+ All Categories
Home > Documents > Biomass CCS - IEAGHG · 2013. 8. 28. · •Dual fluidised bed •Entrained flow Biomass firing...

Biomass CCS - IEAGHG · 2013. 8. 28. · •Dual fluidised bed •Entrained flow Biomass firing...

Date post: 14-Feb-2021
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
22
Biomass CCS Dr Amit Bhave CEO, cmcl innovations 7 th IEAGHG International CCS Summer School 21 st -26 th July, University of Nottingham, UK
Transcript
  • Biomass CCS

    Dr Amit Bhave

    CEO, cmcl innovations

    7th IEAGHG International CCS Summer School21st -26th July, University of Nottingham, UK

  • TESBiC: Techno-economic analysis and road-mapping of biomass to power with

    CO2 capture

    C-FAST: Carbon-negative hydrocarbon fuels from algal biomass

    K2: Coupling of real world data and fast response algorithms

    Modelling low carbon technologies

    cmcl innovations

    Engineering software, technical consulting & training

    - automotive, truck & non-road

    - clean energy and process engineering

    innovation awards

    kinetics & srm engine suite: advanced IC engine fuels, combustion and emissions simulator

    mod suite: model development suite, data standardisation, uncertainty

    propagation, parameter estimation, optimisation

  • Contents

    • Biomass CCS: scope and context

    • Impetus for biomass CCS

    • Bioenergy strategy and biomass supply chain

    • Biomass CCS technology combinations

    • A case study

    • Summary

  • biomass CCS: scope

    Source: EBTP and ZEP joint report on BioCCS, 2012

    Biomass fuelled power generation with CCS for heat and/or power

  • Impetus for biomass CCS

    • ETI’s ESME toolkit’s least-cost options for meeting the UK’s energy demand and emissions reduction targets to 2050, identify biomass CCS as vital with large, negativeemissions, a high option value and high persistence

    • IEAGHG, 2011: Despite its strong GHG reduction potential, there is a considerable dearth of information for biomass CCS as compared to that for fossil based CCS

    • APGTF, 2011/2012: RD&D strategic themes and priorities - whole system : focus on virtual system simulation and optimisation- capture technologies: focus on economics, efficiency penalty, emissions,

    co-fired biomass, 2nd and 3rd generation technologies

    • EBTP/Zep 2012: Accelerate deployment of advanced biomass conversion processes and establish an EU biomass CCS roadmap towards 2050.

    • TESBiC 2011/2012: Significant gaps that exist in the understanding of biomass CCS -key technical and economic barriers, and UK deployment potential to 2050

  • Bioenergy strategy

    • Renewable Energy Strategy (RES) 15% renewable energy by 2020

    • Sustainable biomass could contribute 8%-11% of the total UK energy demand by 2020

    • International supplies (USA/Canada for example) will be the key contributors

    • Current use of biomass in EU27 and projections for 2020, 2030 up to 2050 reveal a four-fold increase to ~370 Mtoe.

  • Biomass CCS: a system-level approach

    Biomass supply chain

    Biomass pre-processing Biomass thermo-chemical conversion to power

    and CO2 capture

    CO2 transport and storage

  • Biomass supply chain

    Important characteristics of the biomass supply chain :

    • Cost/availability of local vs. imported biomass

    • Location of local biomass sources w.r.t. CO2 network

    • Quality of biomass: low sulfur content, but chloride and potassium salts and ash chemistry (rather than the ash content)

    Types of biomass:

    • Forestry biomass

    • Agricultural residues

    • Energy crops

    • Municipal solid waste

    • Industrial waste

    Biomass supply chain structure:

    • In-field/in-forest collection/harvesting

    • In-field/in-forest handling and transport

    • Loading to/unloading from transportation

    • Transportation

    • Storage

    • Pre-processing

  • Biomass sustainability criteria

    • UK government’s Sustainability Criteria require an independently verified minimum 60% GHG savings (vs. EU fossil grid average) across the whole biomass supply chain

    • If criteria not met, biomass generators will not receive government support necessary to make businesses economically viable

    • Sustainability challenges:

    – Ensuring significant reductions (vs. fossils) in CO2 emissions

    – No negative impact on forest productivity, biodiversity and cover, indigenous populations, etc.

    – Avoiding illegal logging

  • Biomass sustainability measures

    For example, Drax, UK’s largest coal power station (4000 MW capacity) in its transformation to a predominantly biomass-fuelled power generator has incorporated a comprehensive “sustainable biomass procurement programme”

    • Rejection of all non-sustainable biomass

    • All supply chain stages are investigated - cultivation and harvesting, transforming, processing and transportation.

    • Minimum standards on life cycle GHG savings

    • Compliance with policy written in to contracts

    • Extensive data gathering and assessment through a programme of information exchange and an improvement programme

    • Independent 3rd party audit

  • Biomass feedstock pre-processing

    • Coal vs. biomass at plant-site: – Dust management: risk of fire, explosion, etc.– Volume: Lower energy density, distribution– Storage: dry storage and self-heating minimisation

    • Wood chips (1-5 cm long), moisture content high, stored for a limited time, less energy to produce

    • Pellets made from chips, particle size < 2mm, more energy to produce than chips

    • But higher energy density with pellets, do not degrade (rot) so easily, preferred for transport over large distances

    • Torrefaction: – Biomass: Moulds/rot during storage, heterogeneity/particle size reduction– Mild pyrolysis. Range: 230-290oC. Mass loss up to 30%. Retained energy

    content 90%. – Behaves more like coal good feedstock for transition from fossils to biomass– Exothermic nature requires good temperature control– Powdered torrified biomass – high reactivity– Torrefied pelletization requires additive binder– Unknowns: Scale-up and CAPEX, OPEX implications (LCA)

    Biomass feedstock: pellets[50 pence coin added for scale]

  • Biomass conversion to power

    Coal technologies

    • Pulverised coal combustion:

    • Direct co-firing of biomass

    • Conversion to 100% biomass

    • Integrated gasification combined cycle (IGCC) coal gasification:

    • Direct co-firing of biomass

    • Conversion to 100% biomass

    Biomass technologies

    • Dedicated biomass combustion:

    • Bubbling fluidised bed

    • Circulating fluidised bed

    • Fixed grate

    • Dedicated biomass gasification:

    • Bubbling fluidised bed

    • Circulating fluidised bed

    • Dual fluidised bed

    • Entrained flow

    Biomass firing capacity pathways:• Co-firing: cheapest way to get new biomass firing capacity, • Other options such less cost-effective options involve converting existing coal fired plants to operate dedicated biomass, or a new build plant

  • CO2 capture techniques

    Post-combustion

    • Solvent scrubbing, e.g. amines, chilled ammonia

    • Low-temperature solid sorbents, e.g. supported amines

    • Ionic liquids

    • Enzymes

    • Membrane separation of CO2 from flue gas

    • High-temperature solid sorbents, e.g. carbonate looping

    Pre-combustion

    • IGCC with physical solvent absorption

    • Membrane syngas generation, with physical solvent absorption

    • Membrane separation of H2 from syngas

    • Sorbent enhanced reforming using carbonate looping

    • ZECA concept

    Oxy-combustion

    • Oxy-fuel boiler with cryogenic O2separation from air

    • Oxy-fuel boiler with membrane O2separation from air

    • Chemical-looping-combustion using solid oxygen carriers

  • TRLs: CCS technologies

    1 2 3 4 5 6 7 8 9

    Solvent scrubbing

    Low-temp solid sorbents

    Ionic liquids

    Enzymes

    CO2 membrane separation

    Carbonate looping

    Oxy-fuel with cryogenic O2

    Oxy-fuel with membrane O2

    Chemical-looping-combustion

    IGCC with solvent absorption

    H2 membrane separation

    Syngas membrane

    Sorbent enhanced reforming

    ZECA concept

    TRL

    Co-firing

    Dedicated

    TRL = Technology Readiness LevelTRL 1 = Basic researchTRL 2 = Theoretical researchTRL 3 = Applied researchTRL 4 = Bench-scale test rigTRL 5 = Pilot plantTRL 6 = Small-scale demonstration plantTRL 7 = Full-scale demonstration plantTRL 8 = First commercial plants TRL 9 = Mass deployment of fully commercial plants

  • Biomass CCS roadmap: assessment criteria

    Development aspects and prospects

    • Key drivers for development

    • Key development issues, potential show-stoppers

    • Main players internationally

    • Pilot/demonstration /commercial plants and R&D activities

    • Current TRL

    • Likely TRL in 2020

    • Environmental issues

    Feedstocks and feasibility

    • Contaminants of risk, required specifications

    • Pre-processing needs, benefits

    • Appropriate feedstocks, robustness to variability

    • Maximum % co-firing feasible

    • Technical feasibility of component combination

    • Ease of changing to high co-firing / 100% dedicated conversion

    Techno-economics

    • Equipment scales (MW min, MW max), suitability for small-scale

    • Plant LHV efficiency with capture

    • Flexibility, ability to load follow

    • Capital cost with capture

  • Technology combinations

    Solvent

    scrubbing,

    e.g. MEA,

    chilled

    ammonia

    Low-temp

    solid

    sorbents,

    e.g.

    supported

    amines

    Ionic

    liquidsEnzymes

    Membrane

    separation

    of CO2 from

    flue gas

    High-temp

    solid

    sorbents,

    e.g.

    carbonate

    looping

    Oxy-fuel

    boiler with

    cryogenic O2

    separation

    Oxy-fuel

    boiler with

    membrane

    O2

    separation

    Chemical-

    looping-

    combustion

    using solid

    oxygen

    carriers

    IGCC with

    physical

    absorption

    e.g.

    Rectisol,

    Selexol

    Membrane

    separation

    of H2 from

    synthesis

    gases

    Membrane

    production

    of syngas

    Sorbent

    enhanced

    reforming

    using

    carbonate

    looping

    ZECA

    concept

    Direct cofiring

    Conversion to 100% biomass

    Direct cofiring

    Conversion to 100% biomass

    Fixed grate

    Bubbling fluidised bed

    Circulating fluidised bed

    Bubbling fluidised bed

    Circulating fluidised bed

    Dual fluidised bed

    Entrained flow

    22 24

    12

    14

    9 11 13

    Not feasible

    18 20

    11a

    12a

    Not feasible

    Dedicated

    biomass

    gasification

    Not feasible 16

    Dedicated

    biomass

    combustion

    2 4 6 8 106a

    Post-combustion Oxy-combustion Pre-combustion

    Coal IGCC

    gasificationNot feasible Not feasible 15 17 19 21 23

    Pulverised coal

    combustion1 3 5 75a

  • Short-listed biomass CCS technologies

    Criteria

    Co-firing amine

    scrubbing

    Dedicated biomass with

    amine scrubbing

    Co-firing oxy-fuel

    Dedicated biomass oxy-fuel

    Co-firing carbonate looping

    Dedicated biomass chemical looping

    Co-firing IGCC

    Dedicated biomass BIGCC

    Likely TRL in

    2020

    7 to 8 6 to 7 7 6 5 to 6 5 to 6 7 5 to 6

    Key technical

    issues

    Scale-up, amine

    degradation,

    Scale-up, amine

    degradation,

    O2 energy costs, slow response

    O2 energy costs, slow

    response

    Calciner firing, solid degradation, large purge of CaO

    Loss in activity, reaction

    rates, dual bed

    operation

    Complex operation,

    slow response, tar

    cleaning, retrofit

    impractical

    Complex operation,

    slow response, tar

    cleaning, retrofit

    impractical

    Suitability for

    small scale

    Low High Low High Low High Low High

    Plant

    efficiency

    with capture

    OK Low OK Low Good Good High, Good

    Capital costs

    with capture

    OK Expensive OK High ASU costs

    OK OK OK Expensive,

    UK

    deployment

    potential

    Immediate capture retrofit

    opportunities,

    retrofit opportunities

    high long-term

    potential

    retrofit opportunities

    , long-term doubtful

    retrofit opportunities

    , high long-term

    potential

    capture retrofit opportunities,

    cement integration

    Likely first demos in

    Europe, UK in ~2020. High long term potential

    No current UK plants,

    several demos by

    2020Long-term

    doubt

    No current UK plants,

    demo unlikely by

    2020.High long-

    term potential

  • Techno-economics: a case study

    Biomass chemical looping

  • Biomass chemical looping: costing

    Variable Costs Usage £M/yr

    1. Wood fuel 8.29 108 kg/yr 116.0

    2. Oxygen carrier (new) 1.19 106 kg/yr 4.74

    3. Spent carrier (credit) -4.22

    4. Fly ash disposal 1.78 106 kg/yr 0.00356

    5. Cooling water make-up 9588 kg/s 51.4

    Variable costs 167.9

    Maintenance and Labour 20.37

    Insurance 5.09

    Fixed costs 25.46

    Total O&M costs 193.36

    Capacities investigated: 40 to 300 MWe

    Item £M, 2011

    Storage and handling of solid materials 41.1

    Boiler island 220.5

    CO2 compression and drying plant 31.4

    Power island 76.5

    Air reactor (458 m3) 64.8

    Fuel reactor (581 m3) 74.9

    Total installed CAPEX 509.2

    Operation and utilities (% of TIC) 25.5

    Civils and land costs (% of TIC) 50.9

    Project Development Costs (% of TIC) 25.5

    Contingency (% of TIC) 50.9

    Total investment cost 661.9

    Specific investment cost (£M/MWe) 2.21

    268 MWe, net LHV efficiency ~ 38.7%

    Model formulation: CAPEX, OPEX, generation efficiency, and emissions as a function of the nameplate capacities and extent of CO2 capture.

  • Biomass CCS: techno-economic comparison

    TRL

  • Summary - 1

    • To date, little activity at industrial scale on the application of CO2 capture technologies to co-fired or dedicated biomass power plants. This dearth of practical data increases the complexity and uncertainties associated with the estimation and roadmapping of biomass CCS technologies.

    • The industry’s progression to the large fossil-based CCS demonstration projects is slow due to high costs and requirement of significant government subsidies.

    • Dependency on fossil based CCS: Recent setbacks and cancellations of the coal-based CCS projects will further delay the development of biomass CCS. This, however, also presents an opportunity for lower TRL biomass CCS technologies.

    • Incentivising negative CO2 emissions via the capture and storage of biogenic CO2 under the EU emissions trading scheme (ETS) is highly important.

  • Summary - 2

    • Biomass CCS attractive for small (50 MWe), intermediate (250 MWe) and large (~600 MWe) scales. At large scales, the issue of “sustainable biomass procurement” also needs careful consideration.

    • For the eight biomass-based power generation combined with carbon capture technologies varying over a wide range of TRLs, from TRL 3 to TRL 8, the range of techno-economic parameters are the following:

    • ~ 5% to 15% : Range of the efficiency drop

    • ~ 45% to 130%: Range of the increase in specific CAPEX (£/MWe) with CO2 capture

    • ~ 4% to 36%: Range of increase in OPEX (£/yr) with carbon capture

    • CAPEX, LCOE: Generation scales and fuel costs the main drivers


Recommended