Date post: | 18-Jan-2016 |
Category: |
Documents |
Upload: | lorraine-mccormick |
View: | 219 times |
Download: | 0 times |
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015
BI.DIS10: Magnets & generators
2
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 3
Contents
- BI.DIS system parameters- System and pulse generator description- Test results- Final design- Planning, Resources, EVM- Conclusions
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 4
BI.DIS system parameters
Parameter Unit ValueDeflection angle at 160 MeV(vertical)
mrad DIS0: 3.77DIS1: 4.23DIS2: 3.84DIS3: 3.4DIS4: 3.97
Kick flat-top duration µs DIS0: 20DIS1: 170DIS2: 320DIS3: 470DIS4: 620
Kick rise time (1-99)% µs ≤ 2
Kick flat-top ripple (p-p) % ≤ ±1
Magnet current A ~ 1000 A
PFN impedance Ω 6.25
PFN voltage kV 6.25
Repetition rate Hz 1.1
5.4632 5.5042 5.5452 5.5862 5.6272 5.678
x 104
-80
-60
-40
-20
0
20
40
60
80
Drift Space [mm]
Am
plitu
de [m
m]
PSB Injection Geometry for DIS Magnets for D = 0
6.024
-4.78
-12.1
-20.2
5.4 5.6 5.8 6 6.2 6.4 6.6
x 104
-300
-200
-100
0
100
200
Drift Space [mm]
Am
plitu
de [m
m]
~150µs
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 5
System and pulse generator description
• 5 magnets in one vacuum tank• 5 Pulse Forming Networks 6.25 Ω (one per magnet) + 1 spare• PFN voltage up to 10 kV ( ~ 7 kV nominal with H- operation)• IGBT switch (2 × 6.5 kV device in series)• fixed duration (different for each PFN, max 620 µs)• short-circuited magnet• recuperation of a large fraction ( > 50 %) of the PFN stored energy (1270 J)
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 6
BI.DIS10 vacuum tank
Tank (with 5 magnets) under vacuum in SAL6 test cage ready for connection to pulse generator.Pressure ok: 2e-9 mbar.TE-VSC will re-test the water circuit before their final acceptance.Spare tank to be tested later.ENG. Spec: EDMS 1454374
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 7
Prototype pulse generator tests results
• Impedance ~6.25 Ω chosen for 2 µs rise time.• 2×6.5 kV IGBTs in series for operation at ~7 kV/1000 A.• Switches: ABB or Hitachi are suitable.• 60 cells for 620 µs pulse (60 capacitors of 1 µF) to fill the
available space and have a minimum flat-top ripple.
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 8
Prototype pulse generator tests results
Magnet current (= Kick)
Voltage to reach 1000 A is 7 kVdue to resistive losses and rising edge shape adjustment (and optimisation) leading to a PFN impedance near 7 Ω.
Rise-time ≤ 2 µs achievedwith more than 500 ns margin.
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 9
Prototype pulse generator tests results
Ripple ≤ ±1 % achievedwith foreseen improvement to ≤ ± 0.5 % in final installation.
Magnet current (= Kick)
Pulse lengths from 170 to 620 µsachieved with 1, 2, 3 and 4 capacitor rows.20 µs still to be done.
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 10
Pulse generators final design
Each cabinet rack contains two separate PFNs of 60 L-C cells maximum
L-C cell
PFN RackSwitch rack
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 11
Pulse generators final design
Each PFN cabinet half is “hermetic” and has an integrated automatic fire detection and CO2injection system.Pressure relief valves have to be installed to limit the CO2 pressure in the rack.
Pressure relief valve Front cell
IGBT Switch
Earthing device
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 12
Pre-series pulse generator
Pre-series status 17 November 2015
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 13
BI.DIS Prototype
Definitive Design Type Test Performance Reliability Operational conditions Safety Preliminary Controls
Functional Spec.
First Prototype
Design Update Test
Improved Design
Review
12/2014
07/2015
R
ea
lisa
tio
n a
nd
De
ve
lop
me
nt
• Proof of Concept
03/2016 Engineering Spec.• Start of Series
Production
• Definitive Design
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 14
Present Status and tests still to be performed
STATUS• PFN mechanical design complete at 95 % (CATIA 3D models and 2D
fabrication drawings). In stand-by due to the illness of P. Faure.• One full pre-series almost ready for test.• Two IGBT types selected among four manufacturers to meet the pulse
required rise time• Tests with full pulse length (620 ms) and nominal required current (1000
A) performed.• Fire extinguisher test performed.• Final three cabinets ready for delivery by the manufacturer.• More than 60 coils ready for the series.
NEXT TEST
Full operational conditions with closed cabinet to see if we have thermal issues. The departure of Rodolphe will slow down the restart.
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 15
BI.DIS Generator Assembly Schedule
Mar Jun Jul Aug Sep Oct Nov Dec 2017
Start Series Production
1st Rack ReadyEnd April
Ready to installEnd December
2 weeks (FSU!)Cabling
1 weekCell Tuning
2 weeksVerification Test
Feb
1st Definitive Generator
2 weeks (2 x FSU!)Rack Assembly
MayApr
9 w
eeks
MarchStart 2nd Rack
June
1 weekDisassembly
Start 3rd RackSeptember
2nd Rack ReadyEnd July
3rd Rack ReadyNovember
Fast Interlock
Trigger System
2nd Rack
Fast Interlock and Timing
Controls Test 3 weeks
3rd Rack
Validation 2 weeks
9 weeks
9 weeks
1 week
1 week
1 week
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 16
Resources for 2016 (FPS only)
1. Material to be ordered and delivered in 2016 (6 PFNs)• Mechanical components: 100 kCHF• Electrical components: 80 kCHF• Miscellaneous: 20 kCHF
Total: 200 kCHF
2. FSU • Coil manufacture : 35 man.week• PFN cabinet assembly: 18 man.week
Total: 53 man.week
3. CERN FTE• Drawings update and orders: 0.3• Assembly: 0.4• Supervision and tests: 1.3
Total: 2 FTE
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 17
EVM: Provide BI.DIS magnets
Year 2008 2009 2010 2011 2012 2013 2014 2015
PV 131 149 77 146 60 0 0 0EV 0 193 3 263 103 0 0 0AC 167 158 38 56 20 0 0 6
Metrics per year in kCHF
Cumulative metrics per year in kCHFYear 2008 2009 2010 2011 2012 2013 2014 2015
PV 131 280 356 502 562 562 562 562EV 0 193 196 459 562 562 562 562AC 167 324 362 418 438 438 438 444
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 18
EVM: Provide BI.DIS pulse generator
Year 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
PV 0 0 63 85 85 165 389 933 347 149 38EV 0 0 0 33 201 170 383 434AC 3 31 60 135 82 166 213 368
Metrics per year in kCHF
Cumulative metrics per year in kCHF
Year 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
PV 0 0 63 148 233 399 788 1721 2068 2217 2255EV 0 0 0 33 234 405 788 1221AC 3 34 94 230 312 478 691 1059
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 19
Conclusion
The new BI.DIS generators are entering their production phase but the full pre-series version still has to be validated.
Test of the full pre-series one will start hopefully this year for completion early next year.
The goal of having the full system ready for installation end of 2016 should be met assuming that the necessary resources will be available at the right moment. The management has to set priorities accordingly.
THANK YOU FOR YOUR ATTENTION!
R. Rosol, L. Sermeus, T. Stadlbauer , TE-ABT LIU review, 20 November 2015 20