+ All Categories
Home > Documents > BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

Date post: 16-Oct-2021
Category:
Upload: others
View: 6 times
Download: 0 times
Share this document with a friend
23
- - - BLACKTOP CONSULTING ENGINEERS BCE ACN: 150 023 868 ABN: 84 683 812 614 PO Box 918 Geraldton WA 6531 Phone: (08) 9964 5459 Email: [email protected] 10 September 2019 City of Greater Geraldton PO Box 101 Geraldton WA 6531 Job No: 19BCE1874 Your Job ref: 112876 Att: Ms Jessica Felix Dear Jess, Project: Meru Landfill Composting Slab Installation Geotechnical Report EXECUTIVE SUMMARY BCE have completed a geotechnical investigation at the site proposed to construct a trafficable slab for composting of putrescible waste at the Meru Landfill. The purpose of the investigation is to provide a method to complete earthworks at the site which will achieve the required allowable soil bearing capacity and site classification for the slab. The investigation findings suggest that the site comprises of a deep layer of clayey sand. Compacted site soils will be suitable to build upon following construction of a 200mm subbase beneath the concrete slab. Following subbase construction the proposed slab construction site will provide an estimated allowable bearing pressure of 125kPa and a site classification “S” when prepared in accordance with recommendations provided in this report. BACKGROUND On instruction from the City of Greater Geraldton, Blacktop Consulting Engineers (BCE) have completed a geotechnical investigation at the site proposed to construct a slab for composting of putrescible waste at the Meru Landfill. Anticipated project civil works include construction of a new concrete slab and leachate collection bunker at one end of the slab. The following foundation soil requirements are required to ensure the necessary support of the trafficable concrete slab: The foundation soil bearing capacity shall have an allowable bearing capacity of not less than 100kPa. The slab installation site, when classified in accordance with Table 2.1 in AS2870-2011 shall have a site classification “S”. Based on the findings of this geotechnical investigation the City of Greater Geraldton have requested that BCE provide a method to complete earthworks at the site which will achieve the stipulated allowable soil bearing capacity and site classification. The field investigation programme and all related studies were planned and supervised by Civil & Structural Engineers Mr Lester Smith, Mr Sam Omelaniuk & Mr Kristian March from BCE. The materials testing of samples taken during the
Transcript
Page 1: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

- - - BLACKTOP CONSULTING ENGINEERS BCE

ACN: 150 023 868 ABN: 84 683 812 614 PO Box 918 Geraldton WA 6531

Phone: (08) 9964 5459 Email: [email protected]

10 September 2019

City of Greater Geraldton

PO Box 101

Geraldton

WA 6531

Job No: 19BCE1874 Your Job ref: 112876

Att: Ms Jessica Felix

Dear Jess,

Project: Meru Landfill Composting Slab Installation

Geotechnical Report

EXECUTIVE SUMMARY

BCE have completed a geotechnical investigation at the site proposed to construct a trafficable slab

for composting of putrescible waste at the Meru Landfill. The purpose of the investigation is to

provide a method to complete earthworks at the site which will achieve the required allowable soil

bearing capacity and site classification for the slab. The investigation findings suggest that the site

comprises of a deep layer of clayey sand. Compacted site soils will be suitable to build upon following

construction of a 200mm subbase beneath the concrete slab. Following subbase construction the

proposed slab construction site will provide an estimated allowable bearing pressure of 125kPa and a

site classification “S” when prepared in accordance with recommendations provided in this report.

BACKGROUND

On instruction from the City of Greater Geraldton, Blacktop Consulting Engineers (BCE) have

completed a geotechnical investigation at the site proposed to construct a slab for composting of

putrescible waste at the Meru Landfill. Anticipated project civil works include construction of a new

concrete slab and leachate collection bunker at one end of the slab. The following foundation soil

requirements are required to ensure the necessary support of the trafficable concrete slab:

• The foundation soil bearing capacity shall have an allowable bearing capacity of not less than

100kPa.

• The slab installation site, when classified in accordance with Table 2.1 in AS2870-2011 shall

have a site classification “S”.

Based on the findings of this geotechnical investigation the City of Greater Geraldton have requested

that BCE provide a method to complete earthworks at the site which will achieve the stipulated

allowable soil bearing capacity and site classification. The field investigation programme and all

related studies were planned and supervised by Civil & Structural Engineers Mr Lester Smith, Mr Sam

Omelaniuk & Mr Kristian March from BCE. The materials testing of samples taken during the

Page 2: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

2

investigation were completed at Blacktop Material Engineering’s Geraldton NATA accredited

laboratory. Sunset Mini Excavator hire provided the excavator and operator required to undertake test

pit excavation. The site investigation was completed on 29 August 2019.

SCOPE OF REPORT

BCE’s proposal for this study was described in our email to the City of Greater Geraldton dated 20

August2019. The scope of this report includes:

1. Identify the investigation locations.

2. Provide a general description of the site.

3. Describe the soil types encountered during the field investigation which includes the

construction of two test pits to approximately 2m depth. Provide photographs of the site soil

types and test pits.

4. Report depth to groundwater or rock if encountered.

5. Describe the results of the laboratory materials testing completed on the sampled soils

including Particle Size Distribution (PSD), Atterberg Limit Testing, Unified Soil Classification

Symbol (USC), Maximum Modified Dry Density (MMDD) and Soaked CBR.

6. Provide the AS2870-2011 site classification for the site. Advise of calculated ground surface

movements due to soil moisture content change.

7. Provide a description of suitable compaction testing methods for the site.

8. Discuss soil organic content and if required recommend required topsoil strip depth.

9. Report if asbestos, hydrocarbon and / or uncontrolled fill were observed at the site in the

course of the site investigation.

10. Provide soil bearing capacity and settlement estimates for the site.

11. Assess the suitability of site material for use as structural fill purposes and recommended

compaction technique for site materials.

12. Provide soil excavation characteristics and stability criteria for open excavations.

13. Provide erosion and sediment control guidance.

14. Provide recommendations for retaining and geotechnical design parameters for retaining

design.

15. Recommend appropriate wind design criteria.

16. Recommend appropriate earthquake design seismic hazard factor and the subsoil class.

17. Provide advice on completing earthworks for building site preparation.

18. Provide recommendations for the construction and maintenance of site drainage.

Page 3: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

3

1. SITE INVESTIGATION LOCATION

A site plan showing the 2 test pit locations at the site proposed to construct a slab for composting of

putrescible waste at the Meru Landfill is provided in Appendix A. Photographs of the site and the

investigation locations are provided in Appendix B.

GENERAL SITE DESCRIPTION

As can be seen from the photographs provided in Appendix B the site topography is quite flat across

the site. No creek crossings, established water courses or drainage abnormalities appear to run

through the site. It would not appear that the site floods. Bush fire is seen to present a low risk to

improvements at the site. No buildings currently occupy the area where the new slab will be

constructed, however until recently green waste was stockpiled in the area.

2. TEST PIT FINDINGS

Excavation was possible with a 3t excavator to a depth of 2.0m at the site. The investigation findings

suggest that the soils comprise of clayey sand. No hard rock was encountered at either test pit site.

The excavation pit profiles for the two test pits are similar and are shown in the photograph below:

More photographs of the excavated soil type are provided in Appendix B. The material was excavated

as loose soil with a few cemented clumps of clayey sand up to 100mm diameter. The soil appears to

be native. The native soils do not appear to have been previously disturbed.

3. DEPTH TO WATER TABLE & ROCK

Hard rock was not encountered to 2.0m below the site. There was no evidence of the water table

within the excavation depth of 2.0m of the soil surface. It is expected that the water table will exist

+15m below the ground surface.

Page 4: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

4

4. RESULTS OF LABORATORY MATERIALS TESTING

Please refer to Appendix E for an explanation of these tests and comments. All test certificates are

provided in Appendix C. Results are summarised in the following section.

Particle Size Distribution (PSD), Atterberg Limit & Unified Soil Classification Symbol (USC)

Testing

USC’s which provide a description of the site soils are shown in Table 1 below.

Unified Soil Classification Symbol (USC)

Test Pit 1 @ 0.3m below surface. SC

Test Pit 2 @ 1.8m below surface. SC

Table 1: Unified Soil Classification.

The USC symbol for the material represents the following soil description:

• SC is the classification symbol for a sand / clay mixture.

The samples taken from test pit 1 & 2 had 30% & 24% of material passing the 75micron sieve

respectively. Consistency limit results suggest that the material from both test pits contains a low /

moderate clay fraction. These characteristics suggest that the soil will have borderline strength

characteristics and that a subbase layer will be required to be constructed.

Maximum Dry Density / Optimum Moisture Content & Field Moisture Content

The Maximum Modified Dry Density results presented in Table 2 below are what might be expected

for a clayey sand. The maximum dry density of the materials indicate that compaction of the materials

is measurable with a nuclear densometer instrument.

Test Pit No. MMDD (t/m3) / OMC (%)

Test Pit 1 @ 0.3m below surface. 2.09 / 8.5

Test Pit 2 @ 1.8m below surface. 2.11 / 8.0

Table 2: Maximum Modified Dry Density.

Page 5: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

5

California Bearing Ratio (CBR) Test

Results indicate that the sampled material had a CBR value as shown in Table 3 below.

Test Pit No. Soaked

CBR

PI (%) Meet CGG Subgrade

Requirements

Test Pit 1 @ 0.3m below surface. 30 15 No

Test Pit 2 @ 1.8m below surface. 20 11 Yes

Table 3: California Bearing Ratio.

The material from test pit 1 does not meet CGG requirements for subgrade (which is a soaked CBR

exceeding 7% and a PI less than 15). Results indicate that the material is too reactive to build

pavement structures directly on, that’s why the CGG would not allow it on their projects without a

specific pavement improvement design be completed. The subgrade deficiencies can be rectified by

constructing a subbase.

5. AS2870 – 2011 SITE CLASSIFICATION FOR THE SITE

Please refer to Appendix E for an explanation of site classification. The expected surface movement

for the site has been classified in accordance with Table 2.1 in AS2870-2011 and is provided in Table

4 below.

Location Expected Surface Movement

(mm) *

Achievable Site Classification in

Accordance with AS2870 - 2011

Test Pit 1 13 S

Test Pit 2 10 S

Table 4: Expected Surface Movement.

* Estimation of the characteristic surface movement completed in accordance with AS2870-2011.

The predicted shrinkage response of the site soils is quite low. When classified in accordance with

Table 2.1 in AS2870-2011 the site classification is Class “S”. Essentially a Class “S” site is considered

stable and is expected to experience slight ground movement from soil moisture change.

6. SOIL COMPACTION & SUITABLE COMPACTION MEASUREMENT TECHNIQUES

Please refer to Appendix E for an explanation of Perth Sand Penetrometer (PSP) testing and the

limitations of the PSP test. The clay contained in the site soils is well outside of the limits allowed by

AS1289 6.3.3 for PSP measurement. For this reason, the PSP should not be used for the accurate

measurement of compaction of soils at this site. Measurement of soil compaction is required be

undertaken by a NATA accredited agency using a nuclear densometer to Australian Standard 1289

5.8.1 “Soil compaction and density tests using nuclear density gauge”.

7. SOIL ORGANIC CONTENT

The site soils were determined by inspection not to have a high organic content. Please refer to

Appendix E for an explanation of this test and its significance. It is not expected that the organic

content contained in the site soils will present as a problem when compacting the site soils.

Page 6: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

6

8. VISUAL IDENTIFICATION OF ASBESTOS, HYDROCARBON & UNCONTROLLED FILL

Please refer to Appendix E for an explanation of these materials. The economic activities supported at

the site do not appear to have ever included any commercial activities associated with the

manufacture or handling of asbestos cement products. No surface or buried asbestos, hydrocarbon

contamination or uncontrolled fill was observed during the course of the investigation.

9. BEARING CAPACITY AND SETTLEMENT

It is not expected that the native soil type will achieve the stipulated requirement that the slab

installation site shall have an allowable bearing capacity of not less than 100kPa. To achieve the

required bearing capacity BCE recommend the placement of 200mm of engineered fill (Class A road

base or MRWA basecourse quality gravel) between the slab and the native soil.

Provided the earthworks are completed in accordance with recommendations provided in this report

the finished foundation surface will have an estimated maximum allowable bearing pressure of

125kPa. This recommendation is based on a Factor of Safety of 3 against bearing capacity failure

when the soils are compacted to 95%MMDD. Total and differential settlements under the

recommended maximum bearing pressures would generally be anticipated to be less than 20mm and

10mm respectively. The design of site drainage to ensure that foundation soils are kept dry will be

important to achieving the stipulated bearing pressures.

If the City of Greater Geraldton wishes to verify the bearing capacity of the completed earthworks as

exceeding the required 100kPa BCE can arrange a plate load test to be completed. A plate load test

will physically measure the bearing capacity of the finished soil surface.

10. SUITABILITY OF SITE MATERIAL FOR USE AS STRUCTURAL FILL AND

RECOMMENDED COMPACTION METHOD

BCE do not see any issues with achieving compaction of native site materials provided compaction is

undertaken in accordance with recommendations provided in Appendix D of this report. BCE do not

recommend that the site materials be used as structural fill. BCE recommend that the required

engineered fill be imported. Class A road base or MRWA basecourse quality gravel is recommended

to be imported as engineered fill. Please provide a sample of the material proposed to be imported to

BCE (prior to carting to site) who will advise if the material will be satisfactory. Recommended

compaction equipment is a motorised 20t pad foot vibe roller and a motorised 20t flat drum vibe roller.

11. SOIL EXCAVATION CHARACTERISTICS AND CUT AND FILL SLOPE STABILITY

CRITERIA

The angle of repose of the site materials is approximately 32 degrees. Excavations for foundations

may be required using standard earthmoving equipment. Where shoring will not be provided to

excavations it is suggested that excavation batters be sloped at an angle of 1V:3H in soil to prevent

collapse of trench walls. Fill slopes should not be steeper than 1V:3H.

12. EROSION AND SEDIMENT CONTROL

The soils at the site will be susceptible to scouring from medium to high velocity overland water flow

or strong winds. The materials contain fine particles which are easily transported by water and wind

movement. To avoid scouring, embankments receiving flow from significant catchments, should be

paved or otherwise armoured. Provision to stop airborne silt and sand shall be taken during windy

periods during construction by water suppression, until the soils in the work area can be stabilised.

Page 7: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

7

It is expected that the soils around the slab may get boggy, especially when wet, under truck

movements. To achieve a trafficable surface around the slab BCE recommend the placement of

200mm of engineered fill (Class A road base or MRWA basecourse quality gravel) over the surface of

the compacted native site soils in traffic areas.

13. SUITABLE RETAINING OPTIONS

Earth retaining systems shall be designed in accordance with AS4678. Any conventional form of

retaining system designed in accordance with AS4678 will be suitable at the site and will perform well.

BCE would be please to supply certified retaining options if requested.

14. WIND CLASSIFICATION

In accordance with AS1170.2 the site is classified as Region B. The Terrain Category suggested for

the location is Terrain Category 2.

15. EARTHQUAKE

In accordance with Australian Standard AS 1170.4 – 2007 the design seismic hazard factor Z for a 1

in 500-year earthquake event in the project area is 0.09. The Subsoil class of Ce may be assumed.

16. RECOMMENDED PROCEDURE TO COMPLETE SITE WORKS FOR FOOTING

Please refer to Appendix D for the recommended procedure to complete site works in preparation for

footing construction.

17. RECOMMENDATIONS FOR THE CONSTRUCTION AND MAINTENANCE OF SITE

DRAINAGE

It is expected that soil drainage through the clayey sand at the site will be slow. Surface drainage shall

be designed and constructed to avoid water ponding against or near the slab. The ground in the

immediate vicinity of the perimeter footing shall be graded to fall 100 mm minimum away from the

footing over a distance of 3m. The design of site drainage to ensure that foundation soils are kept dry

will be important to achieving the stipulated bearing pressures.

SCOPE & LIMITS OF GEOTECHNICAL INVESTIGATION

This report presents the results of a geotechnical investigation prepared for the purpose of this

commission. The data and advice provided herein relate only to the project and structures described

herein.

The advice tendered in this report is based on information obtained from the investigation locations

tests points and sample points and is not warranted in respect to the conditions that may be

encountered across the site at other than these locations. It is emphasised that the actual

characteristics of the subsurface materials may vary significantly between adjacent test points and

sample intervals and at allocations other than where observations, explorations and investigations

have been made. Subsurface conditions, including groundwater levels and contaminant

concentrations can change in a limited time. This should be borne in mind when assessing the data.

It should be noted that because of the inherent uncertainties in subsurface evaluations, changed or

unanticipated subsurface conditions may occur that could affect total project cost and/or execution.

BCE does not accept responsibility for the consequences of significant variances in the conditions and

the requirements for execution of the work.

Page 8: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

8

Trusting that this meets with your requirements, should you have any further queries, please do not

hesitate to contact the undersigned on (08) 9964 5459.

Yours faithfully

Lester Smith

Engineering Manager

Attachment: Appendix A to E.

Page 9: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

9

Appendix A: Test Pit Locations.

Page 10: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

10

Appendix B: Photographs of site.

Figure 1: Photograph showing proposed slab location.

Figure 2: Material excavated from Test Pit 1.

Page 11: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

11

Figure 3: Material excavated from Test Pit 2.

Page 12: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

12

Appendix C: Soil Test Certificates.

Page 13: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

13

Page 14: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

14

Page 15: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

15

Page 16: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

16

Page 17: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

17

Page 18: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

18

Appendix D: Recommended Procedure to Complete Site Works for Slab.

The following method of work is recommended to prepare the foundation soil for the construction of

the concrete civils.

1. Earthworks shall be carried out in accordance with the principles set out in AS3798-2011.

2. Prior to the commencement of any excavation works all buried services in the area shall

be located. BCE are not aware of any buried services currently in the area.

3. The level of the base of the new concrete slab and leachate collection bunker should be

established on site. The native soil to 0.2m depth below this level shall be excavated and

carted from site. Care should be taken not to disturb the native soil at the base of the

excavation.

The base of the excavations shall be conditioned with moisture and given a minimum 15

passes with a motorised 20t pad foot vibe roller followed by a minimum 15 passes with a

motorised 20t flat drum vibe roller to achieve the required compaction. At the end of the

rolling the soil shall be proof rolled with the flat drum roller. The soil should not deflect or

heave under the weight of the roller as the roller passes over the soil. This will indicate

that the soil is ready for compaction testing.

The compaction of the floor of the new concrete slab and leachate collection bunker

excavation shall be confirmed at 95% modified maximum dry density in accordance with

AS1289 to a depth of 300mm below the finished surface. Testing frequency shall be 4

tests over the area of the new concrete slab and leachate collection bunker with sites

chosen randomly across the site. Compaction testing is required be undertaken by a

NATA accredited agency using a nuclear densometer to Australian Standard 1289 5.8.1

“Soil compaction and density tests using nuclear density gauge”.

The results are required to indicate that the compaction of the material is a minimum of

95% modified maximum dry density in accordance with AS1289. Should the compaction

of soil be found to be less than these requirements, the material will be required to be

recompacted, until compaction requirements are achieved.

The foundation material shall achieve dry back of 70% before applying the recommended

200mm subbase fill layer. Two dry back tests across the slab site shall be undertaken by

a NATA accredited agency.

4. Following rolling and testing of the foundation soil layer approved subbase material (Class

A crushed rock road base or MRWA gravel is recommended) shall be placed in a layer

not exceeding 250mm thick, compacted and tested.

If crushed rock is the preferred fill material the crushed rock shall conform to the Main

Roads Specification 501 “PAVEMENTS” which stipulates that the crushed rock shall have

a Soaked CBR (96%MDD & 100%OMC) of 100% minimum and a linear shrinkage not

exceeding 2%.

If gravel is preferred fill the gravel material shall conform to the Main Roads Specification

501 “PAVEMENTS” which stipulates that the gravel shall have a Soaked CBR (96%MDD

& 100%OMC) of 80% minimum and a linear shrinkage not exceeding 2%.

Page 19: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

19

Prior to placing any imported subbase, the City of Greater Geraldton shall provide a

sample of the material to the BCE Engineer, who will advise immediately of the materials

suitability. Material shall not be carted to site without the written approval from the BCE

engineer.

5. The subbase shall be placed in layers not exceeding 250mm. The compaction of the

subbase layer shall be confirmed at minimum 95% modified maximum dry density in

accordance with AS1289 to a depth of 150mm below the finished surface. Testing

frequency shall be four tests over the slab area. Compaction testing is required be

undertaken by a NATA accredited agency using a nuclear densometer to Australian

Standard 1289 5.8.1 “Soil compaction and density tests using nuclear density gauge”.

Should the compaction of subbase be found to be less than these requirements, the

material will be required to be recompacted, until compaction requirements are achieved.

6. The subbase material shall achieve dry back of 70% before constructing the concrete civil

works. This will ensure that excessive moisture is not trapped in the soil beneath the

concrete so that the soil has good strength. Two dry back tests across the slab site shall

be undertaken by a NATA accredited agency.

7. To reduce the likelihood of differential settlement of the slab, compaction results will also

require uniformity across the site, and should be referred to the Engineer if results are

found to vary markedly across the site.

8. Given the underlying silty sand soil type, attention will be required to be given to site

drainage design to ensure that stormwater is shed away from the constructed slab and

does not ingress the soil beneath the slab. Recommendations are provided in the

geotechnical report for stormwater management.

9. It is expected that the soils around the slab may get boggy, especially when wet, under

truck movements. To achieve a dry weather trafficable surface around the slab BCE

recommend the placement of 200mm of engineered fill (Class A road base or MRWA

basecourse quality gravel) over the surface of the compacted native site soils in traffic

area.

10. BCE would be pleased to provide compaction testing services and provide NATA

endorsed compaction test certificates if requested to do so. Please call BME Laboratory

on 99211878 and they will complete the required NATA accredited compaction test using

a nuclear densometer to Australian Standard 1289 5.8.1 “Soil compaction and density

tests using nuclear density gauge” and dry back testing.

11. Certification by BCE that the completed earthworks at the site have achieved the required

allowable soil bearing capacity and site classification will rely on the presentation by the

City of Greater Geraldton of fill material, compaction and dry back NATA accredited test

results to BCE for each layer of the earthworks construction, prior to the commencement

of pouring concrete, which meet the above requirements.

12. BCE can also confirm the final pad bearing capacity by plate load test if required.

Page 20: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

20

Appendix E: Explanation of Materials Tests Used in This Report.

1. EXPLANATION RESULTS OF LABORATORY MATERIALS TESTING

Particle Size Distribution (PSD), Atterberg Limit & Unified Soil Classification Symbol (USC)

Testing

The particle size distribution of a material is determined by screening a material over sieves and

calculating the mass passing each. The effect of grading on density, internal friction (stability when

wet) and permeability justifies its use as an indicator of likely performance. Particle size distribution

tests were completed in accordance with Test Method AS1289 3.6.1.

Atterberg Limits are conceptual limits when it may be considered a material proceeds through a semi

solid, plastic and liquid states as its moisture increases. These limits are determined using empirical

procedures in the laboratory. The consistency limits are related to the type and amount of clay in a

material. The objection to material with a high clay content is that clay increases in volume and

decreases in strength with increase in moisture content. The volume change tends to destroy the

mechanical interlock and reduce internal friction and stability and results in inferior performance.

Atterberg Limit tests were completed in accordance with Test Methods AS1289 3.9.1, AS1289 3.2.1,

AS1289 3.3.2 & AS1289 3.4.1.

The Unified Soil Classification Symbol (USC) symbol for the site soils was determined in accordance

with AS1726, Table 9 & 10. The silt / clay fraction of the sample is the fraction passing the 75micron

sieve. As a guide, usually soils are preferred for foundation material which do not contain more than

5% fraction passing the 75micron sieve as the silt and clay gives the soil poor strength characteristics

when the soil becomes wet.

Maximum Dry Density / Optimum Moisture Content

Method AS 1289 (5.2.1) Soil compaction and density tests – Determination of the dry density/moisture

content relation of a soil using modified compactive effort has been used to determine the maximum

modified dry density (MMDD) of the soil samples.

Moisture Content

Test Method AS 1289 2.1.1 Soil moisture content tests – Determination of the moisture content of a

soil – Oven drying method (standard method) has been used to determine the moisture content of the

soil samples.

California Bearing Ratio (CBR) Test

The California Bearing Ratio (CBR) Test was originally devised to provide a method of comparing

natural granular materials and crushed rock base and subsequently developed as a means of

assessing subgrades for pavement design purposes. The CBR is a strength test which describes the

effort of a standard piston to penetrate a compacted confined soil specimen. The results are

expressed as a ratio of the loads to cause the same penetration in a standard crushed rock material.

The CBR is an empirical value and does not accurately relate to any of the fundamental properties

governing material strength. Since the material in the test is predominantly subject to shear

deformation, the test can be regarded as an indirect measure of the shear strength. The test has been

successfully used over a long period of time and for a wide range of conditions.

Page 21: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

21

Where soils may be affected by moisture a soaked CBR test is completed. This test provides an

indication of material strength when then the specimen is saturated. An Unsoaked CBR test indicates

material strength at optimum moisture content, or an unsaturated state.

As a reference, Main Roads Specification 501 “PAVEMENTS” table 501.09 stipulates that for gravel

basecourse, suitable for all pavements except freeways and controlled access highways, the Soaked

CBR (96%MDD & 100%OMC) shall be 80% minimum.

The City of Greater Geraldton (CGG) land development guidelines stipulate that subgrade shall have

a soaked CBR exceeding 7% and a PI less than 15. Generally, for gravels (basecourse) a soaked

CBR of >80 is considered good and for sands (subgrade) a soaked CBR of >20 is considered good.

Test Method AS 1289 (6.1.1) Soil strength and consolidation tests – Determination of the California

Bearing Ratio of a soil – Standard laboratory method for a remoulded specimen has been used. The

test has been conducted on soils compacted per AS1289 5.2.1. The subgrade samples were

modelled at 95% maximum modified dry density and 100% optimum moisture content. This is in line

with most land development guidelines. A 4.5kg surcharge was placed on the samples during

modelling to replicate weight of overlying layers which occur in pavement construction.

Soil Reactivity Tests

The test completed to determine soil reactivity AS 1289 7.1.1 Soil reactivity tests – Determination of the

shrinkage index of a soil – Shrink-swell index is the preferred method prescribed in AS2870-2011

Residential slabs and footings to calculate expected ground surface movement and classify the site

based on soil reactivity.

Permeability

Permeability is a measure of the rate at which fluid passes through a porous medium. The

permeability of slow-moving water through a soil varies with, the ratio of voids in the soil (soil

compaction), the shape and arrangement of the particles contained in the soil (the particle size

distribution and silt and clay fraction contained in the soil) and the degree of saturation of the soil.

There are a few methods to measure soil permeability but essentially these can be broken into either

Laboratory tests or Field tests.

Laboratory tests are completed on soil samples remoulded in the laboratory under controlled

conditions. A falling head permeability AS1289.6.7.2 laboratory test was completed on soil samples.

Soils with permeability coefficients 10-1 - 10-4m/s are generally considered as quite permeable and

generally comprise sands and gravels. For drainage purposes these soils are well regarded. Soils

with permeability coefficients 10-4 - 10-6m/s are generally considered as poorly drained and comprised

of very fine sands, organic and inorganic silts, mixtures of sand and silt and clay. Soils with

permeability coefficients 10-6 - 10-9m/s are generally considered practically impervious.

2. EXPLANATION RESULTS OF NUCLEAR DENSOMETER TESTING

Nuclear Densometer Testing

Measurement of soil compaction has been undertaken using a nuclear densometer to Australian

Standard 1289 5.8.1 “Soil compaction and density tests using nuclear density gauge”.

Page 22: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

22

3. EXPLANATION AS2870 – 2011 SITE CLASSIFICATION FOR THE SITE

The ground surface movement has been calculated by the preferred method prescribed in AS2870-

2011 using laboratory tests for soil reactivity AS1289.7.1.1 Shrinkage Index of a Soil completed on

samples. The expected surface movement for each site has been classified in accordance with Table

2.1 in AS2870-2011. For reference:

1. AS 2870-2011 stipulates that sites which experience between 0 – 20mm expected surface

movement may be classified as Class “S”. AS2870 –2011 defines these sites as slightly

reactive clay sites but stable.

2. AS 2870-2011 stipulates that sites which experience between 20 – 40mm expected surface

movement may be classified as Class “M”. Essentially AS2870 –2011 considers this to be a

moderately reactive site.

3. AS 2870-2011 stipulates that sites which experience between 40 – 60mm expected surface

movement may be classified as Class “H1”. Essentially AS2870 –2011 considers this to be a

highly reactive site.

The calculation of expected surface movement does not make any allowance for movements caused

by soil densification settlement. Calculations assume that the site is compacted to 95% modified

maximum dry density in accordance with AS1289, and that the foundation soils are protected from

excessive moisture ingress. Site drainage design shall ensure a stable moisture content regime in the

soils near and beneath the building envelope.

4. EXPLANATION OF SOIL COMPACTION & SUITABLE COMPACTION MEASUREMENT

TECHNIQUES

To avoid the likelihood of settlement, it is required by the Building Code of Australia and Australian

Design Standards that for domestic structures, soils shall be compacted to 95% MMDD in accordance

with AS1289. It is understood that soils at this level of compaction will resist further settlement, under

residential construction loading, and hence provide a reliable and sound foundation.

In quartzose sand soils which contain less than 5% silt often the measurement of eight blows per

300mm depth of penetration using a 16 mm diameter 9.0 kg Perth Sand Penetrometer (PSP) in

accordance with AS1289 6.3.3 is an indication that the sand exists at 95% modified maximum dry

density. For this reason, eight blows per 300mm depth of penetration using a PSP is the compaction

requirement, which most local authorities stipulate a building pad shall achieve prior to building

commencement. AS 1289 6.3.3 provides the specific method for completing PSP tests. AS1289 6.3.3

stipulates that the soil for PSP measurement shall be:

1. Non-cohesive.

2. Not contain particles greater than 2mm diameter.

Such material is classified as non-cohesive sand.

Blacktop suggest that a useful guide for identifying non-cohesive sand shall be the amount of silt and

clay contained in the sample. Silt and clay content is indicated by the fraction of sample passing the

75-micron sieve. If the material exceeds 5% passing the 75micron sieve, then the material should be

considered cohesive. Such material, when dry, will cement together in lumps when excavated. The

PSP cannot accurately measure the compaction in soils which exceed this silt and clay content.

Page 23: BLACKTOP CONSULTING ENGINEERS - der.wa.gov.au

23

5. EXPLANATION OF SOIL ORGANIC CONTENT

When materials contain greater than 2% organic matter compaction can be very difficult to achieve.

2% of decomposed vegetation is a considerable quantity in soil and it can have a significant effect on

the physical characteristics of the soil when it is mixed through the soil. Organic matter which has

entered the soil from stands of native Acacia vegative species tends to suppress the ability of soils to

take on moisture and hence can make the process of soil moisture conditioning and the achievement

of 95% MMDD compaction very difficult. BCE experience in the past suggests that if the material

contains greater than 2% organic matter this could be grounds to replace the material or to entertain a

compaction concession in the engineering specification.

6. EXPLANATION OF ACID SULFATE SOILS (ASS)

The classification of ASS includes both actual acid sulfate soils (AASS) and potential acid sulfate soils

(PASS). AASS are soils that are generating acidity, whereas PASS are soils that have the potential to

generate acidity. ASS are soils containing naturally occurring, fine-grained metal sulfides typically

pyrite (FeS2), formed under saturated, anoxic/reducing conditions. They generally occur in

Quaternary (1.8 Ma – Present) marine or estuarine sediments, predominantly confined to coastal

lowlands (elevations generally below 5mAHD). Within these sediments, the majority of soils that

present an environmental risk are generally confined to Holocene aged material (<10 000 years).

Where these materials have oxidised, they commonly have a mottled appearance (orange and yellow

discolouration) due to the presence of oxidised iron minerals. Although soils described above

represent typical conditions where ASS occurs, the presence of ASS materials is not limited to these

soil types. In Western Australia, ASS materials have been identified in other soil types such as

leached sands and silts. Accordingly, for areas where no data is available, the extent of ASS materials

should be established through field investigations.

When PASS are disturbed, either by excavation or lowering of the water table below natural seasonal

levels, sulfides present are exposed to air, allowing oxidisation and consequently, the formation of

sulfuric acid (H2SO4). AASS are capable of generating acidity in situ in their natural state; disturbance

is not required for acidic discharges to develop. As a result of the presence of AASS, or the oxidation

of PASS, surrounding land (soil) and nearby waterways may become acidic (pH <6.5). Under acidic

conditions, metals such as aluminium (generally at pH <4.5) and iron, as well as trace heavy metals

(including arsenic), become more mobile in the environment and can be taken up by infiltrating

waters. As a result, surface and/or groundwater concentrations of these metals may reach

concentrations which have the potential to cause acute or chronic toxicity to sensitive terrestrial and

aquatic plants and animals. Acidic conditions generated by ASS can also corrode concrete and steel

(pipes, bridge abutments, underground services, and other infrastructure) and can result in the rapid

deterioration of asphalt surfaces where they overlie AASS or PASS.

7. EXPLANATION OF VISUAL IDENTIFICATION OF ASBESTOS, HYDROCARBON &

UNCONTROLLED FILL

Asbestos cement building products were used up until 1987. If buildings at the site pre-dated 1987

there is a chance that building materials containing asbestos were brought to site.


Recommended