1
BLM GUIDANCE FOR WILDERNESS STUDY AREAS: Comparing the Interim Management Policy with Manual 6330
BLM’s policy Manual 6330 regarding the management of wilderness study areas (WSAs) replaces the Interim Management Policy for
Lands under Wilderness Review (IMP). Although the two policy documents differ quite a bit in the way they are structured, the
following provides is a side by side comparison of most pertinent issues in both manuals. Note that not every issue was covered by
both manuals.
Overall, the new Manual 6330 is more aggressive in terms of monitoring and protection for WSAs. BLM’s concept with this manual
was to address the fact that WSA designations are not really working out to be “interim” (since many of them have been in existence
for decades), which led to the title change and some of the differences in the approach. The stronger general direction is set out as:
“BLM’s policy will protect the wilderness characteristics of all WSAs in the same or better condition than they were on October 21,
1976 (or for Section 202 WSAs not reported to Congress, the date the WSA was designated), until Congress determines whether or
not they should be designated as wilderness.”
Other improvements of note over the IMP include removing the exception that permitted designation of open ORV play areas in sand
dune or snow areas (although still permitting pre-existing “open” areas that have not been limited or closed in a subsequent decision);
setting a policy to prohibit new discretionary uses that could impair wilderness suitability (instead of just trying to “minimize” them
under the IMP), including where that use could create an expectation of continued use (with the example of creating a mountain bike
trail on an existing primitive route); and specifically requiring that if conditions in a WSA have been approved, then BLM must not
allow them to regress.
The policy that was removed from the IMP that previously provided important support for protecting WSAs was the direction to look
to the “minimum tool” concept as a useful guide for WSA management. Although used mostly for designated wilderness areas, the
minimum tool concept asks whether the proposed action is necessary and how it can be accomplished using methods and equipment
2
that have the least impact on wilderness characteristics. Although it is not prohibited in Manual 6330, we expect BLM will be less
likely to use the minimum tool approach as a reference for evaluating proposed actions in WSAs. Also, this manual does not
contemplate new designations of WSAs, consistent with the agency’s current policy direction.
Contents GENERAL POLICIES ............................................................................................................................................................................... 3
Alaska ..................................................................................................................................................................................................... 3
General Policy ......................................................................................................................................................................................... 3
Non-impairment Standard and Temporary Uses, Facilities and Activities ............................................................................................ 6
Exceptions to Non-Impairment ............................................................................................................................................................... 7
POLICIES FOR SPECIFIC ACTIVITIES ................................................................................................................................................. 8
Cultural and Paleontological Resources ................................................................................................................................................. 8
Grazing .................................................................................................................................................................................................... 9
Fire ........................................................................................................................................................................................................ 12
Lands Actions: Disposals, use authorizations, rights-of-way, access, and withdrawals ...................................................................... 17
Oil and Gas (includes geothermal, oil shale and tar sands) .................................................................................................................. 21
Hardrock Mining ................................................................................................................................................................................... 27
Coal ....................................................................................................................................................................................................... 31
Recreation ............................................................................................................................................................................................. 33
Soil, Air and Water ............................................................................................................................................................................... 44
Vegetation ............................................................................................................................................................................................. 47
Visual Resource Management .............................................................................................................................................................. 52
Wild Horse and Burros ......................................................................................................................................................................... 53
Wildlife ................................................................................................................................................................................................. 56
3
GENERAL POLICIES
Alaska Issue IMP WSA Manual 6330 Implications
Applicability
of the
policies to
Alaska
“Future wilderness inventories of public
lands administered by the BLM in Alaska
will be conducted pursuant to Section
1320 of ANILCA. Special provisions in
ANILCA for the interim management of
future WSAs in Alaska will be developed
at the time wilderness inventories area
allowed. Pending further policy guidance
from the Secretary of the Interior,
wilderness inventories and the
identification of WSAs subject to an IMP
in Alaska under the provisions of Sections
201 and 202 of FLPMA are not to be
undertaken.”
“[Manual 6330 does not] apply to Alaska
outside of the Central Arctic
Management Area WSA designated
under the authority of Sections 1001 and
1004 of [ANILCA] and which is
managed pursuant to all relevant sections
of ANILCA.” §1.1
The WSA Manual is
generally inapplicable to
Alaska.
General Policy Issue IMP WSA Manual 6330 Implications
Designation
of new
WSAs
“Continued evaluation of lands as
wilderness can be considered in the future
under Section 202 of FLPMA.”
The Manual clarifies that prior to the
2003 settlement agreement with Utah, it
designated Section 202 and 603 WSAs
under FLPMA. §1.1
Although BLM does not
expressly close the door to
the future designation of
WSAs, it is implied in this
manual and elsewhere that it
is not currently designating
WSAs, but is identifying
and designating “lands with
wilderness characteristics”
4
under FLPMA and Manuals
6310 and 6320.
Management
and boundary
adjustments
to WSAs
“The BLM’s management policy is to
continue resource uses on lands under
wilderness review in a manner that
maintains the area’s suitability for
preservation as wilderness. The IMP will
remain in effect on all congressionally
mandated WSAs until Congress acts on
the Secretary’s recommendations. Areas
identified as WSAs under Section 202 of
FLPMA will receive interim management
protection upon designation as a WSA.
[Section 202 WSAs] subsequently found
to be nonsuitable for wilderness
designation may be released from interim
management by the BLM State Director
30 days after approval of the land-use
plan.”
“The BLM’s Policy will protect the
wilderness characteristics of all WSAs in
the same or better condition than they
were in October 21, 1976 (or for Section
202 WSAs not reported to Congress, the
date the WSA was designated), until
Congress determines whether or not they
should be designated as wilderness.”
§1.6(B) (emphasis added).
“FLPMA required that the reports on the
Section 603 WSAs be sent to the
President by October 21, 1991, and to
Congress by October 21, 1993. Section
202 WSAs designated through BLM’s
land use planning process prior to the
1993 report were forwarded to Congress.
Section 202 WSAs designated
subsequent to the 1993 report were not
forwarded to Congress. For those
Section 202 WSAs created after the
1993 Report to Congress, the BLM
may, through land use planning,
adjust the status of and management
standards associated with those post-
1993 Section 202 WSAs. §1.6(A)(2)
Boundaries of 202 WSAs established
through a RMP and not included in the
1993 Reports may be adjusted through a
subsequent RMP process. §1.6(B)(4)
The Manual clarifies that
WSAs will be protected in
the same or better condition
than either Oct. 1976 or the
day they were designated.
The Manual now
differentiates between 202
WSAs that were included in
the 1993 Report to Congress
and those not reported to
Congress, allowing for
boundary and management
adjustments to only those
202 WSAs not in the 1993
Report.
5
Monitoring
Alternate surveillance schedules for any
WSA that could more effectively be
monitored less frequently than once per
month can be used if approved by the
State Director. In the absence of an
approved alternate surveillance schedule,
the minimum standard of surveillance of
once per month shall remain in effect.”
“Alternative monitoring schedules must
specify the frequency of ground or air
monitoring, the resources required to
sustain the schedule, and a justification for
placing monthly monitoring with the
alternative schedule.”
Virtually the same. See §1.6(B)(1)(b) Manual 6330’s monitoring
requirements for WSAs are
the same as the IMP.
New
Discretionary
Uses
Minimize the establishment of new
discretionary uses that would be
incompatible with possible wilderness
designation, even if uses would not
exceed the non-impairment standard.
Policy is not establishing new
discretionary uses in WSAs that would
impair their suitability. No discretionary
activities should be authorized that would
create an expectation of continued use,
thereby impairing the suitability of the
WSA for designation as wilderness.
Gives the example of creating a mountain
biking route on an existing primitive
route, where that use may preclude
potential designation of the area as a
wilderness even if there is no new
surface disturbance. §1.6(B)(5)
Manual 6330 establishes a
stronger policy than the IMP
for new discretionary uses
prohibiting these uses if they
impair wilderness
suitability, including those
that create an expectation of
a continued use, even if it
does not, in and of itself,
violate the non-impairment
mandate.
Maintain
Improved
Not addressed in the IMP If wilderness characteristics have
improved since the WSA was designated,
BLM will manage WSAs in
the same or better condition
6
Conditions BLM will not allow actions that would
cause the regression of the WSA to its
condition at its designation date.
Gives the example that if primitive routes
have been closed and rehabilitated, BLM
will not allow them to be re-established.
§1.6(B)(6)
at the time they were
designated and will not
allow them to be regress
beyond a better state if
conditions do improve.
Minimum
Tool Concept
Discusses the minimum tool concept as
useful as a guide for WSA management,
even though it is used mostly for
designated wilderness areas. The
minimum tool concept asks whether the
proposed action is necessary and how it
can be accomplished using methods and
equipment that have the least impact on
wilderness characteristics.
Gives the example of alternatives for the
development of a water guzzler for
bighorn sheep in a WSA.
Not addressed. Unlike the IMP, Manual
6330 does not mention the
minimum tool concept, even
as a useful guide. BLM will
likely move away from this
concept when discussing
actions in WSAs.
Non-impairment Standard and Temporary Uses, Facilities and Activities Issue IMP WSA Manual 6330 Implications
“The use, facility, or activity must be
temporary. This means a temporary use
that does not create surface disturbance or
involve permanent placement of facilities
may be allowed if such use can easily and
immediately be terminated upon
wilderness designation.”
Essentially the same as the IMP except
adds that:
“A chronic, repeated short-term use
does not meet this definition of
“temporary.”
“Uses, activities, or facilities that
create a demand for uses that would
be incompatible with wilderness
The Manual 6330 is a
slightly stronger standard
than the IMP with regard to
uses, facilities and activities
in WSAs.
7
management also do not meet the
definition of temporary.” §1.6(C)(1).
Prohibits surface disturbance of WSAs
unless activities would be allowed in
Wilderness Areas (e.g. recreational
hiking, pack stock, and livestock grazing).
Essentially the same as the IMP except
Manual 6330 adds an example of
impairing/surface disturbing use to
include landing fixed winged aircraft
unless on an existing airstrip or primitive
route open to other motorized uses.
Specifically disallows
backcountry plane landings
unless on existing airstrips
or primitive routes open to
other motorized uses.
Exceptions to Non-Impairment Issue IMP WSA Manual 6330 Implications
Emergencies
Exception
Exception for actions to prevent loss of
life or property and conducted in a manner
that least impairs wilderness suitability.
Contains very similar language to the
IMP except the IMP stated that “[w]ithin
7 days after the emergency action is
completed, a record of the circumstances
and the action taken will be placed in the
WSA case file and a public notification
will be mailed to all interested parties.”
§1.6(C)(2)(a)
In addition, Manual 6330 requires
human-caused impacts from emergencies
be restored as soon as possible after they
occur and at a level as close to or better
than conditions that existed before the
emergency. §1.6(C)(2)(c)
Unlike the IMP, Manual
6330 does not require a
record of circumstances to
be filed and the public
notified within 7 days,
although it does require
BLM to comply with all
NEPA obligations for
emergency actions.
Manual 6330 requires
speedy and quality
restoration after the
emergency action occurs.
Public Safety
Exception
Exception for uses and facilities that are
minimum necessary for public health and
safety.
Adds that action to remediate human-
caused hazards are excepted from the
non-impairment standard and must be
mitigated and the area restored.
However, altering naturally occurring
hazards is not permissible. §1.6(C)(2)(b)
Manual 6330 is more
specific for responding to
safety hazards in WSAs.
8
Valid
Existing
Rights (VER)
Exception
Exception for VERs to be recognized and
managed under the non-impairment
standard if there would be no interference
with the enjoyment of the right or else
manage under the unnecessary or undue
degradation standard.
Requires activities to be managed to
prevent unnecessary impacts to
wilderness characteristics if BLM
determines that the right can only be
exercised through activities that will
cause impairment. WSAs. §1.6(C)(2)(d)
Manual 6330 is slightly
stronger in holding VERs to
an “unnecessary impacts to
wilderness characteristics”
standard rather than the
general “unnecessary or
undue degradation”
standard if impairment
cannot be avoided.
Grandfathered
Uses
Exception
Exception for uses and facilities that were
preexisting to designation. These uses
may continue in the same manner and
degree as on the designation date.
Hardrock mining activities allow for the
logical pace and progression of mining
operations
Same as IMP, except clarifies that
grandfathered uses include only grazing,
mining, and mineral leases and do not
include recreational uses (as stated in
FLPMA). §1.6(C)(2)(e)
Manual 6330 is virtually the
same as the IMP except
clarifies the specific
grandfathered uses that may
occur in WSAs.
Enhancing
Wilderness
Values
Exception
Exception for actions that benefit
wilderness characteristics even though
they might be impairing. Must be done in
the least disturbing manner.
Same as IMP, except Manual 6330
deletes reference to looking at the
original wilderness inventory for baseline
conditions and also deletes the
illustrations of this concept that were in
the IMP (i.e. drift fence, guzzlers).
§1.6(C)(2)(f)
Manual 6330 provides
general guidance for this
exception rather than the
more explanatory approach
taken in the IMP, which
may give BLM more
discretion to apply this
exception.
POLICIES FOR SPECIFIC ACTIVITIES
Cultural and Paleontological Resources Issue IMP WSA Manual 6330 Implications
Inventories
and Research
“Cultural and paleontological resource
inventories, studies, and research
Same as IMP. §1.6(D)(1)
9
involving surface examination may be
permitted if they satisfy the
nonimpairment criteria.”
Grazing Issue IMP WSA Manual 6330 Implications
New
Livestock
Development
Distinguishes between temporary and
permanent developments:
Temporary: must (1) analyze certain
effects on wilderness values, (2) truly
enhance wilderness values, and (3)
satisfy the non-impairment standard.
Permanent: must (1) analyze certain
effects on wilderness values, (2) truly
enhance wilderness values, and (3) are
substantially unnoticeable. Also, must
not require motorized access if the
area were designated as wilderness.
Only approved if non-impairment
standard met, or exception applies.
The standard for applying the
“Enhancing Wilderness
Characteristics” exception in this case
is “if the structure’s benefits to the
natural functioning of the ecosystem
outweigh the increased presence of
human developments and any loss of
naturalness or outstanding
recreational opportunities cause by
the new development.”
NEPA cumulative impacts must be
analyzed.
BLM should consider whether it is
substantially unnoticeable.
Must not require new motorized
access.
No increase in AUMs existing prior
to the new development as result of
the new permanent development.
§1.6(D)(3)(a)(ii)
Manual 6330 sets out a new
standard for when BLM can
say that new livestock
developments “enhance
wilderness characteristics” as
an exception to the non-
impairment standard.
The IMP requires that the
development be substantially
unnoticeable for permanent
structures, whereas Manual
6330 only requires BLM to
consider whether it is
substantially unnoticeable or
not (temporary or
permanent).
Manual 6330 prohibits new
motorized access with any
new structure, temporary or
permanent. IMP only
prohibited motorized access
for permanent structures and
if it would be required if the
area was designated as
10
wilderness.
Manual 6330 has a new
standard that a new
permanent development
cannot increase AUMs.
Salting “In both grandfathered and non-
grandfathered grazing operations, salting
practices may be continued. New salting
locations may be established to improve
the distribution of grazing use as long as
the non-impairment criteria is met.”
Same, except provides the example of
“no vegetation disturbance requiring
restoration would occur at the new site.”
§1.6(D)(3)(b)(i)
Manual 6330 provides a new
example for salting that no
vegetation disturbance
requiring restoration would
occur.
Supplemental
Feeding
“Supplemental feeding may be continued
in grandfathered grazing operations if it
was authorized as part of the operation as
of October 21, 1976. Otherwise,
temporary feeding may only be authorized
under emergency conditions when forage
becomes unavailable through acts of
nature such as a heavy snowfall. Such
temporary feeding may only be allowed in
those cases where BLM has determined
that it satisfies the nonimpairment
criteria.”
Same for grandfathered uses.
§1.6(D)(3)(b)(ii)
Emergency feedings “may only be
allowed for short periods of time while
the emergency exists and until the
livestock can be removed.” Adds
examples of fire and flood to heavy
snowfall. §1.6(D)(3)(b)(iii)
Unlike the IMP, Manual
6330 requires that emergency
feedings only be allowed for
a short period of time until
the livestock can be removed.
Manual 6330 does not
require the feeding to meet
the non-impairment standard
like the IMP, which makes
sense since it is a short term,
temporary exception.
Vegetation
Treatments
Not addressed. If vegetation manipulation was
preexisting to the designation, it may be
maintained by similar treatments as long
as it does not create greater impacts and
achieves the same result.
§1.6(D)(3)(b)(iv)
Manual 6330 has a new
section addressing vegetation
treatments.
Motor
Vehicle Use
Not addressed. Except for pre-designation
authorizations, emergency feedings, or as
specifically authorized by BLM, motor or
Manual 6330 has a new
provision for limiting
motorized vehicle use for
11
mechanical vehicles is restricted to
primitive routes open to the general
public. §1.6(D)(3)(b)(v)
grazing activities.
Changes in
Grazing
Practices
Changes may be allowed in number, kind,
or season of use if, following the
preparation of an EA, the effects are
found to be negligible. Changes cannot
cause declining conditions or trend of the
vegetation or soil and cannot cause
unnecessary or undue degradation of the
lands. The assessment of the proposal
must include an evaluation of the effect on
the following parameters and wilderness
values:
--the natural ecological condition of the
vegetation.
--the visual condition of the lands and
waters.
--erosion.
--changes in the numbers or natural
diversity of fish and wildlife.
--all wilderness values
“Section 603(c) of FLPMA, provides for
the continuation of grazing on lands under
wilderness review, “[p]rovided that in
managing the public lands, the BLM shall
by regulation or otherwise take any action
required to prevent unnecessary or
undue degradation of the lands and their
resources or to afford environmental
protection.” If rangeland within a WSA is
failing to achieve Rangeland Health
Standards, the significant factors
contributing to this failure will be
determined through monitoring and a
review of existing uses. If existing grazing
management practices are found to be a
significant factor in the failure to achieve
standards, new grazing management
practices may be established as needed if
they meet the non-impairment standard or
one of the exceptions.
The NEPA document that authorizes
changes to grazing practices must evaluate,
at a minimum, the following:
watershed function
ecological processes
water quality
habitat quality
non-impairment of wilderness
characteristics”
§1.6(D)(3)(c)
Manual 6330 refers to
rangeland health standards as
the indicator for possible
changes in grazing practices
due to declining conditions if
grazing is a significant factor
in failing to achieve
standards. Grazing can be
modified at that point if
management meets the non-
impairment standard.
Manual 6330 also updates
the minimum factors that
BLM must evaluate when
considering changes to
grazing practices in a NEPA
document.
12
Grazing
Increases
“In order to insure that a proposed increase
in the level of livestock grazing does
not impair an area's wilderness values, the
BLM must quantify those values, as well as
the existing vegetation and associated
resources, and then consider the potential
for impacts to these resources.”
A temporary, non-renewable increase
may be allowed if they meet the non-
impairment standard or exception. If
studying the increase shows that it is
causing impairment, then it will be
decreased or discontinued. §1.6(D)(3)(c)(i)
Manual 6330 applies the
same non-impairment
standard for evaluating
grazing increases, but only
allows for temporary, non-
renewable increases and
requires the allotment to be
studied and uses decreased or
discontinued if studies show
impairment from the
increase.
Grazing
Reductions
The grandfather clause does not freeze
grandfathered grazing uses to the same level
that existed on October 21, 1976. Section
603(c) of FLPMA provides the mandate to
prevent unnecessary or undue degradation
of the lands as it applies to grandfathered
uses. Thus, the grandfather provision will
not prevent implementation of reductions in
authorized use.
Same, but clarifies that grazing “may be
subject to general BLM grazing
management policy. If the rangeland is
failing to achieve standards established
by the BLM, the significant factors that
contribute to those conditions should be
ascertained and temporary or permanent
reductions may be implemented as
needed.” §1.6(D)(3)(c)(ii)
Manual 6330 updates the
IMP to address Rangeland
Health Standards and BLM’s
options if an allotment is
found to be failing.
Fire Issue IMP WSA Manual 6330 Implications
Managing
Fire in
General
BLM will use “caution to avoid
unnecessary impairment of an area's
suitability for preservation as wilderness.
"Light-Hand-On-The-Land" fire
suppression tactics will be used. Fire is a
natural component of many wilderness
ecosystems and fire plans need to give
“The overall goal of managing fire in
WSAs is to allow the frequency and
intensity of the natural fire regime to play
its inherent role in the ecosystem. This
means both allowing fire where
ecosystems evolved in the presence of
fire, and preventing unnatural spread of
Manual 6330 is clearer than
the IMP about BLM’s goals
when managing fire in a
WSA.
Manual 6330 sets out
separate guidance for
13
serious consideration to this fact before
recommending one fire management
technique over another. Resource area
advisors will use the fire plans in making
decisions during emergency fire situations
and prescribed ignitions.”
fire in ecosystems that evolved without
broad-scale fires.”
This goal may be affected by past human
actions (i.e. fire suppression, non-native
invasive grasses), budgets, national fire
management demands, suppression of fire
on adjacent land before it moves into the
WSA, or undesired consequences of
wildfire moving out of the WSA.
§1.6(D)(2)(a)
wildfires and prescribed fires
whereas the IMP leaves it to
the discretion of the fire
plans developed by the
managers.
Wildfires “Emergency fire rehabilitation measures
will continue to be carried out under
guidelines in Handbook H-1742-1 and
Manual Section 1742. Efforts should be
made to rehabilitate any impacts created
by suppression activities prior to releasing
fire crews and associated equipment
following fire containment.”
“Wildfires can be considered emergencies
and, as such, management response to a
wildfire falls under one of the exceptions
to the non-impairment criteria.
Nevertheless, the non-impairment criteria
will be met to the extent practical. This
means using "minimum impact
suppression tactics" or "light hand on the
land" suppression techniques wherever
possible, while providing for the safety of
firefighters and the public and meeting fire
management objectives.”
“Emergency stabilization, rehabilitation,
and restoration of the wilderness resource
created by impacts from wildfires must
satisfy the non-impairment criteria unless
an exception applies. These activities will
be more intensive:
where the effects of the fire were
greater than would occur in an area
where fire already plays its natural
The IMP does not distinguish
between wildfires and
prescribed fires. Manual
6330 is clearer than the IMP
about suppressing wildfires,
stabilization and restoration
methods.
14
role on the landscape
in ecosystems that evolved without
broad-scale fire
for fires whose effects (even within
the natural range) pose an
unacceptable risk to life, property,
or resources outside the WSA
Where wildfires have been managed for
resource benefits, most stabilization,
rehabilitation, and restoration activities are
expected to be limited to the impacts
caused by direct management actions or to
prevent the spread of exotic vegetation.
These activities will not be used to
establish, or re-establish, conditions not
provided for in sections 1.6.D.8
[vegetation] or 1.6.D.11 [wildlife] of this
manual.” §1.6(D)(2)(b)
Prescribed
Fires
Does not specifically discuss prescribed
fires.
“Use of prescribed fires in WSAs is
limited to instances where this use meets
the non-impairment standard or one of
the exceptions, such as to clearly protect
or enhance the land's wilderness
characteristics. The BLM may utilize
prescribed fire in WSAs where the
natural role of fire cannot be returned
solely by reliance on wildfire or where
relying on wildfires might create
unacceptable risks to life, property, or
natural resources outside the WSA.”
“Prescribed fire planning for WSAs must
take into account protection of cultural
The IMP does not distinguish
between wildfires and
prescribed fires and does not
specifically discuss
prescribed fire like Manual
6330.
15
resources.” §1.6(D)(2)(c)
Fuel
Treatment
Does not discuss fuel treatments. In advance of prescribed fire. In some
instances, fuel treatment may be necessary
to protect site-specific resources in
advance of a prescribed fire to prevent the
loss of those resources. This necessity must
be clearly demonstrated in the prescribed
fire plan.
Replacement for wildland fire. Pre-fire
treatment used to replace either type of
wildland fire (sections b and c, above) is
only allowed in WSAs where it meets the
non-impairment standard or one of the
exceptions. Due to their controversial
nature and the complexities of analyzing
the effects of these treatments on the non-
impairment criteria, more extensive NEPA
analysis (e.g. an EIS) including public
involvement may be required when fuel
treatments are proposed for use as a
replacement for wildland fire. The policy
in 1.6.D.8.b.iii [restoration] must be
satisfied. Fuel treatments may be permitted
under the restoration or public safety
exceptions to the non-impairment standard
when:
A. prescribed fire in the WSA will
inevitably cause unacceptable risks
to life, property, or natural
resources outside the WSA; or
B. natural successional processes have
been disrupted by past human
activity to the extent that
Manual 6330 sets out criteria
for using fuel treatments in
advance or prescribed fire or
as a replacement for wildland
fire and has a preference for
low-intensity, repeated
prescribed fires over pre-fire
treatments. The IMP does not
discuss fuel treatments.
16
intervention is necessary in order to
return the ecosystem to a condition
where natural process can function;
or
C. non-native species have altered the
fire regime so that wildland fires
pose an undue risk to the native
ecosystem.
Conclusive documentation of A, B, or C,
above, must be included in the NEPA
analysis of the proposed action. When fuel
treatment is allowed, the BLM must strive
to achieve the desired conditions through
the least impacting method. Fuel
treatments should not be authorized in a
WSA if the same objectives can be
accomplished by the BLM through fuel
treatments on public lands outside of the
WSA.
Low-intensity Prescribed Fire. Repeated
low-intensity prescribed fires are
preferable in most circumstances where
pre-fire treatment is contemplated, even if
this increases the time and cost of
treatment. §1.6(D)(2)(d)
Earth
Moving
Equipment
“All uses of earth moving equipment
within a WSA require authorization.”
Not specifically addressed. Unlike the IMP, Manual
6330 does not address earth
moving equipment proposed
for use in fire management
activities.
Fire Camps “Priority for placement of large fire camps
should be outside WSAs.”
Not specifically addressed. Unlike the IMP, Manual
6330 does not address fire
17
camps.
Motor
Vehicles &
Mechanized
Equipment
“Use of motor vehicles and mechanical
equipment during mop-up should be
minimized.”
Not specifically addressed. Unlike the IMP, Manual
6330 does not address
motorized vehicles and
mechanical equipment for
mop-up.
Suppression
Methods
“Present suppression methods may be
used, including use of power tools,
aircraft, motorboats, and motorized fire-
fighting equipment while applying "light-
hand-on-the-land" techniques. Existing
fire lookout towers and helispots may be
used and maintained; new ones may be
approved as part of the fire management
activity plan if they are the minimum
necessary for fire suppression in the
WSA.”
Not specifically addressed. Unlike the IMP, Manual
6330 does not address
suppression methods in
detail.
Lands Actions: Disposals, use authorizations, rights-of-way, access, and withdrawals Issue IMP WSA Manual 6330 Implications
Disposals Same as Manual 6330, except for land
exchanges:
“Land exchanges may be made when
BLM receives lands within an area under
wilderness review in exchange for public
lands that are not under wilderness
review. In very limited cases or unique
situations, subject to public review and
prior approval by the Director, exchanges
may be made involving public and non-
Federal lands within WSAs when such
action would significantly benefit
Except as described below, public lands
within WSAs may not be disposed of
through any means, including public
sales, exchanges, and patents under the
Recreation and Public Purposes Act.
Under either of the following two
conditions, lands within WSAs may be
subject to disposal:
i. Disposals may be permitted under
normal BLM procedures for
mining patents.
Both manuals contain the
disposal exception for mining
patents.
Manual 6330 only allows for
the exchange of land that is
either within the same WSA
or among multiple WSAs
with approval by the BLM
Director and if benefiting
wilderness values. This is
much more stringent than the
18
wilderness values and improve wilderness
management potential.
ii. Land exchanges involving public
and non-Federal lands, can occur
when the involved lands are
within the same WSA, or when
they are in two or more WSAs.
These are unique situations,
subject to prior approval by the
BLM Director. The exchange
must benefit wilderness values
and/or improve wilderness
management. Such exchanges
may not result in the elimination
of a wilderness characteristic,
including supplemental values, of
a WSA. §1.6(D)(4)(a)
IMP, which allowed for
exchanges if BLM got land
within a WSA in exchange
for land outside of a WSA or
if the exchange significantly
benefitted wilderness values
and improved wilderness
management potential.
Use
Authorization
“Leases under the Recreation and Public
Purposes Act and leases and permits
under 43 CFR 2920 may be authorized
only if BLM determines that the case in
question satisfies the nonimpairment
criteria and complies with guidance in the
IMP applicable to the type of activity
involved. Any permit or lease issued
under 43 CFR 2920 must contain a
stipulation that if the WSA is designated
as a wilderness area, the lease or permit
may be terminated. Provision regarding
disposition of facilities, structures, and
improvements upon termination will be
included in the stipulations included in the
permit or lease.”
“Any permit or lease issued under 43
CFR 2920 must contain a stipulation that
if the WSA is designated as a wilderness
area, the lease or permit may be
terminated.
Commercial filming may be permitted
under 43 CFR 2920 if it is determined to
meet the non-impairment standard or one
of the exceptions. Commercial filming
permits must stipulate that if the WSA is
designated as a wilderness, the permit
will be terminated.” §1.6(D)(4)(b)
Manual 6330 removes
language about satisfying the
non-impairment criteria as
well as reference to the
Recreation and Public
Purposes Act.
Both have the same language
for a lease stipulation that a
lease may be cancelled if the
WSA is designated as
Wilderness.
Unlike the IMP, Manual
6330 adds language for
commercial filming permits
to meet the non-impairment
standards and to have a lease
19
stipulation that a permit may
be cancelled if the WSA is
designated as Wilderness.
Rights-of-
Way
“Existing rights-of-way may be renewed
if they are still being used for their
authorized purpose. Necessary, routine
maintenance to keep an existing right-of-
way facility in a safe and reliable
condition, and any additional actions
authorized in the original permit, may be
permitted. In such cases, every effort
should be made to comply with the
nonimpairment criteria. Emergency
maintenance or emergency repairs may be
made to protect human health and safety
or to protect wilderness values even if the
activity impairs wilderness suitability.
Such emergency actions must be in
compliance with the policy set forth in
Chapter I.B.12.”
“Existing rights-of-way may be renewed
if they are still being used for their
authorized purpose. When processing an
application for renewal of an existing
right-of-way, consistent with 43 CFR
2807.22(a) and 43 CFR 2887.12, the
BLM should consider new, additional, or
modified terms and conditions to
minimize impacts to wilderness
characteristics. Necessary, routine
maintenance to keep an existing right-of-
way facility in a safe and reliable
condition, as well as any additional
actions authorized in the original permit,
may be permitted.” §1.6(D)(4)(c)
Both manuals allow ROW to
be renewed if still being used
for their authorized purpose.
However, only Manual 6330
states that BLM should
consider new, additional or
modified terms and
conditions to minimize
impacts to wilderness
characteristics when
renewing a ROW.
Both manuals allow for
necessary, routine
maintenance. However,
unlike Manual 6330, the IMP
adds that if maintenance is
authorized, “every effort
should be made to comply
with the nonimpairment
criteria” and allows for
emergency maintenance or
repairs.
Access “In cases of access to non-Federal lands
where the BLM has determined that
application of the nonimpairment standard
would unreasonably interfere with the
enjoyment of the landowner's rights. In
each case, the BLM's decision will depend
A ROW may be approved if non-Federal
lands are surrounded by WSA lands and
an access route exists, but no upgrades
greater than what existed when the WSA
was designated. If upgrading is necessary
to use the inholding as originally
Manual 6330 sets out new
standards for access to non-
Federal lands surrounding by
WSAs and implements major
changes in policies regarding
access to inholdings. As stated
in Manual 6330, “This is a
20
upon the nature of the rights conveyed and
the site-specific conditions involved. The
BLM is required by law to provide such
access as is adequate to secure to the
landowner the reasonable use and
enjoyment of non-Federally owned land
which is completely surrounded or
isolated by public lands administered
under FLPMA. In determining adequate
access, the BLM has discretion to evaluate
such things as proposed construction
methods and location, to consider
reasonable alternatives (trails, alternative
routes, including aerial access, and degree
of development) and to establish such
reasonable terms and conditions as are
necessary to protect the public interest.”
conveyed, then a ROW may be issued
but limited to not cause impairment.
Where non-Federal lands are surrounded
by WSA lands and no access route exists,
a ROW may be granted if it meets the
non-impairment standard or exceptions.
If authorized under an exception, BLM
should select the route and specify
development that causes the least impact
to wilderness characteristics.
If a ROW is authorized for access to an
inholding, BLM should consider
authorizing it for a limited period of time.
The ROW would be terminated if the
WSA is designated as Wilderness. All
proposed ROWs must be reviewed by the
Regional Solicitor. BLM should consider
the possible acquisition of a non-Federal
inholding from a willing owner as an
alternative. §1.6(D)(4)(d)
change from the [IMP], which
stated that in all cases the
BLM was required to provide
reasonable access to
inholdings. The [IMP],
however, did not reflect the
fact that reasonable access is
only required in Alaska, under
section 1323(b) of ANILCA.
Because the provision of
reasonable access does not
apply to public lands managed
by the BLM outside of Alaska,
new access can only be
provided to inholdings within
WSAs outside of Alaska
where it is consistent with
FLPMA’s non-impairment
mandate.
Right-of-
Way
Corridors
“Post FLPMA right-of-way corridors may
be designated on lands under wilderness
review, but they do not contain any rights-
of-way grants within them. However, this
will in no way interfere with the
wilderness review. No new rights-of-way
or expansions of existing rights-of-way
will be approved, except under the criteria
in paragraph 3, above. A right-of-way
corridor is not an authorization, but a
Not specifically addressed. Only the IMP addresses ROW
corridors and allows for them
but BLM still must apply the
criteria in the IMP before
approving the ROW.
21
planning tool. The need for actual rights-
of-way within a designated corridor will
be considered during the wilderness study,
but any recommended rights-of-way
inconsistent with Section C.3, above, will
not be approved, unless Congress decides
not to designate the area as wilderness.
Withdrawals “Existing withdrawals may be renewed if
the withdrawal is still serving its purpose.
No new withdrawals may be made except
withdrawals that can satisfy the
nonimpairment criteria. Withdrawals
transferring land or the administration of
lands to other Federal agencies may be
approved if the land will be managed so
as not to impair its suitability for
preservation as wilderness. Withdrawals
for purposes of resource protection may
be made (except withdrawals from
appropriation under the mining laws in
order to preserve wilderness character), as
long as the intended use satisfies the
nonimpairment criteria.”
“Unless a WSA or portion of a WSA was
“previously withdrawn from
appropriation under the mining laws,
such lands shall continue to be subject to
such appropriation during the period of
review unless withdrawn by the
Secretary under the procedures of section
204 of…[FLPMA]…for reasons other
than preservation of their wilderness
character.” Existing withdrawals may be
renewed if the withdrawal is still serving
its purpose. No new withdrawals may be
made except withdrawals that can satisfy
the non-impairment criteria.”
§1.6(D)(4)(e)
Manual 6330 clarifies that
BLM may continue to
enforce existing mineral
withdrawals for WSAs unless
the withdrawal was done
under FLPMA for reasons
other than preserving
wilderness character.
Unlike the IMP, Manual
6330 does not state that lands
can be withdrawn to transfer
land or management to other
federal agencies so long as
non-impairment occurs.
Oil and Gas (includes geothermal, oil shale and tar sands) Issue IMP WSA Manual 6330 Implications
New Leasing “No new leases may be issued on lands
under wilderness review. This applies to
public lands, including split-estate lands
where Federal mineral estate underlies
non-Federal surface, within the
boundaries of an area under review.”
“New leasing of oil and gas minerals,
including leasing with "no surface
occupancy" stipulations, is prohibited
within WSAs under the Federal Onshore
Oil and Gas Leasing Reform Act of 1987
(30 U.S.C. § 181). This includes split-
estate lands within the boundary of the
Manual 6330 clarifies that in
addition to no new leasing in
WSAs, BLM may have a
setback for leases if the WSA
boundary does not have an
official survey.
22
WSA where Federal mineral estate
underlies non-Federal surface. The BLM
may offer lands for lease up to the WSA
boundary. However, where the exact legal
description of the WSA boundary is not
known due to the lack of an official survey,
leasing should be set back from the WSA
boundary. The setback distance will be
determined by the manager, through the
Management of Land Boundaries Plan
where it exists, and be sufficient to
guarantee that wilderness characteristics of
the lands within the WSA boundary are not
impaired.” §1.6(D)(5)(c)(i)
Pre-existing
Leases
“All pre-FLPMA leases represent VERs,
but the rights are dependent upon the
specific terms and conditions of each
lease, including any stipulations attached
to the lease. Activities for the use and
development of such leases must satisfy
the nonimpairment criteria unless this
would unreasonably interfere with rights
of the lessee as set forth in the mineral
lease. When it is determined that the
rights conveyed can be exercised only
through activities that will impair
wilderness suitability, the activities will be
regulated to prevent unnecessary or undue
degradation. Nevertheless, even if such
activities impair the area's wilderness
suitability, they will be allowed to
proceed. A pre-FLPMA lease does not
“Pre-existing mineral leases will be
allowed to be developed according to the
VER conveyed by the specific terms and
conditions of each lease. These rights are
neither absolute nor unqualified, but do
include the right to access different
leasable mineral horizons than were being
tapped at the time of WSA designation
unless the lease specifies otherwise.
Activities for the use and development of
such leases must satisfy the non-
impairment criteria, unless this would
unreasonably interfere with rights set forth
in the mineral lease. Development of pre-
existing leases may be subject to terms and
conditions to minimize impairment of
wilderness characteristics, including:
A. use of best management practices. [e.g.
relocation of pad, no blading of access
Unlike the IMP, Manual
6330 does not distinguish
between pre-FLPMA and
post-FLPMA leases. Manual
6330 also sets out example
terms and conditions that the
lessee may have to comply
with before development can
occur.
23
carry with it a VER to obtain access to the
lease boundaries across Federal land and,
in the absence of "grandfathered" uses,
access may not be granted if it would
violate the nonimpairment standard.”
Post-FLPMA Leases Issued Prior to the
Issuance of the Interim Management
Policy. Regardless of
the conditions and terms under which
these leases were issued, there are no
"grandfathered" uses inherent in post-
FLPMA leases. Activities on post-
FLPMA leases will be subject to a special
wilderness protection stipulation. If there
is already production on any lease issued
in this period, it would be allowed to
continue in the least impairing manner.
Increases in production or production
facilities would not be allowed if the
resultant impacts would further impair.
The nonimpairment criteria apply to all
post-FLPMA leases, whether or not a
wilderness protection stipulation was
included in the lease. Proposed activities
on all post-FLPMA leases are regulated
under the nonimpairment standard at the
time the lessee desires to start any surface-
disturbing activities on the leasehold.
road or well pad, pitless drilling etc.
See manual for other examples].
B. standard practices such as blading or
gravelling well pads or access routes
may be suspended until a well is
proven productive.
C. if there is no legal access to a pre-
existing lease, and that lease is entirely
within a WSA and not contiguous with
any part of the WSA boundary, the
lease may not be developable since: 1)
rights of access across a lease do not
include rights of access to the lease; 2)
such rights of access to a lease must
come in a separate right-of-way
authorization; and 3) no new rights-of-
way will be issued in WSAs for uses
that do not meet the non-impairment
criteria or exceptions described in this
manual.
D. on leases that cross the boundary of a
WSA, the lease rights may be satisfied
without allowing drilling in the WSA,
depending on the proportion of the
leasehold within the WSA.
§1.6(D)(5)(c)(ii)
Suspension
of Lease
Terms
The Secretary of the Interior has the
discretionary authority to direct or assent
to a suspension of the operating and
producing requirements of an oil and gas
Suspension of lease terms may be
requested by lease holders if an
application to conduct operations is
denied because of the potential
The IMP provides more
specific procedures for when
an application for operations
is denied due to potential
24
or geothermal resources lease if it is in the
interest of conservation to do so and when
the specific circumstances involved
warrant such an action.
When the BLM notifies a proponent that
an application to conduct operations is
being denied because of the potential
impairment of wilderness suitability, it
should advise the proponent of the right
to: (1) appeal that denial, (2) request a
suspension of operation, and (3) take such
other actions as appropriate to protect the
rights granted by the lease. It is not
appropriate for the BLM to speculate as to
the potential for suspension since the
specific circumstances involved in each
case will be determining factors in any
decision. However, if the lessees who are
denied the right to conduct operations
because of conflicts with wilderness
review are to be given a reasonable
opportunity to preserve their leases, these
potential conflicts must be identified
promptly during the notice of staking,
application to conduct operations, and
plan of operation. The lessee must also be
promptly notified of the disapproval of the
application.
For leases not encumbered with the
wilderness protection or no-surface-
occupancy stipulations and on
impairment of wilderness suitability as
outlined in paragraphs ii.B or ii.D, above.
The Secretary of the Interior has the
discretionary authority to direct or assent
to such a suspension of the operating or
producing requirements of a lease if it is
in the interest of conservation to do so
and when the specific circumstances
involved warrant such an action, such as
until congressional decision on the
wilderness status of the area is made. §1.6(D)(5)(c)(iii)
impairment of wilderness
suitability and when a
suspension might be in order.
25
which an application for an otherwise
acceptable plan of operations was denied
for wilderness or endangered species
considerations, the Secretary has
established a policy of assenting to
suspension of operating and producing
requirements for the time needed to
complete necessary studies and
consultations and, if applicable, for a
decision on wilderness status to be made.
The same policy would apply in cases
where a discovery of oil and/or gas has
been made in a nonimpairing manner on a
leasehold requiring a wilderness
protection stipulation and for which an
otherwise acceptable plan of development
and production operations has been denied
because it would impair suitability for
wilderness.
On the other hand, in instances where a
lease is encumbered by a wilderness
protection or no surface occupancy
stipulation and there has been no
discovery and a lessee's request for
application for permit to drill has been
denied, the Secretary's policy generally
has been and will be to not grant relief
from the terms of the stipulation by
granting a suspension.”
Exploration Post-FLPMA oil and gas or geothermal
exploration applied for under 43 CFR
Geophysical exploration may be allowed
only if it satisfies the non-impairment
Unlike the IMP, Manual
6330 does not distinguish
26
3150 or 43 CFR 3209 may be approved if
the BLM determines that it satisfies the
nonimpairment criteria. Pre-FLPMA
exploration will be allowed to continue as
provided under the "grandfather" concept.
Consistent with Sections 302(b) and
603(c) of FLPMA, all oil and gas and
geothermal "Notices of Intent to
Conduct Exploration" must be approved
by BLM prior to commencement of
operations. Under 43 CFR 3150, which
requires filing of a notice of intent, the
Authorized Officer has an opportunity to
review the proposed action to determine
whether special practices or procedures
need to be followed by the operator or
whether the general approval contained in
the regulations should be withheld.
Seismic and inventory information
gathering by helicopter or other means not
requiring road blading or improvement
may be allowed if it satisfies the
nonimpairment criteria. Recurring mineral
surveys with other Federal agencies by
various methods may be conducted in
accordance with 43 CFR 3802.1-2 under
the nonimpairment criteria. Casual use
provisions and definitions relating to
exploration are found at 43 CFR 3150.
criteria. §1.6(D)(5)(c)(iv)
between pre-FLPMA and
post-FLPMA leases and
cleans up this section by
requiring a blanket non-
impairment standard for
exploration.
Drilling
Units
Post-FLPMA leases may be included in
drilling units, either alone or in
combination with pre-FLPMA leases.
However, post-FLPMA leases remain
“Drilling units may include existing
leases, but those leases are constrained in
their valid existing rights as described
above. The rights of leases outside the
Manual 6330 cleans up the
language on drilling units,
allowing for existing WSA
leases to be in drilling units,
27
subject to the nonimpairment criteria even
when included in a drilling unit with pre-
FLPMA leases. In this situation, the VERs
of the pre-FLPMA lease must be honored
on the pre-FLPMA lease, but those rights
cannot be extended to post-FLPMA leases
through formation of a drilling unit.
Similarly, if there was a "grandfathered"
use on the pre-FLPMA lease, the use may
proceed in the same manner and degree
onto adjacent pre-FLPMA leases (held by
the same owner) within the drilling unit,
but a "grandfathered" use cannot be
extended to any post-FLPMA leases
through formation of a drilling unit.
Although post-FLPMA leases included in
a drilling unit remain subject to the
nonimpairment criteria, they enjoy other
benefits of unitization, and their terms
may be continued by drilling, or extended
by production, on other leases in the unit.
WSA not subject to the non-impairment
criteria cannot be extended to leases
within the WSA through formation of a
drilling unit, though leases within the
WSA enjoy other benefits of unitization
and their terms may be continued by
drilling, or extended by production, on
other leases in the unit.” §1.6(D)(5)(c)(v)
but subject to their VERs.
However, Manual 6330
prohibits leases outside of the
WSA that are not subject to
non-impairment criteria to be
extended to leases within the
WSA by unitization.
Hardrock Mining Issue IMP WSA Manual 6330 Implications
Location,
Prospecting,
Exploration,
Mining
Mining operations conducted on lands
under wilderness review are subject to the
regulations 43 CFR 3802. These
regulations provide procedures for
notifying the BLM of activities being
conducted or proposed to be conducted on
mining claims and also establish the
standards for approval of the conduct of
Exploration, Prospecting, and Location
of New Mining Claims are permitted in
all WSAs unless withdrawn under other
provisions of law. For WSAs established
under the authority of Section 603 of
FLPMA, all new location, methods and
routes of access, and subsequent
assessment must satisfy the non-
Whereas the IMP discussed
regulations set out for new
mining claims and operations
in WSAs, Manual 6330
explicitly states that new
claims are allowed in WSAs
unless withdrawn under other
provisions of laws and the
28
those operations, including reclamation.
The regulations have several purposes: (1)
to prevent impairment of the wilderness
suitability of areas under wilderness
review; (2) to recognize valid existing
rights; (3) to allow "grandfathered" uses to
continue; (4) to allow continued location
and operations under the mining laws;
and, (5) to prevent unnecessary or undue
degradation of the lands.
impairment criteria. §1.6(D)(5)(g)
development of 603 WSAs
must meet the non-
impairment criteria.
Pre-existing
Claims
All mining claimants who located claims
on or before October 21, 1976, and
are able to demonstrate a discovery as of
that date, as required under the 1872
Mining Law, as amended (prudent man
test), and at the time of approval of a plan
of operations under the regulations
43 CFR 3802, will be allowed to continue
their mining operations to full
development. Activities for the use and
development of such claims must satisfy
the nonimpairment criteria, unless this
would unreasonably interfere with the
claimant's possessory rights of use and
enjoyment of the claim. When it is
determined that the rights conveyed can
be exercised only through activities that
will impair wilderness suitability, the
activities will be regulated to prevent
unnecessary or undue degradation.
Nevertheless, even if such activities
impair the area's wilderness suitability,
those activities will be allowed to proceed.
The degree to which impairing activity,
including assessment work, is allowed
depends on whether the mining claimant
is recognized as having a "valid"
discovery as of October 21, 1976.
A. Mining claimants are recognized as
having a VER if a valid discovery
was made on the claim on or before
October 21, 1976, and the claim
continues to be supported by such a
discovery. A validity exam
performed by BLM, as described in
BLM Manual 3812, Validity
Examinations, determines whether or
not a valid discovery exists. When it
is determined that the claimant's
rights can be exercised only through
activities that will impair wilderness
suitability, they will be allowed to
proceed, the impairment
notwithstanding. Claims that do not
meet the standards of a VER may still
be developed as a grandfathered use
Manual 6330 clarifies that
anything that is not a VER or
grandfathered use must meet
the non-impairment criteria.
Manual 6330 provides that a
BLM validity exam, as set
out in BLM policy,
determines whether or not a
valid discovery exists. This
differs from the IMP, which
requires mining claimants to
demonstrate a valid
discovery under the Mining
Law (prudent man test).
Pre-existing mining
operations that do not satisfy
the requirements of having a
VER nevertheless are
permitted to continue in the
"same manner and degree" as
were occurring in October
29
Before the BLM will grant approval of
operations that do not satisfy the
nonimpairment criteria, the operator will
be required to show evidence of a pre-
FLPMA discovery. If warranted, BLM
may verify data through a field
examination and, only if necessary,
initiate contest proceedings.
If claims have a pre-FLPMA discovery
and are otherwise properly located and
maintained under the mining laws, then
the nonimpairment criteria may be
exceeded. All operations will be regulated
to prevent unnecessary or undue
degradation of the lands until the claims
are patented. Any claim patented in the
California Desert Conservation Area will
continue to be regulated to prevent
unnecessary or undue degradation, even
after the claim has been patented
[FLPMA, Section 601(f)].
All operations are subject to the
regulations 43 CFR 3802, specifying in
what circumstances and in what manner
notification is required.
if they fit the appropriate criteria (see
ii.B, below).
B. Access to claims that meet the
requirements of a VER is permitted,
even if it fails to meet the non-
impairment standard. Such access
must still not cause unnecessary and
undue degradation.
C. Pre-existing mining operations that
do not satisfy the requirements of
having a VER nevertheless are
permitted to continue in the "same
manner and degree" as were
occurring in October 1976 as
grandfathered uses. In practical
terms:
I. The same physical and visual
impacts are allowed to continue at
a logical pace and progression,
provided that the impacts of the
extension or of the new activity
are not of a significantly different
kind than the impacts existing on
October 21, 1976.
II. The quantity of on-the-ground
impacts may be increased by the
logical pace and progression of a
grandfathered use, but the new
impacts may not be of a
significantly different kind than
the impacts involved with the pre-
FLPMA activity.
III. It is the use, rather than the claim,
1976 as grandfathered uses.
In practical terms:
Manual 6330 clarifies what
constitutes development in
the “same manner and
degree” for grandfathered
uses.
Manual 6330 recognizes the
1994 moratorium on
patenting mining claims is
still in place but doesn’t
change BLM’s policy on the
management of patented
mining claims.
30
that is grandfathered. A
grandfathered mineral use may
continue in the same manner and
degree onto adjacent claims held
by the same person, even if the
adjacent claims are post-FLPMA
claims. IV. Access to claims that do not meet
the requirements of a VER is
limited to the "same manner and
degree" that existed on October 21,
1976.
D. Work on pre-existing mining claims
that do not satisfy the definitions of
either VERs or grandfathered uses will
be allowed only if the BLM determines
that the proposed operations satisfy the
non-impairment criteria.
E. Because Congress directed the BLM to
stop patenting mineral claims in 1994,
that process is not discussed here. If
patenting were to resume, this sub-
section of the WSA Management
Manual will be revised. Patented
claims issued prior to 1994 are treated
as private land except in the California
Desert Conservation Area, where
patented claims continue to be
regulated to prevent unnecessary or
undue degradation. §1.6(D)(5)(g)
Temporary
Limitation on
the Exercise
“If impairing activities are proposed on a
pre-FLPMA claim with VERs, within a
WSA which the BLM Director has
Not addressed. Unlike the IMP, Manual
6330 does not create a
temporary limitation of
31
of Valid
Existing
Rights
(VERs).
recommended to the Secretary as suitable
for preservation as wilderness, the
proposed impairing activity may be
temporarily disapproved by the Director
of the BLM. This is a narrow exception
for extraordinary circumstances when the
Secretary and the President may be
expected to recommend the WSA as
suitable for wilderness and Congress may
be expected to act in a short period of
time. Such a disapproval would be for 1
year, subject to renewal, but not to exceed
a total of 2 years.”
exercising VERs for
impending Wilderness bills
that may include WSA lands
at issue.
Coal Issue IMP WSA Manual 6330 Implications
New Leasing “The only BLM-administered lands that
will be offered for competitive lease sale
are those on which a final wilderness
inventory decision has determined that the
lands lack wilderness characteristics.
Once the Congress has determined that a
WSA will not be designated as
wilderness, the area may be considered for
competitive lease.”
New leasing of coal is prohibited within
WSAs. §1.6(D)(5)(e)(i)
Unlike the IMP, Manual
6330 prohibits new coal
leases within WSAs.
Pre-existing
Leases
All pre-FLPMA coal leases represent
VERs, but the rights are dependent upon
the specific terms and conditions of each
lease, including any stipulations attached
to the lease. Activities for the use and
development of such leases must satisfy
Pre-existing coal leases will be allowed
to be developed according to the VER
conveyed by the specific terms and
conditions of each lease. §1.6(D)(5)(e)(ii)
Both the IMP and Manual
6330 allow pre-existing
leases to be developed
according to VER terms and
conditions. However, unlike
the IMP, Manual 6330 does
32
the nonimpairment criteria unless this
would unreasonably interfere with rights
of the lessee as set forth in the mineral
lease. When it is determined that the
rights conveyed can be exercised only
through activities that will impair
wilderness suitability, the activities will
be regulated to prevent unnecessary or
undue degradation. Nevertheless, even if
such activities impair the area's wilderness
suitability, they will be allowed to
proceed.
not hold coal leases to the
nonimpairment standard.
Pre-existing
Preference
Right Lease
Applications
The preference right lease applicant's right
to adjudication of his right to lease will be
recognized. Application of the right,
however, involves application of the coal
unsuitability criteria, including the
wilderness review criterion number 4, of
43 CFR 3461(d)(1) and the imposition of
conditions in the proposed lease to
prevent impairment of the area's
suitability for preservation as wilderness.
The Secretary may initiate exchange
proceedings for coal under 43 CFR
3430.5-4 if he determines that, among
other things, the lands are unsuitable for
coal mining because of wilderness
considerations.
Pre-existing Preference Right Lease
Applications (PRLAs) will be
adjudicated by applying the criterion for
assessing lands unsuitable for coal
mining at 43 CFR 3461.5(d)(1).
Therefore, even though the applicant
showed a pre-existing commercial
discovery of coal, WSAs are considered
unsuitable unless and until congressional
decision not to designate the WSA as
wilderness and to release it from further
review. The Secretary may initiate
exchange proceedings under 43 CFR
3430.5-4. §1.6(D)(5)(e)(iii)
Both the IMP and Manual
6330 are the same for pre-
existing preference right
lease applications.
Exploration Exploration licenses are issued for
exploration of unleased Federal land.
Unsuitability criteria will not be applied to
exploration licenses. If the activities
proposed under an exploration license
Coal exploration licenses may be allowed
only if they satisfy the non-impairment
criteria. §1.6(D)(5)(e)(iv)
Both the IMP and Manual
6330 are the same for
exploration licenses.
33
would create impacts that do not satisfy
the nonimpairment criteria, they would
not be approved.
Suspension
of Lease
Terms
The lease suspension policy for oil and
gas applies to coal leases. One factor in
the Secretary's decisions will be the
diligent development requirement that
must be met by the lessee.
Not specifically addressed. Unlike the IMP, Manual
6330 does not address
suspension of coal lease
terms.
Disposal of
Minerals
Materials
(Salable)
Sale and free use of mineral materials will
not be allowed in most instances because
it would not be compatible with the
nonimpairment criteria. The existence of
the use would constrain the Secretary's
ability to recommend the area suitable or
for the Congress to designate the area as
wilderness.
Mineral materials subject to disposal
include, but are not limited to, petrified
wood and common varieties of sand,
stone, gravel, pumice, and clay.
i. Except as provided for in ii, below,
sale or free use of all mineral
materials is not allowed because
such activities cause surface
disturbance and so do not meet the
non-impairment criteria.
ii. Free collection of small amounts of
mineral materials for personal use
may be permitted except:
A. all collection must satisfy the
non-impairment criteria
B. no collection of petrified wood is
allowed in areas where it has been
identified as a supplemental value
of the WSA (except under
scientific permit; see 1.6.D.1).
Unlike the IMP, Manual
6330 contains an exception
for small amounts of mineral
materials for personal use
under specific criteria.
Recreation Issue IMP WSA Manual 6330 Implications
Motorized “No new, permanent recreational ways, “i. Recreational use of motor vehicles or Manual 6330 is much
34
and
Mechanized
Vehicle Use
trails, structures, or installations will be
permitted, except those that are the
minimum necessary for public health and
safety in the use and enjoyment of the
public lands' wilderness values, and that
are necessary to protect wilderness
resource values.”
“Except for emergency situations as
defined in Chapter I.B.12, vehicle
designations in WSAs are to be handled
through the land-use planning process.
Until WSAs are designated as wilderness
or released from study status, vehicle use
within each WSA is governed by the
terms and conditions as identified in
Chapter I.B.11 and any land-use planning
decisions. Open areas may be designated
only:
1) as sand dune or snow areas for use
by the appropriate sand or snow
vehicles, or
2) where an area was designated open
prior to October 21, 1976. No
vehicle designation in a WSA may
allow vehicles to travel off existing
ways and trails, except in these two
circumstances.”
“Organized vehicle events will not be
allowed unless they can meet the
nonimpairment criteria, and are contained
on existing ways and trails or within pre-
mechanical transport (see Glossary) may
only be allowed when such use is
consistent with all applicable laws and
meets the non-impairment standard. The
following are examples of motorized or
mechanized transport uses that are not
likely to impair an area’s suitability and
therefore may be allowed in a WSA:
A. within "open" areas designated prior
to the passage of FLPMA (October
21, 1976), unless the area was
subsequently limited or closed in a
Land Use Plan decision.
B. on primitive routes (or “ways”)
identified by the BLM as existing on
October 21, 1976 (or prior to the
designation date for Section 202
WSAs not reported to Congress) if:
I. identified in the original
wilderness inventory; or
II. if not identified as in I., having
documented proof that the route
existed at that time; and
III. whether I. or II., the route was not
otherwise closed through BLM’s
Travel Management Planning
C. off of primitive routes for the
minimum clearance to allow another
vehicle to pass when driving or
parking vehicles.
Note: offices may consider issuing
supplementary rules where necessary to
provide enforcement of this section of the
more specific in the
management of
recreational use of
motorized and
mechanized vehicles.
Unlike the IMP, Manual
6330 provides examples
for uses that are not
likely to impair
suitability.
Unlike the IMP, Manual
6330 does not include
the exception for sand
dune or snow areas for
“open” areas—just pre-
existing “open” areas
that have not been
limited or closed in a
subsequent decision.
Manual 6330 changes
“ways” to “primitive
routes.” Primitive routes
do not meet the
definition of “wilderness
inventory roads.”
Unlike the IMP, Manual
6330 provides specific
guidance on motorized
and mechanized
vehicles, including:
35
FLPMA sand dune or snow open areas.” WSA Management Manual.
ii. Because their development causes new
surface disturbance, no new motor
vehicle or mechanical transport routes
will be permitted in WSAs. Vehicle
routes other than those defined in b.i.B,
above, should be closed and restored.
iii. No improvement or maintenance of
any primitive routes will be permitted to
facilitate recreational motor vehicle or
mechanized vehicle use in WSAs if it
does not meet the non-impairment
standard or one of the exceptions.
iv. Primitive routes within WSAs may
only be used to the extent that the
physical impacts of the primitive route
are no greater than existed on October
21, 1976 (or prior to the designation date
for Section 202 WSAs not reported to
Congress). During the wilderness
inventory, the BLM evaluated all “ways”
(now referred to as “primitive routes”)
within WSAs and in many cases
established photo documentation of their
condition. Except for emergency
situations as defined in section 1.6.C.2.a,
or for activities authorized under other
exceptions to the non-impairment criteria
in section 1.6.C.2., the BLM must take
action to ensure the route does not exceed
New motorized or
mechanized routes.
improvements or
maintenance of any
primitive routes.
Monitoring routes
Closure of primitive
routes
Unlike the IMP, Manual
6330 does not
specifically address
organized vehicle events.
36
the approximate conditions of impact to the
wilderness characteristics that existed on
October 21, 1976 (or prior to the
designation date for Section 202 WSAs not
reported to Congress). Actions taken to
improve the wilderness characteristics of
the route will impose the least restrictions
on visitors while effectively restoring the
route, and can include closure (seasonally
or year-round) of primitive routes to some
or all types of motorized or mechanical
transport under the authorities of 43 CFR
8341.2 and 8364 where: A. Use has increased appreciably,
causing the route to become more
highly developed (for example, a
two track route that no longer has
center vegetation or has increased
in width).
B. Deterioration of the route has
occurred, causing drivers to bypass
a section(s) of the route (for
example, the surface of a primitive
route has eroded causing drivers to
bypass the original route and drive
parallel to it).
In most cases, closure of primitive routes
will also include restoration of the soil and
vegetation. In some cases, a closure may
be made by gating the road and allowing
for authorized use to continue (for
example, access associated with grazing
administration).
v. If outstanding opportunities for solitude
37
were identified in the original inventory,
the BLM will monitor remaining primitive
routes open to motorized travel within the
area and take actions to prevent the
impairment of the opportunity for solitude.
The BLM cannot allow use (including
increased vehicle use on routes remaining
open to motorized or mechanical transport
within the area) that would impair these
opportunities.
vi. As described in BLM Manual 1626—
Travel and Transportation Manual, “Any
motorized/mechanized linear transportation
feature located within [WSAs] will be
identified in a transportation inventory as a
motorized/mechanized ‘primitive
route’...Primitive routes will not be made a
part of the transportation system, classified
as a transportation asset, or entered into the
Facility Asset Management System
(FAMS) unless one of the following
conditions is met:
A. The routes are designated as non-
motorized and non-mechanized
trails, or
B. Congress releases the WSA from
Wilderness consideration.”
Motorized/mechanized primitive routes
may be signed only to the extent necessary
to prevent resource damage or users getting
lost; they may not be assigned names or
numbers that would appear to create a de
facto route system.
38
vii. Though motorized and mechanical
transport may be permitted to continue
along existing primitive routes, “closed”
designations may be appropriate for
WSAs, or portions of WSAs, where RMP
planning goals are to provide primitive
recreational opportunities, or where needed
for the protection of an identified natural
resource. §1.6(D)(6)(b)
Trails “No new, permanent recreational ways,
trails, structures, or installations will be
permitted, except those that are the
minimum necessary for public health and
safety in the use and enjoyment of the
public lands' wilderness values, and that
are necessary to protect wilderness
resource values. No mechanical transport,
which includes all motorized vehicles plus
trail or mountain bikes, will be allowed on
such trails.”
“As surface disturbing developments, no
new trails or related structures or
installations will be allowed, unless they
meet an exception to the non-impairment
standard. Where trails are allowed under an
exception, no motorized or mechanical
transport (e.g. bicycles) will be allowed on
such trails.”
If found to meet the non-impairment
standard or one of the exceptions, new trail
sections, trail structures, or installations
may be provided under the following
conditions:
i. Hiking or horseback riding use levels
have increased, or are expected to increase,
to the extent that resource impacts are or
are likely to become present (e.g. braided
or duplicate trails, impacts to cultural sites
or other sensitive resources, or accelerated
soil erosion). In these cases, to minimize
recreational use impacts to wilderness
characteristics a single, properly located,
sustainable trail may be provided for under
the "restoration of impacts from violations
Unlike the IMP, Manual
6330 provides specific
conditions for new trails
if the non-impairment
standard is met,
including:
Increase in hiking or
horseback use levels
may cause impacts,
making a single trail
appropriate.
Increase in hiking or
horseback use levels
has created a
dangerous route,
making relocation of
a trail appropriate.
Turning primitive
routes once used for
motorized vehicles
into non-motorized
trails.
39
emergencies" or "protect or enhance
wilderness characteristics or values"
exceptions to the non-impairment criteria
(see sections 1.6.C.2.c and 1.6.C.2.f.)
ii. Hiking or horseback riding use levels
have increased so that a defined route is
present, and the route leads visitors to a
hazard (e.g. along a precipitous ledge or to
an abandoned mine). In these cases, a trail
may be relocated to a more appropriate
location.
iii. A primitive route closed to motor
vehicles is utilized by hiking or horseback
riding. The primitive route may be
managed as a trail, including constructing
water drainage and re-routing of
unsustainable sections as defined in c.i and
c.ii, above. §1.6(D)(6)(c)
Boating 3. Boating may be allowed with or
without motors. The BLM does not have
authority over all waters within the public
lands; some are under jurisdiction of the
States. Therefore, the following guidelines
apply only to those waters on which the
BLM has authority to regulate boating.
a. No waters will be closed to
motorboats solely because they are in
areas under wilderness review.
However, if increasing impacts of
boating (such as shore erosion or
water pollution) threaten to impair
wilderness suitability, the BLM may
close the affected waters to
“Boating may be allowed with or without
motors as long as supporting facilities
and activities within the WSA satisfy the
non-impairment criteria. No launching
ramps or boat docks will be built. A
"brow log" may be used to reduce
erosion at boat landings. A short trail
may be designated and maintained
between boat landings and campsites at
appropriate locations above the waterline
in order to minimize recreational use
impacts to the wilderness resource
consistent with paragraph 6.c, above.”
§1.6(D)(6)(d)
Unlike the IMP, Manual
6330 does not contain
language on motorboats,
river running or river
campsites.
Manual 6330 allows for
the creation of short
trails between boat
landings and campsites.
40
motorboats. In some cases, time or
space restrictions or public education
may make a total closure
unnecessary. The Bureau also has
authority under other programs to
regulate boating to minimize damage
to wildlife and other resource values.
b. River running, with or without
motors, may be permitted.
Cumulative impacts on river
campsites will be monitored to
prevent impairment of wilderness
suitability.
c. No permanent launching ramps or
boat docks will be built. A "brow
log" may be used to reduce erosion at
boat landings. Temporary launching
ramps and boat docks may be
installed only if they satisfy the
nonimpairment criteria.”
Skiing “Cross-country skiing may be allowed.
Downhill (alpine) may be permitted only
if any support facilities within the WSA
satisfy the nonimpairment criteria.
Helicopter skiing, if nonimpairing, may be
allowed at the discretion of the authorized
officer.”
“Skiing is allowed as long as all
supporting facilities and activities within
the WSA satisfy the non-impairment
criteria.” §1.6(D)(6)(e)
Both manuals are
essentially the same.
Aerial
Activities
“Aerial activities such as ballooning,
sailplaning, hang gliding, and parachuting
(sky diving), may be allowed as long as
they do not require cross-country use of
motorized vehicles or mechanical devices
to retrieve equipment, except in areas
“Aerial activities such as ballooning,
hang gliding, paragliding and
parachuting (sky diving), may be allowed
as long as they meet the non-impairment
standard, including not requiring cross-
country use of motorized vehicles or
Manual 6330 clarifies
that these activities must
meet the non-impairment
standard in addition to
not requiring cross-
country motorized or
41
designated as "open" before October 21,
1976.”
mechanical devices to retrieve
equipment, except in areas designated as
“open” before October 21, 1976.”
§1.6(D)(6)(f)
mechanized use.
Rock
Climbing and
Caving
Rock climbing and caving will be allowed
as long as these activities meet the
nonimpairment criteria. The use of power
driven (i.e. fuel or electric) rock drills or
permanent anchors (e.g. bolts) is not
allowed. No marring, scarring or defacing
resulting in adverse impacts to the
wilderness value of naturalness will be
permitted, nor will permanent installations
be permitted. Exceptions to the above
may be allowed for: (a) emergencies, such
as search and rescue operations; and (b)
authorized actions needed for access
travel within WSAs which are the
minimum necessary for public health and
safety in the use and enjoyment of the
wilderness values. Any impacts from
emergency actions (a, above), must be
reclaimed to a substantially unnoticeable
condition following the emergency
situation.
“Rock climbing and caving are allowed
as long as these activities meet the non-
impairment criteria. The placement of
permanent fixed anchors (e.g., bolts) or
artificial holds is not allowed unless it
meets one of the exceptions to the non-
impairment standard, e.g. for
emergencies, such as search and rescue
operations. Any impacts from emergency
actions must be restored to a substantially
unnoticeable condition following the
emergency situation. Generally, fixed
anchors placed prior to FLPMA will not
be removed unless their presence
creates—directly or indirectly—impacts
that exceed the non-impairment
standard.”
§1.6(D)(6)(g)
Both manuals are
essentially the same,
except Manual 6330
allows for pre-existing
anchors to continue to
exist unless impacts
exceed the non-
impairment standard.
Camping “Camping may be allowed. Camping with
recreational vehicles may occur on
existing ways as long as this use meets the
nonimpairment criteria. Primitive
campsites for recreational use may be
established anywhere in the WSA as long
as they meet the nonimpairment criteria.
Low impact camping techniques should
“Camping is generally allowed in WSAs.
Primitive camping (i.e., horse camping and
backpacking) may occur anywhere in the
WSA as long as it meets the non-
impairment criteria. Campsites should be
monitored and action taken to limit use
and/or restore sites where unacceptable
levels of impact are present. Low impact
camping techniques should be promoted
Unlike the IMP, Manual
6330 contains a
provision for monitoring
campsites for
unacceptable levels of
impacts.
Unlike the IMP, Manual
42
be encouraged within all WSAs.” within all WSAs.
Campsite developments (e.g. camping
pads, picnic tables, etc.) may not be
installed. Toilets may only be provided to
protect or enhance wilderness
characteristics where resource damage is
documented and where the toilet would not
rely on motor vehicles for maintenance.
Camping with motor vehicles may occur
on existing primitive routes as long as this
use meets the non-impairment criteria.
Vehicles may drive off of existing
primitive routes no farther than is
necessary to allow another vehicle to pass.
In some cases, camping spurs were
documented in the route analysis during
the wilderness inventory; these may
continue to be used as long as vehicles
cause no more impact than was present at
the time of the inventory.” §1.6(D)(6)(h)
6330 specifically
addresses campsite
developments, toilets,
and “car camping.”
Education
and
Interpretation
“Environmental education and interpretive
programs may be conducted so long as no
permanent facilities are required and the
use does not cause surface disturbance.”
“Environmental education and
interpretive programs may be conducted
as long as they meet the non-impairment
standard or one of the exceptions.”
§1.6(D)(6)(i)
Manual 6330 clarifies
this section by applying
the non-impairment
standard to this use.
Hobby
Collecting
(Rock
Hounding)
“Hobby collecting of mineral specimens
(rockhounding) and vegetative specimens
may be allowed for personal but not
commercial use, as long as the collection
activity method meets the nonimpairment
criteria.”
“Hobby collecting of common rock and
mineral specimens (rock hounding) and
vegetative specimens may be allowed for
personal but not commercial use, as long
as the collection activity method meets
the non-impairment criteria and is not
otherwise prohibited. Collecting common
invertebrate and plant paleontological
Manual 6330 prohibits
collection of
paleontological resources
if those are identified as
a supplemental value and
clarifies that no
collecting of any
resource protected by the
43
resources as allowed under the
Paleontological Resources Protection
subtitle of 16 U.S.C. 7202 will not be
allowed in a WSA where these non-
renewable resources have been identified
as a supplemental value because said use
would impair the area’s suitability for
preservation as wilderness. See also
1.6.D.5.b.ii in this manual. As on any
public land, no hobby collecting of any
resource protected by the Archaeological
Resources Protection Act is permitted.”
§1.6(D)(6)(j)
Archaeological
Resources Protection Act
is permitted.
Gold Panning
and Dredging
“Recreational gold dredging and panning,
when conducted without location of a
mining claim may be allowed as long as it
is done in a manner that satisfies the
nonimpairment criteria. If the activity
would cause significant damage to fish
spawning or rearing areas, it will be
considered to impair wilderness
suitability, and the activity will be
controlled to prevent such impacts.”
“Recreational gold panning, when
conducted without location of a mining
claim, may be allowed as long as it is
done in a manner that satisfies the non-
impairment criteria. If the activity would
cause noticeable damage to fish
spawning or rearing areas, it will be
considered to impair wilderness
suitability, and the activity will be
limited to prevent such impairment.
Dredging is not allowed unless it meets
one of the exceptions to the non-
impairment standard.” §1.6(D)(6)(k)
Unlike the IMP, Manual
6330 prohibits dredging
for gold.
Geocaching Not addressed. “Geocaching and other similar activities
are allowed as long as the use meets the
non-impairment criteria. The BLM must
also ensure that activities that would be
incompatible with wilderness designation
(such as geocaching with physical
Manual 6330 specifically
allows geocaching in
WSAs so long as non-
impairment is being met
and that it is not the
dominant use of the area.
44
caches) do not become the dominant use
of the area, thereby impairing the
solitude or primitive recreational
opportunities that existed at the passage
of FLPMA. See section 1.6.B.5. The
BLM should coordinate with geocachers
to ensure that caches are not placed in
areas with sensitive resources (e.g.
cultural). Where increased use levels are
found to be causing impairment (e.g. new
visitor created trails or soil and
vegetation impacts around the geocache
site) geocaching should be discontinued.”
§1.6(D)(6)(l)
The IMP did not
specifically address
geocaching.
Special
Recreation
Permits
“Concessions and actions that require
authorization under a special recreation
permit will be allowed only if the use and
related facilities satisfy the
nonimpairment criteria. Examples that
may qualify include mobile refreshment
stands, river trip outfitters, guides, and
providers of pack animals and saddle
horses.”
“Activities that require authorization
under a Special Recreation Permit (SRP)
will be allowed only if the use and
related facilities satisfy the non-
impairment criteria (and therefore do not
involve a use of the WSA that would be
incompatible with wilderness
designation). Examples of uses that may
be authorized include river trip outfitters,
hunting or fishing guides, group
backpack trips, and providers of pack
animals and saddle horses.”
§1.6(D)(6)(m)
Both manuals are
essentially the same.
Soil, Air and Water Issue IMP WSA Manual 6330 Implications
Monitoring
Devices
“Permanent snow gauges, air quality
monitoring instruments, water quantity
“Temporary and permanent monitoring
markers, instruments, meteorological
Unlike the IMP, Manual
6330 does not distinguish
45
and quality measuring instruments, and
hydrometeorologic devices may be
established if these are the minimum
necessary for determination of real or
potential threats to human health, safety,
or property and if they are substantially
unnoticeable. These permanent
placements must use miniaturized
equipment, be adequately camouflaged,
and not require maintenance access by
motor vehicle.
Temporary monitoring devices for the
same purposes may be installed, with the
above restrictions on use of motor
vehicles, if they satisfy the nonimpairment
criteria.”
devices, soil pits, snow gauges, and water
quantity and quality measuring
instruments may be established where
needed to monitor threats to human
health, safety, or property or to monitor a
WSA’s natural resources in order to
support restoration or prevent
impairment. Such devices will only be
allowed if they meet the non-impairment
standard or one of the exceptions.”
§1.6(D)(7)(b)
between temporary and
permanent monitoring
devices and holds both to a
“where needed” and the non-
impairment standard.
“Measures required for watershed
rehabilitation, including structures, will be
permitted only if they satisfy the
nonimpairment criteria. Land treatments
(e.g., trenching, ripping, pitting, terracing,
plowing) will not be permitted on lands
under wilderness review. Watershed
rehabilitation work required by
emergency conditions caused by fire,
flood, storms, biological phenomena, or
landslides may involve any treatments
needed but must be conducted to the
extent feasible in a manner that will not
impair wilderness suitability. For
example, the rehabilitation work will use
the methods least damaging to the
“Measures required for watershed
rehabilitation may be permitted if they
satisfy the non-impairment criteria or one
of the exceptions. Watershed
rehabilitation activities to address natural
successional processes that have been
disrupted by past human activity may be
allowed. Intervention will be limited to
what is necessary to allow the system to
return to a natural process and to what is
necessary to address situations where
stabilization through natural processes
would take longer than one growing
season and the impacted area would be
susceptible to significant soil loss during
that time or further ecological departure
Whereas the IMP established
a priority for emergency
rehabilitation work for
watersheds that included less
intrusive techniques, Manual
6330 discusses allowing
intervention only when
necessary to allow a system
to return to a natural process
and to stabilize areas to
return natural processes.
46
wilderness resource. Alternatives to
seeding must be carefully evaluated prior
to the decision to reclaim, if reclamation
is allowed. Reseeding and planting under
emergency conditions will utilize species
native to the area and will minimize cross-
country use of motorized equipment.
Seedings and plantings will be staggered
or irregular so as to avoid a straightline
plantation appearance.”
would occur. (See also section 1.6.D.8).
Approaches that do not restore natural
processes should not be approved.”
§1.6(D)(7)(c)
Clean Air
Act
“Under the Clean Air Act (as amended,
1977), all BLM-administered lands were
given Class II air quality classification,
which allows moderate deterioration
associated with moderate, well controlled
industrial and population growth. The
BLM will continue to manage WSAs as
Class II.
The Department of the Interior will not
recommend reclassification to the more
strict Class I in connection with future
wilderness recommendations resulting
from the BLM wilderness review. The
two processes are separate and distinct,
and are accomplished under two different
laws, FLPMA and the Clean Air Act.
Recommendations for wilderness
designation are made by the BLM through
the Secretary of the Interior and the
President to Congress. Air quality
reclassification is the prerogative of the
States, and it must follow a process
“FLPMA requires the BLM to protect the
quality of air and atmospheric values,
while managing the public lands according
to “multiple use” and “sustained yield”
principles. FLPMA also requires that the
BLM’s land use plans provide for
compliance with applicable air pollution
standards or implementation plans. Under
the Clean Air Act Prevention of Significant
Deterioration (PSD) program, most WSAs
are designated as “Class II” areas. This
allows moderate deterioration associated
with moderate, well-controlled industrial
and population growth. The BLM will
continue to manage WSAs consistent with
FLPMA and the Clean Air Act
requirements for Class II areas, unless an
area is redesignated as “Class I” (a
designation that requires greater
protection) by the appropriate State
through procedures under the Clean Air
Act.” §1.6(D)(7)(d)
Essentially the same except
Manual 6330 points out that
FLPMA requires BLM to
protect the quality of air and
to comply with applicable air
pollution standards.
47
mandated by the Clean Air Act
Amendments of 1977, involving a study
of health, environmental, economic,
social, and energy effects, a public
hearing, and a report to the Environmental
Protection Agency. The Department will
not recommend any change in air quality
classification as part of wilderness
recommendations.”
Vegetation Issue IMP WSA Manual 6330 Implications
Vegetation
Manipulation
Vegetative manipulation by chemical,
mechanical, or biological means will
not be permitted except: (1) plantings or
seedings established before October 21,
1976 may be maintained but not
expanded; (2) activities that qualify under
the manner and degree provision for
grandfathered grazing uses; and, (3)
control of noxious weeds and individual
exotic plants such as tamarisk when there
is no effective alternative and when
control of the noxious weed or exotic
plant is necessary to maintain the natural
ecological balances within a WSA or
portion of a WSA. Hand or aerial seeding
of native species may be done to restore
natural vegetation.
In all cases where vegetative manipulation
is proposed, the activity must conform to
“Whenever possible, natural processes
will be relied on to maintain native
vegetation and to influence natural
fluctuations in populations. Natural
disturbance processes, including fire,
insect outbreaks, and droughts, are
important functions of the ecosystem.
Manipulation of vegetation through
management-ignited fire, chemical
application, mechanical treatment, or
human controlled biological means is
allowed only where it meets the non-
impairment standard or one of the
exceptions. Exceptions that may pertain
to vegetative treatment include
emergencies, the protection or
enhancement of wilderness
characteristics, grandfathered uses, valid
existing rights, and actions taken to
recover a federally listed threatened,
Manual 6330 sets forth the
policy that natural processes
will generally be relied on to
maintain vegetation.
Unlike the IMP, Manual
6330 states that “Establishing
non-native plants is an
example of vegetation
management that may impair
and therefore may not be
permitted within a WSA.”
48
the policy guidance of Chapter II of this
manual and not adversely impact
wilderness values within any portion of
the WSA. (See Chapter II.B.4.c for
specific analysis requirements.)
In grandfathered grazing operations, if
vegetative manipulation had been done on
the allotment before October 21, 1976,
and its impacts were noticeable to the
average visitor on that date, the vegetative
treatment may be maintained by
reapplying the same treatment to the same
area. Otherwise, vegetative manipulation
may be used only for control of small
areas of exotic plants when there is no
effective alternative. Limited exceptions
are specified as follows:
--Noxious weeds may be controlled by
grubbing or with chemicals when they
threaten lands outside the WSA or are
spreading within the WSA, provided the
control can be effected without serious
adverse impacts on wilderness values.
--Prescribed burning may be used where
necessary to maintain fire-dependent
natural ecosystems.
--Reseeding may be done by hand or
aerial methods to restore natural
vegetation.
(There is also a provision for reseeding in
emergency reclamation projects,
described in
endangered, or candidate species.
Establishing non-native plants is an
example of vegetation management that
may impair and therefore may not be
permitted within a WSA.” §1.6(D)(8)(a)
49
Section 1, above.)
Emergencies Not specifically addressed. “As an exception to the non-impairment
standard, vegetative manipulation in
emergency situations may be allowed,
e.g. there is no effective alternative for
controlling insect and disease outbreaks
or fires that threaten lands outside of a
WSA. Reseeding or planting of native
species may be undertaken following fire
or other natural disaster if natural seed
sources are not adequate to compete with
non-native vegetation or substantial soil
loss is expected.” §1.6(D)(8)(b)(i)
Manual 6330 clarifies that
reseeding or planting native
species may be an emergency
exception if native seed
sources are not adequate to
compete with non-natives or
substantial soil loss is
expected.
Insect and
Disease
Control
“Trees may be cut when necessary for
insect and disease control or in
emergencies involving fire burning out of
prescription. The use of chemical means
to control disease or insects may be
permitted, if applied to individual trees or
areas up to five acres, or larger areas
under emergency conditions when there is
no effective alternative.”
“Native insect and disease control
activities on vegetation will be allowed
only to the extent that they meet the non-
impairment criteria or one of the
exceptions. When specific insects and
diseases are documented to be non-native
or introduced organisms, then it may be
reasonable to consider whether the
protection and enhancement of wilderness
characteristics exception to the non-
impairment standard applies.”
§1.6(D)(8)(b)(ii)
Manual 6330 applies the
non-impairment standard to
insect and disease control,
whereas the IMP had more
specific standards involving
emergency conditions.
Restoration Not specifically addressed. B. Where it meets the non-impairment
standard or one of the exceptions,
management action may be taken to restore
vegetation to characteristic conditions of
the ecological zone in which the area is
situated where:
Manual 6330 sets out criteria
for when restoration may be
appropriate as well as
management restrictions for
restoration actions.
50
I. natural successional processes have
been disrupted by past human activity,
to the extent that intervention is
necessary in order to return the
ecosystem to a condition where natural
process can function;
II. restoration through natural processes
would require lengthy periods of time
during which the impacted area would
receive unwanted human use or be
susceptible to significant soil loss
without intervention, or further
ecological departure would occur; or,
III. it is necessary to maintain fire-
dependent ecosystems when adjacent
land uses do not allow for natural fire
occurrence. (see section 1.6.D.2.c)
C. Manipulation should only occur when
restoration by natural forces is no longer
attainable, and only to restore or maintain
vegetative communities to the closest
approximation of the natural range of
conditions.
D. Restoration treatments should use the
least disruptive techniques that have the
best likelihood for success. Patient,
incremental treatments should be favored
over aggressive attempts to restore long-
term changes all at once, unless repeated
treatments would pose greater impairment
risk to wilderness characteristics.
E. Monitoring programs must be in place
prior to treatment and must be sufficient to
51
evaluate responses of key ecosystem
components and processes at multiple
scales.
F. Restoration projects are based on
landscape assessments that identify
historical range of variability, current
condition, restoration targets, and
cumulative effects of management. The
decision to manipulate an ecosystem must
be based upon clearly articulated, well-
supported management objectives and
available scientific information. At a
minimum, the EA or EIS for any proposed
manipulation of vegetation must address
the following:
A description based on historical and
scientific evidence of the natural
vegetative community and processes
that would have existed prior to the
effects of industrialized humans.
A description of the existing condition
and how it is a departure from the
natural vegetative community and
processes.
Evidence from existing
research/application that the proposed
treatment will bring about the desired
result.
An evaluation of the likelihood of the
natural system to be self-sustaining
after the treatment. Treatments should
allow for natural processes to resume.
Where this is not possible because of
conditions outside the WSA (e.g. a fire
52
regime influenced by adjacent private
land development), the contributing
conditions and factors must be
described. §1.6(D)(8)(b)(iii)
Collection
and Removal
of Vegetation
“Tree improvement (genetic selection and
pollination), seed collection (climbing and
squirrel cache), and pine nut gathering
may be permitted if these activities are
conducted in a non-impairing manner.”
Collection of seeds, nuts, berries, and
similar items for personal use may be
permitted, as may the collection of
firewood for recreational use while
recreating in the WSA as such uses are
generally not found to impair the area’s
suitability for preservation as wilderness.
Commercial or agency seed or plant
collection may be permitted in support of
restoration as described in section 8.b.iii,
above, or for other restoration or scientific
purposes as long as the non-impairment
standard or one of the exceptions is met.
Collection activities must be conducted in
a non-impairing manner. Forest product
removal, including building material,
fuelwood, Christmas trees, and boughs,
may not permitted as these activities are
generally found to impair, with the
exception of forest products resulting from
stewardship contracts for restoration
activities (1.6.D.8.b.ii.) in which vegetative
products become the property of the
contractor. §1.6(D)(8)(c)
Manual 6330 distinguishes
collection for personal and
commercial use and applies
the non-impairment standard
to both but also only allows
commercial collection for
restoration or scientific
purposes.
Manual 6330 prohibits forest
product removal, including
fuelwood, Christmas trees, and
building material with the
exception of forest products
resulting from restoration
stewardship contracts where
the product becomes the
property of the contractor.
Visual Resource Management Issue IMP WSA Manual 6330 Implications
VRM Class Not specifically addressed. “All WSAs should be managed
according to VRM Class I management
BLM Manual 6330 requires
BLM to manage WSAs for
53
objectives until such time as Congress
decides to designate the area as
wilderness or release it for other uses.”
§1.6(D)(9)
VRM Class I management.
Wild Horse and Burros Issue IMP WSA Manual 6330 Implications
General “Taking into account the fact that wild
horse and burro numbers fluctuate
dramatically within WSAs due to a
variety of factors, the Bureau must still
endeavor to make every effort not to
allow populations within WSAs to
degrade wilderness values, or vegetative
cover as it existed on the date of the
passage of FLPMA. Wild horse and burro
populations must be managed at
appropriate management levels as
determined by monitoring activities to
ensure a thriving natural ecological
balance.”
“Wild horse and burro herds are managed
in WSAs only within geographic areas
identified as having been used by a herd as
its habitat in 1971 as directed by the Wild
Free-Roaming Horse and Burro Act. Wild
horses and burros are managed to remain
in balance with the productive capacity of
the habitat; this includes managing herds
so as not to impair wilderness
characteristics. Wild horse and burro
populations must be managed at
appropriate management levels so as to not
exceed the productive capacity of the
habitat (as determined by available science
and monitoring activities), to ensure a
thriving natural ecological balance, and to
prevent impairment of wilderness
characteristics, watershed function, and
ecological processes. The BLM should
limit population growth or remove excess
animals as necessary to prevent the
impairment of the WSA.”
§1.6(D)(10)(a)
Manual 6330 sets out
additional criteria for
managing wild horses and
burros to prevent impairment
to wilderness characteristics,
watershed function and
ecological processes and for
removing population growth
or removing excess animals
as necessary to prevent
impairment.
Existing Wild
Horse and
Burro
“Wild horse and burro developments
existing within WSAs as of October 21,
1976, may continue to be utilized and
Existing wild horse and burro
developments within WSAs may
continue to be utilized and maintained.
Unlike the IMP, Manual
6330 does not discuss the
possibility of mitigating
54
Developments maintained. Although these developments
existed prior to the passage of FLPMA,
there may be opportunities for mitigating
their impacts on wilderness values. Motor
vehicles may not be used in the
maintenance of these developments
unless the development is on an existing
way or trail.”
§1.6(D)(10)(b) impacts of existing
developments or the use of
motor vehicles.
New
Facilities
“Helicopters and fixed wing aircraft may
be used for the installation of new
temporary facilities, for aerial surveys, for
law enforcement activities, and for the
gathering of wild horses and burros.”
Proposed new facilities and their
potential impacts must be evaluated in
conformance with NEPA (see section
1.6.E). If a portion of the Herd
Management Area (HMA) is outside the
WSA, any new development should be
placed there, where practicable.
i. Water developments. As surface
disturbing developments, new water
sources for wild horse or burro herds can
only be allowed where they meet one of
the exceptions to the non-impairment
standard. Water developments that are
incorporated into the protection of
springs or riparian areas (including water
developments created to replace water
lost elsewhere in the HMA) may be
permitted if they meet an exception to
the non-impairment standard.
ii. Fences. New fences may be allowed
where necessary to protect springs or
other water sources from impairment by
wild horses or burros. Such exclosure
fences must be visually minimized and
Unlike the IMP, Manual
6330 contains new
provisions for water
developments, fences and
traps.
55
large enough to avoid making native
animals susceptible to predation.
iii. Traps. Traps for the removal of
excess wild horses or burros must be
located outside of WSAs whenever
possible. When practical alternatives do
not exist, temporary traps may be located
within WSAs for the effective removal
of animals in excess of the appropriate
management level established for the herd
area. Traps must be situated to minimize
impacts to vegetation and soils. Vehicles
necessary for set-up and take-down of
traps and for transporting excess wild
horses and burros away from the area may
be driven off of existing primitive routes or
boundary roads on a route specified
through the NEPA analysis. At the
completion of the gather, all facilities must
be removed, the route used for trap access
closed to motor vehicles until it is restored
to the original condition, and any new
access route and trap area rehabilitated so
that the route is no longer visible to
subsequent motor vehicle operators.
iv. Motor vehicles and aircraft. Except as
authorized for establishing a trap in b.iii,
above, motor vehicles may not drive off
open primitive routes and roads if doing so
does not meet one of the exceptions to the
non-impairment standard. Helicopters and
fixed wing aircraft may be used for aerial
surveys and for the gathering of wild
horses and burros. §1.6(D)(10)(c)
56
Wildlife Issue IMP WSA Manual 6330 Implications
Coordination
Between
BLM and
State
Agencies
“The BLM will continue to cooperate
with State wildlife agencies in the
management of resident wildlife species
in accordance with established policies
and procedures.
Hunting, fishing, and trapping are
permitted on lands under wilderness
review, under State regulations.
State and Federal agencies may use
temporary enclosures and installations to
trap or transplant wildlife as long as the
nonimpairment criteria are met.”
“The BLM should seek to establish
MOUs with the relevant state wildlife
agencies to identify any state-specific
management activities, policies, and/or
procedures that may involve WSAs and
to determine under what conditions State
fish and wildlife activities will be
conducted in WSAs. Such MOUs, as
well as fish and wildlife management
actions undertaken by the BLM and not
involving the State agency, will include
the provisions described in the following
sub-sections. For all actions, the BLM
will ensure that the non-impairment
criteria are met, or that one of the
exceptions to non-impairment applies.
(See section 1.6.C of this manual.) It is
the expectation that the BLM will work
closely with the state agency in
consideration of all project proposals
involving WSAs. When a project is
under consideration BLM will conduct a
non-impairment analysis and assist state agencies in designing the project to
conform with the non-impairment
standard. Projects will be subject to NEPA
analysis as appropriate.
States regulate where and when the
activities of hunting, fishing, and trapping
Manual 6330 clarifies the
roles of BLM and state
agencies in managing
wildlife in WSAs and
encourages MOUs between
agencies.
57
take place in WSAs. Hunting, fishing, and
trapping are normally unaffected by WSA
designation. The BLM is responsible for
managing the habitat upon which these fish
and wildlife are dependent. In WSAs, the
BLM has an additional responsibility to
assure that management techniques and
tools do not cause impairment to
wilderness characteristics and that fish and
wildlife management activities emphasize
the continuation of natural processes to the
greatest extent possible.” §1.6(D)(11)(a)
Permanent
Structures and
Installations
Certain permanent installations may be
permitted to maintain or improve
conditions for wildlife and fish, if the
benefitting native species enhance
wilderness values. Enhancing wilderness
values in this context means that a natural
distribution, number, and interaction of
indigenous species will be sought; natural
processes will be allowed to occur as
much as possible; and, wildlife species
should be allowed to maintain a natural
balance with their habitat and with each
other.
If healthy, viable, self-sustaining
populations of native species presently
exist within the WSA, then a natural
distribution, number, and interaction has
already been achieved. It is not
permissible, therefore, to artificially
manipulate natural processes to increase
the population of a native species beyond
Permanent facilities used in wildlife
management include guzzlers, water tanks,
and exclosure fences. These structures or
installations are considered either
"existing" or "new."
i. Existing permanent structures and
installations are those that were present on
October 21, 1976 (or prior to the
designation date for Section 202 WSAs not
reported to Congress). Existing wildlife
facilities will be permitted to remain while
the area is under wilderness review, and
may be maintained as long as the
maintenance conforms to the non-
impairment standard.
ii. New permanent structures and
installations include not only proposed
facilities, but those that were built after the
dates described in c.i, immediately above.
New facilities are normally not permitted
in WSAs under the non-impairment
criteria, but may be allowed to be
Unlike the IMP, Manual
6330 distinguishes between
existing and new permanent
structures. Manual 6330
clarifies the criteria for
establishing new structures
for wildlife in WSAs, such as
guzzlers.
58
a natural balance with the habitat within a
WSA. While the existence of a native
species may enhance wilderness values, it
is not the intent of the IMP to "optimize"
population numbers or reach "carrying
capacities" that rely on artificial
installations for subsistence.
Permanent installations to protect sources
of water on which native wildlife depend,
such as exclosures and protective fencing,
may be built if they enhance wilderness
values, are substantially unnoticeable, and
cannot be located outside the WSA
boundary. Permanent riparian, wetland,
and aquatic enhancement installations
may be permitted as long as their purpose
is to enhance wilderness values, protect or
maintain natural conditions, and restore
deteriorated habitat. These installations
must also be substantially unnoticeable.
a. Guzzlers may be maintained, and new
ones may be installed if they enhance
wilderness values, are substantially
unnoticeable, would not require
maintenance involving motor vehicles,
and all alternative locations outside the
WSA have been ruled out. Guzzlers may
be constructed under either of the
following circumstances:
(1) A historic native species does not
presently exist, but the historic record
indicates the WSA was once the
constructed (or remain) if the facility meets
an exception to the non-impairment
criteria.
For example, facilities that clearly protect
or enhance wilderness characteristics by
supporting a natural distribution, number,
and interaction of native species within the
WSA may be allowed. Permanent wildlife
facilities that meet this exception should be
limited to:
A. Structures or installations built for the
benefit of threatened, endangered, or
candidate species if they are
determined essential to species conservation and recovery; or
B. Structures or facilities built to restore
or compensate for habitat that was lost
or deteriorated from modern human
influence.
iii. Except where meeting these
requirements would jeopardize the
recovery of a threatened, endangered, or
candidate species, in addition to meeting
either ii.A or ii.B. immediately above (i.e.
meeting an exception to the non-
impairment standard), wildlife-related
permanent facilities that may be allowed
by the BLM must:
A. be necessary because a determination
has been made that alternative sites
outside the WSA or nonstructural
alternatives will not adequately protect
59
natural range of the native species and
historic perennial water sources inside
the WSA have been lost or are not
available to the native species.
(2) An historic native species exists
within the WSA but the native species
is unable to sustain a natural
distribution, number and interaction
through natural processes or to
maintain a natural balance with its
habitat due to the loss of historic
perennial water sources.
b. In the first circumstance above,
evidence and documentation must be
provided that confirm the WSA was once
the natural range of the native species.
Documentation must also be provided
identifying the number and locations of
historic perennial water sources within the
WSA and the reasons these historic
perennial water sources have been lost or
are not available to the native species.
Restoration of historic perennial water
sources is a more desirable alternative
than the construction of guzzlers for the
benefit of historic native species.
c. If it cannot be substantiated that the
WSA was once the natural range of the
native species, the guzzler project must be
denied. If there are no existing perennial
sources of water found within the WSA
and evidence of historic perennial water
or enhance wilderness characteristics,
B. be substantially unnoticeable,
C. not have a permanent negative impact
on habitat in the WSA,
D. not create a cumulative negative
impact to the vicinity's natural
appearance through its proximity to
other pre-existing facilities in the
WSA, and
E. not require regular vehicle use for
access and/or maintenance (the
authorizing document must describe
how the project will be maintained and
monitored without regular vehicle
access; existing primitive routes may
be used for access in WSAs as long as
such use is consistent with the non-
impairment standard and the applicable
travel management plan).
iv. Unless the primary benefitting species
is threatened, endangered, or a candidate
for listing, the BLM generally will deny
any wildlife water project for which
evidence of the loss of historic natural
water sources cannot be produced.
At a minimum, the EA or EIS for any
proposed new guzzler or other water
capture and delivery structure or
installation must address the following:
the number and locations of historic
natural water sources within the WSA,
60
sources cannot be produced, the guzzler
project must be denied.
d. In the second circumstance above,
evidence and documentation must be
presented that an historic native species
within the WSA is unable to sustain a
natural distribution, number and
interaction through natural processes or to
maintain a natural balance with its habitat
due to the loss of historic perennial water
sources.
the reasons these historic natural water
sources have been lost or are not
available to the native species,
why the native species within the WSA
are unable to sustain a natural
distribution, number, and interaction
through natural processes or to
maintain a natural balance with their
habitat due to the loss of historic
natural water sources, and
why the construction of guzzlers is a
more desirable alternative than
restoration of historic natural water
sources. §1.6(D)(11)(c)
Stocking,
Gathering,
and
Transplanting
Fish &
Wildlife
“Stocking of wildlife and fish species
native to North America may be permitted
within the former historical range of the
species.”
“Introduction of threatened, endangered,
or other special status species native to
North America may be allowed. Such
introductions will be limited to the
historical range of the species unless
introduction is needed to prevent
extinction or is essential for recovery. In
rare instances, permanent enclosures and
related installations may be built for the
benefit of threatened, endangered, or
special status species if they contribute to
a visitor's wilderness experience and if
alternative sites outside the WSA cannot
be located for such construction.”
i. If the species in question is federally
listed as threatened or endangered, the
authority for these actions rests with the
U.S. Fish and Wildlife Service or the
National Oceanic and Atmospheric
Administration National Marine Fisheries
Service and with the States. For non-listed
species, these activities typically are
carried out by the State fish and wildlife
management agencies, which are generally
responsible for determining the type,
number, and distribution of wildlife
involved in these practices. The BLM is
responsible for analyzing activities that
could degrade wilderness characteristics to
determine whether or not they would
satisfy the non-impairment criteria. Close
communication and coordination between
the BLM and State fish and wildlife
management agencies is required on all
Manual 6330 clarifies the
roles of various agencies
regarding listed and non-
listed species.
Both manuals are similar for
stocking, although Manual
6330 adds the purpose of
stocking.
Unlike the IMP, Manual
6330 address gathering
species and applies the non-
impairment standard.
Unlike the IMP, Manual
6330 prohibits the
introduction of non-native
species with a narrow
61
issues regarding stocking, gathering, and
transplanting fish and wildlife.
ii. Stocking of native fish species may be
permitted within the former historical
range of the species. Where non-native
species were being stocked before October
21, 1976 (or prior to the designation date
for Section 202 WSAs not reported to
Congress) such stocking may continue.
The purpose of stocking is to reestablish or
maintain a native species (or non-native
species introduced prior to 1976, or prior to
the designation date for Section 202 WSAs
not reported to Congress) adversely affected by human influence.
iii. Gathering native species (not federally
listed as threatened or endangered) for
relocation may be permitted as long as the
non-impairment criteria are met and the
gather would not create risk that the
species could go into decline. This includes
the use of temporary enclosures used in the
gather. The BLM is responsible for the
analysis and approval of any proposed
surface disturbing activities or construction
of structures or facilities associated with the gather.
iv. For a gather of federally listed
threatened or endangered species, the non-
impairment criteria may be waived under
the requirements of the Endangered Species Act.
exception for listed species
where benefits outweigh the
harm.
62
v. Transplanting will be limited to the
historical range of the species unless
introduction is needed to prevent extinction
or is essential for recovery. The historical
range of the species is determined based on
best available information in coordination
with the State wildlife management
agency. The non-impairment analysis (see
section 1.6.E of this manual) should
consider effects on naturalness, including
the effects on habitat and native species in the WSA.
vi. State and Federal agencies may use
temporary enclosures and installations to
transplant wildlife as long as the non-
impairment criteria are met. The BLM is
responsible for the analysis and approval of
any proposed associated surface disturbing
activities or structure or facility
construction. In rare instances, permanent
enclosures and related installations may be
built for the benefit of threatened,
endangered, or candidate species if
alternative sites outside the WSA cannot be
located for such construction. (See also D.11.c.)
vii. The BLM will prohibit, to extent
practicable and permitted by Federal law,
the introduction of any non-native species
into WSAs. Exceptions to this may be
made for threatened or endangered species
or the rare circumstances where the BLM
determines that the benefits from an
63
introduction of a non-native species clearly
outweigh the potential harm--for example,
biological controls to eradicate non-native
plants. To the extent practicable and
permitted by Federal law, the BLM will
prevent non-native species introduced
elsewhere from becoming established in
WSAs. As noted above, it is important for
the BLM to coordinate and communicate
with the State fish and wildlife agency on
the prevention of non-native species
introduction. §1.6(D)(11)(e)
Removal of
Non-native
Species
“Where exotics were being stocked before
October 21, 1976, the stocking may
continue. Exotics stocked after October
21, 1976 should be eliminated.”
“Except for those species stocked prior to
October 21, 1976 (or prior to the
designation date for Section 202 WSAs not
reported to Congress), the BLM will
remove, to the extent practicable and
permitted by Federal law, any non-native
fish or wildlife species from WSAs, unless
the BLM finds removal of the non-native
species would impair the WSA and its
native species—for example, non-native
vegetation providing critical habitat to a
threatened or endangered species. It is
recognized that some non-native plant or
animal species are so well-established as to
make eradication not feasible.”
§1.6(D)(11)(f)
The IMP established a
general policy of eliminating
non-native species from
WSAs. Manual 6330
qualifies this by stating that
BLM should remove non-
natives “to the extent
practicable” and unless BLM
finds removal would impair
the WSA and its native
species.
Predator or
Other
Wildlife
Damage
Control.
“Animal damage control activities may be
permitted as long as the activity is
directed at a single offending animal, it
will not diminish wilderness values of the
WSA, and it will not jeopardize the
i. Agency action—which will be
coordinated with the U.S. Department of
Agriculture’s Animal and Plant Health
Inspection Service-Wildlife Services—to
control predators (or other native wildlife)
in WSAs should be undertaken only:
Manual 6330 sets out
additional criteria for
predator control.
Unlike the IMP, Manual
64
continued presence of other animals of the
same species or any other species in the
area. Shooting of animals from aircraft
may be allowed, only where specifically
authorized by provisions of State law and
upon the approval of the BLM State
Director.”
A. to prevent transmission of diseases or
parasites affecting human health or safety;
B. to prevent transmission of diseases or parasites affecting other native wildlife;
C. to protect domestic livestock within the WSA; or
D. to enhance recovery of federally listed
threatened or endangered species.
These actions may be taken by the U.S.
Department of Agriculture’s Animal and
Plant Health Inspection Service-Wildlife
Services, the BLM, or delegated to a State
agency. See BLM Manual 6830—Animal
Damage Control.
ii. Predator control activities must be
directed at the specific offending animal or
group of animals. Such activities should be
carried out so as to minimize impacts to the
wilderness characteristics of the WSA
(including the natural interaction of native species).
iii. Nonnative, domestic, and feral animals
maybe killed, hunted, or otherwise
controlled by Federal and State agencies to protect wilderness character.
iv. Acceptable control measures include
lethal and nonlethal methods. Criteria for
choosing a particular method include need,
6330 sets out a new standard
for nonnative, domestic, and
feral animals to be killed,
hunted, or otherwise
controlled by Federal and
State agencies to protect
wilderness character.
Unlike the IMP, Manual
6330 does not specifically
address shooting animals
from aircraft and states that
BLM must “use only the
minimum amount of control
necessary to solve the
problem.”
65
location, environmental conditions, the
preservation of wilderness characteristics,
and applicable Federal and State laws. Use
only the minimum amount of control
necessary to solve the problem.
§1.6(D)(11)(g)
Insect and
Disease
Control
Not specifically address for wildlife
management.
Native insect and disease control activities
will be allowed only to the extent that they
meet the non-impairment criteria or one of
the exceptions. When specific insects and
diseases are documented to be non-native
or introduced organisms, then it may be
reasonable to consider whether the
protection and enhancement of wilderness
characteristics exception to the non-
impairment standard applies.
§1.6(D)(11)(h)
Unlike the IMP, Manual
6330 provides that BLM will
allow native insect and
disease control if they meet
the non-impairment criteria.
If non-native insects or
disease exist, BLM may
examine whether the
enhancement of WC
exception applies.