23 September 2011 Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima Mulilo and Kopano Quarantine Camp Commissioned by the Millennium Challenge Account Namibia with funding from the Millennium Challenge Corporation Final Design, Environmental Assessment and Supervision of the Construction of Quarantine Camps
Transcript
Page 1: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

23 September 2011

Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima

Mulilo and Kopano Quarantine Camp

Commissioned by the Millennium Challenge Account Namibia with funding from the Millennium Challenge Corporation

Final

Design, Environmental Assessment and Supervision of the Construction of Quarantine Camps

Page 2: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 1

PRELIMINARIES

"NOTE", "The Conditions of Contract for Constructionfor Buildin and Engineering Works Designed by theEmployer as issued by the Federation Internationaledes Ingenieurs-Conseils (FIDIC), 2010 Edition, shall beapplicable contract for the execution of the Works"

1/1/1 The Model Preambles for Trades (2008 edition) aspublished by the Association of South African QuantitySurveyors shall be deemed to be incorporated in these billsof quantities and no claims arising from brevity ofdescription of items fully described in the said ModelPreambles will be entertained

Supplementary preambles are incorporated in these bills ofquantities to satisfy the requirements of this project. Suchsupplementary preambles shall take precedence over theprovisions of the said Model Preambles

The contractor's prices for all items throughout these bills ofquantities must take account of and include for all of theobligations, requirements and specifications given in thesaid Model Preambles and in any supplementary preambles

Item

SECTION A-GENERAL CONDITIONS

1.0 - GENERAL PROVISIONS

1/1/2 Clause 1.1 - Definitions Item

1/1/3 Clause 1.2 - Interpretation Item

1/1/4 Clause 1.3 - Communications Item

1/1/5 Clause 1.4 - Law and Language Item

1/1/6 Clause 1.5 - Priority of Documents Item

1/1/7 Clause 1.6 - Contract Agreement Item

1/1/8 Clause 1.7 - Assigment Item

1/1/9 Clause 1.8 - Care and Supply of Documents Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 -

Page 3: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/10 Clause 1.9 - Delayed Drawings or Insturctions Item

1/1/11 Clause 1.10 - Employer's Use of Contractor's Documents Item

1/1/12 Clause 1.11 - Contractor's Use of Employer's Documents Item

1/1/13 Clause 1.12 - Confidential Details Item

1/1/14 Clause 1.13 - Compliance with Laws Item

1/1/15 Clause 1.13 - Compliance with Laws

[a]Contractor to comply with the Namibia EnvironmentalManagement Act No.7 of year 2007 as well as theEnvironmental Assessment Policy of year 1995 byimplementing the Environmental Management Plans (EMP)documented separately as part of this contract. Item

1/1/16 Clause 1.13 - Compliance with Laws

[b]Contractor to comply with Namibia Public Health andSafety Management Policy under Act no.11 of year 2007 byimplementing the Public Health and Safety Awareness Plan(PHSAP) documented separately as part of this contract. Item

1/1/17 Clause 1.14 - Joint and Several Liability Item

2.0 - THE EMPLOYER

1/1/18 Clause 2.1 - Right of Access to the Site Item

1/1/19 Clause 2.2 - Permits, Licences or Approvals Item

1/1/20 Clause 2.3 - Employer's Personnel Item

1/1/21 Clause 2.4 - Employer's Finanacial Arrangement Item

3.0 - THE EMPLOYER

1/1/22 Clause 3.1 - Engineer's Duties and Authority Item

1/1/23 Clause 3.2 - Delegation by the Engineer Item

1/1/24 Clause 3.3 - Instructions of the Engineer Item

1/1/25 Clause 3.4 - Replacement of the Engineer Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 2 -

Page 4: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/26 Clause 3.5 - Determinations Item

4.0 THE CONTRACTOR

1/1/27 Clause 4.1 - Contractor's General Obligations Item

1/1/28 Clause 4.2 - Performance Security Item

1/1/29 Clause 4.3 - Contractor's Security Item

1/1/30 Clause 4.4 - Subcontractors Item

1/1/31 Clause 4.5 - Assignment of Bennefit of Subcontract Item

1/1/32 Clause 4.6 - Co-operation Item

1/1/33 Clause 4.7 - Setting Out Item

1/1/34 Clause 4.8 - Safety Procedures Item

1/1/35 Clause 4.9 - Quality Assurance Item

1/1/36 Clause 4.10 - Site Data Item

1/1/37 Clause 4.11 - Sufficiency of the Accepted Contract Amount Item

1/1/38 Clause 4.12 - Unforseeable Physical Conditions Item

1/1/39 Clause 4.13 - Rights of Way and Facilities Item

1/1/40 Clause 4.14 - Avoidance of Interference Item

1/1/41 Clause 4.15 - Access Route Item

1/1/42 Clause 4.16 - Transport of Goods Item

1/1/43 Clause 4.17 - Contractor's Equipment Item

1/1/44 Clause 4.18 - Protection of the Environment Item

1/1/45 Clause 4.19 - Electricity, Water and Gas Item

1/1/46 Clause 4.20 - Employer's Equipment and Free-IssueMaterial Item

1/1/47 Clause 4.21 - Progress Reports Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 3 -

Page 5: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/48 Clause 4.22 - Security of the Site Item

1/1/49 Clause 4.23 - Contractor's Operations on Site Item

1/1/50 Clause 4.24 - Fossils Item

5.0 NOMINATED SUBCONTRACTORS

1/1/51 Clause 5.1 - Definition of "nominated Subcontractor" Item

1/1/52 Clause 5.2 - Objection to Nomination Item

1/1/53 Clause 5.3 - Payments to nominated Subcontractors Item

1/1/54 Clause 5.4 - Evidence of Payments Item

6.0 STAFF AND LABOUR

1/1/55 Clause 6.1 - Engagement of Staff and Labour Item

1/1/56 Clause 6.2 - Rates of Wages and Conditions of Labour Item

1/1/57 Clause 6.3 - Persons in the Service of Employer Item

1/1/58 Clause 6.4 - Labour Laws Item

1/1/59 Clause 6.5 - Working Hours Item

1/1/60 Clause 6.6 - Facilities for Staff and Labour Item

1/1/61 Clause 6.7 - Health and Safety Item

1/1/62 Clause 6.8 - Contractor's Superintendence Item

1/1/63 Claause 6.9 - Contractor's Personnel Item

1/1/64 Clause 6.10 - Records of Contractor's Personnel andEquipment Item

1/1/65 Clause 6.11 - Disorderly Conduct Item

7.0 - PLANT, MATERIALS AND WORKMANSHIP

1/1/66 Clause 7.1 - Manner of Execution Item

1/1/67 Clause 7.2 - Samples Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 4 -

Page 6: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/68 Clause 7.3 - Inspection Item

1/1/69 Clause 7.4 - Testing Item

1/1/70 Clause 7.5 - Rejection Item

1/1/71 Clause 7.6 - Remedial Work Item

1/1/72 Clause 7.7 - Ownership of Plant and Material Item

1/1/73 Clause 7.8 - Royalties Item

8.0 - COMMENCEMENT, DELAYS ANDSUSPENSION

1/1/74 Clause 8.1 - Commencement of Work Item

1/1/75 Clause 8.2 - Time of Completion Item

1/1/76 Clause 8.3 - Programme Item

1/1/77 Clause 8.4 - Extension of Time for Completion Item

1/1/78 Clause 8.5 - Delays caused by Authorities Item

1/1/79 Clause 8.6 - Rate of Progress Item

1/1/80 Clause 8.7 - Delay Damages Item

1/1/81 Clause 8.8 - Suspension of Work Item

1/1/82 Clause 8.9 - Consequences of Suspension Item

1/1/83 Clause 8.10 - Payment for Plant and Materials in Event ofSuspension Item

1/1/84 Clause 8.11 - Prolonged Suspension Item

1/1/85 Clause 8.12 - Resuption of Work Item

9.0 - TESTS ON COMPLETION

1/1/86 Clause 9.1 - Contractor's Obligation Item

1/1/87 Clause 9.2 - Delayed Tests Item

1/1/88 Clause 9.3 - Retesting Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 5 -

Page 7: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/89 Clause 9.4 - Failure to Pass Tests on Completion Item

10.0 - EMPLOYER'S TAKING OVER

1/1/90 Clause 10.1 - Taking Over of the Works and Sections Item

1/1/91 Clause 10.2 - Taking Over of Parts of the Works Item

1/1/92 Clause 10.3 - Interference with Tests on Completion Item

1/1/93 Clause 10.4 - Surfaces Requiring Reinstatement Item

11.0 - DEFECTS LIABILITY

1/1/94 Clause 11.1 - Completion of Outstanding Work andRemedying Defects Item

1/1/95 Clause 11.2 - Cost of Remedying Defects Item

1/1/96 Clause 11.3 - Extension of Defects Notification Period Item

1/1/97 Clause 11.4 - Failure to Remedy Defects Item

1/1/98 Clause 11.5 - Removal of Defective Work Item

1/1/99 Clause 11.6 - Futher Tests Item

1/1/100 Clause 11.7 - Right of Access Item

1/1/101 Clause 11.8 - Contractor to Search Item

1/1/102 Clause 11.9 - Performance Certificate Item

1/1/103 Clause 11.10 - Unfulfilled Obligations Item

1/1/104 Clause 11.11 - Clearance of Site Item

12.0 - MEASUREMENT AND EVALUATIONLIABILITY

1/1/105 Clause 12.1 - Works to be Measured Item

1/1/106 Clause 12.2 - Method of Measurement Item

1/1/107 Clause 12.3 - Evaluation Item

1/1/108 Clause 13.4 - Ommisions Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 6 -

Page 8: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

13.0 - VARIATIONS AND ADJUSTMENTS

1/1/109 Clause 13.1 - Right to Vary Item

1/1/110 Clause 13.2 - Value Engineering Item

1/1/111 Clause 13.3 - Variation Procedure Item

1/1/112 Clause 13.4 - Payment in Applicable Currencies Item

1/1/113 Clause 13.5 - Provisional Sums Item

1/1/114 Clause 13.6 - Daywork Item

1/1/115 Clause 13.7 - Adjustments for Changes in Legislation Item

1/1/116 Clause 13.8 - Adjustments for Changes in Cost Item

14.0 - CONTRACT PRICE AND PAYMENTS

1/1/117 Clause 14.1 - The Contract Price Item

1/1/118 Clause 14.2 - Advance Payment Item

1/1/119 Clause 14.3 - Application for Iterim Payment Certificates Item

1/1/120 Clause 14.4 - Schedule of Payments Item

1/1/121 Clause 14.5 - Plant and Materials Intended for the Works Item

1/1/122 Clause 14.6 - Issue of Interim Payment Certificates Item

1/1/123 Clause 14.7 - Payment Item

1/1/124 Clause 14.8 - Delayed Payment Item

1/1/125 Clause 14.9 - Payment of Retention Money Item

1/1/126 Clause 14.10 - Statement at Completion Item

1/1/127 Clause 14.11 - Application for Final Payment Certificate Item

1/1/128 Clause 14.12 - Discharge Item

1/1/129 Clause 14.13 - Issue of Final Payment Certificate Item

1/1/130 Clause 14.14 - Cessation of Employer's Liability Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 7 -

Page 9: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/131 Clause 14.15 - Currencies of Payment Item

15.0 - TERMINATION BY EMPLOYER

1/1/132 Clause 15.1 - Notice to Correct Item

1/1/133 Clause 15.2 - Termination by Employer Item

1/1/134 Clause 15.3 - Valuation at Date of Termination Item

1/1/135 Clause 15.4 - Payment after Termination Item

1/1/136 Clause 15.5 - Employer's Entitlement to Termination Item

16.0 SUSPENSION AND TERMINATION BYCONTRACTOR

1/1/137 Clause 16.1 - Contractor's Entitlement to Suspend Work Item

1/1/138 Clause 16.2 - Termination by Contractor Item

1/1/139 Clause 16.3 - Cessasion of Work and Removal ofContractor's Equipment Item

1/1/140 Clause 16.4 - Payment on Termination Item

17.0 - RISK AND RESPONSIBILITY

1/1/141 Clause 17.1 - Indemnities Item

1/1/142 Clause 17.2 - Contractor's Care of the Work Item

1/1/143 Clasue 17.3 - Employer's Risks Item

1/1/144 Clause 17.4 - Consequences of Employer's Risks Item

1/1/145 Clause 17.5 - Intellectual and Industrial Property Rights Item

1/1/146 Clause 17.6 - Limitation of Liability Item

18.0 - INSURANCE

1/1/147 Clause 18.1 - General Requirements for Insurance Item

1/1/148 Clause 18.2 - Insurance for Works and Contractor'sEquipment Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 8 -

Page 10: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/149 Clause 18.3 - Insurance against Injury to Persons andDamage to Property Item

1/1/150 Clause 18.4 - Insurance for Contractor's Personnel Item

19.0 - FORCE MAJUERE

1/1/151 Clause 19.1 - Definition of Force Majuere Item

1/1/152 Clause 19.2 - Notice of Force Majuere Item

1/1/153 Clause 19.3 - Duty to Minimise Delay Item

1/1/154 Clause 19.4 - Consequences of Force Majuere Item

1/1/155 Clause 19.5 - Force Majuere Affecting Subcontractor Item

1/1/156 Clause 19.6 - Optional Termination, Payment and Release Item

1/1/157 Clause 19.7 - Release from Performance under the Law Item

20.0 - CLAIMS, DISPUTES AND ARBITRATION

1/1/158 Clause 20.1 - Contractor's Claim Item

1/1/159 Clause 20.2 - Appointment of the Dispute AdjudicationBoard Item

1/1/160 Clause 20.3 - Failure to Agree Dispute Adjudication Board Item

1/1/161 Clause 20.4 - Obtaining Dispute Adjudication Board'sDecision Item

1/1/162 Clause 20.5 - Amicable Settlement Item

1/1/163 Clause 20.6 - Arbitration Item

1/1/164 Clause 20.7 - Failure to Comply Dispute Adjudication Board's Decision Item

1/1/165 Clause 20.8 - Expiry of Dispute Adjusication Board'sAppointment Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 9 -

Page 11: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

SECTION B - MODEL PRELIMINARIES

1/1/166 Model Preliminary Document can be purchased from theInstitute of Namibian Quantity Surveyor's offices situated at22 Stein Street, Klein Windhoek, Windhoek during weekdays from 8H00 to 12H00

All references in this document made to "the Architect" willmean Engineer, except wher the professionis meant. Item

B1: Supplementary Documentation

1/1/167 B1.1: Bills of Quantities

These Bills of Quantities contain pages and annexures asindexed on the flyleaf.

These Bills of Quantities are consecutively numbered andthe Tenderer is required to check the number of pages andshould any be found missing or in duplicate or the figuresortyping indistinct or there be any doubt, obscurity or ambiguityas to the meaning or intent of the descriptions, particulars,etc. He must inform the Quantity Surveyor at once in writingand have the same rectified or explained as the case maybe. No claim whatsoever will be afterwards admitted due tothe Contractor having failed to comply with any of the aboveconditions.

No alterations, erasure, omission or addition is to be madein the text and conditions of these Bills of Quantities andshould any such alteration, amendment, note or addition bemade, the same will not be recognised, but the reading ofthese Bills of Quantities, as prepared by the QuantitySurveyor will be adhered to.

The item in these Bills of Quantities are to be read andpriced in conjunction with and the descriptions regarded asampified by the Model Preambles for Trades asrecommended andpublished by the Institute of NamibianQuantity Surveyors, 2008 Edition, and no claim arising frombrevity of description of items fully described in the saidModel Preambles for Trades will be entertained. Item

1/1/168 B1.2: Bills of Quantities Item

1/1/169 B1.3: Availability of Construction Documentation forcontracts based on Provisional Bills of Quantities Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 0 -

Page 12: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/170 B1.4: Name of Architect, Quantity Surveyor and SpecialistConsultants Item

1/1/171 Refer to the Appedix To Tender Item

1/1/172 B1.5: Lodging and Scrutiny of priced Bills of Quantities Item

1/1/173 These Bills of Quantities must be extended in black ink Item

1/1/174 B1.6: Meaning of Words Item

1/1/175 B1.7: Performance Guarantee by Contractor Item

1/1/176 B1.8: Payment Guarantee by Employer Item

1/1/177 B1.9: Waiver of Contractor's Lien Item

1/1/178 B1.10: Signing powers Item

1/1/179 B1.11: Tenders Item

1/1/180 Notwithstanding anything contained in thes clause, tendersshall be valid for a period as stipulated in the separate BidInvitation Documents, from the closing date of tenders. TheEmployer reserves the right to correct any arithmetical orother errors in the extension of the rates and totals in thetender and/or to adjust any rates that are considered by himto be unbalanced and unacceptable. Such adjustments willbe done without affecting the Tender Sum. Item

1/1/181 B1.12: Inspection of Documents Item

B2 The Site

1/1/182 B2.1: Site and Bounderies Item

1/1/183 The sites will be as indicated on the site plans in the BiddingDocuments. Item

1/1/184 B2.2: Area of the Works Item

1/1/185 The Area of the Works to be occupied by the Contractor,any restriction on the area and the limit of access or exit willbe pointed out to the Contractor by the Engineer on handingover of the Site. Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 1 -

Page 13: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/186 B2.3: Boundary Beacons, setting-out pegs and masterdatum Item

1/1/187 The Contractor shall notify the Engineer if anyencroachments of adjoining foundations, buildings,structures, pavements, etc., exist so that the necessaryarrangements can be made for the rectification of any suchencroachments Item

1/1/188 B2.4: Site soil investigation Item

1/1/189 No site soil investigation report is available and the Tendereris advised to inspect the site to as certain the exactnature ofthe ground and report to the Engineer. Item

1/1/190 B2.5: Viewing of the Site Item

1/1/191 No claims for extras arising from the Contractor havingfailed to comply with this Clause will be entertained. Item

1/1/192 B2.6: Existing premises occupied Item

1/1/193 B2.7: Dimensional accurancy of work executed under theprevious contract Item

1/1/194 B2.8: Patent Defects in work executed under the previouscontract Item

1/1/195 B2.9: Existing known services Item

1/1/196 Existing services and points of connection are shown on theSite plan or will be pointed out on the Site by the Engineer. Item

1/1/197 B2.10: Unknown Services Item

1/1/198 B2.11: Protection of trees Item

1/1/199 B2.12: Articles of Value Item

1/1/200 B2.13: Inspection of nearby properties etc. Item

B3 Management of Contract

1/1/201 B3.1: Management of Works Item

1/1/202 B3.2: Programming of The Works Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 2 -

Page 14: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/203 B3.3: Progress Meetings Item

1/1/204 B3.4: Technical Meetings Item

B4: Materials and Workmanship

1/1/205 B4.1: Samples of materials Item

1/1/206 B4.2: Samples of workmanship and mockups Item

1/1/207 B4.3: Ordering of materials Item

B5: Temporary Works and Plant

1/1/208 B5.1: Deposits and Fees Item

1/1/209 B5.2: Enclosure of Works Item

1/1/210 B5.3: Pavement crossings and parking meters Item

1/1/211 B5.4: Advertising Item

1/1/212 B5.5: Plant and Equipment Item

1/1/213 B5.6: Special Scaffolding Item

1/1/214 No special scaffolding is measured as these Bills ofQuantities are based on the Sixth edition of the StandardSystem for Measuring Building Work.

Item

1/1/215 B5.7: Contractor's Offices and Sheds Item

1/1/216 Under NO circumstances may any of the buildings at anystage be used for temporary accommodation for workerscontractor's offices or storage of materials. Item

1/1/217 B5.8: Offices Item

1/1/218 B5.9: Office of the Clerk of Works Item

1/1/219 B5.10: Main Noticeboards (one per site) Item

1/1/220 B5.11: Subcontractor's Noticeboard Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 3 -

Page 15: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

B6: Temporary Services

1/1/221 B6.1: Water The contractor shal provide water for TheWorks in accordance with Alternative A Item

1/1/222 B6.2: Electricity and Lighting The contractor shall provideelectricity and lighting for The Works in accordance withAlternative A Item

1/1/223 B6.3: Telephones The contractor shall provide telephonesfor the Works in accordance with Alternative A Item

1/1/224 B6.4: Toilets The contractor shall provide toilets for TheWorks in accordance with Alternative A Item

B7: Prime Cost and Provisional Amounts

1/1/225 B7.1: Cash Discount All Prime Cost and Provisional Sumsare net and do not include a cash discount, nor will theContractor be allowed or entitled to a cash discount. Item

1/1/226 B7.2: Taking delivery and fixing of prime cost items Item

1/1/227 B7.3: Nominated or Selected Subcontract Documents Item

1/1/228 B7.4: Attendance on Nominated or Selected Subcontractors Item

1/1/229 B7.5: Fuel, power and water for commissioning ofmechanical and other specialised installation Item

B8: Financial Aspects

1/1/230 B8.1: Sales Taxes Delete the whole of this clause andreplace with the following: Item

1/1/231 B8.1: Taxes, etc. Provision is made in the separate BidInvitation Documents for all inclusion of Value Added Tax(VAT) at 15%. The Contractor shall price these Bills ofQuantities excluding Value added Tax (VAT).

Item

1/1/232 B8.2: Contract price adjustment provisions N/A

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 4 -

Page 16: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/233 B8.3: Payment of Preliminaries Payment of Preliminaries willbe calculated from the priced items within the Preliminariesin accordance with Alternative B In addition to theexclusions mentioned in the third paragraph of this clause itshall be deemed that "day works" be added as a fourthexclusion Item

1/1/234 B8.4: Adjustment of Preliminaries The Adjustment ofPreliminaries will be on the basis of fixed price, value relatedand time related items in accordance with Method 3. Inaddition to the exclusions mentioned in this paragraph ofthis clause it shall be deemed that day works be added as afouth exclusion.

Item

1/1/235 B8.5: Certificate payment projection Item

1/1/236 B8.6: Dayworks Item

1/1/237 B8.7: Information supplied by Contractor Item

B9: General

1/1/238 B9.1: Protection Item

1/1/239 B9.2: Protection of existing and/or partially occupied works. Item

1/1/240 B9.3: Safety Item

1/1/241 B9.4: Site security Item

1/1/242 B9.5: Notice before covering work Item

1/1/243 B9.6: Disturbance Item

1/1/244 B9.7: Clearing and cleaning Item

1/1/245 B9.8: Vermin Item

1/1/246 B9.9: Overhand Work Item

1/1/247 B9.10: Jobbing Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 5 -

Page 17: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

SECTION C - SPECIFIC PRELIMINARIES

1/1/248 Site instructions

Instructions issued on site are to be recorded in triplicate ina site instruction book which is to be maintained on site bythe contractor. Item

1/1/249 Warranties for material and workmanship Where warrantiesfor materials and/or workmanship are called for, thecontractor shall obtain a written warranty, addressed to theemployer, from the firm supplying the materials and/or doingthe work and shalldeliver same to the engineer on thecertified completion ofthe contract. The warranty shall statethat workmansip, materials and installation are warranted fora specified period from the date of final completion and thatany defects that may arise during the specified period shallbe made goodat the expense of the firm supplying thematerials and/or doing the work, upon written notice to doso. The warranty will not be enforced if the work is damagedby defects in the construction of the building in which casethe responsibility for replacement shall rest entirely with thecontractor. Item

1/1/250 Co-operation of contractor for cost management It isspecifically agreed that the contractor accepts the obligationof assisting the engineer in implementing proper costmanagement. The contractor will be advised by the engineerof all cost management procedures which will beimplemented tot ensure that the final building cost does notexceed the budget. The engineer undertakes to makeavailable to the contractor all budgetary allowances and costassessments/reports to enable the proper procedure to beimplemented and the contractor shall attend all cost planreview and cost management meetings. The contractorundertakes to extend these procedures, as necessary, to allsubcontractors Item

1/1/251 Testing of windows for watertightness Each window shall betested for watertightness with water sprayed on usingadequate pressure. If in the opinion of the engineer, thepressure proves to be inadequate, then the pressure shallbe boosted by means of compressed air or other approvedmeans. Item

1/1/252 Revenue Stamps The Contractor must allow for and provideall necessary revenue stamps require. Item

Carried Forward N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 6 -

Page 18: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1/1/253 Proprietary Branded Products The Contractor shall takedelivery of, handle, store, use, apply and/or fix all proprietarybranded products in strict accordance with themanufacturers' instructions after consultation with themanufacturer's authorised representative. Item

1/1/254 Non-Cession of Monies The Contractor shall not cede norassign his rights or claims to any monies due or to becomedue under the contract. Item

1/1/255 As Built Drawings The position of construction breaks andthe extent of individual concrete pours are to be recorded bythe Contractor on the Structural Engineer's drawings andare to be submitted to the Architect and the StructuralEngineer for their records. The Contractor shall furnish theArchitect with a set of marked up drawings indicating thepositions of all plumbing and drainage pipework as actuallybuilt.

Item

1/1/256 Social Security Act and will also instruct all his sub- contractors to do the same. Social Security The contractorshall provide for and effect Social Security for all his/heremployees on the works in respect of the Item

1/1/257 Employment of Namibian People The contractor isencouraged to employ Namibia citizens for skilled and semiskilled artisans and employ unskilled labour from the area ofintervention. Item

1/1/258 All Namibian skilled artisans and Namibian unskilledemployees are to be registered according to the SocialSecurity Act of 1994 (Act No. 34 of 1994), and the Tenderermust submit Certificates of Good Standing with the SocialSecurity Commission, which are obtainable from theCommission. Item

Carried to Final Summary N $ Section No. 1PreliminariesBill No. 1Preliminaries

- 1 7 -

Page 19: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 1

ALTERATIONS

For preambles see Model Preambles for Trades

REMOVAL OF EXISTING WORK

Breaking up and removing mass concrete, brick work,etc

2/1/1 Concrete apron m2 19

Breaking up and removing mass concrete, brick work,pipe work, contaminated soil and river boulders,including disposing of contaminated soil

2/1/2 Septic tanks m3 40

Dismantle and remove existing solar geysers, includingsealing of all holes and making safe of electricalconnections

2/1/3 Solar geysers No 8

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 1Alterations

- 1 8 -

Page 20: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 2

EARTHWORKS (PROVISIONAL)

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

SUPPLEMENTARY PREAMBLES

The quantities of excavation, filling, carting away, etcmeasured are the nett volumes and the Contractor is tomake allowances in his prices for the bulking of material.

Descriptions of carting away of excavated material shall bedeemed to include loading excavated material onto trucksdirectly from the excavations or, alternatively, from stockpiles situated on the building site.

The nature of the ground is assumed to be loose sandymaterial, therefore "earth".

SITE CLEARANCE, ETC

Site clearance

2/2/1 Digging up and removing rubbish, debris, vegetation,hedges, shrubs and trees not exceeding 200mm girth, bush,etc. m2 4

EXCAVATION, FILLING, ETC

Excavation in earth not exceeding 2m deep

2/2/2 Surface beds & thickenings m3 35

Extra over trench and hole excavations in earth forexcavation in

2/2/3 Soft rock m3 50

2/2/4 Hard rock m3 150

Carried Forward N $ Section No. 2Building WorksBill No. 2Earthworks (Provisional)

- 1 9 -

Page 21: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Risk of collapse of excavations

2/2/5 Sides of trench and hole excavations not exceeding 1,5mdeep m2 5

Extra over all excavations for carting away

2/2/6 Surplus material from excavations and/or stock piles on siteto a dumping site to be located by the contractor m3 35

Keeping excavations free of water

2/2/7 Allow for keeping all excavations clear of water or mud Item

In-situ material ripped and re-compacted to 95% ModAASHTO density

2/2/8 Under surface beds m3 122

Prescribed density tests on filling

2/2/9 "Modified AASHTO Density" test No 250

SOIL POISONING

"Shell-Drite" or other approved anti-termite soil poisonguaranteed against termite infestation for a period often years

2/2/10 Under floors etc, including forming and poisoning shallowfurrows against foundation walls etc, filling in furrows andramming m2 20

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 2Earthworks (Provisional)

- 2 0 -

Page 22: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 3

CONCRETE, FORMWORK ANDREINFORCEMENT

For preambles see "Model Preambles for Trades"

SUPPLEMENTARY PREAMBLES

Cost of tests

The costs of making, storing and testing of concrete testcubes as required under clause 7 "Tests" of SABS 1200 Gshall include the cost of providing cube moulds necessaryfor the purpose, for testing costs and for submitting reportson the tests to the architect. The testing shall beundertaken by an independent firm or institution nominatedby the contractor to the approval of the architect. (Testcubes are measured separately)

Formwork

Description of formwork shall be deemed to include use andwaste only (except where described as "left in" or"permanent"), for fitting together in the required forms,wedging, plumbing and fixing to true angles and surfaces asnecessary to ensure easy release during stripping and forreconditioning as necessary before re-use

The vertical strutting shall be carried down to suchconstruction as is sufficiently strong to afford the requiredsupport without damage and shall remain in position untilthe newly constructed work is able to support itself.

Formworks to soffits of solid etc shall be deemed to beslabs not exceeding 250mm thick unless otherwisedescribed

Formwork to sides of bases, pile caps, ground beams, etcwill only be measured where it is prescribed by the engineerfor design reasons. Formwork necessitated by irregularityor collapse of excavated faces will not be measured and thecost thereof shall be deemed to be included in the allowancefor taking the risk of collapse of the sides of the excavations,provision for which is made in "Earthworks"

Carried Forward N $ Section No. 2Building WorksBill No. 3Concrete, Formwork & Reinforcement

- 2 1 -

Page 23: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

REINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

25MPa/19mm concrete

2/3/1 Surface beds m3 1

REINFORCED CONCRETE

25MPa/19mm concrete

2/3/2 Concrete slabs m3 6

TEST BLOCKS

2/3/3 Making and testing 150 x 150 x 150mm concrete strengthtest cube (Provisional) No 22

SMOOTH FORMWORK

Smooth formwork to sides

2/3/4 Edges and risers not exceeding 300mm high m 138

Smooth formwork to soffits

2/3/5 Slabs propped up not exceeding 1500mm high abovebearing level cast in panels exceeding 1m2 and notexceeding 2m2 m2 26

Boxing in smooth formwork to form

2/3/6 25mm Chamfers at corners m 59

REINFORCEMENT

Fabric reinforcement

2/3/7 Type 245 fabric reinforcement in concrete surface beds,slabs, etc m2 39

2/3/8 Type 311 fabric reinforcement in concrete surface beds,slabs, etc m2 30

2/3/9 Type 395 fabric reinforcement in concrete surface beds,slabs, etc m2 23

Carried Forward N $ Section No. 2Building WorksBill No. 3Concrete, Formwork & Reinforcement

- 2 2 -

Page 24: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

CONCRETE SUNDRIES

Finishing top surfaces of concrete smooth with a steelfloat

2/3/10 Top of slabs m2 26

2/3/11 Surface beds m2 19

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 3Concrete, Formwork & Reinforcement

- 2 3 -

Page 25: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 4

MASONRY

SUPPLEMENTARY PREAMBLES

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

BRICKWORK

Prices for brickwork shall include for setting up and buildingwindows and door frames into position in brick walls,wedging, pinning, building solid against frames, etc.,bedding of roof coverings, wall plates, base plates, etc.,forming ventilation flues through walls for air bricks, etc.,building ends of rafters, purlins, joists, bars, pipes, bolts, etc.into or through brickwork including wrapping in polyethylenesheeting as necessary.

Sizes in descriptions

Where sizes in descriptions are given in brick units, "onebrick" shall represent the length and "half brick" the width ofa brick.

Hollow walls, etc

Descriptions of hollow walls shall be deemed to includeleaving every fifth perpend of the bottom course of theexternal skin open as a weep hole.

Walls in two skins described as "bagged and sealed" shallbe deemed to include having the outer face of the inner skinbagged with 1:6 cement and sand mixture and sealed withtwo coats "Brixeal" bitumen emulsion waterproofing coating.

Pointing

Descriptions of recessed pointing to fair face brickwork andface brickwork shall be deemed to include square recessed,hollow recessed, weathered pointing, etc.

Carried Forward N $ Section No. 2Building WorksBill No. 4Masonry

- 2 4 -

Page 26: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Decorative blocks

Blocks shall be of approved manufacture, sound, well burntor cured and uniform and true in size, shape and colour.

Samples

Samples of all masonry building units, except those for wallsdescribed as "load bearing", shall consist of a minimum of 6units. Samples of building units to be used in wallsdescribed as "load bearing" shall consist of 30 units fromevery 30 000 units delivered to site.

SUPERSTRUCTURE

Brickwork of concrete bricks in class II mortar

2/4/1 Half brick walls m2 92

Brick reinforcement

2/4/2 75mm Wide reinforcement built in horizontally m 947

BRICKWORK SUNDRIES

Expansion joints

2/4/3 6mm "Jointex" or similar approved bitumen impregnatedfibreboard in expansion joint not exceeding 300mm widebuilt vertically between brick walls m 62

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 4Masonry

- 2 5 -

Page 27: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 5

WATERPROOFING

DAMP-PROOFING OF WALLS AND FLOORS

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

One layer of 375 micron "Consol Plastics Brikgrip DPC"or similar approved embossed damp proof course

2/5/1 In walls m2 5

One layer of 250 micron "Consol Plastics Brikgrip DPC"or similar approved embossed damp proof course

2/5/2 Under surface beds m2 4

JOINT SEALANTS, ETC

Approved silicone sealant, including preparation ofsurfaces, application of primers and protection ofadjacent surfaces

2/5/3 Rake out 6mm thick "Jointex" fibreboard in verticalexpansion joint in brickwork for a depth of 10mm and pointwith approved silicone sealant m 62

2/5/4 8 x 8mm At junction of sanitary fitting, mirror, etc, with tiledwall m 12

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 5Waterproofing

- 2 6 -

Page 28: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 6

CARPENTRY AND JOINERY

Particle board:

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

SUPPLEMENTARY PREAMBLES

Particle board shall comply with the following specifications:

a) SABS 1300 Particle board: exterior and flooring type

b) SABS 1301 Particle board: interior type

Joinery

Descriptions of frames shall be deemed to include frames,transomes, mullions, rails, etc.

Descriptions of hardwood joinery shall be deemed to includepelleting of bolt holes.

Fixing

Items described as "nailed" shall be deemed to be fixed withhardened steel nails or shot pins to brickwork or concrete.

Decorative laminate finish

Laminate finish shall be glued under pressure. Edge stripsshall be butt jointed at junctions with adjacent similar finish.

FLOORS AND SKIRTINGS

Wrot Meranti

2/6/1 19 x 75 mm Rounded skirting plugged to walls including 19mm quadrant bead planted on including mitres, etc. m 244

Carried Forward N $ Section No. 2Building WorksBill No. 6Carpentry & Joinery

- 2 7 -

Page 29: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

DOORS, ETC

Semi-solid flush panel Class 4 medium duty door withhardboard finish both sides and concealed hardwoodedges to sides, hung to steel frames

2/6/2 44mm Double door 1511 x 2 032mm high No 20

JOINERY

Attention is directed to the relevant sections of the ModelPreambles to Trades which must be read in conjunctionherewith.

All hardwoods required for joinery is to be in selected WrotMeranti all housed, framed, grooved, tongued, blocked,dovetailed, notched, glued and screwed together with allscrew heads countersunk and pellated with matching timberplugs including all cutting and waste.

Joinery fittings are measured in number and prices for allfittings are to include for manufacturing and fixing the unitsin position complete with all doors, drawers, etc, withFormica or Melawood finishes and edging or paintedfinishes, including all ironmongery, glazing, etc, as shown onthe joinery fitting drawings attached to the back of these Billsof Quantities

Metal support framing and sanitary fittings to joinery fittings,where applicable, have been separately measured in therelevant bills - Metalwork and Plumbing & Drainagerespectively

Plywood

2/6/3 18mm Thick shelving treated with furniture oil, screwed toshelf brackets (elsewhere measured) m2 15

2/6/4 18mm Thick decking treated with furniture oil, screwed tomild steel stand (elsewhere measured) m2 19

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 6Carpentry & Joinery

- 2 8 -

Page 30: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 7

IRONMONGERY

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

SUPPLEMENTARY PREAMBLES

Finishes to ironmongery

Where applicable finishes to ironmongery are indicated bysuffixes in accordance with the following list: BS Satin bronze lacquered CH Chromium plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodized silver AB Anodized bronze AG Anodized gold ABL Anodized black PB Polished brass PL Polished and lacquered PT Epoxy coated SD Sanded

LOCKS

The following locks are in one set with a master key:

2/7/1 "Solid Art 390/311" chromium plated two lever morticelockset. No 30

The following locks are to be replaced

2/7/2 "Solid Art 390/311" chromium plated two lever morticelockset. No 40

BATHROOM FITTINGS

"Vaal Potteries" or similar approved

2/7/3 '654010V70/94' 150 x 150mm Toilet roll holder plugged No 10

Carried Forward N $ Section No. 2Building WorksBill No. 7Ironmongery

- 2 9 -

Page 31: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

'Craneware'

2/7/4 150 x 150mm White single soap dish fixed to wall No 20

Approved

2/7/5 25mm Diameter CP towel rail 450mm long including CP endbrackets, plugged No 10

SUNDRIES

"Union" or similar approved

2/7/6 AL8730SC Floor mounted door stop, plugged No 60

2/7/7 '8025SS' Hat and coat hook with rubber buffers screwed tosteel door frame No 10

Approved

2/7/8 20mm Diameter pipe hanger for wardrobe, including allfittings m 17

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 7Ironmongery

- 3 0 -

Page 32: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 8

METALWORK

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

SUPPLEMENTARY PREAMBLES

Descriptions

Descriptions of bolts shall be deemed to include nuts andwashers.

Descriptions of expansion anchors and bolts and chemicalanchors and bolts shall be deemed to include nuts, washersand mortices in brickwork or concrete.

Metalwork described as"holed for bolt(s)" shall be deemedto exclude the bolts unless otherwise described.

Unless otherwise described mild steelwork is to include for afactory applied coat of red lead oxide primer aftermanufacture and before leaving the works.

Prices for metalwork are to include for all cutting, fitting,welding, brazing, soldering, drilling, bolting, riveting andforming mitred and welded intersections of metalcomponents as well as for setting up and fixing in position orbuilding into brickwork, or casting into concrete complete.

SUNDRY STEELWORK

Welded mild steel pupose made kitchen sink & counterstand

2/8/1 50 x 50 x 5mm Angle section support frame welded togetherand built into wall as per Architect's specifications m 279

Mild steel shelve supports

2/8/2 50 x 50 x 5mm Angle section shelving support confected toshelves using 4 x self cutting screws recessed into shelvesand bolted to wall using 8mm bolts and including fisherplugs m 72

Carried Forward N $ Section No. 2Building WorksBill No. 8Metalwork

- 3 1 -

Page 33: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

PRESSED STEEL DOOR FRAMES

1,2mm Double rebated frames suitable for half brickwalls with 2 x 100mm standard steel butt hinges perdoor leaf with and including rubber buffers and strikerplate, complete

2/8/3 Frame for double door 1359 x 2 032mm high No 20

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 8Metalwork

- 3 2 -

Page 34: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 9

PLASTERING

For preambles see Model Preambles for Trades

INTERNAL PLASTER

Cement plaster on brickwork

2/9/1 On walls m2 107

2/9/2 On narrow widths m2 12

EXTERNAL PLASTER

Cement plaster on brickwork

2/9/3 On walls m2 80

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 9Plastering

- 3 3 -

Page 35: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 10

TILING

For preambles see Model Preambles for Trades

WALL TILING

200 x 200 x 7mm 'San Lorenzo' or equal approvedceramic tiles fixed with adhesive to plaster (plasterelsewhere) with 'TAL Goldstar' adhesive and flushpointed with 4mm wide tinted waterproof jointingcompound

2/10/1 On walls in isolated panels, splashbacks, etc. (Provisional) m2 23

2/10/2 On walls m2 36

2/10/3 On narrow widths m2 1

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 10Tiling

- 3 4 -

Page 36: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 11

PLUMBING AND DRAINAGE

SUPPLEMENTARY PREAMBLES

PLUMBING AND DRAINAGE (PROVISIONAL)

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

SUPPLEMENTARY PREAMBLES

"Polycop" polypropylene pipes

Polypropylene pipes 54mm diameter and under shall beseamless copper coloured class 16 pipes jointed with"Fast-fuse" heat welded thermoplastic or brass compressionfittings as designed for use with copper pipes as stated.

Pipes shall be firmly fixed to walls etc, with coloured nylonsnap-in pipe clips with provision for accommodating thermalmovement and jointed and fixed strictly in accordance withthe manufacturer's instructions.

All pipe diameters are nominal external.

"Polylink" polypropylene pipes

Polypropylene pipes 63mm diameter and over shall be class12 pipes jointed with cast iron "Supraclamp" running joints.

Fusion welded bends, once or twice mitred as necessary,and tees shall be factory manufactured.

Fusion welded bends and tees shall include jointing to pipeswith PVC rubber ring double Z joint couplers.

Branch tees shall include flanged and bolted joints to"Polycop" branch pipes in addition and for brasscompression male iron to copper straight couplers.

Reducers shall include jointing to pipes with PVC rubber ringdouble Z joint couplers and reducers shall be of sufficientoverall length to accommodate same.

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 3 5 -

Page 37: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

All pipes shall be jointed and fixed strictly in accordance withthe manufacturer's instructions.

All pipe diameters are nominal external.

uPVC pipes and fittings

Soil, waste and vent pipes and fittings shall be solvent weldjointed.

uPVC pressure pipes and fittings

Pipes for water supply shall be of the class stated.

Pipes of 40mm diameter and smaller shall be plain endedwith solvent welded uPVC loose sockets and fittings.

Pipes of 50mm diameter and greater shall have sockets andspigots with push in type integral rubber ring joints. Bendsshall be uPVC and all other fittings shall be cast iron, all withsimilar push-in type joints.

Copper pipes

Pipes shall be hard drawn and half-hard pipes of the classstated. Class 0 (thin walled hard drawn) pipes shall not bebent. Class 1 (thin walled half-hard), class 2 (half-hard) andclass 3 (heavy walled half-hard) pipes shall only be bent withbenders with inner and outer formers. Fittings to copperwaste, vent and anti-syphon pipes, capillary solder fittingsand compression fittings shall be "Cobra Watertech" type.Capillary solder fittings shall comply with ISO 2016. Onlycompression fittings shall be used in walls or in ground.

Fixing of pipes

Unless specifically otherwise stated, descriptions of pipesshall be deemed to include fixing to walls etc, casting in,building in or suspending not exceeding 1m belowsuspension level.

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 3 6 -

Page 38: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Reducing fittings

Where fittings have reducing ends or branches they aredescribed as "reducing". In the case of pipes with diametersnot exceeding 60mm only the largest end or branch size isgiven. Should the contractor wish to use other fittings andbushes or reducers he may do so on the understanding thatno claim in this regard will be entertained. In the case ofpipes with diameters exceeding 60mm all sizes are givenand no claim for extra bushes, reducers, etc, will beentertained.

Exposed concrete surfaces

Exposed surfaces of concrete stormwater channels, coverslabs, inspection eye marker slabs, gulley tops, cleaning eyetops, catchpits, inspection chambers, etc shall be finishedsmooth with plaster.

Excavations

No claim for rock excavation will be entertained unless thecontractor has timeously notified the Engineer thereof priorto backfilling.

"Soft rock" and "hard rock" shall be as defined in"Earthworks".

Laying, backfilling, bedding, etc. of pipes

Pipes shall be laid and bedded and trenches shall becarefully backfilled in accordance with manufacturers'instructions.

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 3 7 -

Page 39: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Where no manufacturers' instructions exist pipes shall belaid in accordance with clauses 5.1 and 5.2 of each of thefollowing:

SABS 1200 L : Medium-pressure pipelinesSABS LD : SewersSABS LE : Stormwater drainage

Pipe trenches etc shall be backfilled in accordance withclauses 3, 5.5, 5.6, 5.7 and 7 of SABS 1200 DB :Earthworks (Pipe trenches).

Pipes shall be bedded in accordance with clauses 3.1 to3.4.1, 5.1 to 5.3 and 7 of SABS 1200 LB : Bedding (Pipes).

Unless otherwise described bedding of rigid pipes shall beclass B bedding.

Flush pans

Flush pans shall have straight or side outlets and "P" or "S"traps as necessary.

Stainless steelbasins, sinks, wash troughs, urinals, etc.

Units shall have standard aprons on all exposed edges andtiling keys against walls where applicable.

Waste unions

Descriptions of waste unions shall be deemed to includerubber or vulcanite plugs and chains fixed to fittings.

"Densyl" petrolatum anti-corrosion tape asmanufactured by Denso SA (Pty) Ltd.

Pipes to be taped shall be coated with the appropriateprimer and the tape shall be applied with minimum 15mmlap per spiral unless otherwise described.

Couplings and fittings to pipes shall be taped in strictaccordance with the manufacturer's instructions including allmastic, tape, "Layflat" sheeting, securing of same, etc.

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 3 8 -

Page 40: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

RAINWATER DISPOSAL

0,8 mm Galvanized sheet iron rainwater goods:

2/11/1 100 x 150 x 100 mm VHV galvanized sheet iron concealedeaves gutter fixed to falls on splay rebated roof trusses. m 220

2/11/2 75 mm Diameter galvanized sheet iron seamless rainwaterdownpipe fixed to walls on alloy brackets at not exceeding1500 mm centres. m 100

Extra over eaves gutter for:

2/11/3 Outlet with 75 mm diameter nozzle and domical galvanizediron grating. No 40

2/11/4 Closed end No 40

Extra over downpipe for:

2/11/5 Shoe No 40

2/11/6 600 mm Projecting eaves offset. No 40

"Fulbore" or other approved outlets

2/11/7 100 mm Diameter vertical outlet type including joint to 75mm diameter mild steel rainwater downpipe (elsewheremeasured) including casting in position into slab. No 40

SANITARY FITTINGS

'Citi Metal Products/Franke' grade 304 (18/10) or equalapproved stainless steel sanitary fittings includingsealing all sanitary fittings against tiled walls withapproved silicone

2/11/8 1500 x 535mm Double centre bowl stainless inset sink,fitted onto mild steel stand (measured elsewhere) No 10

'Cobra" or equal approved sanitary fittings includingsealing all sanitary fittings against tiled walls withapproved silicone

2/11/9 White wash hand basin with tap holes with overflow orchainstay hole bolted to wall with concealed wall brackets No 10

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 3 9 -

Page 41: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

2/11/10 White colour P-trap WC pan with 6 litre cistern andcomplete with flushing mechanism No 12

2/11/11 900 x 900 x 150mm "Granada" shower tray completeshower door and waste outlet, bedded in position No 12

WASTE UNIONS, ETC

Chromium plated

2/11/12 32mm '301' CP Basin waste with backnut and '309' anti-theftplug No 10

2/11/13 40mm '317-40' Sink waste with back nut, CP chain andvulcanite plug No 20

TRAPS, ETC

PVC

2/11/14 Bottle trap No 20

2/11/15 P-trap Shower trap with 'Cobra 323' grating No 12

'Cobra Watertech' or equal approved

2/11/16 32mm '335' CP bottle trap with CP tail pipe including wallflange No 10

TAPS, VALVES, ETC

'Cobra Watertech' or equal approved

2/11/17 15mm '232/350CP' angle regulating valve with 350mm longsupply pipe No 22

2/11/18 15mm 'Star 211' pillar tap No 20

2/11/19 15mm '206 Star' wall mounted CP toilet bibtap No 12

2/11/20 15mm 'ECCP 431' built-in type shower set comprising onepair '128' Star stop taps, 'KP2.6' vandal resistant showerhead with self cleaning nozzle No 12

2/11/21 15mm '500-21' CP wall type elbow action single tap No 20

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 4 0 -

Page 42: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

2/11/22 15mm Diameter 171/041 Star CP wall type sink mixer withoverarm swivel outlet No 10

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 4 1 -

Page 43: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

WATER SUPPLIES

Class 10 HDPe type pipes

2/11/23 25mm Pipes laid in and including trenches not exceeding1m deep m 55

Extra over Class 10 HDPe type IV pipes for "Plasson"fittings

2/11/24 25mm Fittings No 40

2/11/25 25mm Bend No 40

2/11/26 HDPe/Cu adaptor No 10

2/11/27 HDPe/GMS adaptor No 10

GMS pipes

2/11/28 20mm Pipes m 10

Extra over GMS pipes for fittings

2/11/29 20mm Fittings No 20

Sundries

2/11/30 600 x 600mm Brick valve box 600mm deep internallyincluding 100mm thick concrete slab with 300mm high halfbrick walls all round and including Saint-Gobain stop-cockbox product 2670 type I/d, duty class I/D and including balltype valve with M.S support 10mm thick anchored to floorslab No 10

SANITARY PLUMBING

uPVC pipes

2/11/31 110mm Pipes m 60

Extra over uPVC pipes for fittings

2/11/32 110mm Bend No 24

2/11/33 110mm Access bend No 12

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 4 2 -

Page 44: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

2/11/34 110mm Access junction No 24

2/11/35 110mm Access horn No 12

2/11/36 110mm Pan connector No 12

2/11/37 110mm P-trap No 12

2/11/38 110mm 'GI Two-way' vent valve No 12

Sundries

2/11/39 Testing waste pipe system Item

INTERNAL WATER RETICULATION

Class 0 copper pipes

2/11/40 15mm Pipes m 180

2/11/41 22mm Pipes m 147

2/11/42 22mm Pipes chased into brickwork m 15

Extra over class 0 copper pipes for soldered typefittings

2/11/43 15mm Fittings No 206

2/11/44 22mm Fittings No 130

Extra over class 0 copper pipes for compression typefittings

2/11/45 22mm Fittings No 40

Brass

2/11/46 25mm Gate valve No 20

2/11/47 35mm Gate valve No 10

2/11/48 50mm Gate valve No 10

Carried Forward N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 4 3 -

Page 45: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Sundries

2/11/49 Leave or form 300 x 150 x 110mm deep plastered valverecess in half brick wall No 100

2/11/50 Testing water pipe system Item

WATER HEATERS

Wood fired heater as per Henco Engineering or similarapproved (piping measured elsewhere)

2/11/51 150 Litre wood fired water heater No 10

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 11Plumbing & Drainage (Provisional)

- 4 4 -

Page 46: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 12

GLAZING

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

TOPS, SHELVES, DOORS, MIRRORS, ETC

5mm Silvered float glass copper backed mirrors withbevelled edges holed for and fixed with chromiumplated dome capped mirror screws with rubber buffersto plugs in brickwork or concrete

2/12/1 Mirror 300 x 500mm high No 10

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 12Glazing

- 4 5 -

Page 47: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 13

PAINTWORK

NOTES:Attention is directed to the relevant sections of the ModelPreambles to All Trades which forms a part of this Bill andmust be read in conjunction herewith.

PREPARATORY WORK TO EXISTING WORK

Previously painted plastered surfaces

Surfaces shall be thoroughly washed down and allowed todry completely before any paint is applied. Blistered orpeeling paint shall be completely removed and cracks shallbe opened, filled with a suitable filler and finished smooth

Previously painted metal surfaces

Surfaces shall be thoroughly rubbed and cleaned down.Blistered or peeling paint shall be completely removed andsanded down to bare metal

Previously painted wood surfaces

Surfaces shall be thoroughly cleaned down. Blistered orpeeling paint shall be completely removed and sanded downand cracks and crevices shall be primed, filled with suitablefiller and finished smooth

SUPPLEMENTARY PREAMBLES

Paint are to manufactured and supplied by PLASCONPAINTS (PTY) LTD or equal approved and applied in strictaccordance with the manufacturer/supplier's specification.

All work to be executed in strict accordance with thespecifications of Plascon Paints (Pty) Ltd. The coatingsystems are as per Plascon's 'List of Decorative PaintProducts' unless otherwise specified. Full specifications areavailable at Tel. + 27 (0)11 301-4600 or from the variousbranch offices.

Primers and first coats may be thinned in accordance withthe paint specifications of Plascon Paints (Pty) Ltd to aid theabsorption of the paint.

Carried Forward N $ Section No. 2Building WorksBill No. 13Paintwork

- 4 6 -

Page 48: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

All surfaces must be sound, clean and have a moisturecontent of less than 8% for walls generally and 3% forslabs/screeds etc.

Where surfaces of plaster etc are sandy / friable, the firstcoat must be replaced with 'Plascon Merit' plaster primerthinned 10% with turpentine.

PAINTWORK ETC, TO PREVIOUSLY PAINTEDWORK

ON CONCRETE SURFACES

Prepare and clean using sugar soap powder cleanerand apply two coats CAT 60, Bitumen Emulsion(Supplier: Colas, Okahandja)

2/13/1 On apron ground slabs m2 505

ON FLOATED PLASTER

Prepare and stop with 'Polycell Medall 90' and applyone coat 'Plascon Alkaline Plaster Primer (UC56) andapply two coats 'Plascon Wall & All', colour Oatmeal(WAA 8) paint

2/13/2 On external walls m2 1,724

Prepare and stop with 'Polycell Medall 90' and applyone coat 'Plascon Alkaline Plaster Primer (UC56) andapply two coats 'Plascon Super Acrylic', colour BrokenWhite (EPL 314) paint

2/13/3 On internal walls m2 1,542

Prepare and cleaning and apply two coats 'PlasconSure Coat PVA', colour White paint

2/13/4 Internal ceilings m2 666

ON METAL

Carried Forward N $ Section No. 2Building WorksBill No. 13Paintwork

- 4 7 -

Page 49: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Spot priming defects in pre-primed surfaces with'Namelcote Zinc Chromate Metal Primer' (UC53) andapply one coat 'Plascon Merit Universal Undercoat'(UC1) and two coats 'Plascon Super Universal Enamel',colour Light Brown (G370) paint

2/13/5 On door frames m2 159

Spot priming defects in pre-primed surfaces with'Namelcote Zinc Chromate Metal Primer' (UC53) andapply one coat 'Plascon Merit Universal Undercoat'(UC1) and two coats 'Plascon Super Universal Enamel',colour Windsor Green (G33) paint

2/13/6 On external window frames (measured on flat) m2 86

Spot priming defects in pre-primed surfaces with'Namelcote Zinc Chromate Metal Primer' (UC53) andapply one coat 'Plascon Merit Universal Undercoat'(UC1) and two coats 'Plascon Super Universal Enamel',colour Broken Ivory paint

2/13/7 On internal window frames (measured on flat) m2 86

ON WOOD

Spot priming defects in pre-primed surfaces withapproved 'Wood Primer' and two coats 'Plascon SuperUniversal Enamel', colour Light Brown (G370) paint

2/13/8 On doors m2 209

Prepare and apply one coat 'Plascon Woodcare SandingSealer' smoothed of using steel wool after drying andtwo coats 'Plascon Woodcare Polywax Exterior Sealer'

2/13/9 On doors m2 66

2/13/10 On plywood shelving and decking (both side measured) m2 68

2/13/11 On skirtings not exceeding 300mm girth m 610

ON FIBRE CEMENT

Carried Forward N $ Section No. 2Building WorksBill No. 13Paintwork

- 4 8 -

Page 50: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Spot priming defects in pre-primed surfaces withapproved 'Wood Primer' and two coats 'Plascon SuperUniversal Enamel', colour Windsor Green (G33) paint

2/13/12 On fascias m2 106

Carried Forward N $ Section No. 2Building WorksBill No. 13Paintwork

- 4 9 -

Page 51: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

PAINTWORK ETC, TO NEW WORK

ON FLOATED PLASTER

Prepare surfaces and remove all loose material, applyone coat 'Plascon Alkaline Plaster Primer (UC56) andapply two coats 'Plascon Wall & All', colour Oatmeal(WAA 8) paint

2/13/13 On external walls m2 80

Prepare surfaces and remove all loose material, applyone coat 'Plascon Alkaline Plaster Primer (UC56) andapply two coats 'Plascon Super Acrylic', colour BrokenWhite (EPL 314) paint

2/13/14 On internal walls m2 120

ON METAL

Apply 'Namelcote Zinc Chromate Metal Primer' (UC53)and apply one coat 'Plascon Merit Universal Undercoat'(UC1) and two coats 'Plascon Super Universal Enamel',colour Battleship Grey (G13) paint

2/13/15 On mild steel frame m2 56

ON WOOD

Spot priming defects in pre-primed surfaces withapproved 'Wood Primer' and two coats 'Plascon SuperUniversal Enamel', colour Light Brown (G370) paint

2/13/16 On doors m2 40

SUNDRIES

ON FLOORS

Prepare and clean floors using sugar soap powdercleaner

2/13/17 On internal floors m2 640

Carried Forward to Summary of Section No. 2 N $ Section No. 2Building WorksBill No. 13Paintwork

- 5 0 -

Page 52: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Section No. 2

Building Works

SECTION SUMMARY - Building Works

Bill Page AmountNo No

1 -18-Alterations

2 -20-Earthworks (Provisional)

3 -23-Concrete, Formwork & Reinforcement

4 -25-Masonry

5 -26-Waterproofing

6 -28-Carpentry & Joinery

7 -30-Ironmongery

8 -32-Metalwork

9 -33-Plastering

10 -34-Tiling

11 -44-Plumbing & Drainage (Provisional)

12 -45-Glazing

13 -50-Paintwork

Carried to Final Summary N $ Section No. 2Building Works

- 5 1 -

Page 53: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO. 1

EXTERNAL WORKS

SEPTIC TANK - TYPE 1

Excavation in earth for septic tank

3/1/1 Not exceeding 2m deep m3 82

3/1/2 Exceeding 2m and not exceeding 4m deep m3 24

Extra over excavation in earth for excavation in

3/1/3 Soft rock m3 10

3/1/4 Hard rock m3 6

Extra over all excavations for carting away

3/1/5 Surplus material from excavations and/or stock piles on siteto a dumping site to be located by the Contractor m3 70

Risk of collapse of excavations

3/1/6 Sides of trench and hole excavations exceeding 1,5m andnot exceeding 3m deep m2 112

Selected earth filling obtained from the excavationsand/or prescribed stock piles on site compacted to 98%Mod AASHTO density

3/1/7 Backfilling to trenches, holes, etc m3 36

Compaction of surfaces

3/1/8 Compaction of ground surface under floors etc includingscarifying for a depth of 150mm, breaking down oversizematerial, adding suitable material where necessary andcompacting to 98% Mod AASHTO density m2 38

10MPa/19mm Unreinforced concrete

3/1/9 Surface blinding under surface beds m3 2

10MPa/19mm Reinforced concrete

3/1/10 In filling in hollow walls m3 12

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 5 2 -

Page 54: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

30MPa/19mm Reinforced concrete

3/1/11 Surface beds cast in panels on waterproofing m3 8

3/1/12 Slabs m3 6

Finishing top surfaces of concrete smooth with a woodfloat

3/1/13 Surface beds m2 38

3/1/14 Slabs m2 26

Smooth formwork to sides

3/1/15 Edges and risers not exceeding 300mm high m 28

Rough formwork to soffits

3/1/16 Slabs including removing shuttering through 600 x 600mmwide opening m2 16

High tensile steel reinforcement to structural concretework

3/1/17 10mm Diameter bars t 0.18

3/1/18 12mmDiameter bars t 0.16

Fabric reinforcement

3/1/19 Type 195 fabric reinforcement in concrete surface beds,slabs, etc m2 76

3/1/20 Type 395 vertically between brick skins in hollow walls m2 116

Brickwork of 7MPa concrete bricks in class II mortar

3/1/21 One brick walls m2 12

3/1/22 440mm Hollow wall in two half brick skin including wire ties m2 60

Bricks reinforcement

3/1/23 75mm Wide reinforcement built in horizontally m 298

3/1/24 150mm Wide reinforcement built in horizontally m 30

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 5 3 -

Page 55: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Waterproofing

3/1/25 Waterproofing (DPC) between concrete slab and brickwork m2 12

Screeds to falls on concrete

3/1/26 40mm Thick on surface bed m2 14

Bagging and including two coats of Flintcoat

3/1/27 On external walls m2 68

Steel troweled waterproof cement plaster

3/1/28 On walls m2 72

3/1/29 On walls in narrow widths m2 2

uPVC pipes

3/1/30 110mm Pipes laid in and including trenches not exceeding1m deep m 16

Extra over uPVC pipes for fittings

3/1/31 110mm Bend No 8

3/1/32 110mm Junction No 8

3/1/33 110mm Vent valve No 8

Gratings, covers, etc

3/1/34 600 x 600mm Type 8B double seal cast iron manhole coverand frame bedded in concrete No 4

FRENCH DRAIN

Excavation in earth for septic tank

3/1/35 Not exceeding 2m deep m3 30

Extra over excavation in earth for excavation in

3/1/36 Soft rock m3 4

3/1/37 Hard rock m3 2

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 5 4 -

Page 56: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Extra over all excavations for carting away

3/1/38 Surplus material from excavations and/or stock piles on siteto a dumping site to be located by the Contractor m3 30

Risk of collapse of excavations

3/1/39 Sides of trench and hole excavations exceeding 1,5m andnot exceeding 3m deep m2 82

Clean granular filling material of 20 to 100mm suppliedby the Contractor

3/1/40 Filling to trench m3 16

Coarse river sand filling supplied by the Contractor

3/1/41 Filling to trench m3 14

'Bidim' or similar approved material

3/1/42 U14 Filter fabric to sides,top and bottom of trench m2 76

0,5mm Thick previously used galvanised corrugatediron

3/1/43 French drain trench covering m2 40

Mass concrete

3/1/44 Around inspection pipe m3 0.2

Perforated uPVC pipes laid in open trench

3/1/45 110mm uPVC pipes m 28

3/1/46 110mm x 45 Degree access junction No 8

3/1/47 110mm End cap No 2

MULTI PURPOSE HOLDING PENS AND CRUSHPENS

Excavation in compacted fill not exceeding 2m deep

3/1/48 Bases m3 24

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 5 5 -

Page 57: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Risk of collapse of excavations

3/1/49 Sides of trench and hole excavations not exceeding 1,5mdeep m2 322

Extra over all excavations for carting away

3/1/50 Surplus material from excavations and/or stock piles on siteto a dumping site to be located by the contractor m3 24

Keeping excavations free of water

3/1/51 Keeping excavations free of all water other thansubterranean water Item

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 5 6 -

Page 58: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

UNREINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

25MPa/19mm concrete

3/1/52 Foundations m3 24

Cast in items

3/1/53 Steel uprights No 336

STRUCTURAL STEEL, ETC

Welded and bolted multi-purpose holding pens andcrush pens structure of round, steel tube, posts, angles,channel and round bar, including braces, cleats, gusset,base plates and connection plates bolted to steel orconcrete all as per attached drawings

3/1/54 Structure of hollow steel tubes 48mm diameter with 3mmwall thickness t 7.00

3/1/55 Structure of hollow steel tubes 102mm diameter with 3mmwall thickness t 5.92

3/1/56 Structure of 10 and 12mm round bars t 0.32

GATES

Gates of 48mm diameter hot rolled round steel tube asper dwg no. HR11/15/2

3/1/57 Gate 2500mm x 1340mm high (A) No 8.00

3/1/58 Gate 2000mm x 1340mm high (B) No 40

3/1/59 Gate 900mm x 1340mm high (C) No 2

SUNDRIES

3/1/60 Neck clamps complete as per specification No 4

3/1/61 12mm Chains m 30.00

3/1/62 Steel caps welded on top of 102mm steel posts No 304.00

PAINTWORK ETC, TO NEW WORK

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 5 7 -

Page 59: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

ON METAL

Prepare remove all rust and mill scale and weldingspots and spot prime defects with one coat 'NamelcoatZinc Chromate Metal Primer (UC53)', one coat 'MeritUniversal Undercoat (UC1)' and two coats 'PlasconSuper Universal Enamel (NY1/G)' paint

3/1/63 On rails, bars, cornices, etc. m 3,364

3/1/64 Gates measured on flat m2 272

ADJUSTABLE LOADING RAMP

Excavation in compacted fill not exceeding 2m deep

3/1/65 Bases m3 2

Risk of collapse of excavations

3/1/66 Sides of trench and hole excavations not exceeding 1,5mdeep m2 4

Extra over all excavations for carting away

3/1/67 Surplus material from excavations and/or stock piles on siteto a dumping site to be located by the contractor m3 2

Keeping excavations free of water

3/1/68 Keeping excavations free of all water other thansubterranean water Item

UNREINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

25MPa/19mm concrete

3/1/69 Foundations m3 2

STRUCTURAL STEEL, ETC

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 5 8 -

Page 60: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Welded and bolted adjustable loading ramp of round,steel tube, posts, angles, channel and round bar,including braces, cleats, gusset, base plates andconnection plates bolted to steel or concrete

3/1/70 Structure of hollow steel tubes 48mm diameter 3mm wallthickness t 0.72

3/1/71 Structure of hollow steel tubes 60mm diameter 3mm wallthickness t 0.06

3/1/72 Structure of hollow steel tubes 102mm diameter 3mm wallthickness t 0.74

3/1/73 Structure taper flanged channels 100 x 50mm 10.6kg/m t 0.46

3/1/74 Structure of angles 40 x 40 x 5mm t 0.14

3/1/75 Structure of round bars 10 and 12mm diameter t 0.24

GATES

Gates of 48mm diameter hot rolled round steel tube asper dwg no. HR11/15/3

3/1/76 Gates 450mm x 1600mm high No 8.00

SUNDRIES

3/1/77 3mm mild steel plates m2 18

3/1/78 12mm Chains m 6.00

3/1/79 Steel caps welded on top of 102mm steel posts No 32.00

PAINTWORK ETC, TO NEW WORK

ON METAL

Prepare remove all rust and mill scale and weldingspots and spot prime defects with one coat 'NamelcoatZinc Chromate Metal Primer (UC53)', one coat 'MeritUniversal Undercoat (UC1)' and two coats 'PlasconSuper Universal Enamel (NY1/G)' paint

3/1/80 On rails, bars, cornices, etc. m 606

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 5 9 -

Page 61: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

3/1/81 Gates measured on flat m2 2

3/1/82 Steel plates m2 36

PLUMBING AND DRAINAGE

For preambles see Model Preambles for Trades

SUPPLEMENTARY PREAMBLES

'Polycop' polypropylene pipes:

Polypropylene pipes 54mm diameter and under shall beseamless copper coloured class 16 pipes jointed with"Fast-fuse" heat welded thermoplastic or brass compressionfittings as designed for use with copper pipes as stated

Pipes shall be firmly fixed to walls etc with coloured nylonsnap-in pipe clips with provision for accommodating thermalmovement and jointed and fixed strictly in accordance withthe manufacturer's instructions

All pipe diameters are nominal external

'Polylink' polypropylene pipes:

Polypropylene pipes 63mm diameter and over shall be class12 pipes jointed with cast iron "Supraclamp" running joints

Fusion welded bends, once or twice mitred as necessary,and tees shall be factory manufactured

Fusion welded bends and tees shall include jointing to pipeswith PVC rubber ring double Z joint couplers

Branch tees shall include flanged and bolted joints to"Polycop" branch pipes in addition and for brasscompression male iron to copper straight couplers

Reducers shall include jointing to pipes with PVC rubber ringdouble Z joint couplers and reducers shall be of sufficientoverall length to accommodate same

All pipes shall be jointed and fixed strictly in accordance withthe manufacturer's instructions

All pipe diameters are nominal external

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 6 0 -

Page 62: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

uPVC pipes and fittings:

Soil, waste and vent pipes and fittings shall be solvent weldjointed

uPVC pressure pipes and fittings:

Pipes for water supply shall be of the class stated

Pipes of 40mm diameter and smaller shall be plain endedwith solvent welded uPVC loose sockets and fittings

Pipes of 50mm diameter and greater shall have sockets andspigots with push in type integral rubber ring joints. Bendsshall be uPVC and all other fittings shall be cast iron, all withsimilar push-in type joints

Copper pipes:

Pipes shall be hard drawn and half-hard pipes of the classstated. Class 0 (thin walled hard drawn) pipes shall not bebent. Class 1 (thin walled half-hard), class 2 (half-hard) andclass 3 (heavy walled half-hard) pipes shall only be bent withbenders with inner and outer formers. Fittings to copperwaste, vent and anti-syphon pipes, capillary solder fittingsand compression fittings shall be "Cobra Watertech" type.Capillary solder fittings shall comply with ISO 2016. Onlycompression fittings shall be used in walls or in ground

Fixing of pipes:

Unless specifically otherwise stated, descriptions of pipesshall be deemed to include fixing to walls etc, casting in,building in or suspending not exceeding 1m belowsuspension level

Reducing fittings:

Where fittings have reducing ends or branches they aredescribed as "reducing". In the case of pipes with diametersnot exceeding 60mm only the largest end or branch size isgiven. Should the contractor wish to use other fittings andbushes or reducers he may do so on the understanding thatno claim in this regard will be entertained. In the case ofpipes with diameters exceeding 60mm all sizes are givenand no claim for extra bushes, reducers, etc will beentertained

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 6 1 -

Page 63: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Exposed concrete surfaces:

Exposed surfaces of concrete stormwater channels, coverslabs, inspection eye marker slabs, gulley tops, cleaning eyetops, catchpits, inspection chambers, etc shall be finishedsmooth with plaster

Excavations:

No claim for rock excavation will be entertained unless thecontractor has timeously notified the Engineer thereof priorto backfilling

"Soft rock" and "hard rock" shall be as defined in"Earthworks"

Laying, backfilling, bedding, etc. of pipes:

Pipes shall be laid and bedded and trenches shall becarefully backfilled in accordance with manufacturers'instructions

Where no manufacturers' instructions exist pipes shall belaid in accordance with clauses 5.1 and 5.2 of each of thefollowing:

SABS 1200 L : Medium-pressure pipelinesLD : SewersLE : Stormwater drainage

Pipe trenches etc shall be backfilled in accordance withclauses 3, 5.5, 5.6, 5.7 and 7 of SABS 1200 DB :Earthworks (Pipe trenches)

Pipes shall be bedded in accordance with clauses 3.1 to3.4.1, 5.1 to 5.3 and 7 of SABS 1200 LB : Bedding (Pipes).

Unless otherwise described bedding of rigid pipes shall beclass B bedding

'Densyl' petrolatum anti corrosion tape asmanufactured by Denso SA (Pty) Ltd:

Pipes to be taped shall be coated with the appropriateprimer and the tape shall be applied with minimum 15mmlap per spiral unless otherwise described

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 6 2 -

Page 64: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Couplings and fittings to pipes shall be taped in strictaccordance with the manufacturer's instructions including allmastic, tape, "Layflat" sheeting, securing of same, etc

WATER SUPPLY

High density polyethylene Class 6 piping complyingwith SABS 533

3/1/83 25mm Pipes laid in ground not exceeding 1m deep m 6

3/1/84 50mm Pipes laid in ground not exceeding 1m deep m 337

Extra on HDPE class 6 pipes for uPVC compressionfittings

3/1/85 25mm HDPE to galvanised mild steel reducer No 6

3/1/86 50mm Reducer No 34

3/1/87 50mm Bend No 16

3/1/88 50mm Tee No 6

3/1/89 50mm Threaded 'BSP' adaptor No 9

3/1/90 50mm Elbow HDPE/GMS male/female adaptor No 8

3/1/91 50mm HDPE/GMS flanged male/female adaptor No 12

3/1/92 63mm Reducer No 15

Galvanised threaded mild steel pipes

3/1/93 40mm Pipes m 75

3/1/94 40mm Pipes fixed to steel structure m 15

3/1/95 50mm Pipes m 29

3/1/96 50mm Pipes fixed to steel structure m 121

Extra over galvanised mild steel pipes for steel fittings

3/1/97 50mm Elbow No 42

3/1/98 50mm Reducer No 22

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 6 3 -

Page 65: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

3/1/99 10mm Diameter U-bolt clamp for 50mm galvanised mildsteel pipe No 16

Galvanised flanged mild steel pipes

3/1/100 50mm Pipes m 96

Extra over galvanised flanged mild steel pipes for steelfittings

3/1/101 40mm Screwed end cap No 4

3/1/102 50mm Bend No 12

Valves, etc

3/1/103 40mm Ball valve as supplied by Cobra Brass No 4

3/1/104 25mm Pressure gauge with 50 x 25mm galvanised mildsteel Tee intersection No 1

3/1/105 50mm Stop valve No 10

3/1/106 50mm Gate valve No 6

3/1/107 50mm 'Cobra Type 700-50' high pressure float valve No 5

3/1/108 50mm 'Southern Cross All Brass' high pressure float valveinstalled in zinc reservoir No 1

3/1/109 50mm Air valve type Vent-o-mat RBXb No 1

3/1/110 50mm Ball type check valve No 4

3/1/111 50mm Low pressure 'Southern Cross All Brass' float valve No 1

Valve chamber on 100mm thick 20 MPa/19mm concretebase, half brick wall sides and bagged finish internallyto receive cast iron stop cock box (measuredelsewhere) finished smooth on all exposed surfacesincluding all necessary excavation, backfilling, cartingaway, formwork, etc

3/1/112 Valve chamber 800 x 800mm and not exceeding 500mmdeep internally No 2

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 6 4 -

Page 66: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Valve chamber covers, etc

3/1/113 'Saint Gobain' stop cock box product 2670 type l/d dutyclassl/D No 4

Sundries

3/1/114 20mm Galvanised mild steel garden stand pipe 1,5m longwith 500mm burried under ground with 'Cobra - 108LK' tapwith hose connector, the pipe fitted into a 110mm UPVCsleeve filled withe 15Mpa mass concrete the sleeve paintedwith enamel paint to specification No 3

3/1/115 110mm x 100mm Long UPVC sleeve cast into concretesurface bed No 4

3/1/116 20Mpa/19mm concrete borehole slab, size 1 450 x 400 x100mm thick cast after pipe installation is completed,including all formwork, excavations, etc No 4

3/1/117 Mild steel cage for borehole size 1 250 x 400 x 600mm highof 50 x 50 x 5mm angle iron frame filled in with 25 x 25 x3mm angle iron intermediate support for axpanded metal,the sides covered with 25mm expanded metal and the topcovered with slightly sloping galvanised corrugated iron, thecage provided with 4 x 150 x 150 x 10mm mild steel baseplates, each bolted to concrete base with 4 x M10 chemicalbolts, including all finishing, painting etc No 4

3/1/118 50 x 50 x 5mm Mild steel angle valve support kg 140

3/1/119 'Densyl' petrlatum anti-corrosion tape to 50mm galvanisedmild steel pipes m 6

Testing

3/1/120 Testing water pipe system as per SANS 1200 and all leaksto be repaired Item

Testing of existing water pipelines

3/1/121 Testing water pipe system as per SANS 1200 No 4

Budgetary allowance

3/1/122 Allow an amount of N$20,000-00 for repairs to existingwater pipelines Item

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 6 5 -

Page 67: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

WATER TROUGH

1,6mm Thick mild steel water through as manufacturedby Hemco Enginnering

3/1/123 Water trough 5m long x 600mm wide x 200mm deep fixedto mild steel channel section bearers No 7

3/1/124 Feeding trough as per specification No 3

3/1/125 Refurbish existing water trough 5m long x 600mm wide x200mm deep fixed to mild steel channel section bearers No 1

3/1/126 Float valve cover plate, size 400mm long x 600mm wide x200mm high No 1

WATER TROUGH SUPPORT

Excavation in compacted fill not exceeding 2m deep

3/1/127 Trenches m3 12

Risk of collapse of excavations

3/1/128 Sides of trench and hole excavations not exceeding 1,5mdeep m2 48

Extra over all excavations for carting away

3/1/129 Surplus material from excavations and/or stock piles on siteto a dumping site to be located by the contractor m3 15

Keeping excavations free of water

3/1/130 Keeping excavations free of all water other thansubterranean water Item

25MPa/19mm concrete

3/1/131 Surface beds including ground beams m3 27

Testing

3/1/132 Making and testing a set of four 150 x 150 x 150mmconcrete strength test cubes per concrete pour, one crushedat 7 days and 3 at 28 days (Provisional) No 4

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 6 6 -

Page 68: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

Finishing top surfaces of concrete smooth with a woodfloat

3/1/133 Surface beds m2 120

Rough formwork to sides

3/1/134 Edges of slabs not exceeding 300mm high m 92

Mesh reinforcement

3/1/135 Mesh ref. 395 fabric reinforcement in slabs m2 84

Channel section trough support fixed to concrete basewith L-shaped anchor bolt cast into concrete

3/1/136 100 x 50mm x 11kg/m Channel section beams kg 46.20

Bolts to beams, etc

3/1/137 M16 Grade 8.8 HD anchor bolt 200mm long embedded intop of concrete No 24

Carried Forward N $ Section No. 3External WorksBill No. 1External Works

- 6 7 -

Page 69: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

SOIL DRAINAGE

uPVC pipes

3/1/138 110mm Pipes laid in and including trenches not exceeding2m deep including bedding and backfilling all in accordanceto SABS standards m 357

Extra over uPVC pipes for fittings

3/1/139 110mm Bend No 23

3/1/140 110mm IE Junction No 16

3/1/141 110mm T Junction No 9

Sundries

3/1/142 Testing drainage pipe system Item

Carried to Final Summary N $ Section No. 3External WorksBill No. 1External Works

- 6 8 -

Page 70: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Item Unit Quantity Rate AmountNo

BILL NO 1

PROVISIONAL SUMS

NOTE:

The following sums and amounts are NET.

Under no circumstances may any Provisional Sum beextended at an amount lower than the amount given in theBill.

Unless a specific percentage mark-up for Attendance isindicated in the Rate column, the amount priced by theContractor for Attendance against each Provisional Sumshall be deemed to to be the Lump Sum ad shall not beadjusted unless the scope of th sub-contract variessignificantly.

Provisional sums contained herein may be omitted andreduced to claim for any loss by way of reductions oreomissions or any discount, or percentage relating toProvisional Sums or PC amounts or any loss of profit relatedthereto.

General

Unless otherwise described, all prime cost amounts andprovisional sums exclude the cash discount of 5% andinclude for delivery to site of all articles concerned

All prime cost amounts and provisional sums are net andinclude for delivery to site of all articles concerned

Profit

Where stated, the contractor may allow for profit if required

General attendance upon nominated sub-contractors anddirect contractors

The item "Allow for general attendance" which follows eachprovisional sum for selected sub-contractors and directcontractors work, shall be deemed to cover all thecontractor's costs incurred in providing free of charge to theselected sub-contractors and direct contractors, thefollowing:

Carried Forward N $ Section No. 4Provisional SumsBill No. 1Provisional Sums

- 6 9 -

Page 71: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

Brought Forward N $

1. The services as in clause B7.3 of the Preliminaries

2. Hoisting of the selected sub-contractor's and directcontractor's material in batches that can be handled by thecontractor's hoist or crane during normal working hours

3. Making good in all trades and cleaning down andremoval of rubbish on completion

Taking delivery

Taking delivery of goods or articles by the contractor on siteshall mean getting in, unpacking, checking that the quantityis correct and that the goods are complete and undamaged,submitting a report thereof to the interested parties andissuing vouchers for the receipt of such goods. Thecontractor shall store the goods and will be held responsiblefor the safety thereof and indemnify the employer againstany damage or loss which may occur

PROVISIONAL SUMS, ETC

Note: The following sums are for work to be executed by thecontractor and will, where applicable, be measured andvalued at bill or agreed rates on completion.

ELECTRICAL INSTALLATION

4/1/1 Provide the sum of N$ 80,000.00 (Eighty ThousandNamibian Dollars) for the electrical installation Item 80,000 00

4/1/2 Profit Item

4/1/3 Allow for general attendance Item

BORE HOLE PUMP REPAIRS

4/1/4 Provide the sum of N$ 50,000.00 (Fifty Thousand NamibianDollars) for bore hole pump repairs complete Item 50,000 00

4/1/5 Allow for profit Item

4/1/6 Allow for general attendance on sub-contractor Item

Carried to Final Summary N $ Section No. 4Provisional SumsBill No. 1Provisional Sums

- 7 0 -

Page 72: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

71

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

SECTION 5 BULK POWER FOR KOPANO PLEASE NOTE : All rates called for below shall be individually and realistically priced. Omissions, nominal or minimal rates, or 'INCLUDED' in place of any rate called for, will NOT be accepted. ALL QUANTITIES TO FINALLY CONFIRMED AT SETTING-OUT STAGE

GENERAL

1.1 Provision of all calculations, working drawings, manuals and as-built drawings as called for

Sum

1.2 Submission of calculations of all line parameters, conductor sag profiles, tensions, pole structure foundations for approval, prior to commencement of construction

Sum

1.3 Drawings and manuals, as specified, prints and magnetic media, including line profile drawing, sag charts and templates, condition of First Delivery, all locations

Sum

1.4 Compilation of meter serial number and consumer installation list, handed over to client in XLS spreadsheet data file. NB : THIS ITEM IS A SPECIFIC REQUIREMENT FOR THIS CONTRACT

Sum

1.5 Provision of GPS waypoint coordinate list of all consumer positions and LV reticulation line angle structures in text data file, based on WGS84 datum. NB : THIS ITEM IS A SPECIFIC REQUIREMENT FOR THIS CONTRACT

Sum

1.6

SETTING OUT

1.7 Setting out of site in conjunction with Engineer, ALL sites

Sum

TOTAL CARRIED FORWARD

Page 73: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

72

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD 1.8 COMMISSION & TEST

1. 9 Provision of all testing equipment to carry out specified tests including payment of fees to any outside Authority in respect of inspections and/or testing of the Works

Sum

1.10 Preliminary testing and inspection of installation with Engineer, to ensure correct and safe installation, prior to Practical Completion inspection with Client and Supply Authority, including insulation tests on all cables, earth resistance measurements on earth mats and electrodes

Sum

1.11 Testing and commissioning of entire installation, including compilation of detailed inspection and test records as per NRS 1034

Sum

1.12 Provision of THREE-PHASE generator on site for testing and commissioning in absence of NORED supply (provisional item, to be confirmed on site prior to commencement of commissioning process). NB : THIS ITEM IS A SPECIFIC REQUIREMENT FOR THIS CONTRACT

Sum

TOTAL CARRIED FORWARD

Page 74: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

73

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD 2.1 MV RETICULATION MV

RETICULATION POLES, CREOSOTED PINE TO SABS 753

2.2 Pole, 13 m x 180 mm top dia, for MV overhead line at road crossings

ea 1.0 Rate Only

2.3 Pole, 12 m x 180 mm top dia, for MV overhead line for special clearance requirements

ea 1.0 Rate Only

2.4 Pole, 11 m x 180 mm top dia, for MV overhead line MV OVERHEAD LINE INSULATORS, CONDUCTOR AND ACCESSORIES

ea 44.0

2.5 33 kV strain insulator assembly, Cullinan EP 1044, 40 kN, longrod, porcelain, twisted tongue/clevis (incl eye-bolts and nuts, formed dead-end, thimble clevis, D-shackle and M20 eyebolt)

ea 24.0

2.6 33 kV line post insulator assembly, Cullinan EP 480, 4 kN post type, porcelain (incl conductor wrap lock ties, spindle, nut and washers)

ea 123.0

2.7 33 kV stand-off insulator assembly, Cullinan EP 480 4 kN post type, porcelain (incl conductor wrap lock ties, spindle, nut and washers) MV CONDUCTOR

ea 5.0

2.8 Conductor, ACSR, code RABBIT m 15300 2.9 Crimped ACSR joints on angle

structure jumpers

set/3 15.0

2.10 Mechanical in-line ACSR joints MV POLE-TOP EQUIPMENT

set/3 16.0

TOTAL CARRIED FORWARD

Page 75: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

74

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD 2.11 Galvanised 33 kV A-frame cross-arm,

intermediate type, complete with threaded rod, nuts, flat, spring and curved washers

ea 1.0

2.12 Galvanised 33 kV A-frame cross-arm, strain type, complete with threaded rod, nuts, flat, spring and curved washers

ea 4.0

2.13 Galvanised 33 kV horizontal cross-arm, strain type, complete with pole clamps, threaded rod, stay arm, coach screw nuts, flat, spring and curved washers

ea 2.0

MV LINE TERMINATION

2.14 33 kV line supply load-break cutout fuse assembly, incl galvanised special horizontal mounting cross-arm, spacers and stay strap and mounting brackets, solid fuse, conductor jumpers and clamps, threaded rod, coach screws, nuts, curved washers etc

set/3 1.0

2.15 Line MV stay assembly, complete with 380 x 380 x 6 mm galvanised baseplate, stay rod, 7x4 mm² stay wire, thimble, dead-end/guy grips, insulator, tumbuckle and painted steel pipe stay guard

ea 7.0

2.16 Butt earth for intermediate poles, complete with galvanised steel down conductor, shorted BCEW coils, top strap and staples, as specified

ea 44.0

2.17 Line number plate, embossed aluminium, on first pole of OHL and spur-lines

ea 1.0

2.18 Pole number plate, alphanumerical, punched on aluminium plate 50 x 30 mm, nailed to pole 2000 mm agl

ea 1.0 Rate Only

TOTAL CARRIED FORWARD

Page 76: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

75

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD

CONVERSION OF EXISTING MV STRUCTURES

2.19 Convert existing 33 kV HLPCD pole structure to intermediate A-frame configuration : remove 3 x HLP insulators, replace by intermediate A-frame (labour only -material included elsewhere) MV POLE & STAY FOUNDATIONS TO SABS 1200

ea 1.0

2.20 Excavate / drill pole OHL foundations as per site setting out to required depth in ALL types of material, erection, backfill & compaction of foundation backfill. NOTE : No additional or extra-over rates for different types of materials will be accepted

ea 44.0

2.21 Excavate / drill stay foundations as per site setting out to required depth in ALL types of material, erection, backfill & compaction of foundation backfill. NOTE : No additional or extra-over rates for different types of materials will be accepted

ea 10.0

MV OVERHEAD LINE ROUTE

2.22 Survey of line route and peg all pole positions

km 5.1

2.23 Manual route clearing for overhead line, 10 m wide, incl removal of all roots and stumps mechanical clearing not permissible

km 5.1

2.24 Compensation for removal of fruit-bearing trees, only on instruction by engineer

Prov 25000 00

TOTAL CARRIED FORWARD

Page 77: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

76

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD

TRANSFORMERS & ACCESSORIES Including complete erection of structure with meter and crows-foot earthing

3.1 Transformer pole support, 11 m x 180 mm top diameter

ea

1.0

3.2 Transformer pole support, 9 m x 140 mm top diameter

ea

1.0

3.3 Transformer MV stay assembly, complete with 380 x 380 x 6 mm galvanised baseplate, stay rod, 7x4 mm² stay wire, thimble, dead-end/guy grips, insulator, tumbuckle and painted steel pipe stay guard

ea 2.0

3.4 Pole-mounted transformer, 100 kVA, 33 000/415 V, Dyn 11

ea 1.0 Rate Only

3.5 Pole-mounted transformer, 50 kVA, 33 000/415 V, Dyn 11

ea 1.0 Rate Only

3.6 Pole-mounted transformer, 25 kVA, 33 000/415 V, Dyn 11

ea 1.0

3.7 Transformer platform, consisting of two galvanised steel cradles, two galvanised steel channel iron supports complete with all mounting hardware

ea 1.0

3.8 33 kV transformer cut-out fuse assembly, incl galvanised special horizontal mounting cross-arm, spacers and stay strap and mounting brackets, 10 A fuse, conductor jumpers and clamps, threaded rod, coach screws, nuts, curved washers etc

set/3 1.0

3.9 Transformer surge arrester, 33 kV, Areva Varisil HE33-SD (with disconnector), 10 kA, incl galvanised mounting bracket, stay strap, coach screw, threaded rod, nuts, curved washers, conductor jumpers and earth wire connectors, lugs and clamps etc

set/3 1.0

TOTAL CARRIED FORWARD

Page 78: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

77

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD 3.10 Surge arrester, 6 kV, Areva Varisil

HE06 (without disconnector), 10 kA, LV neutral to MV earth, incl mounting bracket, conductor jumpers and earth wire connectors, lugs and clamps

ea 1.0

3.11 Surge arrester, 250 V, 1,5 kA, LV phases to neutral, incl mounting bracket, conductor lugs, jumpers and clamps, installed on transformer below LV terminal bushings on flexible earth connections TRANSFORMER METERBOARD Pole-mounted three-phase Type B meterboard, COMPLETE WITH

Set/4 1.0

3.12

Pole-mounted board

ea

1.00

3.13 80 A ABB / JSO, 25 kA, three phase main circuit breaker

ea 1.00

3.14 80 A ACTARIS / GEC kWH meters

ea

3.00

3.15 3-phase+neutral surge arrester, 40 kA

Set/4 1.00

3.16 Isolator, three phase, 40 A, 10 kA, in series with surge arresters Pole-mounted three-phase Type C meterboard, COMPLETE WITH :

ea

1.00

3.17 Pole-mounted board

ea 1.00 Rate Only

3.18 150 A, 25 kA, three phase ABB / JSO main circuit breaker

ea 1.00 Rate Only

TOTAL CARRIED FORWARD

Page 79: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

78

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD 3.19 Landis & Gyr ZMG405 kVA/kWh

meter (as supplied by NORED), to NORED/NamPower specification, commissioned and configured

ea 1.00 Rate Only

3.20

3 x 150/5 A CT's

Set/3

1.00

Rate Only

3.21 Meter voltage circuit protection fuses or 1 A resettable overload unit

Set/3 1.00 Rate Only

3.22 Removable neutral-earth link

ea

1.00

Rate Only

3.23 3-phase+neutral surge arrester, 40 kA

Set/4 1.00 Rate Only

3.24 Isolator, three phase, 100 A, 10 kA, in series with surge arresters

ea

1.00 Rate Only

3.25 Transformer label, engraved anodised aluminium, 300 x 200 mm, as per drawing TRANSFORMER EARTHING

ea 1.00

3.26 Transformer MV earth electrode, consisting of 4 off 1 500 mm long earth rods driven vertically into the ground 5 m from transformer position, interconnected with 2 off 5 m x 50 x 3 mm copper bar and connected to transformer tank with 70 mm² PVC insulated earth wire, including trenching, backfill and compaction

ea 1.0

3.27 Transformer LV earth electrode, consisting of 4 off 1 500 mm long earth rods driven vertically into the ground 2 m from transformer position, interconnected with 2 off 5 m x 50 x 3 mm copper bar and connected to transformer neutral with 70 mm² insulated earth wire, including trenching, backfill and compaction

ea 1.0

TOTAL CARRIED FORWARD

Page 80: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

79

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD 3.28 Earth conductor protective pipe, 20

mm thin-wall galvanised pipe, 3 m long, strapped to pole with stainless steel band-it strapping LV CABLES CABLE, LV, PVCSWA, STRANDED COPPER CONDUCTOR

ea 2.0

3.29 Cable, PVCSWA, 4 x 50 mm², transformer to Type C meter board, fastened to pole with stainless steel straps at 500 mm intervals

m 10.0

3.30 Cable, PVCSWA, 4 x 35 mm², transformer to Type B meter board, fastened to pole with stainless steel straps at 500 mm intervals

m 10.0 Rate Only

3.31 Cable, PVCSWA, 4 x 50 mm², Type B meter board to changeover board in generator room

m 50.0

3.32 Cable, PVCSWA, 4 x 35 mm², Type B meter board to ABC LV reticulation distribution board, fastened to pole with stainless steel straps at 500 mm intervals

m 10.0 Rate Only

3.33 Cable, PVCSWA, 4 x 6 mm² from current change over board to new staff houses

m 10.0 Rate Only

3.34 Cable termination, indoor, 4 x 50 mm², including cable gland and shroud

ea 1.0

3.35 Cable termination, outdoor, 4 x 50 mm², including cable hood and terminal lugs

ea 1.0

3.36 Cable termination, indoor, 4 x 35 mm², including cable gland and shroud

ea 1.0 Rate Only

TOTAL CARRIED FORWARD

Page 81: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

80

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

3.37 Cable termination, outdoor, 4 x 35

mm², including cable hood and terminal lugs

ea 1.0 Rate Only

3.38 Cable termination, outdoor, 4 x 6 mm², including cable hood and terminal lugs

ea 2.0 Rate Only

3.39 BCEW, 25 mm², installed with 50 mm² LV cables, connected to earth electrode and distribution board earth stud

m 50.0

3.40 BCEW, 6 mm², installed with 6 mm² LV cables, connected to earth electrode and distribution board earth stud

m 50.0 Rate Only

3.41 Kick pipe for main cable and earth conductor, 50 mm galvanised BOSAL thin-wall steel tube, 3 m long, strapped to pole with stainless steel straps

ea 1.0

3.42 Stainless steel strapping of OHL supply cables to poles, at 500 mm intervals TRANSFORMER POLE & STAY FOUNDATIONS TO SABS 1200

Sub 1.0

3.43 Excavate / drill pole OHL foundations as per site setting out to required depth in ALL types of material, erection, backfill & compaction of foundation backfill. NOTE : No additional or extra-over rates for different types of materials will be accepted

ea 2.0

3.44 Excavate / drill stay foundations as per site setting out to required depth in ALL types of material, erection, backfill & compaction of foundation backfill. NOTE : No additional or extra-over rates for different types of materials will be accepted

ea 2.0

TOTAL CARRIED FORWARD

Page 82: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

81

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD 3.45

CHANGEOVER BOARD Manual changeover board, complete with changeover switch and indicator lights, mounted in a wall box

ea

1.00

3.46 Main incoming circuit breaker, 40 A SH3-G3, 10 kA, Curve 1, for 25 kVA transformer

ea 1.0

3.47 Feeder circuit breaker, 15 A, Single phase

ea 2.0

3.48 House control circuit breaker, 5 A Single phase

ea 2.00

3.49 LV surge diverters, connected to phase/neutral and earth bars

Set/4 1.0

3.50 Main DB crows foot earth electrode, consisting of three vertical earth rods inter connected by 3 x 2 m, 35 mm² BCEW and by insulated 35 mm² earth conductor to DB earth stud, including compression gland

ea 1.0

3.51 Distribution board wiring diagram, printed on A3 paper, laminated in plastic sheeting and fixed to DB door

ea 1.0

3.52 ADDITIONAL ITEMS Items omitted above, required for a safe and functional installation. Please specify

TOTAL CARRIED FORWARD

Page 83: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

82

ITEM DESCRIPTION UNIT QTY RATE AMOUNT N$ c

BROUGHT FORWARD

PROVISIONAL ITEMS The rates for Provisional Items DO NOT necessarily form part of the contract, and are to be applied only on specific written instruction by the Engineer, at the discretion and approval of the Client. Rates and amounts listed in this Section WILL betaken into consideration during Tender Adjudication

4.1 PROFIT ON MATERIAL State profit percentage for supply, delivery to site, storage and insurance for items not mentioned in other Sections of this Schedule of Quantities

4.2 Per cent mark-up on Suppliers' invoice DAYWORKS Rates for work over and above rates quoted for elsewhere in this document

% 1.0

4.3

LABOUR

4.4 Electrician

N$/hr 20.0

4.5

Wireman

N$/hr

20.0

4.6

Linesman

N$/hr

10.0

4.7

Jointer

N$/hr

15.0

4.8 Labourer (Employee)

N$/hr

30.0

4.9

Labourer (Casual)

N$/hr

30.0

4.10

PLANT

4.11 Compressor N$/hr

50.0

4.12

Hammers Other

N$/hr 50.0

4.13

TRANSPORT

4.14 1 ton LDV

N$/km 100.0

4.15

5 ton truck

N$/km

50.0

TOTAL CARRIED FORWARD

Page 84: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

83

ITEM DESCRIPTION UNIT QTY TOTAL RATE AMOUNT N$ c

BROUGHT FORWARD 4.16

8 ton truck

N$/km

25.0

4.17

GENERAL MATERIAL

4.18 Circuit breaker, JSO, 25 kA or equivalent, rated 125 A

ea

3.0

4.19 Circuit breaker, JSO, 25 kA or equivalent, rated 100 A

ea

3.0

4.20 Consumer distribution board. 24 way, single phase, surface mount, installed in building back to back with external meterboard, complete with wall penetration, interconnecting wiring and wall fastener screws and plugs

ea 3.0

4.21 MCB, main supply, 30 A TP, 5 kA, SF3 -G3, installed in meterboard

ea 3.0

4.22 MCB, 80 A, 1 ph, 10 kA, for supply to special consumers

ea

3.0

4.23 Feeder circuit breaker, SH3-G3, 10 kA, or equivalent, Curve 1, rated 40 A

ea 3.0

4.24 Feeder circuit breaker, SH1-G3, 10 kA, or equivalent, Curve 1, rated 40 A

ea 3.0

4.25 Termination, indoor, PVCSWA cable, 4x16 mm², underground consumer supply connection

m 5.0

4.26 Insulated copper earth wire, 35 mm² OVERHEAD LINE MATERIAL

m 50.0

4.27 33 kV line post insulator assembly, Cullinan EP 306, 12,5 kN post type at road crossings and two adjacent structures, porcelain (incl conductor twin ties, spindle, nut and washers)

ea 3.0

TOTAL CARRIED FORWARD

Page 85: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

84

ITEM DESCRIPTION UNIT QTY TOTAL RATE AMOUNT N$ c

BROUGHT FORWARD 4.28 Conductor, ACSR, code GOPHER

m 100.0

4.29 Conductor, ACSR, code FOX

m

100.0

4.30 Conductor, ACSR, code MINK m 100.0 4.31

Conductor, ACSR, code HARE

m

100.0

4.32

CIVIL WORK : TO SABS 1200 EXCAVATION AND TRENCHING

4.33 Excavate / drill 2 200 mm deep, backfill and compact in ALL types of material for 13 m poles

ea 1.0

4.34 Excavate / drill 2 000 mm deep, backfill and compact in ALL types of material for 12 m LV poles

ea 1.0

4.35 Excavate / drill 1 800 mm deep, backfill and compact in ALL types of material for 11 m poles

ea 10.0

4.36 Excavate / drill 1 500 mm deep, backfill and compact in ALL types of material for 8 m LV poles

ea 10.0

4.37 Excavate / drill 1 200 mm deep, backfill and compact in ALL types of material for Airdac support / termination poles

ea 10.0

4.38 Excavate / drill 1 600 mm deep, backfill and compact in ALL types of material for MV & LV stays

ea 10.0

4.39 Trenching in ALL types of material for LV OHL and consumer supply cables, 800 mm deep, 500 mm wide Quantity is provisional -to be finalised on site

m 100.0

4.40 Route clearing for overhead line, 8 m wide

km 5.0

TOTAL CARRIED FORWARD

Page 86: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

85

BROUGHT FORWARD 4.41

ADDITIONAL ITEMS

Items omitted above, required for a safe and functional installation. Please specify

TOTAL CARRIED FORWARD TO SUMMARY

Page 87: Bills of Quantities for Civil, Structural, Mechanical and ... Kopano and Katima QC.pdf · Bills of Quantities for Civil, Structural, Mechanical and Electrical Works at Katima ...

MCA Katima Mulilo and Kopano Camp

86

FINAL SUMMARY

Section

No Page Amount

N$

c

1 Preliminaries -17-

2 Building Works -51-

3 External Works -68-

4 Provisional Sums -70-

5 Bulk Power for Kopano -85-

Sub Total N$

Contingencies Allow the 5% of total contract amount for Contingencies to be used as directed by the Engineer and deducted in whole or in part if not required

N$

Carried to Form of Tender N$


Recommended