCB) Country: India Issued on: 26.02.2016
Transcript

Works 3: Remediation works of NMK-KIE Page 1

BIDDING DOCUMENTS Under

NATIONAL COMPETITIVE BIDDING (NCB)

For Procurement of Remediation works of Noor Mohammed

Kunta (NMK), Kattedan Industrial Estate (KIE), Ranga Reddy Dist, Telangana State, India

NCB No. 003/TSPCB/CBIPMP/NMK Works/2016 Project: Capacity Building for Industrial Pollution Management Project (CBIPMP) Employer: Telangana State Pollution Control Board (TSPCB) Country: India Issued on: 26.02.2016

Works 3: Remediation works of NMK-KIE Page 2

Telangana State Pollution Control Board (TSPCB) Capacity Building for Industrial Pollution Management Project (CBIPMP) World Bank Assisted Project. A-3, Industrial Estate, Sanath Nagar, Hyderabad – 500 018 Ph.No. 040-23887726, e-mail:[email protected] NATIONAL COMPETITIVE BIDDING (NCB)

(Civil Works)

Name of Work Remediation works of Noor

Mohammed Kunta, Kattedan

Industrial Area (KIE) in Rangareddy

District, Telangana State

Period of Sale of Bidding

Documents

From: 26.02.2016

To 11.04.2016

Time And Date Of Pre Bid

Conference

11.03.2016 at 11:00 hrs (IST)

Last Date and Time For Receipt of

Bids

12.04.2016 at 15:00 hrs (IST)

Time and Date of Opening of Bids 12.04.2016 at 15:30 hrs (IST)

Place of Opening of Bids Meeting Hall - I

TSPCB, Paryavaran Bhavan,

A-3, Industrial Estate,

Sanath Nagar, Hyderabad - 500018

Officer Inviting Bids The Project Director / Member

Secretary, TSPCB

*: tentative dates

Works 3: Remediation works of NMK-KIE Page 3

INVITATION FOR BID

(IFB)

Works 3: Remediation works of NMK-KIE Page 4

Telangana State Pollution Control Board (TSPCB) Capacity Building for Industrial Pollution Management Project (CBIPMP)

World Bank Assisted Project. A-3, Industrial Estate, Sanath Nager, Hyderabad – 500 018

Ph.No. 040-23887726, e-mail:[email protected]

INVITATIONS FOR BIDS (IFB) NATIONAL COMPETITIVE BIDDING Loan No.: Loan 7924-IN/Credit No.: 4755-IN Date: 26.02.2016 Bid No.: 003/TSPCB/CBIPMP/NMK Works/2016

1. The Government of India has received a credit from the International Development Association / loan from the International Bank for Reconstruction & Development towards the cost of the “Capacity Building for Industrial Pollution Management (CBIPM) Project and intends to apply a part of the funds to cover eligible payments under the contracts for construction of works as detailed below. Bidding is open to all bidders from eligible source countries as defined in the IBRD Guidelines for Procurement. Bidders from India should, however, be registered with the Government of Telangna or other State Governments/Government of India, or State/Central Government Undertakings. Bidders are advised to note the minimum qualification criteria specified in Clause 4 of the Instructions to Bidders to qualify for the award of the contract.

2. The Telangana State Pollution Control Board (TSPCB) invites bids for the construction of

remediation works as per table below. The bidders may submit bids for all of the following works.

3. Bidding documents (and additional copies) may be purchased from the office of

Telangana State Pollution Control Board, Paryavaran Bhavan, A-3-Industrial Estate, Sanathnagar, Hyderabad-18, Telangana, India from 26.02.2016 to 11.04.2016 for a non-refundable fee (Two sets) of INR. 10,000/- (Rupees Ten Thousand Only) in the form of cash or Demand Draft on any Scheduled bank payable at Hyderabad in favour of “Member Secretary, TSPCB, Hyderabad”. The Bid Documents are also uploaded on to our website http://tspcb.cgg.gov.in. Interested bidders may download or purchase the Bid Documents from our office. The bidders can also obtain further information about the project from our office at address of “Telangana State Pollution Control Board”A-3, Industrial Estate, Sanath Nagar, Hyderabad - 500018. Bidding documents requested by mail will be despatched by registered/speed post on payment of an extra amount of Rs. 1,000/-. The Telangana State Pollution Control Board will not be held responsible for the postal delay if any, in the delivery of the documents or non-receipt of the same.

4. Bids must be accompanied by security of the amount specified for the work in the table

below, drawn in favour of "The Member Secretary, Telangana State Pollution Control

Works 3: Remediation works of NMK-KIE Page 5

Board." Bid security will have to be in any one of the forms as specified in the bidding document and shall have to be valid for 45 days beyond the validity of the bid.

5. Bids must be delivered to Senior Environmental Engineer (SEE) and PIU Head of CBIPMP,

Telangana State Pollution Control Board, Paryavarana Bhavan, A-3, Industrial Estate, Sanath Nagar, Hyderabad- 500018 on or before 12.04.2016 hours on 15.00 and will be opened on the same day at 15.30 hours, in the presence of the bidders who wish to attend. If the office happens to be closed on the date of receipt of the bids as specified, the bids will be received and opened on the next working day at the same time and venue.

6. A pre-bid meeting will be held on 11.03.2016 at 11.00 Hrs at the office of Telangana State

Pollution Control Board, Paryavaran Bhavan, A-3, Industrial Estate, Sanath Nagar, Hyderabad – 500018 to clarify the issues and to answer questions on any matter that may be raised at that stage as stated in Clause 9.2 of ‘Instructions to Bidders’ of the bidding document. Bidders are requested to visit the site prior to the Pre Bid meeting in order to have full acquaintance with the site conditions.

7. Other details can be seen in the bidding documents.

Package

No

Name of works

Approx. Value

of works *

Bid security

Cost of Bid Document

Period of Completion

1 2 3 4 5 6

NMK-KIE/003

Remediation works of Noor Mohammed Kunta, Kattedan Industrial Area (KIE) in Rangareddy District, Telangana

INR.37,15,48,000/- (Rupees thirty seven crores fifteen lakhs forty eight thousand only)

INR.37,15,480/- (Rupees thirty seven lakhs fifteen thousand four hundred and eighty only)

INR. 10,000/-

(Rupees ten thousand only)

17 Months

* The above approx. value of work has been arrived based on AP standard data, SSR of 2014-15, SSR 2015-16 and market consultation

Signature and Seal of Contractor Authorized Signatory

Works 3: Remediation works of NMK-KIE Page 6

CONTENT OF BID DOCUMENT

SECTION 1 INSTRUCTIONS TO BIDDERS (ITB)

SECTION 2 FORMS OF BID, QUALIFICATION INFORMATION AND LETTER OF ACCEPTANCE

SECTION 3 CONDITION OF CONTRACT

SECTION 4 CONTRACT DATA

SECTION 5 SPECIFICATIONS

SECTION 6 DRAWINGS

SECTION 7 BILL OF QUANTITY

SECTION 8 FORMS OF SECURITIES

SECTION 9 ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN

Works 3: Remediation works of NMK-KIE Page 7

SECTION 1 : INSTRUCTION TO BIDDERS(ITB)

Works 3: Remediation works of NMK-KIE Page 8

Section 1: Instructions to Bidders Table of Clauses

A. General Page No. D. Submission of Bids Page No.

1. Scope of Bid 3 19. Sealing and Marking of Bids 17

2. Source of Funds 3 20. Deadline for Submission of Bids 17

3. Eligible Bidders 3 21. Late Bids 18

4. Qualification of the Bidder 3 22. Modification and Withdrawal of Bids18

5. One Bid per Bidder 12

6. Cost of Bidding 12

7. Site Visit 12

B. Bidding Documents E. Bid Opening and Evaluation

8. Content of Bidding Documents 12 23. Bid Opening 18

9. Clarification of Bidding Documents 13 24. Process to be Confidential 19

10. Amendment of Bidding Documents13 25. Clarification of Bids 19

26. Examination of Bids and Determination of Responsiveness 19

27. Correction of Errors 19

C. Preparation of Bids 28. Currency for Bid Evaluation/Deleted 19

29. Evaluation and Comparison of Bids 20

11. Language of Bid 14 30. Preference for Domestic Bidders

/Deleted 20

12. Documents Comprising the Bid 14

13. Bid Prices 14 F. Award of Contract

14. Currencies of Bid and Payment 15

15. Bid Validity 15 31. Award Criteria 21

16. Bid Security 15 32. Employer's Right to Accept any Bid and

Works 3: Remediation works of NMK-KIE Page 9

to Reject any or all Bids 21

17. Alternative Proposals by Bidders 16 33. Notification of Award 21

18. Format and Signing of Bid 16 34. Performance Security 22

35. Advance Payment and Security 22

36. Adjudicator 22

37. Corrupt or Fraudulent Practices 22

Works 3: Remediation works of NMK-KIE Page 10

A. General

1. Scope of Bid

1.1 The Telangana State Pollution Control Board, (TSPCB) (referred to as Employer in these documents) invites bids for the construction of works (as defined in these documents and referred to as "the works") detailed in the table given in IFB.

1.2 The successful bidder will be expected to complete the works by the intended completion date specified in the Contract data.

2. Source of Funds

2.1 The Government of India has received a loan/credit from the International Bank for Reconstruction and Development/the International Development Association (hereinafter interchangeably called “the Bank”) towards the cost of CBIPMP Project and intends to apply a part of the funds to cover eligible payments under the contract for the Works. Payments by the Bank will be made only at the request of the borrower and upon approval of the Bank in accordance with the Loan/Credit Agreement, and will be subject in all respects to the terms and conditions of that Agreement. Except as the Bank may specifically otherwise agree, no party other than the borrower shall derive any rights from the Loan/Credit Agreement or have any rights to the loan/credit proceeds.

2.2 The loan agreement prohibits a withdrawal from the loan account for the purpose of any payment to persons or entities, or for any import of goods, if such payment or import, to the knowledge of the Bank, is prohibited by a decision of the United Nations Security Council, taken under Chapter VII of the Charter of the United Nations.

3. Eligible Bidders

3.1 This Invitation for Bids is open to all bidders from the eligible countries as defined under the IBRD Guidelines for Procurement). Any materials, equipment, and services to be used in the performance of the Contract shall have their origin in the eligible source countries. The details of the eligible source countries may be had from the web link below: http://www.worldbank.org/en/country

3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a statement that the Bidder is not associated, nor has been associated in the past, directly or indirectly, with the Consultant or any other entity that has prepared the design, specifications, and other documents for the Project or being proposed as Project Manager for the Contract. A firm that has been engaged by the Borrower to provide consulting services for the preparation or supervision of the works, and any of its affiliates, shall not be eligible to bid.

Works 3: Remediation works of NMK-KIE Page 11

3.3 Government-owned enterprises in the Employer’s country may only participate if they are legally and financially autonomous, operate under commercial law and are not a dependent agency of the Borrower or Sub-borrower.

3.4 Bidders shall not be under a declaration of ineligibility for corrupt and fraudulent practices issued by the Bank in accordance with sub-clause 37.1.

4. Qualification of the Bidder

4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.

4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.

4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:

(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;

(b) total monetary value of construction work performed for each of the last five years;

(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;

(d) major items of construction equipment proposed to carry out the Contract;

(e) qualifications and experience of key site management and technical personnel proposed for the Contract;

(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;

(g) evidence of adequacy of working capital for prime and other partners for this contract (access to line (s) of credit and availability of other financial resources)

(h) authority to seek references from the Bidder's bankers;

(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information

Works 3: Remediation works of NMK-KIE Page 12

shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;

(j) proposals for subcontracting components of the Works which in aggregate add to more than 20 percent of the Bid Price (for each, the qualifications and experience of the identified sub-contractor in the relevant field should be annexed; vertical splitting of work for sub-contracting is not acceptable);

(k) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment, materials and manpower planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.

(l) For bids submitted by joint venture firms, the Joint venture agreement shall be furnished as per the format attached in the tender documents.

4.4 Bids from Joint ventures are also acceptable. However the prime bidder (51%) will be solely responsible for the overall construction works and satisfactory performance of the entire assignment of remediation works. The number of members of JV to be limited to three member companies including prime bidder.

Bids submitted by a joint venture of Prime bidder (51%) and / or a maximum of two other partners shall comply with the following requirements:

[a] The bid shall include all the information listed in Sub-clause 4.3 above;

[b] The bid and, in case of a successful bid, the Agreement, shall be signed so as to be legally binding on all partners;

[c] One of the partners shall be nominated as being in charge, and this authorization shall be evidenced by submitting a power of attorney signed by legally authorized signatories of all the partners;

[d] The partner in charge shall be authorized to incur liabilities and receive instructions for and on behalf of any and all partners of the joint venture and the entire execution of the contract, including payment, shall be done exclusively with the partner in charge;

[e] All partners of the joint venture shall be liable jointly and severally for the execution of the contract in accordance with the contract terms, and a statement to this effect shall be included in the authorization mentioned under [c] above, as well as in the bid and in the Agreement [in case of a successful bid];

[f] The joint venture agreement should indicate precisely the role of all members of JV in respect of planning, design, construction equipment, key personnel, work execution, and financing of the project. All members of JV should have active participation in execution

Works 3: Remediation works of NMK-KIE Page 13

during the currency of the contract. This should not be varied/modified subsequently without prior approval of the employer;

[g] The joint venture agreement should be registered in Hyderabad, India so as to be legally valid and binding on partners; and

[h] A copy of the Joint Venture Agreement entered into by the partners shall be submitted with the bid. Alternatively, a Letter of Intent to execute a joint Venture Agreement in the event of a successful bid shall be signed by all partners and submitted with the bid, together with a copy of the proposed Agreement. In case a Letter of Intent is submitted with the bid, the Joint Venture Agreement will have to be signed and registered before the contract is issued and signed, without delaying the project’s time line.

[i] "The Joint Venture shall jointly be bound unto the Employer for the successful performance of the Contract and shall be fully responsible for the works in terms of quality requirements and timeliness in performance in accordance with the Contract. Irrespective of Joint responsibility, it is expressly understood that PRIME BIDDER will be present at the site of the works, through its authorized representative at all times and play lead role in mobilizing resources and execution of the contract. The PRIME BIDDER will incur liabilities and receive instructions for and on behalf of any or all partners of the Joint Venture and entire execution of the contract shall be done by the PRIME BIDDER and payment under the contract shall be received by the PRIME BIDDER. The precise responsibility of the members of the Joint Venture in respect of planning, quality, execution of the works shall be mentioned in the Joint Venture Agreement as per attached format (Annex I) and the execution of the same will be the sole responsibility of the Prime Bidder.

If in the determination of the Employer that the PRIME BIDDER is unable to fulfil its responsibility as per the Contract, the Employer shall be at liberty to terminate the contract which shall be binding on all partners of the Joint Venture." In this case, the Employer will claim compensation for losses suffered.

Qualification Criteria:

General (1) Evaluation of the Bidders’ qualifications will be based on compliance with all the following minimum pass-fail criteria listed in the following sections, considering relevant information as demonstrated by the Bidders’ responses in the Information Forms that they submit as per the attached Bid Forms. Additional requirements for joint ventures are also highlighted in the bid documents.

(2) Bidders may submit the Bid either as,

Works 3: Remediation works of NMK-KIE Page 14

(a) A stand-alone firm, company, legal entity formed as per the applicable law; or

(b) A joint venture, provided that they meet the requirements of the Bidding Documents. For the purpose of assessing some qualification criteria, the qualifications and experience of subcontractors may be included and the specific provisions in this regard are set out in the Bid Documents.

Subcontracting The percentage of works which can be sub-contracted shall not exceed 49% of the works with a maximum of two members. (1) Bidders will be evaluated based on the qualifications of,

(a) the Bidder; and (b) nominated subcontractors and sub-consultants only with respect to the experience evaluation as set out in the bid documents, and only if the subcontractors and sub-consultants are nominated for the purpose of this bid.

Bidders may nominate personnel of subcontractors and sub-consultants to fill the key positions listed in the further section of the bid documents as set out for qualification criteria.

(2) The Bidder shall provide a detailed list of all nominated subcontractors and sub-consultants and a record of their experience and qualifications in the applicable Information Forms. (3) the bidder to specify the total amount of work which will be sub contracted; out of the total works in BoQ and highlight the costs for the same. (4) Bidders will not be permitted to change the subcontractors and sub-consultants nominated in their Bid unless previously agreed upon by the Employer.. Contractor’s Responsibility After award of the Contract, the subcontracting of any part of the work, except for those subcontractors and sub consultants nominated in the Bid, shall require the prior written consent of the Employer / Engineer in charge. Notwithstanding such consent, the Contractor shall remain responsible for the acts, defaults, and neglects of all subcontractors and sub consultants during Contract implementation. Definitions:

For the purpose of this Bidding Document,

Works 3: Remediation works of NMK-KIE Page 15

a) Environmental dredging is an excavation activity or operation carried out underwater, in shallow seas or fresh water areas with the purpose of gathering up polluted bottom sediments and safely disposing of them at a different location in accordance with applicable environmental regulations.

b) Dewatering is the removal of water from sediment with the use of flocculants, electrolytes and/or bags or tubes of geotextile, with the aim to contain the polluted sediments within those bags or tubes.

c) a “Containment cell” means a remediation facility including a bottom liner and closing top liner that is designed to receive polluted sediments or soil in such away that complete containment of this polluted material in the closed containment cell can be guaranteed.

4.5 A. To qualify for award of the contract, each bidder in its name should have in the last

five years i.e. 2010-11, 2011-12, 2012-13 , 2013-14 and 2014-15 of experience in the relevant works

(a) achieved, in the last five years, a minimum annual financial turnover (Experience under construction contracts related to the lake remediation) of Rs.38 Crores (Rupees forty crores only)@ - in any one year during the last five years. Balance Sheets and Profit and Loss Statements shall have to be submitted by the bidder as proof of the same.

(b) Satisfactorily completed, as a prime contractor, (or as subcontractor duly certified by the employer/main contractor) at least one similar work (lake remediation or dredging) of value not less then Rs. 18 crores (Rupees twenty crores only) @ in any one year during the last five years.

(c) The prime bidder / JV partner should have executed similar Hazardous Waste Landfill facility construction / closure works as per HWM 2008 Rules or sanitary landfill construction / closure works as per MSW Rules 2000 of a value not less then Rs.2.00 crores (Rupees Two

Crores only) @ in any one year during the last five years. (d) The contractor or at least a selected sub contractor from a list of empanelled sub

contractors with the contractor should have executed similar work of laying the sand layer with value of atleast Rs-50.00 lakhs (excluding sand cost). in any one year during the

last five years. @ - at 2015 price level. Financial Turnover and Cost of Completed works of previous years shall be given weightage of 5% per year based on Rupee value to bring them to 2015 price level,

(e) Minimum quantities of work required for environmental dredging, dewatering and construction of a containment cell, including processing works along with succesfull completion certificates as a Prime bidder / Joint Venture (JV):

- Earthworks for excavation, backfilling and profiling (levelling and compaction) for construction of containment cells and general remediation works of quantity 15,000 cum. for single bidder or JV together.

Works 3: Remediation works of NMK-KIE Page 16

- HDPE Liner laying, welding and installation experience for construction of containment cell of quantity 20,000 sq.m for single bidder or JV together

- Environmental Dredging work including handling of sediment material. The experience of the mechanical dredging in water / acquatic environment will only be considered at least 20,000cum. for single bidder or JV together or identified sub-contractor.

- De watering of sediments with the use of flocculants /electrolytes and/ or bags of tubes

of geotextile with the aim to contain the polluted sediments within those bags or tubes

for a total quantity of 20,000 cum for single bidder or JV together or identified sub-

contractor.

- application of 0.30 m thick layer of sand with aim to cover underwater bottom of fresh water bodies or shallow seas of quantity 10,000 sq.m for single bidder or JV together or identified sub-contractor.

The bidders are requested to submit the project reference / data sheets of relevant assignments

and Engineer in Charge or client reference with address and contact details.

(f) The Contractors / Companies shall have all necessary regulatory licences for execution of the work and provide necessary proofs of licences for the same.

For the purpose of demonstrating its experience in accordance with above sections, the Bidder, may include the experience of the subcontractors and/or sub-consultants nominated in the Information Forms.

Financial Capabilities

(1) The bidder shall submit along with the bid a banker’s certificate (only as per format attached) that it has available cash credit facility equivalent to minimum INR 7.9 crores specifically obtained for the purpose of this bid. (2) The Bidder’s audited balance sheets or, if not required by the laws of the Bidder’s country, other financial statements acceptable to the Owner, for the last three years shall be submitted and must demonstrate the current soundness of the Bidder’s financial position and indicate its prospective long-term profitability. If deemed necessary by the Owner, the Owner shall have the authority to make inquiries with the Bidder’s bankers. Personnel Capabilities

The Bidder shall supply general information on the management structure of the firm, and shall make provision for suitably qualified personnel to fill the key positions listed in the ITB, as required during Contract implementation. The Bidder shall supply information on a candidate for each key position, who shall meet the experience requirements specified. The Bidder may nominate personnel of subcontractors and sub consultants to fill key positions listed in the ITB.

Works 3: Remediation works of NMK-KIE Page 17

Litigation History and Legal Matters The Bidder shall provide accurate information on the “Historical Contract Non-Performance Form” about contract non-performance and pending litigation with respect to contracts completed or ongoing under its execution over the last five years. A consistent history of awards against the Bidder or any Partner of a joint venture may result in rejection of the Bid. Right to Waive The Owner reserves the right to waive minor deviations in the qualification criteria if they do not materially affect the capability of a Bidder to perform the Contract.

4.5 B. Each bidder should further demonstrate:

(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work (Minimum No required):

- Dredger equipped with an auger head – 1

The actual operation and movement of the dredging equipment should be computer guided on the basis of this 3D model and a high accuracy dGPS positioning system. The combination of the 3D model guidance and dGPS positioning has to allow for a total vertical dredging accuracy of + 0.03 m.

- Hydraulic dredger with auger head and with a daily capacity of at least 350 cums per day, including sufficient floating pipelines to transport the sediment slurry - 1 No.

- Mixing unit which is able to add the required amount of flocculants/electrolytes to a minimum amount of 350 cums of sediment per day - 2 No.

- System consisting of pumps and pipes, which is at least able to pump a minimum amount of 350 cums of sediments per day and additional required volumes of process water and flocculants/electrolytes with appropriate pressure in the tubes of geotextile - 2 No.

- Rainbow unit which is able to apply 100 cums of sand per day in a 0.3 m thick layer on the floor of Lake NMK - 1 No.

- Pontoons - 10 No. or in a number sufficient to provide 2 times a free working platform of at least 20 sq.m and a bearing capacity sufficient to transport an hydraulic excavator.

- Hydraulic excavator 1.5 cum bucket size - 2 No. or in a number sufficient to handling up to 800 cum per day

Works 3: Remediation works of NMK-KIE Page 18

- Tippers 5 cum - 5 No. or in a number sufficient to handling and transporting up to 400 cums per day

- Trucks 10 t - No. 10. Or in a number sufficient to handling and transporting up to 800 cums per day.

- Complete set of welding and laying equipment for HDPE liner, set should have at least a capacity to install 1,500 sq.m of liner per day - 2 No.

- Soil compaction rollers (5-15 ton) - 2 Nos

- Hydraulic Excavator with 1.5 m3 bucket - 2 Nos

- 2 tonnes flat vibratory roller - 2 Nos

- 2 m3 Front End Loaders, Loader Backhoes - 2 Nos

- 3 m3 Water Tankers for amongst others dust prevention- 2 Nos

- 10 ton Bulldozers - 1 Nos

- 150 mm bore drilling equipment for monitoring wells till 300 feet deep - 3 Nos

The bidder shall state type and number of equipment which he has owned / leased in the submission. The bidder shall also confirm that maintenance and repair staff and spare parts will be available on site so as to guarantee an uptime of 95% throughout the project.

Based on the studies, carried out by the Engineer in charge, the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule are shown in the above list.

The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.

(b) availability of Key personnel’s Proposed for this project with highlighted adequate experience of similar works:

Following Qualification of Key personnel’s are the minimum requirements which the Bidder shall demonstrate especially for the Environmental Dredging, Dewatering and Containment Cell Construction Works:

The Bidder must demonstrate that it has the personnel for the key positions that meet the

following requirements:

Works 3: Remediation works of NMK-KIE Page 19

Sr.

No

Position Nos Total Work

Experience

(Years)

Experience

in Similar

Works

(Years)

1 Project Manager (Graduate Civil Engineer with

experience in dredging and remediation works

/ containment cell construction works)

1 10 3

2 Engineer / Specialist with experience of

operating dredging equipment and installation

of underwater cover layers

1 7 3

3 Engineer / Specialist with experience of

sediment dewatering with flocculants/

electrolytes and tubes of geotextile

1 7 3

4 Quality Assurance Engineer - Experience in

HDPE Liner system (Laying, Welding and

Jointing, Installation, Testing for leak proof

joints) and Geo Composite Layer Laying Works

– Drainage Arrangements etc.

1 7 3

5 Site Engineer (Civil) 2 5 3

6 HDPE Welders – 1 each 1 5 3

Contractor shall mobilise other expert personnel’s for waste collection and disposal, surface water drainage works, gabion construction and installation as necessary.

(c) liquid assets and/or availability of credit facilities of no less than Rs 7 Crores in the format given in Section 2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)

4.6 The figures for each of the partners of a joint venture shall be added together to determine the Bidder’s compliance with the minimum qualifying criteria of Sub-clause 4.5. Failure to comply with this requirement will result in rejection of the joint venture’s bid.

Sub-contractor’s experience and resources will not be taken into account in determining the Bidder’s compliance with the qualifying criteria, except to the extent stated in Clause 4.5 [A] above.

4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under:

Works 3: Remediation works of NMK-KIE Page 20

Assessed Available Bid capacity = ( A*N*1.5 - B )

where

A = Maximum value of civil engineering works executed in any one year during the last five years (updated to 2015 price level) taking into account the completed as well as works in progress.

N = Number of years prescribed for completion of the works for which bids are invited = 1 year

B = Value, at 2015 price level, of existing commitments and on-going works to be completed during the next 1 year (period of completion of the works for which bids are invited)

4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:

- made misleading or false representations in the forms, statements and attachments submitted in proof of the qualification requirements; and/or

- record of poor performance such as abandoning the works, not properly completing the contract, inordinate delays in completion, litigation history, or financial failures etc.; and/or

- participated in the previous bidding for the same work and had quoted unreasonably high bid prices and could not furnish rational justification to the employer.

5. One Bid per Bidder

5.1 Each bidder shall submit only one bid for one contract, either individually or as a partner in a Joint Venture. A bidder who submits or participates in more than one Bid (other than as a subcontractor or in cases of alternatives that have been permitted or requested) will cause all the proposals with the Bidder’s participation to be disqualified.

6. Cost of Bidding

6.1 The bidder shall bear all costs associated with the preparation and submission of his Bid, and the Employer will in no case be responsible and liable for those costs.

7. Site visit

7.1 The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and examine the Site of Works and its surroundings and obtain all information that may be necessary for preparing the Bid and entering into a contract for construction of the Works. The costs of visiting the Site shall be at the Bidder's own expense.

Works 3: Remediation works of NMK-KIE Page 21

B. Bidding Documents

8. Content of Bidding Documents

8.1 The set of bidding documents comprises the documents listed in the table below and addenda issued in accordance with Clause 10:

Invitation for Bids

Section 1 Instructions to Bidders

2 Forms of Bid and Qualification Information

3 Conditions of Contract

4 Contract Data

5 Specifications

6 Drawings

7 Bills of Quantities

8 Forms of Securities

9 ESMP for Remediation of Lake NMK in Kattedan Industrial Area (KIE) in

Rangareddy District

8.2 Of the two sets of the bidding documents supplied, two sets shall be completed and returned with the bid.

9. Clarification of Bidding Documents

9.1 A prospective bidder requiring any clarification of the bidding documents may notify the Employer in writing or by cable (hereinafter "cable" includes email:[email protected]) at the Employer's address indicated in the invitation to bid. The Employer will respond to any request for clarification which he received earlier than 15 days prior to the deadline for submission of bids. Copies of the Employer's response will be forwarded to all purchasers of the bidding documents, including a description of the enquiry but without identifying its source.

9.2 Pre-bid meeting

9.2.1 The bidder or his official representative is invited to attend a pre-bid meeting which will take place on 11.03.2016 at 11.00 Hrs (IST) at the office of Telangana State Pollution Control Board, Paryavaran Bhavan, A-3, Industrial Estate, Sanath Nagar, Hyderabad – 500018.

Works 3: Remediation works of NMK-KIE Page 22

9.2.2 The purpose of the meeting will be to clarify issues and to answer questions on any matter that may be raised at that stage.

9.2.3 The bidder is requested to submit any questions in writing or by cable to reach the Employer not later than one week before the meeting.

9.2.4 Minutes of the meeting, including the text of the questions raised (without identifying the source of enquiry) and the responses given will be transmitted without delay to all purchasers of the bidding documents. Any modification of the bidding documents listed in Sub-Clause 8.1 which may become necessary as a result of the pre-bid meeting shall be made by the Employer exclusively through the issue of an Addendum pursuant to Clause 10 and not through the minutes of the pre-bid meeting.

9.2.5 Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.

10. Amendment of Bidding Documents

10.1 Before the deadline for submission of bids, the Employer may modify the bidding documents by issuing addenda.

10.2 Any addendum thus issued shall be part of the bidding documents and shall be communicated in writing to all the purchasers of the bidding documents. Prospective bidders shall acknowledge receipt of each addendum in writing to the Employer.

10.3 To give prospective bidders reasonable time in which to take an addendum into account in preparing their bids, the Employer shall extend as necessary the deadline for submission of bids, in accordance with Sub-Clause 20.2 below.

C. Preparation of Bids

11. Language of the Bid

11.1 All documents relating to the bid shall be in the English language.

12. Documents comprising the Bid

12.1 The bid submitted by the bidder shall comprise the following:

(a) The Bid (in the format indicated in Section 2).

(b) Bid Security;

(c) Priced Bill of Quantities;

(d) Qualification Information Form and Documents;

Works 3: Remediation works of NMK-KIE Page 23

and any other materials required to be completed and submitted by bidders in accordance with these instructions. The documents listed under Sections 2, 4 and 7 of Sub-Clause 8.1 shall be filled in without exception.

12.2 Bidders bidding for this contract together with other contracts stated in the IFB to form a package will so indicate in the bid together with any discounts offered for the award of more than one contract.

13. Bid Prices

13.1 The contract shall be for the whole works as described in Sub-Clause 1.1, based on the priced Bill Quantities submitted by the Bidder.

13.2 The bidder shall fill in rates and prices and line item total (both in figures and words) for all items of the Works described in the Bill of Quantities along with total bid price (both in figures and words). Items for which no rate or price is entered by the bidder will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantities. Corrections, if any, shall be made by crossing out, initialing, dating and rewriting.

13.3 All duties, taxes, and other levies payable by the contractor under the contract, or for any other cause shall be included in the rates, prices and total Bid Price submitted by the Bidder.

Note: “Bidders may like to ascertain availability of excise/custom duty exemption benefits available in India to the contracts financed under World Bank loan/credits. They are solely responsible for obtaining such benefits which they have considered in their bid and in case of failure to receive such benefits for reasons whatsoever, the employer will not compensate the bidder (contractor). Where the bidder has quoted taking into account such benefits, he must give all information required for issue of certificates in terms of such notifications as per form attached to the Qualification Information in the bid. To the extent the employer determines the quantity indicated therein are reasonable keeping in view the bill of quantities, construction programme and methodology, the certificates will be issued within 60 [sixty] days of signing of contract and no subsequent changes will be permitted. No certificate will be issued for items where no quantity/capacity of equipment is indicated in the statement. The bids which do not conform to the above provisions will be treated as non responsive and rejected. Any delay in procurement of the construction equipment /machinery/goods as a result of the above shall not be a cause for granting any extension of time.”

13.4* The rates and prices quoted by the bidder shall be fixed for the duration of the Contract and shall not be subject to any adjustment on any account.

Works 3: Remediation works of NMK-KIE Page 24

14. Currencies of Bid and Payment

14.1 The unit rates and the prices shall be quoted by the bidder entirely in Indian Rupees.

15. Bid Validity

15.1 Bids shall remain valid for a period not less than ninety days after the deadline date for bid submission specified in Clause 20. A bid valid for a shorter period shall be rejected by the Employer as non-responsive.

15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may request that the bidders may extend the period of validity for a specified additional period. The request and the bidders' responses shall be made in writing or by cable. A bidder may refuse the request without forfeiting his bid security. A bidder agreeing to the request will not be required or permitted to modify his bid except as provided in 15.3 hereinafter, but will be required to extend the validity of his bid security for a period of the extension, and in compliance with Clause 16 in all respects.

15.3 In the case of contracts in which the Contract Price is fixed (not subject to price adjustment), in the event that the purchaser requests and the Bidder agrees to an extension of the validity period, the contract price, if the Bidder is selected for award shall be the bid price corrected as follows:

The price shall be increased by the factor (value of factor B)1 for each week or part of a week that has elapsed from the expiration of the initial bid validity to the date of issue of letter of acceptance to the successful Bidder.

15.4 Bid evaluation will be based on the bid prices without taking into consideration the above correction.

16. Bid Security

16.1 The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in column 4 of the table of IFB for this particular work. This bid security shall be in favour of Member Secretary, Telangana State Pollution Control Board, Hyderabad, and may be in one of the following forms:

- A bank guarantee issued by a nationalized / scheduled bank located in India or a

reputable bank located abroad having corresponding bank in India, in the form

given in Section 8; or

- Certified cheque, Bank draft or Letter of Credit in favour of Member Secretary,

Telangana State Pollution Control Board, Hyderabad payable at Hyderabad

16.2 Bank guarantees issued as surety for the bid shall be valid for 45 days beyond the validity of the bid.

Works 3: Remediation works of NMK-KIE Page 25

16.3 Any bid not accompanied by a acceptable Bid Security and not secured as indicated in Sub-Clauses 16.1 and 16.2 above shall be rejected by the Employer as non-responsive. The bid security of a joint venture must define as ‘bidder’ all joint venture partners and list them in the following manner : a joint venture consisting of ‘…….’, ‘……….’, and ‘……….’and specify the name of the Lead Partner.

16.4 The Bid Security of unsuccessful bidders will be returned within 28 days of the end of the bid validity period specified in Sub-Clause 15.1.

16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed the Agreement and furnished the required Performance Security.

16.6 The Bid Security may be forfeited

(a) if the Bidder withdraws the Bid after Bid opening during the period of Bid validity;

(b) if the Bidder does not accept the correction of the Bid Price, pursuant to Clause 27; or

(c) in the case of a successful Bidder, if the Bidder fails within the specified time limit to

(i) sign the Agreement; or

(ii) furnish the required Performance Security.

17. Alternative Proposals by Bidders

17.1 Bidders shall submit offers that comply with the requirements of the bidding documents, including the basic technical design as indicated in the drawings and specifications.

Alternative solutions will not be accepted.

8. Format and Signing of Bid

18.1 The Bidder shall prepare one original and one copy of the documents comprising the bid as described in Clause 12 of these Instructions to Bidders, bound with the volume containing the Form of Bid, and clearly marked "ORIGINAL" and "COPY" as appropriate. In the event of discrepancy between them, the original shall prevail.

18.2 The original and copy of the Bid shall be typed or written in indelible ink and shall be signed by a person or persons duly authorized to sign on behalf of the Bidder, pursuant to Sub-Clauses 4.3. All pages of the bid where entries or amendments have been made shall be initialled by the person or persons signing the bid.

18.3 The Bid shall contain no alterations or additions, except those to comply with instructions issued by the Employer, or as necessary to correct errors made by the bidder, in which case such corrections shall be initialled by the person or persons signing the bid.

Works 3: Remediation works of NMK-KIE Page 26

18.4 The Bidder shall furnish information as described in the Form of Bid on commissions or gratuities, if any, paid or to be paid to agents relating to this Bid, and to contract execution if the Bidder is awarded the contract.

D. Submission of Bids

19. Sealing and Marking of Bids

19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as "ORIGINAL" and "COPY". These envelopes (called as inner envelopes) shall then be put inside one outer envelope.

19.2 The inner and outer envelopes shall

(a) be addressed to the Employer at the following address:

Project Director / Member Secretary, Telangana State Pollution Control Board, Paryavarana Bhavan, A-III, Industrial Estate, Sanath Nagar, Hyderabad - 500 018.

and

(b) bear the following identification:

- Bid for Remediation works of Noor Mohammed Kunta, Kattedan Industrial Area (KIE) in Rangareddy District, Telangana

- Bid Reference No. 003/TSPCB/WB-CBIPMP/NMK Works/2016

- DO NOT OPEN BEFORE 15.30 hrs (IST) on 12.04.2016

19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause 21.

19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the misplacement or premature opening of the bid.

20. Deadline for Submission of the Bids

20.1 Bids must be received by the Employer at the address specified above no later than 12.04.2016 upto 15.00 Hrs (IST). In the event of the specified date for the submission of bids declared a holiday for the Employer, the Bids will be received upto the appointed time on the next working day.

Works 3: Remediation works of NMK-KIE Page 27

20.2 The Employer may extend the deadline for submission of bids by issuing an amendment in accordance with Clause 10, in which case all rights and obligations of the Employer and the bidders previously subject to the original deadline will then be subject to the new deadline.

21. Late Bids

21.1 Any Bid received by the Employer after the deadline prescribed in Clause 20 will be returned unopened to the bidder.

22. Modification and Withdrawal of Bids

22.1 Bidders may modify or withdraw their bids by giving notice in writing before the deadline prescribed in Clause 20.

22.2 Each Bidder's modification or withdrawal notice shall be prepared, sealed, marked, and delivered in accordance with Clause 18 & 19, with the outer and inner envelopes additionally marked "MODIFICATION" or "WITHDRAWAL", as appropriate.

22.3 No bid may be modified after the deadline for submission of Bids.

22.4 Withdrawal or modification of a Bid between the deadline for submission of bids and the expiration of the original period of bid validity specified in Clause 15.1 above or as extended pursuant to Clause 15.2 may result in the forfeiture of the Bid security pursuant to Clause 16.

22.5 Bidders may offer discounts to, or modify the prices of their Bids only by submitting Bid modifications in accordance with this clause, or included in the original Bid submission.

E. Bid Opening and Evaluation

23. Bid Opening

23.1 The Employer will open all the Bids received (except those received late), including modifications made pursuant to Clause 22, in the presence of the Bidders or their representatives who choose to attend at Meeting Hall-II of TSPCB at 15.30 Hrs (IST) hours on the date and the place specified in Clause 20. In the event of the specified date of Bid opening being declared a holiday for the Employer, the Bids will be opened at the appointed time and location on the next working day.

23.2 Envelopes marked "WITHDRAWAL" shall be opened and read out first. Bids for which an acceptable notice of withdrawal has been submitted pursuant to Clause 22 shall not be opened. Subsequently all envelopes marked “Modification” shall be opened and the submissions therein read out in appropriate detail.

23.3 The Bidders' names, the Bid prices, the total amount of each Bid and of any alternative Bid (if alternatives have been requested or permitted), any discounts, Bid modifications and withdrawals, the presence or absence of Bid security, and such other details as the

Works 3: Remediation works of NMK-KIE Page 28

Employer may consider appropriate, will be announced by the Employer at the opening. No bid shall be rejected at bid opening except for the late bids pursuant to Clause 21. Bids [and modifications] sent pursuant to Clause 22 that are not opened and read out at bid opening will not be considered for further evaluation regardless of the circumstances. Late and withdrawn bids will be returned un-opened to bidders.

23.4 The Employer shall prepare minutes of the Bid opening, including the information disclosed to those present in accordance with Sub-Clause 23.3.

24. Process to Be Confidential

24.1 Information relating to the examination, clarification, evaluation, and comparison of Bids and recommendations for the award of a contract shall not be disclosed to Bidders or any other persons not officially concerned with such process until the award to the successful Bidder has been announced. Any effort by a Bidder to influence the Employer's processing of Bids or award decisions may result in the rejection of his Bid.

25. Clarification of Bids

25.1 To assist in the examination, evaluation, and comparison of Bids, the Employer may, at his discretion, ask any Bidder for clarification of his Bid, including breakdowns of the unit rates. The request for clarification and the response shall be in writing or by cable, but no change in the price or substance of the Bid shall be sought, offered, or permitted except as required to confirm the correction of arithmetic errors discovered by the Employer in the evaluation of the Bids in accordance with Clause 27.

25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to its bid from the time of the bid opening to the time the contract is awarded. If the Bidder wishes to bring additional information to the notice of the Employer, it should do so in writing.

25.3 Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid comparison or contract award decisions may result in the rejection of the Bidders’ bid.

26. Examination of Bids and Determination of Responsiveness

26.1 Prior to the detailed evaluation of Bids, the Employer will determine whether each Bid (a) meets the eligibility criteria defined in Clause 3; (b) has been properly signed; (c) is accompanied by the required securities and; (d) is substantially responsive to the requirements of the Bidding documents.

26.2 A substantially responsive Bid is one which conforms to all the terms, conditions, and specifications of the Bidding documents, without material deviation or reservation. A material deviation or reservation is one (a) which affects in any substantial way the scope, quality, or performance of the Works; (b) which limits in any substantial way, inconsistent with the Bidding documents, the Employer's rights or the Bidder's

Works 3: Remediation works of NMK-KIE Page 29

obligations under the Contract; or (c) whose rectification would affect unfairly the competitive position of other Bidders presenting substantially responsive Bids.

26.3 If a Bid is not substantially responsive, it will be rejected by the Employer, and may not subsequently be made responsive by correction or withdrawal of the non-conforming deviation or reservation.

27. Correction of Errors

27.1 Bids determined to be substantially responsive will be checked by the Employer for any arithmetic errors. Errors will be corrected by the Employer as follows:

(a) where there is a discrepancy between the rates in figures and in words, the rate in words will govern; and

(b) where there is a discrepancy between the unit and the line item total resulting from multiplying the unit rate by the quantity, the unit rate as quoted will govern.

27.2 The amount stated in the Bid will be adjusted by the Employer in accordance with the above procedure for the correction of errors and, with the concurrence of the Bidder, shall be considered as binding upon the Bidder. If the Bidder does not accept the corrected amount the Bid will be rejected, and the Bid security may be forfeited in accordance with Sub-Clause 16.6 (b).

28. Deleted

29. Evaluation and Comparison of Bids

29.1 The Employer will evaluate and compare only the Bids determined to be substantially responsive in accordance with Clause 26.

29.2 In evaluating the Bids, the Employer will determine for each Bid the evaluated Bid Price by adjusting the Bid Price as follows:

(a) making any correction for errors pursuant to Clause 27; or

(b) making an appropriate adjustments for any other acceptable variations, deviations; and

(c) making appropriate adjustments to reflect discounts or other price modifications offered in accordance with Sub Clause 22.5.

29.3 The Employer reserves the right to accept or reject any variation, deviation, or alternative offer. Variations, deviations, and alternative offers and other factors which are in excess of the requirements of the Bidding documents or otherwise result in unsolicited benefits for the Employer shall not be taken into account in Bid evaluation.

Works 3: Remediation works of NMK-KIE Page 30

29.4 The estimated effect of the price adjustment conditions under Clause 47 of the Conditions of Contract, during the period of implementation of the Contract, will not be taken into account in Bid evaluation.

29.5 If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer's estimate of the cost of work to be performed under the contract, the Employer may require the Bidder to produce detailed price analyses for any or all items of the Bill of Quantities, to demonstrate the internal consistency of those prices with the construction methods and schedule proposed. After evaluation of the price analyses, the Employer may require that the amount of the performance security set forth in Clause 34 be increased at the expense of the successful Bidder to a level sufficient to protect the Employer against financial loss in the event of default of the successful Bidder under the Contract.

30. Deleted

F. Award of Contract

31. Award Criteria

31.1 Subject to Clause 32, the Employer will award the Contract to the Bidder whose Bid has been determined to be substantially responsive to the Bidding documents and who has offered the lowest evaluated Bid Price, provided that such Bidder has been determined to be (a) eligible in accordance with the provisions of Clause 3, and (b) qualified in accordance with the provisions of Clause 4.

31.2 If, pursuant to Clause 12.2 this contract is being let alongwith other contracts, the lowest evaluated Bid Price will be determined when evaluating this contract in conjunction with other contracts to be awarded concurrently, taking into account any discounts offered by the bidders for the award of more than one contract.

32. Employer's Right to Accept any Bid and to Reject any or all Bids

32.1 Notwithstanding Clause 31, the Employer reserves the right to accept or reject any Bid, and to cancel the Bidding process and reject all Bids, at any time prior to the award of Contract, without thereby incurring any liability to the affected Bidder or Bidders or any obligation to inform the affected Bidder or Bidders of the grounds for the Employer's action.

33. Notification of Award and Signing of Agreement

33.1 The Bidder whose Bid has been accepted will be notified of the award by the Employer prior to expiration of the Bid validity period by cable, telex or facsimile confirmed by registered letter. This letter (hereinafter and in the Conditions of Contract called the "Letter of Acceptance") will state the sum that the Employer will pay the Contractor in consideration of the execution, completion, and maintenance of the Works by the Contractor as prescribed by the Contract (hereinafter and in the Contract called the "Contract Price").

Works 3: Remediation works of NMK-KIE Page 31

33.2 The notification of award will constitute the formation of the Contract, subject only to the furnishing of a performance security in accordance with the provisions of Clause 34.

33.3 The Agreement will incorporate all agreements between the Employer and the successful Bidder. It will be signed by the Employer and kept ready for signature of the successful bidder in the office of employer within 28 days following the notification of award along with the Letter of Acceptance. Within 21 days of receipt, the successful Bidder will sign the Agreement and deliver it to the Employer.

33.4 Upon the furnishing by the successful Bidder of the Performance Security, the Employer will promptly notify the other Bidders that their Bids have been unsuccessful.

34. Performance Security

34.1 Within 21 days of receipt of the Letter of Acceptance, the successful Bidder shall deliver to the Employer a Performance Security in any of the forms given below for an amount equivalent to 5% of the Contract price plus additional security for unbalanced Bids in accordance with Clause 29.5 of ITB and Clause 52 of Conditions of Contract:

- A bank guarantee issued by a nationalized / scheduled bank located in India or a reputable bank located abroad having corresponding bank in India, in the form given in Section 8; or

- Certified cheque, Bank draft or Letter of Credit in favour of Member Secretary, Telangana State Pollution Control Board, Hyderabad payable at Hyderabad

34.2 If the performance security is provided by the successful Bidder in the form of a Bank Guarantee, it shall be issued either (a) at the Bidder's option, by a Nationalized/Scheduled Indian bank or (b) by a foreign bank located in India and acceptable to the Employer or (c) by a foreign bank through a correspondent Bank in India [scheduled or nationalized]. The performance security of a joint venture shall be in the name of the joint venture.

34.3 Failure of the successful bidder to comply with the requirements of sub-clause 34.1 shall constitute a breach of contract, cause for annulment of the award, forfeiture of the bid security, and any such other remedy the Employer may take under the contract, and the Employer may resort to awarding the contract to the next ranked bidder.

35 Advance Payment and Security

35.1 The Employer will provide an Advance Payment on the Contract Price as stipulated in the Conditions of Contract, subject to maximum amount, as stated in the Contract Data.

36. Adjudicator

36.1 The Employer proposes that Sri. A Gautham, SE, PHE be appointed as Adjudicator under the Contract, at a daily fee of Rs 5000/- plus reimbursable expenses. If the Bidder disagrees

Works 3: Remediation works of NMK-KIE Page 32

with this proposal, the Bidder should so state in the Bid. If in the Letter of Acceptance, the Employer has not agreed on the appointment of the Adjudicator, the Adjudicator shall be appointed by Chairman, Institute of Engineers, Hyderabad at the request of either party.

37. Fraud and Corruption: 37.1 It is the Bank’s policy to require that Borrowers (including beneficiaries of Bank loans), as

well as bidders, suppliers, and contractors and their subcontractors under Bank-financed contracts, observe the highest standard of ethics during the procurement and execution of such contracts. 1 In pursuance of this policy, the Bank:

(a) defines, for the purposes of this provision, the terms set forth below as follows:

(i) “corrupt practice”2 is the offering, giving, receiving or soliciting, directly or indirectly, of anything of value to influence improperly the actions of another party;

(ii) “fraudulent practice”3 is any act or omission, including a

misrepresentation, that knowingly or recklessly misleads, or attempts to mislead, a party to obtain a financial or other benefit or to avoid an obligation;

(iii) “collusive practice”4 is an arrangement between two or more parties

designed to achieve an improper purpose, including to influence improperly the actions of another party;

(iv) “coercive practice”5 is impairing or harming, or threatening to impair or harm,

directly or indirectly, any party or the property of the party to influence improperly the actions of a party;

(v) “obstructive practice” is

1 In this context, any action taken by a bidder, supplier, contractor, or a sub-contractor to influence the procurement process or

contract execution for undue advantage is. 2 “another party” refers to a public official acting in relation to the procurement process or contract execution]. In this context,

“public official” includes World Bank staff and employees of other organizations taking or reviewing procurement decisions. 3 a “party” refers to a public official; the terms “benefit” and “obligation” relate to the procurement process or contract execution;

and the “act or omission” is intended to influence the procurement process or contract execution. 4 “parties” refers to participants in the procurement process (including public officials) attempting to establish bid prices at

artificial, non competitive levels. 5 a “party” refers to a participant in the procurement process or contract execution.

Works 3: Remediation works of NMK-KIE Page 33

(aa) deliberately destroying, falsifying, altering or concealing of evidence material to the investigation or making false statements to investigators in order to materially impede a Bank investigation into allegations of a corrupt, fraudulent, coercive or collusive practice; and/or threatening, harassing or intimidating any party to prevent it from disclosing its knowledge of matters relevant to the investigation or from pursuing the investigation, or

(bb) acts intended to materially impede the exercise of the Bank’s inspection and audit rights provided for under sub-clause 37.1(e) below.

(b) will reject a proposal for award if it determines that the Bidder recommended for award has, directly or through an agent, engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in competing for the contract in question;

(c) will cancel the portion of the loan allocated to a contract if it determines at any

time that representatives of the Borrower or of a beneficiary of the loan engaged in corrupt, fraudulent, collusive, or coercive practices during the procurement or the execution of that contract, without the Borrower having taken timely and appropriate action satisfactory to the Bank to remedy the situation;

(d) will sanction a firm or individual, including declaring them ineligible, either

indefinitely or for a stated period of time, to be awarded a Bank-financed contract if it at any time determines that they have, directly or through an agent, engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in competing for, or in executing, a Bank-financed contract; and

(e) will have the right to require that a provision be included in bidding documents

and in contracts financed by a Bank Loan, requiring bidders, suppliers, contractors and consultants to permit the Bank to inspect their accounts and records and other documents relating to the Bid submission and contract performance and to have them audited by auditors appointed by the Bank.

37.2 Furthermore, bidders shall be aware of the provision stated in Sub-Clause 23.2 and

Clause 64 of the Conditions of Contract.

Works 3: Remediation works of NMK-KIE Page 34

Section 2: FORMS OF BID, QUALIFICATION INFORMATION AND LETTER OF ACCEPTANCE

Works 3: Remediation works of NMK-KIE Page 35

Section 2: FORMS OF BID, QUALIFICATION INFORMATION AND LETTER OF ACCEPTANCE

Table of Forms:

- CONTRACTOR’S BID

- QUALIFICATION INFORMATION

- LETTER OF ACCEPTANCE

- NOTICE TO PROCEED WITH THE WORK

- AGREEMENT FORM

- JOINT VENTURE AGREEMENT

Works 3: Remediation works of NMK-KIE Page 36

Contractor's Bid

Description of the Works: Remediation of Noor Mohammed Kunta, Kattedan Industrial Area (KIE) in

Rangareddy District, Telangana

BID

To : The Project Director / Member Secretary, T.S. Pollution Control Board

Address : Sanathnagar, Hyderabad

GENTLEMEN,

Having examined the bidding documents including addendum, we offer to execute the Works described above in accordance with the Conditions of Contract, Specifications, Drawings and Bill of Quantities accompanying this Bid for the Contract Price of _________ [in figures] (__________________________________________________) [in letters].6

The advance Payment required is: Rupees ________________.

We accept the appointment of ________________________ as the Adjudicator.

(OR)

We do not accept the appointment of ___________________ as the Adjudicator and propose instead that _______________________ be appointed as Adjudicator whose daily fees and biographical data are attached.

This Bid and your written acceptance of it shall constitute a binding contract between us. We understand that you are not bound to accept the lowest or any Bid you receive.

We hereby certify that we have taken steps to ensure that no person acting for us or on our behalf will engage in bribery.

We also undertake that, in competing for (and, if the award is made to us, in executing) the above contract, we will strictly observe the laws against fraud and corruption in force in India namely “Prevention of Corruption Act 1988”.

1 To be filled in by the Bidder, together with his particulars and date of submission at the bottom of the Form of Bid.

Works 3: Remediation works of NMK-KIE Page 37

Commissions or gratuities, if any, paid or to be paid by us to agents relating to this Bid, and to contract execution if we are awarded the contract, are listed below :

Name and address of agent Amount Purpose of Commission or gratuity

______________________ ________ ____________________________

______________________ ________ ____________________________

______________________ ________ ____________________________

(if none, state “none”)

We hereby confirm that this Bid complies with the Eligibility, Bid Validity and Bid Security required by the Bidding documents.

Yours faithfully,

Authorized Signature:

Name & Title of Signatory: _________________________________________________________________

Name of Bidder : ______________________________________________

Address : _______________________

Qualification Information

The information to be filled in by the Bidder in the following pages will be used for purposes of post qualification as provided for in Clause 4 of the Instructions to Bidders. This information will not be incorporated in the Contract.

1. For Individual Bidders

1.1 Constitution or legal status of Bidder

[Attach copy]

Place of registration: _______________________________

Principal place of business: _______________________________

Works 3: Remediation works of NMK-KIE Page 38

Power of attorney of signatory of Bid

[Attach]

1.2 Total value of Civil Engineering construction works related to environmental dredging, dewatering and construction of containment cells

2010-2011 2011-2012 2012-2013 2013-2014 2014 - 2015

1.3 Information on Work performed

1.3.1 Work performed as prime contractor (in the same name) on works of a similar nature over the last five years. 2010-2015**

______________________________________________________________________________

Project Name

Name

of the Employer*

Descrip-tion of work

Contract No.

Value of contract (Rs.

Million)

Date of issue of work order

Stipulated period of completion

Actual date of completion*

Remarks explaining reasons for delay and work completed

______________________________________________________________________________

______________________________________________________________________________

1.3.2 Quantities of work executed as prime contractor (in the same name and style) in the last five years: **

Year Name of the Work

Name of the Employer*

Quantity of work performed (cum) @ Remarks *

Environmental Dredging/ Application of cover layers under water/ Excavation, backfilling and levelling

Dewatering

Construction of containment cell/ HDPE Lining Works

(indicate contract Ref)

2010-2011

2011-2012

2012-2013

2013-2014

Works 3: Remediation works of NMK-KIE Page 39

2014-2015

Contractor should exhibit his quantities of works executed in relation to the Environmental Dredging, Dewatering and Containment Cell Construction Works related to:

Excavation, backfilling and levelling of soil and sand.

HDPE Lining Works

Environmental dredging

Dewatering of sediments

Application of 0.10 m thick layer of sand with aim to cover underwater bottom of fresh water bodies or sallow seas

*Attach certificate(s) from the Engineer(s)-in-Charge

@The item of work for which data is requested should tally with that specified in ITB clause 4.5A(c).

**Iimmediately preceding the financial year in which bids are received.

Attach certificate from Chartered Accountant.

1.4 Information on Bid Capacity (works for which bids have been submitted and works which are yet to be completed) as on the date of this bid.

(A) Existing commitments and on-going works:

Descriptio

n of Work

Place &

State

Contract

No. &

Date

Name &

Address of

Employer

Value of

Contract

(Rs.

Million)

Stipulated

period of

Completion

Value of Works*

remaining to be

completed (Rs.

Million)

Anticipate

d Date of

Completio

n

(1) (2) (3) (4) (5) (6) (7) (8)

(B) Works for which bids already submitted:

Description

of Work

Place &

State

Name &

Address of

Employer

Estimated

value of

Works (Rs.

million)

Stipulated

period of

Completion

Date when

decision is

expected

Remarks if

any

(1) (2) (3) (4) (5) (7) (8)

Works 3: Remediation works of NMK-KIE Page 40

* Attach certificate(s) from the Engineer(s)-in-Charge.

1.5 The following items of Contractor's Equipment are essential for carrying out the Works. The Bidder should list all the information requested below. Refer also to Sub Clause 4.3 (d) of the Instructions to Bidders.

Item of

Equipment

Requirement

Availability proposals

Remarks (From

whom to be

purchased)

No. Capacity Owned/

leased/to be

procured

Nos./

Capacity

Age/

Conditio

n

1.6 Qualifications and experience of key personnel proposed for administration and execution of the Contract. Attach biographical data. Refer also to Sub Clause 4.3 (e) and 4.5 (B) (b) of instructions to Bidders and Sub Clause 9.1 of the Conditions of Contract.

Position Name

Qualifications

Years of

experience

(general)

Years of

experience in

the proposed

position

Project Manager

*

*

*

etc.

*

*

*

*

*

*

*

*

*

*

*

*

*

*

*

*

1.7 Proposed subcontracts and firms involved. [Refer ITB Clause 4.3 (j)]

Sections of the Works Value of Sub-

Contract

Sub-contractor (Name &

Address)

Experience in

similar Work

Works 3: Remediation works of NMK-KIE Page 41

*

*

*

*

*

*

*

*

*

*

*

*

*

*

*

*

1.8 Financial reports for the last five years: balance sheets, profit and loss statements, auditors' reports (in case of companies/corporation), etc. List them below and attach copies.

1.9 Evidence of access to financial resources to meet the qualification requirements: cash in hand, lines of credit, etc. List them below and attach copies of support documents [sample format attached].

1.10. Name, address, and telephone, telex, and fax numbers of the Bidders' bankers who may provide references if contacted by the Employer.

1.11 Information on litigation history in which the Bidder is involved. Other Party(ies) Employer

Cause of Dispute

Amount

involved

Remarks showing

present status

1.12 Statement of compliance under the requirements of Sub Clause 3.2 of the instructions to Bidders.

______________________________________________________________________________

______________________________________________________________________________

______________________________________________________________________________

1.13 Proposed work method and schedule. The Bidder should attach descriptions, drawings and charts as necessary to comply with the requirements of the Bidding documents. [Refer ITB Clause 4.1 and 4.3 (k)].

2. Joint Ventures

2.1 The information listed in 1.1-1.12 above shall be provided for each partner of the joint venture.

2.2 The information in 1.13 above shall be provided for the joint venture.

Works 3: Remediation works of NMK-KIE Page 42

2.3 Attach the power of attorney of the signatory[ies] of the bid authorizing signature of the bid on behalf of the joint venture.

2.4 Attach the agreement among all partners of the joint venture [and which is legally binding on all partners], which shows the requirements as indicated in sub-clause 4.4 of the Instructions to Bidders’. Alternatively, a Letter of Intent to execute a Joint Venture Agreement in the event of a successful bid shall be signed by all partners and submitted with the bid, together with a copy of the proposed Agreement

2.5 Furnish details of participation proposed in the joint venture as below:

DETAILS OF PARTICIPATION IN THE JOINT VENTURE

PARTICIPATION DETAILS FIRM ‘A’ (Lead Partner)

FIRM ‘B’ FIRM ‘C’

Financial

Name of the Banker(s)

Works 3: Remediation works of NMK-KIE Page 43

PARTICIPATION DETAILS FIRM ‘A’ (Lead Partner)

FIRM ‘B’ FIRM ‘C’

Planning

Construction Equipment

Key Personnel

Execution of Work

(Give details on contribution of each)

Works 3: Remediation works of NMK-KIE Page 44

PARTICIPATION DETAILS FIRM ‘A’ (Lead Partner)

FIRM ‘B’ FIRM ‘C’

3. Additional Requirements

3.1 Bidders should provide any additional information required to fulfil the requirements of Clause 4 of the Instructions to the Bidders, if applicable.

____________________________________________________________________________________________

Works 3: Remediation works of NMK-KIE Page 45

SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR AVAILABILITY OF CREDIT FACILITIES –* CLAUSE 4.5 [B] [c] OF ITB

BANK CERTIFICATE

This is to certify that M/s. …………………………… is a reputed company with a good financial standing.

If the contract for the work, namely …………………………………………………………. [funded by the World Bank] is awarded to the above firm, we shall be able to provide overdraft/credit facilities to the extent of Rs. …………… to meet their working capital requirements for executing the above contract.

__ Sd. __

Name of Bank

Senior Bank Manager

Address of the Bank

______________________________________________________________________________

* Change the text as follows for Joint venture:

This is to certify that M/s. ……………………………… who has formed a JV with M/s. …………………………… and M/s. …………………………………………. for participating in this bid, is a reputed company with a good financial standing.

If the contract for the work, namely …………………………………………………………. [funded by the World Bank] is awarded to the above Joint Venture, we shall be able to provide overdraft/credit facilities to the extent of Rs. …………… to M/s. …………………….. to meet the working capital requirements for executing the above contract.

[This should be given by the JV members in proportion to their financial participation.]

Works 3: Remediation works of NMK-KIE Page 46

Form ……….

(Name of the Project)

(Declaration regarding customs/excise duty exemption for materials/

construction equipment bought for the work)

(Bidder’s Name and Address)

To: ………………………

(Name of the Employer)

Dear Sir:

Re: [Name of Work] ………………………… -

Certificate for Import/Procurement of Goods/Construction Equipment

1. We confirm that we are solely responsible for obtaining customs/excise duty waivers which we have considered in our bid and in case of failure to receive such waivers for reasons whatsoever, the Employer will not compensate us.

2. We are furnishing below the information required by the Employer for issue of the necessary certificates in terms of the Government of India Central Excise Notification No. 108/95 and Customs Notification No. 85/99.

3. The goods/construction equipment for which certificates are required are as under:

Items Make/ Brand Name

Capacity [where applicable]

Quantity Value State whether it will be procured locally or imported [if so from which country]

Remarks regarding justification for the quantity and their usage in works

Goods

[a] Bitumen

[b] Others

Construction Equipment

[a]

[b]

[c]

Works 3: Remediation works of NMK-KIE Page 47

[d]

4. We agree that no modification to the above list is permitted after bids are opened.

5. We agree that the certificate will be issued only to the extent considered reasonable by the Employer for the work, based on the Bill of Quantities and the construction programme and methodology as furnished by us along with the bid.

6. We confirm that the above goods will be exclusively used for the construction of the above work and construction equipment will not be sold or otherwise disposed of in any manner for a period of five years from the date of acquisition.

Date: ___________________ (Signature) ____________________

Place: __________________ (Printed Name) _________________

(Designation) __________________

(Common Seal) ________________

This certificate will be issued within 60 days of signing of contract and no subsequent changes will be permitted.

Works 3: Remediation works of NMK-KIE Page 48

Letter of Acceptance

(Letterhead paper of the Employer)

________________________[date]

To: _______________________________________________________________________ [name and address of the Contractor]

Dear Sirs,

This is to notify you that your Bid dated ____________ for execution of the ________________________

___________________________________________________________ [name of the contract and identification number, as given in the Instructions to Bidders] for the Contract Price of Rupees ——————————— ____________________________________ (_____________) [amount in words and figures], as corrected and modified in accordance with the Instructions to Bidders1 is hereby accepted by our Agency.

We accept/do not accept that __________________________ be appointed as the Adjudicator2.

We note that as per bid, you do not intend to subcontract any component of work.

[OR]

We note that as per bid, you propose to employ M/s. .......................................... as sub-contractor for executing ….........................................

[Delete whichever is not applicable]

You are hereby requested to furnish Performance Security, plus additional security for unbalanced bids in terms of ITB clause 29.5, in the form detailed in Para 34.1 of ITB for an amount of Rs.————— within 21 days of the receipt of this letter of acceptance valid up to 28 days from the date of expiry of Defects Liability Period i.e. up to........... and sign the contract, failing which action as stated in Para 34.3 of ITB will be taken.

We have reviewed the construction methodology submitted by you along with the bid in response to ITB Clause 4.3[k] and our comments are given in the attachment. You are requested to submit a revised Program including environmental management plan as per Clause 27 of General Conditions of Contract within 14 days of receipt of this letter.

Yours faithfully,

Works 3: Remediation works of NMK-KIE Page 49

Authorized Signature

Name and Title of Signatory

Name of Agency

1 Delete "corrected and" or "and modified" if only one of these actions applies. Delete "as corrected and modified in accordance with the Instructions to Bidders" if corrections or modifications have not been effected.

2 To be used only if the Contractor disagrees in his Bid with the Adjudicator proposed by the Employer in the "Instructions to Bidders."

Works 3: Remediation works of NMK-KIE Page 50

Issue of Notice to proceed with the work

(Letterhead of the Employer)

————— (date)

To

—————————————— (name and address of the Contractor)

——————————————

——————————————

Dear Sirs:

Pursuant to your furnishing the requisite security as stipulated in ITB clause 34.1 and signing of the contract agreement for the construction of —————— @ a Bid Price of Rs.——————, you are hereby instructed to proceed with the execution of the said works in accordance with the contract documents.

Yours faithfully,

(Signature, name and title of signatory authorized to sign on behalf of Employer)

Works 3: Remediation works of NMK-KIE Page 51

Agreement Form

Agreement

This agreement, made the ___________________ day of ______________19_______, between__________________________________________________________________________________________________________________________[name and address of Employer]

(Hereinafter called “the Employer)” of the one part and ______________________________________________ ________________________________________________________________________________________________________________________________________________[name and address of contractor] (hereinafter called “the Contractor” ) of the other part.

Whereas the Employer is desirous that the Contractor execute _____________________________ ________________________________________________________________________________________________________________________________________________________________________________[ name and identification number of Contract] (hereinafter called “the Works”) and the Employer has accepted the Bid by the Contractor for the execution and completion of such Works and the remedying of any defects therein, at a contract price of Rs.................................................................................

NOW THIS AGREEMENT WITNESSETH as follows:

1. In this Agreement, words and expression shall have the same meanings as are respectively assigned to them in the Conditions of Contract hereinafter referred to, and they shall be deemed to form and be read and construed as part of this Agreement.

2. In consideration of the payments to be made by the Employer to the Contractor as hereinafter mentioned, the Contractor hereby covenants with the Employer to execute and complete the Works and remedy any defects therein in conformity in all aspects with the provisions of the Contract.

3. The Employer hereby covenants to pay the Contractor in consideration of the execution and completion of the Works and the remedying the defects wherein the Contract Price or such other sum as may become payable under the provisions of the Contract at the times and in the manner prescribed by the Contract.

Works 3: Remediation works of NMK-KIE Page 52

4. The following documents shall be deemed to form and be read and construed as part of this Agreement, viz.:

i) Letter of Acceptance;

ii) Notice to proceed with the works;

iii) Contractor’s Bid;

iv) Contract Data;

v) Conditions of contract (including Special Conditions of Contract);

vi) Specifications;

vii) Drawings;

viii) Bill of Quantities; and

ix) Any other document listed in the Contract Data as forming part of the contract;

x) Joint Venture Agreement

In witness whereof the parties thereto have caused this Agreement to be executed the day and year first before written.

The Common Seal of ____________________________________________________________

was hereunto affixed in the presence of:

Signed, Sealed and Delivered by the said _________________________________________________

________________________________________________________________________________

_______________________________________________________________________________

In the presence of:

Binding Signature of Employer _________________________________________________

Binding Signature of Contractor _____________________________________________________

Works 3: Remediation works of NMK-KIE Page 53

JOINT VENTURE AGREEMENT

PERFORMA FOR JOINT VENTURE AGREEMENT/CONSORTIUM BETWEEN M/s. …………… and M/s………… and M/s………………………….

For NCB No……………………………………Invitation for Bid No………………….of TSPCB, Telangana under CBPIMP project.

The Joint Venture Agreement executed on this day of ………………………………………..between M/s…………………………………………, a company under the Laws of Company Act, 1956 and having its registered office at ……………..…………………, ……………………………………………………………... and Corporate Office at ………………………………………………. (herein after called the LEAD PARTNER, which expression shall include its successors, Executers and permitted Assigns)

AND M/s……………………………………………….. a company having its registered office at ………………………………………………………………(herein after called as PARTNER, which expression shall include its successors, Executors and permitted Assigns)

AND M/s……………………………………. a company having its registered office at ………………………………………………………………(herein after called as PARTNER, which expression shall include its successors, Executors and permitted Assigns) for the purpose of making a Bid and entering into a contract (in case of award) for “Civil Works for…………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………” NCB No…………………………………………………………..of TSPCB, Telangana (herein after called as the EMPLOYER).

WHEREAS, the EMPLOYER invited Bids as per above mentioned tender Document for the “…………………………………………………..”

WHEREAS in accordance with Instruction to Bidders of the Tender Specification. A Bidder may be a private entity or a government-owned entity or any combination of such entities with the intent to enter into an agreement supported by a letter of intent or under an agreement in the form of a Joint Venture or consortium.

NOW THIS INDENTURE WITNESSETH AS UNDER

In consideration of the above premises and agreements all the partners to this Joint Venture do hereby now agree as follows:

Works 3: Remediation works of NMK-KIE Page 54

1. In consideration of the award of the Contract by the Employer to the Joint Venture / Consortium partners, we, the Partners to the Joint Venture Agreement do hereby agree that M/s. ……………………………….. Shall act as LEAD PARTNER and further declare and confirm that we shall jointly be bound unto the Employer for the successful performance of the Contract and shall be fully responsible for the works in terms of quality requirements and timeliness in performance in accordance with the Contract. Irrespective of Joint responsibility, it is expressly understood that LEAD PARTNER will be present at the site of the works, through its authorized representative at all times and play lead role in mobilizing resources and execution of the contract. The LEAD PARTNER will incur liabilities and receive instructions for and on behalf of any or all partners of the Joint Venture and entire execution of the contract shall be done by the LEAD PARTNER and will be the sole responsibility of the lead partner of the consortium and payment under the contract shall be received by the LEAD PARTNER. The precise responsibility of the members of the Joint Venture in respect of planning, quality, execution of the works are as under : LEAD PARTNER : PARTNER – A : PARTNER – B : If in the determination of the Employer that the LEAD PARTNER is unable to fulfill its responsibility as above, the Employer shall be at liberty to terminate the contract which shall be binding on all partners of the Joint Venture.

2. In case of any breach of the said Contract by the LEAD PARTNER or other Partners of the Joint Venture Agreement, the Partner(s) do hereby agree to be fully responsible for the successful performance of the Contract and to carry out all the obligations and responsibilities under the Contract in accordance with the requirements of the Contract.

3. Further, if the Employer suffers any loss or damage on account of any breach in the Contract or any shortfall in meeting the performance guaranteed as per the works Contract, the Partner(s) of these presents undertake to promptly make good such loss or damages caused to the Employer, on its demands without any demur. It shall not be necessary or obligatory for the Employer to proceed against LEAD PARTNER to these presents before proceeding against or dealing with other Partner(s).

4. The financial liability of the Partners of this Joint Venture agreement to the Employer, with respect to any of the claims arising out of the performance or non-performance of the obligations set forth in the said Joint Venture Agreement, read in conjunction with the relevant conditions of the Contract shall, however, not be limited in any way so as to restrict or limit the liabilities of any of the Partners of the Joint Venture agreement.

5. It is expressly understood and agreed between the Partners to this Joint Venture agreement that the responsibilities and obligations of each of the Partners has been

Works 3: Remediation works of NMK-KIE Page 55

delineated in clause no. 1 herein above to this agreement. It is further agreed by the Partners that the above sharing of responsibilities and obligations shall not in any way be a limitation of joint responsibilities of the Partners under this Contract.

6. This Joint Venture Agreement shall be construed and interpreted in accordance with the laws of India, courts of ………………….., Telangana shall have the exclusive jurisdiction in all matters arising there under.

7. It is further agreed that the Joint Venture agreement shall be irrevocable and shall form an integral part of the contract, and shall continue to be enforceable till the Employer discharges the same. It shall be effective from the date first mentioned above for all purposes and intents. IN WITNESS WHEREOF, the Partners to the Joint Venture Agreement have through their Authorized Representatives executed these presents and affixed Common Seals of their companies, on the day, month and year first mentioned above. [Name, Signature of all Joint Venture Partners] [Name and Signature of Witnesses]

Works 3: Remediation works of NMK-KIE Page 56

SECTION 3:CONDITION OF CONTRACT

Works 3: Remediation works of NMK-KIE Page 57

Conditions of Contract

Table of Contents

No Title Page No Title Page

A. General 3 D. Cost Control 11

1 Definitions 3 37 Bill of Quantities 11

2 Interpretation 4 38 Changes in the Quantities 11

3 Language and Law 5 39 Variations 12

4 Engineer's Decisions 5 40 Payments for Variations 11

5 Delegation 5 41 Cash Flow Forecasts 12

6 Communications 5 42 Payment Certificates 12

7 Subcontracting 5 43 Payments 13

8 Other Contractors 6 44 Compensation Events 13

9 Personnel 6 45 Tax 14

10 Employer’s & contractor's Risks 6 46 Currencies 14

11 Employer's Risks 6 47 Price Adjustments 14

12 Contractor’s Risks 6 48 Retention 15

13 Insurance 6 49 Liquidated Damages 15

14 Site Investigation Reports 7 50 Bonus (deleted) 15

15 Queries about the Contract Data 7 51 Advance Payment 15

16 Contractor to Construct the Works 7 52 Securities 16

17 The Works to Be Completed by the Intended Completion Date

7 53 Dayworks (deleted) 16

18 Approval by the Engineer 7 54 Cost of Repairs 16

19 Safety 8 E. Finishing the Contract 16

20 Discoveries 8 55 Completion 16

21 Possession of the Site 8 56 Taking Over 16

Works 3: Remediation works of NMK-KIE Page 58

22 Access to the Site 8 57 Final Account 16

23 Instructions 8 58 Operating and Maintenance Manuals 17

24 Disputes 8 59 Termination 17

25 Procedure for Disputes 9 60 60. Payment upon Termination 46 18

26 Replacement of Adjudicator 9 61 Property 18

B. Time Control 9 62 Release from Performance 18

27 Program 9 63 Suspension of World Bank Loan or Credit 18

28 Extension of the Intended Completion Date

10 64 Corrupt or Fraudulent Practice 19

29 Acceleration (deleted) 10 F Special Conditions of Contract 20

30 Delays Ordered by the Engineer 10 1 LABOUR 20

31 Management meetings 10 2 COMPLIANCE WITH LABOUR REGULATIONS 20

32 Early Warning 10 3 SUB-CONTRACTING (GCC Clause 7) 22

C. Quality Control 4 ARBITRATION (GCC Clause 25.3) 23

33 Identifying Defects 10 5 PROTECTION OF ENVIRONMENT 24

34 Tests 11 6 LIQUIDATED DAMAGES 25

35 Correction of Defects 11

Works 3: Remediation works of NMK-KIE Page 59

Conditions of Contract

A. General

1. Definitions

1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of Contract but keep their defined meanings. Capital initials are used to identify defined terms.

The Adjudicator is the person appointed jointly by the Employer and the Contractor to resolve disputes in the first instance, as provided for in Clauses 24 and 25. The name of the Adjudicator is defined in the Contract Data.

Bill of Quantities means the priced and completed Bill of Quantities forming part of the Bid.

Borrower means the Government of India

Compensation Events are those defined in Clause 44 hereunder.

The Completion Date is the date of completion of the Works as certified by the Engineer in accordance with Sub Clause 55.1.

The Contract is the contract between the Employer and the Contractor to execute, complete and maintain the Works. It consists of the documents listed in Clause 2.3 below.

The Contract Data defines the documents and other information which comprise the Contract.

The Contractor is a person or corporate body whose Bid to carry out the Works has been accepted by the Employer.

The Contractor's Bid is the completed Bidding document submitted by the Contractor to the Employer.

The Contract Price is the price stated in the Letter of Acceptance and thereafter as adjusted in accordance with the provisions of the Contract.

Days are calendar days; months are calendar months.

Works 3: Remediation works of NMK-KIE Page 60

A Defect is any part of the Works not completed in accordance with the Contract.

The Defects Liability Period is the period named in the Contract Data and calculated from the Completion Date.

The Employer is the party who will employ the Contractor to carry out the Works.

The Engineer is the person named in the Contract Data (or any other competent person appointed and notified to the contractor to act in replacement of the Engineer) who is responsible for supervising the execution of the works and administering the Contract.

Equipment is the Contractor's machinery and vehicles brought temporarily to the Site to construct the Works.

The Initial Contract Price is the Contract Price listed in the Employer's Letter of Acceptance.

The Intended Completion Date is the date on which it is intended that the Contractor shall complete the Works. The Intended Completion Date is specified in the Contract Data. The Intended Completion Date may be revised only by the Engineer by issuing an extension of time.

Materials are all supplies, including consumables, used by the contractor for incorporation in the Works.

Plant is any integral part of the Works which is to have a mechanical, electrical, electronic or chemical or biological function.

The Site is the area defined as such in the Contract Data.

Site Investigation Reports are those which were included in the Bidding documents and are factual interpretative reports about the surface and sub-surface conditions at the site.

Specification means the Specification of the Works included in the Contract and any modification or addition made or approved by the Engineer.

The Start Date is given in the Contract Data. It is the date when the Contractor shall commence execution of the works. It does not necessarily coincide with any of the Site Possession Dates.

A Subcontractor is a person or corporate body who has a Contract with the Contractor to carry out a part of the work in the Contract which includes work on the Site.

Works 3: Remediation works of NMK-KIE Page 61

Temporary Works are works designed, constructed, installed, and removed by the Contractor which are needed for construction or installation of the Works.

A Variation is an instruction given by the Engineer which varies the Works.

The Works are what the Contract requires the Contractor to construct, install, and turn over to the Employer, as defined in the Contract Data.

The World Bank means "International Bank for Reconstruction and Development (IBRD)” and International Development Association (IDA)".

2. Interpretation

2.1 In interpreting these Conditions of Contract, singular also means plural, male also means female or neuter, and the other way around. Headings have no significance. Words have their normal meaning under the language of the Contract unless specifically defined. The Engineer will provide instructions clarifying queries about the Conditions of Contract.

2.2 If sectional completion is specified in the Contract Data, references in the Conditions of Contract to the Works, the Completion Date, and the Intended Completion Date apply to any Section of the Works (other than references to the Completion Date and Intended Completion date for the whole of the Works).

2.3 The documents forming the Contract shall be interpreted in the following order of priority:

(1) Agreement

(2) Letter of Acceptance, notice to proceed with the works

(3) Contractor’s Bid

(4) Contract Data

(5) Conditions of Contract including Special Conditions of Contract

(6) Specifications

(7) Drawings

(8) Bill of Quantities and

(9) any other document listed in the Contract Data as forming part of the Contract.

3. Language and Law

3.1 The language of the Contract and the law governing the Contract are stated in the Contract Data.

Works 3: Remediation works of NMK-KIE Page 62

4. Engineer's Decisions

4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters between the Employer and the Contractor in the role representing the Employer.

5. Delegation

5.1 The Engineer may delegate any of his duties and responsibilities to other people except to the Adjudicator after notifying the Contractor and may cancel any delegation after notifying the Contractor.

6. Communications

6.1 Communications between parties which are referred to in the conditions are effective only when in writing. A notice shall be effective only when it is delivered (in terms of Indian Contract Act).

7. Subcontracting

7.1 The Contractor may subcontract with the approval of the Engineer but may not assign the Contract without the approval of the Employer in writing. Subcontracting does not alter the Contractor's obligations.

8. Other Contractors

8.1 The Contractor shall cooperate and share the Site with other contractors, public authorities, utilities, and the Employer between the dates given in the Schedule of Other Contractors. The Contractor shall as referred to in the Contract Data, also provide facilities and services for them as described in the Schedule. The employer may modify the schedule of other contractors and shall notify the contractor of any such modification.

9. Personnel

9.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel as referred to in the Contract Data to carry out the functions stated in the Schedule or other personnel approved by the Engineer. The Engineer will approve any proposed replacement of key personnel only if their qualifications, abilities, and relevant experience are substantially equal to or better than those of the personnel listed in the Schedule.

9.2 If the Engineer asks the Contractor to remove a person who is a member of the Contractor’s staff or his work force stating the reasons the Contractor shall ensure that the person leaves the Site within seven days and has no further connection with the work in the Contract.

Works 3: Remediation works of NMK-KIE Page 63

10. Employer’s and Contractor's Risks

10.1 The Employer carries the risks which this Contract states are Employer’s risks, and the Contractor carries the risks which this Contract states are Contractor’s risks.

11. Employer's Risks

11.1 The Employer is responsible for the excepted risks which are (a) in so far as they directly affect the execution of the Works in the Employer’s country, the risks of war, hostilities, invasion, act of foreign enemies, rebellion, revolution, insurrection or military or usurped power, civil war, riot commotion or disorder (unless restricted to the Contractor’s employees), and contamination from any nuclear fuel or nuclear waste or radioactive toxic explosive, or (b) a cause due solely to the design of the Works, other than the Contractor’s design.

12. Contractor’s Risks

12.1 All risks of loss of or damage to physical property and of personal injury and death which arise during and in consequence of the performance of the Contract other than the excepted risks are the responsibility of the Contractor.

13. Insurance

13.1 The Contractor shall provide, in the joint names of the Employer and the Contractor, insurance cover from the Start Date to the end of the Defects Liability Period, in the amounts and deductibles stated in the Contract Data for the following events which are due to the Contractor’s risks:

(a) Loss of or damage to the Works, Plant and Materials;

(b) Loss of or damage to Equipment;

(c) Loss of or damage of property (except the Works, Plant, Materials and Equipment) in connection with the Contract; and

(d) Personal injury or death.

13.2 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for the Engineer’s approval before the Start Date. All such insurance shall provide for compensation to be payable in the types and proportions of currencies required to rectify the loss or damage incurred.

13.3 If the Contractor does not provide any of the policies and certificates required, the Employer may affect the insurance which the Contractor should have provided and recover the premiums the Employer has paid from payments otherwise due to the Contractor or, if no payment is due, the payment of the premiums shall be a debt due.

Works 3: Remediation works of NMK-KIE Page 64

13.4 Alterations to the terms of an insurance shall not be made without the approval of the Engineer.

13.5 Both parties shall comply with any conditions of the insurance policies.

14. Site Investigation Reports

14.1 The Contractor, in preparing the Bid, shall rely on any site Investigation Reports referred to in the Contract Data, supplemented by any information available to the Bidder.

15. Queries about the Contract Data

15.1 The Engineer will clarify queries on the Contract Data.

16. Contractor to Construct the Works

16.1 The Contractor shall construct and install the Works in accordance with the Specification and Drawings, and as per instructions of Engineer.

17. The Works to Be Completed by the Intended Completion Date

17.1 The Contractor may commence execution of the Works on the Start Date and shall carry out the Works in accordance with the program submitted by the Contractor, as updated with the approval of the Engineer, and complete them by the Intended Completion Date.

18. Approval by the Engineer

18.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary Works to the Engineer, who is to approve them if they comply with the Specifications and Drawings.

18.2 The Contractor shall be responsible for design of Temporary Works.

18.3 The Engineer's approval shall not alter the Contractor's responsibility for design of the Temporary Works.

18.4 The Contractor shall obtain approval of third parties to the design of the Temporary Works where required.

18.5 All Drawings prepared by the Contractor for the execution of the temporary or permanent Works, are subject to prior approval by the Engineer before their use.

19. Safety

19.1 The Contractor shall be responsible for the safety of all activities on the Site.

Works 3: Remediation works of NMK-KIE Page 65

20. Discoveries

20.1 Anything of historical or other interest or of significant value unexpectedly discovered on the Site is the property of the Employer. The Contractor is to notify the Engineer of such discoveries and carry out the Engineer's instructions for dealing with them.

21. Possession of the Site

21.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of the relevant activities and this will be Compensation Event.

22. Access to the Site

22.1 The Contractor shall allow the Engineer and any person authorized by the Engineer access to the Site, to any place where work in connection with the Contract is being carried out or is intended to be carried out and to any place where materials or plant are being manufactured / fabricated / assembled for the works.

23. Instructions

23.1 The Contractor shall carry out all instructions of the Engineer which comply with the applicable laws where the Site is located.

23.2 Inspections and Audits by the Bank The Contractor shall permit the Bank and/or persons appointed by the Bank to

inspect the Site and/or the accounts and records of the Contractor and its subcontractors relating to the performance of the Contract, and to have such accounts and records audited by auditors appointed by the Bank if required by the Bank. The Contractor’s attention is drawn to Clause 64 [Corrupt or Fraudulent Practices] which provides, inter alia, that acts intended to materially impede the exercise of the Bank’s inspection and audit rights provided for under Sub-Clause 23.2 constitute a prohibited practice subject to contract termination (as well as to a determination of ineligibility under the Procurement Guidelines).

24. Disputes

24.1 If the Contractor believes that a decision taken by the Engineer was either outside the authority given to the Engineer by the Contract or that the decision was wrongly taken, the decision shall be referred to the Adjudicator within 14 days of the notification of the Engineer's decision.

25. Procedure for Disputes

Works 3: Remediation works of NMK-KIE Page 66

25.1 The Adjudicator shall give a decision in writing within 28 days of receipt of a notification of a dispute.

25.2 The Adjudicator shall be paid daily at the rate specified in the Contract Data together with reimbursable expenses of the types specified in the Contract Data and the cost shall be divided equally between the Employer and the Contractor, whatever decision is reached by the Adjudicator. Either party may refer a decision of the Adjudicator to an Arbitrator within 28 days of the Adjudicator's written decision. If neither party refers the dispute to arbitration within the above 28 days, the Adjudicator's decision will be final and binding.

25.3 The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special Conditions of Contract.

26. Replacement of Adjudicator

26.1 Should the Adjudicator resign or die, or should the Employer and the Contractor agree that the Adjudicator is not fulfilling his functions in accordance with the provisions of the Contract, a new Adjudicator will be jointly appointed by the Employer and the Contractor. In case of disagreement between the Employer and the Contractor, within 30 days, the Adjudicator shall be designated by the Appointing Authority designated in the Contract Data at the request of either party, within 14 days of receipt of such request.

B. Time Control

27. Program

27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a Program including Environmental Management Plan showing the general methods, arrangements, order, and timing for all the activities in the Works along with monthly cash flow forecast.

27.2 An update of the Program shall be a program showing the actual progress achieved on each activity and the effect of the progress achieved on the timing of the remaining work including any changes to the sequence of the activities.

27.3 The Contractor shall submit to the Engineer, for approval, an updated Program at intervals no longer than the period stated in the Contract Data. If the Contractor does not submit an updated Program within this period, the Engineer may withhold the amount stated in the Contract Data from the next payment certificate and continue to withhold this amount until the next payment after the date on which the overdue Program has been submitted.

27.4 The Engineer's approval of the Program shall not alter the Contractor's obligations. The Contractor may revise the Program and submit it to the Engineer again at any

Works 3: Remediation works of NMK-KIE Page 67

time. A revised Program is to show the effect of Variations and Compensation Events.

28. Extension of the Intended Completion Date

28.1 The Engineer shall extend the Intended Completion Date if a Compensation Event occurs or a Variation is issued which makes it impossible for Completion to be achieved by the Intended Completion Date without the Contractor taking steps to accelerate the remaining work and which would cause the Contractor to incur additional cost.

28.2 The Engineer shall decide whether and by how much to extend the Intended Completion Date within 21 days of the Contractor asking the Engineer for a decision upon the effect of a Compensation Event or Variation and submitting full supporting information. If the Contractor has failed to give early warning of a delay or has failed to cooperate in dealing with a delay, the delay by this failure shall not be considered in assessing the new Intended Completion Date.

29. Acceleration (Deleted)

30. Delays Ordered by the Engineer

30.1 The Engineer may instruct the Contractor to delay the start or progress of any activity within the Works.

31. Management Meetings

31.1 Either the Engineer or the Contractor may require the other to attend a management meeting. The business of a management meeting shall be to review the plans for remaining work and to deal with matters raised in accordance with the early warning procedure.

31.2 The Engineer shall record the business of management meetings and is to provide copies of his record to those attending the meeting and to the Employer. The responsibility of the parties for actions to be taken is to be decided by the Engineer either at the management meeting or after the management meeting and stated in writing to all who attended the meeting.

32. Early Warning

32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely future events or circumstances that may adversely affect the quality of the work, increase the Contract Price or delay the execution of works. The Engineer may require the Contractor to provide an estimate of the expected effect of the future event or circumstance on the Contract Price and Completion Date. The estimate is to be provided by the Contractor as soon as reasonably possible.

Works 3: Remediation works of NMK-KIE Page 68

32.2 The Contractor shall cooperate with the Engineer in making and considering proposals for how the effect of such an event or circumstance can be avoided or reduced by anyone involved in the work and in carrying out any resulting instruction of the Engineer.

C. Quality Control

33. Identifying Defects

33.1 The Engineer shall check the Contractor's work and notify the Contractor of any Defects that are found. Such checking shall not affect the Contractor's responsibilities. The Engineer may instruct the Contractor to search for a Defect and to uncover and test any work that the Engineer considers may have a Defect.

33.2 The contractor shall permit the Employer’s Technical auditor to check the contractor’s work and notify the Engineer and Contractor of any defects that are found. Such a check shall not affect the Contractor’s or the Engineer’s responsibility as defined in the Contract Agreement.

34. Tests

34.1 If the Engineer instructs the Contractor to carry out a test not specified in the Specification to check whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test and any samples. If there is no Defect the test shall be a Compensation Event.

35. Correction of Defects

35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.

35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer’s notice.

36. Uncorrected Defects

36.1 If the Contractor has not corrected a Defect within the time specified in the Engineer’s notice, the Engineer will assess the cost of having the Defect corrected as well as any costs caused by this delay should also be included, and the Contractor will pay those amounts.

Note: Where in certain cases, the technical specifications provide for acceptance of works within specified tolerance limits at reduced rates, Engineer will certify payments to Contractor accordingly.

Works 3: Remediation works of NMK-KIE Page 69

D. Cost Control

37. Bill of Quantities

37.1 The Bill of Quantities shall contain items for the construction, installation, testing, and commissioning work to be done by the contractor.

37.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for the quantity of the work done at the rate in the Bill of Quantities for each item.

38. Changes in the Quantities

38.1 If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent, provided the change exceeds 1% of Initial Contract Price, the Engineer shall adjust the rate to allow for the change duly notifying the employer.

38.2 The Engineer shall not adjust rates from changes in quantities if the Initial Contract Price is exceeded by more than 15 percent, except with the Prior approval of the Employer. In case of less than 15 percent, the Employer needs to be notified prior to adjustment .

38.3 If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost breakdown of any rate in the Bill of Quantities.

39. Variations

39.1 All Variations shall be included in updated Programs produced by the Contractor.

40. Payments for Variations

40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.

40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work.

40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in

Works 3: Remediation works of NMK-KIE Page 70

accordance with Clause 40.1), the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs.

40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.

40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.

41. Cash flow forecasts

41.1 When the Program is updated, the contractor is to provide the Engineer with an updated cash flow forecast.

42. Payment Certificates

42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously alongwith details of measurement of the quantity of works executed in a tabulated form as approved by the Engineer.

42.2 The Engineer shall check the details given in the Contractor's monthly statement and within 14 days certify the amounts to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance).

42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractor.

42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed.

42.5 The value of work executed shall include the valuation of Variations and Compensation Events.

42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.

43. Payments

43.1 Payments shall be adjusted for deductions for advance payments, retention, other recoveries in terms of the contract and taxes, at source, as applicable under the law. The Employer shall pay the Contractor the amounts certified by the Engineer within 28 days of the date of each certificate. If the Employer makes a late payment, the Contractor shall be paid interest on the late payment in the next payment. Interest

Works 3: Remediation works of NMK-KIE Page 71

shall be calculated from the date by which the payment should have been made upto the date when the late payment is made at 8% per annum.

43.2 If an amount certified is increased in a later certificate or as a result of an award by the Adjudicator or an Arbitrator, the Contractor shall be paid interest upon the delayed payment as set out in this clause. Interest shall be calculated from the date upon which the increased amount would have been certified in the absence of dispute.

43.3 Items of the Works for which no rate or price has been entered in will not be paid for by the Employer and shall be deemed covered by other rates and prices in the Contract.

44. Compensation Events

44.1 The following are Compensation Events unless they are caused by the Contractor:

(a) The Employer does not give access to a part of the Site by the Site Possession Date stated in the Contract Data.

(b) The Employer modifies the schedule of other contractors in a way which affects the work of the contractor under the contract.

(c) The Engineer orders a delay or does not issue drawings, specifications or instructions required for execution of works on time.

(d) The Engineer instructs the Contractor to uncover or to carry out additional tests upon work which is then found to have no Defects.

(e) The Engineer unreasonably does not approve for a subcontract to be let.

(f) Ground conditions are substantially more adverse than could reasonably have been assumed before issuance of Letter of Acceptance from the information issued to Bidders (including the Site Investigation Reports), from information available publicly and from a visual inspection of the Site.

(g) The Engineer gives an instruction for dealing with an unforeseen condition, caused by the Employer, or additional work required for safety or other reasons.

(h) Other contractors, public authorities, utilities or the Employer does not work within the dates and other constraints stated in the Contract, and they cause delay or extra cost to the Contractor.

(i) The advance payment is delayed.

(j) The effect on the Contractor of any of the Employer’s Risks.

(k) The Engineer unreasonably delays issuing a Certificate of Completion.

Works 3: Remediation works of NMK-KIE Page 72

(l) Other Compensation Events listed in the Contract Data or mentioned in the Contract.

44.2 If a Compensation Event would cause additional cost or would prevent the work being completed before the Intended Completion Date, the Contract Price shall be increased and/or the Intended Completion Date is extended. The Engineer shall decide whether and by how much the Contract Price shall be increased and whether and by how much the Intended Completion Date shall be extended duly notifying the Employer.

44.3 As soon as information demonstrating the effect of each Compensation Event upon the Contractor's forecast cost has been provided by the Contractor, it is to be assessed by the Engineer and the Contract Price shall be adjusted accordingly. If the Contractor's forecast is deemed unreasonable, the Engineer shall adjust the Contract Price based on Engineer’s own forecast. The Engineer will assume that the Contractor will react competently and promptly to the event.

44.4 The Contractor shall not be entitled to compensation to the extent that the Employer's interests are adversely affected by the Contractor not having given early warning or not having cooperated with the Engineer.

45. Tax

45.1 The rates quoted by the Contractor shall be deemed to be inclusive of the sales and other taxes that the Contractor will have to pay for the performance of this Contract. The Employer will perform such duties in regard to the deduction of such taxes at source as per applicable law.

46. Currencies

46.1 All payments shall be made in Indian Rupees.

47. Price Adjustment

47.1 Contract price shall be adjusted for increase or decrease in rates and price of labour, materials, fuels and lubricants in accordance with the following principles and procedures and as per formula given in the contract data:

(a) The price adjustment shall apply for the work done from the start date given in the contract data upto end of the initial intended completion date or extensions granted by the Engineer and shall not apply to the work carried out beyond the stipulated time for reasons attributable to the contractor.

(b) The price adjustment shall be determined during each quarter from the formula given in the contract data.

Works 3: Remediation works of NMK-KIE Page 73

(c) Following expressions and meanings are assigned to the work done during each quarter:

R = Total value of work done during the quarter. It would include the amount of secured advance for materials paid for (if any) during the quarter, less the amount of the secured advance recovered, during the quarter. It will exclude value for works executed under variations for which price adjustment will be worked separately based on the terms mutually agreed.

47.2 To the extent that full compensation for any rise or fall in costs to the contractor is not covered by the provisions of this or other clauses in the contract, the unit rates and prices included in the contract shall be deemed to include amounts to cover the contingency of such other rise or fall in costs.

48. Retention

48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion and Acceptance of the whole of the Works.

48.2 On Completion and Acceptance of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.

48.3 On completion and acceptance of the whole works, the contractor may substitute retention money (balance half) with an “on demand” Bank guarantee.

49. Liquidated Damages

49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the Contract Data for each day that the Completion Date is later than the Intended Completion Date (for the whole of the works or the milestone as stated in the contract data). The total amount of liquidated damages shall not exceed the amount defined in the Contract Data. The Employer may deduct liquidated damages from payments due to the Contractor. Payment of liquidated damages does not affect the Contractor's liabilities.

49.2 If the Intended Completion Date is extended after liquidated damages have been paid, the Engineer shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment certificate. The Contractor shall be paid interest on the over payment calculated from the date of payment to the date of repayment at the rates specified in Sub Clause 43.1.

50. Bonus (Deleted)

Works 3: Remediation works of NMK-KIE Page 74

51. Advance Payment

51.1 The Employer shall make advance payment to the Contractor of the amounts stated in the Contract Data by the date stated in the Contract Data, against provision by the Contractor of an Unconditional Bank Guarantee in a form and by a bank acceptable to the Employer in amounts and currencies equal to the advance payment. The guarantee shall remain effective until the advance payment has been repaid, but the amount of the guarantee shall be progressively reduced by the amounts repaid by the Contractor. Interest will not be charged on the advance payment. The bank guarantee of a joint venture shall be in the name of the joint venture.

51.2 The Contractor is to use the advance payment only to pay for Equipment, Plant and Mobilization expenses required specifically for execution of the Works. The Contractor shall demonstrate that advance payment has been used in this way by supplying copies of invoices or other documents to the Engineer.

51.3 The advance payment shall be repaid by deducting proportionate amounts from payments otherwise due to the Contractor, following the schedule of completed percentages of the Works on a payment basis. No account shall be taken of the advance (mobilization and equipment only) payment or its repayment in assessing valuations of work done, Variations, price adjustments, Compensation Events, or Liquidated Damages.

51.4 Secured Advance:

The Engineer shall make advance payment in respect of materials intended for but not yet incorporated in the Works in accordance with conditions stipulated in the Contract Data.

52. Securities

52.1 The Performance Security shall be provided to the Employer no later than the date specified in the Letter of Acceptance and shall be issued in an amount and form and by a bank or surety acceptable to the Employer, and denominated in Indian Rupees. The Performance Security shall be valid until a date 28 days from the date of expiry of Defects Liability Period and the additional security for unbalanced bids shall be valid until a date 28 days from the date of issue of the certificate of completion. The performance security of a joint venture shall be in the name of the joint venture’

53. Dayworks (Deleted)

Works 3: Remediation works of NMK-KIE Page 75

54. Cost of Repairs

54.1 Loss or damage to the Works or Materials to be incorporated in the works between the start date and the end of the defects correction periods shall be remedied by the contractor at the contractors cost if the loss or damage arises from the contractors acts or omissions. The contractor is also responsible for guarding the site at his expense. Losses/damages due to vandalism or theft should be covered by the Contractor.

E. Finishing the Contract

55. Completion

55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of the Works and the Engineer will do so upon deciding that the Work is completed.

56. Taking Over

56.1 The Employer shall take over the Site and the Works within seven days of the Engineer issuing a certificate of Completion.

57. Final Account

57.1 The Contractor shall supply to the Engineer a detailed account of the total amount that the Contractor considers payable under the Contract before the end of the Defects Liability Period. The Engineer shall issue a Defect Liability Certificate and certify any final payment that is due to the Contractor within 56 days of receiving the Contractor's account if it is correct and complete. If it is not, the Engineer shall issue within 56 days a schedule that states the scope of the corrections or additions that are necessary. If the Final Account is still unsatisfactory after it has been resubmitted, the Engineer shall decide on the amount payable to the Contractor and issue a payment certificate, within 56 days of receiving the Contractor’s revised account.

58. Operating and Maintenance Manuals

58.1 If “as built” Drawings and/or operating and maintenance manuals are required, the Contractor shall supply them by the dates stated in the Contract Data.

58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the Contract Data, or they do not receive the Engineer’s approval, the Engineer shall withhold the amount stated in the Contract Data from payments due to the Contractor.

59. Termination

Works 3: Remediation works of NMK-KIE Page 76

59.1 The Employer or the Contractor may terminate the Contract if the other party causes a fundamental breach of the Contract.

59.2 Fundamental breaches of Contract include, but shall not be limited to the following:

(a) The Contractor stops work for 28 days when no stoppage of work is shown on the current program and the stoppage has not been authorized by the Engineer;

(b) The Engineer instructs the Contractor to delay the progress of the Works and the instruction is not withdrawn within 28 days;

(c) The Employer or the Contractor is made bankrupt or goes into liquidation other than for a reconstruction or amalgamation;

(d) A payment certified by the Engineer is not paid by the Employer to the Contractor within 56 days of the date of the Engineer's certificate;

(e) the Engineer gives Notice that failure to correct a particular Defect is a fundamental breach of Contract and the Contractor fails to correct it within a reasonable period of time determined by the Engineer;

(f) The Contractor does not maintain a security which is required;

(g) the Contractor has delayed the completion of works by the number of days for which the maximum amount of liquidated damages can be paid as defined in the Contract data; and

(h) If the Contractor, in the judgment of the Purchaser has engaged in fraud and corruption, as defined in GCC Clause 64, in competing for or in executing the Contract.

(i) The contractor (in case of joint venture) has modified the composition of the joint venture and/or the responsibility of each member of the joint venture from what is stated in joint venture agreement without prior approval of the Employer.

59.3 When either party to the Contract gives notice of a breach of contract to the Engineer for a cause other than those listed under Sub Clause 59.2 above, the Engineer shall decide whether the breach is fundamental or not.

59.4 Notwithstanding the above, the Employer may terminate the Contract for convenience.

59.5 If the Contract is terminated the Contractor shall stop work immediately, make the Site safe and secure and leave the Site as soon as reasonably possible.

Works 3: Remediation works of NMK-KIE Page 77

60. Payment upon Termination

60.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the Engineer shall issue a certificate for the value of the work done less advance payments received up to the date of the issue of the certificate, less other recoveries due in terms of the contract, less taxes due to be deducted at source as per applicable law and less the percentage to apply to the work not completed as indicated in the Contract Data. Additional Liquidated Damages shall not apply. If the total amount due to the Employer exceeds any payment due to the Contractor the difference shall be a debt payable to the Employer.

60.2 If the Contract is terminated at the Employer's convenience or because of a fundamental breach of Contract by the Employer, the Engineer shall issue a certificate for the value of the work done, the reasonable cost of removal of Equipment, repatriation of the Contractor's personnel employed solely on the Works, and the Contractor's costs of protecting and securing the Works and less advance payments received up to the date of the certificate, less other recoveries due in terms of the contract and less taxes due to be deducted at source as per applicable law.

61. Property

61.1 All materials on the Site, Plant, Equipment, Temporary Works and Works are deemed to be the property of the Employer, if the Contract is terminated because of a Contractor’s default.

62. Release from Performance

62.1 If the Contract is frustrated by the outbreak of war or by any other event entirely outside the control of either the Employer or the Contractor the Engineer shall certify that the Contract has been frustrated. The Contractor shall make the Site safe and stop work as quickly as possible after receiving this certificate and shall be paid for all work carried out before receiving it and for any work carried out afterwards to which commitment was made.

63. Suspension of World Bank Loan or Credit

63.1 In the event that the World Bank suspends the Loan or Credit to the Employer, from which part of the payments to the Contractor are being made:

(a) The Employer is obligated to notify the Contractor of such suspension within 7 days of having received the World Bank’s suspension notice.

(b) If the Contractor has not received sums due to it upon the expiration of the 28 days for payment provided for in Sub-Clause 43.1, the Contractor may immediately issue a 14-day termination notice.

Works 3: Remediation works of NMK-KIE Page 78

64. Corrupt or Fraudulent Practices: 64.1 If the Employer determines that the Contractor has engaged in corrupt, fraudulent,

collusive coercive or obstructive practices, in competing for or in executing the Contract, then the Employer may, after giving 14 days notice to the Contractor, terminate the Contractor's employment under the Contract and expel him from the Site, and the provisions of Clause 59 shall apply.

Should any employee of the Contractor be determined to have engaged in corrupt, fraudulent, collusive, coercive, or obstructive practice during the execution of the Works, then that employee shall be removed in accordance with Clause 9 [Personnel].

For the purposes of this Sub-Clause:

(i) “Corrupt practice”7 is the offering, giving, receiving or soliciting, directly or indirectly, of anything of value to influence improperly the actions of another party;

(ii) “fraudulent practice”8 is any act or omission, including a misrepresentation, that

knowingly or recklessly misleads, or attempts to mislead, a party to obtain a financial or other benefit or to avoid an obligation;

(iii) “Collusive practice”9 is an arrangement between two or more parties designed to

achieve an improper purpose, including to influence improperly the actions of another party;

(iv) “Coercive practice”10 is impairing or harming, or threatening to impair or harm,

directly or indirectly, any party or the property of the party to influence improperly the actions of a party;

(v) “Obstructive practice” is

7 “another party” refers to a public official acting in relation to the procurement process or contract execution]. In

this context, “public official” includes World Bank staff and employees of other organizations taking or reviewing procurement

decisions.

8 a “party” refers to a public official; the terms “benefit” and “obligation” relate to the procurement process or

contract execution; and the “act or omission” is intended to influence the procurement process or contract execution.

9 “parties” refers to participants in the procurement process (including public officials) attempting to establish bid

prices at artificial, non competitive levels.

10 a “party” refers to a participant in the procurement process or contract execution.

Works 3: Remediation works of NMK-KIE Page 79

(aa) deliberately destroying, falsifying, altering or concealing of evidence material to the investigation or making false statements to investigators in order to materially impede a Bank investigation into allegations of a corrupt, fraudulent, coercive or collusive practice; and/or threatening, harassing or intimidating any party to prevent it from disclosing its knowledge of matters relevant to the investigation or from pursuing the investigation, or

(bb) acts intended to materially impede the exercise of the Bank’s inspection and audit rights provided for under Sub-Clause 23.2 [Inspections and Audits by the Bank].”

Works 3: Remediation works of NMK-KIE Page 80

F. Special Conditions of Contract

1. LABOUR:

The Contractor shall, unless otherwise provided in the Contract, make his own arrangements for the engagement of all staff and labour, local or other, and for their payment, housing, feeding and transport.

The Contractor shall, if required by the Engineer, deliver to the Engineer a return in detail, in such form and at such intervals as the Engineer may prescribe, showing the staff and the numbers of the several classes of labour from time to time employed by the Contractor on the Site and such other information as the Engineer may require.

2. COMPLIANCE WITH LABOUR REGULATIONS:

During continuance of the contract, the Contractor and his sub contractors shall abide at all times by all existing labour enactments and rules made there under, regulations, notifications and bye laws of the State or Central Government or local authority and any other labour law (including rules), regulations, bye laws that may be passed or notification that may be issued under any labour law in future either by the State or the Central Government or the local authority. Salient features of some of the major labour laws that are applicable to construction industry are given below. The Contractor shall keep the Employer indemnified in case any action is taken against the Employer by the competent authority on account of contravention of any of the provisions of any Act or rules made there under, regulations or notifications including amendments. If the Employer is caused to pay or reimburse, such amounts as may be necessary to cause or observe, or for non-observance of the provisions stipulated in the notifications/bye laws/Acts/Rules/regulations including amendments, if any, on the part of the Contractor, the Engineer/Employer shall have the right to deduct any money due to the Contractor including his amount of performance security. The Employer/Engineer shall also have right to recover from the Contractor any sum required or estimated to be required for making good the loss or damage suffered by the Employer.

The employees of the Contractor and the Sub-Contractor in no case shall be treated as the employees of the Employer at any point of time.

SALIENT FEATURES OF SOME MAJOR LABOUR LAWS APPLICABLE TO ESTABLISHMENTS ENGAGED IN BUILDING AND OTHER CONSTRUCTION WORK

(The law as current on the date of bid opening will apply)

a) Workmen Compensation Act 1923: The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

b) Payment of Gratuity Act 1972: Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years service or more or on death the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

Works 3: Remediation works of NMK-KIE Page 81

c) Employees P.F. and Miscellaneous Provision Act 1952 (since amended): The Act Provides for monthly contributions by the employer plus workers @ 10% or 8.33%. The benefits payable under the Act are:

(i) Pension or family pension on retirement or death, as the case may be.

(ii) Deposit linked insurance on the death in harness of the worker.

(iii) Payment of P.F. accumulation on retirement/death etc.

d) Maternity Benefit Act 1951: The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

e) Contract Labour (Regulation & Abolition) Act 1970: The Act provides for certain welfare measures to be provided by the Contractor to contract labour and in case the Contractor fails to provide, the same are required to be provided, by the Principal Employer by Law. The Principal Employer is required to take Certificate of Registration and the Contractor is required to take license from the designated Officer. The Act is applicable to the establishments or Contractor of Principal Employer if they employ 20 or more contract labour.

f) Minimum Wages Act 1948: The Employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, and Runways are scheduled employments.

g) Payment of Wages Act 1936: It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

h) Equal Remuneration Act 1979: The Act provides for payment of equal wages for work of equal nature to Male and Female workers and for not making discrimination against Female employees in the matters of transfers, training and promotions etc.

i) Payment of Bonus Act 1965: The Act is applicable to all establishments employing 20 or more employees. The Act provides for payments of annual bonus subject to a minimum of 8.33% of wages and maximum of 20% of wages to employees drawing Rs.3500/-per month or less. The bonus to be paid to employees getting Rs.2500/- per month or above upto Rs.3500/- per month shall be worked out by taking wages as Rs.2500/-per month only. The Act does not apply to certain establishments. The newly set-up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of this Act.

j) Industrial Disputes Act 1947: The Act lays down the machinery and procedure for resolution of Industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

Works 3: Remediation works of NMK-KIE Page 82

k) Industrial Employment (Standing Orders) Act 1946: It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the Employer on matters provided in the Act and get the same certified by the designated Authority.

l) Trade Unions Act 1926: The Act lays down the procedure for registration of trade unions of workmen and employers. The Trade Unions registered under the Act have been given certain immunities from civil and criminal liabilities.

m) Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of Child Labour is prohibited in Building and Construction Industry.

n) Inter-State Migrant workmen’s (Regulation of Employment & Conditions of Service) Act 1979: The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The Inter-State migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, travelling expenses from home upto the establishment and back, etc.

o) The Building and Other Construction workers (Regulation of Employment and Conditions of Service) Act 1996 and the Cess Act of 1996: All the establishments who carry on any building or other construction work and employs 10 or more workers are covered under this Act. All such establishments are required to pay cess at the rate not exceeding 2% of the cost of construction as may be modified by the Government. The Employer of the establishment is required to provide safety measures at the Building or construction work and other welfare measures, such as Canteens, First-Aid facilities, Ambulance, Housing accommodations for workers near the work place etc. The Employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

p) Factories Act 1948: The Act lays down the procedure for approval at plans before setting up a factory, health and safety provisions, welfare provisions, working hours, annual earned leave and rendering information regarding accidents or dangerous occurrences to designated authorities. It is applicable to premises employing 10 persons or more with aid of power or 20 or more persons without the aid of power engaged in manufacturing process.

3. SUB-CONTRACTING (GCC Clause 7)

Please add the following as Clause 7.2:

Works 3: Remediation works of NMK-KIE Page 83

The contractor shall not be required to obtain any consent from the employer for:

(a) the sub-contracting of any part of the Works for which the Sub-contractor is named in the contract;

(b) the provision of labour; and (c) The purchase of materials which are in accordance with the standards specified in the

Contract. Beyond this if the contractor proposes sub-contracting any part of the work during

execution of works, because of some unforeseen circumstances to enable him to complete the work as per terms of the contract, the Engineer will consider the following before according approval:

- The contractor shall not sub-contract the whole of the Works.

- The contractor shall not sub-contract any part of the Work without prior consent of the Engineer. Any such consent shall not relieve the contractor from any liability or obligations under the contract and he shall be responsible for the acts, defaults and neglects of any sub-contractor, his agents or workmen as fully as if they were the acts, defaults or neglects of the contractor, his agents or workmen.

- The Engineer should satisfy whether (a) the circumstances warrant such sub-contracting; and (b) the sub-contractors so proposed for the Work possess the experience, qualifications and equipment necessary for the job proposed to be entrusted to them in proportion to the quantum of work to be sub-contracted.

- If payments are proposed to be made directly to that sub-contractor, this should be subject to specific authorization by the prime contractor so that this arrangement does not alter the contractor's liability or obligations under the contract.

4. ARBITRATION (GCC Clause 25.3)

The procedure for arbitration will be as follows:

25.3 (a) In case of Dispute or difference arising between the Employer and a domestic contractor relating to any matter arising out of or connected with this agreement, such disputes or difference shall be settled in accordance with the Arbitration and Conciliation Act, 1996. The arbitral tribunal shall consist of 3 arbitrators one each to be appointed by the Employer and the Contractor. The third Arbitrator shall be chosen by the two Arbitrators so appointed by the Parties and shall act as Presiding arbitrator. In case of failure of the two arbitrators appointed by the parties to reach upon a consensus within a period of 30 days from the appointment of the arbitrator

appointed subsequently, the Presiding Arbitrator shall be appointed by the President of the Institution of Engineers (India)

(Note:1. All bidders are expected to indicate clearly in the bid, if they proposed sub-contracting elements of the works amounting to more than 20 percent

of the Bid Price. For each such proposal the qualification and the experience of the identified sub-contractor in the relevant field should be furnished

Works 3: Remediation works of NMK-KIE Page 84

(b) In the case of dispute with a foreign contractor the dispute shall be settled in accordance with provisions of UNCITRAL Arbitration Rules. The Arbitral Tribunal shall consist of three Arbitrators one each to be appointed by the Employer and the Contractor. The third Arbitrator shall be chosen by the two Arbitrators so appointed by the Parties, and shall act a presiding arbitrator. In case of failure

of the two arbitrators appointed by the parties to reach upon a consensus within a period of 30 days from the appointment of the arbitrator appointed subsequently, the Presiding arbitrator shall be appointed by the * President of the Institution of Engineers (India)

. (c) If one of the parties fails to appoint its arbitrator in pursuance of sub-clause (a) and (b) above within 30 days after receipt of the notice of the appointment of its arbitrator by the other party, then the * President of the Institution of Engineers (India), both in cases of the Foreign Contractor as well as Indian Contractor, shall appoint the arbitrator. A certified copy of the order of the * President of the Institution of Engineers (India), making such an appointment shall be furnished to each of the parties.

(d) Arbitration proceedings shall be held at Hyderabad, India, and the language of the arbitration proceedings and that of all documents and communications between the parties shall be English.

(e) The decision of the majority of arbitrators shall be final and binding upon both parties. The cost and expenses of Arbitration proceedings will be paid as determined by the arbitral tribunal. However, the expenses incurred by each party in connection with the preparation, presentation, etc. of its proceedings as also the fees and expenses paid to the arbitrator appointed by such party or on its behalf shall be borne by each party itself.

alongwith the bid to enable the employer to satisfy himself about their qualifications before agreeing for such sub-contracting and include it in the

contract. In view of the above, normally no additional sub-contracting should arise during execution of the contract.

Note 2. However, [a] sub contracting for certain specialized elements of the work is not unusual and acceptable for carrying out the works more

effectively; but vertical splitting of the works for subcontracting is not acceptable. [b] In any case, proposal for sub-contracting in addition

to what was specified in bid and stated in contract agreement will not be acceptable if the value of such additional sub-

contracting exceeds 25% of value of work which was to be executed by Contractor without sub-contracting.

Note 3. Assignment of the contract may be acceptable only under exceptional circumstances such as insolvencies/liquidation or

merger of companies etc.

Works 3: Remediation works of NMK-KIE Page 85

(f) Where the value of the contract is Rs.50 millions and below, the disputes or differences arising shall be referred to the Sole Arbitrator. The Sole Arbitrator should be appointed by agreement between the parties; failing such agreement, by the appointing authority, namely the * President of the Institution of Engineers (India)

. (g) Performance under the contract shall continue during the arbitration proceedings and payments due to the contractor by the owners shall not be withheld, unless they are the subject matter of the arbitration proceedings.

5. PROTECTION OF ENVIRONMENT:

Add the following as GCC Clause 16.2:

The contractor shall take all reasonable steps to protect the environment on and off the Site and to avoid damage or nuisance to persons or to property of the public or others resulting from pollution, noise or other causes arising as a consequence of his methods of operation.

During continuance of the contract, the contractor and his sub-contractors shall abide at all times by all existing enactments on environmental protection and rules made there under, regulations, notifications and bye-laws of the State or Central Government, or local authorities and any other law, bye-law, regulations that may be passed or notification that may be issued in this respect in future by the State or Central Government or the local authority.

Salient features of some of the major laws that are applicable are given below :

The Water (Prevention and Control of Pollution) Act, 1974, This provides for the prevention and

control of water pollution and the maintaining and restoring of wholesomeness of water. 'Pollution'

means such contamination of water or such alteration of the physical, chemical or biological

properties of water or such discharge of any sewage or trade effluent or of any other liquid, gaseous

or solid substance into water (whether directly or indirectly) as may, or is likely to, create a nuisance

or render such water harmful or injurious to public health or safety, or to domestic, commercial,

industrial, agricultural or other legitimate uses, or to the life and health of animals or plants or of

aquatic organisms.

The Air (Prevention and Control of Pollution) Act, 1981, This provides for prevention, control and

abatement of air pollution. 'Air Pollution' means the presence in the atmosphere of any 'air pollutant',

which means any solid, liquid or gaseous substance (including noise) present in the atmosphere in

such concentration as may be or tend to be injurious to human beings or other living creatures or

plants or property or environment.

*

Works 3: Remediation works of NMK-KIE Page 86

The Environment (Protection) Act, 1986, This provides for the protection and improvement of

environment and for matters connected therewith, and the prevention of hazards to human beings,

other living creatures, plants and property. 'Environment' includes water, air and land and the inter-

relationship which exists among and between water, air and land, and human beings, other living

creatures, plants, micro-organism and property.

The Public Liability Insurance Act, 1991, This provides for public liability insurance for the purpose

of providing immediate relief to the persons affected by accident occurring while handling

hazardous substances and for matters connected herewith or incidental thereto. Hazardous substance

means any substance or preparation which is defined as hazardous substance under the Environment

(Protection) Act 1986, and exceeding such quantity as may be specified by notification by the

Central Government.

[Employers should note that the Loan Agreement between IBRD and the borrowing country may

establish specific measures to be taken during construction of the Works for the protection of the

environment. Sub-clause 16.2 should be modified/expanded to take into account such specific

A separate Environmental and Social Management Plan has been prepared for the proposed works and the contractor shall implement the recommended measures in full compliance to the Management Plan as enclosed with the Bid Documents.

Summary of the Environmental and Social Management Plan is presented in the Section 9.

Except those mentioned in the BOQ, the costs associated with the Environmental Management Plan as per the above summary will have to be considered by the contractor in his cost and is the responsibility of the contractor.

6. LIQUIDATED DAMAGES:

Sub-clause 49.1:

Please substitute the last sentence with the following:

“Time is the essence of the contract and payment or deduction of liquidated damages shall not relieve the contractor from his obligation to complete the work as per agreed construction program and milestones or from any other of the contractor’s obligations and liabilities under the contract.”

Works 3: Remediation works of NMK-KIE Page 87

SECTION 4: CONTRACT DATA

Works 3: Remediation works of NMK-KIE Page 88

Contract Data

Items marked "N/A" do not apply in this Contract.

The following documents are also part of the Contract: Clause Reference

· The Schedule of Operating and Maintenance Manuals [58]

· The Schedule of Other Contractors [8]

· The Schedule of Key Personnel [9]

· The Methodology and Program of Construction & Environmental Management Plan[27]

· The Schedule of Key and Critical equipment to be deployed [27]

On the work as per agreed program of construction

· Site Investigation reports [14]

The Borrower is Government of India / MoEF [1.1]

The World Bank means "International Bank for Reconstruction and Development (IBRD)” and

International Development Association (IDA)". and loan refers to an IBRD Loan 7924-IN/IDA Credit No. 4755-IN [1.1]

The above insertions should correspond to the information provided in the Invitation of Bids.

The Employer is

Name: Telangana State Pollution Control Board, (1.1)

Address: Paryavarana Bhavan, A-3, Industrial Estate, Sanath Nagar, Hyderabad - 18

Name of authorized Representative: Project Director / Member Secretary

The Engineer is to be notified later (1.1)

Name:

Address : TSPCB, Hyderabad

Name of Authorized Representative:

The Adjudicator appointed jointly by the Employer and Contractor is:

Works 3: Remediation works of NMK-KIE Page 89

Name: Mr. A. Guatham, SE, PHE [1.1]

Address : Hyderabad

The name and identification number of the Contract is [1.1]

Remediation of Noor Mohammed Kunta, Kattedan Industrial Area (KIE) in Rangareddy District, Telangana , and Bid No.: 003/TSPCB/CBIPMP/NMK Works/2016

The Works consist of the remediation of Noor Mohammed Kunta, Kattedan Industrial Area (KIE) in Rangareddy District, Telangana with the objective to eliminate the risks to people and environment related and to facilitate the future land use changes in to a mixed zone. The Work includes inter alia:

1. Site preparations, including the installation of a monitoring system for control of contaminant exposure via surface water, groundwater, process water, drainage water, sediments and air

2. Installation of containment cells for the application of tubes of geotextile, including the installation of a HDPE liner

3. Removal and transport of (floating) vegetation in Lake NMK and (stagnant) water ponds in KIE and subsequent composting of the material within the available project area and subsequent re-use of the compost within the available project area

4. Excavation, transport and disposal of wastes from the open hillock, (stagnant) water ponds, swamps and drains in KIE

5. Levelling of soil and rubble heaps at the open hillock in KIE to support a degree of landscaping

6. Excavation, transport and containment of sediments from 2 swamps throughout KIE

7. Excavation, transport and containment of sediments from open drains throughout KIE

8. Excavation, transport and containment of sediments from 2 stagnant water ponds in KIE

9. Excavation, transport and containment of sediments from the stream in the plains downstream of Lake NMK

10. Excavation, transport and containment of sediments from Lake NMK 11. Closure of the containment cells, including the installation of a HDPE liner and

drainage layer 12. Construction of drainage channels around the containment cells 13. Installation of a vegetative layer (top soil) on top of the containment cells and

preparing for redevelopment of the cells into green zones 14. Application of a sand layer at the bottom of Lake NMK 15. Monitoring of cover layer, surface water, groundwater, process water, drainage

water, sediments and air to control contaminant exposure

Works 3: Remediation works of NMK-KIE Page 90

The Start Date shall be the date of issue of notice to proceed with the work. [1.1]

The Intended Completion Date for the whole of the Works is 17 Months (including monsoon period) with the following milestones: [17, 28]

Milestone dates:

Milestone Activities\Month 1 2 3 4 5 6 7 8 9 1

0

1

1

1

2

1

3

1

4

1

5

1

6

1

7

Project Steps

1. Site preparation, including construction

of 2 dewatering cells x x x

2. Waste collection, transport and disposal

from open hill lock, drains, swamps and

stagnant water ponds and discharge

channel

x x

3. Sediment removal, transport and

dewatering from stagnant water pond 1,

stagnant water pond 2 and Lake NMK

x x x x x x x x x

4. Sediment removal, transport and

dewatering from drains KIE, swamp 3,

swamp 4 and the discharge channel

x x x

5. Installation of final cover layer (HDPE

liner, drainage layer & vegetation layer)

on the containment cells

x x x x

6. Installation of cover layer at the bottom

of Lake NMK and revetment of the bund x x x x x x x x x x x x

7. Final clearance of the work area

x

The following documents also form part of the Contract: [2.3]

1. Remediation Plan, Final report

2. Site Assessment Report, Final report

3. Environmental and Social Baseline Report, Final report

4. Environmental and Social Management Plan, Final report

Works 3: Remediation works of NMK-KIE Page 91

The Contractor shall submit a revised Program including Environmental Management Plan for the Works (in such form and detail as the engineer shall reasonably prescribe) within 14 days of delivery of the Letter of Acceptance. [27]

[This program should be in adequate detail and generally conform to the program submitted along with bid in response to ITB Clause 4.3 (k). Deviations if any from that should be clearly explained and should be satisfactory to the Engineer]

The Site Possession Dates shall be: [21]

30 days after the signing of the Contract Agreement

The Site is located at Kattedan Industrial Area (KIE) in Rangareddy District, Telangana [1]

and is defined in drawings nos. IND50-1/0

The Defects Liability Period is 1 year from the date of certification of completion of works. (where sectional completion certificate is issued this will apply from those dates for those sections). [35]

Insurance requirements are as under: [13]

Minimum Cover for Insurance Maximum deductible for

Insurance

(i) Works and Plant and

Materials

At least equivalent to contract

amount

as applicable as per the

insurance company

(ii) Loss or damage to

Equipment

At least equivalent to value of

equipment

as applicable as per the

insurance company

(iii) Other Property

At least equivalent to value of

other property

as applicable as per the

insurance company

(iv) Personal injury or

death insurance:

a) for other people;

Rs 500,000/- (@ Rs.1,00,000

per person per occurrence)

--

Works 3: Remediation works of NMK-KIE Page 92

Minimum Cover for Insurance Maximum deductible for

Insurance

(i) Works and Plant and

Materials

At least equivalent to contract

amount

as applicable as per the

insurance company

(ii) Loss or damage to

Equipment

At least equivalent to value of

equipment

as applicable as per the

insurance company

(iii) Other Property

At least equivalent to value of

other property

as applicable as per the

insurance company

(iv) Personal injury or

death insurance:

a) for other people;

Rs 500,000/- (@ Rs.1,00,000

per person per occurrence)

--

b) for Contractor’s Employees In accordance with the statutory

requirements applicable to India

The following events shall also be Compensation Events: Nil [44]

The period between Program updates shall be 15 days. [27]

The amount to be withheld for late submission of an updated

Program shall be 5% of Current Bill amount or minimum of Rs 1.00 Lac [27]

The language of the Contract documents is English [3]

The law which applies to the Contract is the laws of Union of India [3]

The currency of the Contract is Indian Rupees. [46]

Fees and types of reimbursable expenses to be paid to the Adjudicator [25]

Works 3: Remediation works of NMK-KIE Page 93

Amount of Rs.5,000/- per day of adjudication plus reimbursable expenses for travel are fixed as fees of adjudicator

Appointing Authority for the Adjudicator MS, TSPCB / PD, CBIPMP [26]

The proportion of payments retained (retention money) shall be 6% from each bill

subject to a maximum of 5% of final contract price [48]

The liquidated damages for the whole of the works are is ten percent of final works:

For all milestones it is calculated at 0.05% per day basis. [49]

In case the bidder / contractor delays in completion of one or more milestones, but is able to complete the entire work within the contractual completion date, then the LD deducted per milestone shall be returned.

The maximum amount of liquidated damages for the whole of the works is 10 percent of final contract price. [49]

The amounts of the advance payment are: [51]

Nature of Advance

Amount (%) Conditions to be fulfilled

Mobilisation

5% of the contract value

On submission of un-conditional Bank Guarantee. The Bank Guarantee shall be for an equivalent amount and shall be from any Nationalized/Scheduled Bank of India or from a reputed foreign Bank having corresponding Bank in India. (to be drawn before end of 20% of Contract period)

Repayment of advance payment for mobilization and equipment: [51]

The advance shall be repaid with percentage deductions from the interim payments certified by the Engineer under the Contract. Deductions shall commence in the next Interim Payment Certificate following that in which the total of all such payments to the Contractor has reached not less than 15 percent of the Contract Price or two months from the date of payment of first instalment of advance, whichever period concludes earlier, and shall be made at the rate of 5% percent of the amounts of all Interim Payment Certificates until such time as the advance has been repaid, always provided that the advance shall be completely repaid prior to the expiry of the original time for completion.

The security bank guarantee for the project will also be released on the completion of commissioning and handling over of the site and all other contractual documentation formalities.

Works 3: Remediation works of NMK-KIE Page 94

The Securities shall be for the following minimum amounts equivalent as a percentage of the Contract Price: [52]

Performance Security for 5 per cent of contract price plus additional security for unbalanced bids if applicable [in terms of ITB Clause 29.5].

The standard form of Performance Security acceptable to the Employer shall be an unconditional Bank Guarantee of the type as presented in Section 8 of the Bidding Documents.

*The date by which operating and maintenance manuals are required is within 28 days of issue of certificate of completion of whole or section of the work, as the case may be. [58]

*The date by which “as-built” drawings (in scale similar to the scale of the drawings in the tender documents) in 2 sets are required is within 28 days of issue of certificate of completion of whole or section of the work, as the case may be.[58]

The amount to be withheld for failing to supply “as built” drawings and/or operating and maintenance manuals *by the date required is Rs.5,00,000/- [58]

The following events shall also be fundamental breach of contract: [59.2]

1. The Contractor has contravened Sub-clause 7 of GCC read with SCC and Clause 9.0 of GCC

2. The contractor does not adhere to the agreed construction program and agreed environmental management plan (Clause 27 of GCC) and also fails to take satisfactory remedial action as per agreements reached in the management meetings (Clause 31) for a period of 60 days.

3. The contractor fails to carry out of the instructions of Engineer within a reasonable time determined by the Engineer in accordance with GCC Clause 16.1 and 23.1.

The percentage to apply to the value of the work not completed representing the Employer's additional cost for completing the Works shall be 20 percent. [60]

Works 3: Remediation works of NMK-KIE Page 95

Section 5 : Specifications

Works 3: Remediation works of NMK-KIE Page 96

Scope of Work

Works 3: Remediation works of NMK-KIE Page 97

CONTENTS 1 Project background

2 Location and description of the site

3 Characterization of Kadapa Landfill

4 Description of the Works

4.1 Strategy

4.2 Future site use

4.3 Contractors Responsibility

4.4 Technical Description

5 Construction period

5.1 Project steps and time schedule

APPENDICES Appendix A Project Steps &Time Schedule

1. Project background The Works consist of the remediation of Noor Mohammed Kunta, Kattedan Industrial Area (KIE) in

Rangareddy District, Telangana . The objective of this remediation project is to eliminate the risks to

people and environment originating from the observed pollutions in KIE and Lake NMK, to facilitate the

future land use changes in to a mixed zone and to support improvement of the water quality in Lake

NMK to irrigation standards.

The project is part of the Capacity Building for Industrial Pollution Management Project (CBIPMP) that

helps the Ministry of Environment & Forests (MoEF) of the Government of India (GOI), to build capacity

at the state and central level, and develop a framework to address these issues in a comprehensive and

systemic manner under an area-wide management approach.

The Telangana Pollution Control Board (TSPCB) was sanctioned a pilot project, funded by the World

Bank, for two sites; Noor Mohammed Kunta Lake in Hyderabad, and Ukkayyapalli Municipal solid waste

dumpsite in Kadapa. The Consortium of Witteveen+Bos, Tauw, COWI A/S and Kadam Environmental

Consultants under the name of Pollution Control Board Consultants (PCBC) were selected to provide the

consultancy services for both the projects. As part of this project the remediation of the NMK/KIE area

has to be implemented. The remediation work for NMK/KIE area is the object for this tender.

The Contractor shall design (to the extent specified in the Contract), execute and complete the Works in

accordance with the Contract and with the Engineer in Charge’s instructions and shall remedy any defects

in the Works.

The Contractor is responsible for the adequacy, stability and safety of all site operations and of all

methods of construction. Except to the extent specified in the Contract, the contractor is responsible for

all Contractors Documents, Temporary Works and such design of each item of the project as is required

for satisfactory completion of the project.

Works 3: Remediation works of NMK-KIE Page 98

2. Location and description of the site Noor Mohammad Kunta (NMK Lake) and Katedan Industrial Estate (KIE) in Rangareddy District, Telangana

are located in Rajendranagar municipality adjoining Hyderabad city. The location of the site is shown in

the topographic overview in Figure 1.

Figure 1 Location of the NMK/KIE area

The NMK/KIE site is heavily polluted due to presence of heavy metals, organics, inorganics etc., and has

been identified as a ‘hot spot’. The major part of this pollution originates from (historical) pollution

sources located in KIE. In the plains downstream research field of the Agricultural University of

Hyderabad are located. In the past the University filed complaints about pollution migrating from the lake

into the research fields. Water of NMK Lake flows downstream into a system of interlinked lakes and

finally reaches the Mir Alam Tank.

The KIE was developed by the Telangana Industrial Investment Corporation (TSIIC) during the 1980s.

Prior to that, there is no information of industrial pollution of the Lake and the surrounding environment

(especially the groundwater). Currently KIE cover an area of about 110 hectares and consists of

approximately 550 small and medium scale industrial units.

When the ANGRAU brought the problems to light, the KIE consisted various types of industries, both

‘polluting’ and ‘non-polluting’11, including lead extraction facilities and textile industries. During the first

decade of this century, the regulatory authorities commenced a re-location of polluting industries to

other industrial areas, and this resulted in a slight reduction of pollution levels

11 Although these terms are commonly used, there is no formal definition of a ‘polluting’ or a ‘non-polluting’

industry.

Works 3: Remediation works of NMK-KIE Page 99

The KIE is situated on the North side of the Old Kurnool Road. KIE is on the West side bordered by the

residential areas of Budvel Colony, Sri Ram Nagar and Venkateswara Colony. Along the Northern border

of KIE runs the Railway Line Secundarabad-Kurnool. Residential area Sai Baba Nagar is located between

the western border of KIE and the Inner Ring Road.

Apart from the individual industrial units and the network of roads in KIE the open central hillock area, 4

(stagnant) water ponds or swamps and the drainage lines are of special interest for the remediation

project. In the open hillock area waste is disposed off and heaps of soil and rubble are present as well. In

the (stagnant) ponds, swamps and drainage lines waste and polluted sediments have been accumulated.

Within KIE about 1,000 resident have their living quarters and about ten thousand people are (self)

employed in the estate.

The most relevant existing features at and around the KIE site are:

1. Open central hillock area

2. Stagnant water ponds (2)

3. Swamps (2)

4. Drainage lines

5. Railway line Secundarabad-Kurnool

6. Residential areas Budvel Colony, Sri Ram Nagar and Venkateswara Colony

7. Inner Ring Road and adjacent residential area Sai Baba Nagar

8. Old Kurnool Road

The most relevant features of the KIE site are shown in Figure 2.

Works 4: Remediation works of NMK-KIE Page 100

Figure 2 Most relevant features of KIE

Works 4: Remediation works of NMK-KIE Page 101

Lake NMK is a small surface water body currently having a surface area of about 6.2 ha. The depth

of the Lake ranges from 0.5 m in the edges to 3.5 m - 4 m in the deepest part. The total capacity of

the Lake has been estimated as 0.1626 MCM. The Full Tank Level of the lake is 97.70 meter. The

surface area of the lake is about 68,760 m2.

Lake NMK has two feeder channels. The channel running from the south-eastern side and joining

the Lake on the eastern side is the main feeder channel. The other channel joins the Lake in the

southern side and the stream is ~1.4 km long. Apart from these two streams the outlet of the STP

situated on the bank of NMK lake is also joining the NMK Lake. The areas to the south and south-

east of the Lake form its catchment, which in turn forms part of the catchment area of the Musi

River. The Lake therefore drains into surrounding downstream plains including the Agricultural

University and other areas.

Lake NMK is situated directly to the North-west of the railway line Secundarabad-Kurnool. On the

South-west shore of NMK Lake a 4.0 MLD Sewage Treatment Plant (STP) is situated. Between the

railway line and the STP a stretch of barren land is situated which is located within the FTL boundary

of the Lake. The bund of NMK Lake on the north-western side runs directly parallel to the

Hyderabad-Bangalore National Highway NH7. The northern half of the bund is occupied by a

cemetery which is serving the local communities. The hillocks on the north eastern side of NMK Lake

are in a process of gradual urbanisation.

Apart from the remediation works the following works will be implemented:

- construction of fences along the FTL line of the Lake and around the open hillock in KIE, prior to

start of remediation works;

- construction of a new weir, prior to start of remediation works

- Upgradation of the existing STP to 10MLD capacity along with the remediation works

After the sediments have been removed from NMK Lake, the sediments are placed in containment

cells. After the upgrading of the STP has been completed, a sand layer has to be applied on the

bottom of NMK Lake, as part of this Contract.

Works 3: Remediation works of NMK-KIE Page 102

The relevant existing features at and around NMK Lake are:

1. STP

2. Bund

3. Culvert to the East

4. Culvert to the South

5. Railway line Secundarabad-Kurnool

6. Residential area to the North

7. Hyderabad-Bangalore National High Way NH7

8. Residential area to the South

9 Current outlet

10 Position of new weir

11 Position of new fences

12 Cemetery

The most relevant features of NMK Lake are shown in Figure 3.

Figure 3 Most relevant features of NMK Lake

Works 3: Remediation works of NMK-KIE Page 103

In the plains downstream of NMK Lake a small discharge channel is present. This discharge channel

conveys the discharge of NMK lake into Silon chevuru. The length of the discharge channel in the

plains is about 740 meter. The discharge channel has a maximum width of about 2.25 meters and is

less than 1 meter deep. On average it contains a 0.3 m thick layer of polluted soil at the bottom of

the channel,

Directly adjacent to both sides of the discharge channel the student research farms of agricultural

production fields (paddy, other crops and/or grass) of the University are positioned. A small

University road crosses the discharge channel at about 200 meter above its mouth into Silon

chevuru. At this crossing a small culvert conveys the discharge water. The small road is directed

towards the main entrance of the University complex on NH7.

Works 3: Remediation works of NMK-KIE Page 104

The relevant existing features in the plains downstream are:

1. Discharge channel

2. NMK Lake

3. Silon Chevru

4. Culvert in the discharge channel

5. Small University Road

6. Hyderabad-Bangalore National High Way NH7

8. Agricultural fields adjacent to the discharge channel

10 Position of new weir

The most relevant features of the plains downstream are shown in Figure 4.

Figure 4 Most relevant features of plains downstream

Works 3: Remediation works of NMK-KIE Page 105

In the Metropolitan Development Plan 2031, the NMK/KIE area is destined as mixed zone. The plains

downstream remain dedicated to the Agricultural University.

3. Characterization of NMK/KIE area

The investigation of NMK/KIE was carried out in 2011 and 2012 and the following estimates of the

volumes of wastes, polluted soil and polluted sediments may have changed due to ongoing

deposition of waste and accumulation of sediments since the end of the investigations. Also the

current topographic situation may have been slightly altered since the surveys which were

conducted in 2012.

General characterization of NMK/KIE area

In general the KIE area is characterized by thin layers of topsoil covering more hard strata directly

underneath. The topsoil is KIE is in general impacted by industrial activities in the area resulting in

significantly increased heavy metal pollution with amongst others lead. Locally the topsoil is also

polluted with other heavy metals and organic compounds such as TPH.

Within individual industrial units site specific hot spots have been identified. In the soil those hot

spots are in general contained within the industrial units itself. Industrial activities of some units

have also resulted in plumes of groundwater pollution. Although those plumes are not always

limited to the perimeters of the individual industrial units, they did not resulted in an significant

general impact of the groundwater underneath KIE.

An large extent of the groundwater underneath KIE shows only limited evidence of being impacted

by the industrial activities of the past. The groundwater underneath NMK Lake and the plains

downstream show even less evidence of being impacted by such activities.

In general there is a clear relation between the observed contaminations in KIE, NMK and the plains

downstream. Concentrations of contaminants show a clear decrease in the down gradient direction.

Works 3: Remediation works of NMK-KIE Page 106

Apart from distance, the actual decrease strongly depends on the estimated travel time. The longer

the distance and/or travel time the lower the concentrations tend to be.

As the remediation works are mainly targeting on the wastes present in the open hillock area, and

the sediments as present in the swamps, stagnant waters and open drains of KIE, NMK Lake and the

discharge channel in the plains, in the following sections more detailed information is provided

about those sub-sites.

Waste, soil and rubble in open hillock area KIE

TSIIC has recently collected all waste present in the verges and open common areas in KIE. All waste

have been temporarily stored in the central open hillock area. TSIIC has indicated that a volume of

about 1,000 m3 of waste has been collected and temporarily stored in the central open hillock area.

In addition to the waste TSIIC has also collected heaps of soil and rubble from the verges of the road.

TSIIC has disposed the collected materials on the basis of visual observations in the following 4

depots:

Containing only soil;

Containing soil and rubble;

Containing ashes and slacks

Containing different types of waste.

Waste already present in the hillock area before TSIIC’s waste collection activities in KIE has been left

as it was dumped. The amount of waste originally present in the central open hillock area is

estimated at about 2,500 m3, bringing the total amount of waste currently present in this area at

3,500 m3. It is assumed that in this volume about 10% of soil is included which has been mixed up

with the waste.

Waste has in the past been disposed off in an unorganized manner in the open hillock area of KIE.

Waste is scattered all over this area, thickness of waste layers can vary significantly and is sometimes

‘hidden‘ under layers of disposed topsoil.

Works 3: Remediation works of NMK-KIE Page 107

The different types of waste present varies significantly, amongst other but not limited to that the

following types of waste have been identified to be present:

Municipal solid waste;

Slacks and ashes

Production residues

Biochemical wastes

Asbestos containing material

Etc…

Heaps containing soil and/or inert rubble (bricks, concrete and cement, free of visual signs of

contamination) are under this project not considered to be waste and can be applied for a limited

amount of landscaping.

Sediments and drainage waters in open drains KIE

The sediments in the open drains contain significantly increased levels of heavy metals. Especially

high concentrations of chromium, copper, lead and zinc are present. In addition high levels of

antimony, barium, TPH and cresols have been encountered.

In the surface water of the open drains in general high levels of lead are present. Locally extremely

high concentrations of chromium, copper and zinc and elevated levels of cresols have been reported

due to incidental discharge of industrial waste water.

In table 3.1 the investigation results for the open drains are summarized with regard to observed

minimum, maximum and geometric mean concentrations of the identified Components of Potential

Concern (CoPC’s).

Table 3.1. Observed concentration in Open Drains KIE

Value type Unit Cr Cu Zn Pb Barium Cresols TPH

Sediment

Geom. mean mg/kg 433.11 1,038.67 1,415.33 1,043.22 360.00 10.00 2,055.56

Min value mg/kg 15.00 24.00 74.00 79.00 360.00 10.00 110.00

Works 3: Remediation works of NMK-KIE Page 108

Max value mg/kg 2,000.00 4,600.00 4,200.00 2,900.00 360.00 10.00 6,700.00

Surface water

Geom. mean ug/L 352.60 425.14 7,288.89 265.02 120.00 1,400.00 822.00

Min value ug/L 2.40 <0.5 30.00 5.20 120.00 1,400.00 68.00

Max value ug/L 2,300.00 3,400.00 59,000.00 930.00 120.00 1,400.00 1,800.00

In table 3.2 the volume of contaminated sediments present in the open drains has been assessed.

Table 3.2. Volume of sediments in open drains KIE

Length

(m) Width (m)

Thickness

(m)

Volume

(m3)

3,000 0.5 0.2 300

In addition a certain amount of waste may be present in the drains.

Swamps and stagnant waters

In KIE 2 swamps and 2 stagnant water ponds have been identified. The position of those swamps

and stagnant water ponds in KIE have been presented on Drawing No. IND50-1/04 (stagnant water

ponds 1 and 2 and swamps 3 and4).

The sediments in the investigated swamps and stagnant water ponds contain in general significantly

increased levels of chromium, copper, lead and zinc. In addition high levels of TPH have been

encountered.

In the surface waters elevated levels of TPH were detected. Apart from an elevated level of lead in

the surface water at the open hillock, no significantly increased concentrations of heavy metals were

reported in the surface water of the swamps and stagnant water ponds.

The investigation results have been summarized in table 3.3.

Works 3: Remediation works of NMK-KIE Page 109

Table 3.3. Observed concentration in swamps and stagnant waters at KIE

Value

type Unit Ni Cr Cd Cu Zn Pb Hg TPH

Sediment

Geom.

mean mg/kg 7.06 516.97 300.44 195.61 1,264.16 959.42 1.45 1,470.17

Min

value mg/kg 14.44 23.70 1.10 7.97 81.40 20.30 <0.1 22.40

Max

value mg/kg 43.53 2,965.58 1,200.00 832.80 5,900.00 6,600.00 22.70 9,962.00

Surface

water

Geom.

mean ug/L 24.81 10.19 5.03 10.00 106.86 114.66 0.13 580.00

Min

value ug/L <0.5 <0.1 <0.4 <0.5 11.00 5.00 <0.5 <50

Max

value ug/L 60.00 40.00 32.00 26.00 430.00 700.00 0.33 1,900.00

The volumes of contaminated sediments and clay present in the investigated stagnant water ponds

1 and 2 are presented in table 3.4.

Table 3.4. Volumes of sediment and clay in stagnant water ponds

Substance Thickness (m) Surface (m

2)

Volume (m3)

Stagnant water pond

1

Sediment 1.0 1,084 1,084

Clay 0.2 1,084 216

Stagnant water pond

2

Sediment 1.5 3,440 5,160

Clay 0.5 3,440 1,720

Works 3: Remediation works of NMK-KIE Page 110

The estimated quantities of sediments and soil in swamp3 are respectively 100m3 and 250m3 in

total. Those volumes are present in an estimated area of 20 by 25 meters.

In swamp 4 the amount of sediment is estimated at 100 m3. The amount of soil in this swamp is as

well estimated at 100m3. Those volumes are present in an estimated area of 20 by 20 meters.

In addition a certain amount of waste will be present in the swamps, stagnant water ponds and the

channel in the plains. This volume of waste is estimated at 100 m3.

Sediment and surface water of NMK Lake

Based on the field observations, surveys and analytical results, the sediment and clay layers of NMK

Lake are contaminated with heavy metals (mainly lead and copper) and TPH. In the sediments and

top of the clay layer positioned directly underneath the sediments of the lake, pink dyes were

observed to be present. In the native sandy clay with gravel, underneath the clay layer with pink

dyes, no significant elevated concentrations of heavy metals or TPH are present.

No significantly increased levels of contaminants were observed in the surface water of NMK Lake.

In the surface water from the inlet at the south side of NMK Lake a significantly increased level of

TPH was measured.

In table 3.5 the investigation results for the sediments, clay and surface water of NMK Lake are

summarized.

Table 3.5. Observed concentration in sediment and surface water of NMK Lake

Sub

component

sites

Value type Unit Hg Cd Cu Pb TPH

Sediment

Geom.

mean mg/kg 1.64 48.48 125.76 590.78 6,613.73

Min value mg/kg <0.1 <0.4 7.20 16.00 <0.1

Works 3: Remediation works of NMK-KIE Page 111

Max value mg/kg 37.00 1,292.70 940.00 4,623.40 44,000.0

0

Surface

water

Geom.

mean ug/L 0.07 BDL 5.93 17.61 118.29

Min value ug/L <0.05 BDL <0.5 <0.5 <50

Max value ug/L 0.17 BDL 24.00 59.00 560.00

Based on the topographic survey and the sediment investigation, the volume of sediments is

estimated at 32,317 m³ and the volume of contaminated clay at 13,752 m³. These amounts are

based on an average sediment thickness of approximately 0.47 m and an average clay thickness of

approximately 0.2 m over a total area of 68,760 m2. These volumes have been summarized in table

3.6.

Table 3.6. Volumes of contaminated sediment and clay in NMK Lake

Substance Thickness (m) Surface (m2) Volume (m3)

Sediment 0.47 68,760 32,317

Clay 0.2 68,760 13,752

Sediment and surface water in the plains downstream

The sediment in the open drain contains locally significantly increased levels of lead and TPH. The

concentrations are increasing from the beginning to the end of the open drain. In the surface water

elevated levels of lead were observed. The observed concentrations are summarized in table 3.7.

Table 3.7. Observed concentrations in sediment and water of the plains

Value type Unit Cu Zn Pb TPH

Sediment Geom.

mean mg/kg 40.58 465.87 312.42 2,300.16

Works 3: Remediation works of NMK-KIE Page 112

Min value mg/kg <0.5 14.00 10.00 3.8

Max value mg/kg 184.56 1,297.20 2,187.18 46,000.00

Surface

water

Geom.

mean ug/L 6.25 37.17 35.02 108.00

Min value ug/L <5 <10 <0.5 <50

Max value ug/L 20.00 110.00 93.00 360.00

The volume of polluted sediment in the stream is estimated at about 500 m3. In addition a certain

amount of waste will be present in the discharge channel.

Physical characteristics of NMK Lake

With regard to Lake NMK at least three critical physical conditions have to be taken into

consideration. These are:

- Water balance of the lake

- Vertical equilibrium of confined groundwater pressure versus combined weight of surface water,

sediment and the impermeable clay layer

- Bund stability

The delicate water balance of the lake greatly depends on the presence of the clay layer

underneath the sediments of the lake. For this reason damage to this clay layer has to be

prevented by all means. This clay layer can amongst other loose it’s integrity through uncontrolled

excavation or dredging or loss of vertical equilibrium through uncontrolled outflow of surface

water from the NMK Lake.

Given the limited volume of the water balance of NMK Lake and the requirement to maintain the

vertical equilibrium of the clay layer by all means, the potential loss of (process) water from the

Lake requires careful considerations.

Works 3: Remediation works of NMK-KIE Page 113

NMK Lake is contained behind a bund parallel to NH7. In this respect bund stability has to be

maintained by all means.

Given the presence of the graves and for esthetical reasons the height of the bunds should not be

more than about 1.5 meter above FTL. This is the current design height of the bund.

Extensive drainage patterns are observed at the outer sections of the bund. This is especially the

case at the graveyard. This observation can be an indication that the bund is not in the best

conditions at this section and is leaking water.

4. Description of the Works (elaborated area wise i.e., NMK, KIE (swamps, open

areas, drains) and Plains)

The selected remediation measures for the NMK/KIE area are a combination of measures included in

the so called “Bund and On-Site Containment Options” which have been elaborated in the final

remediation plan.

In KIE the remediation measures aim at the collection of waste, polluted topsoil and sediments

which are present in the public areas of the open hillock, the drains, swamps and stagnant water

ponds. Although the measures will not lead to a complete remediation of KIE, the direct inflow of

polluted material into Lake NMK will be reduced to acceptable levels and the surface water runoff

structure will be improved in such a manner that it will be able to trap polluted sediments before

they enter Lake NMK. Waste will be transported to off-site disposal facilities, the sediments will be

contained in tubes of geo-textile in stagnant water pond 2.

In Lake NMK the polluted sediments will be removed through dredging. The collected sediments will

be dewatered, stabilized and contained in tubes of geo-textile. The tubes with sediments will be

placed in containment cells along the bunds of the Lake. After the sediments have been removed, a

sand layer will be installed on the floor of the Lake. This sand layer should prevent that after

remediation the residual pollution present in the clay layer can migrate into the surface water of the

Lake.

Works 3: Remediation works of NMK-KIE Page 114

In the past small volumes of polluted sediments have entered the discharge channel in the plains. It

is expected that after remediation this will no longer be possible. To reduce the impact of the past,

the polluted sediments will be excavated and transported to KIE for permanent containment in

tubes of geo-textile in stagnant water pond 2.

Based on the recommendations of the Technical Evaluation Panel (TEP) it was decided to contain the

sediments as far as practically feasible from the surface waters of the NMK Lake.

In addition it was decided upon the recommendations of the TEP to include plastic liners (2 mm

HDPE) in the design of the containment cells.

After the remediation of the area, the containment cells shall be closed in order to be re-instated as

a green zone with the aim to prevent re-contamination of these sub-sites.

4.1 Strategy

Historical industrial activities have lead to significant pollution in KIE, NMK and the plains. Current

activities in KIE and NMK still contribute to the overall pollution load in the area.

The general objective of remediation of the site is the removal of (unacceptable) risks to people and

environment related to soil, sediment, surface water and groundwater pollutions present at the KIE,

NMK Lake and the plains of the Agricultural University.

The TSPCB envisions the following end-result of the entire project by the end of 2015:

- No more contamination of the water in Lake NMK due to polluted aquatic sediment.

- The human and ecological risks currently posed by Lake NMK are taken away.

- Sustainable water quality in the lake should at least comply with the irrigation standards.

- The lake area is fit for recreational use, visitors do no longer experience unpleasant odour or visual

observations, while the embankments and lake fringe have undergone a significant ecological

restoration and or beautification.

- Further industrial and domestic pollution is prevented.

Works 3: Remediation works of NMK-KIE Page 115

- Spread – horizontal and vertical – of polluted groundwater, underlying the lake, the KIE and the

research fields of the Agricultural University, is prevented or controlled.

This would be the end situation of the project and is based on the assumption that key-stakeholders

will contribute significantly to the sustainability of the project. Key stakeholders are several

Governmental departments like the HMDA, the TSIIC and the KIE Association of Small Scale

Industries.

To reach this end situation an area wide strategy has to be implemented. The works under the

subject Contract will facilitate the implementation of this area wide strategy.

The remediation works under this contract aims at establishing the following objectives:

The pollution load present in the sediments of NMK Lake and the small stream in the

plains has to be remediated. Remediation will be done by means of excavation or dredging and on-

site containment. Any remaining on-site pollution has to be controlled and should no longer pose

unacceptable human and ecological risks.

The following pollution sources in KIE have to be remediated under this contract on

priority basis:

o Collection and off-site disposal of (temporarily) stored waste in the open hillock area.

o Cleaning of existing drains and on-site containment of collected sediments.

o Remediation of polluted sediments in selected swamps and stagnant water ponds

through excavation or dredging and on-site containment.

o Installation of check dams in stagnant water ponds to stop uncontrolled inflow of

contaminated surface waters. Its anticipated that further improvements with regard to water

collection and treatment will be implemented under a separate works contract for the upgradation

of the STP.

Ecological restoration, beautification and landscaping will support sustainable remediation of NMK

Lake and the open hillock area where deemed practically feasible.

Thus the remediation of the NMK/KIE area under this Contract comprises of the following steps:

Works 3: Remediation works of NMK-KIE Page 116

1. Site preparations, including the installation of a monitoring system for control of contaminant

exposure via surface water, groundwater, process water, drainage water, sediments and air for

the workmen and surrounding environment and population.

2. Installation of containment cells for the application of tubes of geotextile, including the

installation of a HDPE liner. Installation of barrier layers as per the specifications of HWM Rules

2008.

3. Removal and transport of (floating) vegetation in Lake NMK and swamps and stagnant water

ponds in KIE and the remaining part of the project area and subsequent composting of the

material and subsequent re-use of the compost within the available project area.

4. Excavation, transport and disposal of wastes from the open hillock, swamps, stagnant water

ponds and drains in KIE and the open channel in the plains.

5. Levelling of soil and rubble heaps at the open hill lock in KIE to support a degree of landscaping.

6. Excavation, transport and containment of sediments from 2 swamps throughout KIE.

7. Excavation, transport and containment of sediments from open drains throughout KIE.

8. Excavation, transport and containment of sediments from 2 stagnant water ponds in KIE.

9. Excavation, transport and containment of sediments from the stream in the plains downstream

of Lake NMK.

10. Excavation, transport and containment of sediments from Lake NMK.

11. Closure of the containment cells, including the installation of a HDPE liner. Installation of barrier

layers as per the specifications of HWM Rules 2008..

12. Construction of drainage channels around the containment cells.

13. Installation of a vegetative layer (top soil) on top of the containment cells and preparing for

redevelopment of the cells into green zones. Topsoil for the vegetative layer should be ordinary

earth of native origin and should support the redevelopment of containment cells into a green

zone

14. Application of a sand layer at the bottom of Lake NMK.

15. Monitoring of cover layers, surface waters, groundwaters, process waters, drainage waters,

sediments and air to control contaminant exposure throughout the entire project area.

Works 3: Remediation works of NMK-KIE Page 117

4.2 Future site use

Open hillock area in KIE

The open hillock area in KIE will be completely fenced before the start of the remediation works

under this Contract. After all the wastes have been collected and transported to an off-site waste

disposal facility, the heaps off soil and inert rubble will be levelled in such a way that it facilitates a

minimum of landscaping. The objective of this limited landscaping is to smooth the surface of the

area and to fill the major depressions where stagnant water can accumulate. It is expected that a

certain degree of landscaping will support the area wide effort in KIE to stop illegal waste dumping.

The landscaping only allows for shallow rooting (grassy) vegetation, no further dumping of waste

and illegal quarrying is possible on it. For the time being the area will not be made accessible for the

public.

Drains

Once the drains in KIE have been cleaned further appropriate management of the drains falls under

the responsibilities of TSIIC. Potential impacts caused by the remediation works under this Contract

have to be restored before the responsibility of the drains is given back to TSIIC.

Swamps 3 and 4

Under the remediation works of this Contract swamps 3and 4will be cleaned from waste and

sediments. In addition the capacity of the swamps will be increased by removing a limited amount of

waterlogged topsoil directly around the centre of the swamps.

Once the swamps in KIE have been cleaned further appropriate management of the swamps falls

under the responsibilities of TSIIC. Potential impacts caused by the remediation works under this

Contract have to be restored before the responsibility of the swamps is given back to TSIIC. The

same applies for the stagnant water ponds 1 and 2.

Stagnant water ponds 1 and 2 near the pump house and the railway track

Works 3: Remediation works of NMK-KIE Page 118

Under the remediation works of this Contract the stagnant water ponds will be cleaned from waste

and sediments. In addition the capacity of the ponds will be increased by removing waterlogged

polluted topsoil directly around the centre of the ponds.

To prevent direct inflow of polluted drain water in NMK Lake a total of 4 check dams will be installed

under this Contract. These check dams will facilitate the stagnant water ponds to function as

sediment traps.

The check dams and sediment traps will require monitoring to ensure their functioning, integrity and

stability. Trapped sediments have to be removed from the sediment traps when this is deemed

appropriate for maintenance reasons. Those collected sediments have to be disposed to an off-site

disposal facility.

After remediation, ground works or groundwater extraction in the area need to be restricted and

can only be executed with prior approval of the competent authorities.

Containment cell in stagnant water pond 2.

For the on-site containment of the sediments from KIE and the discharge channel in the plains, part

of the stagnant water pond adjacent to the pump station can be used. The total available footprint

of the containment cell in this position is about 50 by 85 meters. For the effective storage of

sediments in the tubes of geotextile remains thus an area of about 30 by 65 meters in the middle of

the containment cell.

To be able to accommodate all sediments from KIE and the discharge channel in the plain, the

future containment cell is expected to have a height of approximately 6 m above the surrounding

area. The actual height shall be the result of the effective dewatering of the sediments and hence

variation of the final height is expected to be between 5 and 7 m. With a flat top and 1: 3 side slopes

on all sides, it will be a distinct feature. The top cover only allows for shallow rooting (grassy)

vegetation and no construction is possible on it. For the time being the area will not be made

accessible for the public.

Works 3: Remediation works of NMK-KIE Page 119

The top cover as well as the groundwater underneath the site will require monitoring to ensure that

no further exposure to the contaminants can take place. After rehabilitation, ground works or

groundwater extraction in the area need to be restricted and can only be executed with prior

approval of the competent authorities.

NMK Lake

The sediments in NMK Lake will be removed and contained in cells along the bunds of the Lake.

Once the upgradation of the STP and water collection management system have been completed

(under a separate Contract), a sand layer will be applied on the bottom of NMK Lake. The application

of the sand layer is the final remediation activity under this Contract.

After the sand layer has been applied, the bund of NMK Lake will be made accessible to the public.

As it is anticipated that water will not meet bathing standards, swimming in the lake has to be

restricted. Potential for fishing has to be assessed on the basis of future monitoring results. Given

the vulnerability of the applied cover layer of sand on the floor of the Lake no construction is

possible on it and human induced turbulence of the water should be avoided.

The cover layer of sand as well as surface water and the groundwater underneath the lake will

require monitoring to ensure that no further exposure to the contaminants can take place. After

remediation, ground works or groundwater extraction in the area need to be restricted and can only

be executed with prior approval of the competent authorities.

Containment cells in NMK

For the on-site containment of the sediments from NMK Lake, the bunds along the perimeter of the

Lake can be applied. Along the western and northern bunds an 10 meter wide containment cell with

a total length of about 500 meter can be installed. In the south-eastern corner of the Lake a

containment cells of about 6,500 m2 can be installed. Part of the outer perimeter of those

containment cells will consist of gabions.

To be able to accommodate all sediments from NMK Lake, the future containment cell is expected to

have a height of approximately 2 m above the surrounding area. The actual height shall be the result

Works 3: Remediation works of NMK-KIE Page 120

of the effective dewatering of the sediments and hence variation of the final height is expected to be

between 1.5 and 2.5 m. The top cover only allows for shallow rooting (grassy) vegetation and no

construction is possible on it. For the time being the area will not be made accessible for the public.

The top cover as well as the groundwater underneath the site will require monitoring to ensure that

no further exposure to the contaminants can take place. After rehabilitation, ground works or

groundwater extraction in the area need to be restricted and can only be executed with prior

approval of the competent authorities.

Discharge channel in the plains

After the sediments in the discharge channel have been excavated and transported to one of the

containment cells the site will return to its original functions. Any impacts caused by the remediation

works on the adjacent agricultural fields or the transport route have to be restored to its initial

conditions.

4.3 Contractors Responsibility

The present Tender is an Item Rate Tender. The technical designs, drawings and quantities are

presented in the Tender Documents; in case any details are not included the same should be

brought to the notice of the Empoyer well in advance of filling of the Tender prior to the submission

date. Contractor should carry out a thorough site visit and based on their estimations quote for the

tender as per BOQ.

Bidders are responsible and accountable for overall stability and performance of the entire

construction works of the Remediation Works (as specified in these tender documents) and shall

take a guarantee of successful completion of works with Defect Liability period of 1 year and further

Operation and Maintenance (for at least 5 years) as per the applicable guidelines (including latest

revisions) and standard design practices.

4.4 Technical Description

Works 3: Remediation works of NMK-KIE Page 121

A. Creation of Working Area: Prior to any dredging of sediments or excavation of wastes a working

area and project office have to be established at barren land directly to the South of the Sludge

drying beds of the current STP. Access to the area is through a temporary road construction between

NH7 and the barren land. From this working area the contractor can access the entire Lake NMK, by

boats or pontoons. If the Contractors prefers to construct temporarily access roads between this

working area and the projected containment cells in Lake NMK, he is free to do so as long as any

polluted sediments present at the projected alignment of such roads have been removed prior to

their construction.

If the Contractor requires additional working space he is allowed to use a portion of the open hill

lock area in KIE for this reason, once the wastes present in this section of the area has been

removed.

B.Establishment of a Monitoring System: Prior to any dredging of sediments or excavation of

wastes, a monitoring system has to be installed in the project area and a baseline monitoring round

has to be carried out. The monitoring system has to cover contaminant exposure resulting from the

remediation works via surface water, groundwater, process water, drainage water, sediments and

air in KIE, NMK Lake and the plains downstream.

In addition the groundwater pollution in the southwest of KIE has to be investigated. The

monitoring has to delineate this pollution and to characterize its source zones.

The design of the required monitoring wells is presented in Drawing No.IND50-1/05 ((Refer to

Section VI). Further requirements with regard to the monitoring and baseline investigation are

presented in Section 5 (General Items and Particular Specifications).

C. Construction of Containment Cells: Prior to any dredging of sediments the bottom structures of

the containment cells have to be constructed. The footprint of the containment cells along the

bunds of the Lake are 100 by 10 meter, 200 by 10 meter, 200 by 10 meter and 100 by on average 65

meters. The footprint of the containment cell in the stagnant water pond adjacent to the pumping

station is about 85 by 50 meter.

Works 3: Remediation works of NMK-KIE Page 122

The bottom liner of HDPE 2mm has on both sides to be protected with a sand layer. The sand should

be well graded and free of sharp objects and or particle larger than 5 millimetre. The sand layer on

top of the liner has to contain at least 5 kg of active carbon per square meter of surface. This layer

has also to be equipped with a sufficient number of drains for the effective extraction of process

water.

On all sides the floor of the containment cells has to be encircled by a ring dyke of ordinary

earth/sand with inner and outer slopes not steeper than respectively 1:1 and 1:3 and a minimum

crest width of 1 meter. The height of the dyke has to be at least the same as the effective filling

height of the selected tubes of geotextile. In Lake NMK this ring dyke is replaced by a gabion

structure or the existing bunds.

The HDPE 2 mm liner of the floor has to extended on the inner slope of the dykes until it reaches the

crest which it should fully cover. The HDPE liner on the inner slopes and crest has to be roughened

on both sides. Here again the liner has to be protected on both sides with similar sand layer of at

least 0.5 meter thick or a non-woven geotextile.

The HDPE liner has to achieve a permeability coefficient of less than 1 x 10-7 cm/sec.

With regard to the design of the containment cells along bunds and hillock and in south eastern

corner of Lake NMK and in stagnant water pond 2 reference is made towards Drawing Nos IND50-1-

5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10, IND50-1-5-11, IND50-1-2-1, IND50-1-2-2

and IND50-1-2-3 (Refer to Section VI).

D. Clearing of Vegetation: NMK Lake is encircled with a layer of floating vegetation. In the swamps

and stagnant water ponds of KIE also vegetation is present. Furthermore vegetation and stumps

have to be removed from other project areas such as the containment cells.

Vegetation free of soil has to be shredded upon collection and composed at authorized composting

facilities in the vicinity of the project site. The resulting compost can be applied as a soil additive in

the topsoil layers of the containment cells and the landscaped parts of the open hilock area in KIE.

Works 3: Remediation works of NMK-KIE Page 123

E. Works at Open Hillock area, :During the remediation works all waste have to be removed from the

open hillock in KIE. The waste present in the open hillock has to be separated in hazardous waste,

non-hazardous waste, municipal waste and/or any other category which facilitates the most

efficient and safe off-site disposal strategy. Detailed field surveys should establish the exact

positions, extent and type of waste present in the open hillock area of KIE. Where deemed

appropriate field investigation have to include trial excavations and chemical testing. Field

investigation should be such that it can be guaranteed that all waste present within the open hillock

area will be identified for final removal.

Excavated waste have to be loaded directly onto trucks which can be closed and sealed off after they

have been loaded. Once fully loaded the trucks have to transport the waste to the appropriate

disposal facilities, which meet the requirements for the specific type of waste loaded in that specific

truck. Transport documents have to provide the exact details of the type of waste transported, the

weight, the time of transport, the name of the receiving authorised disposal facility etc.. Those

documents have to be countersigned by the operator of the specific authorised disposal site.

After complete removal of all waste in the open hillock area of KIE the soil and inert rubble heaps

have to be levelled with the objective to obtain a limited degree of landscaping. Inert rubble has to

be covered with at least 1.0 meter of soil. Stagnant water ponds and depressions are preferably

filled up to the level of the surroundings. The landscaping principle is presented in Drawing No.

IND50-1-6-3 (Refer to Section VI)

F. Works in swamps and ponds of KIE: In addition waste present in the drains, stagnant water

ponds and swamps of KIE and the discharge channel in the plains has to be separated from the

sediment and transported to an authorised off-site disposal facility as soon as a full truck load has

been collected. Separation can be done by hand or by sieving. Separation is only required for waste

which cannot be pumped into the tubes of geotextile. Awaiting transport the waste has to be

temporarily stored in a closed compartment or containers.

Sediments and water logged topsoil can be excavated from swamps 3 and 4 with standard hydraulic

excavator. A total volume of 200 m3 of sediments and 350 m3 of soil have to be removed from the 2

Works 3: Remediation works of NMK-KIE Page 124

swamps in total. The required excavation depths are presented on Drawing Nos. IND50-1-3-1,

IND50-1-3-2, IND50-1-3-3, IND50-1-4-1, IND50-1-4-2 and IND50-1-4-3 (Refer to Section VI).

Excavated sediments and soil have to be transported in closed dumpers to the stagnant water pond

2 adjacent to the collector station. Here they can be disposed of in a temporary depot, awaiting final

placement in the containment cell situated over here. As long as the temporary depots are situated

within the footprint of the stagnant water ponds no dedicated protection measures are required.

In recent years the stagnant water ponds behind the railway track and adjacent to the collector

station were completely filled up with accumulated sediments. To restore the efficiency of the

sediment trap it is necessary to remove the sediments and to enlarge the capacity of the stagnant

water ponds by excavation part of the topsoil. A total volume of 6,244 m3 of sediment and 1,936 m3

of soil has to be removed or excavated. In Drawings Nos. IND50-1-1, IND50-1-1-2 and IND50-1-1-3

(Refer to Section VI) the required excavation profiles have been presented.

The excavated soil and sediment have to be transported to one of the constructed containment cells

for de-watering and final containment. After dredging the sediments can be directly pumped to

those cells with a floating pipe line. Soil can either be moved by excavators and dozers or a

combination of a tractor and closed dumper. If work optimizing requires so, soil and sediment from

stagnant water pond 2 can be transported to and applied in the containment cells which are

projected to be constructed around Lake NMK.

G. Works in Drains of KIE: The drains in KIE are either lined are unlined. In Drawing No. IND50-1-6-6

(Refer to Section VI) the drains to be cleaned are presented. Cleaning should start in the upstream

sections of the drains and proceed from there in the downstream direction.

In the lined section all sediment have to be removed by manual labour, while taking into account all

required health and safety precautions.

In the unlined sections sediments can be removed either by manual labour or small excavators

which are suitable for the specific conditions. In the unlined sections only the soft sediments present

should be removed. Excavation of soil beyond the design contours of the drains has to be avoided.

Works 3: Remediation works of NMK-KIE Page 125

It is estimated that a total volume of 300 m3 of sediments has to be removed from the drains in the

entire KIE area.

Removed sediments have to be directly loaded on closed dumpers and transported to the stagnant

water pond adjacent to the pump station. Here they can be disposed of in a temporary depot,

awaiting final placement in the containment cell situated over here. As long as the temporary depots

are situated within the footprint of the stagnant water ponds no dedicated protection measures are

required.

H. Works in the discharge channel situated in the Plains: The soft top sediments from the discharge

channel in the plains downstream have to be removed with a hydraulic excavator. In Drawing No.

IND50-1-7-1 (Refer to Section 6) the position of the discharge channel and the expected excavation

profile are presented. Cleaning should start in the upstream sections of the discharge channel from

the outlet of lake NMK and proceed from there in the downstream direction.

As the sides of the discharge channel can only be approached during the dry season when there are

no longer crops present in the fields, the execution of this part of the work is limited to this season

only. Excavation and transport works have to be closely coordinated with responsible staff from the

University and have to be executed in line with their instructions for approval.

Excavation of soil beyond the design contours of the discharge channel has to be avoided.

It is estimated that a total volume of 500 m3 of sediments has to be removed from the discharge

channel.

Removed sediments have to be directly loaded on closed dumpers and transported via University

roads and public roads to the stagnant water pond adjacent to the pump or collector station. Here

the sediments can be disposed of in a temporary depot, awaiting final placement in the containment

cell situated over here. As long as the temporary depots are situated within the footprint of the

stagnant water ponds no dedicated protection measures are required.

Works 3: Remediation works of NMK-KIE Page 126

I.Works at Lake NMK: Previous investigation has shown that the sediments and clay layer at the

bottom of Lake NMK are significantly contaminated with TPH and heavy metals. Given the fact that

the clay layer is an essential prerequisite for the mere existence of Lake NMK this clay layer will not

be excavated and its integrity has to be protected by all means. The polluted sediments have

however to be removed by dredging. A total of 32,317 in-situ m3 of sediments have to be removed.

In Drawing No. IND50-1-5-1 (Refer to Section VI) the position and thickness of the sediment layer as

off 2012 are presented. Drawing No. IND50-1-5-2 (Refer to Section VI) presents the situation after

the sediments have been removed.

Before dredging of the sediment starts the Contractor has to conduct a continuous survey of the

thickness of the sediment layer and also the height and position of the top of the clay layer in Lake

NMK. For this, a Sub Bottom Profiling investigation (SBP) needs to take place by the use of a

sediment echo sounder suitable for operation in extreme shallow waters verified by undisturbed

sediment sampling in liners or an equivalent (combination of) methodology(ies). The contractor has

to submit a detailed methodology for approval of the Engineer.

This survey has to result in a digital 3D model of the sediment and clay layer. The accuracy of the 3D

model should be such that the thickness of the sediment at any position in the lake is known within

+ 3 centimetres of the actual thickness. The position of the top of the clay layer at any position in the

lake should be known with an accuracy of + 2 centimetres.

The position of the dredging equipment has at all moments to be governed on the basis of

aforementioned 3D computer model and a dGPS positioning system. Sediments have to be dredged

with an accuracy of + 3 centimetres. Intrusion larger than 2 centimetres into the top of the clay layer

are not allowed.

Dredging of the sediment has to be implemented by a hydraulic dredger equipped with either an

auger head or an ecodredger head (or comparable device). Not more than 3 parts of process water

should be required for the removal of one part of (in-situ) sediment. The slurry of water and

sediment has to be transported via a closed pipe line (floating/flexible) to the de-watering and

containment cells. Working pressure in the pipe line has at all times to be adjusted with the

requirements of the dewatering process in the tubes of geotextile.

Works 3: Remediation works of NMK-KIE Page 127

In Figure 5 an example of a hydraulic dredger equipped with an auger head is presented. The

sediment/water slurry is transported with a floating and flexible pipe line.

Figure 5 Hydraulic dredger with auger head

J. The sediments from the drains and stagnant water ponds in KIE, Lake NMK and the discharge

channel in the plains will be dewatered and contained on site. The sediments itself will be contained

in tubes of geotextile. The tubes of geotextile will be placed in the super structure of a containment

cell which will be lined on all sides with a HDPE 2 mm liner. In Drawing Nos. IND50-1-5-4, IND50-1-5-

5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10, IND50-1-5-11, IND50-1-2-1, IND50-1-2-2 and IND50-1-2-

3(-Copy) (Refer to Section VI) the design of the projected containment cells is presented.

Dewatering of sediments is obtained by adding a polymer mixture into the slurry of sediments and

process water. The polymer acts as a flocculent which causes the sediments to form flakes which can

easily be separated from the water with the help of a filter material. Were deemed appropriate

electrolytes have to be used as well to improve the dewatering process. The geotextile of the

aforementioned tubes provide for such a filter material. By pumping the mixture of sediment, water

and polymer/electrolyte into the tubes the sediment flakes will remain inside and the process water

is pressed outside. The applied pressure increases the efficiency of the dewatering process.

Works 3: Remediation works of NMK-KIE Page 128

In figure 6 the dewatering process is schematically presented. All equipment and elements

presented in Figure 6 have to be part of the dewatering of the sediment with tubes of geotextile.

The required working pressure has to be coordinated with the operator of the dredging equipment.

Figure 6 Dewatering with tubes of geo-textile

In figure 7 a photo is presented which shows the actual application of tubes of geotextile for

dewatering and stabilisation of sediments.

Figure 7 Application of tubes of geotextile for dewatering purposes

Works 3: Remediation works of NMK-KIE Page 129

To guarantee a sustainable water balance in Lake NMK it is important that process water is as soon

as possible pumped back to this lake. The drainage layer underneath the tubes can be applied as an

additional filter to ensure that return water pumped towards the lake is clear water which is visibly

free of sediments and contaminants. Process water pumped back to the Lake has at all times to be

within 1.25 times above baseline conditions of the surface water quality of the lake. If the process

water is not meeting those discharge requirements the Contractor has to apply additional treatment

or filter steps.

After the tubes have been filed with the sediments passive dewatering will continue for a while.

Directly after filling, the tubes have to be filled at around 100 % of the filling height recommended

by the manufacturer. After passive dewatering this height will be reduced to about 75% to 50% of

the original height. This settlement will result in stabilisation of the sediments. The total length of

the passive de-watering period has to be decided on , on the basis of the monitoring of the

settlement rate of the filled tubes. Application of new layer of tubes of geo-textile on top of previous

filled tubes has also be governed on the same monitoring results.

Works 3: Remediation works of NMK-KIE Page 130

K.After the sediments in the applied tubes of geotextile have been sufficiently stabilized, the

dewatering cell has to be sealed off with an cover layer. The HDPE liner included in this layer has to

be completely seamed with the HDPE liner of the bottom of the previously constructed de-watering

cell. Once the top cover has been implemented the super structure of the containment cell has been

realized.

In total 4 containment cells have been planned. The first containment cells is projected at the south-

eastern corner of Lake NMK. The second containment cells is projected in stagnant water pond 2

near the collection tank of STP. The remaining 2 containment cells are situated along the western

and northern bunds of Lake NMK. The containment cells are presented in Drawing Nos. containment

cells along bunds and hillock and in south eastern corner of Lake NMK as presented on Drawings

Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11 (Refer to

Section VI).

Following the dewatering and stabilisation of the sediments in the tubes of geotextile, the cover

layer will be constructed consisting of a 30 cm thick soil cover / support layer consisting ordinary

earth of native topsoil (clay), a 0.2 meter thick foundation layer of sand, a HDPE liner of 2.0 mm,

roughened on both sides having permeability coefficient less that 1 x 10-7 cm/sec. On top of the

HDPE liner comes a 20 cm thick drainage layer of coarse sand, which will be covered by a non woven

protective layer (GSE 250 or equivalent) of 250 g/sqm.In the containment cells situated in Lake NMK

part of the sand layers is replaced by non-woven geo-textile and/or geo-composites.

Finally, a 50 till 80 cm thick vegetative top soil layer is added to support natural plant growth and to

minimize erosion. Installation of a vegetative layer (top soil) on top of the containment cells and

preparing for redevelopment of the cells into green zones. Topsoil for the vegetative layer should be

ordinary earth of native origin and should support the redevelopment of containment cells into a

green zone covered with a healthy grass cover.

Works 3: Remediation works of NMK-KIE Page 131

The 5 cells include a surface runoff drainage system.

The Future Layout of the containment cells will have following components:

1. Green Belt area

2. Storm Water Drainage

3. Toe Drain

4. Side slopes (including revetment of the slope along stagnant water pond 2)

5. On top of the cells there would be a green belt area, including a simple sprinkler system.

Around the 5 containment cells, ground water monitoring wells will be constructed to allow for

evaluation of the groundwater quality. The design of the monitoring wells is presented in Drawing

No. IND50-1/05 (Refer to Section VI).

The surface run-off water coming through the drainage layer constructed on top of the containment

cells is collected separately and discharged via an open drainage channel.

L. After the sediments have been (partly) removed from Lake NMK a sand cover has to be applied on

the bottom (top clay layer) of Lake NMK.

A continuous sand layer of 0.3 m has to be installed at the entire bottom of Lake NMK. The sand

layer has to be implemented with a rain bow technique (or comparable technique). The total sand

layer has to be applied with an overall accuracy of + 2 centimetre. The position of the top of the clay

layer which has to be covered is presented in Drawing No. IND50-1-5-2 and the sand layer which has

to be installed in Drawing No. IND50-1-5-3 (Refer to Section VI). About 20,625 m3 of sand is required

for this cover layer.

Application of the sand layer should not lead to an impact on the surface water quality of the lake or

it’s water balance.

In Figure 8 an example of a rainbow technique is presented.

Works 3: Remediation works of NMK-KIE Page 132

Figure 8 Example of a rainbow technique

M. Further requirements with regard to the monitoring during and after the implementation of the

works are presented in Section V (General Items).

5. Construction period

Based on the preliminary planning the award of work will be finalized within 17 months after

commencement. In the calculated scenario, work can be done with an average daily handling speed

of 300 m3 of sediments per day (dredging and dewatering) and 100 m3 of sand per day for the final

cover layer on the bottom of NMK Lake. Based on the infrastructure present, the availability of

materials, space and resources, this is seen as feasible.

5.1 Project steps and time schedule

The various steps in the project are shown at Appendix A. In order to optimize the progress of the

work, the Contractor is free to make changes in the various steps as per written agreement with the

Engineer In charge duly obtaining the approval of the Employer.

The various steps and associated time schedule are included in appendix A.

Works 3: Remediation works of NMK-KIE Page 133

Appendix A Project steps and Time Schedule

Activities\Month in 2014/2015 1 2 3 4 5 6 7 8 9 1

0

1

1

1

2

1

3

1

4

1

5

1

6

1

7

Project Steps

1. Site preparation, including construction

of 2 dewatering cells x x x

2. Waste collection, transport and disposal

from open hill lock, drains, swamps and

stagnant water ponds and discharge

channel

x x

3. Sediment removal, transport and

dewatering from stagnant water pond 1,

stagnant water pond 2 and Lake NMK

x x x x x x x x x

4. Sediment removal, transport and

dewatering from drains KIE, swamp 3,

swamp 4 and the discharge channel

x x x

5. Installation of final cover layer (HDPE

liner, drainage layer & vegetation layer) on

the containment cells

x x x x

6. Installation of cover layer at the bottom

of Lake NMK and revetment of the bund x x x x x x x x x x x x

7. Final clearance of the work area

x

Works 4: Remediation works of NMK-KIE Page 134

General items

Works 4: Remediation works of NMK-KIE Page 135

CONTENTS 6 General Items

6.1.1 Definitions

6.1.2 Measurement and Payment

1.3 Duration ofWorks, licenses and project language

7 Access and temporary use of private land

8 Quality assurance system

9 Progress reports

10 Safety procedures

11 Existing services

12 Contractor's designs, operation and maintenance manuals

12.1 As-built documents

12.2 Operation and maintenance manuals

13 Site installations

13.1 Contractor's Plant

13.2 Water Supply

13.3 Sanitation

13.4 Sewage and Waste Disposal

13.5 Pollution

13.6 Energy Supply

13.7 Supplyof Fuel,Lubricants,etc.

13.8 TemporaryTelephoneConnections

14 Health and safety

14.1 First Aid

14.2 Fire Protection

Works 4: Remediation works of NMK-KIE Page 136

15 Inspection, testing and taking over

15.1 General

15.2 Programme

15.3 Damage to Public and Private Service Installations

15.4 Employer's taking over

16 Supervision and Monitoring Plan

17 References

18 Applicable Environmental Performance Standards

19 Applicable Testing

19.1 Setting Of Field Laboratory by the Contractor

19.2 Testing

19.3 Measurements

19.4 Test Certificates

19.5 Tests On Completion

Works 4: Remediation works of NMK-KIE Page 137

6. General Items

The present section includes General Items for the execution and completion of the works

supplementing the descriptions in the “National Competitive Bidding”.

The (National Competitive Bidding) is based on the FIDIC Conditions of Contract for

Construction".

They should be read in conjunction with the Scope of Work, Particular Specification, Conditions

of Contract, the Bill of Quantities (BoQ) and the Drawings.

6.1 Definitions

6.1.1 General

Acceptable / Approved (Approval) - Acceptable to/approved (approval) by the Engineer in

Charge.

Agreed - Agreed in writing.

As Detailed - As detailed on the drawings.

Authorized / Ordered / Rejected - Authorized / ordered / rejected by the Engineer in Charge.

Designated - Shown on the drawings or otherwise specified by the Engineer or, in relation to an

item scheduled in the bid documents, descriptive of an item to be priced by a bidder.

Indicated - Indicated in or reasonably to be inferred from the contract, or indicated in writing

by the Engineer in Charge.

Instructed / Directed / Permitted -Instructed/directed permitted by the Engineer in Charge.

Satisfactory - Capable of fulfilling or having fulfilled the intended function.

Service - Any pipeline, cable, duct etc. for conveying or transmitting any fluid or other matter.

Submitted - Submitted with the tender or submitted to the Engineer in Charge, as appropriate.

6.1.2 Specific

On Site - means at any location where works during the project takes place, roads during

construction, maintenance and operation etc.

6.1.3 Tolerances

Deviation - The difference between the actual (i.e., measured) size or position or any other

measurement and the specified size or position.

Permissible Deviation - The specified limit(s) of deviation.

Tolerance - The range between the limits within which a size or position must lie.

Works 4: Remediation works of NMK-KIE Page 138

6.1.4 Metric Units

S.I. units of measurement shall be used generally throughout the Contract. All information and

data originating in another system shall be transferred by the Contractor into the S.I. system.

6.1.5 Abbreviations

ASTM American Society for Testing and Materials

a.s.l. above sea level

BoQ Bill of Quantities

cm centimetre

cm²/g square centimetre per gram

d day(s)

dia. Diameter

DIN Deutsche Industrie Norm (German Standard)

DN diameter nominal (=ND)

g/cm³ gram per cubic centimetre

g/m² gram per square meter

h Hour

HDPE high density polyethylene

HP horse power

ISO International Organization for Standardization

kg Kilogram

kg/cm³ kilogram per cubic centimetre

kg/cm² kilogram per square centimetre

km Kilometre

kN kilo Newton

Works 4: Remediation works of NMK-KIE Page 139

L Liter

l.s. lump sum

m Meter

m² square meter

m³ cubic meter

Mb Millibar

mg/l milligram per liter

mg/kg milligram per kilogram

Mln Million

mm millimetre

m³/d cubic meter per day

m/s meter per second

MPa Mega Pascal

mm/s millimeter per second

μg/l microgram per liter

μg/d microgram per day

N Newton

ND nominal diameter (= DN)

NGO non-governmental organization

N/mm² Newton per square millimetre

ng/l nanogram per liter

ng/m³ nanogram per cubic meter

PEHD polyethylene high density (= HDPE)

PN nominal pressure

Works 4: Remediation works of NMK-KIE Page 140

Ppm parts per million

RfC reference concentration

RfD reference dose

S Second

SI Systeme International d‘Unites

T temperature

T ton (weight)

USD United States Dollar

uPVC unplasticized polyvinyl chloride

HDPE High Density Polyethylene Pipe

W Watt

WHO World Health Organization

WWTP wastewater treatment plant

°C Centigrade

° Degree

% Percent

‰ per mill

< smaller/less than

> larger/more than

Works 4: Remediation works of NMK-KIE Page 141

6.2 Measurement and Payment

Bill / Schedule - The bill / schedule of quantities.

Billed / Scheduled Rate - The unit rate or price entered in the bill / schedule at which the

Contractor undertakes to execute the particular work or to provide the required material,

article or service, or to do any or all of these things, as set out in the item concerned.

Billed / Scheduled - Listed in the bill / schedule of quantities.

Fixed charge - A charge for work that is executed without reference to time.

Method-related charge - The sum for an item inserted in the bill by the Contractor when

tendering, to cover items of work relating to his intended method of executing the Works.

Time-related charge - A charge for work the cost of which, to the Employer, is varied in

proportion to the length of time taken to execute the particular item scheduled.

Value-related charge - A charge that is directly proportional to the value of the contract.

6.3 Duration ofWorks, licenses and project language

6.3.1 Duration of Works

Commencement of work on site (Mobilization): (The actual start date shall be the date of issue

of notice to proceed with the work)

Completion of work (Taking Over Certificate): (The intended Completion date for

the whole Works is 17 Months after the commencement of the work)

The entire duration of works is 17 months.

Monsoon break of work depends on the weather.

6.3.2 Licenses

The Contractor must have or successfully apply for all licenses required by the Indian law to

carry out the Works necessary under this Contract.

6.3.3 Project Language

All reports have to be prepared in English and all communication made in English. Applications

for required permits, licenses and similar shall be made in English language and official

drawings and maps shall be prepared in English.

Works 4: Remediation works of NMK-KIE Page 142

7. Access and temporary use of private land

7.1 The site

The Site includes any designated areas and any temporary working areas necessary to carry out

the Works under this contract. No permanent possession of the site or Parts thereof is

necessary within this Contract.

The Contractor shall himself obtain whatever temporary way leaves / renting of land as

required by him and the Contractor shall be responsible for obtaining temporary way leaves /

renting.

7.2 The private land

The cost of obtaining way leaves for temporary working areas and for any additional areas

outside the Site required by the Contractor in connection with the Works as well as for the

access to all of these shall be borne by the Contractor himself. The Contractor shall give to the

occupier of each such area seven days’ notice of his intention to enter and shall ensure that his

methods of working cause the minimum of disturbance to the land and to its owners and

occupiers.

The Contractor shall compensate the temporary land use during the Works as required by

National regulations and laws. The costs shall be included in the bid price as an overall cost and

not as a separate price position.

The Contractor shall at all times provide proper facilities for access and inspection of the Works

by the Engineer in Charge, his assistants, inspectors, agents and representatives of public

agencies having jurisdiction.

The extent of each temporary working area and the period of time for its occupation shall be

such as the Engineer in Charge considers necessary having regard to the Contractor's

reasonable requirements which shall be submitted together with the Work Program to the

Engineer in Charge within 21 days after the Letter of Acceptance.

The Contractor shall reinstate any temporary working areas to the condition prevailing prior to

his initial entry as soon as possible after the work in those areas has been completed thus

keeping the period of occupation to a minimum. The Contractor shall in any event restore the

areas to a tidy and workmanlike condition. Boundary walls, fences and other structures that

have been damaged, removed or otherwise interfered with by the Contractor shall be restored

to a condition at least equivalent to their original condition.

Works 4: Remediation works of NMK-KIE Page 143

Prior to commencing work near overhead (power) lines located in KIE, the Contractor shall

acquaint himself with all the regulations of the responsible electricity supply and other utility

authorities governing such work.

The Contractor shall be responsible for ensuring that all persons working in such areas are

aware of the relatively large distance that high voltage electricity can "short" to earth when

cranes or other large masses of steel are in the vicinity of power lines.

7.3 Access to Adjoining Property

If the Contractor's work will cause unavoidable interference with access to adjoining property,

the Contractor shall first give 7 days’ notice to the occupier of such property and shall provide

temporary means of access for vehicles, animals and pedestrians.

Convenient access to driveways, houses and buildings adjoining the work shall be maintained

and temporary approaches to intersecting streets and alleys shall be provided and kept in good

condition by the Contractor

8. Quality Assurance System

8.1 General

In order to respond to the contract requirements in an optimal way, a Quality Assurance

system shall be established.

The present section defines the following:

› The commitment of the Employer, the Engineer in Charge, the external controllers and the Contractor towards the quality of the Contract.

› The quality assurance plan to be prepared by the Contractor.

8.2 Standards and recommendations

The Contractor shall make sure that the quality control complies with the effective Indian

standards and take guidance from the following international standards:

ISO 9000 Quality Management Systems – Fundamentals and vocabulary. ISO 9001 Quality Management - Requirements.

Works 4: Remediation works of NMK-KIE Page 144

8.3 Quality Assurance procedure

The compilation of the quality assurance procedure will start when the Contractor submits the

Quality Assurance plan, not later than 21 days after the notice to commence the works.

The Contractor commits himself to the active participation in making the Quality Assurance

procedures of the different sub-contractors close to and harmonizing with one another during

the advancement of the design and performance of the works.

It is therefore required of that Contractor participates actively in the elaboration, and in

respect of this Quality Assurance procedures, relying on all his internal competencies in the

matter of Quality Control in the design phase, the implementation phase, understanding that

the Quality Assurance procedure is implemented with the purpose of improving an existing

system and not of substituting or doubling it.

The following people will participate in the meetings for the elaboration of the Quality

Assurance procedure: the Employer, the Engineer in Charge, external controllers, joint

enterprises, subcontractors and major suppliers and all physical or legal persons contributing

to the contract.

The first meeting will take place not later than 15 working days after the Engineer in Charge

receives the Quality Assurance plan from the Contractor.

8.4 Preparation of the Quality Assurance plan

On the basis of the organizational scheme of the Quality Assurance procedure, the Contractor

develops the Quality Assurance plan for this contract, which has to be submitted within 1

month after the signing of the Contract at the time of submission of initial design and drawings.

He has to write all arrangements of the Quality Assurance to be implemented by the

Contractor, the joint enterprises, the subcontractor enterprises and the suppliers in a simple

but exhaustive way.

He shall send it to the Employer, the Engineer in Charge and external controllers as well as all

contributors.

The Contractor makes the documents up-to-date (list of documents, indication of the revision

in course, nature of validation, etc.) in order and assures their traceability.

Finally, he will be responsible for keeping his quality assurance plan up-to-date in accordance

with the quality assurance procedure and the events of the contract.

The Quality Assurance plan should contain at least the following:

Works 4: Remediation works of NMK-KIE Page 145

a. The application range of the Quality Assurance plan

b. Organization and personnel means

The Quality Assurance plan specifies the general organization of the contract with the help of

the nominative organization charts, which should indicate especially the following:

› The elaboration meetings of the Quality Assurance procedure; › The contract progress meetings; › The organization of internal and external control; › It describes the functions, attributions and responsibilities of the personnel on the contract and of the external control responsible; and › It specifies the maximum percentage of the recourse of the temporary personnel.

c. Design control

The Quality Assurance plan especially indicates:

› The distribution of tasks among the sub-contractors; › The nature of documents to be submitted; › The procedures of identification of critical points and the stopping points of the concept; and › The procedures for check of design and documentation.

d. Document control - traceability

The Quality Assurance plan especially indicates:

› The rules for the identification of documents; › The rules for the circulation of the different documents produced; and › The methods for the management of documents (distribution, classification, archiving).

e. Purchases

The Quality Assurance plan especially indicates:

› Lists of suppliers and subcontractors and associated benefits. The Contractor supplies the list of envisaged suppliers and subcontractors as soon as possible; › The procedures of repercussion of the quality requirements of the Engineer in Charge over the suppliers and the subcontractors; and › The precise procedure of the evaluation of subcontractors.

f. Performance and test control

The Quality Assurance plan especially indicates:

› The list of documents and procedures written to define the modes of operation, the resources and the sequence of different activities; › The procedures for the establishment of a list of critical and stopping points of the performance, controls and tests; › The procedures for the internal delivery of subcontracted tasks;

Works 4: Remediation works of NMK-KIE Page 146

› The procedures for the control of products delivered; › The procedures for the controls and tests in course of the performance; › The procedures for final controls and tests before the reception by the representative of the Engineer in Charge; and › The procedures for the management of controlling documents (distribution, classification, archiving).

g. Control of non-compliance

The Quality Assurance plan indicates the procedures for identification, evaluation and

treatment of detected non-compliance.

h. Protection of the site equipment

The Quality Assurance plan indicates the procedures for establishing a list of equipment to be

protected and descriptions of measures to be applied.

i. Annexes

› Design planning; › Work planning; and › Directories of the sub-contractors.

8.5 Quality audits

The Engineer in Charge can at all times audit the Quality Assurance procedure of the

Contractor in the design or implementation phase.

The audit is performed with reference to the Quality Assurance plan of the Contractor and on

the basis of the Quality Assurance procedure.

The auditor establishes an audit report revealing the found gaps or non-compliance not later

than three weeks after the performance of the audit.

Within a period of 10 working days counted from the date of the reception of the report, the

Contractor indicates in writing the corrective actions he wishes to implement, their planning,

the name of the responsible of the control over these corrective actions.

9. Progress reports

9.1 Progress reports

The contractor shall forward progress reports to the Engineer in Charge at regular interval to

be determined by the Engineer in Charge.

9.2 Progress photographs

The Contractor shall periodically take photos that will show the works progress, to show works

that will be hidden later on and to support any claims etc. The photos shall be taken on his

Works 4: Remediation works of NMK-KIE Page 147

expense. The Contractor will provide the Engineer in Charge with 2 copies in 10x15 cm format

plus electronic form on CD-ROM in “jpeg” format. Each photo will be with date and coordinates

(GPS camera) and accompanied by a comment.

10. Safety procedures

The Contractor shall set-up a suitable temporary fence, during the performance of the

contract, in order to protect the site from public access, animal vagabondage etc. The

temporary fence is specified in Particular Specification. Clause 3.12.

The Contractor shall at all times in the conduct of his work and that of his Subcontractors

adhere to the established rules and regulations concerning all Health & Safety Protection

matters at the site.

During construction, the Contractor shall erect, maintain and subsequently remove sufficient

barricades, guards, lighting, sheeting, shoring, temporary sidewalks and bridges, danger signals

as well as temporary fencing and covering of potential accident areas.

Where work is to be carried out in the proximity of buildings, electrical poles or other

structures, the Contractor shall take all necessary precautions, including shoring and strutting,

where necessary, to ensure the safety of the structures that are at risk.

The Contractor shall be responsible for all damages or injury which may be caused on any

property by trespass by the Contractor's or his Subcontractor's employees in the course of

their employment, whether the said trespass was committed with or without the consent or

knowledge of the Contractor.

The health and safety of the community and Site workers during remediation Construction

activities are of primary concern. Health and safety practices to be implemented during

construction include preparation of a health and safety plan (HASP) and excavation plan. Each

contractor and subcontractor on Site will be responsible for the health and Safety of their own

employees during construction. A HASP will be developed by each contractor and

subcontractor that identifies anticipated Site hazards and required personal protective

equipment (PPE) and necessary First Aid Kits associated with each construction activity.

11. Existing services

The Contractor shall consult all relevant authorities and owners of services before commencing

any excavations and shall satisfy himself as to the exact position of existing services that affect

or may be affected by the works. If any service is found to exist, but is not as indicated in the

contract, then the Contractor shall at once give written notification to the Engineer in Charge.

The Contractor shall record the position of all located existing services on the site plan, a copy

of which shall be made available to the Engineer in Charge by the Contractor.

The Contractor shall execute the works in such a manner, that he does not damage or interfere

with existing services on the site. If damage or interference is so caused the Contractor shall

make his own arrangements to execute the repairs at his own cost, and to the approval of the

Engineer in Charge and the relevant authority.

Works 4: Remediation works of NMK-KIE Page 148

It shall be the Contractor's responsibility to safeguard by means of temporary or permanent

supports or otherwise all pipes, cables, structures and other things that would be liable to

suffer damage if such precautionary measures were not taken. This applies to all such items,

existing and proposed, owned by the Borrower or others.

The Contractor may in his design require making connections to existing pipe work.

Connections between existing pipe work and new pipe work shall not be made until the

necessary inspection and tests have been completed and the Engineer in Charge has approved

the new pipe work.

The Contractor shall arrange at his own cost the supply and distribution of electricity, potable

water, telephone, compressed air and other services as are necessary to his site establishment

and shall provide, maintain and remove on completion all pipes, cables and fittings which carry

such services to his operations. All electrical installations forming part of such temporary

installations shall comply with current Indian regulations.

The telephone and water supply connections to the site boundary will be paid and realized by

the Contractor.

The work in KIE includes activities near and under (power) lines crossing the industrial estate.

The contractor shall make sure that the owner of the (power) lines is informed and shall obtain

all necessary approval for work close to or underneath the (power) lines.

12. Contractor's designs, operation and maintenance manuals

Based on the Particular Specification and Drawings included in these tender dossiers, the

Contractor shall, at his own cost, prepare detailed designs including changes to the tender

drawings and complete specifications of materials and workmanship to such detail that not

only the works can be executed on site, but also that the Engineer in Charge can approve the

Contractor's designs and intentions for the execution of the works. In addition, it is the

responsibility of the Contractor to obtain all the necessary approvals, certificates and permits

from the relevant authorities.

For designs which the Contractor shall carry out the following will apply:

General Design Obligations

The Contractor shall carry out, and be responsible for design of permanent works as stated in

the Particular Specifications and for temporary buildings and structures as stated in the

Particular Specifications.

Design Error

If errors, omissions, ambiguities, inconsistencies, inadequacies or other defects are found in

the Contractor's documents, they and the Works shall be corrected at the Contractor's cost,

notwithstanding any consent or approval under this Clause.

The SI-system of units shall be used throughout the contract.

Works 4: Remediation works of NMK-KIE Page 149

All detailed designs shall comply with relevant Indian legislation, regulations, the

Environmental and Social Management Plan (ESMP) documents (appended to the tender

documents) and obtained construction permission .

The detailed designs, calculations and drawings, shall be collected in design reports.

The design reports, etc. shall be submitted in 4 copies. One copy shall be returned to the

Contractor with Engineer in Charge 's comments.

Drawings are to be submitted in time for incorporation of comments without delaying the time

schedule and the completion of the work.

The Engineer in Charge 's review of drawings and calculations etc. shall serve as a spot check

only to prove that the documents have been prepared in accordance with the tender

documents. The review shall not in any way relieve the Contractor of the responsibility for the

completed works being in accordance with the contract.

The Contractor shall design and propose one or more system(s) for numbering of:

› All documents and manuals; › All drawings; › All electrical and mechanical components; › All cables; and › All pipes.

The system(s) shall comprise easy identification of all numbered items, and it shall be easy to

see if drawings are made by the Contractor or one of his sub-contractors (if any).

The Engineer in Charge shall approve the numbering system(s), and all sub-contractors shall

use the approved numbering system(s).

12.1 As-built documents

The Contractor shall prepare and submit to the Engineer in Charge for approval before

completion, duly amended, 4 copies of the as-built documents in printed (A1) and digital (PDF

and DXF) format.These accurate record drawings shall be fully dimensioned to show the

locations, elevations, dimensions and other pertinent details of the work executed under this

contract. All drawings prepared by the Engineer in Charge will be delivered to the Contractor

on a CD in Auto-CAD version.

Within 10 days of receipt of the above drawings, the Engineer in Charge shall return to the

Contractor 2 copies of the drawings showing the amendments required by the Engineer in

Charge. Within 10 days of receipt of the amended drawings the Contractor shall issue to the

Engineer in Charge 6 copies and 1 negative of the amended drawings.

12.2 Operation and maintenance manuals

The operation and maintenance manuals mentioned in this chapter, refer to the constructed

Works and installations.

Works 4: Remediation works of NMK-KIE Page 150

The Contractor shall not later than fourteen (14) days before completion submit draft copies

(two (2) in English of the operation and maintenance manuals to the Engineer in Charge. The

manuals shall be bound into suitable durable loose-leaf binders of A4 size.

For all installations, the manuals shall include:

› A general part comprising contents, description of the installation and relevant addresses and phone numbers; › Documentation - as built; › Functional description; › List of components indicating manufacture, type, component numbers, ordering numbers, other data and position; › Maintenance instructions stating maintenance routines and intervals; › Fault finding instructions; › Calibration reports for analogue signal circuits; › Data leaflets; › List of spare parts; › List of tools; and › List of consumables; › For mechanical installations like pumps the manual shall further as a minimum include:

› Pump / Machinery type and serial no. (all in one chart); › Operating instructions; › Lubrication charts and maintenance instructions (all equipment included in one chart); › Fault finding details for rectification of basic faults; › List of spare parts giving part numbers in relation to a drawing preferably of the exploded view type. The list shall be appropriate for correct reordering of the complete component and its spare parts; › Brochures including all components accompanied with names and addresses of suppliers; › Performance curves, diagrams, test certificates etc.; › Specification of corrosion protection; and › Specifications for repair of all painted/coated surfaces.

For all electrical components the manual shall be divided into separate sections for the

following installations:

› Control panels; › Instruments; › Control and measuring components (signaling system); and › Other components.

The manual shall further elaborate on the electrical equipment including but not be limited to:

› CE-labelling and declaration of conformity; › Layout drawings; › Schematic and wiring diagrams;

Works 4: Remediation works of NMK-KIE Page 151

› Detailed description; › Specific operation instructions; › Specific maintenance instructions; › Component list for all equipment; › Fault-finding chart; and › Emergency procedures.

All information in the manuals shall apply specifically to the equipment being supplied, and

shall be free from such irrelevant matters as might be contained in the manufacturer's general

literature. Other types of machines and options not included in the contract are not allowed in

the instructions.

Immediately after completion, the suitable corrected manual shall be compiled into its final

form and be submitted to the Engineer in Charge for approval.

The final version of the operating and maintenance manual shall be submitted with four (4)

copies in English and four (4) copies in Telugu.

The taking over certificate will not be issued until all copies of the final instructions have been

handed over.

13. Site installations

13.1 Contractor's Plant

When working near settlements, the Contractor shall provide and use suitable and effective

silencing devices for pneumatic tools and other plant that would otherwise cause a noise level

exceeding 85 dB (A) during excavation and other work. Alternatively, he shall effectively isolate

the source of any such noise by means of barriers in order to comply with above requirement.

13.2 Water Supply

The Contractor shall make his own arrangements for the supply of all water for his camp,

equipment, office and other temporary buildings as well as for the execution of the Works.

Temporary water connection may be arranged by tanker delivery if necessary and no other

source is available. Water for drinking purposes shall be of drinking water quality and

adequately identified.

13.3 Sanitation

The Contractor shall maintain the Site and all working areas in adequate hygienic conditions. In

all matters of health and sanitation, he shall comply with the requirements of the local Medical

Officer of Health or other competent authority and the Health & Safety Protection measures.

The Contractor shall provide adequate changing, washing and showering and other sanitation

facilities.

Works 4: Remediation works of NMK-KIE Page 152

13.4 Sewage and Waste Disposal

The Contractor shall make provision for the discharge or disposal from his camp, offices, site

installations and the Works of all water as well as of all liquid and solid waste products

however arising. The methods of disposal shall be to the satisfaction of legal requirements and

to the Engineer in Charge and of any authority or person having an interest in any land or

watercourse over or in which water and waste products may be so discharged.

13.5 Pollution

The Contractor shall take all reasonable measures to minimize any dust nuisance, pollution of

streams and inconvenience to or interference with the public (or others) as result of his site

installations.

13.6 Energy Supply

The Contractor shall install, operate, maintain and subsequently remove temporary supplies of

electricity for power, heating, cooling, lighting and ventilation of all camps, offices, stores,

laboratories and other temporary buildings used by the Contractor in addition to all electricity

requirements in connection with the construction, testing and maintenance of the Works.

The Contractor shall ensure that all proposed electrical installations comply with the

requirements of the responsible electricity authority, shall be responsible for and shall bear all

costs associated with obtaining the written approval of that authority for such connections,

installations and their operations. Prior to placing orders for transformers, conductors, cables

and associated equipment, the Contractor shall ensure by enquiry with the electricity authority

that his proposed equipment is suitable for use with the existing or proposed medium / high

tension electricity supply lines.

The Contractor may use own electric power generator for energy supply.

13.7 Supply of Fuel,Lubricants,etc.

The Contractor shall be responsible for arranging and ensuring that adequate supplies of

petrol, diesel oil, motor oil, kerosene, lubricants and other petroleum products are available at

all times to meet his requirements for the purpose of or in connection with the Contract.

He shall make his own arrangements for the supply of all other types of fuel required for the

purposes of the Contract.

With regard to the transportation, storage and handling of all his fuel requirements, including

all electrical connections, he must strictly comply with all relevant safety codes and regulations.

13.8 TemporaryTelephoneConnections

The Contractor shall arrange at his own cost for temporary telephone connections to his offices

and other installations. He shall be responsible for all installations, connection and disconnects

charges for his and his Representative's offices.

Works 4: Remediation works of NMK-KIE Page 153

14. Health and safety

All works shall be carried out strictly in accordance with current Indian health & safety

legislation and the legislation of India DNSAS 18001 Standard. Special emphasize shall be on

work in potentially contaminated material, sewage drains and for work close to and

underneath power lines.

14.1 First Aid

The Contractor shall make his own arrangements for treatment of casualties on the Site in such

first-aid units as required by Indian legislation. The Contractor shall be responsible for the

construction of such first-aid units and their management and operation and the removal by

ambulance of injured or sick employees to nearby hospitals. The first-aid service shall cover the

Contractor's own personnel as well as that of the Employer, the Engineer in Charge and all

Subcontractors. Trained and certified first-aiders are to be on the site at all times, at a rate of

one certified First Aider per 20 staff on site and equipped with adequate First Aid kits.

14.2 Fire Protection

No naked fire shall be used by the Contractor on or about the Site otherwise than in the open

air without the permission in writing of the Engineer in Charge. If in the Engineer in Charge's

opinion the use of naked fire may cause a fire hazard, the Contractor shall at no extra cost to

the Employer take such additional precautions and provide such additional firefighting

equipment as the Engineer in Charge considers necessary.

The term "naked fire" shall be deemed to include electric arcs and oxyacetylene or other

flames used in welding or cutting metals.

Compliance with the requirements of the Engineer in Charge shall not relieve the Contractor of

any of his obligations under the Contract.

15. Inspection, testing and taking over

15.1 General

The Contractor’s Quality Assurance system shall include procedures for carrying out inspection

and testing of the works both on and off site during the design and construction phase. The

Contractor’s project plan shall include a program for completing such inspections and tests in a

coordinated manner and in accordance with the requirements of the contract.

The Contractor shall provide all labour, plant, materials and services required for testing and

inspecting the works.

The Contractor shall submit to the Engineer in Charge full details of inspections and tests to be

carried out at least 21 days in advance. Attendance at and acceptance of tests and inspections

of the works shall not prejudice the right of the Engineer in Charge to reject any part of the

works if it subsequently fails to comply with the requirements of the contract.

Works 4: Remediation works of NMK-KIE Page 154

The Contractor shall keep a record of all tests and inspections, irrespective of whether or not

they show compliance with the contract and shall issue this record to the Engineer in Charge

on completion of each test and inspection.

15.2 Programme

The Contractor shall submit revised Program (Construction Program).

15.3 Damage to Public and Private Service Installations

Notify the Consultant and Engineer in Charge in writing of any damage to public or private

services and where applicable, notify the service authorities and/or private owners. Make

arrangements for repair to the satisfaction of the Consultant and Engineer in Charge and,

where applicable, the appropriate authorities and owners. Accept any arrangements made by

the Consultant and Engineer in Charge for urgent repairs which will not affect liability

15.4 Employer's taking over

This section specifies the procedure for completion before taking over the remediated sites

and containment cells. For Hand Over of the sites and containment cells to Employer after the

Operation and Maintenance of the remediated sites and containment cells, see Chapter 9.4.

Once the Contractor is satisfied that the necessary tests, to demonstrate compliance with the

Works Requirements, have been completed he shall submit a final test report to the Engineer

in Charge summarizing the test results. This report shall be accompanied by:

› A statement from the Contractor that, in his opinion, the works have passed the tests;

› Obtained licenses and approvals from the Authorities; and

› An application for a taking-over certificate.

The issuing of the taking-over certificate by the Employer will, in addition, take place after the

following demands have been fulfilled to the satisfaction of the Engineer in Charge:

› The operation and maintenance manual has been handed-over to the Engineer in Charge in its final version;

› The as-built drawings have been handed-over to the Borrower;

› All works has been tested on-site for all functions and performance by the Contractor to the satisfaction of the Engineer in Charge, and documented in the Quality Assurance and test report; and the Quality Assurance and test report have been handed-over to the Engineer in Charge.

Works 4: Remediation works of NMK-KIE Page 155

16. Supervision and Monitoring Plan

The general requirements of the supervision and monitoring have been described in the

document “Environmental and Social Management Plan” and is part of this tender. The general

objective of the “Environmental and Social Management Plan” is to describe the measures that

are required to ensure a situation that is stable and acceptable from an environmental, health

and safety perspective. This applies to both the construction phase and the finalized state of

the site. The supervision and monitoring include:

- Environmental management plan to mitigate adverse effects from happening and reduce possible risks during construction - Environmental management plan to mitigate adverse effects from happening and reduce possible risks after construction. Based on the general requirements for monitoring and supervision as presented in the

“Environmental and Social Management Plan” the specifications for those activities have been

presented in the Figures 1 and Tables 1 and 2. Figure 1 presents a map with the proposed

position of the monitoring points. Table 1 presents details and objectives of the different

monitoring activities. Table 2 presents the frequency of the monitoring activities before, during

and after project implementation.

In addition the Contractor has to monitor the ambient air quality. Monitoring points at

residential areas around the remediation site and at three points, upwind, downwind, and

cross wind directions of the remediation site (to measure baseline air quality as per NAAQS

Standards). Monitoring has to be carried out quarterly.

The Contractor shall follow aforementioned specifications and based on Figure 1 and the info

presented in Tables 1 and 2 prepare Contractors Environmental Management Plan.

The Contractor shall follow the Environmental Management Plan the first 2 years after hand-

over.

Works 4: Remediation works of NMK-KIE Page 156

Figure 1 Map with monitoring points

Works 4: Remediation works of NMK-KIE Page 157

Works 4: Remediation works of NMK-KIE Page 158

Table 2 Monitoring detail

Works 4: Remediation works of NMK-KIE Page 159

Zone

Legenda

Point

Type of monitoring point Position of monitoring point Objective Sediment Soil Water Air Others

Plains

1 Sediment Survey and Sampling

Sediments in Pushparahil Cheruvu, 4 composite samples from the quadrants of the lake

To assess thickness, volume and quality sediments in Pushparahil Cheruvu

TPH and heavy metals

2 Surface Water Sampling Point

Surface water at culvert in the discharge channel

To assess water level, discharge volume and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

3 Surface Water Sampling Point

Surface water at outlet of NMK Lake

To asses water level, discharge volume en ad quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

4 Ground Water Monitoring Well

Groundwater between about 5 and 10 meter depth To assess level and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

5 Ground Water Monitoring Well

Groundwater between about 5 and 10 meter depth To assess level and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

6 Ground Water Monitoring Well

Groundwater between about 5 and 10 meter depth To assess level and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

R Visual and Odour Observations

All roads in the area along which sediments and soil are transported

To assess impact of transport on the environment

Presence of odour

Presence of dirt and dust

NMK Lake

L Surface Water Sampling Point At 4 positions in the Lake To assess water quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

Ground Water Monitoring Well

At 4 positions in the Lake, about 2 till 4 meter below FTL

To assess water quality and groundwater levels

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

Survey Sediment

Total area of the lake, continuous measurement

To assess thickness and volume of the sediments

Clay Layer

Total area of the lake, continuous measurement

To assess position of the top of the clay layer

Cover Layer

Total area of the lake, continuous measurement

To assess integrity (thickness and presence) of the cover layer

1 Ground Water Monitoring Well

Groundwater between about 4 and 7 meters depth To assess level and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

Visual Observation

Continuous along entire inner and outer slope as well as the crest of the bund

To identify signs of visual deformation

To identify depresions, cracks, etc..

Visual Observation

Continuous along entire outer slope of the bund

To identifty changes in the drainage pattern

To identify variations in

Works 4: Remediation works of NMK-KIE Page 160

Zone

Legenda

Point

Type of monitoring point Position of monitoring point Objective Sediment Soil Water Air Others

intensity and level of drainage

2 Ground Water Monitoring Well

Groundwater between about 4 and 7 meters depth To assess level and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

3 Ground Water Monitoring Well

Groundwater between about 4 and 7 meters depth To assess level and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

4 Ground Water Monitoring Well

Groundwater between about 4 and 7 meters depth To assess level and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

5 Ground Water Monitoring Well

Groundwater between about 4 and 7 meters depth To assess level and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

1 Soil Investigation

Topsoil (0-0.5 meter below ground level) and subsoil (0.5-2.0 meter below ground level)

To assess basline quality of the soil at the projected office and work space of the Contractor with 4 composite soil samples

TPH, heavy metals, PAH and BTEX

Ground Water Monitoring Well

Groundwater between about 2 and 5 meters depth

To assess level and quality in 2 wells

TPH, heavy metals, PAH and BTEX

1

Top Soil Investigation and Sampling

Topsoil (0-0.5 meter below ground level) and subsoil (0.5-2.0 meter below ground level)

To assess basline quality of the soil at the projected office and work space of the Contractor with 4 composite soil samples

TPH, heavy metals, PAH and BTEX

Ground Water Monitoring Well

Groundwater between about 2 and 5 meters depth

To assess level and quality in 2 wells

TPH, heavy metals, PAH and BTEX

Visual and Odour Observations

Around the perimeter of the containment cell

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

Cover Layer Top containment cell

To assess integrity (thickness and presence) of the cover layer

2

Top Soil Investigation and Sampling

Topsoil (0-0.5 meter below ground level) and subsoil (0.5-2.0 meter below ground level)

To assess basline quality of the soil at the projected office and work space of the Contractor with 4 composite soil samples

TPH, heavy metals, PAH and BTEX

TPH, heavy metals, PAH and BTEX

Ground Water Groundwater between about 2 To assess level and quality in

Works 4: Remediation works of NMK-KIE Page 161

Zone

Legenda

Point

Type of monitoring point Position of monitoring point Objective Sediment Soil Water Air Others Monitoring Well and 5 meters depth 2 wells

Visual and Odour Observations

Around the perimeter of the containment cell

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

Cover Layer Top containment cell

To assess integrity (thickness and presence) of the cover layer

3

Top Soil Investigation and Sampling

Topsoil (0-0.5 meter below ground level) and subsoil (0.5-2.0 meter below ground level)

To assess basline quality of the soil at the projected office and work space of the Contractor with 4 composite soil samples

TPH, heavy metals, PAH and BTEX

TPH, heavy metals, PAH and BTEX

Ground Water Monitoring Well

Groundwater between about 2 and 5 meters depth

To assess level and quality in 2 wells

Visual and Odour Observations

Around the perimeter of the containment cell

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

Cover Layer Top containment cell

To assess integrity (thickness and presence) of the cover layer

4

Top Soil Investigation and Sampling

Topsoil (0-0.5 meter below ground level) and subsoil (0.5-2.0 meter below ground level)

To assess basline quality of the soil at the projected office and work space of the Contractor with 4 composite soil samples

TPH, heavy metals, PAH and BTEX

TPH, heavy metals, PAH and BTEX

Ground Water Monitoring Well

Groundwater between about 2 and 5 meters depth

To assess level and quality in 2 wells

Visual and Odour Observations

Around the perimeter of the containment cell

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

Cover Layer Top containment cell

To assess integrity (thickness and presence) of the cover layer

5

Top Soil Investigation and Sampling

Topsoil (0-0.5 meter below ground level) and subsoil (0.5-2.0 meter below ground level)

To assess basline quality of the soil at the projected office and work space of the Contractor with 4 composite soil samples

TPH, heavy metals, PAH and BTEX

TPH, heavy metals, PAH and BTEX

Ground Water Monitoring Well

Groundwater between about 2 and 5 meters depth

To assess level and quality in 2 wells

Visual and Odour Observations

Around the perimeter of the containment cell

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

Cover Layer Top containment cell

To assess integrity (thickness and presence) of the cover layer

Works 4: Remediation works of NMK-KIE Page 162

Zone

Legenda

Point

Type of monitoring point Position of monitoring point Objective Sediment Soil Water Air Others

KIE

1 Ground Water Monitoring Well

Groundwater between about 5 and 10 meters depth and about 20 and 25 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

2 Ground Water Monitoring Well

Groundwater between about 5 and 10 meters depth and about 20 and 25 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

3 Ground Water Monitoring Well

Groundwater between about 5 and 10 meters depth and about 20 and 25 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

4 Ground Water Monitoring Well

Groundwater between about 5 and 10 meters depth and about 20 and 25 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

5 Ground Water Monitoring Well

Groundwater between about 5 and 10 meters depth and about 20 and 25 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

6 Ground Water Monitoring Well

Groundwater between about 15 and 20 meters depth and about 40 and 45 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

7 Ground Water Monitoring Well

Groundwater between about 15 and 20 meters depth and about 40 and 45 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

8 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

9 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

10 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

1 Sediment Investigation

Accumulated sediments in the pond

To assess thickness, volume and quality of accumulated sediments in

TPH and heavy metals

Works 4: Remediation works of NMK-KIE Page 163

Zone

Legenda

Point

Type of monitoring point Position of monitoring point Objective Sediment Soil Water Air Others

the pond

Surface Water Sampling Point Surface water in the pond

To assess volume, waterflow and water quality

TPH, heavy metals, COD, BOD, pH, Ec, particular matter, odour and colour

Visual and Odour Observations

Around the perimeter of the pond

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

2 Sediment Investigation

Accumulated sediments in the pond

To assess thickness, volume and quality of accumulated sediments in the pond

TPH and heavy metals

Surface Water Sampling Point Surface water in the pond

To assess volume, waterflow and water quality

TPH, heavy metals, COD, BOD, pH, Ec, particular matter, odour and colour

Visual and Odour Observations

Around the perimeter of the pond

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

3 Sediment Investigation

Accumulated sediments in the pond

To assess thickness, volume and quality of accumulated sediments in the pond

TPH and heavy metals

Surface Water Sampling Point Surface water in the pond

To assess volume, waterflow and water quality

TPH, heavy metals, COD, BOD, pH, Ec, particular matter, odour and colour

Visual and Odour Observations

Around the perimeter of the pond

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

4 Sediment Investigation

Accumulated sediments in the pond

To assess thickness, volume and quality of accumulated sediments in the pond

TPH and heavy metals

Surface Water Sampling Point Surface water in the pond

To assess volume, waterflow and water quality

TPH, heavy metals, COD, BOD, pH, Ec, particular matter, odour and colour

Visual and Odour Observations

Around the perimeter of the pond

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

1 Drain Water Sampling Point

Water in the drain at the selected monitoring point

To assess water level, discharge volume and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

Visual Observation

Reaccumulated sediment in the drains

To assess thickness, volume and quality of accumulated sediments in the drains

TPH and heavy metals

2 Drain Water Sampling Point

Water in the drain at the selected monitoring point

To assess water level, discharge volume and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

Visual Observation

Reaccumulated sediment in the drains

To assess thickness, volume and quality of accumulated sediments in the drains

TPH and heavy metals

Works 4: Remediation works of NMK-KIE Page 164

Zone

Legenda

Point

Type of monitoring point Position of monitoring point Objective Sediment Soil Water Air Others

3 Drain Water Sampling Point

Water in the drain at the selected monitoring point

To assess water level, discharge volume and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

Visual Observation

Reaccumulated sediment in the drains

To assess thickness, volume and quality of accumulated sediments in the drains

TPH and heavy metals

4 Drain Water Sampling Point

Water in the drain at the selected monitoring point

To assess water level, discharge volume and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

Visual Observation

Reaccumulated sediment in the drains

To assess thickness, volume and quality of accumulated sediments in the drains

TPH and heavy metals

5 Drain Water Sampling Point

Water in the drain at the selected monitoring point

To assess water level, discharge volume and quality

TPH, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour and colour

Visual Observation

Reaccumulated sediment in the drains

To assess thickness, volume and quality of accumulated sediments in the drains

TPH and heavy metals

1 Waste Inventory All spots and sources of waste in the open hill lock area

To identify, quantify and characterise all waste present within the open hill lock area

Visual and Odour Observations

Around the perimeter of the open hill lock area

To assess the impact of the works on the air quality

Presence of odour

Presence of dust

Soil Investigation Topsoil sampling

To assess the general top soil quality in the open hill lock area after wastes has been removed (10 composite samples)

TPH, PAH, heavy metals

S Soil Investigation Topsoil sampling (about 15 samples)

To horizontally delineate and characterise the source of soil pollution in the first 2 meters below ground surface

TPH, volatile organics, organic matter, clay and sand fractions, odour, colour and natural attenuation/biodegradation parameters

Works 4: Remediation works of NMK-KIE Page 165

Zone

Legenda

Point

Type of monitoring point Position of monitoring point Objective Sediment Soil Water Air Others

Soil Investigation

Subsoil sampling (about 15 samples)

To vertically delineate and characterise the source of soil pollution between 2 meters below surface and the first water bearing horizon

TPH, volatile organics, organic matter, clay and sand fractions, odour, colour and natural attenuation/biodegradation parameters

Ground Water Monitoring Well

Groundwater between about 10 and 15 meters depth in 5 monitoring wells

To horizontally delineate and characterise the source of ground water pollution in the phreatic or first water bearing horizon

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

Ground Water Monitoring Well

Groundwater between about 15 and 70 meters depth in 5 monitoring wells

To vertically delineate and characterise the source of ground water pollution in different water bearing horizons, including a geohydrological characterisation

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

1 Ground Water Monitoring Well

Groundwater between about 15 and 20 meters depth and about 40 and 45 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

2 Ground Water Monitoring Well

Groundwater between about 15 and 20 meters depth and about 40 and 45 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

3 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

4 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec,

Works 4: Remediation works of NMK-KIE Page 166

Zone

Legenda

Point

Type of monitoring point Position of monitoring point Objective Sediment Soil Water Air Others

about 50 and 60 meter depth salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

5 Ground Water Monitoring Well

Groundwater between about 15 and 20 meters depth and about 40 and 45 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

6 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

7 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

8 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

9 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

10 Ground Water Monitoring Well

Groundwater between about 20 and 25 meters depth and about 50 and 60 meter depth

To assess level and quality at 2 depths

TPH, volatile organics, heavy metals, COD, BOD, pH, Ec, salinity, particular matter, odour, colour and natural attenuation/biodegradation parameters

Works 4: Remediation works of NMK-KIE Page 167

Table 3 Frequency of monitoring

Zone Legenda Point Type of monitoring point Baseline Investigation Project Implementation After project implementation Plains

1 Sediment Survey and Sampling yes yes, at the end of project implementation yes, once after 5 years

2 Surface Water Sampling Point yes

yes, levels every day, analysis every week during dredging and filling of tubes of geotextile yes, every 3 months

3 Surface Water Sampling Point yes

yes, levels every day, analysis every week during dredging and filling of tubes of geotextile

yes, every 3 months

4 Ground Water Monitoring Well

yes + installation of well no once a year

5 Ground Water Monitoring Well

yes + installation of well no once a year

6 Ground Water Monitoring Well

yes + installation of well no once a year

R Visual and Odour Observations no on a daily basis

no

NMK Lake

L Surface Water Sampling Point yes

yes, every week during dredging and filling of tubes of geotextile

yes, every 3 months

Ground Water Monitoring Well

yes + installation of wells yes, levels every day and analysis every 3 months

levels every 3 months, analysis once per 3 months

Survey Sediment yes yes, once after dredging is completed

yes, once after 5 years

Clay Layer yes yes, once after dredging is completed

no

Cover Layer no yes, once after it has been applied

every year

1 Ground Water Monitoring Well

yes + installation of well yes, levels every day, analysis every month

levels every 3 months, analysis every year

Visual Observation baseline observation on a daily basis

every 3 months

Visual Observation baseline observation on a daily basis

every 3 months

2 Ground Water Monitoring Well

yes + installation of well yes, levels every day, analysis every month

levels every 3 months, analysis every year

3 Ground Water Monitoring Well

yes + installation of well yes, levels every day, analysis every month

levels every 3 months, analysis every year

4 Ground Water Monitoring Well

yes + installation of well yes, levels every day, analysis every month

levels every 3 months, analysis every year

5 Ground Water Monitoring Well

yes + installation of well yes, levels every day, analysis every month

levels every 3 months, analysis every year

6 Ground Water Monitoring Well

yes + installation of well yes, levels every day, analysis every month

levels every 3 months, analysis every year

1 Soil Investigation yes no

yes, after contractor has abondened the area

Ground Water Monitoring Well

yes + installation of well yes, every month

yes, after contractor has abondened the area

Works 4: Remediation works of NMK-KIE Page 168

Zone Legenda Point Type of monitoring point Baseline Investigation Project Implementation After project implementation

1 Top Soil Investigation and Sampling yes no

no

Ground Water Monitoring Well

yes + installation of well yes, every month

once a year

Visual and Odour Observations baseline observations yes on a daily basis

no

Cover Layer no no

yes, every 3 months

2 Top Soil Investigation and Sampling yes no

no

Ground Water Monitoring Well

yes + installation of well yes, every month

once a year

Visual and Odour Observations baseline observations yes on a daily basis

no

Cover Layer no no

yes, every 3 months

3

Top Soil Investigation and Sampling yes no

no

Ground Water Monitoring Well

yes + installation of well yes, every month

once a year

Visual and Odour Observations baseline observations yes on a daily basis

no

Cover Layer no no

yes, every 3 months

4

Top Soil Investigation and Sampling yes no

no

Ground Water Monitoring Well

yes + installation of well yes, every month

once a year

Visual and Odour Observations baseline observations yes on a daily basis

no

Cover Layer no no

yes, every 3 months

5 Top Soil Investigation and Sampling yes no

no

Ground Water Monitoring Well

yes + installation of well yes, every month

once a year

Visual and Odour Observations baseline observations yes on a daily basis

no

Cover Layer no no

yes, every 3 months

KIE

1 Ground Water Monitoring Well

yes + installation of well no

once a year

2 Ground Water Monitoring Well

yes + installation of well no

once a year

3 Ground Water Monitoring Well

yes + installation of well no

once a year

4 Ground Water Monitoring Well

yes + installation of well no

once a year

Works 4: Remediation works of NMK-KIE Page 169

Zone Legenda Point Type of monitoring point Baseline Investigation Project Implementation After project implementation KIE

5 Ground Water Monitoring Well

yes + installation of well no

once a year

6 Ground Water Monitoring Well

yes + installation of well no

once a year

7 Ground Water Monitoring Well

yes + installation of well no

once a year

8 Ground Water Monitoring Well

yes + installation of well no

once a year

9 Ground Water Monitoring Well

yes + installation of well no

once a year

10 Ground Water Monitoring Well

yes + installation of well no

once a year

1 Sediment Investigation no no yes, once a year

Surface Water Sampling Point no no

yes, 2 times a year

Visual and Odour Observations no yes on daily basis

no

2 Sediment Investigation no no yes, once a year

Surface Water Sampling Point no no

yes, 2 times a year

Visual and Odour Observations no yes on daily basis

no

3 Sediment Investigation no no yes, once a year

Surface Water Sampling Point no no

yes, 2 times a year

Visual and Odour Observations no yes on daily basis

no

4 Sediment Investigation no no yes, once a year

Surface Water Sampling Point no no

yes, 2 times a year

Visual and Odour Observations no yes on daily basis

no

1 Drain Water Sampling Point no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

Visual Observation no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

2 Drain Water Sampling Point no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

Visual Observation no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

3 Drain Water Sampling Point no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

Visual Observation no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

Works 4: Remediation works of NMK-KIE Page 170

Zone Legenda Point Type of monitoring point Baseline Investigation Project Implementation After project implementation

4 Drain Water Sampling Point no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

Visual Observation no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

5 Drain Water Sampling Point no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

Visual Observation no yes, 2 times a month during drain clean-up

yes, 2 times a year after drain clean-up has been implemented

1 Waste Inventory yes no

no

Visual and Odour Observations base line observation daily observations

no

Soil Investigation no

yes after waste has been removed and before area starts to be used as a work space for the Contractor

yes once, after Contractor has abondened the area

S Soil Investigation yes no

no

Soil Investigation yes no

no

Ground Water Monitoring Well

yes + installation of well no

once a year

Ground Water Monitoring Well

yes + installation of well no

once a year

1 Ground Water Monitoring Well

yes + installation of well no once a year

2 Ground Water Monitoring Well

yes + installation of well no once a year

3 Ground Water Monitoring Well

yes + installation of well no once a year

4 Ground Water Monitoring Well

yes + installation of well no once a year

5 Ground Water Monitoring Well

yes + installation of well no once a year

6 Ground Water Monitoring Well

yes + installation of well no once a year

7 Ground Water Monitoring Well

yes + installation of well no once a year

8 Ground Water Monitoring Well

yes + installation of well no once a year

9 Ground Water Monitoring Well

yes + installation of well no once a year

10 Ground Water Monitoring Well

yes + installation of well no once a year

Works 4: Remediation works of NMK-KIE Page 171

17. References

The following guidelines and reference shall be referred / followed to by the Contractor for

execution of the project:

› Telangana Pollution Control Board – TSPCB. Final Site Assessment Report.

› Telangana Pollution Control Board – TSPCB. Remediation Plan.

› Telangana Pollution Control Board – TSPCB. Environmental and Social Baseline Report.

› Telangana Pollution Control Board – TSPCB. Environmental and Social Management Plan

› Guidelines and Check-list for evaluation of MSW Landfills proposals with Information on existing landfills. Program Objective Series: Probes/124/2008-2009. August 2008.

› MSW Rules 2000

› HWM Rules 2008

› Bio-Medical Wastes (Management & Handling) Rules, 1998.

› Indian Standard (I.S) References List: Applicable for Landfill Closure:

› IS 1200 (Part 22) - 1988 Method of Measurement of Building and Civil Engineering works - Part 22 - Materials

› IS 11134 - 1984 Code of practice for Setting out of Buildings

› IS 875 (Part 1) - 1987 Code of practice for Design Loads (other than Earthquake) for Buildings and Structure

› IS 269 Specification for 33 grade ordinary Portland Cement

› IS 12269 Specification for 53 grade ordinary Portland Cement

› IS 383 Specification for coarse and fine aggregate from Natural Source for Concrete

› IS 456 Code of practice for plain and reinforced concrete

› IS 516 Method of test for strength of concrete

› IS 1199 Method of sampling and analysis of concrete

› IS 1200 (Part II) Method of Measurement of Building and Civil Engineering work (concrete work)

Works 4: Remediation works of NMK-KIE Page 172

› IS 1322 Specification for bitumen felt for water proofing and damp proofing

› IS 1791 Specification for batch type concrete mixers

› IS 226 Structural Steel

› IS 456 - 2000 Aggregate and Admixtures concreting

› IS 516 Method of test for strength of concrete

› IS : 1200 (Part V) Method of measurement of building and civil engineering work - concrete work (Part 5 - Form work)

› IS : 10262 Recommended guidelines for concrete mix design

› IS 226-1975 Structural steel (Standard quality) (5th Revision) superseded by IS : 2062:1992

› IS 800-1984 Code of practice for use of structural steel in general in steel construction

› IS 1077-1992 Common Clay Bricks

› IS 2212-1991 Brick Work

› IS 5454-1978 Method of Sampling of Bricks

› IS 3495-1976 Test for Clay Building Bricks

› IS 1200-1976 Method of Measurement

› IS 73-1992 Specification of paving bitumen (2nd revision)

› IS 5317-1987 Specification for bitumen mastic for bridges decking and roads (1st revision) (Reaffirmed 1991)

› IS 5640-1970 Method of test for determining aggregate impact value of soft coarse aggregates (Reaffirmed 1993)

› List of IRC Standard Codes

› 215-1995 Types of Bitumen / Road Tar

› 6241-1971 Testing Road Materials / Method of Test for determination of stripping value of road aggregates

Works 4: Remediation works of NMK-KIE Page 173

› 1201 to 1220-1978 Testing Road Materials / Method of testing Tar and Bituminous Materials

› 5890-1970 Black Topping Machinery / Mobile Hot Mix Asphalt Mixing Plants

› 3251 (part I) 1965 Black Topping Machinery / Asphalt Paver Finishers

› 3251 (part 2) – 1992 Black Topping Machinery / Asphalt Paver Finisher-

› 4919-1981 Glossary of terms Applicable to Landscape of Horticulture works

› 11272-1985 Glossary of terms relating to Horticulture Equipment

› 4984-1987 Specification for high density polyethylene pipes for potable water supplies, sewage and industrial effluents (3rd revision)

› IS 4984 and IS 14333: HDPE Pipes Code

18. Applicable Environmental Performance Standards

(A) Applicable Environmental Standards during the remediation works.

No process water or polluted pore water from the site should flow outside the site boundary without treatment.

No MSW, HWM or biomedical waste constituents should be blown by wind outside the site boundary.

No surface run-off from the site should flow out outside the site boundary

No fire incidence or smoke emission from the side should occur.

No MSW, HWM or biomedical waste should be observed floating/deposited outside the project area that can be attributed to site operations after completion of mobilization period.

At no stage of remediation operations from the date of mobilization the night time noise levels at the boundary of (except for the side of the main road and up to distance of 50 m on branch roads) should exceed the noise standards for residential area.

The air pollution level should not exceed the ambient air quality standard after completion of the remediation works.

(B) Applicable Environmental Standards during the maintenance operations.

Works 4: Remediation works of NMK-KIE Page 174

Ground and surface water quality in the monitoring wells and monitoring points with respect to BOD, heavy metals and organics must not exceed 25% of the baseline value in any of the ground water monitoring wells. The Contractor shall analyze the baseline BOD, heavy metals and organics at the commencement of the Work.

There should not be any perceptible change (statistically significant) over the mean value of baseline conditions with respect to color and TDS/electrical conductivity in ground water monitoring wells and surface water monitoring points.

Odour - No foul odour should be discernable at the boundary of the site towards the inhabitations.

The air pollution level at the site should not exceed the ambient air quality standard.

Process water and Surface Water Flow - No Process Water flow should take place from the site into the surroundings onto the ground.

No run-off from the site should occur outside the boundary.

Measures as per the Environmental Management Plan - In addition to (A) and (B) above the

contractor will be required to comply with the environmental management plan and

environmental monitoring plans.

19. Applicable Testing

19.1 Setting Of Field Laboratory by the Contractor

The Contractor shall set up a field laboratory of his own at the work site which should be open

for use and inspection by Employer’s representative at any time. Alternately the contractor is

allowed to transfer samples to an accredited local off site laboratory for testing and have the

sample analysed within 24 hours or sooner if the nature of the particular work requires this.

Engineer in Charge shall inspect the field laboratory upon setting up (and periodically

thereafter) and verify the adequacy and accuracy of all equipment thereof.

All the pressure gauges and other measuring equipment of the laboratory shall be checked and

calibrated regularly as directed by the Engineer in Charge by an agency and the Test

certificates shall be furnished to the Engineer in Charge.

Works 4: Remediation works of NMK-KIE Page 175

The Contractor shall render all reasonable assistance and help in making such checks and tests.

The cost of all checks and calibrations shall be borne by the Contractor. The cost of all tests for

materials shall also be borne by the Contractor.

19.2 Testing

For all sampling and testing the contractor has to prepare and implement a QA/QC plan,

including procedures for calibraton of the testing equipment.

If Engineer in Charge requires tests, the Contractor shall carry out such tests in accordance

with the specifications, TOR, BOQ and conditions of the contract. The Contractor shall provide

all documents and other information necessary for testing and such assistance, labour,

materials, electricity, fuel, stores, apparatus and instruments as are necessary to carry out such

tests efficiently. The Contractor shall provide such engineering support and technical know-

how as Engineer in charge shall reasonably request for the purpose of the tests.

If the tests required are elaborate and require prior setting up of equipment or instruments,

the Contractor shall agree, with Engineer in Charge and Engineer’s Representative, the time

and place for the testing. Engineer in Charge shall give the Contractor not less than 24 hours'

notice of his intention to attend such tests. The Contractor shall provide sufficient suitably

qualified and experienced staff to carry out such tests.

The Contractor shall promptly forward to Engineer in charge duly certified reports of the tests.

When the specified tests have been passed, Engineer in Charge shall endorse the Contractor's

test certificate, or issue a confirmation to him, to that effect.

Employer is entitled to insist for the Contractor to carry out any tests of any type, as it deems

fit. If such test is not in accordance with specifications or Prudent Utility Practices, then

Employer shall bear the cost of such tests. Except that if the Materials or Works fail such tests,

the cost of the test shall be borne by the Contractor, and the Contractor shall also rectify the

Materials or Works at his cost. The tests shall include checking of construction records,

documents and drawings, trial runs, checks of profiles and levels, borings and cores or any

other tests that may be reasonably necessary to confirm that the works meet the

specifications.

Works 4: Remediation works of NMK-KIE Page 176

19.3 Measurements

Any provisions of measurement referred to in this Contract will be applicable for the

assessment of quantum of work done for payment of works executed. All such assessments

shall be based on measurements duly entered in measurement books. All items of work shall

be entered in a measurement book, level book, etc., as

prescribed by Engineer in Charge so that a complete record of the entire Works under this

Contract shall be established.

Measurements shall be signed and dated by both Parties on the Site on completion of

measurement forthwith. The original measurement books shall be kept in the custody of

Engineer in Charge. All payments under this Contract shall require to be supported by

measurements for assessing quantum of work, adherence to specifications, and achievement

of Project milestones.

Measurements shall be taken jointly by Engineer in Charge or his assistant and by the

Contractor or his authorised representative. Before taking measurements of any work

Engineer in Charge or his assistant shall give reasonable notice of the date of measurement to

the Contractor.

If the Contractor fails to attend or send an authorised representative for measurement on the

notified date, or being present fails to countersign, Engineer in Charge shall record such

absence or failure to countersign, and take measurements ex-parte.

The Contractor can inspect the measurement books available with Engineer in Charge, and if

the Contractor fails to countersign or record the objection within a week from the date of

measurement, then in any such event, measurements taken by Engineer in Charge or his

assistant shall be taken to be correct measurements of the work and shall be binding and

conclusive on the Contractor.

The Contractor shall, without any extra charge, provide assistance with every appliance,

instruments and supporting tests and any other things necessary for

measurements and certification.

Works 4: Remediation works of NMK-KIE Page 177

19.4 Test Certificates

All manufacturers certificates of tests, proof sheets, mill sheets etc. showing that the materials

have been tested in accordance with the requirements of the appropriate Indian Standard,

other relevant Standard Specification or these specifications shall be supplied free of charge on

request to the Engineer in Charge or his representatives. Such details shall be submitted with

every new batch of materials used at site.

Samples of the following materials shall be submitted to the Engineer in Charge or his

representatives free of charge for testing and approval.

i. Stone hard core and filling ii. Aggregate

iii. Sand iv. Steel including HTS wire, Barbed wires v. Bituminous materials

vi. Cement vii. Clay material brought from outside.

viii. HDPE liners ix. HDPE pipes x. Geo Composites

xi. PVC pipes xii. non-woven geotextiles

xiii. Tubes of geotextile xiv. Flocculants and /or electrolites xv. Any other materials as directed by Engineer in Charge

Samples provided to the Engineer in Charge or his representative for their retention is to be in

labelled boxes suitable for storage. Materials or workmanship not corresponding in character

and quality with approved samples shall be rejected.

Samples required for testing and approval must be supplied giving sufficient time to allow for

such testing and approval due allowance being made to the fact that if

samples are rejected further samples shall be required. Delay to the work arising from the late

submission of samples shall not be acceptable as a reason for delay in the completion of the

works.

If the materials are not found to comply with the various provisions laid down in the relevant

Codes, other relevant standard specifications or these specifications, the same shall be

rejected irrespective of the test certificate submitted by the Contractor.

Works 4: Remediation works of NMK-KIE Page 178

In addition, the Engineer in Charge shall have the right to request the Contractor at any time to

draw samples of aggregates or any other materials from stockpiles on the site or any other

locations to be indicated by the Engineer in Charge or his representative. The samples are to

be drawn in accordance with IS 2386 and tested in a laboratory approved by the Engineer in

Charge in accordance with the appropriate clauses of IS 2386 at the cost of the Contractor.

The Engineer in Charge is entitled to inspect any place where any materials including steel –

Reinforcement work, any casting work, laying, profiling, ramming and consolidation etc. The

Contractor shall carry out tests at such locations as are reasonably required.

19.5 Tests On Completion

Notice of Readiness

As soon as construction of the works is over, in the opinion of the Contractor, reached

Substantial Completion, the Contractor shall so notify Engineer in Charge and the Employers

Representative.

Tests on Completion of Construction

The Contractor shall carry out the Verification of Completion of construction after he has

provided the relevant documents as required by Engineer in Charge. The Contractor shall give

to Employers Representative and the Engineer in Charge 21 days' notice of the date after

which the Contractor will be ready to carry out the Verification of Completion.

Unless otherwise agreed, such Tests shall be carried out within 14 days after this date, on such

day or days as the Engineer in Charge shall instruct.

The results of the Verification of Completion shall be compiled and evaluated by

Engineer in Charge. As soon the Verification of Completion has been carried out, the

Contractor shall provide Employers Representative and the Engineer in Charge with a certified

report of the results of all such Tests, and documents in support thereof.

Works 4: Remediation works of NMK-KIE Page 179

Delayed Tests

If the Verification of Completion are being unduly delayed by the Contractor,

Employers Representative may by notice require the Contractor to carry out such Tests within

21 days after the receipt of such notice. The Contractor shall carry out such Tests on such day

or days within that period as the Contractor may fix and of which he shall give notice to

Employers Representative and the Engineer in Charge.

If the Contractor fails to carry out the Verification of Completion within 21 days,

Engineer’s Representative may proceed with such Tests. All such Tests so carried out by

Engineer’s Representative shall be at the risk and cost of the Contractor.

These Verification of Completion shall then be deemed to have been carried out in the

presence of the Engineer in Charge and the Contractor and the results of such Tests and the

costs shall be accepted as accurate.

Re-Testing

If the Verification of Completion is not satisfied, the Works shall not be deemed fit for

Substantial Completion, and Engineer in Charge may require such failed tests, and the

Verification of Completion on any related work, to be repeated under the same terms and

conditions.

Failure to Pass Tests On Completion

If the Works, or a part thereof, fails to pass the Verification of Completion, the Engineer in

Charge shall scrutinise the results of the tests, and shall be entitled to:

Works 4: Remediation works of NMK-KIE Page 180

(a) order further repetition of Verification of Completion, in which case the Contractor shall be

obliged to carry out such adjustments, repairs, replacements and/or modifications as may be

required to ensure that the Works or part achieve the specifications; or

(b) if the works are Substantially Complete, recommend the issue of a Taking Over Certificate.

The issue of a Taking Over Certificate under this Clause, shall not relieve the Contractor of the

obligation successfully to conclude the Tests and the Contractor shall be obliged to carry out

such adjustments, repairs, replacements and/or modifications as may be required to ensure

that the Works or part achieve the specifications.

(c) reject the Works or part (as the case may be), in which event the Contractor shall proceed

with its obligations under this Contract.

Tests to be Continual

The nature of the works is such that they shall be inspected and tested on a continuous basis

as the work progresses, and such tests and inspections shall be completely at the discretion of

Engineer in Charge, in accordance with technical requirements and Prudent Utility Practices.

Notwithstanding any such tests carried out during the progress of the work, the

Contractor shall carry out and complete the Tests On Completion, for the Works to

be taken over. These tests shall include, but not be restricted to the following:

Checking of construction records, documents and drawings,

Measurements to ascertain compactness and stability of the contained sediments

Tests to ascertain thickness of capping of containment cells and sand layer above bottom of NMK lake

Checks of profiles and levels,

Borings and cores

Material Test Reports.

Check for drainage channels and drainage system

Check of erosion control measures. Any other tests that may be reasonably necessary to confirm that the works meet the

specifications as highlighted in the Tender Documents.

Works 4: Remediation works of NMK-KIE Page 181

Particular specification

Works 4: Remediation works of NMK-KIE Page 182

CONTENTS 1 ............................ Features of the preferred remediation option for NMK/KIE

1.1 ................................................................................. Concept of Tube Option

1.2 .......................................................................... Features of the Tube Option

2 ...................................................................................... Description of the Site

2.1 ................................................................................................... Project Area

2.2 ........................................................................... Distribution of Project Area

3 ................................................ Site Preparation and General Work Conditions

3.2 ............................................................................................ Building Facilities

3.3 ......................................................................... Survey and Setting out Work

3.4 ...................................................................................... Permits and Licenses

3.5 ................................................................................... Protection of Property

3.6 ...................................................................................... Temporary Drainage

3.7 .................................................... Temporary Facilities for Construction Use

3.8 ...................................................................................... Provide Site Security

3.9 ..................................................................... Groundwater Monitoring Wells

3.10 ...................................................................................... Un-Impacted Areas

3.11 ........................................................................ Above ground (Power) Lines

3.12 ........................................................................................Fencing of the Site

3.13 .......................................................................... Closing of the existing gate

3.14 ........................................................................................Fencing of the Site

3.15 ........................ Temporary Site Fence – Barbed Wire Fences and MS Gate

3.16 ............................................................. Rent of Land and Storage Buildings

3.17 ........................................ Access Route, Signboard and Traffic Precautions

4 .............................................................. Quality Control & Testing Procedures

4.1 ..................................................................................................... References

4.2 ....................................... Applicable Environmental Performance Standards

4.3 .......................................................................................... Applicable Testing

4.4 ............................................................................................. Test Certificates

5 ............................. Removal of Vegetation, including Crushing of Composting

5.1 ........................................................................................................... General

5.2 .................................................................................... Methodology of work

5.3 .................................................. Removal procedure for vegetative material

5.4 ............................................................. Crushing and composting procedure

6Excavation, Loading and Transport of Waste Material from the open hillock area in KIE

6.1 ........................................................................................................... General

6.2 .................................................................................................. Methodology

7 ......................... Installation of the bottom structure of the containment cells

7.1 ........................................................................................................... General

7.2 .................................................................................................. Methodology

7.3 ........................................................................... Transport of Clean Material

8Remediation and clean-up of the drains and ponds 3 and 4 in KIE as well as the discharge

channel in the plains ...........................................................................................

8.1 ........................................................................................................... General

8.2 .................................................................................................. Methodology

9 .......................................... Remediation and clean-up of ponds 1 and 2 in KIE

Works 4: Remediation works of NMK-KIE Page 183

9.1 ........................................................................................................... General

9.2 .................................................................................................. Methodology

9.3 ......................................................... Methodology for construction of weirs

10 ...................................................Remediation of the sediments in Lake NMK

10.1 ......................................................................................................... General

10.2 ................................................................................................... Procedures

10.3 ................................................................................................ Methodology

11 ..................... Dewatering of the sediments and application of the geotubes

11.1 ......................................................................................................... General

11.2 ................................................................................................... Procedures

11.3 ................................................................................................ Methodology

12 .........................................................Design of Cover Layer Containment Cell

12.1 ......................................................................................................... General

12.2 ................................................................................................ Methodology

12.3 .................................................................................................... Vegetation

12.4 .............................................................................. Revetment along pond 1

12.5 ......................................................................... Transport of Clean Material

13 .................................... Cover layer and revetment of the bund in Lake NMK

13.1 ......................................................................................................... General

13.2 ................................................................................................... Cover layer

13.3 ................................................................................ Revetment of the bund

14 .......................................................................... Development for Future Use

14.1 ...........................................Installation of Irrigation System & Horticulture

14.2 ................................... Surface water collection and storm water drainage

14.3 .......................................................................................... Permanent fence

14.4 ............................................. Installation of Monitoring Wells & Bore wells

Works 4: Remediation works of NMK-KIE Page 184

1 Features of the preferred remediation option for NMK/KIE

1.1 Concept of Tube Option

The remediation works under this Contract facilitate the final implementation of an area wide

remediation strategy for the whole NMK/KIE area. As such the works under this Contract will

result in the containment of large quantities of sediments and the removal/disposal of a

considerable amount of illegally dumped waste. In addition the required monitoring will

provide valuable data for the implementation of other components of the area wide

remediation strategy.

The remediation works under this contract in KIE and the plains include the following main

items:

- collection and offsite disposal (TSDF) of waste present in the open hillock area of KIE

- collection and on-site transport of sediments from the open drains in KIE

- excavation and on-site transport of sediments from the discharge channel in the plains

- dredging/excavation and on-site transport of sediments from swamps and the (stagnant)

water ponds in KIE

- sediments from the open drains, discharge channel, swamps and stagnant water ponds will

be dewatered in tubes of geotextile which are positioned in a containment cell in one of the

stagnant water ponds

- construction of check dams to prevent direct inflow of drainage water and sediments into

NMK Lake

The remediation works under this contract at NMK Lake include the following main items:

- dredging of sediments from the bottom of the Lake

- dewatering of the dredged sediments in tubes of geotextile which are positioned in a

containment cells which are situated along the bunds of the Lake

- application of a cover layer of sand on top of the original clay bottom of NMK Lake

Works 4: Remediation works of NMK-KIE Page 185

Before excavation/collection/dredging of sediments can commence, dewatering cells have to

be constructed. As such the dewatering cells provide the bottom liner of the final containment

cells.

Before the slurry of sediments and surface water can be pumped into the tubes of geotextile

for dewatering, flocculants and/or electrolytes have to be added to the mixture. After

dewatering the process water has to be filtered, collected and pumped back into the Lake.

After the sediments have been removed and dewatered the containment cells will be closed,

capped and covered with a vegetation layer.

To be able to accommodate all sediments as well as the new top cover the containment cell in

stagnant water pond 2 is to attain a height of about 6-7 meters above the surrounding area.

The actual height shall be the result of the effect of dewatering on the volume of sediments

and variation of the final height between 5 and 8 m can be accepted. The containment cells

will have a flat top and 1:3.0 slopes on all sides. The top cover only allows for shallow rooting

(grassy) vegetation and no construction is possible on it. Keeping these limitations in mind, the

area can be made accessible to the public for various purposes.

The containment cells along the bunds of Lake NMK will attain a height between 1.5 and 2.0

meters above Full Tank Level (FTL +97.7 meter). To minimize the footprint of those cells part of

the perimeter of those cells will consist of a gabion structure.

For reasons of work order optimization it is allowed to exchange volumes of sediments

between the containment cells of KIE/plains and NMK.

The top cover as well as the sediments, the ground- and surface water of the whole area will require monitoring to ensure that no further exposure to the contaminants can take place.

1.2 Features of the Tube Option

The features of the remediation option for the NMK/KIE site are as follows:

Works 4: Remediation works of NMK-KIE Page 186

General Items 1. Project area 2. Temporary fencing 3. Clearance work 4. Health and safety aspects 5. Social aspects 6. Environmental protection 7. Permanent Fence

Particular Items (Scope of Work) 1. Installation of Bottom Layers for the Containment Cells

Installation of fill layer to level original surface and to form core of ring dyke around the containment cell in stagnant water pond 2

Installation of a sand layer or non-woven geotextile as foundation for the barrier layer

Installation of a barrier layer with HDPE liner system.

Installation of a drainage layer, consisting of sand mixed with active carbon and containing HDPE drains

2. Collection and offsite disposal of waste from open hillock area

Waste investigation

Excavation and collection of waste according to waste type

Transport of waste

Disposal of waste 3. Cleaning of drains

Collection and transport of waste

Excavation/collection of sediments

Transport of sediments

Disposal of sediments 4. Cleaning of discharge channel in the plains

Collection and transport of waste

Excavation/collection of sediments

Transport of sediments

Disposal of sediments 5. Cleaning of swamps 3 and 4

Collection and transport of waste

Excavation of soil and sediments

Transport of soil and sediments

Disposal of soil and sediments 6. Cleaning of stagnant water ponds 1 and 2

Collection and transport of waste

Dredging of sediments

Transport of sediments

Dewatering and containment of sediments in tubes of geotextile

Excavation of soil

Transport of soil

Application of soil 7. Sediment removal from Lake NMK

Works 4: Remediation works of NMK-KIE Page 187

Dredging of sediments

Transport of sediments

Dewatering and containment of sediments in tubes of geotextile 8. Construction of check dams 9. Covering of tubes of geotextile

Installation of fill or clay layer, including profiling of the slopes on each side

Installation of sand layer or non-woven geotextile 10. Construction of Cover Layer as per HWM Rules 2008

Installation of a barrier layer with HDPE liner system.

Installation of a drainage layer

Installation of Vegetative Soil layer

Establishing of a grass blanket 11. Construction of a drainage system

Excavation of Ditches

Installation of Drains

Installation of Discharge pipes

Excavation and partially revetment of Surface Water Drainage channels draining all surface waters to nearby surface water

Revetment of the containment cell bund along stagnant water pond 2 12. Installation of a sand cover on top of the bottom of Lake NMK

Installation of the sand layer 13. Monitoring and after care of cover layers, sediments, surface water and groundwater to

control contaminant exposure.

2 Description of the Site

The NMK/KIE site is located south west of Hyderabad as shown on Drawing Nol. IND50-1/01:

Regional Map showing site location of KIE/NMK (Refer Section VI). The complete project area is

elaborated in the Scope of Work (Refer Section V). The description of the site presented in this

section to be read in conjunction with the Scope of work as defined in Section V.

The various break ups of the project areas have been elaborated in details in this section;

which needs to be addressed by the bidder/contractor during the remediation works on site.

The existing situation of the NMK/KIE site is presented in the following Topographical Survey

Maps (as of March 2012):

Open hillock area: IND50-1/02 (Refer Section VI)

Swamp 4: IND50-1-4-1 (Refer Section VI)

Swamp 3: IND50-1-3-1 (Refer Section VI)

Stagnant water ponds 1 and 2:IND50-1-1 (Refer Section VI)

Lake NMK: IND50-1/03 (Refer Section VI)

Works 4: Remediation works of NMK-KIE Page 188

Drains in KIE: IND50-1-6-6 (Refer Section VI)

Discharge channel: IND50-1-7-1 (Refer Section VI)

Variation from the topography shall be expected as dumping activities and sediment

accumulation have been continuing on site since the topographical survey was conducted.

2.1 Project Area

The total project area is about 191,000 m2 out of which Lake NMK is 68,000 m2 and the open

hillock area about 74,000 m2. Theperimeter of the lake is of approx. 1,140 m and the perimeter

of the open hillock area is approx. 1,710m.

Drawing No, IND50-1/04 enclosed in Section VI presents the Layout showing Contractors Area

(showing the complete Project area) to be utilized during the remediation works. The following

areas are available for the Contractor:

Swamps 3 and 4: areas within the pink borders

Stagnant water ponds 1 and 2: areas within the purple borders

Open hillock area KIE: area within the green border

Drains: drains as indicated with the light blue lines and on average a 4 m width strip directly alongside those drains

Discharge channel in the plains: stream as indicated with the dark blue line and on average a 4 meter width strip directly along one side of the channel

Lake NMK, office and work space and containment cells: area within the orange border.

With regard to above borders reference is made towards Drawing No. IND50-1/04.

The open hillock area, swamps 3 and 4, stagnant water ponds 1 and 2 and the major part of

Lake NMK perimeters are already fenced off before the start of the remediation works. A

temporary site fence (approximately 230 m) has to be constructed along the backside

periphery of the Contractors office and work space behind the STP as depicted in Drawing no

IND50-1/04.

It is anticipated that a mobile fence will be sufficient, to effectively separate the works on the

drains and channel from the surrounding area.

2.2 Distribution of Project Area

The project area consists of:

- Lake NMK. (Refer Drawing No. IND50-1/04 enclosed in Section VI)

Works 4: Remediation works of NMK-KIE Page 189

Surface area of Lake NMK is 68,000 m2, the lake has about 60,000 m2 of free water, the remaining 8,000 m2 is covered with floating vegetation in front of the various shore lines

The perimeter of the lake is approximately 1,140 m

The existing floating vegetation shall be collected and removed from the lake. The plant material shall be crushed before it will be composted at authorized compost facilities in the vicinity of the project site. The compost shall be later used in the vegetative layers of the containment cells and the leveled surfaces of the open hillock area in KIE.

A temporary fence shall be constructed along the south side of the office and work space of the Contractor in the barren land behind the STP; demarcating the actual project working area during remediation works.

- The temporary office and workspace. (Refer Drawing No. IND50-1/04 enclosed in Section VI)

Located towards the south of Lake NMK in the back of the STP.

Size is approximately 13,200 m2 + 14,136 m2 brining it to a toal size of 27,336 m2.

The area has to be cleared of all shrubs, bushes and waste. After the vegetation is cleaned from soil and waste, it shall be crushed with a shredder and put forward for composting.

The waste shall be segregated and recycled/disposed of according to Indian regulations.

The area shall be leveled so that no large differences in height (> 5 cm) will remain.

An office building of about 300 m2 shall be constructed in this area.

The remaining area shall remain open and shall be provided with parking, garden, temporary sanitary waste disposal arrangements etc. A temporary road of 5 m wide in between the Temporary office and work space area and having an approach from the main road NH7 shall be constructed for easy access of trucks and vehicles during the remediation works. The total length of road will be approximately 450 m length.

2.3 - The containment cells along the bunds of Lake NMK (Refer Drawings Nos. IND50-1-5-4, IND50-

1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-112-3 enclosed in Section VI).

Located along the western, northern and southeastern bunds of Lake NMK.

Size is approximately 1,000, 2,000, 2,000 and 6,500 m2 respectively

The areas have to be cleared of all shrubs, bushes and waste. After the vegetation is cleaned from soil, it shall be crushed with a shredder and put forward for composting.

The area shall be leveled so that no large differences in height (> 5 cm) will remain. The lowest areas shall be heightened with soil (fill) to provide a level basis for the construction of the containment cell. Soil for fill material has to be free of particles large then 0.1 m.

2.4 - Stagnant water pond 1 (Refer Drawing No. IND50-1/04 enclosed in Section VI)

Located towards the northeast of Lake NMK.

Size is approximately 5,810 m2.

The area has to be cleared of all shrubs, bushes and other type of vegetation. After the vegetation is cleaned from soil, it shall be crushed with a shredder and put forward for composting.

- Stagnant water pond 2 and the containment cell (Refer Drawing No. IND50-1/04 enclosed in Section VI)

Located towards the northeast of Lake NMK.

Size is approximately 8,350 m2.

Works 4: Remediation works of NMK-KIE Page 190

The area has to be cleared of all shrubs, bushes and other type of vegetation. After the vegetation is cleaned from soil and waste, it shall be crushed with a shredder and put forward for composting. Once the area is cleared the actual remediation and construction of the containment cell can commence.

The waste shall be segregated and recycled/disposed of according to Indian regulations.

Once the sediment and polluted soil have been removed at the projected footprint of the containment cell the area shall be leveled so that no large differences in height (> 5 cm) will remain. The lowest areas shall be heightened with soil (fill) to provide a level basis for the construction of the containment cell. Soil for fill material has to be free of particles large then 0.1 m.

- Swamp 3 (Refer Drawing No. IND50-1/04 enclosed in Section VI).

Located towards the east of Lake NMK in the central part of KIE

Size is an approximately 1,290 m2

The area has to be cleared of all shrubs, bushes and other type of vegetation. After the vegetation is cleaned from soil, it shall be crushed with a shredder and put forward for composting. Once the area is cleared the actual remediation can commence.

2.5 - Swamp 4 (Refer Drawing No. IND50-1/04 enclosed in section VI).

Located towards the southeast of Lake NMK in the western part of KIE

Size is an approximately 990 m2

The area has to be cleared of all shrubs, bushes and other type of vegetation. After the vegetation is cleaned from soil and waste, it shall be crushed with a shredder and put forward for composting. Once the area is cleared the actual remediation can commence.

The waste shall be segregated and recycled/disposed of according to Indian regulations.

2.6 - Drains in KIE (Refer Drawing No. IND50-1/04 enclosed in section VI).

Located throughout the entire KIE

Total length of the drains is approximately 3,000 m.

Unlined sections of the drains shall be cleared of all shrubs, bushes and other types of vegetation. After the vegetation is cleaned from soil, it shall be crushed with a shredder and put forward for composting. Once the area is cleared the actual remediation can commence for the unlined sections.

2.7 - Discharge channel in the plains (Refer Drawing No. IND50-1/04 enclosed in section VI).

Located towards the northwest of Lake NMK

Total length of the discharge channel is approximately 740 m.

The channel has to be cleared of all shrubs, bushes and other types of vegetation to the extent that it does not longer obstructs an efficient remediation of the channel bottom. After the vegetation is cleaned from soil and waste, it shall be crushed with a shredder and put forward for composting. Once the area is cleared the actual remediation of the channel can commence

The waste shall be segregated and recycled/disposed of according to Indian regulations.

2.8 - Open hillock area KIE (Refer No. IND50-1/04 enclosed in section VI).

Located towards the southeast of Lake NMK in the central part of KIE.

Size is approximately 74,000 m2

Works 4: Remediation works of NMK-KIE Page 191

The area has to be cleared of all shrubs, bushes and waste to the extent that is necessary for the efficient removal of waste or the partial usage of this area as additional work space for the Contractor. After the vegetation is cleaned from soil, it shall be crushed with a shredder and put forward for composting.

The whole area will be leveled so that no abrupt unnatural depressions will remain. Parts of the area which will be temporarily used as work space will be leveled so that no large differences in height (> 5 cm) will remain.

2.9 The topographical map and current cross sectional elevations for Lake NMK are presented in

Drawing Nos. IND50-1/03 and IND5-1-5-1 – refer Section VI:

› Lake NMK with location of 3 cross sections: 1. Cross section Profile 1 - Northwest to Southeast 2. Cross section Profile 2 - Northwest to Southeast 3. Cross section Profile 3 - Northwest to Southeast

› The current situation is based on topographical survey carried out in March 2012. Some

changes in height might have taken place since the survey due to on-going illegal waste

dumping in the open hill lock area and the accumulation of sediments in the swamps, stagnant

water ponds, drains, the lake and the discharge channel.

This part of the document provides detailed specifications to be followed for different items of

works for remediation activities. All work shall be strictly in accordance with the Technical

Specifications, unless otherwise approved /desired by the Engineer in Charge in writing.

3 Contractors Obligation

3.1 Site Preparation and General Work Conditions

Prior to commencing with the remediation works, the Contractor / bidder shall prepare the

site by:

› Protecting existing structures; › Providing Temporary Fencing, were required. Caution tape and similar (plastic chains

etc.) are not acceptable as Temporary Fencing. › Providing site security; › Preparation of areas for temporary storage, depots and office as highlighted above. › Contractor is responsible for Site accommodation, setting up mixing plant, access road,

water supply, electricity and general site arrangements, › Office furniture, equipment and communications › Contractor to provide the following and expenditure to be made for the same: a) Corporate office of contractor.

Works 4: Remediation works of NMK-KIE Page 192

b) Technical agents for site supervision. (Reimbursement to the technical agents provision is dispensed with where ‘over heads and contractor’s profit’ provision is included in the data rates)

c) Documentation and “as built” drawings.

d) Mobilization/ de-mobilization of resources. (Payment of mobilization advances shall be dispensed with where ‘over heads and contractor’s profit’ provision is included in the data rates)

e) Labour camps with minimum amenities and transportation to work sites.

f) Two (2nos) Light vehicles 4 x 4, suitable for 4 persons for site supervision including administrative and managerial requirements.

g) Laboratory equipment and quality control including field and laboratory testing. (Contractors have to establish Quality Control laboratory in accordance with Indian legislations and standards or best international practices)

h) Minor T & P and survey instruments and setting outworks, including verification of line, dimensions, etc. X- and Y-coordinates have to be surveyed with a precision of +0.02 m and Z-coordinates with a precision of 0.005 m.

i) Continuos (24/7) Watch and Ward – Guarding of the Site, with three shifts

j) Traffic management/ Safety management during construction.

k) Expenditure on safeguarding environment, amongst others including the cleaning of access and regress roads.

l) Sundries.

m) Taxes and Duties – Contractor to specify the taxes and duties applicable under the contract and mention them separately under the items of BOQ. Other inherent costs are to be borne by the contractor which are not specified in the Cost Estimates.

n) Work Insurance/ compensation to be arranged by contractor / bidder.

3.2 Building Facilities

The building facilities shall include, but not be limited to the following buildings required for

the comprehensive operations. The Contractor shall provide any other buildings and facilities

required for the proposed work/operations.

Office (AC equipped)

Toilets/Wash Room

Works 4: Remediation works of NMK-KIE Page 193

Three-chamber undressing/showering/dressing (black/white) compartments for workers working in contaminated areas or in direct contact with lake sediments.

Workshop and Warehouse

Heavy Equipment Storage

Guardhouse

3.3 Survey and Setting out Work

(1) Data for Setting out Work

The Contractor shall be deemed to have ascertained before the Tender Date the extent and

probable accuracy of the information and reference points likely to be available to him and

shall carry out all additional survey works necessary for setting out the Works.

Elevations shown for the various parts of the works refer to the LAND SURVEY Datum. The

Contractor shall obtain from the Survey of India / Other Govt. Departments the location and

level of a bench mark and then establish the necessary lines at the surface of the ground and

at convenient locations for the construction of works. From the established base lines and

bench marks, the Contractor shall extend the necessary lines and levels for construction of the

works and shall preserve all stakes set out for lines, bench marks, or measurement of the work

in their proper places. Any expense incurred in replacing the said stakes, which the Contractor

may have failed to preserve, shall be borne by the Contractor.

(2) Existing Utility Lines – Power, Water Supply, Electrical & Instrument cables, overhead lines etc

Prior to any construction activity, the Contractor shall locate and identify all possible existing

utility lines. These shall be marked on the ground and also on relevant drawings prior to

commencement of construction activities. These shall be adequately protected against

damage by construction works.

(3) Geological Data

The Contractor shall obtain all geological information pertaining to the site, including the

physical and chemical characteristics of sub-surface soils. Indicative results of soil

investigations carried out in the NMK-KIE area are available for reference in the earlier reports

made as enclosed along with these tender documents. However, the Contractor shall be

responsible for verifying the adequacy/accuracy of this data prior to commencement of the

Works.

The Contractor shall bear the costs of all necessary additional site investigations, e.g. soil

investigation work and survey work etc. required for the implementation of the Work. The

results of Geotechnical Investigations undertaken by the Contractor will be compared with the

results presented as part of the ESMP Report and the investigations indicating inferior

geotechnical properties of soil will be considered for the design purpose.

(4) Access to the Site

Works 4: Remediation works of NMK-KIE Page 194

The Contractor shall submit temporary access plans that shall be carried out prior to

constructing, documenting the original condition, maintaining and afterwards removing and

reinstating any access required for or in connection with, the execution of the Works. All

temporary access for construction purposes shall be reinstated to its original condition, and to

a satisfactory degree of safety and stability.

(5) Site Preparation and clearance

The site preparation of the temporary areas for storage, depot and office includes removal of

scrubs, waste and other surface material and levelling of the area within.

The contractor shall carry out the Site preparation and dressing, cleaning and grubbing within

the entire project area to be utilized by the contractor with levelling, excavation, clearing and

cleaning of site, removal of scrubs and other wastes (to be documented and disposed of

according to Indian ledislation), vegetation and other surface material and levelling within less

than 5 cm of depth including all tools and plants, machinery and equipments, manpower and

labours etc complete, utilizing the excavated materials for low area filling work, disposing the

waste materials onto an off-site TSDF facility as directed by engineer in charge and to the

satisfaction of engineer in charge.

3.4 Permits and Licenses

Unless otherwise explicitly stipulated in these specifications, all permits and licenses necessary

for the proper execution of the Works shall be secured by the Contractor at its own expense

and in time.

3.5 Protection of Property

(1) Protection of Existing Structures

The Contractor will be responsible for construction such that these activities are planned for in

the construction schedule and do not delay the completion of the overall project. These

activities include demarcation and protection of existing on site and off site structures and the

project area prior to construction such as:

› Vegetation in the surrounding area › Utility lines › Demarcation of areas by means of temporary fencing. › (2) Protection of Adjacent Property

The Contractor shall conduct its operations in such a manner as to avoid any damage to

adjacent properties, improvements or facilities, buildings, trees, ground cover, electric lines,

fences, guide posts, culverts, property and other markers, signs, structures, conduits, cables,

pipelines and other facilities within or adjacent to the street or right-of-way.

Works 4: Remediation works of NMK-KIE Page 195

The Contractor shall provide and install suitable safeguards to protect such items from injury

or damage, and should such item be damaged by reason of the Contractor operations, these

items shall be replaced or restored to a condition as good as they were in when the Works

commenced, or as required by the specifications.

The Contractor shall not disturb any monuments, boundary stones or survey markers without

permission of client, and it shall bear the expense of resetting any monuments, boundary

stones or survey markers, which may be disturbed.

The Contractor shall be responsible for all damage to streets, utilities, roads, highways, ditches,

embankments, bridges, culverts or other public or private property, which may be caused by

transporting equipment’s, materials, or men to or from the works. In the event of damage, the

Contractor shall make satisfactory and acceptable arrangements with the property owner over

the damaged property concerning its repair or replacement.

(3) Protection of Utilities and Substructures

The Contractor will be responsible for protecting all utilities. The Contractor will arrange for

the location and marking of underground utility lines which might include water, sanitary

sewer, storm water sewer, electrical, natural gas, telephone, and cable etc. The Contractor will

take necessary precautions to prevent disrupting and damaging the utility lines during

remediation. For any utilities identified in the waste or polluted sediments, the Contractor will

consult with the project Engineer in Charge regarding procedures to preserve or excavate and

restore the utility backfill. The presently identified utilities are:

› Sewage lines between the pumping station and the STP. › Several sewage lines along the road separating stagnant water pond 1 and stagnant

water pond 2. › Several above ground Power and Communication lines throughout KIE. › A diligent search of known utility records has been made in an endeavour to indicate on the drawings

accompanying these Tender Documents, the nature and location of all utilities which exist within the

limits of the work. However, the accuracy or completeness of the utilities indicated on the drawings is not

guaranteed. Utility structures and/or service connections to adjacent property may or may not be shown

on the drawings. The Contractor shall acknowledge its responsibility as set forth hereinafter

(4) Contact with Utility Owners

It shall be the responsibility of the Contractor, before commencing any excavation, to contact

all possible owners of utilities within the works area and to ascertain from records or

otherwise, the existence, position and ownership of all utilities, utility structures and service

connections. No error or omission regarding the said utilities shall be construed to relieve the

Contractor from its responsibility in protecting all such facilities.

(5) Maintenance and Repair

Unless otherwise indicated on the drawings or in the specifications, all water lines, lighting,

power, telephone, or radio cables and conduits; sewer lines; house connection lines and other

subsurface structures of any nature encountered as the work progresses shall be maintained

Works 4: Remediation works of NMK-KIE Page 196

by the Contractor at its own expense and shall not be disturbed, disconnected, or damaged by

him during the progress of the work. Should the Contractor in the performance of the work

disturb, disconnect, or damage any of the above, all expenses of whatever nature arising from

such disturbance or the replacement or repair thereof, shall be borne by him.

(6) Temporary Works

Within a reasonable time (and in any case not less than 21 days) before the Contractor intends

to commence construction of any of the Temporary Works, it shall submit the working plan,

including drawings, of the same for the approval of the Engineer in Charge. An approval from

the Engineer in Charge shall mean that the Contractor can proceed with the Works; however

this shall not relieve the Contractor of responsibility for the sufficiency of the Temporary

Works or of its other duties and responsibilities under the Contract. The Contractor shall make

safe and reinstate all areas affected by Temporary Works

3.6 Temporary Drainage

The Contractor shall keep the site well drained to facilitate both remediation and site

operations. All works are to be carried out in a dry condition. Excavated areas shall be kept

well drained and free from standing water.

The Contractor shall construct, operate and maintain all temporary dykes, water courses, and

other works including pumping and well-point dewatering that may be necessary, to exclude

water from the site while remediation is in progress. Such temporary works shall not be

removed without the approval of the Engineer in Charge. The Contractor shall take all

necessary precautions to avoid flotation of any partially completed structure.

3.7 Temporary Facilities for Construction Use

(1) Water Supply

The Contractor shall arrange for and provide suitable supplies of water at the site for drinking,

washing, sanitation, and general cleaning in addition to that required for the Works. Any water

for construction purposes shall not be sourced from private houses or other consumers’

premises. The Contractor shall make its own arrangements with concerned authorities to

ensure the required availability of water during the construction period.

(2) Electrical Supplies

The Contractor shall arrange for reliable power supplies to be provided to the remediation

sites until all remediation works have been completed.

The contractor shall obtain the necessary approvals, make the necessary arrangements and

also bear the expenses for permanent power supply provisions to the working sites.

(3) Sanitation

Works 4: Remediation works of NMK-KIE Page 197

The Contractor shall provide all necessary sanitary facilities required within the sites, and shall

maintain the sites in a sanitary condition at all times. All matters concerning with health and

sanitation shall comply with the requirements of the municipalities / concerned authorities.

(4) Telephone

The Contractor shall apply for telecommunication facilities in connection with the Works.

(6) Temporary Yards

The Contractor shall be responsible for the temporary storage of all equipment and materials

until they are incorporated in the Works. All equipment and materials at the site shall be

adequately stored or housed and protected against deterioration, damage and loss.

(7) Contractor Offices

The Contractor shall construct, maintain and subsequently remove all temporary offices,

sanitary conveniences, stores, workshops, staff quarters, compounds, parking areas and the

like necessary for the satisfactory completion and maintenance of the site development, and

the setting and layout of these shall be made with the approval of the Engineer in Charge. The

Contractor shall pay all fees required by law to the relevant authorities in this respect.

(8) Contractor Temporary Site Services

The Contractor shall also provide, maintain and subsequently remove temporary services for

water supply, drainage, lighting and ventilation, roads, paths, parking places and be

responsible for disposal of waste of its staff, the TSPCB or the TSPCB’s Representatives, and for

the employees of its subcontractors, if any. Details and layout of services shall be approved by

the Engineer in Charge. The Contractor shall also obtain any necessary approvals or permits

from any Government Agencies and Local Authorities to establish such services within the Site.

This facility shall be designed to withstand local climatic conditions and shall be provided with

sufficient office furniture, appliances, etc. The site office shall be provided with windows of

appropriate opening, suitable lighting etc. A firm path shall be maintained in all-weather

condition between the nearest access road and the office. The Contractor shall maintain, clean

daily and, when necessary, light the office throughout the period of this Contract.

The Contractor shall pay all deposits and charges, comply with all by-laws, maintain all services

and pay all bills for electricity, water, telephones, etc. for the full duration of the Contract.

The Contractor shall keep the office accessible at all times and in every way habitable for

working purposes throughout the duration of the Contract. It shall also provide such labour

and cleaning materials as are required to maintain the site office in a thoroughly clean and

sanitary condition.

The Contractor shall provide twenty-four (24) hours security services.

(9) Provisions and Services for TSPCB Site Work

Works 4: Remediation works of NMK-KIE Page 198

The Contractor shall provide and maintain in good condition all the necessary temporary

facilities and services for TSPCB’s site work during the duration of the works, to include, but

not limited to, the following:-

a) Safety helmets, boots (S3 or S5 as required) and other safety equipment b) First aid kit c) Survey instruments d) Water and lighting e) Provision of Laboratory and testing services f) Temporary accommodation for workers g) Remediation equipment and machineries whenever necessary

3.8 Provide Site Security

3.8.1. Guarding of the site The Contractor shall be required to provide watchmen during and after normal working hours

to guard all utilities, plants, equipment, material, etc. delivered on site and to ensure that all

signs, lights, fences, etc. are in their proper place. The contractor / watchmen provided by him

shall be responsible to guard all work carried out under this contract, including part of the

works that may have been taken over by the Employer, as well as to guard any goods or

materials provided by the Employer for use in the works falling under this contract. The

provision of watchmen shall continue until all the works have been taken over by the

Employer.

The Employer will not take responsibility for any acts of vandalism, theft, etc.

Outside lighting, around the office buildings and on the parking area, shall be installed to the

satisfaction of the Engineer in Charge. Temporary power facility has to be provided by the

Contractor on his own costs.

3.9 Groundwater Monitoring Wells

Existing and newly installed groundwater monitoring wells will be maintained during

remediation and will be used to monitor groundwater quality after remediation. The

Contractor will be responsible for protecting the remaining wells during remediation and for

repairing any damage to the wells caused during remediation. The Contractor shall in the field

and based on the Final Site Assessment Report and his own monitoring plan identify possible

groundwater monitoring wells or drinking water wells and agree with the Engineer in Charge

on the wells to be preserved. In case some groundwater wells will need to be abandoned this

must only be done after agreement with the Engineer in Charge and following national or

international standards for abandoning wells in order to ensure against leachate of surface

water entering into groundwater source. Drinking water wells will have to be replaced by the

Contractor at his own cost.

Works 4: Remediation works of NMK-KIE Page 199

The groundwater monitoring shall follow the requirements of the Environmental and Social

Management Plan and the further details as included in Section VII.

3.10 Un-Impacted Areas

The Contractor will install barriers to prevent uncontrolled entry of equipment into areas

outside the excavation limit (i.e., un-impacted areas).

3.11 Above ground (Power) Lines

The work in KIE includes activities near and under (power) lines. The contractor shall make

sure that the owner of the (power) lines is informed and shall obtain all necessary approval for

work close to or underneath the (power) lines.

3.12 Fencing of the Site

3.12.1. Closing of the existing gate The existing gates shall be closed, during the remediation works, in a way that no additional

waste can be disposed off at the different project areas and in a way that prevent

unauthorised access to the site.

3.12.2. Fencing of the Site The Contractor is to provide, install and maintain suitable barriers and fences to protect the

work, construction camp, storage yard, existing facilities and construction and installation

operations and to remove same when no longer required by the Employer, or at completion of

work.

The open hillock, swamps 3 and 4, stagnant water ponds 1 and 2 are already completely

fenced at the commencement of the works under this Contract. Apart from the south side of

the perimeter of the office and work space for the Contractor the whole of the NMK area is

already completely fenced at the commencement of the remediation works. At the south side

of the office and work space first a temporary fences has to be erected. This fence has to be

replaced by a final fence after the remediation works have been implemented.

With regard to the works on the drains in KIE and the discharge channel in the plains, a mobile

barrier has to be applied which separates the ongoing works in a particular section from the

surrounding areas.

Barriers and fences shall comply fully with local laws and regulations.

All fences shall be structurally adequate for the required purposes and shall be maintained

during the entire remediation period. Only temporarily barriers and fences installed under this

Contract shall be completely removed on completion of the work. The Contractor is to clean

the site and repair any damage that may have been caused by him.

Works 4: Remediation works of NMK-KIE Page 200

The fencing at the south side of the office and work space shall consist of a temporary fence

during the construction period and a permanent fence to be used after the remediation works

have been implemented.

Site entry gate houses shall be established at the office and work space at Lake NMK, at the

entrance to stagnant water pond 2 and at the entrance to the open hillock area in KIE to

provide shelter from sun and rain for the watchmen. The entry gate houses shall be minimum

5 m2.

3.12.3. Temporary Site Fence - Barbed Wire Fences and MS Gate The drawing for the temporary fence shall be referred to as Drawing No. IND50-1-5-7 in

Section VI. This specification / requirements of fence and associated gate work including

foundation, RCC Pre-cast Posts and Tying of barbed wires to the RCC posts etc thereof as

elaborated under:

EARTHWORK FOR CIVIL WORKS

The excavation for the RCC post shall be 0.45m x 0.45m x 0.45m depth below GL.

PLAIN CEMENT CONCRETE FOR FOUNDATION

The PCC of grade 1:3:6 shall be placed on a clean bed at the designed level. Concrete in no case

shall be dropped from a height of more than 1m. Stone aggregates for concrete shall be of

approved quality and size. All concrete work shall strictly be carried out as per IS: 456.

CONCRETE IN PRECAST RCC POSTS

Concrete shall be of M20 grade with 20mm and down size crushed stone aggregates

conforming to IS: 383. The work shall be carried out as per IS: 456 in all respects. Necessary

moulds shall be provided for casting the concrete posts and the same shall be smooth finished

with 1:2 cement sand mortar as directed by the Engineer in Charge. The concrete shall be

cured for a minimum period of 14 days. The Precast posts will be further rooted in the

excavated holes of 0.45m x 0.45m x 0.45m depth.

RCC posts shall be 2.2mt in height and size 100mm x 100mm. 0.2 m of RCC posts shall be

embedded in the excavated hole of 0.45 x 0.45 x 0.45 m depth.

REINFORCEMENT

The steel for reinforcing bars shall be in the form of MS round bars conforming to IS: 432 grade

1 or high yield deformed bars conforming to IS: 1786. All reinforcement shall be free from

loose rust or scales oil, grease, and any other harmful matter. The steel reinforcement shall be

secured to one another with 16: SWG black annealed binding wire.

BARBED WIRE FENCING

Materials

Barbed wire shall conform as per IS: 278. The weight of the completed barbed wire shall be

136 gm/m. The coating on the wire shall be smooth and relatively free of lumps, globes or

points. Wire with excessive roughness blisters, salammoniac spots shall be rejected. Barbed

Works 4: Remediation works of NMK-KIE Page 201

wire shall be made from two strands of galvanized, twisted 2.5mm (12 gauges) steel wire with

4 points of barbs. Each barb shall have two turns, tightening around one or both line wires

making altogether four complete turns. The barb shall be so finished that four points are set

and locked at right angles to each other.

Erection of Barbed wire Fencing:

Erection of Posts

RCC posts shall be spaced at regular intervals not exceeding 3m. Every 30m interval extra

double RCC post shall be provided.

Fixing Barbed wire fencing:

There shall be six evenly spaced rows of line wire. The bottom wire shall be close to the ground

unless otherwise noted in the drawings. Each line wire shall be secured to each intermediate

post by a wire stirrup passed through a hole in the posts and secured to the line wire by three

complete turns on each side of the post.

There shall be 6 Nos. of Barbed wire horizontal and 2 Nos. of barbed wire inclined between

two posts.

3.13 Rent of Land and Storage Buildings

Apart from the access roads at the premises of the Agricultural University, along certain

stretches of the drains in KIE and a certain portion of the access road towards the office and

works space south of Lake NMK, the Contractor is not obliged to rent additional temporary

land. Costs for renting aforementioned stretches and roads has to be included in the budget of

the Contractor.

3.14 Access Route, Signboard and Traffic Precautions

3.17.1 Access route The contractor shall ensure construction of WBM access road from public road to office and

work space area. The approximate location of the road is shown on Drawing No IND50-1/04 in

Section VI. The road is temporary and shall be removed on completion. It is the responsibility

of the Contractor to ensure that the access road has a quality sufficient for the trucks used

during the work. It is considered that 5 m wide and approximately 450 m length of temporary

road shall be constructed. The exact length of the road is to be decided by the Contractor

based on site operations.

From above working area the contractor can access the entire Lake NMK, by boats or

pontoons. If the Contractors prefers to construct temporarily access roads between this

working area and the projected containment cells in Lake NMK, he is free to do so as long as

any polluted sediments present at the projected alignment of such roads have been removed

prior to their construction. The road is temporary and shall be removed on completion. It is the

responsibility of the Contractor to ensure that the access road has a quality sufficient for the

Works 4: Remediation works of NMK-KIE Page 202

trucks used during the work. The exact length and width of the road is to be decided by the

Contractor based on site operations.

3.17.2 Traffic precautions The Contractor shall observe all rules and regulations regarding the use of public access roads.

The cost of maintaining all necessary safety measures and temporary structures and making

any necessary repairs, replacements or similar operations and all or any other costs required

by reason of this use of such roads shall be borne by the Contractor and the Contractor shall

save harmless and indemnify the Employer in respect of all claims, demands, proceedings,

damages, costs, charges and expenses whatsoever arising out of or in relation to any such

operation or interference. Public roads affected by soil and mud from the works should be

cleaned daily.

3.17.3. Signboard Soonest possible after the Contractor has been given access to site, the Contractor shall on site

provide, erect and maintain 4 separate signboards bearing:

› Project Title; › The Financier's name; › The Borrower's name; › The Employer's name; › The Engineer in Charge's name; › The Contractor's (and Subcontractors’) name(s); › Address of location; and › Such other information as the Engineer in Charge may direct to be inserted upon it.

The signboard shall be not less than 2.5 m x 2.5 m lettered in , Telugu and English.

The Contractor shall remove the signboard from the site on completion of the works.

4 Quality Control & Testing Procedures

4.1 References

The following guidelines and reference shall be referred / followed to by the Contractor for

execution of the project:

› MSW Rules 2000.

› HWM Rules 2008.

› Biomedical waste rules 1998.

Works 4: Remediation works of NMK-KIE Page 203

› Indian Standard (I.S) References List: Applicable for Remediation Works:

› IS 1200 (Part 22) - 1988 Method of Measurement of Building and Civil Engineering works - Part 22 - Materials

› IS 269 Specification for 33 grade ordinary Portland Cement

› IS 12269 Specification for 53 grade ordinary Portland Cement

› IS 383 Specification for coarse and fine aggregate from Natural Source for Concrete

› IS 456 Code of practice for plain and reinforced concrete

› IS 516 Method of test for strength of concrete

› IS 1199 Method of sampling and analysis of concrete

› IS 1200 (Part II) Method of Measurement of Building and Civil Engineering work (concrete work)

› IS 1791 Specification for batch type concrete mixers

› IS 226 Structural Steel

› IS 456 - 2000 Aggregate and Admixtures concreting

› IS 516 Method of test for strength of concrete

› IS: 1200 (Part V) Method of measurement of building and civil engineering work - concrete work (Part 5 - Form work)

› IS: 10262 Recommended guidelines for concrete mix design

› IS 226-1975 Structural steel (Standard quality) (5th Revision) superseded by IS: 2062:1992

› IS 800-1984 Code of practice for use of structural steel in general in steel construction

› IS 1200-1976 Method of Measurement

› IS 5640-1970 Method of test for determining aggregate impact value of soft coarse aggregates (Reaffirmed 1993)

› List of IRC Standard Codes

Works 4: Remediation works of NMK-KIE Page 204

› 6241-1971 Testing Road Materials / Method of Test for determination of stripping value of road aggregates

› 4919-1981 Glossary of terms Applicable to Landscape of Horticulture works

› 11272-1985 Glossary of terms relating to Horticulture Equipment

› 4984-1987 Specification for high density polyethylene pipes for potable water supplies, sewage and industrial effluents (3rd revision)

› IS 4984 and IS 14333: HDPE Pipes Code

4.2 Applicable Environmental Performance Standards

(C) Applicable Environmental Standards during the remediation works.

No polluted water from the site should flow outside the site boundary without treatment.

No MSW, HWM or biomedical waste constituents or polluted soil and sediment should be blown by wind outside the site boundary.

No surface run-off from the site should flow out outside the site boundaries

No fire incidence or smoke emission from the side should occur.

No MSW, HWM or biomedical waste should be observed floating/deposited outside the project area that can be attributed to site operations after completion of mobilization period.

At no stage of remediation operations from the date of mobilization the night time noise levels at the boundary (except for the side of the main road and up to distance of 50 m on branch roads) should exceed the noise standards for residential area.

The air pollution level should not exceed the ambient air quality standard after completion of remediation works.

(D) Applicable Environmental Standards during the maintenance operations.

Ground water quality in the monitoring wells with respect to heavy metals and organics must not exceed 25% of the baseline value in any of the ground water monitoring wells. The Contractor shall analyse the baseline concentrations at the commencement of the Work.

There should not be any perceptible change (statistically significant) over the mean value of baseline conditions with respect to colour and TDS/electrical conductivity in ground water monitoring wells and surface water sampling points. The Contractor shall analyse the baseline values at the commencement of the Work.

Works 4: Remediation works of NMK-KIE Page 205

Odour - No foul odour should be discernable at the boundary of the site towards the inhabitations.

The air pollution level at the site should not exceed the ambient air quality standard. The air quality during the Work shall be monitored by the Contractor.

Surface Water Flow - No uncontrolled surface water flow should take place from the site into the surroundings onto the ground.

No uncontrolled run-off from the site should occur outside the boundary.

Measures as per the Environmental Management Plan - In addition to (A) and (B) above the

contractor will be required to comply with the environmental management plan and

environmental monitoring plans.

4.3 Applicable Testing

4.3.1. Setting Of Field Laboratory by the Contractor The Contractor shall set up a field laboratory of his own at the work site which should be open

for use and inspection by Employer’s representative at any time. Alternatively the Contractor

is allowed to transfer samples to an accredited local off-site laboratory for testing and have the

sample analysed within 24 hours or sooner if the nature of the particular work requires this.

For all sampling and testing the Contractor has to prepare and implement a QA/QC plan,

including procedures for calibration of the testing equipment.

Engineer in Charge shall inspect the field laboratory upon setting up (and periodically

thereafter) and verify the adequacy and accuracy of all equipment thereof.

All the pressure gauges and other measuring equipment of the laboratory shall be checked and

calibrated regularly as directed by the Engineer in Charge by an agency and the Test

certificates shall be furnished to the Engineer in Charge.

The Contractor shall render all reasonable assistance and help in making such checks and tests.

The cost of all checks and calibrations shall be borne by the Contractor. The cost of all tests for

materials shall also be borne by the Contractor.

4.3.2. Testing If Engineer in Charge requires tests, the Contractor shall carry out such tests in accordance

with the specifications, BOQ and conditions of the contract. The Contractor shall provide all

documents and other information necessary for testing and such assistance, labour, materials,

electricity, fuel, stores, apparatus and instruments as are necessary to carry out such tests

efficiently. The Contractor shall provide such engineering support and technical know-how as

Engineer in charge shall reasonably request for the purpose of the tests.

If the tests required are elaborate and require prior setting up of equipment or instruments,

the Contractor shall agree, with Engineer in Charge and Engineer’s Representative, the time

Works 4: Remediation works of NMK-KIE Page 206

and place for the testing. Engineer in Charge shall give the Contractor not less than 24hours'

notice of his intention to attend such tests. The Contractor shall provide sufficient suitably

qualified and experienced (certified) staff to carry out such tests, including sampling.

The Contractor shall promptly forward to Engineer in charge duly certified reports of the tests.

When the specified tests have been passed, Engineer in Charge shall endorse the Contractor's

test certificate, or issue a confirmation to him / her, to that effect.

Employer is entitled to insist for the Contractor to carry out any tests of any type, as it deems

fit or alternatively insist to have tests verified in an independent laboratory, at the expense of

the Contractor. If such test is in accordance with specifications or Prudent Utility Practices,

then Employer shall bear the cost of such tests. Except that if the Materials or Works fail such

tests, the cost of the test shall be borne by the Contractor, and the Contractor shall also rectify

the Materials or Works at his cost. The tests shall include checking of construction records,

documents and drawings ,trial runs, checks of profiles and levels, borings and cores or any

other tests that maybe reasonably necessary to confirm that the works meet the

specifications.

The contractor shall provide sufficient suitably qualified and experience (certified) staff to carry

out such tests, including sampling.

Employer is entitled to insist for the contractor to carry out any tests of any type, as it deems

fit or alternatively insist to have tests verified in an independent laboratory, at the expense of

the contractor.

4.3.3. Measurements Any provisions of measurement referred to in this Contract will be applicable for the

assessment of quantity of work done for payment of works executed. All such assessments

shall be based on measurements duly entered in a measurement books. All items of work shall

be entered in a measurement book, level book, etc., as prescribed by Engineer in Charge so

that a complete record of the entire Works under this Contract can be established.

Measurements shall be signed and dated by both Parties on the Site on completion of

measurement forthwith. The original measurement books shall be kept in the custody of

Engineer in Charge. All payments under this Contract shall require to be supported by

measurements for assessing quantum of work, adherence to specifications, and achievement

of Project milestones.

Measurements shall be taken jointly by Engineer in Charge or his assistant and by the

Contractor or his authorised representative. Before taking measurements of any work the

Engineer in Charge or his assistant shall give reasonable notice of the date of measurement to

the Contractor.

If the Contractor fails to attend or send an authorised representative for measurement on the

notified date, or being present fails to countersign, Engineer in Charge shall record such

absence or failure to countersign, and take measurements ex-parte.

Works 4: Remediation works of NMK-KIE Page 207

The Contractor can inspect the measurement books available with Engineer in Charge, and if

the Contractor fails to countersign or record the objection within a week from the date of

measurement, then in any such event, measurements taken by Engineer in Charge or his

assistant shall be taken to be correct measurements of the work and shall be binding and

conclusive on the Contractor.

The Contractor shall, without any extra charge, provide assistance with every appliance,

instruments and supporting tests and any other things necessary for measurements and

certification.

4.4 Test Certificates

All manufacturers certificates of tests, proof sheets, mill sheets etc. showing that the materials

have been tested in accordance with the requirements of the appropriate Indian Standard,

other relevant Standard Specification these specifications shall be supplied free of charge on

request to the Engineer in Charge or his representatives. Such details shall be submitted with

every new batch of materials used at site.

Samples of all the materials used in the Remediation Works shall be submitted to the Engineer

in Charge or his representatives free of charge for testing and approval.

4.5 Personnel Protective Equipment (PPE):

The Contractors at his own expense has to supply all personnel working in the contaminated

zone at least with the following set of PPE:

disposable single use coveralls type CE catogories 4, 5 and 6

nitril gloves

safety shoes (S3 type) or safety boots (S5)

disposable polypropylene safety socks, with bow ties and eleastic top closure

safety glasses

full face mask with P3 and A type filters

all other safety equipment as deemed appropriate by the Contractor

5 Removal of Vegetation, including Crushing of Composting

Under the current Contract no demolishing works are required. Only vegetation has to be

removed.

5.1 General

Vegetation has to be removed from the following objects:

Works 4: Remediation works of NMK-KIE Page 208

Dense vegetation present within the water line of Lake NMK, which covers an area of about 8,000 m2

Medium to dense vegetation present in the work and office space, which covers an area of about 13,200 m2

Medium to dense vegetation present near the projected containment cell in the south-eastern corner of Lake NMK, which covers an area of about 14,140 m2

Medium to dense vegetation from swamps 3 and 4, stagnant water ponds 1 and 2, which covers an total area of 16,436 m2

Sparse to medium vegetation from the unlined sections of the drains in KIE to such an extent that is required for an efficient and complete remediation of those sections

Vegetation from the discharge channel in the plains to such an extent that is required for an efficient and complete remediation of this channel

Vegetation from the open hillock area in KIE to such an extent that is required for an efficient and complete removal of the waste or the application of certain sections of this area for temporarily work space. The open hillock covers an area of 74,000 m2

The total tonnage of the vegetation that has to be removed is estimated to be about 650 tonnes of fresh vegetation. Were required for efficient composting, the vegetation has to be crushed in chips smaller than 0.05 m, before it is transported to a authorized compost facility in the vicinity of the project area. The contractor shall take care that applicable permits are obtained and rules and/or

regulations concerning removal of vegetation and composting are followed. Produced compost

has to apply with the quality standards as per MSW2008 rules and the standards for city

compost as per rules of the Agricultural Department.

There are no existing utilities that should be removed at the remediation sites. When utility

lines are encountered, that are not indicated on the drawings, the Engineer in Charge shall be

notified prior to further work in that area. Uncovered utilities by work should be terminated in

a manner conforming to the nationally recognized code covering the specific utility and

approved by the Engineer in Charge.

5.2 Methodology of work

The Contractor shall report to the Engineer in Charge details of any underground chambers,

vaults, wells, etc discovered during the removal of vegetation and deal with as instructed. The

Contractor shall provide, maintain, alter and adapt temporary supports of adequate strength

to maintain integrity/stability of adjoining buildings, nearby services and thoroughfares. The

contactor shall take necessary precautions to prevent fire or explosion caused by gas or vapour

present.

Works 4: Remediation works of NMK-KIE Page 209

1. No vegetation shall be removed from the premises as a whole, or in a substantially whole condition, but all vegetation shall be crushed on the premises.

2. No vegetation shall be removed from the premises which still contain soil or sediment onto its root system.

3. If a Permit is required for removal of vegetation or cutting of trees, this shall be procured by the Contractor from the appropriate authorities before commencement of the works.

4. Excavations from root holes shall be filled with soil from the surrounding area.

5. When the removal of vegetation is substantially complete, the Contractor shall notify the Engineer in Charge that the work will be ready for final inspection.

6. The Contractor shall comply with applicable laws and ordinances governing the storage and composting of plant material; and shall commit no trespass on any private property in the processing of the plant materials without permission of the property owners involved.

5.3 Removal procedure for vegetative material

1. Perform removal of vegetation in such manner as to eliminate hazards to persons and property; to minimize interference with use of adjacent areas, utilities and structures or interruption of use of such utilities; and to provide free passage to and from such adjacent areas of structures.

2. Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of all personnel during removal operations.

3. Before beginning of any harvest or cutting work, the Contractor shall survey the site and examine the drawings and specifications to determine the extent of the work. The Contractor shall take necessary precautions to avoid damages to existing items to remain in place, to be reused, or to remain the property.

4. The Contractor shall coordinate the work of this section with all other work at the remediation sites.

5. When Utility lines are encountered that are not indicated on the drawings, the Engineer in Charge shall be notified prior to further work in that area.

6. The Contractor shall provide dust control in case of excess dust generation during the harvesting and cutting of the vegetation and the crushing of the vegetative material

Works 4: Remediation works of NMK-KIE Page 210

5.4 Crushing and composting procedure

The crushing of vegetative material and trees shall take place as close as possible to the place

of origin. The (crushed) material shall be transported to the authorized compost facilities by

regular combination of a tractor and a dumper.

The crusher shall be of a size sufficiently for the type of vegetation that has to be removed..

To facilitate an efficient and controlled composting process the Contractor has to contract an

authorized composting facility.

The composted material shall be reused e.g. for the vegetative layer of the containment cells

or on the surface of the landscaped central hillock area.

6 Excavation, Loading and Transport of Waste Material from the open hillock area in KIE

6.1 General

In the open hillock area of KIE traditionally all kinds of waste have been illegally dumped, as is

the case in other parts of this industrial estate. Since March 2012, APPIIC has been collecting

the illegally dumped waste in the other public areas of KIE and has transported this waste to

the open hillock area for temporary storage, awaiting the final removal of the wastes under

this remediation project.

Illegal waste dumping was unorganized and happened at random all over the open hillock

area. Mixing of waste from different sources of origin was common practice. From time to time

waste volumes present in the area were reduced by burning of the dumped wastes. APPIIC has

made an attempt to separate the waste and soil collected by them in the following four

categories for temporary storage:

Solid waste (hazardous and municipal)

Slags and ashes

Soil

Mixed soil and inert rubble

Under this project the following categories of waste have to be removed from the site:

Hazardous waste, amongst others asbestos

Municipal solid waste

Biomedical waste

Works 4: Remediation works of NMK-KIE Page 211

Slags, ashes and/or (sewage) sludges

Given the high dynamics of waste dumping in the open hillock a waste inventory has to be

carried out before the actual excavation and removal of the wastes can commence. The waste

inventory has to be carried out in such an extent that all sources of waste present in the open

hillock area of KIE will be identified, delineated and characterised according to above 4

categories and the volumes of every individual sources have been established.

The waste inventory has to be carried out through either the excavation of trial trenches or the

use of drilling equipment. A senior waste expert of the Contractor has to permanently

supervise the waste inventory in the field and has to document the results with the help of

logbooks, photo evidence, sample material contained in transparent closed containers and

maps representing the results of the measurements in the field. This expert has to categorize

the waste into the 4 categories as mentioned above.

Trial trenches or drill cores shall remain available for inspection by the Engineer in Charge for

at least 10 working days.

Based on oral information provided by the estate manager of APPIIC the total quantity of

waste present in the open hillock of KIE is currently estimated to be 3,500 m3. Of which is

about 100 m3 biomedical waste and the remaining volume more or less evenly distributed

between hazardous waste (1,100 m3), municipal solid waste (1,200 m3) and slacks, ashes

and/or (sewage) sludge’s (1,100 m3). In addition APPIIC has temporarily stored about 500 m3

soil and 750 m3 soil mixed with inert rubble in this open area.

Given the mixed character of the waste present in the open hillock area of KIE, the whole

waste inventory has to be carried out under the most strict health and safety precautions,

including the use of suitable boots, gloves, coveralls, masks and filters which meet the

international requirements for asbestos conditions and a three step decontamination and

wash unit between the polluted zone and the surrounding area.

Once the different source of waste have been identified, delineated and characterized, the

waste has to be removed by means of excavation and directly loaded on trucks which are

water tight and can be closed at the top. Waste removal has to be done in the following work

order: biomedical waste, hazardous waste, slags/ashes/(sewage)sludge’s and municipal solid

waste.

Biomedical waste, hazardous waste and slags/ashes/(sewage)sludge’s have to be transported

to an officially recognized TSDF near Hyderabad for further treatment and/or disposal. The

municipal waste has to be transported to one of the officially operated Municipal Solid Waste

Dumps in Hyderabad for final disposal. The distance between those facilities and the open

hillock sites are about 60 km on average.

Once all wastes sources at the open hillock area of KIE have been removed the available soil

(with inert rubble) shall be used to fill up the depressions were waste has been removed or for

general levelling and landscaping of the area. Inert rubble should not be applied in the upper

Works 4: Remediation works of NMK-KIE Page 212

1.0 m of the profiled soil strata. No soil from outside sources will be applied for fill, levelling or

landscaping.

Once (portions of) the open hillock area in KIE is free from waste and has been levelled in

accordance with the required specifications it can be used as additional working space for the

contractor.

6.2 Methodology

The method of excavation and transport can be freely chosen by the Contractor under the

conditions that the below described principles are followed.

1. In case unexpected hospital waste is observed during excavation, the Contractor shall stop the excavation of the particular area and inform the Engineer in Charge. The Contractor shall follow the instructions from the Engineer in Charge. Hospital waste shall be separately excavated and directly transported to a TSDF for further treatment or disposal.

2. In case the waste shows indication of asbestos during excavation, the Contractor shall stop the excavation of the particular area and inform the Engineer in Charge. The Contractor shall follow the instructions from the Engineer in Charge. Asbestos shall be sorted and packed onsite in double plastic (container) bags by contractor’s staff using the proper Personal Protective Equipment. When repacked the asbestos waste will be transported to a TSDF for final disposal .

3. In case the waste shows indications of unexpected chemical contamination from smell, odour or colour or presence of drums with unknown content, the Contractor shall stop the excavation of the particular area and inform the Engineer in Charge. The Contractor shall follow the instruction from the Engineer in Charge. Unexpected chemical contaminated waste will be onsite packed in adequate packaging material by contractor’s staff using the proper Personal Protective Equipment (PPE) as specified in Section 4.5 under particular specification. When repacked, the Chemical contaminated waste will be transported to a TSDF for final treatment or disposal.

4. All vehicles leaving the site shall be cleaned from soil and waste adhering to the vehicles tyres and body. Cleaning shall be performed in the transition zone between the open hillock area and the surrounding areas.

7 Installation of the bottom structure of the containment cells

After the vegetation, stumps, shrubs, debris waste, sediment and/or polluted soil have been

removed from the projected footprint of the containment cells at the bunds, hillock and

southeastern corner of Lake NMK and in stagnant water pond 2 and the remaining surface has

been levelled, the actual installation of the bottom construction of these containment cells can

commence.

Works 4: Remediation works of NMK-KIE Page 213

The bottom construction of the containment cell in stagnant water pond 2 consist of the

following separate layers:

- fill layer (variable thickness)

- foundation layer (0,5 m thick)

- HDPE layer of 2 mm

- drainage layer (0.5 m thick)

The fill layer has also to provide for the core of the ring dyke around the containment cells.

The bottom construction of the containment cells in Lake NMK consist of the following

separate layers:

- fill layer (variable thickness)

- sand layer (minimum thickness 0,15 m) with drains

- HDPE layer of 2 mm

- drainage layer (0.35 m thick) with drains and active carbon

On the surrounding slopes of the bottom construction the sand layers on both sides of the

HDPE liner are (partially) replaced by non-woven geo-textiles 250 g/sq.m (GSE250 or

equivalent). A total of 4,553 m2 of geo-textile is required for this replacement. With regard to

the specifications of the geo-textile reference is made towards chapter 12, were full

specifications for the geo-textile have been provided.

Newly installed gabions or existing bund slopes isolate the bottom construction from the

surrounding areas. A 1.5 mm thick HDPE liner in combination with clay prevent the direct

inflow of surface water through the open structure of the gabions.

7.1 General

Conceptual design of the bottom construction of the containment cells are shown on Drawings

Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11 and

in stagnant water pond 2 as presented on Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-

1-2-3 in Section VI. The Contractor shall make sure that the construction of the bottom of the

containment cells is in accordance with the Indian Standard HWM 2008.

Total area of the bottom construction of the containment cells in Lake NMK shall be

approximately 1,000 (100x10 meters), 2,000 (200 x 10 meters), 2,000 (200 x 10 meters) and

6,500 (average 65 x 100 meters) m2 respectively. Total area of the bottom structure of the

containment cell in stagnant water pond 2 shall be approximately 5,400 m2, which is equal to

an projected footprint of about 90 by 60 m (exclusive the future drain around the cell).

Works 4: Remediation works of NMK-KIE Page 214

After completion of the bottom construction of the containment cell a construction has to be

established which is designed to minimize infiltration losses of process water and provide a

stabile compartment for the application of the tubes of geotextile.

7.2 Methodology

7.2.1. Fill layer for containment cell in stagnant water pond 2 After the original sediment, polluted soil or other material has been removed and the

remaining surface has been leveled, the fill layer has to be installed. A fill layer of ordinary

earth with a thickness between 2.0 till 2.5 m has to be applied, depending on the actual height

of the original surface.

The fill layer has to provide for a flat working platform. The top of this platform has to be equal

or higher than the FTL of Lake NMK. The fill material is also applied to install the core of the

ring dyke around the outside of the containment cell.

In stagnant water pond 2 about 7,860 m3 of soil is required for the fill layer. The contractor has

to deliver the fill material. The contractor is allowed to use topsoil from the remaining parts of

stagnant water ponds 1 and 2 (light grey areas as presented on Drawing Nos. IND50-1-1-1, IND

50-1-1-2 and IND50-1-1-3 as a partial source for the required fill volume, as long at the

required specifications for the fill layer can be met. The Contractor shall report to the Engineer

the properties and testing results of the materials he intend to use for the approval of the

Engineer before the first delivery to the site is effectuated.

The fill layer shall be compacted with a tractor with a 2T roller for each layer of 0,5 m thick. If

the fill layer is thicker than 0.5 meter, the layer has to be installed in separate layers of which

none is thicker than 0.5 m. Each layer should at least be compacted into 2 directions, with a

minimum of 2 passes in each direction, with perpendicular orientation.

As fill material has sometimes to be applied on waterlogged and soft soils, the Contractor has

to assess after the installation of each individual layer when water pressure and the on-going

settlement of the subsoil allow for the installation of an additional layer of fill material, as high

water pressure and substantial settlement rates can be signs of instability of the subsoil. The

same assessment has also to be made during the entire construction of the bottom structure,

the filling of the tubes of geotextile and the closure of the containment cells!

The fill layer should result in a stable and flat working area, on which the bottom construction

of the containment cell can be further installed. The inner slope of the core of the ring dyke

has to obtain slopes 1:1, and the outer slope of the same has to be 1:3. After leveling no large

differences in height (> 3 cm) on the surface of the fill layer shall remain.

Soil materials used for the fill layer shall be free of any material with particular seize above 10

centimeter. The content of organic material shall be less than 4%.

Requirements, tolerances and check

Tolerance, requirements and check for fill layers:

Works 4: Remediation works of NMK-KIE Page 215

Parameter Requirement Tests

Value Tolerance Nos.

Vertical alignment:

- Level at slopes (1:3) Designed

alignment

+/- 0.03 m 25 per 10,000 m2

- Level at top (1:>30) +/- 0.03 m 25 per 10,000 m2

- Top of fill layer Equal or

above FTL

No single values

below FTL

25 per 10,000 m2

Maximum grain size and

organic matter content

See text

above

See table 1 per 1,000 m3

7.2.1. Gabions and fill layer for cells in Lake NMK After the original sediment has been removed from the projected foot prints of the

containment cells in Lake NMK and the remaining surface has been leveled, the actual

construction of those cells can start. After leveling no large differences in height (> 3 cm) on

the surface shall remain.

The construction of the containment cells in Lake NMK shall start with the installation of the

combined gabion, clay, HDPE 1,5 mm barriers. The HDPE 1.5 mm shall be installed between

the gabion structure and the clay. The clay shall be placed against the wall of the gabions with

a slope of 1:1 and covers the entire height of the gabions.

The Contractor shall apply reinforced gabions with a maximum width of 2 meter and a

maximum height of 3.95 m (average about 2.5). The total volume of those gabions is about

4050 m³. In addition about 2,755 m2 of HDPE 1,5 mm liner is required and 2,920 m3 clay. With

regard to the specifications of the HDPE liner reference is made towards chapter 12, were full

specifications and requirements have been provided for handling and laying of HDPE liners.

0.9 Cum of coarse aggregates per Cum of reinforced gabion are to be applied with a blending

ratio of 50:40 for the fraction 120-80 mm and 80-40 mm respectively. Only approved, clean,

hard, graded aggregates for gabion filling are to be be applied.

Providing, fabricating and placing in position of reinforcement steel bars (12 and 8 mm rods)

and chain like mesh (size: 30 mm x 30 mm x 8 G) for the construction of the gabion support

structures, including cleaning, straightening, cutting, bending, hooking, lapping, welding

wherever required, tying with 2.50 mm diameter soft annealed steel wire. A minimum of 25 kg

of reinforced steel and 3.5 m2 of chain like mesh per 1 m³ of gabion volume has to be applied.

The Contractor has to submit a final design for the reinforcement for approval to the Engineer

in Charge.

At the cells on the western and northern bund those gabion, clay, HDPE barriers shall only be

installed at the Lake side of the containment cells. Apart from the clay barrier placed against

Works 4: Remediation works of NMK-KIE Page 216

the inner wall of the gabions no fill material is required for the construction of the cells along

the western and northern bunds of Lake NMK.

In the southeastern corner the gabion, clay, HDPE barrier shall be installed all around the

containment cell. To guarantee the stability of the gabion structure on the lake side of this

particular cell a support berm (slope 1:3) of clay shall be installed on the outside perimeter of

this gabion. Fir this a total volume of 1,406 m3 of clay is required.

The applied clay shall have a minimum plasticity index of 12 as tested by Atterberg Limit tests

(ASTM D4318). Clay materials shall contain no sod, brush, roots, frozen soil, or other

perishable materials. Rock particles larger than 0.075 mshall be removed prior to compaction

of the clay.

For the installation of the gabions along the western, southern and eastern border of this

containment cell in the south-eastern corner of the Lake a trench has to be excavated of about

2,5 meter deep and 2,5 meter width and with a total volume of about 1.400 m3. The excavated

soil can later be applied as fill material during the closure of the containment cells.

As the top of the foundation layer in the south-eastern containment cell is projected at +96.80

meters and requires a minimal thickness of 0.15 meter, this implies that the original soil of the

entire cell has to be leveled to a maximum height of +96.65 meter. It is expected that about

1,000 m3 of soil has to be redistributed within the perimeter of the cell to obtain the required

degree of leveling. It is anticipated that no off-site disposal of soil is required for this particular

cell.

Only after the foundation layer has been installed to a level of +96.8 meter, dewatering of the

containment cells in Lake NMK is allowed. During the construction of the containment cells the

integrity of the natural clay layer underneath the Lake has to be maintained at all means.

As the containment cells shall be installed on waterlogged and soft soils, the Contractor has to

assess after the installation of each individual layer when water pressure and the on-going

settlement of the subsoil allow for the installation of an additional layer, as high water

pressure and substantial settlement rates can be signs of instability of the subsoil. This

assessment has to be made during the entire construction of the bottom structure, the filling

of the tubes of geotextile and the closure of the containment cells!

7.2.2. Foundation layer Once the fill layer and the subsoil are sufficiently stable the foundation layer has to be applied

in one work course. A foundation layer of 0.5 m thick consisting of sand has to be applied in

the containment cell projected in stagnant water pond 2. A foundation layer of 0.15 m thick

consisting of sand has to be applied in the containment cells projected in Lake NMK.

At stagnant water pond 2, sand should be supplied and distributed from areas already covered

by the foundation layer. Where required ramps have to be applied on the supply routes to

guarantee stability of the foundation layers. Equipment distributing the soil should be provided

with tracks.

Works 4: Remediation works of NMK-KIE Page 217

In Lake NMK the sand has to be applied with a rain bow or equivalent technique in the

containment cells, as those cells can only be dewatered after this foundation layer has been

applied. To support the dewatering of those cells 110 mm HDPE drains have to be installed at 5

meter intervals in the foundation layer of the cells in Lake NMK.

Underneath the containment cells in Lake NMK about 1,725 m3 of sand is required for the

foundation layer. In stagnant water pond 2 about 1,380 m3 of sand is required for the

foundation layer. The contractor has to deliver the foundation material. The Contractor shall

report to the Engineer the properties and testing results of the materials he intend to use for

the approval of the Engineer before the first delivery to the site is effectuated.

The foundation layer shall be compacted with a tractor with 2 T rollerin the containment cell of

stagnant water pond 2. The Contractor shall ensure that the foundation layer shall be

compacted into 2 directions, with a minimum of 2 passes in each direction, with perpendicular

orientation.

The foundation layer should result in a stable and flat working area, on which the bottom

construction of the containment cells can be further installed.

The inner slope of the core of the ring dyke in stagnant water pond 2 has to obtain slopes 1:1,

and the outer slope of the same has to be 1:3. The slopes of the bunds in Lake NMK are about

1:3.

The 1:1 slope of the clay behind the gabion shall not be covered with a sand layer. Here a non-

woven geo-textile of 250 g/sq.m (GSE 250 or equivalent) shall be applied as a protective layer

for the HDPE liner (about 2,940 m2).

Just before the installation of the HDPE liner the top of the foundation layer shall be leveled.

After leveling no large differences in height (> 2 cm) on the surface of the foundation layer

shall remain and the surface should be free of any debris that could damage the liner or

prevent an even/smooth deployment of the liners.

The content of organic material shall be less than 2%. The coefficient of permeability of the

drainage material shall be k > 10-4 m/s.

Grain size distribution:

Sieve size (mm) Quantity of particles (%)

passed through sieves

20 100

10 30 - 100

5 15 - 60

2 5-35

Works 4: Remediation works of NMK-KIE Page 218

Sieve size (mm) Quantity of particles (%)

passed through sieves

1 0-20

0,5 0-10

Maximum grain size is 20 mm.

Requirements, tolerances and check

Tolerance, requirements and check for foundation layer:

Parameter Requirement Tests

Value Tolerance Nos.

Vertical alignment:

- Level at slopes (1:3) Designed

alignment

+/- 0.02 m 25 per 10,000 m2

- Level at top (1:>30) +/- 0.02 m 25 per 10,000 m2

- Thickness of foundation

layer

Min. 0.50 m No single values

less than 0.5 m

25 per 10,000 m2

Grain size distribution of

drainage layer

See table See table 1 per 500 m3

7.2.3. Barrier Layer with HDPE liner After the foundation layer has been applied and leveled a barrier layer of HDPE shall be

installed.

The final bottom construction shall have a barrier layer with a permeability coefficient less that

1 x 10-7 cm/sec or less. This can be achieved with provision a liner of 2.0 mm HDPE (as per

standard specifications of HWM 2008). It is assumed that the naturally occurring clay which is

currently situated underneath the sediments provides for the required second barrier system.

The liner system reduces the infiltration of rain and process waters in the subsoil. Net demand

of HDPE liner in the bottom structure of the containment cell in Lake NMK is 11,500 m2. In

stagnant water pond 2 the net demand is about 3,055 m2 HDPE liner.

The construction of the liner is as such that the different bands are welded providing a

completely closed membrane preventing (process) water to enter the subsoil.

Works 4: Remediation works of NMK-KIE Page 219

The installation procedure must be planned in such a way, that the total installation - i.e. from

installing the first strip of HDPE liner until the start to the installation of the drainage layer is

performed as a continuous operation, ensuring that at no time an installed area of HDPE liner

is left open/uncovered for longer time than absolutely necessary.

Description of Liner System

The liner system consists of one 2.0 mm textured (both sites) HDPE liner (to enhance the slope

stability).

Requirements and specification of HDPE liner

The material for the polymer liner shall be High Density Poly Ethylene (HDPE) with the

following specifications:

Parameter Requirement Toleranc

e

Check method

Appearance No visible flaws or

defects

Textured on both sites

Visual inspection

Thickness 2.0 mm - 10 % ISO 4648:1991 or

similar standard

Density min. 0.94 g/cm3 Non ASTM D 1505

Melt Flow Index (190/5) 0.6 - 2.0 g/10min Non ASTM D1238

Carbon Black Content min. 2.0 % Non ASTM D4218

Tensile characteristics:

ASTM D792, Type IV

Machine and cross-machine

direction:

- Tensile strength at break min. 15 N/mm Non

- Tensile strength at yield Min. 20 N/mm Non

- Elongation at break Min. 100% Non

- Elongation at yield Min. 10% Non

Tear resistance Min. 150 N Non ASTM D 1004

Puncture Resistance Force min. 300 N Non ASTM D 4833

Works 4: Remediation works of NMK-KIE Page 220

Parameter Requirement Toleranc

e

Check method

Strength of welded seams

ISO 527-3:1993

ISO 37:1994 or similar

standard

- Shear

Min. 90% of tensile

strength at point of

yield

Non

- Peel

Min. 75% of tensile

strength at point of

yield

Non

Oxidative Induction Time Min. 100 min non ASTM D 3895

Environmental stress-cracking Min. 200 hours

non ASTM D 5397-99,

Appendix

Delivery and Storage Requirements for HDPE Liners The liner material shall be delivered at the site with a datasheet from the producer certifying

the characteristics of the material according to the above specifications. Further the delivery

shall be accompanied by a protocol with the results of the producers quality check for the

specific batch delivered to the site

The membrane shall be protected against physical damages during transport to the site and

during storage at the site.

The manufactures guidelines for storage, handling and installation of the HDPE liner shall be

followed.

Conformance Testing for HDPE liners

General

The installer shall elaborate an installation plan showing the position of the individual rolls of

material and deliver the plan to the Engineer for approval before installation works

commence.

Installation may only be done by technical staff approved by the producer of the liner material

(the manufacturer) and with equipment approved by the same.

Welding

All welding-seams shall be double-seam welds with the possibility of testing with pressurised

air, or extrusion welds with a spark-leader welded into the seam, enabling full testing of the

tightness of the seams with high-voltage spark methods.

Works 4: Remediation works of NMK-KIE Page 221

At the beginning and end of each day of installation a welding test shall be performed by each

combination of welding equipment and welder in work to ensure the correct adjustments of

welding temperature, pressure and -speed according to the prevailing weather conditions. The

welding shall be tested for seam strength (peel and shear) and the results are reported to the

Engineer.

The welding test shall be repeated after any interruption of the installation works during the

day, caused by e g. changes in weather conditions or equivalent.

The tests have to be performed by the Contractor himself or a recognised laboratory with

suitable testing equipment and experience.

Before welding each lane of material shall be laid out without wrinkles, but with sufficient

material and overlapping to ensure, that no significant problems arise during the welding due

to temperature variations.

All edges of the liner material shall be protected against soiling until the time of welding. The

Contractor decides the method for protection and submits the description to the Engineer for

approval.

Overlapping shall be done with overlaps in the direction of the slope of the liner, i.e. roof-tile

like.

The seam between the membrane at any near-horizontal areas and the membrane at a slope

shall be positioned at the near-horizontal plane and no closer to the top of the slope than 1.0

m.

No machinery of any kind is allowed to operate directly on top of the installed liner. At all

times sufficient protection of the liner shall be ensured before any machinery is allowed to

enter. Sufficient protection can be e.g. min. 1.0 m of soil for wheel operated equipment or 0.5

m of soil for track operated equipment.

Covering

Until the membrane has been checked and approved the liner material shall be anchored using

sandbags or any other equivalent system ensuring, that the installed liner material is not

moved by wind or down slope by gravity.

The Contractor shall cover the installed liner with a soil layer immediately upon check and

approval by the Engineer. At slopes the cover material shall be installed starting from the toe

of the slope taking any slack in the liner material to the top of the slope. The liner shall be

anchored at all beams.

Check of liner material and installation

The check of the installation works shall be based on a check plan elaborated by the Contractor

and approved by the Engineer. The check plan shall describe who has the responsibility for

performing each check, the extent of the check and when the check shall be performed.

Works 4: Remediation works of NMK-KIE Page 222

Further the plan shall indicate whether the works may proceed or shall wait pending the

results of the tests and checks.

Stage Item Subje

ct to

chec

k

Method Extent Acceptance

Delivery Liner material Datas

heet

quality

check

1 nos. per

roll

Delivered

Reception Liner material Appe

aranc

e

Visual 1 nos. per

2,000 m2

No flaws or

defects

Thick

ness

Measure

ment

1 nos. per

2,000 m2

Less than

10% negative

deviation

from

specification

Mech

anica

l

prop

erties

Stress

and

strain at

break 1 nos. per

2,000 m2

Less than

10% negative

deviation

from

specification

Stress

and

strain at

yield

Start of

welding Welding seams

Tight

ness

(in-

situ)

Vacuum

bell,

pressuri

sed

double

seam,

spark-

testing

1 nos. per

welder per.

welding

machine per.

day

cut sample

min. 36 cm x

60 cm

No leaks

Stren

gth

(cut

Shear

and peel

Sheer: Min.

90% of

tensile

Works 4: Remediation works of NMK-KIE Page 223

Stage Item Subje

ct to

chec

k

Method Extent Acceptance

samp

le)

strength at

point of yield

Peel: Min.

75% of

tensile

strength at

point of yield

During

installatio

n

Liner material

Appe

aranc

e

Visual 100% No flaws or

defects

Welding seams

Tight

ness

(in-

situ)

Vacuum

bell,

pressuri

sed

double

seam,

spark-

testing

100% No leaks

Mech

anica

l

prop

erties

(cut

samp

le)

Stress

and

strain at

break 1 nos. per

5,000 m2

Less than

10% negative

deviation on

shear

Less than

25% negative

deviation on

peel

Stress

and

strain at

yield

Works 4: Remediation works of NMK-KIE Page 224

Drainage Layer After the Engineer in Charge has approved the installed HDPE liner, a drainage layer of 0,5 m

thick, consisting of sand shall be installed in the containment cell situated in stagnant water

pond 2. In the containment cell in Lake NMK a drainage layer of 0,35 m thick, consisting of

sand shall be installed.

At the bottom floor of the containment cell drains of 110 mm HDPE have to be applied in the

drainage layer. One drain per 5 meter width. Before sand is applied on the HDPE liner, HDPE

drains 110 mm with filter material wrapped around it shall be installed on the HDPE liner at

intervals of 5 meter between them. Drains have to be lain by hand and fixated with small

heaps of sand. Drains have to be blind at a distance of 1.5 meter from the toe of the inner

slopes towards the perimeter of the containment cells. This allows for vacuum drainage of the

(process) water from the containment cell.

Sand of the drainage layer should be supplied and distributed from areas already covered by

the drainage layer. Where required ramps have to be applied on the supply routes to

guarantee stability of the drainage and HDPE layers. Equipment distributing the soil should be

provided with tracks. Sand of the drainage layer has to be applied in two work courses

consisting of one layer of 25 cm and a second layer of 25 or 10 m cm. Before the second top

layer is applied the top 10 centimeter of the first layer shall be mixed with active carbon at a

dose of 5 kg per sqm.

The powder activated carbon (PAC) has to meet the following criteria:

Iodine number : min. 650

Molasses number (EUR) : max. 700

When the drainage material has been installed, excavations for e.g. installation of drainage

pipes and filter material around the pipes may only be done manually, and all excavated

trenches shall be visually inspected and approved by the Engineer in Charge before drain pipes

are installed.

In the containment cells in lake NMK about 4,025 m3 sand is required for the drainage layer in

the bottom construction. In stagnant water pond 2 about 1,600 sand is required for the

drainage layer. The contractor has to deliver the drainage material. The Contractor shall report

to the Engineer the properties and testing results of the materials he intend to use for the

approval of the Engineer before the first delivery to the site is effectuated.

The drainage layer shall be compacted with 5 T power rollers. The Contractor shall ensure that

the foundation layer shall be compacted into 2 directions with perpendicular orientation.

The inner slope of the core of the ring dyke at stagnant water pond 2 has to obtain slopes 1:1,

and the outer slope of the same has to be 1:3.

On the inner slopes of the containment cells in Lake NMK no sand shall be applied. On those

slopes a non-woven geotextile of 250 g/sq.m (GSE 250 or equivalent) shall be installed. In total

Works 4: Remediation works of NMK-KIE Page 225

about 2,363 m2 geo-textile is required for the coverage of those slopes. With regard to the

specifications of the geo-textile reference is made towards chapter 12, were full specifications

for the geo-textile have been provided.

The content of organic material shall be less than 2%. The coefficient of permeability of the

drainage material shall be k > 10-4 m/s in order to have easy access to the rainfall runoffs and

process waters. The drainage layer shall be clean of any dirt and any contamination.

Grain size distribution:

Sieve size (mm) Quantity of particles (%)

passed through sieves

20 100

10 30 - 100

5 15 - 60

2 5-35

1 0-20

0,5 0-10

Maximum grain size is 20 mm.

Requirements, tolerances and check

Tolerance, requirements and check for foundation layer:

Parameter Requirement Tests

Value Tolerance Nos.

Vertical alignment:

- Level at slopes (1:3) Designed

alignment

+/- 0.03 m 25 per 10,000 m2

- Level at the bottom

(1:>30)

+/- 0.03 m 25 per 10,000 m2

- Thickness of foundation

layer

Min. 0.50 m No single values

less than 0.5 m

25 per 10,000 m2

Grain size distribution of

drainage layer

See table See table 1 per 500 m3

Works 4: Remediation works of NMK-KIE Page 226

7.3 Transport of Clean Material

The Contractor is free to decide the method for transport of clean material e.g. clay, soil or

sand required for the construction of the containment cells. However, the Contractor shall

follow all Indian rules and regulations including all traffic rules. This also apply to transport of

clean material required for other work components.

8 Remediation and clean-up of the drains and swamps 3 and 4 in KIE as well as the discharge channel in the plains

8.1 General

The drains, swamps and stagnant water ponds in KIE as well as the discharge channel in the

plains are all elements of the water management infrastructure of the area. Due to industrial

discharge, surface water erosion and uncontrolled dumping of waste, polluted sediments and

some quantities of waste have accumulated in the drains, swamps, stagnant water ponds and

channel. With regard to the swamps, stagnant water ponds and channel also small volumes of

soil have been polluted.

The objective of this task is to remove waste, sediments and polluted soil from the drains,

swamps, stagnant water ponds and channel. This should result in cleaner drains, swamps,

stagnant water ponds and channel which shall obtain through this remedial action better self

cleaning and sediment trapping capacities and as such shall also attract less waste.

Based on previous investigation results the following volumes of sediments and polluted soil

are expected to be removed:

drains: 300 m3 of sediments

swamps 3 and 4: 200 m3 of sediments and 350 m3 of polluted topsoil

discharge channel: 500 m3 of sediments (part of the sediments consists of more clayey material)

Where waste is present in the drains, swamps, stagnant water ponds and discharge channel

the waste has to be collected separately and transported to the open hill lock area for

temporary storage. It is estimated that about 100 m3 of waste have to be collected from those

areas. The collected waste has to be transported in combination with the waste of the open

hill lock area to the TSDF or municipal waste disposal site. After the waste has been collected

the sediments and soil have to be excavated.

Works 4: Remediation works of NMK-KIE Page 227

The positions of the drains to be cleaned in KIE are presented on Drawing No. IND50-1-6-6

(Refer to Section VI). In a cross section on this drawing a particular example of an drain is

presented.

The topographic situation of swamp 3 is presented on Drawing No. IND50-1-3-1 (Refer to

Section VI). The excavation plan for swamp 3 is presented on Drawing No. IND50-1-3-2 (Refer

to Section VI). A cross section of swamp 3 is presented on Drawing No. IND50-1-3-3 (Refer to

Section VI).

The topographic situation of swamp 4 is presented on Drawing No. IND50-1-4-1 (Refer to

Section VI). The excavation plan for swamp 4 is presented on Drawing No. IND50-1-4-2 (Refer

to Section VI). A cross section of swamp 4 is presented in Drawing No.IND50-1-4-3 (Refer to

Section VI).

The positions of the discharge channel to be cleaned in the plains is presented on Drawing No.

IND50-1-7-1 (Refer to Section VI). In a cross section on this drawing a profile of the channel is

presented.

Given the observed concentrations of contaminants and the mixed character of the waste

water all works under this task have to be carried out under the most strict health and safety

precautions, including the use of suitable boots, gloves, coveralls and masks and a

decontamination and wash unit.

Swamps 3 and 4 are already fenced off from the surrounding area. As it is practically

impossible to fence off the drains in KIE and the channel in the plains it is proposed that the

actual works are separated from the surrounding areas with mobile barriers, bearing clear

instructions not to enter the area of the remediation works.

The sediments and soil have to be removed by means of excavation and directly loaded on

trucks which are water tight and have to be closed at the top. The sediments and soil have to

be transported to stagnant water pond 2 for further processing and dewatering.

Arrived at stagnant water pond 2 the sediments have to be disposed off in a dedicated

compartment from which they have to be pumped with a underwater pump towards the tubes

of geotextile for dewatering and containment. The dedicated compartment has to be

constructed in the deeper part of stagnant water pond 2 with a vertical curtain of geotextile.

The vertical curtain has to be fixated at the bottom with weights and at the top has to be

fixated to closed pipes which floats on the water. If handled with care and appropriate

adjustment between rate of disposal and further forward pumping such a simple construction

is sufficient to control the environmental impact of these operations.

The soil and more clayey material shall be directly disposed in the containment cell were it

shall serve as infill material around the geotubes.

Works 4: Remediation works of NMK-KIE Page 228

8.2 Methodology

The method of excavation and transport can be freely chosen by the Contractor under the

conditions that the below described principles are followed.

Planning of the work has to be coordinated in close operations with staff of TSIIC, the Agricultural University and the adjacent owners of the industrial premises. Works can only commence after the consent of those stakeholders. Any costs related to getting access have to be borne by the Contractor.

Transport routes have to be returned in their original conditions after the works at the drains and channel have been completed.

During transport sediments, soil and adhering water should not be spilled. On regular intervals (around 2 hours in between) the road surface of the transport routes have to be inspected on the presence of evidence of such spills. If such signs are encountered the road surface has to be cleaned immediately.

Excavation of soil and sediments should not lead to an increased design profile of the unlined drains and discharge channel. If additional pollution is observed outside the initial design profile of the unlined drains and discharge channel during excavation, the Contractor shall stop the excavation of the particular area and inform the Engineer in Charge. The Contractor shall follow the instructions from the Engineer in Charge.

Excavations within the original profile of unlined drains or the discharge channel as well as the excavations of swamps 3 and 4 do not require any backfilling. Although the excavation surface has to be levelled in such a way that the surface appears as a smooth surface.

In case the excavations shows indications of unexpected chemical contamination from smell, odour or colour or presence of drums with unknown content, etc.. the Contractor shall stop the excavation of the particular area and inform the Engineer in Charge. The Contractor shall following the instruction from the Engineer in Charge.

The transport zone and working area along the drains and discharge channel should not occupy more than 4 meters in width on one side of the drains or channel. A section of not more than 20 meter in total length along the drains or channel is allowed to be demarcated as “black zone” were no trespassers are allowed.

All vehicles leaving the “black zones” shall be cleaned from soil and waste adhering to the vehicles’ tyres and body. Cleaning shall be performed in the transition zone between the “black zone” and the surrounding areas.

Personnel leaving the ” black zones” have to be decontaminated in a specially demarcated area between the “black zone” and the surrounding area. This area has to

Works 4: Remediation works of NMK-KIE Page 229

be split in a polluted zone, a zone for washing ad a clean zone (“white zone”). A simple but effective mobile setup shall be supplied by the Contractor.

Before the “black zone” can be moved, this zone has to be freed of any signs of contamination.

9 Remediation and clean-up of stagnant water ponds 1 and 2 in KIE

9.1 General

Stagnant water ponds 1 and 2 are elements of the water management infrastructure of the

area. Due to industrial discharge, surface water erosion and uncontrolled dumping of waste,

polluted sediments and some quantities of waste have accumulated in the 2 stagnant water

ponds. With regard to the 2 stagnant water ponds also a considerable amount of original

topsoil has been polluted.

The objective of this task is to remove waste, sediments and polluted soil from the 2 stagnant

water ponds. This should result in cleaner (stagnant water) ponds which shall obtain through

this remedial action better self cleaning and sediment trapping and water buffering capacities

and as such shall also attract less waste.

Based on previous investigation results the following volumes of sediments and polluted soil

are expected to be removed:

Stagnant water pond 2: 5,160 m3 of sediments and 1,720 m3 of polluted topsoil (clay)

Stagnant water pond 1: 1,084 m3 of sediments and 216 m3 of polluted topsoil (clay)

Where waste is present in the stagnant water ponds, the waste has to be collected separately

and transported to the open hill lock area for temporary storage. It is estimated that about 100

m3 of waste has to be collected in total from both stagnant water ponds in total. The collected

waste has to be transported in combination with the waste of the open hill lock area to the

TSDF or municipal waste disposal site. After the waste has been collected the sediments and

soil have to be excavated.

The topographic situation of stagnant water ponds 1 and 2 is presented on Drawing Nol.

IND50-1-1-1 (Refer to Section VI). The excavation plan for stagnant water ponds 1 and 2 is

presented on Drawing No. IND50-1-1-2 (Refer to Section VI). A cross section of stagnant water

ponds 1 and 2 is presented on Drawing No. IND50-1-3-3 (Refer to Section VI).

Given the observed concentrations of contaminants and the mixed character of the waste

water all works under this task have to be carried out under the most strict health and safety

precautions, including the use of suitable boots, gloves, coveralls and masks (reference is made

to section 4.5 of the particular specifications) and a decontamination and wash unit.

Stagnant water ponds 1 and 2 are already fenced off from the surrounding area.

Works 4: Remediation works of NMK-KIE Page 230

The sediments from stagnant water ponds 1 and 2 have to be removed by means of dredging.

A small pontoon equipped with a underwater pump mounted at a portable beam of sufficient

length is already suitable for the job. Sediments have to be directly pumped towards the

containment cells for further processing and dewatering in the tubes of geotextile. Were

required intermediate booster pumps have to be applied to guarantee enough capacity and

sufficient working pressure in the pipe systems through which the slurry of sediments and

water is pumped towards the containment cells.

Stagnant water Ponds 1 and 2 have during the dredging works to be separated from the

surrounding surface water courses. This has to be done with simple temporary dams of earth.

If temporary loss of process water results in a drop of water during dredging this has to be

compensated by the inflow of surface water from the surrounding area.

After the sediments have been removed, the polluted soil has to be removed by means of

excavation. Preferably this shall be done under dry conditions, for which the water level in the

stagnant water ponds shall temporarily be lowered with approximately 1 meter. The soil has to

be transported to stagnant water pond 2 for final disposal in the containment cell as infill and

cover material.

As the containment cell in stagnant water pond 2 can only be constructed after the sediments

and polluted soil have been removed from the footprint of the bottom construction of this cell,

the Contractor is either allowed:

to temporarily store the sediments and polluted topsoil from this part of stagnant water pond 2, in the remaining part of stagnant water pond 2 and stagnant water pond 1. The area of the containment cells has in this case to be isolated from the remaining part of stagnant water pond 2 by an earth dam.

to pump the sediments of stagnant water pond 2 towards the containment cell situated in Lake NMK and temporarily store the polluted topsoil in the remaining part of stagnant water pond 2. To cope with the capacity of the 2 containment cells this implies that a similar volume of sediments from Lake NMK later on has to be pumped towards the containment cell of stagnant water pond 2.

9.2 Methodology

The method of excavation and transport can be freely chosen by the Contractor under the

conditions that the below described principles are followed.

Planning of the work has to be coordinated in close operations with staff operating the pump house and STP.

The soil from stagnant water pond 2 has to be transported within the perimeters of this stagnant water pond by utilizing excavators with an extended arm or by means of a combination of regular excavators and dozers. Soil from stagnant water pond 1 requires intermediate transport with a tractor/dumper combination. The soil from stagnant water pond 1 has either be stockpiled within the perimeter of stagnant water

Works 4: Remediation works of NMK-KIE Page 231

pond 2 (awaiting further transport and application) or has directly to be applied as infill or cover material in the containment cell.

During transport, soil and water should not be spilled. On regular intervals (around 2 hours in between) the road surface of the most direct transport route between stagnant water ponds 1 and 2 has to be inspected on the presence of evidence of such spills. If such signs are encountered the surface of the transport route has to be cleaned immediately.

Excavation of soil and sediments should not go beyond the excavations profiles as presented on the Drawing Nos. IND50-1-1-2 and IND50-1-1-3 (Refer to Section VI). If during excavation and dredging additional pollution or sediments are observed outside the initial excavation profile, the Contractor shall stop the dredging or excavation activities in the particular area and inform the Engineer in Charge. The Contractor shall follow the instructions from the Engineer in Charge.

Excavations within the original excavation profiles do not require any backfilling. Although the excavation surface has to be levelled in such a way that the surface appears as a smooth surface.

In case the excavations shows indications of unexpected chemical contamination from smell, odour or colour or presence of drums with unknown content, etc.. the Contractor shall stop the excavation of the particular area and inform the Engineer in Charge. The Contractor shall follow the instructions of the Engineer in Charge.

All vehicles leaving the premises of stagnant water ponds 1 or 2 shall be cleaned from soil and waste adhering to the vehicles tyres and body. Cleaning shall be performed in the transition zone between the stagnant water ponds perimeters and the surrounding areas.

Personnel leaving the perimeters of the stagnant water ponds has to be decontaminated in a specially demarcated area between the stagnant water ponds and the surrounding area. This area has to be split in a polluted zone, a zone for washing and a clean zone. With appropriate care a simple mobile setup shall be sufficient.

9.3 Methodology for construction of check dam

After the sediment and soil have been removed from stagnant water ponds 1 and 2, 4 concrete

check dams have to be constructed at the edges of stagnant water pond 1. The position of the

check dams and a principal cross section of the check dams are presented on Drawing Nos.

IND50-1-1-1, IND50-1-1-2,IND50-1-1-3 and IND40-1-1-4 (Refer to Section VI). The check damss

shall facilitate the required future sediment trapping in stagnant water ponds 1 and 2.

Works 4: Remediation works of NMK-KIE Page 232

The wall of the check dams has to have an overall thickness of 0.3 meter. The top of the

concrete dam should consists of a 0.1 m thick wearing coat. This dam has to be, along the

entire cross sectional length of the stagnant water pond plus 1.5 meter, placed on top of a

foot plate of 0.3 meter thick and 1.5 m width, which is positioned on top of the stiff clay layers

as present in the subsoil of stagnant water pond 1. The whole structure has to be made of

steel reinforced concrete cement.

Each check dam has to contain a steel pipe in the middle section of the check dam. The top of

the pipe has to be 0.2 m below the top of the check dam. The pipe has to have a diameter of

0.3 m and a wall thickness of 0.01 m. The pipes in check dam numbers 1, 2 and 3 have to

include on the side of stagnant water pond 1 a check valve. The pipe in dam number 4 has to

have such a check valve on the side of stagnant water pond 2. Thickness of the cover of the

check valve and the required flense to connect it to the pipe should be 0.01m. The pipes and

check valves in the 4 check dams shall facilitate the inflow of surface water from Lake NMK as

this is required for the appropriate water management of the 2 stagnant water ponds.

The check dams have to be constructed in a drained construction pit, which is free of water.

The length and the surface height of the 4 check dams is as follows:

Check dam 1: length 7.5, surface top height 0.02 m above FTL

Check dam 2: length 22.5 m, surface top height 0.03 m above FTL

Check dam 3: length 17.5 m, surface top height 0.03 m above FTL

Check dam 4: length 10.5 m, surface top height 0.04 m above FTL

10 Remediation of the sediments in Lake NMK

10.1 General

Previous site investigations have shown that the sediments in Lake NMK are severely

contaminated with among others TPH and heavy metals such among others lead. Removal of

all the polluted sediments from Lake NMK is an essential prerequisite for restoring the water

quality of the Lake towards irrigation standards.

A total of about 32,317 m3 of polluted sediments have been identified to be present in Lake

NMK. The thickness of the sediment layer varies between only a few centimetre till almost 1.5

m. On average the sediment layer is about 0.47 m thick.

The topographic situation of Lake NMK in 2012 is presented on Drawing No. IND50-1/03

(Refer to Section VI). On Drawing No. IND50-1-5-8 (Refer to Section VI) the distribution of the

lead concentration in the sediments of Lake NMK are presented for informative reasons only.

Before the commencement of the works under this Contract, fences and a weir shall be

constructed at Lake NMK under 2 separate Contracts. For informative reasons only the design

Works 4: Remediation works of NMK-KIE Page 233

of the weir is presented on Drawing No. IND50-1-5-12 (Refer to Section VI). The alignment of

the fences is presented on Drawing No,IND50-1-5-7 (Refer to Section VI).

Three cross sections of the Lake, showing the estimated thickness of the sediment layer and a

top view of the distribution of the sediments in 2012 are presented on Drawing No. IND50-1-

5-1 (Refer to Section VI). Drawing No. IND50-1-5-2 (Refer to Section VI) presents the same

cross sections and top view, but now without the previous presented sediments. As such this

drawing gives an impression of the extent of the required dredging volumes in 2012.

10.2 Procedures

Although the thin clay layer underneath the sediments has proven to be contaminated as well,

the integrity of this clay layer has to be maintained at all means as it is an important

prerequisite for the mere existence of the lake. Neither dredging nor unacceptable lowering of

the water level in the lake should result in any damage of the integrity of this clay layer.

Damage to the integrity of the thin clay layer by dredging has to be avoided by selection of

appropriate equipment (for example an dredger equipped with an auger head) and an

accurate and actual 3D model of the sediment layer and the top of the clay layer.

Earlier stability assessments have shown that the stability of the clay layer is at stake when the

water level in the Lake drops below 1.25 m below FTL. As actual stability depends on the water

pressure of the groundwater and the water level in the Lake, daily assessment of the actual

allowed drop in water level has to be assessed by the Contractor on the basis of actual

monitoring results, taking some margin of safety into account.

Given the limited volume of the water balance of Lake NMK loss of process water has to be

avoided at all means. However some temporarily and permanent loss of process water cannot

be avoided. To maintain an optimal water level in the Lake the Contractor has to balance the

rate of dredging, the amount of required process water, the inflow towards the Lake and the

discharge from the Lake in such a manner that under normal conditions the water level in the

Lake is maintained around the FTL level. Discharge from the Lake should be such that the

interests of stakeholders downstream are not harmed and the discharge channel in the plains

shall not fall dry.

As the Lake is a dynamic environment the Contractor has, before the dredging works can

commence, to conduct a continuous survey of the lake with an appropriate technique of his

choice. Survey results have to be supported by additional hand measurements with for

example an auger drill, hand probe or comparable devices. The top of the sediment has to be

measured with an accuracy of + 0.03 m. The top of the clay layer has to be measured with an

accuracy of + 0.02 m. On the basis of the survey results the final volume of sediments in Lake

NMK shall be fixed.

The survey results have to be incorporated in a continuous 3D model of the sediments and the

top of the clay layer. The actual operation and movement of the dredging equipment should

be computer guided on the basis of this 3D model and a high accuracy dGPS positioning

Works 4: Remediation works of NMK-KIE Page 234

system. The combination of the 3D model guidance and dGPS positioning has to allow for a

total dredging accuracy of + 0.03 m.

Given the observed concentrations of contaminants in the sediment all works under this task

have to be carried out under the most strict health and safety precautions, including the use of

suitable boots, gloves, coveralls and masks and a decontamination and wash unit as specified

in section 4.5 under particular specifications.

Lake NMK has already been fenced off from the surrounding area.

The sediments from Lake NMK have to be removed by means of dredging. Before dredging can

commence the Contractor has to establish a baseline investigation of the surface water quality

in the Lake. During the implementation of the dredging works, no water shall be discharged

from the Lake which show visible evidence of pollution or which contain concentrations of

more than 25% above the baseline concentrations. Baseline concentrations have to be

established for the parameters as mentioned in the monitoring requirements for the surface

water in Lake NMK as included in Section V (General Items).

During dredging the Contractor should monitor the water quality near the dredging operations

carefully. For protection of the overall quality of the surface water in Lake NMK he has to

select the appropriate dredging equipment (e.g. a dredger equipped with an auger head) and

apply a full range of protective measures (e.g. vertical screens of geotextile or air bubble

screens to form close compartments). In addition he requires to have a full array of mitigation

measures available for direct action (e.g. surfactants, oil skimmers, etc..).

A relatively small dredging unit equipped with appropriate underwater equipment and

dynamic position guidance is already suitable for the job. Sediments have to be, via a floating

pipeline,directly pumped towards the containment cells for further processing and dewatering

in the tubes of geotextile. Were required intermediate booster pumps have to be applied to

guarantee enough capacity and sufficient working pressure in the pipe systems through which

the slurry of sediments and water is pumped towards the containment cells. The transport

pipes should not leak any sediment/water slurry during the transport.

10.3 Methodology

The method of dredging and transport can be freely chosen by the Contractor under the

conditions that the below described principles are followed.

Planning of the work has to be coordinated in close operations with staff operating the pump house and STP

During transport, sediment and water should not be spilled. On regular intervals (around 2 hours in between) the transport system has to be inspected on the presence of evidence of such spills. If such signs are encountered the system should be repaired to its original functioning.

Works 4: Remediation works of NMK-KIE Page 235

Dredging of sediments should not go beyond the final dredging profiles as established in the basis of the approved 3D model of the Contractor. If during excavation and dredging additional pollution or sediments are observed outside the initial dredging profile, the Contractor shall stop the dredging or excavation activities in the particular area and inform the Engineer in Charge. The Contractor shall follow the instructions from the Engineer in Charge.

In case the excavations shows indications of unexpected chemical contamination from smell, odour or colour or presence of drums with unknown content, etc.. the Contractor shall stop the excavation of the particular area and inform the Engineer in Charge. The Contractor shall follow the instruction from the Engineer in Charge.

All equipment leaving Lake NMK has to be cleaned from sediment and waste adhering to the equipment. Cleaning shall be performed in the transition zone between the lake perimeter and the surrounding areas.

Personnel leaving the perimeters of the Lake has to be decontaminated in a specially demarcated area between the Lake and the surrounding area. This area has to be split in a polluted zone, a zone for washing and a clean zone.

11 Dewatering of the sediments and application of tubes of geotextile

11.1 General

Previous site investigations have shown that the sediments in the drains, swamps and stagnant

water ponds of KIE, Lake NMK and the discharge channel in the plains are severely

contaminated with among others TPH and heavy metals such as lead. Removal of all the

polluted sediments from the drains, swamps, stagnant water ponds, lake and discharge

channel is an essential prerequisite for restoring the water quality of the Lake towards

irrigation standards.

A total of about 32,317 m3 of polluted sediments have been identified to be present in Lake

NMK. And in addition 7,244 m3 of sediments are present in the drains, swamps and stagnant

water ponds in KIE and the discharge channel in the plains.

Based on feasibility testing and assessment of available remediation options on-site

dewatering and containment was selected as the preferred remediation option for the

sediments. De-watering has to be obtained through the use of tubes of geotextile in

combination with the application of flocculants and/or electrolytes into the slurry of sediment

and process water, while containment is obtained through the tubes of geotextile in

combination with the superstructure of the containment cell liner.

Feasibility testing has shown that de-watering of the geotubes shall result at least in a volume

reduction of about 57.5%. This implies that the volume of sediments from NMK has to be

reduced to 13,752 m3 and the volume of the sediments from the drains, swamps, stagnant

Works 4: Remediation works of NMK-KIE Page 236

water ponds and discharge to about 3,080 m3. As such a total storage volume of about 16,832

m3 of sediment is required.

Based on the total storage volume of 16,832 m3 for sediments it is expected that about 147

tubes of geotextile with a circumference of 9 meter and a length of 27.5 meter are required for

the containment of the sediments. The design of the containment cells in Lake NMK are

presented on D Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and

IND50-1-5-11 (Refer to Section VI). This drawing presents a top view and a cross section of the

design of the containment cell with tubes of geotextile.

The design of the containment cell situated at stagnant water pond 2 is presented on Drawings

Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3 (Refer to Section VI). This drawing presents a

top view and a cross section of the design of the containment cell with tubes of geotextile.

Initial feasibility tests showed that for the sediments in KIE a mixture with the following ratios

gave the best results for de-watering and volume reduction: 3,000 ml of in-situ sediment:

9,000 ml of surface water: 960 ml 0.1 % flocculant solution. The following results were

obtained:

Initial volume of in-situ sediment was after dewatering reduced till a volume of only 42.5% of this initial volume;

Pink dyes were completely contained within the test tube

The process water draining from the test tube was colourless without oil film and dye

The analysed effluent from the hanging bag test shows low concentrations of heavy metals and TPH.

Heavy metals and TPH retained well in the sludge after dewatering in the test tubes.

The indicative leaching test (shake test) with the dewatered sludge shows that there is almost no release of heavy metals and TPH

The dewatered sludge released very well from the geotextile of the test tube

The obtained rate of dewatering was meeting the overall time requirements of the entire project.

Typical analytical results in µg/l for the process water draining from the test tube were in the

following range:

Sample As [µg/l]

Cd [µg/l]

Cr [µg/l]

Cu [µg/l]

Hg [µg/l]

Ni [µg/l]

Pb [µg/l]

Zn [µg/l]

TPH (sum C10-C40) [µg/l]

Water sample 1 1.5 < 0.4 < 5.0 5.3 < 0.10 5.2 16 30 1,100 Water sample 2 1.8 < 0.4 8.1 14 0.12 8.2 45 65 110 Water sample 3 2.0 < 0.4 < 5 < 5 < 0.1 < 5.0 5.3 16 1,000

Works 4: Remediation works of NMK-KIE Page 237

The results of a leaching test simulating a leaching period of at least 20 years showed the

following leaching result in mg/kg dm:

Sample As mg/kg

Cd mg/kg

Cr mg/kg

Cu mg/kg

Hg mg/kg

Ni mg/kg

Pb mg/kg

Zn mg/kg

TPH (sum C10-C40) mg/kg

Sludge after dewatering

< 0.1 < 0.002

0.053 < 0.1 < 0.0008

< 0.1 < 0.2 < 0.6

4.4

Based on aforementioned test about 12,660 kg of pure flocculent is required for the

dewatering of all sediments from Lake NMK, the drains of KIE, swamp 3 and 4, stagnant water

pond 1 and 2 and the channel in the plains. With raw water from Lake NMK and an mixing unit

the Contractor has to prepare a 0.1% flocculent solution on-site.

11.2 Procedures

The selected final type and concentration of flocculents/electrolytes and their application

ratio’s are subject to prior approval by The Client and it’s supervising Consultant.

The contractor has to supply, prepare and apply a suitable flocculants/electrolytes in order to

have sufficient coagulation and flocculation to achieve the following:

• The process water draining from the geo tube should be colourless without oil film and dye

• The analyzed process water should show low concentrations of heavy metals and TPH.

• Heavy metals, dyes and TPH shall be retained in the sludge after dewatering in the Geo

tubes.

• The indicative leaching test (shake test) with the dewatered sludge shall demonstrate no

release of heavy metals and TPH

• Clear separation of sludge after addition of flocculant should be obtained,

The volume of sediments shall be reduced to 40% after dewatering.

Any flocculent and/or electrolyte solution proposed by the Contractor shall at least meet all of

the aforementioned results of the initial feasibility test.

The time taken for selection of a suitable flocculant / electrolyte and its approval from the

engineer in charge shall be a part of the timeline given for the completion of the particular

milestone. No additional time shall be given for this activity.

Works 4: Remediation works of NMK-KIE Page 238

As the type and concentration of flocculant/electrolyte and its application ratio’s proved to be

very critical the Contractor has to reassess the required type, concentration and application

rates of the flocculants and/or electrolytes before the de-watering commences. The

Contractor is responsible for taking representative and sufficient sludge samples to analyse the

sediments, perform in situ tests, to determine dosages and types of polymers if necessary, and

control their injection to obtain good flocculation.

Dewatering operations have to include all costs, charges tools and plants, materials, labour

and manpower, dredgers, pumps, control units, mixing units, valves, transport lines,

excavators, loader backhoes, front end loaders, tractor trailors, etc complete as directed by

engineer in charge and to the satisfaction of engineer in charge

In the presence of the Engineer in Charge the Contractor has to discuss his plan for the

complete dewatering procedures and layouts with the tube manufacturer. During this meeting

also the results of the tests performed on the sludge have to be discussed. Those test have to

be conducted in accordance with protocols developed by the manufacturer of the tubes.

Those protocols have to be submitted to the Engineer in Charge before any test shall

commence or decisions on the sizing the tubes shall be made.

The tube manufacturer has to be certificated and a copy of this certificate has to be provided

to the Engineer in Charge. In this context, a traceability procedure has to be in place to be able

to determine possible causes in the event of a failure of a tube based on stored reference

samples at the factory.

The manufacturer of woven tubes has to control the quality of all stages of production, the

production of the yarns, the weaving and the final tube manufacturing.

The yarns have to be specifically designed for dewatering and solids containment. Similarly the

woven tubes should be designed specifically for dewatering and solids containment.

The Contractor has to be able to submit protocols for testing the sediments, the polymer

selection and safety and best practice during the dewatering. The Contractor should be able to

submit evidence that his protocols are valid and that those protocols are fully supported by the

manufacturer of the tubes.

Works 4: Remediation works of NMK-KIE Page 239

The Contractor has to provide evidence to the Engineer in Charge that the design of the

facilities (platform - polymer station, waste management, etc.) has been discussed with the

tube manufacturer and that the comments forwarded by the last have been included in the

final design.

Textiles used in the manufacturing of the tubes have to meet the following filtration

characteristics:

- The tube must be made from a woven monofilament polypropylene,

manufactured so that the yarns retain their respective positions in whatever direction force

is exerted. Textiles must be stable vis-à-vis biological degradation and resistant to naturally

occurring chemicals such as alkalis and acids and naturally occurring UV conditions .

- Tensile strength MD according to EN-ISO 10319 ≥ 70 kN / m

- CD according to EN-ISO 10319 ≥ 95 kN / m

- Permeability according to EN ISO 11058 ≥ 1,800 liters / m². min

- Characteristic opening O90 according to EN ISO 12956 250mμ

- UV Resistance after exposure to 200 KLY 12224 and EN ISO 12226 60%

- Minimum strength of circumferential seams according to EN ISO 10321

≥ 65 kN / m

On demand of the Chief Engineer in Charge the Contractor has to submit the results of control

tests on seam strength at the delivery of the tubes on site.

Only a single longitudinal seam will be permitted on each tube.

Each tube has to be produced with one or more filling points. These filling points have to be

located on the centre line of the tube surface. The filling points have to be constructed with

flanges to maintain fabric stability during filling.

The tubes have to be delivered to the site, wound on a core of steel and protected by a

package provided with a label for traceability. The packaging shall be removed at the last

moment and labels retrieved and delivered to the Engineer in Charge.

Final Size (length and perimeter) of the tubes has to be defined following the results of the

aforementioned qualification tests as conducted by the Contractor, in terms of volume in situ

process, and depending on the space available for storage of tubes.

Works 4: Remediation works of NMK-KIE Page 240

Given the observed concentrations of contaminants in the sediment, all works under this task

have to be carried out under the most strict health and safety precautions, including the use of

suitable boots, gloves, coveralls and masks and a decontamination and wash unit as specified

in section 4.5 under particular specifications).

The containment cells near Lake NMK and in stagnant water pond 2 have already been fenced

off from the surrounding area (in earlier stages of the project).

During the implementation of the de-watering works, no water shall be discharged into the

Lake which show visible evidence of pollution or which contain concentrations of more than

25% above the baseline concentrations. Baseline concentrations have to be established for the

parameters as mentioned in the monitoring requirements for the surface water in Lake NMK

as included in Section V (General Items). In addition no traces of electrolytes and/or

flocculants should be traceable at the discharge point of the Lake near the new weir.

During de-watering the Contractor should monitor the water quality near the discharge points

of the process water carefully on the basis of daily visual observations.

The Contractor has to assure that the water sediment slurry is at all times arriving at the

platform, mixing unit and/or geotubes at the required working pressure and the appropriate

sediment:surface water ratio, in accordance with the specifications of his final design. These

working pressures and ratios have to be monitored and recorded continuously. The same

applies for all of the required working conditions of the mixing and dosing unit for the

flocculants/electrolytes and their injection rates. If deviations from the specifications of the

final design of the Contractor occur, the Contractor has to take all necessary corrective actions

immediately.

Given the vulnerability of the water balances it is important that free process water is

recharging Lake NMK and the stagnant water ponds as soon as possible. For this reason the

Contractor has to guarantee optimal drainage of the containment cell at all times with an

appropriate number of pumps. A free water layer thickness of more than 0.1 meter is not

allowed to be present in the containment cell at any time. Were required drainage of process

water has to be supported by vacuum pumps which are connected to the drainage pipes which

are situated in the drainage layer of the containment cells.

11.3 Methodology

Exact details of dewatering with tubes of geotextile and flocculants/electrolytes depent on

final work plan that the Contractor has to elaborate. Small deviations from the design,

specifications, scope of work, etc.. as presented in the bidding documents can be accepted

under the conditions that the below described principles are followed.

Planning of the work has to be coordinated in close operations with staff operating the pump house and STP.

Works 4: Remediation works of NMK-KIE Page 241

During dewatering, sediment and water should not be spilled. On regular intervals (around 2 hours in between) the dewatering system has to be inspected on the presence of evidence of such spills. If such signs are encountered the system should be repaired to its original functioning.

Application of tubes of geotextile should not go beyond the final design profiles as approved by the Engineer in Charge. If during dewatering additional storage volumes are required, the Contractor shall stop the dewatering and inform the Engineer in Charge. The Contractor shall follow the instructions from the Engineer in Charge.

All equipment leaving the containment cells has to be cleaned from sediment and waste adhering to the equipment. Cleaning shall be performed in the transition zone between the lake perimeter and the surrounding areas.

Personnel leaving the perimeters of the Lake has to be decontaminated in a specially demarcated area between the Lake and the surrounding area. This area has to be split in a polluted zone, a zone for washing and a clean zone.

12 Design of Cover Layer Containment Cell

After dewatering of the sediments has been completed , the filled tubes with sediments have

been stabilized sufficiently and the drainage layer at the bottom of the containment cell is dry,

the cover layer (capping of the tubes filled with sediments in the containment cells) shall be

laid.

The final cover of the containment cell in stagnant water pond 2 shall be designed to minimize

infiltration and erosion. The final cover shall meet the following specifications, namely:

A fill layer of clay or stiff soil of at least 30 cm thick covering the tubes of geotextile filled with sediment completely. Extra fill material has to be applied at the projected slopes of the containment cells to guarantee smooth 1:3 slopes.

A sand layer (20 cm thick)

HDPE layer of 2 mm

Drainage layer (20 cm thick)

On top of the Drainage layer a protective cover of non woven Geotextile (GSM 250) shall be laid for separating the drainage & vegetative layer.

On top of the non woven Geotextile (GSM 150) layer there shall be a vegetative layer (ordinary earth) of 80 cm to support natural plant growth and to minimize erosion.

Revetment has to be installed at one of the slopes of the containment cell in stagnant water pond 2

Works 4: Remediation works of NMK-KIE Page 242

The final cover of the containment cells in Lake NMK shall be designed to minimize infiltration

and erosion. The final cover shall meet the following specifications, namely:

A fill layer of clay or stiff soil has to be applied at the projected sides of the containment cells to guarantee that the projected volume of the cells is filled up completely. ›

A protective layer of non-woven geo-textile 250 g/sq. m (GSE 250 or equivalent) ›

HDPE layer of 2 mm

Drainage layer consisting of a sandwich construction of two geo-textiles and an artificial drainage element in between with a high water flow capacity

On top of the drainage layer there shall be a vegetative layer (ordinary earth) of 50 cm to support natural plant growth and to minimize erosion.

12.1 General

Conceptual design of the top liner construction of the containment cells are shown on

Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10, IND50-1-5-

11, IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3 in Section VI. The Contractor shall make sure

that the construction of the top liner of the containment cells is in accordance with the Indian

Standard HWM 2008.

Total area of the top liner construction of the containment cells in Lake NMK shall be

approximately 11,500 m2 in total. Total area of the top structure of the containment cell in

stagnant water pond 2 shall be approximately 4,625 m2, which is equal to an projected

footprint of about 90 by 60 m (exclusive the future drain around the cell).

After completion of the top liner construction of the containment cell a construction shall be

established which is designed to minimize infiltration of rain water and provide a stabile

compartment for the containment of the contaminated sediments.

12.2 Methodology

12.2.1. Fill layer After dewatering of the sediments has been completed , the filled tubes with sediments have

been stabilized sufficiently and the drainage layer at the bottom of the containment cell is dry,

the fill layer has to be installed. A fill layer of clay or stiff native soil with a thickness of at least

30 cm has to be applied in the containment cell in stagnant water pond 2.

The applied clay shall have a minimum plasticity index of 12 as tested by Atterberg Limit tests

(ASTM D4318). Clay materials shall contain no sod, brush, roots, frozen soil, or other

Works 4: Remediation works of NMK-KIE Page 243

perishable materials. Rock particles larger than 3 inches shall be removed prior to compaction

of the clay

The fill layer has to provide for a flat working platform. Additional fill material at the sides of

the tubes filled with sediments has to guarantee smooth 1:3 slopes.

In the containment cells in Lake NMK no minimum thickness is required. Here the fill material

has to fill up the remaining volume of the containment cell.

In stagnant water pond 2 about 1,351 m3 of soil is required for the fill layer. In the

containment cells at the western and northern bunds of Lake NMK about 1.500 m3 of soil is

required to fill the remaining volume of the containment cell. In the containment cells at the

south eastern corner of Lake NMK about 1,125 m3 of soil is required to fill the remaining

volume of the containment cell and to provide for the final slopes of 1:100. Clay and soil (4,176

m3) excavated during the remediation and construction activities has to be utilized for the

construction of the fill layer.

The fill layer shall be compacted with hand operated power rollers for each layer of 0,5 m

thick. If the fill layer is thicker than 0.5 meter, the layer has to be installed in separate layers of

which none is thicker than 0.5 m. Each layer should at least be compacted into 2 directions,

with a minimum of 2 passes in each direction, with perpendicular orientation.

The fill layer should result in a stable and flat working area, on which the remaining top liner

construction of the containment cell has to be further installed. The outer slope has to be 1:3.

After leveling no large differences in height (> 3 cm) on the surface of the fill layer shall remain.

Soil materials used for the fill layer shall be free of any material with particular seize above 5

centimeter. The content of organic material shall be less than 4%.

Requirements, tolerances and check

Tolerance, requirements and check for drainage layers:

Parameter Requirement Tests

Value Tolerance Nos.

Vertical alignment:

- Level at slopes (1:3) Designed

alignment

+/- 0.03 m 25 per 10,000 m2

- Level at top (1:>30) +/- 0.03 m 25 per 10,000 m2

- Top of fill layer Designed

alignment

+/- 0.03 m 25 per 10,000 m2

Maximum grain size and

organic matter content

See text

above

See text above 1 per 1,000 m3

Works 4: Remediation works of NMK-KIE Page 244

12.2.2. Foundation layer in stagnant water pond 2 Once the fill layer has been installed the foundation layer has to be applied in one work course.

A foundation layer of 0,2 m thick consisting of sand has to be applied. Sand should be supplied

and distributed from areas already covered by the foundation layer. Where required ramps

have to be applied on the supply routes to guarantee stability of the foundation layers.

Equipment distributing the soil should be provided with tracks.

In stagnant water pond 2 about 525 m3 of sand is required for the foundation layer. The

contractor has to deliver the foundation material. The Contractor shall report to the Engineer

the properties and testing results of the materials he intend to use for the approval of the

Engineer before the first delivery to the site is effectuated.

The foundation layer shall be compacted with hand operated power rollers. The Contractor

shall ensure that the foundation layer shall be compacted into 2 directions, with a minimum of

2 passes in each direction, with perpendicular orientation.

The foundation layer should result in a stable and flat working area, on which the HDPE liner of

the containment cell has to be further installed. The outer slopes of the same has to be 1:3.

Just before the installation of the HDPE liner the top of the foundation layer shall be leveled.

After leveling no large differences in height (> 2 cm) on the surface of the foundation layer

shall remain and the surface should be free of any debris that could damage the liner or

prevent an even/smooth deployment of the liners.

The content of organic material shall be less than 2%. The coefficient of permeability of the

drainage material shall be k > 10-4 m/s.

Grain size distribution:

Sieve size (mm) Quantity of particles (%)

passed through sieves

20 100

10 30 - 100

5 15 - 60

2 5-35

1 0-20

0,5 0-10

Maximum grain size is 20 mm.

Requirements, tolerances and check

Works 4: Remediation works of NMK-KIE Page 245

Tolerance, requirements and check for foundation layer:

Parameter Requirement Tests

Value Tolerance Nos.

Vertical alignment:

- Level at slopes (1:3) Designed

alignment

+/- 0.02 m 25 per 10,000 m2

- Level at top (1:>30) +/- 0.02 m 25 per 10,000 m2

- Thickness of foundation

layer

Min. 0.20 m No single values

less than 0.2 m

25 per 10,000 m2

Grain size distribution of

drainage layer

See table See table 1 per 500 m3

12.2.2. Foundation layer in containment cells of Lake NMK Once the fill layer has been installed a geo-textile layer has to be installed for the protection of

the HDPE liner above.

Requirements of Geotextiles The Geotextile shall be a non-woven Geotextile of UV-stable polypropylene, polyethylene or

polyester capable of resisting exposure to the sun for minimum two years.

A protective layer with GSM 250 or equivalent qualities has to be installed to protect the HDPE

liner.

Net demand of geotextile in the top structure of the containment cell in Lake NMK is 11,500

m2.

The Geotextile shall be installed with the HDPE liner on top and below by the fill layer or tubes

of geotextile. Thus after installation the Geotextile shall be protected against UV-radiation.

Simple overlapping with a width of min. 0.5 m shall connect lanes of installed Geotextile.

Alternatively sewn connections may be used. Sewn connections shall have tensile strength

equal to the tensile strength of the Geotextile.

Delivery, Unloading, Site Handling and Storage Requirements for Geotextiles The Geotextile shall be stored and handled during the construction works in such a way, that

the product after installation has no sign of damages or reduction in performance due to UV-

radiation. The manufactures guidelines for storage, handling and installation of Geotextile shall

be followed.

Material Delivery:

a) Upon arrival on site, QA personnel shall take an inventory of all materials on-site.

Works 4: Remediation works of NMK-KIE Page 246

b) Roll numbers of the non- woven Geotextile shall be logged on the inventory Check List and cross referenced with the Bill of Loading.

c) Copies of Inventory Check List and signed Bill of Loading should be sent to supplier headquarters while the on-site QA personnel retain the original copies.

d) Any visible damage to roll materials should be noted on the roll and Inventory Check List.

Site Unloading Procedures:

a) A forklift or front end loader fitted with a tapered pole is recommended for loading & unloading no woven Geotextile rolls.

b) The pole should be long enough to extend at least 2/3 (10 feet) of the way in to the non woven Geotextile roll core to avoid the possibility of buckling or breaking the core.

c) Non-woven Geotextile rolls may be lifted from flatbed trailers using straps hoisted by a crane of loader.

d) No more than three rolls should be lifted at the same time. For special length rolls, 1,000 feet or longer, each roll should be handled one at a time.

Site Handling & Storage Procedures:

a) Non – woven Geotextile rolls should be lifted off of the ground when moving.

b) Non- woven Geotextile should be deployed as closely as possible to the designated location minimizing dragging against the ground surface.

c) Operations of heavy construction equipment directly on the non- woven Geotextile should be avoided.

d) Non – woven geotextiles should be stored in a flat, dry and well drained area. All sources of contamination, such as oil, grease, soil and aggregate should be separated from the materials.

e) During on-site storage, non-woven geotextiles rolls should be protected from moisture, sunlight, theft and vandalism.

f) The protective wrapping should not be removed until the non- woven geotextiles is ready to be installed.

g) If stored outdoors for long durations, the non woven Geotextile should be elevated from the ground surface and covered with a tarpaulin or other opaque plastics.

Ultraviolet Light Exposure:

When left exposed to ultraviolet light, all non woven geotextiles slowly degrade, losing

strength in the process. It is highly recommended not to expose non woven geotextiles to

sunlight prior to installation. Once installed, geotextiles should be covered with designated

Works 4: Remediation works of NMK-KIE Page 247

overlaying material. The non – woven Geotextile should not be left exposed to sunlight for

more than 30 days.

Installation Procedure for Geotextiles Non-woven Geotextile should be installed only after the underlying material or sub grade has

been properly inspected and approved. The non – woven geotextiles should be installed to the

grade and location specified in project specifications. The project construction quality

assurance and construction quality control (CQA/CQC) guidelines must be followed during the

installation.

Care should be taken not to entrap stones or excessive moisture in the non woven Geotextile

during placement. In the presence of Wind, all geotextiles should be weighed with temporary

ballasting such as sandbags. On slopes, the non- woven Geotextile should be securely

anchored and then rolled down the slope in such a manner as indicated by good construction

practices and safety considerations.

Prior to the placement of overlying materials, a Certificate of Acceptance must be signed by a

responsible party and an installer’s representative. All overlying materials on the non woven

Geotextile should be placed such that:

The non - woven Geotextile and the underling material are not damaged.

Any movement on the non – woven Geotextile is kept to a minimum.

Excess stresses in the non- woven Geotextile are kept to a minimum.

12.2.3. Barrier Layer with HDPE liner After the foundation layer has been applied and leveled a barrier layer of HDPE shall be

installed.

The final top liner construction shall have a barrier layer with a permeability coefficient less

that 1 x 10-7 cm/sec or less. This has to be achieved with provision a liner of 2.0 mm HDPE (as

per standard specifications of HWM 2008 rules).

The liner system reduces the infiltration of rain water. Net demand of HDPE liner in the top

structure of the containment cell in Lake NMK is 11,500 m2. In stagnant water pond 2 the net

demand is about 3,140 m2 HDPE liner.

The construction of the liner is as such that the different bands are welded providing a

completely closed membrane preventing rain water to enter the contained sediments.

The installation procedure must be planned in such a way, that the total installation - i.e. from

installing the first strip of HDPE liner until the start to the installation of the drainage layer is

performed as a continuous operation, ensuring that at no time an installed area of HDPE liner

is left open/uncovered for longer time than absolutely necessary.

Works 4: Remediation works of NMK-KIE Page 248

Description of Liner System The liner system consists of one 2.0 mm textured (both sites) HDPE liner (to enhance the slope

stability).

Requirements and specification of HDPE liner

The material for the polymer liner shall be High Density Poly Ethylene (HDPE) with the

following specifications:

Parameter Requirement Tolerance Check method

Appearance No visible flaws or defects

Textured on both sites

Visual inspection

Thickness 2.0 mm - 10 % ISO 4648:1991 or

similar standard

Density min. 0.94 g/cm3 Non ASTM D 1505

Melt Flow Index (190/5) 0,6 - 2.0 g/10min Non ASTM D1238

Carbon Black Content min. 2.0 % Non ASTM D4218

Tensile characteristics:

ASTM D792, Type

IV

Machine and cross-machine

direction:

- Tensile strength at break min. 15 N/mm Non

- Tensile strength at yield Min. 20 N/mm Non

- Elongation at break Min. 100% Non

- Elongation at yield Min. 10% Non

Tear resistance Min. 150 N Non ASTM D 1004

Puncture Resistance Force min. 300 N Non ASTM D 4833

Strength of welded seams

ISO 527-3:1993

ISO 37:1994 or

similar standard

- Shear Min. 90% of tensile

strength at point of yield Non

- Peel Min. 75% of tensile

strength at point of yield Non

Works 4: Remediation works of NMK-KIE Page 249

Parameter Requirement Tolerance Check method

Oxidative Induction Time Min. 100 min non ASTM D 3895

Environmental stress-cracking Min. 200 hours

non ASTM D 5397-99,

Appendix

Delivery and Storage Requirements for HDPE Liners The liner material shall be delivered at the site with a datasheet from the producer certifying

the characteristics of the material according to the above specifications. Further the delivery

shall be accompanied by a protocol with the results of the producers quality check for the

specific batch delivered to the site

The membrane shall be protected against physical damages during transport to the site and

during storage at the site.

The manufactures guidelines for storage, handling and installation of the HDPE liner shall be

followed.

Conformance Testing for HDPE liners

General

The installer shall elaborate an installation plan showing the position of the individual rolls of

material and deliver the plan to the Engineer for approval before installation works

commence.

Installation may only be done by technical staff approved by the producer of the liner material

(the manufacturer) and with equipment approved by the same.

Welding

All welding-seams shall be double-seam welds with the possibility of testing with pressurised

air, or extrusion welds with a spark-leader welded into the seam, enabling full testing of the

tightness of the seams with high-voltage spark methods.

At the beginning and end of each day of installation a welding test shall be performed by each

combination of welding equipment and welder in work to ensure the correct adjustments of

welding temperature, pressure and -speed according to the prevailing weather conditions. The

welding shall be tested for seam strength (peel and shear) and the results are reported to the

Engineer.

The welding test shall be repeated after any interruption of the installation works during the

day, caused by e g. changes in weather conditions or equivalent.

The tests have to be performed by the Contractor himself or a recognised laboratory with

suitable testing equipment and experience.

Works 4: Remediation works of NMK-KIE Page 250

Before welding each lane of material shall be laid out without wrinkles, but with sufficient

material and overlapping to ensure, that no significant problems arise during the welding due

to temperature variations.

All edges of the liner material shall be protected against soiling until the time of welding. The

Contractor decides the method for protection and submits the description to the Engineer for

approval.

Overlapping shall be done with overlaps in the direction of the slope of the liner, i.e. roof-tile

like.

The seam between the membrane at any near-horizontal areas and the membrane at a slope

shall be positioned at the near-horizontal plane and no closer to the top of the slope than 1.0

m.

No machinery of any kind is allowed to operate directly on top of the installed liner. At all

times sufficient protection of the liner shall be ensured before any machinery is allowed to

enter. Sufficient protection has to be e.g. min. 1.0 m of soil for wheel operated equipment or

0.5 m of soil for track operated equipment.

Covering

Until the membrane has been checked and approved the liner material shall be anchored using

sandbags or any other equivalent system ensuring, that the installed liner material is not

moved by wind or down slope by gravity.

The Contractor shall cover the installed liner with a soil layer immediately upon check and

approval by the Engineer. At slopes the cover material shall be installed starting from the toe

of the slope taking any slack in the liner material to the top of the slope. The liner shall be

anchored at all beams.

Check of liner material and installation

The check of the installation works shall be based on a check plan elaborated by the Contractor

and approved by the Engineer. The check plan shall describe who has the responsibility for

performing each check, the extent of the check and when the check shall be performed.

Further the plan shall indicate whether the works may proceed or shall wait pending the

results of the tests and checks.

Stage Item Subject

to check

Method Extent Acceptance

Delivery Liner

material

Datashee

t

quality check 1 nos. per

roll

Delivered

Reception Liner Appearan Visual 1 nos. per No flaws or defects

Works 4: Remediation works of NMK-KIE Page 251

Stage Item Subject

to check

Method Extent Acceptance

material ce 2,000 m2

Thickness Measurement 1 nos. per

2,000 m2

Less than 10%

negative deviation

from specification

Mechanic

al

propertie

s

Stress and strain at

break 1 nos. per

2,000 m2

Less than 10%

negative deviation

from specification Stress and strain at

yield

Start of

welding

Welding

seams

Tightness

(in-situ)

Vacuum bell,

pressurised double

seam, spark-testing

1 nos. per

welder per.

welding

machine

per. day

cut sample

min.36 cm

x 60 cm

No leaks

Strength

(cut

sample) Shear and peel

Sheer: Min. 90% of

tensile strength at

point of yield

Peel: Min. 75% of

tensile strength at

point of yield

During

installation

Liner

material

Appearan

ce Visual 100% No flaws or defects

Welding

seams

Tightness

(in-situ)

Vacuum bell,

pressurised double

seam, spark-testing

100% No leaks

Mechanic

al

propertie

s

(cut

sample)

Stress and strain at

break

1 nos. per

5,000 m2

Less than 10%

negative deviation on

shear

Less than 25%

negative deviation on

peel

Stress and strain at

yield

Works 4: Remediation works of NMK-KIE Page 252

12.2.4. Drainage Layer in stagnant water pond 2 After the Engineer in Charge has approved the installed HDPE liner, a drainage layer of 0,2 m

thick, consisting of sand shall be installed.

At the top of the slope, at the intermediate terrace and the toe of the slope drains of 110 mm

HDPE have to be applied in the drainage layer. These drains have to be connected to 110 mm

blind pipes which shall convey the drainage water along the outer slope of the drainage layer

towards the toe ditches of the storm water runoff system. Blind pipes have to be laid with an

interval of 30 meter.

Before sand is applied on the HDPE liner, the HDPE drains 110 mm with filter material wrapped

around it have to be installed on the HDPE liner. Drains have to be lain by hand and fixated

with small heaps of sand.

Sand of the drainage layer should be supplied and distributed from areas already covered by

the drainage layer. Where required ramps have to be applied on the supply routes to

guarantee stability of the drainage and HDPE layers. Equipment distributing the soil should be

provided with tracks. Sand of the drainage layer has to be applied in one work course

consisting of one layer of 20 cm.

When the drainage material has been installed, excavations for e.g. installation of drainage

pipes and filter material around the pipes may only be done manually, and all excavated

trenches shall be visually inspected and approved by the Engineer in Charge before drain pipes

are installed.

At the cell in stagnant water pond 2 about 925 m3 sand is required for the drainage layer. The

contractor has to deliver the drainage material. The Contractor shall report to the Engineer the

properties and testing results of the materials he intend to use for the approval of the Engineer

before the first delivery to the site is effectuated.

The outer slope of the same has to be 1:3.

The content of organic material shall be less than 2%. The coefficient of permeability of the

drainage material shall be k > 10-4 m/s in order to have easy access to the rainfall runoffs and

process waters. The drainage layer shall be clean of any dirt and any contamination.

Grain size distribution:

Sieve size (mm) Quantity of particles (%)

passed through sieves

20 100

10 30 - 100

5 15 - 60

2 5-35

Works 4: Remediation works of NMK-KIE Page 253

Sieve size (mm) Quantity of particles (%)

passed through sieves

1 0-20

0,5 0-10

Maximum grain size is 20 mm.

Requirements, tolerances and check

Tolerance, requirements and check for drainage layer:

Parameter Requirement Tests

Value Tolerance Nos.

Vertical alignment:

- Level at slopes (1:3) Designed

alignment

+/- 0.02 m 25 per 10,000 m2

- Level at the bottom

(1:>30)

+/- 0.02 m 25 per 10,000 m2

- Thickness of foundation

layer

Min. 0.20 m No single values

less than 0.2 m

25 per 10,000 m2

Grain size distribution of

drainage layer

See table See table 1 per 500 m3

12.2.5. Protective layer with non woven geo-textile Requirements of Geotextiles Geotextile are used for protection of the drainage layer against penetration of dirt and fines

from the vegetative layer.

The Geotextile shall be a non-woven Geotextile of UV-stable polypropylene, polyethylene or

polyester capable of resisting exposure to the sun for minimum two years.

A protective layer with GSM 150 or equivalent qualities has to be installed to protect the

drainage layer.

In stagnant water pond 2 the net demand is about 4625 m2 geotextile.

The Geotextile shall be installed with the vegetative layer on top and below by the drainage

layer. Thus after installation the Geotextile shall be protected against UV-radiation.

Simple overlapping with a width of min. 0.5 m shall connect lanes of installed Geotextile.

Alternatively sewn connections may be used. Sewn connections shall have tensile strength

equal to the tensile strength of the Geotextile.

Works 4: Remediation works of NMK-KIE Page 254

Delivery, Unloading, Site Handling and Storage Requirements for Geotextiles The Geotextile shall be stored and handled during the construction works in such a way, that

the product after installation has no sign of damages or reduction in performance due to UV-

radiation. The manufactures guidelines for storage, handling and installation of Geotextile shall

be followed.

Material Delivery:

e) Upon arrival on site, QA personnel shall inventory all materials on-site.

f) Roll numbers of the non- woven Geotextile shall be logged on the inventory Check List and cross referenced with the Bill of Loading.

g) Copies of Inventory Check List and signed Bill of Loading should be sent to supplier headquarters while the on-site QA personnel retain the original copies.

h) Any visible damage to roll materials should be noted on the roll and Inventory Check List.

Site Unloading Procedures:

e) A forklift of front end loader fitted with a tapered pole is recommended for loading & unloading no woven Geotextile rolls.

f) The pole should be long enough to extend at least 2/3 (10 feet) of the way in to the non woven Geotextile roll core to avoid the possibility of buckling or breaking the core.

g) Non-woven Geotextile rolls may be lifted from flatbed trailers using straps hoisted by a crane of loader.

h) No more than three rolls should be lifted at the same time. For special length rolls, 1000 feet or longer, each roll should be handled one at a time.

Site Handling & Storage Procedures:

h) Non – woven Geotextile rolls should be lifted off of the ground when moving.

i) Non- woven Geotextile should be deployed as closely as possible to the designated location minimizing dragging against the ground surface.

j) Operations of heavy construction equipment directly on the non- woven Geotextile should be avoided.

k) Non – woven geotextiles should be stored in a flat, dry and well drained area. All sources of contamination, such as oil, grease, soil and aggregate should be separated from the materials.

l) During on-site storage, non-woven geotextiles rolls should be protected from moisture, sunlight, theft and vandalism.

Works 4: Remediation works of NMK-KIE Page 255

m) The protective wrapping should not be removed until the non- woven geotextiles is ready to be installed.

n) If stored outdoors for long durations, the non woven Geotextile should be elevated from the ground surface and covered with a tarpaulin or other opaque plastics.

Ultraviolet Light Exposure:

When left exposed to ultraviolet light, all non woven geotextiles slowly degrade, losing

strength in the process. It is highly recommended not to expose non woven geotextiles to

sunlight prior to installation. Once installed, geotextiles should be covered with designated

overlaying material. The non – woven Geotextile should not be left exposed to sunlight for

more than 30 days.

Installation Procedure for Geotextiles Non-woven Geotextile should be installed only after the underlying material or sub grade has

been properly inspected and approved. The non – woven geotextiles should be installed to the

grade and location specified in project specifications. The project construction quality

assurance and construction quality control (CQA/CQC) guidelines must be followed during the

installation.

Care should be taken not to entrap stones or excessive moisture in the non woven Geotextile

during placement. In the presence of Wind, all geotextiles should be weighed with temporary

ballasting such as sandbags. On slopes, the non- woven Geotextile should be securely

anchored and then rolled down the slope in such a manner as indicated by good construction

practices and safety considerations.

Prior to the placement of overlying materials, a Certificate of Acceptance must be signed by a

responsible party and an installer’s representative. All overlying materials on the non woven

Geotextile should be placed such that:

The non - woven Geotextile and the underling material are not damaged.

Any movement on the non – woven Geotextile is kept to a minimum.

Excess stresses in the non- woven Geotextile are kept to a minimum.

12.2.4. Drainage Layer in containment cells at Lake NMK After the Engineer in Charge has approved the installed HDPE liner, a drainage layer of a

sandwich construction of two geo-textiles and an artificial drainage element in between with a

high water flow capacity has to be installed.

At the edge of the gabions drains of 110 mm HDPE have to be applied in the drainage layer.

These drains have to be connected to 110 mm blind pipes which shall convey the drainage

water towards Lake NMK. Blind pipes have to be laid with an interval of 30 meter.

Works 4: Remediation works of NMK-KIE Page 256

Before sand is applied on the HDPE liner, the HDPE drains 110 mm with filter material wrapped

around it have to be installed on the HDPE liner. Drains have to be lain by hand and fixated

with small heaps of sand.

The drainage mat should be supplied and distributed from areas already covered by the

drainage layer and vegetative layer. Where required ramps have to be applied on the supply

routes to guarantee stability of the drainage and HDPE layers. Equipment should be provided

with tracks.

When the drainage material has been installed, excavations for e.g. installation of drainage

pipes and filter material around the pipes may only be done manually, and all excavated

trenches shall be visually inspected and approved by the Engineer in Charge before drain pipes

are installed.

At the cells in Lake NMK about 11,500 m2 of drainage mat is required for the drainage layer.

The contractor has to deliver the drainage material. The Contractor shall report to the Engineer

the properties and testing results of the materials he intend to use for the approval of the

Engineer before the first delivery to the site is effectuated.

1) Geocomposite (Drainage mat)

The drainage mat is a sandwich construction of two geotextiles and an artificial drainage

element in between with a high water flow capacity.

The drainage mats shall comply with the following standards:

Parameter Requirement Tolerance Check method

Appearance No visible flaws or defects Visual inspection

Structure Sandwich construction Visual inspection

Polymer type (filter

element)

PP or PE -

Polymer type (Geotextile) PP or PE -

Flow capacity

(20 KPa and I = 0.1))

0.20 l/s/m Min. ISO 12958 or

similar relevant

standard

Flow capacity

(50 KPa and I = 0.1))

0.15 l/s/m Min. ISO 12958 or

similar relevant

standard

Weight (filter element) 600 g/m² Min. -

Weight (Geotextile) 100 g/m2 Min. -

Works 4: Remediation works of NMK-KIE Page 257

Parameter Requirement Tolerance Check method

Thickness (filter element) 3.0 mm Min. -

Thickness (Geotextile) 0.4 mm (each) Min. -

Strength (filter element) 1 kN/m Min. -

Strength (Geotextile) 7.0 kN/m Min. -

Permeability (Geotextile) 50 mm/s

Delivery and Storage Requirements for Geocomposite The Geocomposite material shall be delivered at the site with a datasheet from the producer

certifying the characteristics of the material according to the above specifications. Further the

delivery shall be accompanied by a protocol with the results of the producers quality check for

the specific batch delivered to the site

The membrane shall be protected against physical damages during transport to the site and

during storage at the site. Geocomposite roles on stock shall be protected for UV radiation by

covering with tarpaulins.

Installation of Geo composite (ii) General

The installer shall elaborate an installation plan showing the position of the individual rolls of

material and deliver the plan to the Engineer for approval before installation works

commence.

Geocomposite on slopes (in slope direction) shall be in one piece and connection of two roles

in slope direction shall only take place in berms or in areas with slope less steep than 1:3.

Installation may only be done by technical staff approved by the producer of the liner material

(the manufacturer) and with equipment approved by the same. The manufactures guidelines

for storage, handling and installation of Geocomposite shall be followed.

(iii) Jointing of Geocomposite

In flow direction Geocomposite shall be joined by opening of Geotextile for connection of the

two filter elements, as shown in figure below. The overlap shall be minimum 0.15 m.

Works 4: Remediation works of NMK-KIE Page 258

Drainage mats have to be connected by simple overlapping in perpendicular direction to the

slope direction. Overlapping shall be minimum 0.10 m.

(iv) Covering

Until the Geocomposite has been checked and approved the Geocomposite material shall be

anchored using sandbags or any other equivalent system ensuring, that the installed material

is not moved by wind or down slope by gravity.

The Contractor shall cover the installed liner with a vegetation soil layer immediately upon

check and approval by the Engineer. At slopes the cover material shall be installed starting

from the toe of the slope taking any slack in the liner material to the top of the slope.

The Geocomposite shall be covered with soil not less than 2 weeks after installation.

(v) Connections to structures

Geocomposite are cut in shape as required and with maximum distance between the

penetrating structure and the Geocomposite at 0.25 m.

At the toe of the slopes it is important that there are a good connection between the

Geocomposite and the erosion stone layer. The Geocomposite shall at minimum have a 0.5 m

overlap in directly connection with the stone layer.

(vi) Check of liner material and installation

The check of the installation works shall be based on a check plan elaborated by the Contractor

and approved by the Engineer. The check plan shall describe who has the responsibility for

performing each check, the extent of the check and when the check shall be performed.

Further the plan shall indicate whether the works may proceed or shall wait pending the

results of the tests and checks.

Stage Item Subject to

check

Method Extent Acceptance

Delivery Liner material Datasheet quality check 1 nos.

per roll

Delivered

Reception Liner material Appearance Visual 1 nos.

per 1,000

m2

No flaws or defects

Thickness Measuremen

t

1 nos.

per 1,000

m2

Less than 10%

negative deviation

from specification

During

installatio

n

Liner material Appearance Visual 100% No flaws or defects

Overlaps

Works 4: Remediation works of NMK-KIE Page 259

12.2.6. Vegetation Layer A vegetation layer of 80 cm shall be placed above the Geotextile layer at the containment cell

in stagnant water pond 2. A vegetation layer of 50 cm shall be placed above the geocomposite

(drainage mat) layer at the containment cells in Lake NMK. . The vegetation layer has to be

brought into the area by the Contractor. The Contractor shall ensure that the vegetation soil is

uncontaminated. The vegetation layer should have an organic percentage of around 3 %. The

compost made from the cleared vegetation has to be used to elevate the organic content,

making the soil suitable for a healthy vegetation cover in the future.

At stagnant water pond 2 a total of 3.700 m3 of soil is required. For the containment cells in

Lake NMK a total volume of clay/soil of 5,750 m3 is required.

General Contractor shall procure and deliver all topsoil for final covering of the dumpsite.

Specification for ordinary earth for vegetative layer:

› Vegetative layer to support natural plant growth › Humus content minimum 5% and nutrient content levels which are normally

associated with fertile soil › Density maximum 1.6 tons/m³ (wet condition) › Water content 20-40% (under installation)

Installation Only light compaction shall be introduced (maximum e.g. by a bulldozer or other belt

machines).

Control Requirements, tolerances and check

Tolerance, requirements and check for soil layers:

Parameter Requirement Tests

Value Tolerance Nos.

- Level of surface As designed +0.05m / -

0.05m

25 per 10,000 m2

- Thickness of vegetative

layer

0.80 m +0.05m / -

0.05m

25 per 10,000 m2

Composition of

vegetative layer (Humus,

nitrogen and water

content)

See text

above

See text above 1 per 2,000 m3

Works 4: Remediation works of NMK-KIE Page 260

Average density Max. 1.6

tons/m³

+100 kg / - 50 kg On request by the

Engineer

The Contractor shall report to the Engineer the properties and testing results of the materials

he intend to use for the approval of the Engineer before the first delivery to the site is

effectuated.

12.3 Vegetation

12.3.1. General Vegetation:

Grass (To minimise erosion) over an total area of 16,125 m2. Local adopted plants that are resistant to drought and extreme temperatures shall be used.

The containment cells shall be planted with local species of grass. To prevent the top surface

from erosion, the total surface shall be covered with grass. Short-rooted, self-spreading plants

shall be selected from among local species to provide a vegetation cover.

Grass shall be of the species proposed by the Contractor and approved by the Engineer and

shall be of the best quality and free from disease.

The Contractor shall present a plantation plan for all the grass for the Engineers approval.

Making of Lawns

Making of lawns may be if two types:-

(a) Rough grassing

(b) Fine grassing.

In case of rough grassing, grass roots are planted at 6 inch (15 cm.) apart and in case of fine

grassing; roots are at interval of 4 inch (10 cm.). In the latter type, seeds of the good "doob"

grass may be used instead of roots when the contract for planting and maintenance of the

lawn for one year is with one agency.

Method. Proper ploughing should be done first of all, which should be followed by breaking of

clods removal of rubbish, spreading and mixing of well-decayed manure, dragging with

"swahga" and then levelling the entire lawn. The grassing shall be done by planting good

"doob" grass at specified intervals or planting seed which shall be followed by watering.

Rate. Rate in addition to the above items includes the supply of doob grass.

Works 4: Remediation works of NMK-KIE Page 261

Maintenance. Maintenance shall be for a period of one year. When handed over at the end of

the period of maintenance, the lawn shall be free from bare patches, with the edges neatly

trimmed. The contractor shall be responsible that the grass grows properly and in the event of

its not doing so he shall grass or regrass, such parts, as have not grown. No area which does

not show a good healthy growth shall be paid for. Rate of maintenance of lawns includes

watering, deweeding, mowing, rolling at intervals, and replanting where necessary.

12.3.2 Installation Seeding of grass shall take place immediately after installation and approval of the vegetative

layer irrespectively of time of year. It is of highest importance that a well-established and

robust grass cover is in place as fast as possible to reduce extension of surface erosion.

Irrigation and maintenance of the vegetative layer and vegetation shall be performed from the

very beginning.

12.3.3. Control The Contractor shall submit documentation of type of grass seed used (name and distribution).

12.4 Revetment along stagnant water pond 2

The north slope of the containment cell in stagnant water pond 2 dips in te water of this

stagnant water pond. To protect the integrity of the slope, a revetment shall be installed

around FTL. The revetment of the bund consist of the following elements

Non-woven Geotextile (GSM 250 or comparable, 0.5 mm thick)

layer of closely placed revetment stones (0.23 m thick)

The revetment shall be installed at the slope along stagnant water pond 2 over an length of

about 90 m. The revetment shall be applied under a slope of 1:3. Along the slope the

revetment is about 2 meters width. The revetment is presented on Drawing Nos. IND50-1-2-1,

IND50-1-2-2 and IND50-1-2-3.

12.4.1. Protective layer with non woven geo-textile Requirements of Geotextiles Geotextile are used as filter material behind the revetment stones.

The Geotextile shall be a non-woven Geotextile of UV-stable polypropylene, polyethylene or

polyester capable of resisting exposure to the sun for minimum two years.

A protective layer with GSM 250 or equivalent qualities has to be installed to protect the slope.

Net demand of geotextile is 405 m2.

The Geotextile shall be installed between the core of the slope below and the revetment

stones on top. Thus after installation the Geotextile shall be protected against UV-radiation.

Works 4: Remediation works of NMK-KIE Page 262

Simple overlapping with a width of min. 0.5 m shall connect lanes of installed Geotextile.

Alternatively sewn connections may be used. Sewn connections shall have tensile strength

equal to the tensile strength of the Geotextile.

Before the geotextile can be installed the slope should be leveled, resulting in a smooth slope.

12.4.2. Delivery, Unloading, Site Handling and Storage Requirements for Geotextiles Reference is made towards section 12.2.5.2 of the particular specifications.

Installation Procedure for Geotextiles Reference is made towards section 12.2.5.3 of the particular specifications.

12.4.3. Revetment Stones applied for the revetment should be of the same type as applied along the shoreline of

the STP premises. The granite stones required for the revetment have to be of regular form.

The regular form has to guarantee a uniform appearance of the revetment. Total thickness of

the layer should be at least 0.23 m.

The Contractor shall report to the Engineer the properties and testing results of the materials

he intend to use for the approval of the Engineer before the first delivery to the site is

effectuated.

Revetment should be installed and constructed in conformity with the manuals, handbooks

and guidelines of the Irrigation Department. The Irrigation Department has to approve the

work plan for the revetment of the Contractor.

A total volume of 95 m3 of stones is required for the work.

12.5 Transport of Clean Material

The Contractor is free to decide the method for transport of clean material e.g. clay, soil or

sand required for the construction of the containment cells. However, the Contractor shall

follow all Indian rules and regulations including all traffic rules. This also apply to transport of

clean material required for other work components.

13 Cover layer in Lake NMK

13.1 General

Previous site investigations have shown that the clay layer underneath the sediments in Lake

NMK is severely contaminated with among others TPH and heavy metals such as lead. Removal

of the clay layer is not feasible because this layer is an important prerequisite of the mere

existence of the lake. Its impervious characteristic prevents that the surface water infiltrates to

the subsoil in such a rate that Lake NMK shall fall dry. The same character has prevented till

now that pollution present in the sediments of the Lake were entering the subsoil to a

Works 4: Remediation works of NMK-KIE Page 263

significant extent. For this reason it was decided not to remove the clay layer and to protects

its integrity by all means.

Although the clay layer shall remain in place, some precautions have to be taken to prevent

that pollutions and nutrient loads can enter the water column of the Lake by diffusion or other

release processes such as desorption. The application of a cover layer of 0.3 meter sand is an

effective measure to limit the impact of such release processes on the impact of the surface

water quality.

A total of about 20.625 m3 of sand is required to provide for aforementioned cover layer of 0.3

m thick all over Lake NMK. This sand layer has to be installed after the sediments have been

removed (in a section of the lake).

The sand layer has to be implemented with an rain bow technique (or comparable technique.

The total sand layer has to be applied with an overall accuracy of + 2 centimetre. The position

of the top of the clay layer which has to be covered is presented on Drawing No. IND50-1-5-2.

On Drawing Nol. IND50-1-5-3 (refer to Section VI) the cover layer of sand is presented in a top

view drawing and in 3 cross sections.

13.2 Cover layer

The sand layer has to be implemented with a rain bow technique (or comparable technique.

The total sand layer has to be applied with an overall accuracy of + 2 centimetres.

Given the observed concentrations of contaminants in the sediment all works under this task

have to be carried out under the most strict health and safety precautions, including the use of

suitable boots, gloves, coveralls and masks and a decontamination and wash unit.

Lake NMK has already been fenced off from the surrounding area (in earlier stages of the

project).

During the implementation of the sand cover, no water shall be discharged into the Lake which

show visible evidence of pollution or which contain concentrations of more than 25% above

the baseline concentrations. Baseline concentrations have to be established for the

parameters as mentioned in the monitoring requirements for the surface water in Lake NMK

as included in Section V (General Items).

The Contractor has to assure that the water sand slurry is at all times arriving at the spraying

platform at the required working pressure and the appropriate sand/surface water ratio, in

accordance with the specifications of his final design. These working pressures and ratios have

to be monitored and recorded continuously. The same applies for the movements of the

spraying platform. If deviations from the specifications of the final design of the Contractor

occur, the Contractor has to take all necessary corrective actions immediately.

Given the vulnerability of the water balances it is important that the process water applied has

a closed cycle with NMK Lake.

Works 4: Remediation works of NMK-KIE Page 264

Sand for the cover layer has to be applied with a wet technique (rainbow method or

comparable) in individual layers of approximately 0.05 m maximum thickness. The thickness of

each layer has to be monitored with a footplate before and after installing the specific layer in

(a section of) the Lake.

It is not allowed to implement the sand layer in bulk. The clay layer has to have the chance to

adjust to new top loads of the cover layer in such a way that stability of the clay layer is never

at risks with regard to geotechnical phenomena as well as with regard to release processes of

contaminants or nutrients.

In case during the works indications are observed of unexpected chemical contamination from

smell or odour or colour the Contractor shall stop the works in the particular area and inform

the Engineer in Charge. The Contractor shall following the instruction from the Engineer in

Charge.

All equipment leaving Lake NMK has to be cleaned from sediment and waste adhering to the

equipment. Cleaning shall be performed in the transition zone between the lake perimeter and

the surrounding areas.

Personnel leaving the perimeters of the Lake has to be decontaminated in a specially

demarcated area between the Lake and the surrounding area. This area has to be split in a

polluted zone, a zone for washing and a clean zone.

The content of organic material in the sand shall be less than 2%. The sand layer shall be clean

of any dirt and any contamination.

Grain size distribution:

Sieve size (mm) Quantity of particles (%)

passed through sieves

20 100

10 30 - 100

5 15 - 60

2 5-35

1 0-20

0.5 0-10

Maximum grain size is 20 mm.

Requirements, tolerances and check

Tolerance, requirements and check for foundation layer:

Works 4: Remediation works of NMK-KIE Page 265

Parameter Requirement Tests

Value Tolerance Nos.

- Level at the bottom + 0.02 m 25 per 10,000 m2

- Thickness of cover layer Min. 0.30 m No single values

less than 0.3 m

25 per 10,000 m2

Grain size distribution of

drainage layer

See table See table 1 per 500 m3

14 Development for Future Use

Developments for Future Use include the following items::

Installation of an Irrigation System on the 5 containment cells to support the development of a sustainable grass layer.

On the containment cell in stagnant water pond 2 Storm Water Drainage Channels for effective drainage of surface runoffs shall be installed. This drainage system consists of the following elements:

- drainage ditch around the flat top surface of the containment cell

- drainage ditch on the intermediate berms of the containment cell

- ditch around the toe of the containment cell

- system of discharge drain pipe which connect the

aforementioned ditches

On the containment cell in the south-eastern corner of Lake NMK Storm Water Drainage Channels for effective drainage of surface runoffs shall be installed. This drainage system consists of the following elements:

- drainage ditch around the flat top surface of the containment cell

- ditch at the southern and eastern border of the containment cell

- system of discharge drain pipe which connect the

aforementioned ditches

On the containment cell at the western bund of Lake NMK a Storm Water Drainage Channel for effective drainage of surface runoffs shall be installed. This drainage system consists of the following elements:

Works 4: Remediation works of NMK-KIE Page 266

- drainage ditch between original bund and new containment cell

- system of discharge drain pipe which connects the

aforementioned ditch with Lake NMK

On the containment cell at the Northern bund of Laae NMK no Storm Water Drainage channels are required

Installation of ground water monitoring wells in the NMK-KIE area.

The top of the containment cell in stagnant water pond 2 shall have a maximum height of 6-8

meters. This cell has a near flat top surfaces.. The containment cell in stagnant water pond 2

has a flat top surface of about 19 x 52 = 988 m2.

The containment cell to the south-eastern corner of Lake NMK has a flat top surface which

covers about 6,500 m2

The containment cell in stagnant water pond 2 has a uniform 1:3 slopes in all directions. About

halfway the slopes of this cell have a small intermediate berm.

Te containment cells in Lake NMK have a near flat surface and are bordered by the walls of the

gabions.

A schematic layout plan showing the future layout of the containment cells is presented on

Drawing Nos. Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-

10, IND50-1-5-11, IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3 (refer to Section VI).

14.1 Installation of Irrigation System & Horticulture

The irrigation requirement of water for the containment cells in stagnant water pond 2 and the

south-eastern corner of Lake NMK is around 50 KLD each. A similar requirement has been

assessed for the combined cells on the western and northern bunds of Lake NMK. This amount

of water has to be pumped from Lake NMK. The water shall be sprinkled in the area by means

of Hose pipe connections of 25 mm diameter pipes.

The irrigation fixed pipes of 50 mm diameter and the HDPE feeding pipe of about 800 meter

long of 75 mm (including valve arrangements of 2 inches at regular intervals) shall be buried in

the vegetative cover layer without disturbing the drainage layer or the HDPE liner system. The

intervals and provision of the valves shall be done on site by the contractor with approval of

the Engineer in Charge.

Water has to be pumped by means of electrical pumps of capacity 10 m3/hr – 40m head, to the

Sprinkler System via the feeder pipe. Pumps have to be installed in NMK Lake (2). The pumps

have to be connected to the electricity system of the STP. The on/off switch of the pumps has

to be located at the premises of the STP.

After complete capping of the containment cells, proper Horticulture and Landscaping shall be

done on the entire containment cell areas with grass.

Works 4: Remediation works of NMK-KIE Page 267

14.2 Surface water collection and storm water drainage

14.2.1. Construction of Storm Water Drains There are 4 different surface water drain system:

› At the Top of the containment cells in stagnant water pond 2 (type 1); size of grass lined drainage channel proposed to be provided at top most berm is 0.5 m width x 0.5 m depth

› Around the top of the containment cell in the south eastern corner of Lake NMK and at the western bund of the same lake (type 2); size of grass lined drainage channel proposed to be provided is 0.3 m width x 0.3 m depth.

› Intermediate Drain (type 3); size of grass lined drainage channel proposed to be provided at intermediate berm is 0.3 m width and 0.3 m depth

› Along the periphery of the containment cell in stagnant water pond 2 (type 4) ; size of grass lined drainage channel proposed to be provided is maximal 6.0 m width and 1.0 m depth with 1:3 side slopes

› Along the periphery of containment cell in the south-eastern corner of Lake NMK (type 5) ; size of reveted drainage channel proposed to be provided is maximal 7.0 m width and 1.0 m depth with 1:3 side slopes and 1.0 m width bottom.

› Stones applied for the revetment of channel type 4 should be of the same type as applied along the shoreline of the STP premises. The granite stones required for the revetment have to be of regular form. The regular form has to guarantee a uniform appearance of the revetment. Total thickness of the layer should be at least 0.3 m.

› The Contractor shall report to the Engineer the properties and testing results of the materials he intend to use for the approval of the Engineer before the first delivery to the site is effectuated.

› Revetment should be installed and constructed in conformity with the manuals, handbooks and guidelines of the Irrigation Department. The Irrigation Department has to approve the work plan for the revetment of the Contractor.

› A total volume of 440 m3 of stones is required for the work.

The design of the surface water drains are presented on Drawing Nos. IND50-1-5-4, IND50-1-5-

5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10, IND50-1-5-11, IND50-1-2-1, IND50-1-2-2 and

IND50-1-2-3 (refer to Section VI).

If subsoil of low strength is observed the Contractor shall consult the Engineer for possible

enhancement of the subsoil.

Works 4: Remediation works of NMK-KIE Page 268

1) Design of Surface Water Drains

The containment cells surface water drainage systems are designed based on the peak rainfall

intensity.

Surface Water Runoff Drain:

For surface water drainage the design is based on the peak rainfall intensity of 25 mm / hr. The

table of estimation of sizing of storm water drainage is presented below for the largest of the 2

containment cells:

Works 4: Remediation works of NMK-KIE Page 269

DESIGN OF STORM WATER DRAIN FOR THE CONTAINMENT CELL IN STAGNANT WATER POND 2

Sr.

No. Area Area Runoff

Maximum

Rainfall Quantity of Velocity

Area of

Drain

Drain

Size

Served (sq. m) Co.eff. intensity Runoff Q = AIR of flow Q/v

Area

I R

mm/hr

R

m/hr cu.m/hr. cu.m/sec m/sec Sq.mt. mt.

(sq. m)

1 3000 3000 0.9 25 0.025 67,500 0.019 0.6 0.0313 0.19

2 5625 5625 0.9 25 0.025 126,663 0.035 0.6 0.0586 0.25

3 11000 11000 0.9 25 0.025 247,500 0.069 0.6 0.115 0.37

14.2.2. Surface Run off Drainage Layer and surrounding Drainage Channel The drainage layer in the cover of the cell in stagnant water pond 2, consisting 0.20 m thick

sand layer shall terminate in a drain coffer. In the drain coffer a 110 mm drain shall collect the

access drain water. At intervals of average 30 m distance closed pipes shall convey the

collected drain water into type 4 drain channels.

Top berm pipe shall be laid up to intermediate berm at every 30mt intervals of 110 OD HDPE

pipe and from intermediate berm to bottom pipe shall be laid at interval of 30mt of 200 OD

HDPE pipe.

The drainage layer in the cover of the cell in the south-eastern corner of Lake NMK, consisting

of a 5 mm thick geo-composite drainage layer shall terminate in a drain coffer. In the drain

coffer a 110 mm drain shall collect the access drain water. At intervals of average 30 m

distance closed pipes shall convey the collected drain water into type 5 drain channels or

directly into Lake NMK.

Storm water drainage pipes of 110 mm OD HDPE have to be connected to the surface water

drainage at every 30mt intervals.

The drainage layer in the cover of the cell at the western and northern bund of Lake NMK,

consisting of a 5 mm thick geo-composite drainage layer shall terminate in a drain coffer. In

the drain coffer a 110 mm drain shall collect the access drain water. At intervals of average 30

m distance closed pipes shall convey the collected drain water directly into Lake NMK.

Underneath the type 2 drain at the western bund of Lake NMK a drain 110 mm OD HDPE shall

be installed for catchment of drain and surface water run-off. This drain shall at average

Works 4: Remediation works of NMK-KIE Page 270

intervals 0f 30 meter be connected to a 200 mm OD HDPE discharge pipe, which shall convey

the drainage water to Lake NMK.

14.3 Installation of Monitoring Wells & Bore wells

The requirements for the supervision and monitoring have been highlighted in Section V

General Items. Based on the tables presented in section V General Items a total of 74 ground

water monitoring wells have to be installed by the Contractor.

Twenty one monitoring wells shall have a depth of 5 m each.

Eight monitoring wells shall have a depth of 10 m each.

Five monitoring wells shall have a depth of 15 m each.

Five monitoring wells shall have a depth of 20 m each.

Fifteen monitoring wells shall have a depth of 25 m each.

Five monitoring wells shall have a depth of 45 m each.

Ten monitoring wells shall have a depth of 60 m each.

Five monitoring wells shall have a depth of 70 m each.

On Drawing No. IND50-1/05 details are presented about the way the monitoring wells have to

be constructed. The position of the required monitoring points is presented in Figure 1 of

Section V General Items and more detailed information on position and depth is presented in

the following table.

In an additional table the required number and type of analysis for groundwater, sediment and

soil have been presented. In addition to these analysis also air samples have to be taken and

analysed as described in the General Items of section V.

Zone MW ID

Symbol

Symb. No.

Lattitude Longitude Filter ID Depth [m]

Plains 1

4 17.316408 78.424883

1a 5-10

2

5 17.318326 78.426027

2a 5-10

3

6 17.319089 78.427384

3a 5-10

NMK Lake

1

L 17.315649 78.426753

1a 2-4 (below FTL)

Works 4: Remediation works of NMK-KIE Page 271

Zone MW ID

Symbol

Symb. No.

Lattitude Longitude Filter ID Depth [m]

2

L 17.316161 78.427461

2a 2-4 (below FTL)

3

L 17.315656 78.427989

3a 2-4 (below FTL)

4

L 17.315173 78.427220

4a 2-4 (below FTL)

5

1 17.317226 78.427253

5a 4-7

6

2 17.316658 78.426756

6a 4-7

7

3 17.315834 78.425861

7a 4-7

8

4 17.315833 78.429068

8a 4-7

9

5 17.314601 78.428050

9a 4-7

10

1 17.313848 78.426296

10a 2-5

11

1 17.314034 78.427259

11a 2-5

12

1 17.313951 78.426942

12a 2-5

13

2 17.314894 78.430455

13a 2-5

14

2 17.314982 78.429981

14a 2-5

15

3 17.315866 78.429939

15a 2-5

16

3 17.316099 78.428364

16a 2-5

17

4 17.316824 78.427657

17a 2-5

18

4 17.316524 78.427206

18a 2-5

19

5 17.316097 78.426626

19a 2-5

Works 4: Remediation works of NMK-KIE Page 272

Zone MW ID

Symbol

Symb. No.

Lattitude Longitude Filter ID Depth [m]

20

5 17.315691 78.426110

20a 2-5

KIE 1

1 17.316226 78.430568

1a 5-10

1b 20-25

2

2 17.314761 78.429430

2a 5-10

2b 20-25

3

3 17.313167 78.428318

3a 5-10

3b 20-25

4

4 17.311274 78.427133

4a 5-10

4b 20-25

5

5 17.317134 78.432112

5a 5-10

5b 20-25

6

6 17.315394 78.433725

6a 15-20

6b 40-45

7

7 17.316630 78.435388

7a 15-20

7b 40-45

8

8 17.313858 78.434559

8a 20-25

8b 50-60

9

9 17.315410 78.437815

9a 20-25

9b 50-60

10

10 17.312824 78.437010

10a 20-25

10b 50-60

Works 4: Remediation works of NMK-KIE Page 273

Zone MW ID

Symbol

Symb. No.

Lattitude Longitude Filter ID Depth [m]

11

S 17.309560 78.430721

11a 10-15

12

S 17.309560 78.430721

12a 65-70

13

S 17.309792 78.430630

13a 10-15

14

S 17.309792 78.430630

14a 65-70

15

S 17.309748 78.430765

15a 10-15

16

S 17.309748 78.430765

16a 65-70

17

S 17.309377 78.430810

17a 10-15

18

S 17.309377 78.430810

18a 65-70

19

S 17.309619 78.431129

19a 10-15

20

S 17.309619 78.431129

20a 65-70

21

1 17.313116 78.431560

21a 15-20

21b 40-45

22

2 17.311432 78.430085

22a 15-20

22b 40-45

23

3 17.311688 78.433396

23a 20-25

23b 50-60

24

4 17.309648 78.433044

24a 20-25

24b 50-60

25

5 17.310466 78.428719

25a 15-20

25b 40-45

26

6 17.308245 78.432466

26a 20-25

Works 4: Remediation works of NMK-KIE Page 274

Zone MW ID

Symbol

Symb. No.

Lattitude Longitude Filter ID Depth [m]

26b 50-60

27

7 17.308276 78.431278

27a 20-25

27b 50-60

28

8 17.308639 78.429973

28a 20-25

28b 50-60

29

9 17.310703 78.431724

29a 20-25

29b 50-60

30

10 17.310946 78.435279

30a 20-25

30b 50-60

Works 4: Remediation works of NMK-KIE Page 275

Zone Point Analytical suite Project phase Matrix to perform anlysis on

Baselline

Investigation

During project

Implementati

on

After project

implementati

on

Sedi-

ment Soil Water

Number of samples

Plains

1 TPH and heavy metals 4 4 4 x

2

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 64 20

x

3

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 64 20

x

4

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 0 5

x

5

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 0 5

x

6

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 0 5

x

R

Works 4: Remediation works of NMK-KIE Page 276

NMK Lake

L

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 4 248 80

x

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 4 28 4

x

1

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 17 5

x

2

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 17 5

x

3

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 17 5

x

Works 4: Remediation works of NMK-KIE Page 277

4

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 17 5

x

5

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 1 17 5

x

1

TPH, heavy metals,

PAH and BTEX 8 0 8

x

TPH, heavy metals,

PAH and BTEX 2 34 2

x

1

TPH, heavy metals,

PAH and BTEX 8 0 8

x

TPH, heavy metals,

PAH and BTEX 2 34 2

x

2

TPH, heavy metals,

PAH and BTEX 8 0 8

x

TPH, heavy metals,

PAH and BTEX 2 34 2

x

3

TPH, heavy metals,

PAH and BTEX 8 0 0

x

TPH, heavy metals,

PAH and BTEX 2 34 2

x

Works 4: Remediation works of NMK-KIE Page 278

4

TPH, heavy metals,

PAH and BTEX 8 0 0

x

TPH, heavy metals,

PAH and BTEX 2 34 2

x

5

TPH, heavy metals,

PAH and BTEX 8 0 0

x

TPH, heavy metals,

PAH and BTEX 2 34 2

x

KIE

1

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

2

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

3

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

Works 4: Remediation works of NMK-KIE Page 279

4

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

5

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

6

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

7

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

8

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

9

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

Works 4: Remediation works of NMK-KIE Page 280

10

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

1 TPH and heavy metals 0 0 5

x

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], particular

matter, odour and

colour 0 0 10

x

2 TPH and heavy metals 0 0 5

x

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], particular

matter, odour and

colour 0 0 10

x

3 TPH and heavy metals 0 0 5

x

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], particular

matter, odour and

colour 0 0 10

x

4 TPH and heavy metals 0 0 5

x

TPH, heavy metals,

COD, BOD, 0 0 10

x

Works 4: Remediation works of NMK-KIE Page 281

temperature, O2, pH,

Ec, Eh [mV], particular

matter, odour and

colour

1

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 0 4 2

x

TPH and heavy metals 0 4 2

x

2

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 0 4 2

x

TPH and heavy metals 0 4 2

x

3

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 0 4 2

x

TPH and heavy metals 0 4 2

x

4

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity,

particular matter,

odour and colour 0 4 2

x

TPH and heavy metals 0 4 2

x

5

TPH, heavy metals,

COD, BOD,

temperature, O2, pH,

Ec, Eh [mV], salinity, 0 4 2

x

Works 4: Remediation works of NMK-KIE Page 282

particular matter,

odour and colour

TPH and heavy metals 0 4 2

x

1

TPH, PAH, heavy

metals 0 10 10

x

S

TPH, volatile organics,

organic matter, clay

and sand fractions,

odour, colour 15 0 0

15

TPH, volatile organics,

organic matter, clay

and sand fractions,

odour, colour 15 0 0

15

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 5 0 25

5

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 5 0 25

5

1

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular 2 0 10

x

Works 4: Remediation works of NMK-KIE Page 283

matter, odour and

colour

2

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

3

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

4

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

5

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

6

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

7

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV], 2 0 10

x

Works 4: Remediation works of NMK-KIE Page 284

salinity, particular

matter, odour and

colour

8

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

9

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

10

TPH, volatile organics,

heavy metals, COD,

BOD, temperature,

O2, pH, Ec, Eh [mV],

salinity, particular

matter, odour and

colour 2 0 10

x

Based on above table 7 analytical suites have to be applied for the different matrices. In the

following tables the specifications for each of the seven suites are presented. Contractor has to

include costs for sampling, packing material, transport to off-site laboratories, testing,

reporting and supporting analysis.

Specification for Suite 1:

Matrix: Sediment Suite 1: TPH and Heavy Metals

Component Technique Method of Testing Detection Limit

TPH (C10-C40) GC-FID Equal to NEN-EN-ISO

16703, EPA 8015b&m

<35 mg/kg dm

Heavy Metals (Pb, Cd,

Cr, Zn, Hg, Cu, Ni, As)

ICP-MS Cf. pb 3010-5 and cf.

NEN-EN-ISO 17294-2

<10, <0.2, <5.0, <20,

<0.05, <5.0, <4.0, <5.0

mg/kg dm

Works 4: Remediation works of NMK-KIE Page 285

Specification for Suite 2:

Matrix: Soil Suite 2: TPH , Heavy Metals, PAH and BTEX

Component Technique Method of Testing Detection Limit

TPH (C10-C40) GC-FID Equal to NEN-EN-ISO

16703, EPA 8015b&m

<35 mg/kg dm

Heavy Metals (Pb, Cd,

Cr, Zn, Hg, Cu, Ni, As)

ICP-MS Cf. pb 3010-5 and cf.

NEN-EN-ISO 17294-2

<10, <0.2, <5.0, <20,

<0.05, <5.0, <4.0, <5.0

mg/kg dm

PAH GC-MS Cf. pb. 3010-6 and gw.

NEN-ISO 18287

Individual PAH <0.05

mg/kg dm

BTEX HS GC/MS Cf. pb. 3010-6 and gw.

NEN-ISO 18287, EPA

8260b

Individual BTEX <0.05

mg/kg dm

Specification for Suite 3:

Matrix: Soil Suite 3: TPH , Heavy Metals

Component Technique Method of Testing Detection Limit

TPH (C10-C40) GC-FID Equal to NEN-EN-ISO

16703, EPA 8015b&m

<35 mg/kg dm

Heavy Metals (Pb, Cd,

Cr, Zn, Hg, Cu, Ni, As)

ICP-MS Cf. pb 3010-5 en cf.

NEN-EN-ISO 17294-2

<10, <0.2, <5.0, <20,

<0.05, <5.0, <4.0, <5.0

mg/kg dm

Specification for Suite 4:

Matrix: Soil Suite 4: TPH , Heavy Metals and PAH

Component Technique Method of Testing Detection Limit

TPH (C10-C40) GC-FID Equal to NEN-EN-ISO

16703, EPA 8015b&m

<35 mg/kg dm

Heavy Metals (Pb, Cd,

Cr, Zn, Hg, Cu, Ni, As)

ICP-MS Cf. pb 3010-5 and cf.

NEN-EN-ISO 17294-2

<10, <0.2, <5.0, <20,

<0.05, <5.0, <4.0, <5.0

mg/kg dm

PAH GC-MS Cf. pb. 3010-6 and gw.

NEN-ISO 18287

Individual PAH <0.05

mg/kg dm

Works 4: Remediation works of NMK-KIE Page 286

Specification for Suite 5:

Matrix: Soil Suite 5: TPH, Volatile Organics, Organic Matter, Clay and Sand fraction,

Odour, Colour

Component Technique Method of Testing Detection Limit

TPH (C10-C40) GC-FID Equal to NEN-EN-ISO

16703, EPA 8015b&m

<35 mg/kg dm

BTEX and SVOC HS GC/MS Cf. pb. 3010-6 and gw.

NEN-ISO 18287, EPA

8260b

Individual BTEX <0.05

mg/kg dm

VOC <0.1 mg/kg dm

Organic Matter Gravimetric Cf. pb 3010-3 and cf.

NEN 5754

<0.7 % (m/m) dm

Clay fraction Sedimentation Cf. pb 3010-3 and cf.

NEN 5754

<2.0 % (m/m) dm

Sand fraction Sieving Cf. NEN 5753 <0.1 % (m/m) dm

Odour N/A N/A N/A

Colour (apparent) N/A N/A N/A

Specification for Suite 6:

Matrix: Water Suite 6: TPH, Heavy Metals, COD, BOD, Temperature, O2, pH, Ec, Eh (mV),

TSS, TDS, Odour and Colour

Component Technique Method of Testing Detection Limit

TPH (C10-C40) GC-FID Cf. NEN-EN-ISO 9377-2 <50 µg/L

Heavy Metals ICP-MS Cf. NEN-EN-ISO 17294-

2

<5.0, <0.4, <5.0, <10,

<0.1, <5.0, <5.0, <1.5

µg/L

COD Titrimetric Cf. NEN 6633/A1: <5.0 mg O2/L

BOD Potentiometric Cf. NEN-EN 1899-1&

cf. NEN-ISO5814

(EN25814)

<1.0 mg O2/L

Temperature N/A Measured at arrival at Degrees Celsius

Works 4: Remediation works of NMK-KIE Page 287

the laboratory

O2 (DO) Potentiometric Cf. NEN-ISO 5814 <0.1 mg O2/L

pH Potentiometric Cf. NEN-EN-ISO 10523 (0-14)

Ec Conductometry Cf. NEN-ISO 7888 Ec(20 degrees) <1

mS/m. Ec(25 degrees

<10 µS/cm/<1 mS/m

Eh (mV) Potentiometric ASTM 1498-76 mV

Total Suspended Solids

(TSS)

Gravimetric Cf. NEN-EN 872, NEN

6484, NEN 6621

<2mg/L, <2mg/L,

<5mg/L

Total Dissolved Solids

(TDS)

Gravimetric Cf. NEN 6499 & EN

15934

<0.01 % (m/v)

Odour N/A N/A N/A

Colour (apparent) N/A N/A N/A

Specification for Suite 7:

Matrix: Water Suite 7: TPH, Heavy Metals, PAH and BTEX

Component Technique Method of Testing Detection Limit

TPH (C10-C40) GC-FID Cf. NEN EN ISO 9377-2 <50 µg/L

Heavy Metals (Pb, Cd,

Cr, Zn, Hg, Cu, Ni, As)

ICP-MS Cf. NEN-EN-ISO 17294-

2

<5.0, <0.4, <5.0, <10,

<0.1, <5.0, <5.0, <1.5

µg/L

PAH LV-GC-MS EPA 8270c Individual PAH <0.01

µg/L, acenaphthylene

<0.05 µg/L

BTEX HS-GC-MS Cf. ISO 11423-1 Individual BTEX, <0.2

µg/L

Works 4: Remediation works of NMK-KIE Page 288

15 Tabular presentation of specifications

15.1 Introduction

In the following tables the specifications contained in above sections 1 till 14 have been

summarized. These tables have to be read in conjunction with the full specifications as

contained in above sections 1 till 14.

Below tables have also been used as input for the preparation of the Bill of Quantaties as

contained in Section VII. The Bill of Quantaties should be read and interpreted in conjuction

with below tables and the contend of above section 1 till 14.

Quantities expressed in Tonnes are determined by - and for costs of - the Contractor by

weighing in mean of transportation by weighing over a certified weighbridge. Weighing

receipts shall be submitted to the Engineer in charge. Other quantities are determined in the

work by survey, measurements and delivery notes.

Part 1: Site Mobilization and installation of bottom structure of Containment cells

Sr.

No.

Description of Item Qty. Unit

101

Supply and laying of ordinary earth brought from outside as a fill

layer of thickness varying between 2.0 till 2.5 meter consisting of

natural soil, silty clays mixed with sand as prevalent in Hyderabad

Region and suitable as fill material underneath the containment cell

in stagnant water pond 2 as presented in Drawing Nos. IND50-1-2-1

and IND50-1-2-2 including spreading and compaction of ordinary

earth in order to achieve 90% of proctor density. Compaction has

to be done on layers with a maximum thickness of 500 mm. The

spreading and compaction has to be achieved by means of a tractor

with 2T roller to required finished thicknesses and laid on flat

surfaces including supply, transportation to site of works, loading

and unloading of the materials, all labour and manpower,

equipments required for placing and spreading (dozers, tractor

trailors, front end loaders), compacting with equipments (soil

compactor rollers) and machinery, necessary testing as per ISO /

ASTM standards, fuel oil, incidental and other operational charges

etc complete as directed by Engineer in charge and to the

satisfaction of engineer in charge.

7860 cu.m

102 Excavation, Loading, Unloading, Transportation, Temporarily

Storage and Backfilling of soil originating from trench required for

installation of gabions at the southern, western and eastern

1400 cu.m

Works 4: Remediation works of NMK-KIE Page 289

Sr.

No.

Description of Item Qty. Unit

perimeter of the containment cell in the south-eastern corner of

Lake NMK as presented on Drawing Nos. IND50-1-5-9, IND50-1-5-

10 and IND50-1-5-11. Dimensions of the required trench are about

200 m x 2.5 m x on average 2.5 m. After temporarily storage soil

has to be used as fill material during the closure of the containment

cell. Including all tools and plants, materials, labour and manpower,

excavators, front end loaders, tractor trailors, etc. complete as

directed by engineer in charge and to the satisfaction of the

engineer in charge

103

Supplying, fabricating and placing in position gabions, consisting of

reinforced steel bars, chain like mesh and coarse aggregates in

containment cells in Lake NMK as presented on Drawing Nos.

IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11. Gabions have to be placed over a total length of

about 875 m of which is 375 m in the southeastern corner and

500m along the bunds and hillock. Maximum width of the gabions

is 2m. Height of gabions is ranging between about 2 m and 4 m in

the southeastern corner with an average height of 2.73 m. Height

of the gabions along the bund and hillock is about to 2 m.

Supplying, providing and apllying reinforcement steel bars (12 and

8 mm rods) and chain like mesh (size: 30 mm x 30 mm x 8 G) for the

construction of gabions, including cleaning, straightening, cutting,

bending, hooking, lapping, welding wherever required, tying with

2.50 mm diameter soft annealed steel wire. A minimum of 25 kg of

reinforced steel and chain like mesh per 1 m³ of gabion volume has

to be applied. In addition 0.9 Cum of coarse aggregates per Cum of

gabion has to be supplied and applied with a blending ratio of

50:40 for the fraction 120-80 mm and 80-40 mm respectively. Only

approved, clean, hard, graded aggregates for gabion filling should

be applied. Including initial lead up to 50 meters and all lifts for

finished item of work, costs of all materials, machinery, labour,

formwork, scaffolding, placing in position, leveling, finishing, etc.,

complete as directed by engineer in charge and to the satisfaction

of the engineer in charge.

4050 cu.m

104

Supply, Laying & Jointing of 1.5 mm thick HDPE Membrane Liner

(both side textured) acting as a main barrier layer for inflow of

surface water into the containment cell, placed between the gabion

and the clay as presented on Drawing Nos. IND50-1-5-4, IND50-1-5-

2755 sq. m

Works 4: Remediation works of NMK-KIE Page 290

Sr.

No.

Description of Item Qty. Unit

5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11,

including its unrolling, laying, jointing and welding as per ISO /

ASTM Standards with proper junction overlaps, welding at

junctions/joints using welding machines, providing sufficient

anchoring ensuring, that the installed liner material is not moved by

wind or down slope by gravity, necessary testing as per ASTM / ISO

standards etc complete including all materials, labour and

manpower, transportation, loading and unloading, storing and

stacking at safe place, safe handling, welding and jointing

equipments with materials, tools and plants etc complete as

directed by engineer in charge and to the satisfaction of engineer in

charge.

105

Supply and Laying of clay brought from outside behind (or in front

of) the gabions of the containment cells in Lake NMK as presented

on Drawing Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-

5-9, IND50-1-5-10 and IND50-1-5-11. Clay behind the gabions has

to be applied under a slope of 1:1 from the top of the gabion

towards the floor of the containment cell. In front a slope of 1:3 has

to be applied. The clay in combination with the HDPE liner and the

gabions has effectively to block the inflow of surface water into the

dewatered containment cells, including spreading and compaction

of clay in layers of 500 mm maximum thickness to achieve 90% of

proctor density. The spreading and compaction has to be achieved

by means of hand operated vibratory rollers to required finished

thicknesses and laid on flat surfaces including supply,

transportation to site of works, loading and unloading of the

materials, all labour and manpower, equipments required for

transport, placing and spreading (dozers, loaders backhoe, tractor

trailors, dumpers and poclain, front end loaders), compacting with

equipments (soil compactor rollers) and machinery, necessary

testing as per ISO / ASTM standards, fuel oil, incidental and other

operational charges etc complete as directed by Engineer in charge

and to the satisfaction of engineer in charge.

4325 cu.m

106

Levelling of containment cell in the south eastern corner of Lake

NMK over an area of 6,500 sq.m, including Excavation and

Backfilling of soil within the containment cell in the south-eastern

corner of Lake NMK as presented on Drawing Nos. IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11. On average required volume of

1000 cu.m

Works 4: Remediation works of NMK-KIE Page 291

Sr.

No.

Description of Item Qty. Unit

earth replacement is about 0.4 cu.m of soft soil per sq.m. Levelling

has to be done in an average water depth of about 2.5 m. Including

all tools and plants, materials, labour and manpower, excavators

and other heavy machinery, tractor trailors, pontoons, etc.

complete as directed by engineer in charge and to the satisfaction

of the engineer in charge

107a

Supply of sand brought from outside as a foundation layer, also

acting as support layer for HDPE membrane liner using sand (0.0 -

2.0 cm size) having rounded grain size materials between 0 - 20

mm, consisting of natural sand including supply, transportation to

site of works, loading and unloading of the materials, all labour and

manpower, equipments required for transport to the site,

necessary testing as per ISO / ASTM standards, fuel oil, incidental

and other operational charges etc complete as directed by Engineer

in charge and to the satisfaction of engineer in charge. The

foundation layer shall have organic content of < 1%. Grain size and

organic content shall be tested and got approved from the Engineer

in-charge before transportation to the site.

3105 cu.m

107b

Laying of sand brought from outside as a foundation layer in

containment cell in stagnant water pond 2 as presented on Drawing

Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3, also acting as

support layer for HDPE membrane liner using sand (0.0 - 2.0 cm

size) having rounded grain size materials between 0 - 20 mm, of

thickness 500 mm consisting of natural sand including spreading

and compaction of the sand to achieve 90% of proctor density. The

spreading and compaction has to be achieved by means of 5 tonnes

soil compaction rollers to required finished thicknesses and laid on

flat surfaces including supply, transportation to site of works,

loading and unloading of the materials, all labour and manpower,

equipments required for placing and spreading (dozers, tractor

trailors, front end loaders), compacting with equipments (soil

compactor rollers) and machinery, necessary testing as per ISO /

ASTM standards, fuel oil, incidental and other operational charges

etc complete as directed by Engineer in charge and to the

satisfaction of engineer in charge. The foundation layer shall have

organic content of < 1%. Grain size and organic content shall be

tested and got approved from the Engineer in-charge before

1380 cu.m

Works 4: Remediation works of NMK-KIE Page 292

Sr.

No.

Description of Item Qty. Unit

transportation to the site.

107c

Laying of sand brought from outside as a foundation layer in the

containment cells along bunds and hillock and in south eastern

corner of Lake NMK as presented on Drawing Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-

5-11, using sand (0.0 - 2.0 cm size) having rounded grain size

materials between 0 - 20 mm, of thickness 350 mm consisting of

natural sand including spreading in 7 layers of 50 mm each . The

spreading has to be controlled distribution of sand with a rainbow

technique and laid on flat surfaces and slopes of the lake floor

including supply, transportation to site of works, loading and

unloading of the materials, all labour and manpower, equipments

required for placing and spreading (boats, pontoons, pressure

pipes, underwater pumps, dozers, loaders backhoe, tractor trailors,

dumpers and poclain, front end loaders) and machinery, necessary

testing as per ISO / ASTM standards, fuel oil, incidental and other

operational charges etc complete as directed by Engineer in charge

and to the satisfaction of engineer in charge. The sand shall have

organic content of < 1%. Grain size and organic content shall be

tested and got approved from the Engineer in-charge before

transportation to the site.

1725 cu.m

107d

Supply, laying, jointing & fixing110 mm dia. HDPE Perforated /

Slotted Pipe warped with Geo Textile - 6 Kg/cm2 pressure as per IS

4984/14333, PE 100 grade in foundation layer of containment cells

along bunds and hillock and in south eastern corner of Lake NMK as

presented on Drawing Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6,

IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11.

2300 m

107e

Supply, laying, jointing & fixing110 mm dia. HDPE Closed Pipe, 6

Kg/cm2 pressure as per IS 4984/14333, PE 100 grade in foundation

layer of containment cells along bunds and hillock and in south

eastern corner of Lake NMK as presented on Drawing Nos. Nos.

IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11. The pipes connecting to perforated / slotted

pipes which are situated on bottom of the foundation layer layer.

The pipes shall run at the inner slopes of the clay body which is

placed behind the gabions and as such run below the bottom liner

of the containment cells. Pipes have to run from toe of inner slope

160 m

Works 4: Remediation works of NMK-KIE Page 293

Sr.

No.

Description of Item Qty. Unit

of ring dyke till top of the gabions.

107f

Supply, Laying and Jointing of Non-woven Needle Punched Geo

Textile of 250 GSM (grams per sq. m) minimum) of U.V. stabilized

polypropylene, polyethylene or polyester material acting as a

protection layer below part of the HDPE bottom liner in

containment cells along bunds and hillock and in south eastern

corner of Lake NMK as presented on Drawing Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-

5-11, laid over the inner slope of the clay body which is placed

behind the gabions including its unrolling, laying, overlapping and

jointing with special welding and anchoring ensuring proper joints

and junction overlaps, necessary testing as per ASTM / ISO

standards etc complete including all materials, labour,

transportation, loading and unloading, stacking at safe place, safe

handling, welding and jointing equipments with materials, tools

and plants etc complete as directed by engineer in charge and to

the satisfaction of engineer in charge.

2190 sq.m

108

Supply, Laying & Jointing of 2.0 mm thick HDPE Membrane Liner

(both side textured) acting as a main barrier layer (in the bottom

liner) in containment cells along bunds and hillock and in south

eastern corner of Lake NMK as presented on Drawings Nos. IND50-

1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and

IND50-1-5-11 and in stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3, laid over

the sand of the foundation layer or the geo-textile applied on the

clay body at the back of the gabions including its unrolling, laying,

jointing and welding as per ISO / ASTM Standards with proper

junction overlaps, welding at junctions/joints using welding

machines, providing sufficient anchoring, necessary testing as per

ASTM / ISO standards etc complete including all materials, labour

and manpower, transportation, loading and unloading, storing and

stacking at safe place, safe handling, welding and jointing

equipments with materials, tools and plants etc complete as

directed by engineer in charge and to the satisfaction of engineer in

charge. The HDPE Liner is provided in order to achieve the

permeability coefficient of minimum of 1 x 10-7 cm/sec as directed

by engineer in charge and to the satisfaction of engineer in charge.

14555 sq.m

Works 4: Remediation works of NMK-KIE Page 294

Sr.

No.

Description of Item Qty. Unit

109

Supply, laying, jointing & fixing110 mm dia. HDPE Perforated /

Slotted Pipe warped with Geo Textile - 6 Kg/cm2 pressure as per IS

4984/14333, PE 100 grade in containment cells along bunds and

hillock and in south eastern corner of Lake NMK as presented on

Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11 and in stagnant water pond 2 as

presented on Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-

2-3. The slotted drain pipes connecting to closed pipes which are

situated on inner slope of the ringdyke. The pipes shall run in the

bottom of the drainage layer and as such run below the tubes filled

with sediment and the cover layers of the containment cells.

2650 m

110

Supply, laying, jointing & fixing110 mm dia. HDPE Closed Pipe, 6

Kg/cm2 pressure as per IS 4984/14333, PE 100 grade in

containment cells along bunds and hillock and in south eastern

corner of Lake NMK as presented on Drawings Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-

5-11 and in stagnant water pond 2 as presented on Drawing Nos.

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3. The pipes connecting to

perforated / slotted pipes which are situated on bottom of the

drainage layer. The pipes shall run in the bottom of the drainage

layer on the inner slopes of the ring dykes and as such run below

the tubes filled with sediment and the cover layers of the

containment cells. Pipes have to run from toe of inner slope of ring

dyke till top of outer slope of the same.

225 m

111

Supply and laying of activated carbon, with a minimum Iodine

number of 650 and a maximum Molasses numner (EUR) of 700. 5

kg of active carbon per sq.m has to applied and mixed with sand of

the drainage layer (item 112b) between 0.25 and 0.35 below the

projected top of the drainage layer. Laying in drainage layer of

containment cells along bunds and hillock and in south eastern

corner of Lake NMK as presented on Drawings Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-

5-11 and in stagnant water pond 2 as presented on Drawing Nos.

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3.

72775 kg

112 Supply and Laying of sand brought from outside as a drainage layer

in containment cells along bunds and hillock and in south eastern

corner of Lake NMK as presented on Drawings Nos. IND50-1-5-4,

5625 cu.m

Works 4: Remediation works of NMK-KIE Page 295

Sr.

No.

Description of Item Qty. Unit

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-

5-11 and in stagnant water pond 2 as presented on Drawing Nos.

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3, also acting as support

layer for tubes of geotextile, using sand (0.0 - 2.0 cm size) having

rounded grain size materials between 0 - 20 mm and permeability

of k> 10-4 m/s, of thickness betwwen 350 and 500 mm consisting

of natural sand including spreading in 2 layers of 250 mm each and

compaction of the sand to achieve 90% of proctor density. The

spreading and compaction has to be achieved by means of 5 tonnes

soil compaction rollers to required finished thicknesses and laid on

flat surfaces and inner slopes of the ring dyke including supply,

transportation to site of works, loading and unloading of the

materials, all labour and manpower, equipments required for

placing and spreading (dozers, tractor trailors, dumpers, front end

loaders), compacting with equipments (soil compactor rollers) and

machinery, necessary testing as per ISO / ASTM standards, fuel oil,

incidental and other operational charges etc complete as directed

by Engineer in charge and to the satisfaction of engineer in charge.

The drainage layer shall have organic content of < 1%. Grain size

and organic content shall be tested and got approved from the

Engineer in-charge before transportation to the site.

113

Supply, Laying and Jointing of Non-woven Needle Punched Geo

Textile of 250 (GSM (grams per sq. m) minimum) of U.V. stabilized

polypropylene, polyethylene or polyester material acting as a

protection layer below the tubes with sediment in containment

cells along bunds and hillock and in south eastern corner of Lake

NMK as presented on Drawings Nos. IND50-1-5-4, IND50-1-5-5,

IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11, laid

over the HDPE liner of the bottom structure including its unrolling,

laying, overlapping and jointing with special welding and anchoring

ensuring proper joints and junction overlaps, necessary testing as

per ASTM / ISO standards etc complete including all materials,

labour, transportation, loading and unloading, stacking at safe

place, safe handling, welding and jointing equipments with

materials, tools and plants etc complete as directed by engineer in

charge and to the satisfaction of engineer in charge.

2363 sq.m

114 Collection, crushing, loading, transportation, unloading and

composting of vegetation from the entire project area as presented 131436 sq.m

Works 4: Remediation works of NMK-KIE Page 296

Sr.

No.

Description of Item Qty. Unit

on Drawing No. IND50-1/04. Vegetation has to be removed from

the following objects:

Dense vegetation present within the water line of Lake NMK, which covers an area of about 8,000 m2

Medium to dense vegetation present in the work and office space, which covers an area of about 13,200 m2

Medium to dense vegetation present near the projected containment cell in the south-eastern corner of Lake NMK, which covers an area of about 14,140 m2

Medium to dense vegetation from swamps 3 and 4, stagnant water ponds 1 and 2, which covers an total area of 16,436 m2

Sparse to medium vegetation from the unlined sections of the drains in KIE to such an extent that is required for an efficient and complete remediation of those sections

Some vegetation from the discharge channel in the plains to such an extent that is required for an efficient and complete remediation of this channel

Some vegetation from the open hillock area in KIE to such an extent that is required for an efficient and complete removal of the waste or the application of certain sections of this area for temporarily work space. The open hillock covers an area of 74,000 m2

After the vegetation has been collected and crushed the Contractor

has to arrange for the composting of the collected and crushed

vegetation. Composting has to been done by authorized

composting facilities in the vicinity of the project site. The produced

compost has to comply with the quality standards for compost as

per MSW 2008 rules and the standards for city compost as per the

rules of the agricultural department. After the compost has been

produced the Contractor has to mix this compost into the

vegetative layer of the containment cells.

Including all labour and manpower, equipments required for

crushing, , transport, placing and spreading (loaders backhoe,

crushers, tractor trailors, front end loaders, etc.), necessary testing

as per ISO / ASTM standards, fuel oil, incidental and other

Works 4: Remediation works of NMK-KIE Page 297

Sr.

No.

Description of Item Qty. Unit

operational charges etc complete as directed by Engineer in charge

and to the satisfaction of engineer in charge.

Part 2: Waste handling in KIE and landscaping of open hill lock in KIE

Sr.

No.

Description of Item Qty. Unit

201

Inventory of waste present in open hillock as presented on

Drawing No. IND50-1/04 including all tools and plants, materials,

labour and manpower, excavators and other heavy machinery,

etc complete as directed by engineer in charge and to the

satisfaction of engineer in charge

1 lumpsum

202

Excavation and Loading of MSW from the entire open hillock

(1,212 tonnes), the complete stagnant water ponds 1 and 2 , the

full extend of the swamps 3 and 4, the entire length of the drains

in KIE and the complete channel in the plains (a total of 202

tonnes) as presented on Drawing No. IND50-1/04 onto trucks to

off-site MSW landfill including all tools and plants, materials,

labour and manpower, excavators, dumper trucks and loader

backhoes, front end loaders, tractor trailors, etc complete as

directed by engineer in charge and to the satisfaction of engineer

in charge – (1400 cu.m = 1414 Tonnes). The MSW is spread all

over the surfaces of the aforementioned sub-sites. Sometimes in

the form of litter, but also as waste heaps or layers of up to about

2m thickness.

1414 Tonnes

203

Transportation and unloading of MSW to an authorized public

collection point operated by GHMC within 5 kilometers distance

of the site as directed by engineer in charge and to the

satisfaction of engineer in charge – (1400 cu.m = 1414 Tonnes).

1414 Tonnes

Works 4: Remediation works of NMK-KIE Page 298

204

Excavation, Loading, Unloading and transportation of biomedical

waste from open hillock as presented on Drawing No. IND50-1/04

onto closed trucks to off-site authorized treatment facility for

biomedical waste including all tools and plants, materials, labour

and manpower, excavators, dumper trucks and loader backhoes,

front end loaders, tractor trailors, etc complete as directed by

engineer in charge and to the satisfaction of engineer in charge –

(100 cu.m = 101 Tonnes). Several small spots of biomedical waste

have been observed in the open hillock.

101 Tonnes

205

Disposal costs of biomedical waste to be paid to an authorized

treatment facility for biomedical waste as directed by engineer in

charge and to the satisfaction of engineer in charge – (100 cu.m =

101 Tonnes).

101 Tonnes

206

Excavation, Loading, Unloading and transportation of hazardous

waste and slacks, ashes and sludges from open hillock as

presented on Drawing No. IND50-1/04 onto closed trucks to off-

site TSDF facility including all tools and plants, materials, labour

and manpower, excavators, dumper trucks and loader backhoes,

front end loaders, tractor trailors, etc complete as directed by

engineer in charge and to the satisfaction of engineer in charge –

It is estimated that about 1,100 cu.m of hazardous waste is

present in the open hillock. The volume of ashes, slacks and

sludges is also estimated at about 1,100 cu.m (1100 cu.m = 1111

Tonnes for Hazardous waste and 1100 cu.m = 1650 Tonnes for

ashes, slacks and sludges). Some heaps of sludges, slacks and

ashes are about 4 meter heigh. Majority of the material is spread

in layers between 0.25 and 0.75 meter of a significant portion of

the open hillock.

2761 Tonnes

207

Disposal costs of hazardous waste and slacks, ashes and sludges

to be paid to an authorized public TSDF operator as directed by

engineer in charge and to the satisfaction of engineer in charge –

. (1100 cu.m = 1111 Tonnes for Hazardous waste and 1100 cu.m =

1650 Tonnes for ashes, slacks and sludges)

2761 Tonnes

Works 4: Remediation works of NMK-KIE Page 299

208

Excavation, loading, off loading, transportation, backfilling and

leveling of soill and soil mixed with rubble as per Drawings No.

IND50-1-6-1, IND50-1-6-2 and IND50-1-6-3, including all tools and

plants, materials, labour and manpower, excavators, dozers,

loader backhoes, front end loaders, tractor trailors, etc complete

as directed by engineer in charge and to the satisfaction of

engineer in charge – (1250 cu.m). It has been estimated that the

total quantity of soil and soil with rubble is about 1,250 Cu.m. and

the majority of this material has been temporarily stored at 2

locations within the hillock.

1250 Cu.m

Part 3: Containment of sediments from Lake NMK and KIE

Sr.

No.

Description of Item Qty. Uni

t

A : Excavation, transportation and / or intermediate storage of sediment and polluted

topsoil

301

Clean up of all the drains of length 3000meters (approx.) in the entire KIE

area till the extend that all sediments have been removed through

Excavation, Loading, Unloading and Transportation of poluted sediments

from open drains in KIE as presented in Drawing No. IND50-1-6-6 onto

closed and water tight trucks to intermediate storage depot in stagnant

water pond 2 including all tools and plants, materials, labour and

manpower, excavators, loader backhoes, front end loaders, tractor

trailors, etc complete as directed by engineer in charge and to the

satisfaction of engineer in charge. In Drawing No. IND50-1-6-6 the length

of the major drains in KIE are presented.

300 Cu.

m

302

Clean up of swamps 3 and 4 in KIE till the extend that all polluted topsoil

has been removed as presented on Drawing Nos. IND50-1-3-1, IND50-1-3-

2, IND50-1-3-3, IND50-1-4-1, IND50-1-4-2 and IND50-1-4-3 through

Excavation, Loading, Unloading and Transportation of polluted top soil

from swamps 3 and 4 in KIE onto closed and water tight trucks to fill layer

above filled tubes of geotextile in containment cell situated in stagnant

water pond 2 including all tools and plants, materials, labour and

manpower, excavators, loader backhoes, front end loaders, tractor

trailors, etc complete as directed by engineer in charge and to the

satisfaction of engineer in charge. In sections V and VI the dimensions of

the excavation have been detailed.

350 Cu.

m

Works 4: Remediation works of NMK-KIE Page 300

Sr.

No.

Description of Item Qty. Uni

t

303

Clean up of swamps 3 and 4 in KIE as presented on Drawings IND50-1-3-1,

IND50-1-3-2, IND50-1-3-3, IND50-1-4-1, IND50-1-4-2 and IND50-1-4-3

through Excavation, Loading, Unloading and Transportation of poluted

sediment from swamps 3 and 4 in KIE onto closed and water tight trucks to

intermediate storage depot in stagnant water pond 2 including all tools

and plants, materials, labour and manpower, excavators, loader backhoes,

front end loaders, tractor trailors, etc complete as directed by engineer in

charge and to the satisfaction of engineer in charge. In sections V and VI

the dimensions of the excavation have been detailed.

200 Cu.

m

304

Clean up of channel in the plains as presented on Drawing No. IND50-1-7-1

through Excavation, Loading, Unloading and Transportation of poluted

sediment from the same channel onto closed and water tight trucks to fill

layer above filled tubes of geotextile in containment cell situated in

stagnant water pond 2 including all tools and plants, materials, labour and

manpower, excavators, loader backhoes, front end loaders, tractor

trailors, etc complete as directed by engineer in charge and to the

satisfaction of engineer in charge. In sections V and VI the dimensions of

the excavation have been detailed.

500 Cu.

m

305

Clean up of stagnant water pond 1 in KIE as presented on Drawing Nos.

IND50-1-1-1, IND50-1-1-2, IND50-1-1-3 through Excavation, Loading,

Unloading and Transportation of poluted top soil from stagnant water

pond 1 in KIE on closed and water tight dumper trucks to fill layer above

filled tubes of geotextile in containment cell situated in stagnant water

pond 2 including all tools and plants, materials, labour and manpower,

excavators, loader backhoes, front end loaders, tractor trailors, etc

complete as directed by engineer in charge and to the satisfaction of

engineer in charge. In sections V and VI the dimensions of the excavation

have been detailed.

216 Cu.

m

306

Clean up of stagnant water pond 1 in KIE as presented on Drawing Nos.

IND50-1-1-1, IND50-1-1-2, IND50-1-1-3 through Dredging and

Transportation of poluted sediment from stagnant water pond 1 in KIE

directly into closed pressures lines via mixture and feeding unit into tubes

of geotextile, including all tools and plants, materials, labour and

manpower, dredging equipment, pontoons, excavators, pressure lines,

mxing and feeder units etc complete as directed by engineer in charge and

to the satisfaction of engineer in charge. In sections V and VI the

dimensions of the excavation have been detailed.

108

4

Cu.

m

Works 4: Remediation works of NMK-KIE Page 301

Sr.

No.

Description of Item Qty. Uni

t

307

Clean up of stagnant water pond 2 in KIE as presented on Drawing Nos.

IND50-1-1-1, IND50-1-1-2, IND50-1-1-3 through Excavation, Loading,

Unloading and Transportation of poluted top soil from stagnant water

pond 2 in KIE onto on tippers or small dumper trucks to fill layer above

filled tubes of geotextile in containment cell situated in the same stagnant

water pond including all tools and plants, materials, labour and

manpower, excavators, front end loaders, tractor trailors, etc complete as

directed by engineer in charge and to the satisfaction of engineer in

charge. Including intermediate storage of polluted soil, if polluted soil

underneath the containment cell in stagnant water pond 2 has to be

relocated temporarily to allow for the construction of the same cell. In

sections V and VI the dimensions of the excavation have been detailed.

172

0

Cu.

m

308

Clean up of stagnant water pond 2 in KIE as presented on Drawing Nos.

IND50-1-1-1, IND50-1-1-2, IND50-1-1-3 through Dredging and

Transportation of poluted sediment from stagnant water pond 2 in KIE

directly into closed pressures lines via mixture and feeding unit into tubes

of geotextile, including all tools and plants, materials, labour and

manpower, dredging equipment, pontoons, excavators, pressure lines,

mxing and feeder units etc complete as directed by engineer in charge and

to the satisfaction of engineer in charge. Including intermediate storage, if

polluted sediments underneath the containment cell in stagnant water

pond 2 have to be relocated temporarily to allow for the construction of

the same cell. In sections V and VI the dimensions of the excavation have

been detailed.

516

0

Cu.

m

Ancillary Civil Works

309

Construction of RCC M 20 Check wall cast in situ , PCC (1:3:6) at base

(Refer Drawing Nos IND 50-1-1-3 and IND50-1-1-4) including cement, sand,

aggregates (10 to 25 mm size) and s as per standard IS Codes, excavation,

dewatering of pits, surface dressing, preparation of bed by levelling,

casting of RCC slabs, centering, shuttering, machine mixing, placing,

vibrating, finishing smooth, watering and curing, all materials,

machineries, tools and tackles, fuel, transportation, incidental and other

operation charges etc complete as directed by engineer in charge. Further

specifications have been provided on Drawing No. IND50-1-1-4.

chec

k-7.5 m x 0.3 m x 2.02 m for the wall + 7.5 m x 1.5 m x 0.3 for the foot 8

Cu.

m

Works 4: Remediation works of NMK-KIE Page 302

Sr.

No.

Description of Item Qty. Uni

t

dam

1

chec

k-

dam

2

22.5 m x 0.3 m x 2.03 m for the wall + 22.5 m x 1.5 m x 0.3 for the foot 24 Cu.

m

chec

k-

dam

3

17.5 m x 0.3 m x 2.03 m for the wall + 17.5 m x 1.5 m x 0.3 for the foot 19 Cu.

m

chec

k-

dam

4

10.5 m x 0.3 m x 2.04 m for the wall + 10.5 m x 1.5 m x 0.3 for the foot 12 Cu.

m

310

Supply and installation of steel pipe in the middle section of each wall of

the check-dam as per specification presented on Drawing No. IND50-1-1-4.

Pipe has to be installed in position before cement of this wall shall be

poured. The top of the pipe has to be 0.2 m below the top of this wall. The

pipe has to have a diameter of 0.3 m and a wall thickness of 0.01 m. The

pipes in check-dams numbers 1, 2 and 3 have to include on the side of

stagnant water pond 1 a check valve. The pipe in check-dam number 4 has

to have such a check-valve on the side of stagnant water pond 2. Thickness

of the check-valve and the required flense to connect it to the pipe should

be 0.01m. (Refer Drawing No IND 50-1-1-4) Including Steel as per standard

IS Codes, all materials, machineries, tools and tackles, fuel, transportation,

incidental and other operation charges etc complete as directed by

engineer in charge.

4 No

s.

B : Dredging sediment in LakeNMK

311

To conduct a continuous bathemetric survey of lake NMK as presented on

Drawing No, IND50-1/03. Survey results have to be supported by

additional hand measurements at 100 points with for example an auger

drill, hand probe or comparable devices. Results of hand measurements

and bathemetric serveys have to match with each other. The top of the

sediment has to be measured with an accuracy of + 0.03 m. The top of the

clay layer has to be measured with an accuracy of + 0.02 m. The survey

687

60

sq.

m

Works 4: Remediation works of NMK-KIE Page 303

Sr.

No.

Description of Item Qty. Uni

t

results have to be incorporated in a continuous 3D computer model of the

sediments and the top of the clay layer. Survey, including all tools and

plants, materials, labour and manpower, boats, pontoons and other

machinery, etc complete as directed by engineer in charge and to the

satisfaction of engineer in charge

312

Dredging and transportation of sediments from Lake NMK as presented on

Drawing Nos. IND50-1-5-1 and IND50-1-5-2 with a hydraulic dredger

equipped with an auger head, ecodredge or comparable device, including

all incidenal works, leads, charges and other costs. The actual operation

and movement of the dredging equipment should be at all times be

computer guided on the basis of the established 3D computer model and a

high accuracy dGPS positioning system. At all times the actual position of

the auger head or comparable device has to be known in real time along

all six axes of free movement with an accuracy of 5 mm. The combination

of the 3D model guidance and dGPS positioning has to allow for a total

dredging accuracy of + 0.03 m. Transportation has to be done with

pressure lines towards a dewatering cell at about 500 meters distance

where the sediment slurry has to be directly fed into tubes of geotextile.

The slurry of sediments and water has to be delivered at a constant

pressure and water/sediment ratio. The sediments are severly

contaminated with TPH, heavy metals and contain residual dyes.This

presssure and ratio have to be monitored at all times and in real time.

Dredging has to be done in varying water depths ranging from only a few

decimeters up till 3.8 meters depth. Dredging and transport operations

have to include all tools and plants, materials, labour and manpower,

dredgers, pontoons, transport lines, excavators, loader backhoes, front

end loaders, tractor trailors, etc complete as directed by engineer in

charge and to the satisfaction of engineer in charge .

323

17

Cu.

m

C : Dewatering of Sediment

313

Dewatering of sediments from Lake NMK within the bottom liner of the in

containment cells along bunds and hillock and in south eastern corner of

Lake NMK as presented on Drawings Nos. IND50-1-5-4, IND50-1-5-5,

IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11 and in stagnant

water pond 2 as presented on Drawing Nos. IND50-1-2-1, IND50-1-2-2 and

IND50-1-2-3 with a combination of tubes of geotextile and the application

of flocculants and / or electrolyte admixtures, a real time monitored

mixing unit and all pumps and valves required to inject the sediment slurry

323

17

Cu.

m

Works 4: Remediation works of NMK-KIE Page 304

Sr.

No.

Description of Item Qty. Uni

t

in the tubes of geotextile and to pump the process water back to the lake

or stagnant water ponds, including all incidenal works, leads, charges,

tests, certification, QA & QC procedures and other costs.

Including supply and application of tubes of geotextile with a

circumference of 9 meters (+0.2m) and a length of 27.5 meter (+0.5

meter) at the NMK/KIE site (all costs and charges included), which are

manufactured under ISO9001.The manufacturer of woven tubes has to

control the quality of all stages of production, the production of the yarns,

the weaving and the final tube manufacturing. The yarns have to be

specifically designed for dewatering and solids containment. Similarly the

woven tubes should be designed specifically for dewatering and solids

containment. Textiles used in the manufacturing of the tubes have to

meet the following filtration characteristics:

· The tube must be made from a woven monofilament polypropylene,

manufactured so that the yarns retain their respective positions in

whatever direction force is exerted. Textiles must be stable vis-à-vis

biological degradation and resistant to naturally occurring chemicals such

as alkalis and acids and naturally occurring UV conditions. · Tensile strength MD according to EN-ISO 10319 ≥ 70 kN / m

· CD according to EN-ISO 10319 ≥ 95 kN / m

· Permeability according to EN ISO 11058 ≥ 1,800 liters / m². min

· Characteristic opening O90 according to EN ISO 12956

250mμ

· UV Resistance after exposure to 200 KLY 12224 and EN ISO 12226

60%

· Minimum strength of circumferential seams according to EN ISO

10321 ≥ 65 kN / m

Only a single longitudinal seam shall be permitted on each tube. Each tube

has to be produced with one or more filling points. These filling points

have to be located on the centre line of the tube surface. The filling points

have to be constructed with flanges to maintain fabric stability during

filling.

Including supply, preparation and application of flocculants and /or

electrolyte solution. The contractor has to use a suitable

flocculants/electrolytes in order to have sufficient coagulation and

flocculation to achieve the following:

Works 4: Remediation works of NMK-KIE Page 305

Sr.

No.

Description of Item Qty. Uni

t

• The process water draining from the geo tube should be colourless

without oil film and dye

• The analyzed process water should show low concentrations of heavy

metals and TPH.

• Heavy metals, dyes and TPH shall be retained in the sludge after

dewatering in the Geo tubes.

• The indicative leaching test (shake test) with the dewatered sludge shall

demonstrate no release of heavy metals and TPH

• Clear separation of sludge after addition of flocculant should be

obtained,

The volume of sediments shall be reduced to 40% after dewatering.

Typical analytical results in µg/l for the process water draining from the

Geo tubes shall be minimum to the levels as under:

Sample As Cd Cr Cu Hg Ni Pb Zn TPH (sum C10-

C40)

Water sample 1 1.5 <

0.4

<

5.0

5.3 < 0.10 5.2 16 30 1,100

Water sample 2 1.8 <

0.4

8.1 14 0.12 8.2 45 65 110

Water sample 3 2.0 <

0.4

<

5.0

<

5.0

< 0.10 < 5.0 5.3 16 1,000

The results of a leaching test simulating a leaching period of at least 20

years shall be minimum to the levels as under in mg.kgdm:

Sample As Cd Cr Cu Hg Ni Pb Zn TPH (sum C10-C40)

Sludge after dewatering

< 0.10

< 0.0020

0.053

< 0.10

< 0.00080

< 0.10

< 0.20

< 0.60

4.4

Any flocculent and/or electrolyte solution proposed by the Contractor

Works 4: Remediation works of NMK-KIE Page 306

Sr.

No.

Description of Item Qty. Uni

t

shall at least meet all of the aforementioned results of the initial

feasibility test.

The time taken for selection of a suitable flocculant / electrolyte and its

approval from the engineer in charge shall be a part of the timeline given

for the completion of the particular milestone. No additional time shall be

given for this activity.

As the type and concentration of flocculant/electrolyte and its application

ratio’s proved to be very critical the Contractor has to reassess the

required type, concentration and application rates of the flocculants

and/or electrolytes before the de-watering commences. The Contractor is

responsible for taking representative and sufficient sludge samples to

analyse the sediments, perform in situ tests, to determine dosages and

types of polymers if necessary, and control their injection to obtain good

flocculation.

Dewatering operations have to include all costs, charges tools and plants,

materials, labour and manpower, dredgers, pumps, control units, mixing

units, valves, transport lines, excavators, loader backhoes, front end

loaders, tractor trailors, etc complete as directed by engineer in charge

and to the satisfaction of engineer in charge

314

Dewatering of sediments from stagnant water ponds 1 and 2, swamps 3

and 4, drains in KIE and channel downstream within the bottom liner of

the in containment cell in stagnant water pond 2 as presented on Drawing

Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3 or in the containment

cells along bunds and hillock and in south eastern corner of Lake NMK as

presented on Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6,

IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11, with a combination of tubes

of geotextile and the application of flocculants and / or electrolyte

admixtures, a real time monitored mixing unit and all pumps and valves

required to inject the sediment slurry in the tubes of geotextile and to

pump the process water back to the lake or stagnant water ponds,

including all incidenal works, leads, charges, tests, certification, QA & QC

procedures and other costs.

Including supply and application of tubes of geotextile with a

circumference of 9 meters (+0.2m) and a length of 27.5 meter (+0.5

meter) at the NMK/KIE site (all costs and charges included), which are

724

4

Cu.

m

Works 4: Remediation works of NMK-KIE Page 307

Sr.

No.

Description of Item Qty. Uni

t

manufactured under ISO9001.The manufacturer of woven tubes has to

control the quality of all stages of production, the production of the yarns,

the weaving and the final tube manufacturing. The yarns have to be

specifically designed for dewatering and solids containment. Similarly the

woven tubes should be designed specifically for dewatering and solids

containment. Textiles used in the manufacturing of the tubes have to

meet the following filtration characteristics:

· The tube must be made from a woven monofilament polypropylene,

manufactured so that the yarns retain their respective positions in

whatever direction force is exerted. Textiles must be stable vis-à-vis

biological degradation and resistant to naturally occurring chemicals such

as alkalis and acids and naturally occurring UV conditions. · Tensile strength MD according to EN-ISO 10319 ≥ 70 kN / m

· CD according to EN-ISO 10319 ≥ 95 kN / m

· Permeability according to EN ISO 11058 ≥ 1,800 liters / m². min

· Characteristic opening O90 according to EN ISO 12956 250mμ

· UV Resistance after exposure to 200 KLY 12224 and EN ISO 12226

60%

· Minimum strength of circumferential seams according to EN ISO 10321 ≥

65 kN / m

Only a single longitudinal seam shall be permitted on each tube. Each tube

has to be produced with one or more filling points. These filling points

have to be located on the centre line of the tube surface. The filling points

have to be constructed with flanges to maintain fabric stability during

filling.

Including supply, preparation and application of flocculants and /or

electrolyte solution.The contractor has to use a suitable

flocculants/electrolytes in order to have sufficient coagulation and

flocculation to achieve the following:

• The process water draining from the geo tube should be colourless

without oil film and dye

• The analyzed process water should show low concentrations of heavy

metals and TPH.

• Heavy metals, dyes and TPH shall be retained in the sludge after

dewatering in the Geo tubes.

• The indicative leaching test (shake test) with the dewatered sludge shall

demonstrate no release of heavy metals and TPH

Works 4: Remediation works of NMK-KIE Page 308

Sr.

No.

Description of Item Qty. Uni

t

• Clear separation of sludge after addition of flocculant should be

obtained,

The volume of sediments shall be reduced to 40% after dewatering.

Typical analytical results in µg/l for the process water draining from the

Geo tubes shall be minimum to the levels as under:

Sample As Cd Cr Cu Hg Ni Pb Zn TPH (sum C10-C40) Water sample 1 1.5 <

0.4 < 5.0

5.3 < 0.10

5.2 16 30 1,100

Water sample 2 1.8 < 0.4

8.1 14 0.12 8.2 45 65 110

Water sample 3 2.0 < 0.4

< 5.0

< 5.0

< 0.10

< 5.0

5.3 16 1,000

The results of a leaching test simulating a leaching period of at least 20

years shall be minimum to the levels as under in mg.kgdm:

Sample As Cd Cr Cu Hg Ni Pb Zn TPH (sum C10-C40)

Sludge after dewatering

< 0.10

< 0.0020

0.053

< 0.10

< 0.00080

< 0.10

< 0.20

< 0.60

4.4

Any flocculent and/or electrolyte solution proposed by the Contractor

shall at least meet all of the aforementioned results of the initial

feasibility test.

The time taken for selection of a suitable flocculant / electrolyte and its

approval from the engineer in charge shall be a part of the timeline given

for the completion of the particular milestone. No additional time shall be

given for this activity.

Works 4: Remediation works of NMK-KIE Page 309

Sr.

No.

Description of Item Qty. Uni

t

As the type and concentration of flocculant/electrolyte and its application

ratio’s proved to be very critical the Contractor has to reassess the

required type, concentration and application rates of the flocculants

and/or electrolytes before the de-watering commences. The Contractor is

responsible for taking representative and sufficient sludge samples to

analyse the sediments, perform in situ tests, to determine dosages and

types of polymers if necessary, and control their injection to obtain good

flocculation.

Dewatering operations have to include all costs, charges tools and plants,

materials, labour and manpower, dredgers, pumps, control units, mixing

units, valves, transport lines, excavators, loader backhoes, front end

loaders, tractor trailors, etc complete as directed by engineer in charge

and to the satisfaction of engineer in charge

Part 4: Installation of cover layer on top of the containment cells.

Sr.

No.

Description of Item Qty. Unit

A : Installation of Cover Layers on Containment Cells

401

Laying of ordinary earth brought from inside as a fill and clay layer

on top of the tubes with sediment in the containment cells along

the bund and hillock and in southeastern corner of NMK as

presented on Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-

6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11 and in stagnant

water pond 2 as presented on Drawing Nos. IND50-1-2-1, IND50-1-

2-2 and IND50-1-2-3. First of all a significant amount of fil material

has to be applied on the slopes of the filled geotubes to obtain

smooth 1:3 slopes. Between 6 till 12 Cu.M fill material is required to

obtain smooth slopes at the containment cell in stagnant water

pond 2. Along the bund and hillock about 3.0 Cu.m of fill is required

per m length of the containment cell. On top of the containment

cell in pond 2 a clay layer of 0.3 m thick is required. Earth suitable

as fill material underneath HDPE top liner of the containment cells

including spreading and compaction of ordinary earth in layers of at

least 300 mm thickness to achieve 90% of proctor density. Material

from inside originates from excavation of polluted topsoil from

stagnant water ponds 1 and 2 and swamps 3 and 4 of KIE, the

excavation of the gabion trench and from excavation of storm

4176 cu.m

Works 4: Remediation works of NMK-KIE Page 310

Sr.

No.

Description of Item Qty. Unit

water runoff ditches around the containment cells). The spreading

has to be done to the required finished thicknesses and has to be

laid on flat surfaces and slopes up to 1:3, including supply,

transportation to site of works, loading and unloading of the

materials, all labour and manpower, equipments required for

placing and spreading (dozers, loaders backhoe, tractor trailors,

front end loaders), compacting with equipments (soil compactor

rollers) and machinery, necessary testing as per ISO / ASTM

standards, fuel oil, incidental and other operational charges etc

complete as directed by Engineer in charge and to the satisfaction

of engineer in charge.

402a

Supply and Laying of sand brought from outside as a foundation

layer in the containment cell in stagnant water pond 2 as presented

on Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3, also

acting as support layer for HDPE membrane liner using sand (0.0 -

2.0 cm size) having rounded grain size materials between 0 - 20

mm, of thickness 200 mm consisting of natural sand including

spreading and compaction of the sand in layers of 200 mm

maximum thickness to achieve 90% of proctor density. The

spreading and compaction has to be achieved by means of 5 tonnes

soil compaction rollers to required finished thicknesses and laid on

flat surfaces including supply, transportation to site of works,

loading and unloading of the materials, all labour and manpower,

equipments required for placing and spreading (dozers, loaders

backhoe, tractor trailors, dumpers and poclain, front end loaders),

compacting with equipments (soil compactor rollers) and

machinery, necessary testing as per ISO / ASTM standards, fuel oil,

incidental and other operational charges etc complete as directed

by Engineer in charge and to the satisfaction of engineer in charge.

The foundation layer shall have organic content of < 1%. Grain size

and organic content shall be tested and got approved from the

Engineer in-charge before transportation to the site.

525 cu.m

402b

Supply, Laying and Jointing of Non-woven Needle Punched Geo

Textile of (250 GSM (grams per sq. m) minimum) of U.V. stabilized

polypropylene, polyethylene or polyester material acting as a

protection layer below part of the HDPE top liner in the

containment cells along the bund and hillock and in southeastern

corner of NMK as presented on Drawings Nos. IND50-1-5-4, IND50-

11500 sq.m

Works 4: Remediation works of NMK-KIE Page 311

Sr.

No.

Description of Item Qty. Unit

1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11,

laid over the tubes with sediment/the fill layer including its

unrolling, laying, overlapping and jointing with special welding and

anchoring ensuring proper joints and junction overlaps, necessary

testing as per ASTM / ISO standards etc complete including all

materials, labour, transportation, loading and unloading, stacking at

safe place, safe handling, welding and jointing equipments with

materials, tools and plants etc complete as directed by engineer in

charge and to the satisfaction of engineer in charge.

403

Supply, Laying & Jointing of 2.0 mm thick HDPE Membrane Liner

(both side textured) in the containment cells along the bund and

hillock and in southeastern corner of NMK as presented on

Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11 and in stagnant water pond 2 as

presented on Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-

2-3 acting as a main barrier layer (in the top liner), laid over the

sand of the foundation layer or the protective layer of the geo-

textile including its unrolling, laying, jointing and welding as per ISO

/ ASTM Standards with proper junction overlaps, welding at

junctions/joints using welding machines, providing sufficient

anchoring, necessary testing as per ASTM / ISO standards etc

complete including all materials, labour and manpower,

transportation, loading and unloading, storing and stacking at safe

place, safe handling, welding and jointing equipments with

materials, tools and plants etc complete as directed by engineer in

charge and to the satisfaction of engineer in charge. The HDPE Liner

is provided in order to achieve the permeability coefficient of

minimum of 1 x 10-7 cm/sec as directed by engineer in charge and

to the satisfaction of engineer in charge.

14615 sq.m

404

Supply, laying, jointing & fixing110 mm dia. HDPE Perforated /

Slotted Pipe wraped with Geo Textile - 6 Kg/cm2 pressure as per IS

4984/14333, PE 100 grade in the drainage layer on top of the

topliner of the containment cells along the bund and hillock and in

southeastern corner of NMK as presented on Drawings Nos. IND50-

1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and

IND50-1-5-11 and in stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3- The

slotted drain pipes connecting to closed pipes which are situated

1950 m

Works 4: Remediation works of NMK-KIE Page 312

Sr.

No.

Description of Item Qty. Unit

on outer slopes of the containment cells. The pipes shall run in the

bottom of the drainage layer and as such run below the final cover

layers of the containment cells.

405

Supply, laying, jointing & fixing110 mm dia. HDPE Closed Pipe, 6

Kg/cm2 pressure as per IS 4984/14333, PE 100 grade in the

drainage layer of the top slopes of the containment cells along the

bund and hillock and in southeastern corner of NMK as presented

on Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-

5-9, IND50-1-5-10 and IND50-1-5-11 and in stagnant water pond 2

as presented on Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-

1-2-3 - The pipes connecting to perforated / slotted pipes which are

situated on top and toe of the outer slope and the intermediate

berms. The pipes shall run in the bottom of the drainage layer on

the outer slopes of the containment cells and as such run below the

final cover layers of the containment cells.

350 m

406a

Supply and Laying of sand brought from outside as a drainage layer

on top of the HDPE top liner of the containment cell in stagnant

water pond 2 as presented on Drawing Nos. IND50-1-2-1, IND50-1-

2-2 and IND50-1-2-3, using sand (0.0 - 2.0 cm size) having rounded

grain size materials between 0 - 20 mm and permeability of k > 10-

4 m/s, of thickness 200 mm consisting of natural sand including

spreading in 1 layer of 200 mm and compaction of the sand to

achieve 90% of proctor density. The spreading and compaction has

to be done to required finished thicknesses and laid on flat surfaces

and slopes up to 1:3 including supply, transportation to site of

works, loading and unloading of the materials, all labour and

manpower, equipments required for placing and spreading (dozers,

loaders backhoe, tractor trailors, dumpers, front end loaders),

compacting with equipments (soil compactor rollers) and

machinery, necessary testing as per ISO / ASTM standards, fuel oil,

incidental and other operational charges etc complete as directed

by Engineer in charge and to the satisfaction of engineer in charge.

The foundation layer shall have organic content of < 1%. Grain size

and organic content shall be tested and got approved from the

Engineer in-charge before transportation to the site.

925 cu.m

Works 4: Remediation works of NMK-KIE Page 313

Sr.

No.

Description of Item Qty. Unit

406b

Supply, laying and Jointing of Geo Composite (Drainage Mat) in the

containment cells along the bund and hillock and in southeastern

corner of NMK as presented on Drawings Nos. IND50-1-5-4, IND50-

1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11

having sandwich construction of two Non-woven needle punch

geotextiles filtration layers (of 150 GSM) having artificial drainage

element (Geo Net) in between of 5 mm thickness having

permeability of 1 x 10-2 cm/sec including its unrolling, laying,

jointing having proper junction overlaps, anchoring, necessary

testing as per ASTM / ISO standards etc complete including all

materials, labour, transportation, loading and unloading, stacking at

safe place, safe handling, welding and jointing equipments with

materials, tools and plants etc complete as directed by engineer in

charge and to the satisfaction of engineer in charge. The Geo-

composite mat shall be protected against physical damages during

transport to the site / during storage at the site. Geo-composite

rolls on stock shall be protected from UV radiation by covering with

tarpaulins. Geo-composites on slopes (in slope direction) shall be in

one piece and connection of two roles in slope direction shall only

take place on berms. The items is complete including all materials,

laying and jointing, anchoring, welding, labour and manpower etc

complete as per specifications, as directed by engineer in charge

and to the satisfaction of engineer in charge.

11500

Sq.m

407

Supply, Laying and Jointing of Non-woven Needle Punched Geo

Textile in the containment cells in stagnant water pond 2 as

presented on Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-

2-3 of (250 GSM (grams per sq. m) minimum) of U.V. stabilized

polypropylene, polyethylene or polyester material acting as a

protection layer below final top cover of vegetative layer, laid over

the Drainage Layer including its unrolling, laying, overlapping and

jointing with special welding and anchoring ensuring proper joints

and junction overlaps, necessary testing as per ASTM / ISO

standards etc complete including all materials, labour,

transportation, loading and unloading, stacking at safe place, safe

handling, welding and jointing equipments with materials, tools and

plants etc complete as directed by engineer in charge and to the

satisfaction of engineer in charge.

4625 sq.m

Works 4: Remediation works of NMK-KIE Page 314

Sr.

No.

Description of Item Qty. Unit

408

Supply and Laying of ordinary earth as clean vegetative soil in the

containment cells along the bund and hillock and in southeastern

corner of NMK as presented on Drawings Nos. IND50-1-5-4, IND50-

1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11

and in stagnant water pond 2 as presented on Drawing Nols.

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3, brought from outside

(supporting growth of grass) as a final cover layer of thickness of

800 mm (stagnant water pond 2) or 500 mm (Lake NMK) mm

consisting of natural soil, silty clays mixed with sand as prevalent in

Hyderabad Region and suitable for landscape development

including spreading and compaction of ordinary earth in layers of

500 mm maximum thickness to achieve 90% of proctor density. The

spreading and compaction has to be achieved by means of 5

tonnes soil compaction rollers to required finished thicknesses and

laid on slopes, berms and flat surfaces as well as top of the

containment cells including supply, transportation to site of works,

loading and unloading of the materials, all labour and manpower,

equipments required for placing and spreading (dozers, loaders

backhoe, tractor trailors, dumpers front end loaders), compacting

with equipments (soil compactor rollers) and machinery, necessary

testing as per ISO / ASTM standards, fuel oil, incidental and other

operational charges etc complete as directed by Engineer in charge

and to the satisfaction of engineer in charge.

9450 cu.m

409

Supply, Laying and Jointing of Non-woven Needle Punched Geo

Textile at the waterfront slope of the containment cell in stagnant

water pond 2 as presented on Drawings Nos. IND50-1-2-1, IND50-1-

2-2 and IND50-1-2-3 of (250 GSM (grams per sq. m) minimum) of

U.V. stabilized polypropylene, polyethylene or polyester material

acting as a filter layer below revetment stones, laid over the outer

slope of the containment cell along stagnant water pond 2

including its unrolling, laying, overlapping and jointing with special

welding and anchoring ensuring proper joints and junction

overlaps, necessary testing as per ASTM / ISO standards etc

complete including all materials, labour, transportation, loading

and unloading, stacking at safe place, safe handling, welding and

jointing equipments with materials, tools and plants etc complete

as directed by engineer in charge and to the satisfaction of

engineer in charge.

405 Sq. M

Works 4: Remediation works of NMK-KIE Page 315

Sr.

No.

Description of Item Qty. Unit

410

Supply and Laying of Granite for SS revetment 225 brought from

outside as a revetment layer on the outer slope of the containment

cell along stagnant water pond 2 as presented on Drawings Nos.

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3, using stones (200 - 400

mm size) having uniform appearances, of thickness 230 mm

consisting of natural hard stones including spreading in 1 layers of

230 mm. Including spreading and laid on slopes of the containment

cell including supply, transportation to site of works, loading and

unloading of the materials, all labour and manpower, equipments

required for placing and spreading (boats, pontoons, dozers,

loaders backhoe, tractor trailors, dumpers and poclain, front end

loaders) and machinery, necessary testing as per ISO / ASTM

standards, fuel oil, incidental and other operational charges etc

complete as directed by Engineer in charge and to the satisfaction

of engineer in charge. Stones shall be tested and got approved from

the Engineer in-charge before transportation to the site.

95 cu.m

B : Ancillary Civil Works

411

Excavation of Open Storm Water Drains at all containment cells in

Lake NMK and stagnant water pond 2, through excavation of

topsoil and profilling of open tenches with the following

dimensions: 0.5 m x 0.5 m or 0.3 m x 0.3 m at the top drain,

intermediate drain of 0.3 m x 0.3 m and bottom drain of 7.0 m x 1.0

m with 1:3 slopes or 6.0 m x 1.0 m with 1:3 slopes at base (Refer

Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10, IND50-1-5-11, IND50-1-2-1, IND50-1-2-2 and IND50-

1-2-3), including, excavation, dewatering of trenches, surface

dressing, preparation of bed by levelling, all materials, machineries,

tools and tackles, fuel, transportation, incidental and other

operation charges etc complete as directed by engineer in charge.

Soil excavated for top and intermediate drains have to be spread in

topsoil layer of the containment cell. Soil excavated from drains at

the bottom has to be applied in fill layer of the the cover layer of

the containment cell.

A

0.5 m x 0.5 m (or 0.25 m3/m) wide drain at top most berm (Type 1)

of the containment cell in stagnant water pond 2. Total volume 18

m3.

71 m

Works 4: Remediation works of NMK-KIE Page 316

Sr.

No.

Description of Item Qty. Unit

B

0.3 m x 0.3 m (or 0.09 m3/m) wide drain at top berm (Type 2) in

containment cells along the bund and in southeastern part of Lake

NMK. Total volume 61 m3.

675 m

C

0.3 m x 0.3 m (or 0.09 m3/m) wide drain at intermediate berm

(Type 3) of the containment cell in stagnant water pond 2. Total

volume 18 m3.

200 m

D

6.0 m x 1.0 m (or 3 m3/m) wide drain at bottom, with slopes 1:3

(Type 3) of the containment cell in stagnant water pond 2. Total

volume 630 m3.

210 m

E

7.0 m x 1.0 m (or 6.2 m3/m) wide drain at bottom, with slopes 1:3

(Type 5) along the southern and eastern perimeter of the

containment cell in the southeastern corner of Lake NMK.. Total

volume 1240 m3.

200 m

412

Supply, Laying and Jointing of Non-woven Needle Punched Geo

Textile of (250 GSM (grams per sq. m) minimum) of U.V. stabilized

polypropylene, polyethylene or polyester material acting as a filter

layer below revetment stones, laid over the slopes of the bottom

drain around the containment in the southeastern corner of Lake

NMK (Refer Drawings Nos. IND50-1-5-9, IND50-1-5-10 and IND50-1-

5-11) including its unrolling, laying, overlapping and jointing with

special welding and anchoring ensuring proper joints and junction

overlaps, necessary testing as per ASTM / ISO standards etc

complete including all materials, labour, transportation, loading

and unloading, stacking at safe place, safe handling, welding and

jointing equipments with materials, tools and plants etc complete

as directed by engineer in charge and to the satisfaction of

engineer in charge.

1470 Sq. M

413

Supply, Laying of Granite for SS revetment 225 brought from

outside as a revetment layer on the slopes and floor of the bottom

dain of the containment cell in the southeastern corner of Lake

NMK (Refer Drawings Nos. IND50-1-5-9, IND50-1-5-10 and IND50-1-

5-11), using stones (200 - 400 mm size) having uniform

appearances, of thickness 300 mm consisting of natural hard stones

including spreading in 1 layers of 300 mm. Including spreading and

laid on slopes of the bottom drain cell including supply,

440 Cu.m

Works 4: Remediation works of NMK-KIE Page 317

Sr.

No.

Description of Item Qty. Unit

transportation to site of works, loading and unloading of the

materials, all labour and manpower, equipments required for

placing and spreading (boats, pontoons, dozers, loaders backhoe,

tractor trailors, dumpers and poclain, front end loaders) and

machinery, necessary testing as per ISO / ASTM standards, fuel oil,

incidental and other operational charges etc complete as directed

by Engineer in charge and to the satisfaction of engineer in charge.

Stones shall be tested and got approved from the Engineer in-

charge before transportation to the site.

414

Supply, laying, jointing & fixing 110 mm OD HDPE pipe PE 100

grade, pressure class 6 kg/cm2 (as per IS 14333 / 4984) to be laid in

the cover layer of the containment cells along the bund and hillock

and in southeastern corner of NMK as presented on Drawings Nos.

IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11 and in stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3 (at an

interval of 30 m down the slopes in the top vegetative layer all

along the periphery) having interconnections between the top

Berm level storm water drainage to the intermediate berm level

storm water drainage for draining of waters from Top berm to

intermediate berm or serving as direct discgarge pipe to the surface

water including all materials, lowering, laying, welding and jointing,

installation of HDPE pipes, testing for any leakages as per IS codes,

tools and tackles, equipments, fuel, labour and manpower,

transportation to site of works with storage, all incidental expenses

and operational charges etc complete as directed by engineer in

charge and to the satisfaction of engineer in charge

30 m

415

Supply, laying, jointing & fixing 200 mm OD HDPE pipe PE 100

grade, pressure class 6 kg/cm2 (as per IS 14333 / 4984) to be laid in

the containment cells along the bund as presented on Drawings

Nos. IND50-1-5-4, IND50-1-5-5 and IND50-1-5-6 and in stagnant

water pond 2 as presented on Drawing Nos. IND50-1-2-1, IND50-1-

2-2 and IND50-1-2-3 (at an interval of 30 m down the slopes in the

top vegetative layer all along the periphery) having

interconnections between the intermediate Berm level storm water

drainage to the bottom ground level storm water drainage at

stagnant water pond 2 and along western bund of Lake NMK for

draining of waters from intermediate berm to ground level storm

550 m

Works 4: Remediation works of NMK-KIE Page 318

Sr.

No.

Description of Item Qty. Unit

water drainage including all materials, lowering, laying, welding and

jointing, installation of HDPE pipes, testing for any leakages as per

IS codes, tools and tackles, equipments, fuel, labour and

manpower, transportation to site of works with storage, all

incidental expenses and operational charges etc complete as

directed by engineer in charge and to the satisfaction of engineer in

charge.

416

Supply, Installation, Testing and Commissioning of Irrigation System

for proper and efficient maintenance of landscaping on the entire

containment cells (all side slopes and top flat areas and berms)

along the bund and hillock and in southeastern corner of NMK as

presented on Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-

6, IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11 and in stagnant

water pond 2 as presented on Drawing Nos. IND50-1-2-1, IND50-1-

2-2 and IND50-1-2-3, consisting of Sprinklers (Pop Up) and Hydrant

System along with its associated appurtenances and fixtures,

irrigation network of HDPE pipes of amongst others 1050mt length

having 75mm pipe size and 776mt having 110 mm size pipe, PE 100

grade as per IS Codes, pressure class 8 kg/cm2, (header, lateral and

branches along with HDPE fittings and Flush / Air valve

arrangements) having inlet connection from the pumps located at

the STP including all materials, labour, valve box arrangements for

distribution of water for sprinklers, necessary Pretreatment system

of softening / pressure filtration or any other treatment as required

for water to be utilized for irrigation system. The item is all

inclusive of supply, laying of pipes, total installation of sprinklers /

hydrant system in the top vegetative soil layer including water

treatment system with all materials, labour, transportation to the

site, loading and unloading, welding and jointing, equipments and

machinery, tools and plants, fuel, all incidental and operation

charges and expenses etc complete as directed by engineer in

charge and to the satisfaction of engineer in charge.

16125 Sqm

417

Construction of Ground Water Quality Monitoring (Piezometric)

wells – 74 Nos spread over NMK-KIE and the plains (reference is

made to section V were details on the exact position and depth of

the monitoring wells have been presented, consisting of drilling of

borehole of 200 mm diameter upto varying depth in soil as well as

rock strata, Supply and laying of slotted casing pipe of HDPE (6

1880 m

Works 4: Remediation works of NMK-KIE Page 319

Sr.

No.

Description of Item Qty. Unit

kg/cm2 PE 100 grade as per IS 4984/IS 14333) of 75 mm diameter –

3 m length and remaining length of blind pipe on top, filling of the

annulus between the casing and the bore with sand and gravels for

filtration, bentonite sealing on the top along with a top cap with

lock and key arrangements metal label/plate for groundwater well

with number cut into it, glued to the well, anchoring of the pad lock

with RCC concreting works as per drawings, including all materials,

manpower and labour, mechanized drilling equipments, loading,

unloading and transportation to the site of all materials, incidental

and other operational charges etc complete as directed by engineer

in charge and to the satisfaction of engineer in charge. These wells

are constructed to monitor the ground water levels and water

quality checks during after care of the dumpsite post closure

activities.

418

Supply, Installation, Testing and Commissioning (SITC) of Electrical

pumps for pumping of surface waters for irrigation purposes along

with Electrical System installations (cabling, push button stations,

supply and laying of suitable cabling with cable trays, MCC Panel

works (Electrical Panel with Cabling for pumps with control Station

near pumpa installed at the STP and having PDB panel mounted on

wall or floor at the STP facilities) etc) upto the STP or for pumping

of water for irrigation purposes including procurement, supply,

transportation to site of works, installation and erection of works,

testing and successful commissioning of the pumping

arrangements, all works as per standards IS codes and materials of

standard IS makes as directed by Engineer in charge and to the

satisfaction of engineer in charge.

Electrical Water Pumps for Pumping of irrigation waters from Lake

NMK to the Irrigation network of Hydrant and Sprinkler System - 35

cu.m per hr 75 m head.- 1 W + 1 SB

2 Nos

Part 5: Installation of cover layer on lake floor

Sr.

No.

Description of Item Qty. Unit

501 Supply and Laying of of sand brought from outside as a cover layer

on the floor of the lake NMK as presented on Drawing No. IND50-1-

5-3, using sand (0.0 - 2.0 cm size) having rounded grain size

20625 Cu. M

Works 4: Remediation works of NMK-KIE Page 320

Sr.

No.

Description of Item Qty. Unit

materials between 0 - 20 mm, of thickness 300 mm consisting of

natural sand including spreading in 15 layers of 20 mm each. The

spreading has to be controlled distribution of sand with rainbow

technique and laid on flat surfaces and slopes of the lake floor

including supply, transportation to site of works, loading and

unloading of the materials, all labour and manpower, equipments

required for placing and spreading (boats, pontoons, pressure

pipes, underwater pumps, tractor trailors, dumpers, front end

loaders) and machinery, necessary testing as per ISO / ASTM

standards, fuel oil, incidental and other operational charges etc

complete as directed by Engineer in charge and to the satisfaction

of engineer in charge. The sand shall have organic content of < 1%.

Grain size and organic content shall be tested and got approved

from the Engineer in-charge before transportation to the site.

502

Regular Sampling and Monitoring of Ambient Air Quality, Surface

and Ground Water Quality from monitoring wells as per Quality

Monitoring Plan elaborated in the Tender Documents (Reference is

made to General Items and Particular Specifications) during

baseline survey and during construction period – Getting done the

analytical works from an NABL Approved Environmental Testing

Laboratory – Submission of Results to Pollution Control Board on

regular basis as per sampling programme. The following number of

tests have to be performed:

Suite 1: 8 analytical tests

Suite 2: 48 analytical tests

Suite 3: 20 analytical tests

Suite 4: 10 analytical tests

Suite 5: 30 analytical tests

Suite 6: 577 analytical tests

Suite 7: 216 analytical tests

1 Lumpsum

Works 4: Remediation works of NMK-KIE Page 321

Part 6: Infrastructural facilities around the containment cells, including Landscaping and Horticulture and Project round up

Sr.

No.

Description of Item Qty. Unit

A : Horticulture

601 Supplying, Providing, Seeding/Planting and Development of Grass -

Local Grass Lawn at the surface of the containment cells along bunds

and hillock and in south eastern corner of Lake NMK as presented

Drawings Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11 and in stagnant water pond 2 as

presented on Drawing Nos. IND50-1-2-1, IND50-1-2-2 and IND50-1-

2-3 including Bed Preparation for seeding/planting of grass

consisting of dressing the surface of the top vegetative layer,

watering, rolling, providing grass brought from outside,

seeding/planting of grass and ramming, watering with providing

fertilizers (enriching NPK value of soil), compost and also chemicals

for weeds control including the cost of fertilizers, chemicals & grass,

manpower and labour charges, unloading and loading of all

materials, transportation to the site of works etc complete as per

standard specifications for horticulture development as directed by

engineer in charge and to the satisfaction of engineer in charge. The

item also covers regular watering at intervals and removal of weeds,

protection etc for 45 - 60 days for initial establishment till grass is

adequately and sufficiently grown. Maintenance, replacement of

worn out of grass upto two years of defect liability period is in the

scope of the contractor.

16125 sq.m

602 Grass - Local Grass Lawn - Cost of grass 16125 sq.m

603 Grass - Local Grass Lawn - Local grass seeding/planting and ramming 16125 sq.m

604 Grass - Local Grass Lawn - Regular watering and removal of weeds,

protection etc for 45 -60 days for initial establishment 16125 sq.m

Works 4: Remediation works of NMK-KIE Page 322

Section 6 :Drawings

(Pl find attached drawings)

Works 4: Remediation works of NMK-KIE Page 323

Section 7 : Bill of Quantities

Works 4: Remediation works of NMK-KIE Page 324

Part 1: Site Mobilization and installation of bottom structure of Containment cells

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

101

Supply and laying of ordinary earth

brought from outside as a fill layer

underneath the containment cell in

stagnant water pond 2 as presented in

Drawing Nos. IND50-1-2-1 and IND50-1-2-

2

7860 cu.m

102

Excavation, Loading, Unloading,

Transportation, Temporarily Storage and

Backfilling of soil originating from trench

required for installation of gabions at the

southern, western and eastern perimeter

of the containment cell in the south-

eastern corner of Lake NMK as presented

on Drawing Nos. IND50-1-5-9, IND50-1-5-

10 and IND50-1-5-11.

1400 cu.m

103

Supplying, fabricating and placing in

position gabions, consisting of reinforced

steel bars, chain like mesh and coarse

aggregates in containment cells in Lake

NMK as presented on Drawing Nos.

IND50-1-5-4, IND50-1-5-5, IND50-1-5-6,

IND50-1-5-9, IND50-1-5-10 and IND50-1-5-

11.

4050 cu.m

104

Supply, Laying & Jointing of 1.5 mm thick

HDPE Membrane Liner (both side

textured) acting as a main barrier layer for

inflow of surface water into the

containment cell, placed between the

gabion and the clay as presented on

Drawing Nos. IND50-1-5-4, IND50-1-5-5,

IND50-1-5-6, IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11

2755 sq. m

Works 4: Remediation works of NMK-KIE Page 325

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

105

Supply and Laying of clay brought from

outside behind (or in front of) the gabions

of the containment cells in Lake NMK as

presented on Drawing Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11.

4325 cu.m

106

Levelling of containment cell in the south

eastern corner of Lake NMK over an area

of 6,500 sq.m, including Excavation and

Backfilling of soil within the containment

cell in the south-eastern corner of Lake

NMK as presented on Drawing Nos.

IND50-1-5-9, IND50-1-5-10 and IND50-1-5-

11.

1000 cu.m

107a

Supply of sand brought from outside as a

foundation layer, also acting as support

layer for HDPE membrane liner

3105 cu.m

107b

Laying of sand brought from outside as a

foundation layer in containment cell in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2

and IND50-1-2-3, also acting as support

layer for HDPE membrane liner

1380 cu.m

107c

Laying of sand brought from outside as a

foundation layer in the containment cells

along bunds and hillock and in south

eastern corner of Lake NMK as presented

on Drawing Nos. IND50-1-5-4, IND50-1-5-

5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11

1725 cu.m

107d

Supply, laying, jointing & fixing110 mm

dia. HDPE Perforated / Slotted Pipe

warped with Geo Textile - 6 Kg/cm2

pressure as per IS 4984/14333, PE 100

2300 m

Works 4: Remediation works of NMK-KIE Page 326

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

grade in foundation layer of containment

cells along bunds and hillock and in south

eastern corner of Lake NMK as presented

on Drawing Nos. IND50-1-5-4, IND50-1-5-

5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11.

107e

Supply, laying, jointing & fixing110 mm

dia. HDPE Closed Pipe, 6 Kg/cm2 pressure

as per IS 4984/14333, PE 100 grade in

foundation layer of containment cells

along bunds and hillock and in south

eastern corner of Lake NMK as presented

on Drawing Nos. Nos. IND50-1-5-4, IND50-

1-5-5, IND50-1-5-6, IND50-1-5-9, IND50-1-

5-10 and IND50-1-5-11.

160 m

107f

Supply, Laying and Jointing of Non-woven

Needle Punched Geo Textile of 250 GSM

(grams per sq. m) minimum) of U.V.

stabilized polypropylene, polyethylene or

polyester material acting as a protection

layer below part of the HDPE bottom liner

in containment cells along bunds and

hillock and in south eastern corner of Lake

NMK as presented on Drawing Nos.

IND50-1-5-4, IND50-1-5-5, IND50-1-5-6,

IND50-1-5-9, IND50-1-5-10 and IND50-1-5-

11

2190 sq.m

108

Supply, Laying & Jointing of 2.0 mm thick

HDPE Membrane Liner (both side

textured) acting as a main barrier layer (in

the bottom liner) in containment cells

along bunds and hillock and in south

eastern corner of Lake NMK as presented

on Drawings Nos. IND50-1-5-4, IND50-1-5-

5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11 and in stagnant water

14555 sq.m

Works 4: Remediation works of NMK-KIE Page 327

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

pond 2 as presented on Drawing Nos.

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3

109

Supply, laying, jointing & fixing110 mm

dia. HDPE Perforated / Slotted Pipe

warped with Geo Textile - 6 Kg/cm2

pressure as per IS 4984/14333, PE 100

grade in containment cells along bunds

and hillock and in south eastern corner of

Lake NMK as presented on Drawings Nos.

IND50-1-5-4, IND50-1-5-5, IND50-1-5-6,

IND50-1-5-9, IND50-1-5-10 and IND50-1-5-

11 and in stagnant water pond 2 as

presented on Drawing Nos. IND50-1-2-1,

IND50-1-2-2 and IND50-1-2-3.

2650 m

110

Supply, laying, jointing & fixing110 mm

dia. HDPE Closed Pipe, 6 Kg/cm2 pressure

as per IS 4984/14333, PE 100 grade in

containment cells along bunds and hillock

and in south eastern corner of Lake NMK

as presented on Drawings Nos. IND50-1-5-

4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11 and in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2

and IND50-1-2-3.

225 m

111

Supply and laying of activated carbon,

with a minimum Iodine number of 650 and

a maximum Molasses numner (EUR) of

700. 5 kg of active carbon per sq.m has to

applied and mixed with sand of the

drainage layer (item 112b) between 0.25

and 0.35 below the projected top of the

drainage layer. Laying in drainage layer of

containment cells along bunds and hillock

and in south eastern corner of Lake NMK

as presented on Drawings Nos. IND50-1-5-

72775 kg

Works 4: Remediation works of NMK-KIE Page 328

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11 and in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2

and IND50-1-2-3.

112

Supply and Laying of sand brought from

outside as a drainage layer in containment

cells along bunds and hillock and in south

eastern corner of Lake NMK as presented

on Drawings Nos. IND50-1-5-4, IND50-1-5-

5, IND50-1-5-6, IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11 and in stagnant water

pond 2 as presented on Drawing Nos.

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3

5625 cu.m

113

Supply, Laying and Jointing of Non-woven

Needle Punched Geo Textile of 250 (GSM

(grams per sq. m) minimum) of U.V.

stabilized polypropylene, polyethylene or

polyester material acting as a protection

layer below the tubes with sediment in

containment cells along bunds and hillock

and in south eastern corner of Lake NMK

as presented on Drawings Nos. IND50-1-5-

4, IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11

2363 sq.m

114

Collection, crushing, loading,

transportation, unloading and composting

of vegetation from the entire project area

as presented on Drawing No. IND50-1/04.

131436 sq.m

115 Installation and removement of

temporarily work road of 5 m width from

main road to contractors area

450 m

116 Mobilization, demobilization, site

preparations, general works and site

aboundeding, as far as not cover in

1 lumpsum

Works 4: Remediation works of NMK-KIE Page 329

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

contractors regular overhead and

contractors profit provision as included in

the data rates

SUB Total* :

Rupees (in Words) :

*: The above prices are exclusive of VAT, Labour Cess and Project Contingencies (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Works 4: Remediation works of NMK-KIE Page 330

Part 2: Waste handling in KIE and landscaping of open hill lock in KIE

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

201 Inventory of waste present in open hillock

as presented on Drawing No. IND50-1/04 1 lumpsum

202

Excavation andLoading of MSW from the

entire open hillock (1,212 tonnes), the

complete stagnant water ponds 1 and 2 ,

the full extend of the swamps 3 and 4, the

entire length of the drains in KIE and the

complete channel in the plains (a total of

202 tonnes) as presented on Drawing No.

IND50-1/04 onto trucks to off-site MSW

landfill

1414 Tonnes

203

Transportation and unloading of MSW to an

authorized public collection point operated

by GHMC within 5 kilometers distance of

the site

1414 Tonnes

204

Excavation, Loading, Unloading and

transportation of biomedical waste from

open hillock as presented on Drawing No.

IND50-1/04 onto closed trucks to off-site

authorized treatment facility

101 Tonnes

205

Disposal costs of biomedical waste to be

paid to an authorized treatment facility for

biomedical waste

101 Tonnes

206

Excavation, Loading, Unloading and

transportation of hazardous waste and

slacks, ashes and sludges from open hillock

as presented on Drawing No. IND50-1/04

onto closed trucks to off-site TSDF facility

2761 Tonnes

Works 4: Remediation works of NMK-KIE Page 331

207

Disposal costs of hazardous waste and

slacks, ashes and sludges to be paid to an

authorized public TSDF operator

2761 Tonnes

208

Excavation, loading, off loading,

transportation, backfilling and leveling of

soill and soil mixed with rubble as per

Drawings No. IND50-1-6-1, IND50-1-6-2 and

IND50-1-6-3

1250 Cu.m

SUB Total* :

Rupees (in Words) :

*: The above prices are exclusive of VAT, Labour Cess and Project Contingencies (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Part 3: Containment of sediments from Lake NMK and KIE

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount (in

INR)

A : Excavation, transportation and / or intermediate storage of sediment and polluted

topsoil

301

Clean up of all the drains of length

3000meters (approx.) in the entire KIE area

till the extend that all sediments have been

removed through Excavation, Loading,

Unloading and Transportation of poluted

sediments from open drains in KIE as

presented in Drawing No. IND50-1-6-6

300 Cu.m

302 Clean up of swamps 3 and 4 in KIE till the

extend that all polluted topsoil has been

removed as presented on Drawing Nos.

350 Cu.m

Works 4: Remediation works of NMK-KIE Page 332

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount (in

INR)

IND50-1-3-1, IND50-1-3-2, IND50-1-3-3,

IND50-1-4-1, IND50-1-4-2 and IND50-1-4-3

through Excavation, Loading, Unloading and

Transportation of polluted top soil

303

Clean up of swamps 3 and 4 in KIE as

presented on Drawings IND50-1-3-1, IND50-

1-3-2, IND50-1-3-3, IND50-1-4-1, IND50-1-4-

2 and IND50-1-4-3 through Excavation,

Loading, Unloading and Transportation of

poluted sediment

200 Cu.m

304

Clean up of channel in the plains as

presented on Drawing No. IND50-1-7-1

through Excavation, Loading, Unloading and

Transportation of poluted sediment

500 Cu.m

305

Clean up of stagnant water pond 1 in KIE as

presented on Drawing Nos. IND50-1-1-1,

IND50-1-1-2, IND50-1-1-3 through

Excavation, Loading, Unloading and

Transportation of poluted top soil from

stagnant water pond 1 in KIE

216 Cu.m

306

Clean up of stagnant water pond 1 in KIE as

presented on Drawing Nos. IND50-1-1-1,

IND50-1-1-2, IND50-1-1-3 through Dredging

and Transportation of poluted sediment

from stagnant water pond 1 in KIE

1084 Cu.m

307

Clean up of stagnant water pond 2 in KIE as

presented on Drawing Nos. IND50-1-1-1,

IND50-1-1-2, IND50-1-1-3 through

Excavation, Loading, Unloading and

Transportation of poluted top soil from

stagnant water pond 2 in KIE

1720 Cu.m

308 Clean up of stagnant water pond 2 in KIE as

presented on Drawing Nos. IND50-1-1-1,

IND50-1-1-2, IND50-1-1-3 through Dredging

5160 Cu.m

Works 4: Remediation works of NMK-KIE Page 333

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount (in

INR)

and Transportation of poluted sediment

from stagnant water pond 2 in KIE

Ancillary Civil Works

309

Construction of RCC M 20 Check wall cast in

situ , PCC (1:3:6) at base (Refer Drawing Nos

IND 50-1-1-3 and IND50-1-1-4) Further

specifications have been provided on

Drawing No. IND50-1-1-4.

check-

dam 1

7.5 m x 0.3 m x 2.02 m for the wall + 7.5 m x

1.5 m x 0.3 for the foot 8 Cu.m

check-

dam 2

22.5 m x 0.3 m x 2.03 m for the wall + 22.5 m

x 1.5 m x 0.3 for the foot 24 Cu.m

check-

dam 3

17.5 m x 0.3 m x 2.03 m for the wall + 17.5 m

x 1.5 m x 0.3 for the foot 19 Cu.m

check-

dam 4

10.5 m x 0.3 m x 2.04 m for the wall + 10.5 m

x 1.5 m x 0.3 for the foot 12 Cu.m

310

Supply and installation of steel pipe in the

middle section of each wall of the check-

dam as per specification presented on

Drawing No. IND50-1-1-4.

4 Nos.

B : Dredging sediment in LakeNMK

311

To conduct a continuous bathemetric survey

of lake NMK as presented on Drawing No,

IND50-1/03.

68760 sq.m

312

Dredging and transportation of sediments

from Lake NMK as presented on Drawing

Nos. IND50-1-5-1 and IND50-1-5-2

32317 Cu.m

C : Dewatering of Sediment

313 Dewatering of sediments from Lake NMK

within the bottom liner of the in 32317 Cu.m

Works 4: Remediation works of NMK-KIE Page 334

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount (in

INR)

containment cells along bunds and hillock

and in south eastern corner of Lake NMK as

presented on Drawings Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11 and in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and

IND50-1-2-3

314

Dewatering of sediments from stagnant

water ponds 1 and 2, swamps 3 and 4, drains

in KIE and channel downstream within the

bottom liner of the in containment cell in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and

IND50-1-2-3 or in the containment cells

along bunds and hillock and in south eastern

corner of Lake NMK as presented on

Drawings Nos. IND50-1-5-4, IND50-1-5-5,

IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and

IND50-1-5-11

7244 Cu.m

SUB Total* :

Rupees (in Words) :

*: The above prices are exclusive of VAT, Labour Cess and Project Contingencies (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Works 4: Remediation works of NMK-KIE Page 335

Part 4: Installation of cover layer on top of the containment cells.

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

A : Installation of Cover Layers on Containment Cells

401

Laying of ordinary earth brought from inside

as a fill and clay layer on top of the tubes

with sediment in the containment cells along

the bund and hillock and in southeastern

corner of NMK as presented on Drawings

Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6,

IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11

and in stagnant water pond 2 as presented

on Drawing Nos. IND50-1-2-1, IND50-1-2-2

and IND50-1-2-3.

4176 cu.m

402a

Supply and Laying of sand brought from

outside as a foundation layer in the

containment cell in stagnant water pond 2 as

presented on Drawing Nos. IND50-1-2-1,

IND50-1-2-2 and IND50-1-2-3, also acting as

support layer for HDPE membrane liner

525 cu.m

402b

Supply, Laying and Jointing of Non-woven

Needle Punched Geo Textile of (250 GSM

(grams per sq. m) minimum) of U.V.

stabilized polypropylene, polyethylene or

polyester material acting as a protection

layer below part of the HDPE top liner in the

containment cells along the bund and hillock

and in southeastern corner of NMK as

presented on Drawings Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11

11500 sq.m

403 Supply, Laying & Jointing of 2.0 mm thick

HDPE Membrane Liner (both side textured)

in the containment cells along the bund and

14615 sq.m

Works 4: Remediation works of NMK-KIE Page 336

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

hillock and in southeastern corner of NMK as

presented on Drawings Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11 and in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and

IND50-1-2-3

404

Supply, laying, jointing & fixing110 mm dia.

HDPE Perforated / Slotted Pipe wraped with

Geo Textile - 6 Kg/cm2 pressure as per IS

4984/14333, PE 100 grade in the drainage

layer on top of the topliner of the

containment cells along the bund and hillock

and in southeastern corner of NMK as

presented on Drawings Nos. IND50-1-5-4,

IND50-1-5-5, IND50-1-5-6, IND50-1-5-9,

IND50-1-5-10 and IND50-1-5-11 and in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and

IND50-1-2-3

1950 m

405

Supply, laying, jointing & fixing110 mm dia.

HDPE Closed Pipe, 6 Kg/cm2 pressure as per

IS 4984/14333, PE 100 grade in the drainage

layer of the top slopes of the containment

cells along the bund and hillock and in

southeastern corner of NMK as presented on

Drawings Nos. IND50-1-5-4, IND50-1-5-5,

IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and

IND50-1-5-11 and in stagnant water pond 2

as presented on Drawing Nos. IND50-1-2-1,

IND50-1-2-2 and IND50-1-2-3

350 m

406a

Supply and Laying of sand brought from

outside as a drainage layer on top of the

HDPE top liner of the containment cell in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and

925 cu.m

Works 4: Remediation works of NMK-KIE Page 337

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

IND50-1-2-3

406b

Supply, laying and Jointing of Geo Composite

(Drainage Mat) in the containment cells

along the bund and hillock and in

southeastern corner of NMK as presented on

Drawings Nos. IND50-1-5-4, IND50-1-5-5,

IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and

IND50-1-5-11

11500

Sq.m

407

Supply, Laying and Jointing of Non-woven

Needle Punched Geo Textile in the

containment cells in stagnant water pond 2

as presented on Drawing Nos. IND50-1-2-1,

IND50-1-2-2 and IND50-1-2-3

4625 sq.m

408

Supply and Laying of ordinary earth as clean

vegetative soil in the containment cells along

the bund and hillock and in southeastern

corner of NMK as presented on Drawings

Nos. IND50-1-5-4, IND50-1-5-5, IND50-1-5-6,

IND50-1-5-9, IND50-1-5-10 and IND50-1-5-11

and in stagnant water pond 2 as presented

on Drawing Nols. IND50-1-2-1, IND50-1-2-2

and IND50-1-2-3

9450 cu.m

409

Supply, Laying and Jointing of Non-woven

Needle Punched Geo Textile at the

waterfront slope of the containment cell in

stagnant water pond 2 as presented on

Drawings Nos. IND50-1-2-1, IND50-1-2-2 and

IND50-1-2-3

405 Sq. M

410

Supply and Laying of Granite for SS

revetment 225 brought from outside as a

revetment layer on the outer slope of the

containment cell along stagnant water pond

2 as presented on Drawings Nos. IND50-1-2-

1, IND50-1-2-2 and IND50-1-2-3

95 cu.m

Works 4: Remediation works of NMK-KIE Page 338

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

B : Ancillary Civil Works

411

Excavation of Open Storm Water Drains at all

containment cells in Lake NMK and stagnant

water pond 2, through excavation of topsoil

and profilling of open tenches with the

following dimensions: 0.5 m x 0.5 m or 0.3 m

x 0.3 m at the top drain, intermediate drain

of 0.3 m x 0.3 m and bottom drain of 7.0 m x

1.0 m with 1:3 slopes or 6.0 m x 1.0 m with

1:3 slopes at base (Refer Drawings Nos.

IND50-1-5-4, IND50-1-5-5, IND50-1-5-6,

IND50-1-5-9, IND50-1-5-10, IND50-1-5-11,

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3)

A

0.5 m x 0.5 m (or 0.25 m3/m) wide drain at

top most berm (Type 1) of the containment

cell in stagnant water pond 2. Total volume

18 m3.

71 m

B

0.3 m x 0.3 m (or 0.09 m3/m) wide drain at

top berm (Type 2) in containment cells along

the bund and in southeastern part of Lake

NMK. Total volume 61 m3.

675 m

C

0.3 m x 0.3 m (or 0.09 m3/m) wide drain at

intermediate berm (Type 3) of the

containment cell in stagnant water pond 2.

Total volume 18 m3.

200 m

D

6.0 m x 1.0 m (or 3 m3/m) wide drain at

bottom, with slopes 1:3 (Type 3) of the

containment cell in stagnant water pond 2.

Total volume 630 m3.

210 m

E

7.0 m x 1.0 m (or 6.2 m3/m) wide drain at

bottom, with slopes 1:3 (Type 5) along the

southern and eastern perimeter of the

containment cell in the southeastern corner

200 m

Works 4: Remediation works of NMK-KIE Page 339

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

of Lake NMK.. Total volume 1240 m3.

412

Supply, Laying and Jointing of Non-woven

Needle Punched Geo Textile of (250 GSM

(grams per sq. m) minimum) of U.V.

stabilized polypropylene, polyethylene or

polyester material acting as a filter layer

below revetment stones, laid over the slopes

of the bottom drain around the containment

in the southeastern corner of Lake NMK

(Refer Drawings Nos. IND50-1-5-9, IND50-1-

5-10 and IND50-1-5-11)

1470 Sq. M

413

Supply, Laying of Granite for SS revetment

225 brought from outside as a revetment

layer on the slopes and floor of the bottom

dain of the containment cell in the

southeastern corner of Lake NMK (Refer

Drawings Nos. IND50-1-5-9, IND50-1-5-10

and IND50-1-5-11), using stones (200 - 400

mm size) having uniform appearances, of

thickness 300 mm

440 Cu.m

414

Supply, laying, jointing & fixing 110 mm OD

HDPE pipe PE 100 grade, pressure class 6

kg/cm2 (as per IS 14333 / 4984) to be laid in

the cover layer of the containment cells

along the bund and hillock and in

southeastern corner of NMK as presented on

Drawings Nos. IND50-1-5-4, IND50-1-5-5,

IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and

IND50-1-5-11 and in stagnant water pond 2

as presented on Drawing Nos. IND50-1-2-1,

IND50-1-2-2 and IND50-1-2-3

30 m

Works 4: Remediation works of NMK-KIE Page 340

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

415

Supply, laying, jointing & fixing 200 mm OD

HDPE pipe PE 100 grade, pressure class 6

kg/cm2 (as per IS 14333 / 4984) to be laid in

the containment cells along the bund as

presented on Drawings Nos. IND50-1-5-4,

IND50-1-5-5 and IND50-1-5-6 and in stagnant

water pond 2 as presented on Drawing Nos.

IND50-1-2-1, IND50-1-2-2 and IND50-1-2-3

550 m

416

Supply, Installation, Testing and

Commissioning of Irrigation System for

proper and efficient maintenance of

landscaping on the entire containment cells

(all side slopes and top flat areas and berms)

along the bund and hillock and in

southeastern corner of NMK as presented on

Drawings Nos. IND50-1-5-4, IND50-1-5-5,

IND50-1-5-6, IND50-1-5-9, IND50-1-5-10 and

IND50-1-5-11 and in stagnant water pond 2

as presented on Drawing Nos. IND50-1-2-1,

IND50-1-2-2 and IND50-1-2-3

16125 Sqm

417

Construction of Ground Water Quality

Monitoring (Piezometric) wells – 74 Nos

spread over NMK-KIE and the plains

(reference is made to section V)

1880 m

418

Supply, Installation, Testing and

Commissioning (SITC) of Electrical pumps

Electrical Water Pumps for Pumping of

irrigation waters from Lake NMK to the

Irrigation network of Hydrant and Sprinkler

System - 35 cu.m per hr 75 m head.- 1 W + 1

SB

2 Nos

SUB Total :

Works 4: Remediation works of NMK-KIE Page 341

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

Rupees (in Words) :

*: The above prices are exclusive of VAT, Labour Cess and Project Contingencies (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Part 5: Installation of cover layer on lake floor

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

501

Supply and Laying of of sand brought from

outside as a cover layer on the floor of the lake

NMK as presented on Drawing No. IND50-1-5-3

20625 Cu. M

502

Regular Sampling and Monitoring of Ambient Air

Quality, Surface and Ground Water Quality from

monitoring wells as per Quality Monitoring Plan

elaborated in the Tender Documents (Reference

is made to General Items and Particular

Specifications) The following number of tests

have to be performed:

Suite 1: 8 analytical tests

Suite 2: 48 analytical tests

Suite 3: 20 analytical tests

Suite 4: 10 analytical tests

Suite 5: 30 analytical tests

Suite 6: 577 analytical tests

Suite 7: 216 analytical tests

1 Lumpsum

Works 4: Remediation works of NMK-KIE Page 342

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

SUB Total* :

Rupees (in Words) :

*: The above prices are exclusive of VAT, Labour Cess and Project Contingencies (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Part 6: Infrastructural facilities around the containment cells, including Landscaping and Horticulture and Project round up

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount (in

INR)

A : Horticulture

601 Supplying, Providing, Seeding/Planting and

Development of Grass - Local Grass Lawn at

the surface of the containment cells along

bunds and hillock and in south eastern corner

of Lake NMK as presented Drawings Nos.

IND50-1-5-4, IND50-1-5-5, IND50-1-5-6, IND50-

1-5-9, IND50-1-5-10 and IND50-1-5-11 and in

stagnant water pond 2 as presented on

Drawing Nos. IND50-1-2-1, IND50-1-2-2 and

IND50-1-2-3 including Bed Preparation for

seeding/planting of grass consisting of dressing

the surface of the top vegetative layer,

watering, rolling, providing grass brought from

outside, seeding/planting of grass and

ramming, watering with providing fertilizers

(enriching NPK value of soil), compost and also

chemicals for weeds control including the cost

of fertilizers, chemicals & grass, manpower

and labour charges, unloading and loading of

16125 sq.m

Works 4: Remediation works of NMK-KIE Page 343

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount (in

INR)

all materials, transportation to the site of

works etc complete as per standard

specifications for horticulture development as

directed by engineer in charge and to the

satisfaction of engineer in charge. The item

also covers regular watering at intervals and

removal of weeds, protection etc for 45 - 60

days for initial establishment till grass is

adequately and sufficiently grown.

Maintenance, replacement of worn out of

grass upto two years of defect liability period

is in the scope of the contractor.

602 Grass - Local Grass Lawn - Cost of grass 16125 sq.m

603 Grass - Local Grass Lawn - Grass

seeding/planting and ramming 16125 sq.m

604 Grass - Local Grass Lawn - Regular watering

and removal of weeds, protection etc for 45

days for initial establishment

16125 sq.m

SUB Total* :

Rupees (in Words) :

*: The above prices are exclusive of VAT, Labour Cess and Project Contingencies (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Works 4: Remediation works of NMK-KIE Page 344

Part 7 : Cost pertaining to Social Management Plan (From ESMP report) – CSR activities

Sr.

No. Description of Item Qty. Unit

Rate

(in

INR)

Amount

(in INR)

701 Cost for implementation of SMP

Sub total* :

Rupees in words

*: The above prices are exclusive of VAT, Labour Cess and Project Contingencies (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Part 8 : Cost of consumables to maintain Horticulture & landscaping during defect

liability period of 1 year

(after completion of construction works and getting the completion certificate)

Sr.

No.

Description of Item Quantity Unit Item

Rate

per

Unit

Amount

(in INR)

801 Maintenance of Horticulture & landscapping -

Consumables like fertilizers, pesticides, removal and

replacement of grass etc.

1 year Lumpsum

802 Power Charges @ 13 KWh of power consumed per

day

1 year Lumpsum

Sub total*:

Rupees in words

*: The above prices are exclusive of VAT andLabour Cess (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Works 4: Remediation works of NMK-KIE Page 345

Part9: After Care - Operation and Maintenance of containment cells for 5 years after Defect Liability Period – I st Year

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

901 Regular Sampling and Monitoring of Ambient Air

Quality, Surface and Ground Water Quality from

monitoring wells as per Quality Monitoring Plan

elaborated in the Tender Documents – Getting done

the analytical works from an NABL Approved

Environmental Testing Laboratory – Submission of

Results to Pollution Control Board on regular basis as

per sampling programme. The following number of

tests have to be performed:

Suite 1: 4 analytical tests, only in 1st year

Suite 2: 24 analytical tests, only in first year

Suite 3: 30 analytical tests, only in first year

Suite 4: 10 analytical tests, only in first year

Suite 6: 93 analytical tests (every year during 5 year

period)

Suite 7: 12 analytical tests, only in first year

1 Per

Year

902 Operation and Maintenance of Irrigation Pumps and

Irrigation System (Sprinklers, Hydrants, Valves and

Appurtenances)

1 Per

Year

903 Operation and Maintenance of Horticulture &

Landscaping – removal of grass which is decayed and

replacement of new grass, regular watering and cutting

/ trimming of grass at regular intervals, application of

fertilizer / compost for soil enrichment and also

biocides for weeds control.

1 Per

Year

904 General Housekeeping of the entire containment cells

– Total clean-up of the site on regular basis.

1 Per

Year

905 Power Costs – Total units of Power consumed per year

- _________ KW

1 Per

Year

Works 4: Remediation works of NMK-KIE Page 346

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

Total Costs per Year for Operation and Maintenance

including consumables, manpower and power costs*

*: The above prices are exclusive of VAT and Labour Cess (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Note: Details of Consumables used, List of Spares provided, Manpower deployed shall be submitted by the contractor. Rate Analysis of the operation and maintenance costs with respect to each of the item shall also be submitted by the contractor.

Summary of Operation and Maintenance Costs for 5 Years:

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

906 Total Operation and Maintenance Costs for the

containment cells and the surrounding project area for

a period of 5 years after the date of completion of

defect liability period as per specifications and

standards described in the tender documents and

signing of the operation and maintenance contract for

5 years period. The rate shall include all labour,

material, plant and machinery, equipments, tools and

tackles, fuel oil, incidental charges, taxes and duties

and other operation charges in totality complete.

a For Ist Year of Operation and Maintenance (Total as per

Table Part 6 above)

1 Per

Year

b For 2nd Year of Operation and Maintenance 1 Per

Year

c For 3rd Year of Operation and Maintenance 1 Per

Year

d For 4th Year of Operation and Maintenance 1 Per

Works 4: Remediation works of NMK-KIE Page 347

Sr.

No.

Description of Item Qty. Unit Rate

(in

INR)

Amount

(in INR)

Year

e For 5th Year of Operation and Maintenance 1 Per

Year

Total for 5 years of Operation and Maintenance Works

Rupees (in Words) :

Signature with Seal of Contractor Authorized Signatory

Works 4: Remediation works of NMK-KIE Page 348

Total Bid Price for Remediation of Noor Mohhamed Kunta, Kattedan Industrial Area (KIE) in Rangareddy District, Telangana

PROJECT: REMEDIATION OF NOOR MOHAMMED KUNTA, KATTEDAN INDUSTRIAL AREA (KIE)

IN RANGAREDDY DISTRICT, TELANGANA

Sr.

No. Description Amount (in INR)

Basic Costs for Remediation NMK_KIE

1 Part 1 - Site Mobilization and installation of bottom structure

of Containment cells

2 Part 2 - Waste handling in KIE and landscaping of open hill

lock in KIE

3 Part 3 - Containment of sediments from Lake NMK and KIE

4

Part 4 - Installation of Cover Layers on top of the

Containment Cells project round up and provision of

infrastructure facility over and around capped dump site

5 Part 5 - Installation of cover layer on lake floor and

revetment of the bund

6 Part 6 - Landscapping and Horticulture

7 Part 7 - Costs of SMP (From ESMP Report)

8 Part 8 - Power and Consumables during Defect Liability

Period of 1 year to be considered as a part of Contract Cost

A Sub total of 1 to 8

Operation and Maintenance Costs

9 PART 9: After Care - Operation and Maintenance for Ist Year

a After Care - Operation and Maintenance for 2nd Year

b After Care - Operation and Maintenance for 3rd Year

c After Care - Operation and Maintenance for 4th Year

Works 4: Remediation works of NMK-KIE Page 349

d After Care - Operation and Maintenance for 5th Year

B Cost for Operation and Maintenance

C Third Party Insurance during Operation and Maintenance -

1%

D Sub total of part 9

E GRAND TOTAL COST (A+D)

Rupees (in words)

Note: The prices for items mentioned from Sl.No.1 to 7 are inclusive of Vat, Labour Cess and Project Contingencies and for Sl.No.8 & 9, the prices are inclusive of Vat % and Labuor Cess (while filling the BoQ please mention the exact percentage)

Signature with Seal of Contractor Authorized Signatory

Works 4: Remediation works of NMK-KIE Page 350

DAY WORK RATES (TO BE QUOTED BY CONTRACTOR):

Schedule of Day Work Rates - Construction: Labour

Sr. No. Description of Item Unit Item Rate per

Unit

Amount in

Words

1 Ganger (Foreman) Day

2 Labour Day

3 Bar Bender Day

4 Mason Day

5 Carpenter Day

6 Electrician Day

7 Surveyor Day

8 Technician Day

9 Engineer Day

10 Driver for passenger car (up to 5

tonnes)

Day

11 Driver for truck (with or without

trailer)

Day

12 Operator for Excavator Day

13 Operator for tractor and Day

Works 4: Remediation works of NMK-KIE Page 351

bulldozer (tread wheel machines)

14 Operator for dumpers/articulated

truck

Day

15 Operator for Soil Compactor /

Landfill Compactor

Day

16 Operator for Drum soil compactor Day

17 Operator for Loader Backhoe /

Front End Loader

Day

18 Operator for Grader Day

19 Operator for Sweeper Day

Signature and Seal of Contractor Authorized Signatory

Schedule of Day Work Rates - Construction: Materials

Sr.

No.

Description of Item Unit Item Rate

per Unit

Amount in

Words

Source with

lead from site

2 Steel Reinforcement – FE

415 (CRS Steel)

Kg

5 Aggregates – 6 mm Cu.m

6 Aggregates – 10 mm Cu.m

7 Aggregates – 12 mm Cu.m

8 Aggregates – 20 mm Cu.m

9 Aggregates – 25 mm Cu.m

10 Aggregates – 40 mm Cu.m

11 Small Gravel – 4 – 6 mm Cu.m

Works 4: Remediation works of NMK-KIE Page 352

12 Rounded Stones – 80 to 200

mm

Cu.m

13 Fine Sand Cu.m

14 Course Sand Cu.m

16 Sand/gravel for drainage

layer

Cu.m

18 Course Rubble Stone – 30 x

30 x 60 cm

Cu.m

Signature and Seal of Contractor Authorized Signatory

Works 4: Remediation works of NMK-KIE Page 353

Schedule of Day Work Rates - Construction: Equipments

Sr. No. Description of Item Unit Item Rate

per Unit

Amount in Words

1 Passenger car (min 5 persons) Hour

2 Truck (with or without trailer)

with a soil capacity of

Up to and incl. 5 m3 Hour

Over 5 to 10 m3 Hour

Over 10 to 15 m3 Hour

Over 15 m3 Hour

3 Excavator, face shovel

Up to and incl. 1 m3 Hour

Over 1 m3 to 2 m3 Hour

Over 2 m3 Hour

4 Tractor and bulldozer with blade

or showel (tread wheel machines)

Up to and incl. 100 kW Hour

Over 100 kW to 150 kW Hour

Works 4: Remediation works of NMK-KIE Page 354

Schedule of Day Work Rates - Construction: Equipments

Sr. No. Description of Item Unit Item Rate

per Unit

Amount in Words

Over 150 kW to 200 kW Hour

Over 200 kW to 300 kW Hour

5 Tractor and bulldozer with ripper

Up to and incl. 200 kW Hour

Over 200 kW to 250 kW Hour

6 Dumper or articulated truck,

capacity

Upto 12 Tonnes

12 - 20 tonnes Hour

Over 20 tonnes to 30 tonnes Hour

7 Soil compactor, Operating weight Hour

Upto 12 tonnes Hour

Up to 20 tonnes Hour

Over 20 tonnes to 30 tonnes Hour

Drum Vibratory Soil Compactor

(padded or smooth)

Up to 6 tonnes Hour

Over 6 tonnes to 20 tonnes Hour

Works 4: Remediation works of NMK-KIE Page 355

Schedule of Day Work Rates - Construction: Equipments

Sr. No. Description of Item Unit Item Rate

per Unit

Amount in Words

8 Sweeper for road cleaning (min 1

m collection capacity)

Hour

9 Generator (diesel), Power Hour

Up to 2.5 kW (mobile)

Over 10 kW to 15 Kw (mobile)

Over 15 kW to 35 kW (stationary)

10 Compressor, Capacity Hour

Up to 35 l/s, min. 7 bar

Over 35 l/s to 100 l/s, min. 12 bar

11 Water (Drainage) pumps, Power Hour

Up to 3 kW

Over 3 kW to 10 kW

Signature and Seal of Contractor Authorized Signatory

Works 4: Remediation works of NMK-KIE Page 356

Works 4: Remediation works of NMK-KIE Page 357

Section 8 : Forms of Securities

Works 4: Remediation works of NMK-KIE Page 358

Forms of Securities

Acceptable forms of securities are annexed. Bidders should not complete the Performance and Advance

Payment Security forms at this time. Only the successful Bidder will be required to provide Performance and

Advance Payment Securities in accordance with one of the forms, or in a similar form acceptable to the

Employer.

Annex A: Bid Security (Bank Guarantee)

Annex B: Performance Bank Guarantee

Annex B1: Performance Bank Guarantee for Unbalanced Items

Annex C: Deleted

Annex D: Bank Guarantee for Advance Payment

Works 4: Remediation works of NMK-KIE Page 359

Annex A

BID SECURITY (BANK GUARANTEE)

WHEREAS, _______________________ [name of Bidder] (hereinafter called "the Bidder") has submitted

his Bid dated _______________________ [date] for the construction of

_____________________________________ [name of Contract] (hereinafter called "the Bid").

KNOW ALL PEOPLE by these presents that We ______________________________ [name of bank] of

____________________________ [name of country] having our registered office at

___________________________________ (hereinafter called "the Bank") are bound unto

______________________________[name of Employer] (hereinafter called "the Employer") in the sum of

___________________1 for which payment well and truly to be made to the said Employer the Bank binds

itself, his successors and assigns by these presents.

SEALED with the Common Seal of the said Bank this _________ day of __________ 19____.

THE CONDITIONS of this obligation are:

(1) If after Bid opening the Bidder withdraws his bid during the period of Bid validity

specified in the Form of Bid;

or

(2) If the Bidder having been notified of the acceptance of his bid by the Employer during

the period of Bid validity:

(a) fails or refuses to execute the Form of Agreement in accordance with the

Instructions to Bidders, if required; or

(b) fails or refuses to furnish the Performance Security, in accordance with the

Instruction to Bidders; or

Works 4: Remediation works of NMK-KIE Page 360

(c) does not accept the correction of the Bid Price pursuant to Clause 27;

we undertake to pay to the Employer up to the above amount upon receipt of his first written demand,

without the Employer having to substantiate his demand, provided that in his demand the Employer will note

that the amount claimed by him is due to him owing to the occurrence of one or any of the three conditions,

specifying the occurred condition or conditions.

This Guarantee will remain in force up to and including the date ____________________2 days after the

deadline for submission of Bids as such deadline is stated in the Instructions to Bidders or as it may be

extended by the Employer, notice of which extension(s) to the Bank is hereby waived. Any demand in

respect of this guarantee should reach the Bank not later than the above date.

DATE _______________ SIGNATURE OF THE BANK _________________________

WITNESS ____________ SEAL _______________________________________

_________________________________________________________________

[signature, name, and address]

____________________________

1 The Bidder should insert the amount of the guarantee in words and figures denominated in Indian

Rupees. This figure should be the same as shown in Clause 16.1 of the Instructions to Bidders.

2 45 days after the end of the validity period of the Bid.

Works 4: Remediation works of NMK-KIE Page 361

PERFORMANCE BANK GUARANTEE

To: ______________________________________________ [name of Employer]

_________________________________________ [address of Employer]

WHEREAS _________________________ [name and address of Contractor] (hereinafter called

"the Contractor") has undertaken, in pursuance of Contract No. _____ dated ________________ to execute

__________________________ [name of Contract and brief description of Works] (hereinafter called "the

Contract");

AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish

you with a Bank Guarantee by a recognized bank for the sum specified therein as security for compliance

with his obligations in accordance with the Contract;

AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;

NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf

of the Contractor, up to a total of ____________________ [amount of guarantee] 1___________________________ [in words], such sum being payable in the types and proportions of

currencies in which the Contract Price is payable, and we undertake to pay you, upon your first written

demand and without cavil or argument, any sum or sums within the limits of ____________________

[amount of guarantee]1 as aforesaid without your needing to prove or to show grounds or reasons for your

demand for the sum specified therein.

We hereby waive the necessity of your demanding the said debt from the Contractor before

presenting us with the demand.

We further agree that no change or addition to or other modification of the terms of the Contract or

of the Works to be performed thereunder or of any of the Contract documents which may be made between

you and the Contractor shall in any way release us from any liability under this guarantee, and we hereby

waive notice of any such change, addition or modification.

Works 4: Remediation works of NMK-KIE Page 362

This guarantee shall be valid until ……… (i.e.) 28 days from the date of expiry of the Defects

Liability Period.

Signature and seal of the guarantor _____________________________

Name of Bank ____________________________________________

Address ____________________________________________

Date ____________________________________________

__________________

1 An amount shall be inserted by the Guarantor, representing the percentage of the Contract Price

specified in the Contract and denominated in Indian Rupees.

Works 4: Remediation works of NMK-KIE Page 363

PERFORMANCE BANK GUARANTEE (for unbalanced items)

To: ______________________________________________ [name of Employer]

_________________________________________ [address of Employer]

WHEREAS _________________________ [name and address of Contractor] (hereinafter called

"the Contractor") has undertaken, in pursuance of Contract No. _____ dated ________________ to execute

__________________________ [name of Contract and brief description of Works] (hereinafter called "the

Contract");

AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish

you with a Bank Guarantee by a recognized bank for the sum specified therein as security for compliance

with his obligations in accordance with the Contract;

AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;

NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf

of the Contractor, up to a total of ____________________ [amount of guarantee] 1___________________________ [in words], such sum being payable in the types and proportions of

currencies in which the Contract Price is payable, and we undertake to pay you, upon your first written

demand and without cavil or argument, any sum or sums within the limits of ____________________

[amount of guarantee]1 as aforesaid without your needing to prove or to show grounds or reasons for your

demand for the sum specified therein.

We hereby waive the necessity of your demanding the said debt from the Contractor before

presenting us with the demand.

We further agree that no change or addition to or other modification of the terms of the Contract or

of the Works to be performed thereunder or of any of the Contract documents which may be made between

you and the Contractor shall in any way release us from any liability under this guarantee, and we hereby

waive notice of any such change, addition or modification.

Works 4: Remediation works of NMK-KIE Page 364

This guarantee shall be valid until …….. (i.e.) 28 days from the date of issue of the certificate of

completion of works.

Signature and seal of the guarantor _____________________________

Name of Bank ____________________________________________

Address ____________________________________________

Date ____________________________________________

__________________

1 An amount shall be inserted by the Guarantor, representing additional security for unbalanced Bids,

if any and denominated in Indian Rupees.

Works 4: Remediation works of NMK-KIE Page 365

BANK GUARANTEE FOR ADVANCE PAYMENT

To: __________________________________________ [name of Employer]

__________________________________________ [address of Employer]

___________________________________________[name of Contract]

Gentlemen:

In accordance with the provisions of the Conditions of Contract, subclause 51.1 ("Advance

Payment") of the above-mentioned Contract, ________________________________ [name and address of

Contractor] (hereinafter called "the Contractor") shall deposit with ________________________ [name of

Employer] a bank guarantee to guarantee his proper and faithful performance under the said Clause of the

Contract in an amount of _____________ [amount of guarantee] 1_________________________________

[in words].

We, the ____________________ [bank or financial institution], as instructed by the Contractor,

agree unconditionally and irrevocably to guarantee as primary obligator and not as Surety merely, the

payment to ____________________ [name of Employer] on his first demand without whatsoever right of

objection on our part and without his first claim to the Contractor, in the amount not exceeding

____________________ [amount of guarantee]1 __________________________________ [in words].

We further agree that no change or addition to or other modification of the terms of the Contract or

of Works to be performed thereunder or of any of the Contract documents which may be made between

_____________________ [name of Employer] and the Contractor, shall in any way release us from any

liability under this guarantee, and we hereby waive notice of any such change, addition or modification.

This guarantee shall remain valid and in full effect from the date of the advance payment under the

Contract until _________________________ [name of Employer] receives full repayment of the same

amount from the Contractor.

Yours truly,

Works 4: Remediation works of NMK-KIE Page 366

Signature and seal: _______________________________

Name of Bank/Financial Institution: _________________

Address: _______________________________________

Date: ____________________

__________________________

1 An amount shall be inserted by the bank representing the amount of the Advance Payment, and

denominated in Indian Rupees.

Works 4: Remediation works of NMK-KIE Page 367

Section 9 : Environmental and Social Management Plan

Works 4: Remediation works of NMK-KIE Page 368

SUMMARY

The Capacity Building for Industrial Pollution Management Project (CBIPMP) helps the Ministry of

Environment & Forests (MoEF) of the Government of India (GOI) to build capacity at the state and central

level, and develop a framework to address these issues in a comprehensive and systemic manner under an

area-wide management approach. The project is also expected to provide for technical capacity building of

selected State Pollution Control Boards (SPCBs) for undertaking environmentally sound remediation of

polluted sites. Four polluted sites – of which two are in Andhra Pradesh (Noor Mohammed Kunta in

Hyderabad and the Ukkayyapalli Municipal solid waste dumpsite in Kadapa) – have been identified for

remediation on pilot basis.

A consulting consortium was engaged to study and prepare remedial options for Noor Mohammed Kunta

(NMK) and Kathadan Industrial Estate (KIE) area. This includes the polluted Noor Mohammed Kunta lake,

the Kattedan Industrial Estate (KIE, historic source of pollution) and the plains directly downstream of the

lake.

Project objectives

The objectives of the consultancy for the remediation of NMK are:

1. To assess the levels and nature of contaminants in groundwater, surface water and soil for the NMK site 2. To conduct detailed site investigations and assessment studies in order to determine the best remedial

approach 3. To conduct environmental and social impacts of the project and to prepare a management plan

accordingly. 4. To prepare technical and engineering designs for the remediation of the NMK site 5. To support the bid process of the remediation works 6. To supervise the execution of the remediation works 7. To suggest measures to make the lake fit for irrigation purposes and the area of the lake more attractive.

Remediation scenario

The preferred remediation option for the Lake NMK-KIE area has more than one option for each sub

location, (Lake NMK, in KIE open areas, drains and swamps and drains in the plains). The selection

procedure and the predesign of the three best options for Lake NMK and the final selection of the Geo tube

option for Lake NMK and the chosen options for open areas KIE and swamps and drains are described in

the Remediation Plan with reference IND50-1/berr9/099 final version.

Works 4: Remediation works of NMK-KIE Page 369

For the Geo tube Option, tubes of geo-textile are used to dewater the sediment of the Lake after dredging.

Next, the tubes are covered with clean soil and a green cover will be developed. It is assumed that the area

where the tubes will be applied will be sealed with plastic liners or a combination of a drainage layer of

reactive sand and an impermeable clay layer which is naturally present in the area.

In the Off site disposal option for open areas KIE, the waste is completely removed from the open areas at

KIE and is disposed offsite. After the waste is collected it will be transported by trucks to a technical landfill

in Hyderabad. The mixed composition of the waste and recovery of the recyclables by the rag pickers, it is

assumed that there is no potential left for waste processing and recycling. Disposal of waste in a technical

landfill is considered as the only feasible option.

The sediments from swamps and drains in the KIE will be completely remediated by excavation/dredging.

Finally the sediment will be pumped by pipelines into tubes of geo-textile. Those tubes will initially facilitate

the dewatering and stabilization of the sediments. After the sediments have been actively dewatered and

stabilized, the tubes will serve as on-site containment compartments for the sediments. The tubes with

sediments will be covered by a layer of clean soil and a green cover will be developed.

Aforementioned remediation works meet the standards of best environmental practices with regard to

remediation of polluted sites.

Environmental and social reporting project framework

The main precondition of the site remediation is a sound environmental and social management of the

remediation works. This precondition is met through a series of actions as described in The World Bank’s

Environmental and Social (‘safeguard’) Policies. Under Indian law there is no obligation to carry out an

Environmental Impact Assessment (ESIA) for remediation, but the TSPCB strongly supports the World

Bank’s Environmental and Social (‘Safeguard’) Policies to ensure a sustainable project implementation. The

related project environmental and social reporting framework is presented schematically as follow:

Works 4: Remediation works of NMK-KIE Page 370

This report at hand – the Environmental and Social Management Plan (ESMP)12 – presents an overview of

the existing remediation site, it summarises the possible environmental and social impacts due to the

project, and it specifically elaborates the proposed measures to eliminate, mitigate or reduce the foreseen

environmental and social impacts during project execution, and during the post-closure (post-execution)

stage.

The specific objective of this ESMP is to describe the measures that will be implemented to ensure a

situation that is stable and acceptable from an environmental, social, health and safety perspective. This

applies to two phases of project execution:

- The site remediation works (‘project execution’) - The maintenance and aftercare during the first two years of operation (‘post-project execution’)

12 This ESMP is one of the project’s deliverables (as appendix to the Remediation Plan), and sets out to provide a clear and sustainable

management response to the identified environmental and social impacts that are foreseen as a result of the project. This ESMP has been

formulated specifically for the final selected remediation option (for this remedial option, see report IND50-1/berr9/099 –RemediationPlan, final

version).

Works 4: Remediation works of NMK-KIE Page 371

Current Environmental Scenario

Overall the environmental impact of the current pollution present at KIE, NMK and a small stream in the

plains downstream of Lake NMK is demonstrated. This impact is considerable at KIE and NMK itself, but

relatively limited in the surrounding areas. The identified environmental impacts of the pollution in the

current situation are mainly related to groundwater, surface water, sediment and soil contamination (e.g.

mineral oil and metals in higher concentrations), dust, odour and smoke emissions due to presence of open

dump and open burning of wastes. The health aspects associated with the current pollution levels are

mainly due to waste dumping, unregulated waste water discharge which impact the nearby habitation, loss

of flora and fauna, aesthetics etc,.

The presence of polluting industries till the year 2003 in KIE, and the illegal dumping of waste, on-site

burning of waste and the unregulated waste water discharge in this estate are established as main sources

of adverse environmental impacts / pollution.

The main pathways for spread of pollution are waste, smoke, dust, sediments and other sources of

pollution include the wind, rainwater percolating through the dumped wastes, rainwater run-off, and the

drainage lines.

The main receptors of pollution are rag-pickers who come in direct contact with the waste dumped while

seeking recyclables, local residents and labourers of KIE, ecology (flora, wildlife, etc) and the student

research farms of ANGRAU University.

During the execution of the remediation works, the main potential adverse impacts are related to

mobilization of pollution due to improper handling of polluted sediments. In addition air and noise impacts

can be expected due to increased traffic movements and the operation of equipment and vehicles.

Foreseen Environmental Impact and mitigation measures

For the environmental aspects of the project there are no major areas of concern or negative impacts

expected. The situation can only improve. Important pre-condition for this assumption is that the

sediments and waste are excavated, transported and disposed or contained under appropriate operational

management and supervision.

The most effective measure to mitigate the environmental impact of the current pollution is the

remediation of sediments and waste in KIE, NMK and the small stream, which is exactly what this project

aims to achieve. Moreover, the remediation activities provide the basis to convert and upgrade the green

profile of the site.

Sustainable remediation results can only be obtained when illegal dumping of waste and inflow of

substandard sewage water in the lake cease to exist. Other governmental agencies are implementing a

waste management infrastructure in KIE with the aim to stop illegal dumping of waste. It is anticipated that

in a parallel project an appropriate infrastructure for waste water collection and treatment will be realized

and inflow of substandard water flows will cease to exist.

Works 4: Remediation works of NMK-KIE Page 372

The proposed remediation works are reducing the risks that the current pollution pose on the environment

significantly. Soil and groundwater pollution at privately owned plots and in the general topsoil pollution

throughout the entire KIE will remain in place. In the remediation plan an area wide management strategy

is elaborated, which aims at reducing the risks of this remaining pollution on the long run. Although this

remaining pollution will not be addressed under the current project, the implementation of an area wide

monitoring program before, during and after the remediation works will provide valuable information for

future follow up projects.

The adverse impacts during remediation works are of a temporary nature, and can best be mitigated by

proper operational management and supervision, proper maintenance of vehicles and equipment, using

modern equipment and mechanised machinery, and phasing out the implementation plan.

The following environmental objectives – during and after the remediation works – are translated into

concrete measures in this ESMP:

- During project execution:

To ensure that air emissions due to the construction related activities do not lead to increased air pollution at and around the project site, by amongst others controlled spraying of water, use of modern equipment and vehicles, etc.

To ensure that the soil and groundwater are not polluted by leakage of lubricants / fuel from vehicles moving within the site, by amongst others controlled filling and storage of fuels and lubricants, etc.

To ensure that noise generated due to the construction related activities does not lead to increased noise levels at and around the project site, by amongst others controlling operating hours, etc.

To ensure that there is smooth traffic both within and outside the facility for the duration of the construction phase, by amongst others traffic regulation, etc.

To ensure that uncontrolled emissions of mineral oil and heavy metals lead to health risks and unsafe situations for the workers, by amongst others emission monitoring, careful operational planning and supervision etc.

- After project execution:

To reduce surface and groundwater pollution from leachate emanating from the containment structures, by amongst others ensuring adequate drainage and water treatment, and monitoring of water quality, etc.

To control car parking for visitors to the lake and the area, by amongst others creating space for car parking, etc.

To ensure that uncontrolled emissions of topsoil and sediment do not lead to water or air pollution or safety risks, by amongst others emission monitoring and sediment trapping, etc.

(vii) Foreseen social impacts

The study carried out for the Environmental & Social Impact Assessment Report under the current project,

identified 61 rag-picker families (195 individuals) who are directly involved in collection and recycling of

solid waste in KIE. This means that in total 195 individuals depend for at least a certain degree on rag

picking and waste processing in KIE.

Works 4: Remediation works of NMK-KIE Page 373

The project foresees a likely loss of income due to the fact that the potential to recycle waste dumped

within KIE will cease to exist. Measures for mitigating these negative impacts are required, for instance

through targeted livelihood support.

Pollution of air, soil, and water by the contaminated soil and sediment and dumped waste results in health

hazards for the involved families and the residents and labourers of KIE.

The remediation will improve the overall sanitation and health of the nearby habitants. The pollution of

soil, sediment and water will be mimized by the present project. Thus, the situation can only improve.

During the two project public consultations, the affected groups of rag-pickers, KIE resident, KIE labourers

and shop operators have expressed to be very concerned about their current health problems and the

limitations this pose on the use of KIE’s resources.

(viii) Social impact mitigation measures

The following social objectives – during and after the remediation works – are: translated into concrete

measures in this ESMP:

- During project execution:

To ensure that livelihoods of people who are dependent on the processing of waste in KIE are secured, by amongst others involving them in project execution, training on the job (controlled recycling), provision of employment opportunity in the project, etc.

- After project execution:

To ensure that livelihoods of the affected persons are improved, by safeguarding regulated employment (as recyclers, green keepers, area maintainers and gabion draftsmen) and capacity development (training), etc.

All the proposed measures are compliant with International and Indian environmental and social policies.

The contractor undertaking the remediation works is responsible for implementing the EMP, the NGO will

implement the social management plan and the consulting consortium that supervisors the project

execution will also supervise the implemention of ESMP. TSPCB and TSIIC will monitor and ensure

satisfactory implementation of this ESMP.