BLM’s Right-of-Way Program

Date post: 16-Jan-2016
Category:
Upload: yaholo
View: 43 times
Download: 5 times
Share this document with a friend
Description:
IRWA 2013 Federal Agency Update Bureau of Land Management (BLM) U.S. Forest Service (USFS) Energy Corridors & Rapid Response Team. BLM’s Right-of-Way Program. Administer over 106,000 ROWs (most in 11 western states) FY12 collected over $50 million in rent - PowerPoint PPT Presentation
19
IRWA 2013 Federal Agency IRWA 2013 Federal Agency Update Update Bureau of Land Management (BLM) Bureau of Land Management (BLM) U.S. Forest Service (USFS) U.S. Forest Service (USFS) Energy Corridors & Rapid Response Team Energy Corridors & Rapid Response Team
Transcript
Page 1: BLM’s Right-of-Way Program

IRWA 2013 Federal Agency IRWA 2013 Federal Agency UpdateUpdate

Bureau of Land Management (BLM)Bureau of Land Management (BLM)U.S. Forest Service (USFS)U.S. Forest Service (USFS)

Energy Corridors & Rapid Response TeamEnergy Corridors & Rapid Response Team

Page 2: BLM’s Right-of-Way Program

BLM’s Right-of-Way ProgramBLM’s Right-of-Way ProgramAdminister over 106,000 ROWs (most in 11 western states)

FY12 collected over $50 million in rent

Title V of Federal Land Policy and Management Act (FLPMA) of 1976

– wind/solar energy development– transmission lines– roads– wireless telecommunications (broadband)– pipelines (non-oil/gas)

Section 28 of Mineral Leasing Act of 1920 (MLA)– oil pipelines– gas pipelines

Allow non-exclusive use (typical 30 year term with right to renew)

Page 3: BLM’s Right-of-Way Program

USFS’s Special Uses ProgramUSFS’s Special Uses ProgramManage over 74,000 special use authorizations

- Agency collects over $100 million in land-use fees annually

- Federal royalties from oil and gas leases on NFS lands were $136 million in calendar year 2009.

Energy ROWs- 6,600 miles of energy-related pipeline - 15,000 miles of transmission line

Allow non-exclusive use (typical 30 year term with right to renew)

FLPMA and Mineral Leasing Act also direct USFS authorizations

Page 4: BLM’s Right-of-Way Program

Energy Policy Act (EPAct) of Energy Policy Act (EPAct) of 20052005

Section 368 Energy CorridorsSection 368 Energy Corridors

Page 5: BLM’s Right-of-Way Program

EPAct Section 368 Energy EPAct Section 368 Energy CorridorsCorridors

Section 368 directs Secretaries of Interior, Agriculture, Defense, Commerce, and Energy to designate corridors in 11 western states

•2008 DOE, BLM, USFS, DOD, USFWS issue Final Programmatic EIS

•2009 BLM ROD designates 5,000 miles of corridors, amends 92 land use plans

•2009 USFS ROD designates 990 miles of corridors, amends 38 land management plans

NOTE: BLM has thousands of miles of “locally designated” corridors established under FLPMA Section 503

Page 6: BLM’s Right-of-Way Program

Environmental ReviewEnvironmental Review

Page 7: BLM’s Right-of-Way Program

Affected StatesAffected States

Page 8: BLM’s Right-of-Way Program

Section 368 Energy Corridors Section 368 Energy Corridors continuedcontinued

• Corridor Uses: oil, gas, hydrogen pipelines, electric transmission

• Identified centerline, width (typically 3,500’) and compatible uses

• Corridors preferred locations for future projects

• RODs do not mandate projects be confined to corridors

• RODs include Interagency Operating Procedures (IOPs) - mandatory requirements to expedite applications and improve consistency

Page 9: BLM’s Right-of-Way Program

Energy Corridor LitigationEnergy Corridor Litigation

July 2009 multiple NGO’s file suit (Wilderness Society, et al. v. United States Department of the Interior, et al.,)

Plaintiffs identify 45 Corridors of Concern (COC) in 11 states

Siting projects within COCs may involve:– additional litigation– increased mitigation– significant environmental impacts– consideration of alternative siting options

Page 10: BLM’s Right-of-Way Program

Plaintiffs Corridors of ConcernPlaintiffs Corridors of Concern

Page 11: BLM’s Right-of-Way Program

Energy Corridor Litigation Energy Corridor Litigation continuedcontinued

July 2012 case dismissed per Settlement Agreement

Key Actions•Oct 2012 - BLM/USFS invite Tribes, industry, environmental groups to participate in training

•Oct 2013 - July 2014 BLM/USFS/DOE provide quarterly reports to Plaintiffs

•July 2013 - BLM/USFS update corridor guidance and training materials

•July 2013 - BLM/USFS/DOE complete MOU, develop work group, develop corridor study plan

•July 2014 - BLM/USFS/DOE complete corridor study and provide recommendations to agency managers

Page 12: BLM’s Right-of-Way Program

Energy Corridor Litigation Energy Corridor Litigation continuedcontinued

Stakeholders (including the public) will be engaged in: •Corridor review process and revisions to Interagency Operating Procedures (IOPs)

•Future land use plan amendments that consider workgroup recommendations

Current Status•Workgroup established (DOE/BLM/USFS)•Developing MOU•Developing Communication Plan•Revising 3 training courses•Updating policy

Page 13: BLM’s Right-of-Way Program
Page 14: BLM’s Right-of-Way Program
Page 15: BLM’s Right-of-Way Program

MOU SummaryMOU Summary

Approved October 2009 for Coordination of Federal Permitting for Transmission Lines on Federal Lands

Purpose:•expedite siting and construction of qualified projects •improve coordination among applicants, federal agencies, states, tribes•improve uniformity, consistency, and transparency •DOE designates single lead agency, monitors schedules

Qualifying Projects: •Cross jurisdictions of two or more MOU agencies•Generally 230kV and above•Regionally/nationally significant lines

Page 16: BLM’s Right-of-Way Program

Rapid Response Team for Rapid Response Team for Transmission (RRTT) – June Transmission (RRTT) – June

20112011Improve quality and timeliness of transmission permitting, review, and consultation by the Federal government on Federal and non‐Federal lands by:•Coordinating permitting, review, and consultation schedules and processes among Federal and state agencies

•Apply uniform and consistent approach to Tribal consultations

•Resolve interagency conflicts, ensure agencies engaged and meet timelines

•October 2011 announce 7 pilot projects

Page 17: BLM’s Right-of-Way Program
Page 18: BLM’s Right-of-Way Program

RRTT Ongoing ActionsRRTT Ongoing ActionsProjects approved

– CAPX 2020 Hampton-Lacrosse– Susquehanna-Roseland

•Issue resolution for 5 western projects•Develop robust and clear application process

– Tool Kit

•Pursue dedicated, funded transmission teams•Evaluate cost recovery authorities•Best Management Practices

– Template documents– Mitigation guidance– Consistent terms and conditions– Early definition of permit/data requirements

Page 19: BLM’s Right-of-Way Program

Lucas Lucero, Branch ChiefLucas Lucero, Branch ChiefBLM - Washington OfficeBLM - Washington [email protected]@blm.gov

Electric Transmission & Corridors: Electric Transmission & Corridors: www.blm.gov/wo/st/en/prog/energy/transmission.html

Rights-of-Way:Rights-of-Way:http://www.blm.gov/wo/st/en/prog/energy/cost_recovery_regulations.html

Vaughan Marable Vaughan Marable USFS - Special Uses Manager USFS - Special Uses Manager [email protected]@fs.fed.us