of 34
7/28/2019 Blowout and Kill Simulation Sample Report
1/34
Well blowout and dynamic wellkill simulations
Exploration well 5505/5-5 NewField North (PL 555)SampleCo E&P
December 2010
7/28/2019 Blowout and Kill Simulation Sample Report
2/34
Customer:
SampleCo
Customer PO no.: Project:
N/A Project nr. 2010-800070
Document title: Doc. no.: WPA-DOC-2010-800070-00
Well blowout and dynamic wellkill simulation of exploration well 5505/5-5 NewField North
Conclusions:
This report summarizes the blowout and dynamic well kill simulations done for exploration well 5505/5-5 NewField North in
production license PL 555.
The well is to be drilled as a slightly deviated exploration well to test hydrocarbon potential in the Res-1 and Not formations.
Secondary targets include Res-1 and Res-2 formations. Based on client input, Res-1 and Res-2 are evaluated as potential producing
formations. Res-1 and Res-2 are treated as two formations, with common properties for Res-1 and Res-2.
The well is vertical down to last casing @ 3450 m TVD RKB. Top Res-1 is expected @ 3555 m TVD RKB. The formations are planned
drilled with an 8 section to TD @ 4031m MD/3930m TVD RKB. The well design considered includes a 36 x 30 conductor set @
475 m TVD RKB, 20 surface csg set @ 1350 m TVD RKB, 13 intermediate csg set @ 2380 m TVD RKB and a 9 reservoir csg set
@ 3450 m TVD RKB.
Sea depth at location is 364 m MSL. The expected fluid to be explored is gas/condensate.
The well is assumed drilled by the semi-submersible drilling rig West Phoenix, with a 39 m RKB-MSL air gap.
The scenarios investigated is (Section 3.2 for details)
- Kick scenarios partly penetrated Res-1- Swab scenarios fully penetrated Res-1 and Res-2
The worst case scenario is described by an open and unrestricted flowpath, and full penetration of Res-1 and Res-2 formations with
maximum permeability estimates. In such an unlikely event, the maximum blowout potential is found to be 4445 Sm/day of gas
condensate and 17.8 MSm3/day of gas. The risk weighted blowout potential is found to be 701 Sm/day of gas condensate and 2.80
MSm/day of gas for a surface blowout and 706 Sm/day of gas condensate and 2.82 MSm/day of gas for a subsea blowout.
Expected duration of a risk weighted blowout can be predicted based upon statistical data from the Sintef Offshore Blowout
database and industry experience values, and is found to be 13.1 days for a surface release and 23.4 days for a subsea release.
In case of a blowout that will have to be killed remotely via a dedicated relief well, simulations show that an unrestricted surface
blowout from fully penetrated Res-1 and Res-2 formations, through an open/cased hole, will have the highest pumping
requirements.
The worst case scenario can be killed by one single relief well, pumping 10.000 LPM of 2.1 sg mud to a total of 200 m to stop HC
influx. Total mud volume required during the operation, including 2 x bottom up circulation, is 693 m.
Note that the high kill fluid densities needed in the worst case scenario might fracture the formation, and operational procedures
should be prepared for circulation of lighter fluids to stabilize the well.
Rev. Date Description Created by: Approved by :
0 03.12.2010 First version V.Gruner T.Rinde
7/28/2019 Blowout and Kill Simulation Sample Report
3/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:3 of 34
Contents
List of figures ............................................................................................................................................ 4
List of tables ............................................................................................................................................. 4
List of acronyms ........................................................................................................................................ 51 Background and Introduction ......................................................................................................... 6
1.1 Introduction ............................................................................................................................ 6
1.2 Objective of work .................................................................................................................... 6
2 Data & Information Collection ........................................................................................................ 7
2.1 Location and water depth ....................................................................................................... 7
2.2 Drilling facilities ....................................................................................................................... 8
2.3 Reservoir properties ............................................................................................................... 8
2.4 Reservoir fluid information ..................................................................................................... 9
2.5 Well design .............................................................................................................................. 9
2.6 Inflow Performance Relationship ......................................................................................... 11
2.7 Permeability sensitivity ......................................................................................................... 11
2.7.1 Res-1 permeability sensitivity ...................................................................................... 122.8 Res-2 permeability sensitivity ............................................................................................... 12
2.9 Water .................................................................................................................................... 13
2.10 Drilling mud and kill fluid ...................................................................................................... 13
3 Blowout Potentials and Duration .................................................................................................. 13
3.1 Blowout scenarios in general ................................................................................................ 13
3.2 Case scenario definitions ...................................................................................................... 14
3.3 Distribution of flowpath probabilities ................................................................................... 16
3.4 Blowout duration .................................................................................................................. 18
3.5 Risk process and distributions............................................................................................... 20
3.5.1 Permeability risking ...................................................................................................... 20
3.5.2 Final blowout risk procedure ....................................................................................... 21
3.6 Possibility for underground blowout .................................................................................... 23
4 Killing Methods of Blowing Wells ................................................................................................. 23
4.1 Design of the relief well ........................................................................................................ 24
4.1.1 Relief well data ............................................................................................................. 25
4.2 Dynamic wellkill through a relief well ................................................................................... 25
4.2.1 Simulation and model assumptions ............................................................................. 26
4.2.2 Simulation results Dynamic kill simulations .............................................................. 26
4.3 Pump and kill mud considerations ........................................................................................ 28
4.3.1 Possible kill sequence ................................................................................................... 28
4.3.2 Minimum pumping requirements on relief well drilling rigs ....................................... 30
4.4 Figures: Worst case gas-only kill scenario ............................................................................. 31
5 References .................................................................................................................................... 32
6 Appendix list ................................................................................................................................. 33
7/28/2019 Blowout and Kill Simulation Sample Report
4/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:4 of 34
List of figures
Figure 1: Map showing location of PL 555 Source: www.arcticweb.com................................................ 7
Figure 2: The semi-submersible drilling rig West Phoenix ....................................................................... 8
Figure 3: Illustrative well schematics for the 5505/5-5 NewField North exploration well [6] ............... 10Figure 4: IPR relationships fully penetrated Res-1 and Res-2 .............................................................. 11
Figure 5: IPR curves - Res-1 Permeability sensitivity ........................................................................... 12
Figure 6: IPR curves Res-2 Permeability sensitivity .......................................................................... 12
Figure 7: Possible blowout paths for the defined scenarios (Illustrative only). ..................................... 15
Figure 8: Blowout duration data from the Sintef Database and the Scandpower report 2010 [2]. ....... 19
Figure 9: NewField North Illustrative risk process for the surface release case. ................................. 21
Figure 10: Relief well - pump power vs. pump discharge pressure ........................................................ 28
Figure 11: Pump rate vs. BHP in possible kill sequence ......................................................................... 29
Figure 12: Oil/gas and mud content in 5505/5-5 during kill sequence .................................................. 29
Figure 13: Typical mud pump capacity ranges. ...................................................................................... 30
Figure 14: Illustrative summary of blowout and killing of the worst case kill scenario. ......................... 31
List of tables
Table 1: Reservoir data for 5505/5-5 NewField North [4], [5]. ................................................................ 9
Table 2: Fluid conditions for the expected fluid from exploration well 5505/5-5 [4], [5]. ....................... 9
Table 3: Probability distribution of flow paths from 20 years of historical data Floaters. .................. 16
Table 4: Risk criteria in duration distribution. ........................................................................................ 20
Table 5: Permeability risk distribution.................................................................................................... 20
Table 6: Permeability risking Kick scenario 5m reservoir exposure .................................................. 20
Table 7: Swab scenario - Permeability risk distribution ......................................................................... 21
Table 8: Permeability risking Swab scenario Full reservoir exposure ............................................... 21Table 9: Blowout rates and duration distributions for a potential surface release................................ 22
Table 10: Blowout rates and duration distributions for a potential subsea release .............................. 22
Table 11: Minimum bullheading rates in order to ensure displacement of gas. .................................... 24
Table 12: Kill data - Worst-case scenario - Blowout through open hole ................................................ 27
Table 13: Kill data - Blowout through drillpipe ....................................................................................... 27
Table 14: Kill data - Blowout through annulus ....................................................................................... 28
7/28/2019 Blowout and Kill Simulation Sample Report
5/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:5 of 34
List of acronyms
API American Petroleum Institute
BHA Bottomhole assembly
BHP Bottomhole pressure
BOP Blowout preventerCGR Condensate gas ratio
DHSV Down hole safety valve
DP Drillpipe
ECD Equivalent circulating density
GOR Gas oil ratio
ID Inner diameter
IPR Inflow performance relationship
LPM Liter per minute
MD Measured depth
MSL Mean sea level
N/G Net/Gross
OD Outer diameterOH Open hole
OIM Offshore Installation Manager
PWL Planned well location
RKB Rotary kelly bushing
sg. Specific gravity
TD Total depth
TVD True vertical depth
WBM Water based mud
WPA Wellpro Academica AS
7/28/2019 Blowout and Kill Simulation Sample Report
6/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:6 of 34
1 Background and Introduction
1.1 Introduction
This study is part of establishing input for required approval and contingency planning
purposes as required in NORSOK D-010 in terms of estimating the expected blowout ratesand their duration, as well as checking the ability to kill potential blowouts based on defined
scenarios and specified input for the well 5505/5-5 NewField North in PL 555.
Wellpro Academica AS (WPA), an independent and specialized competence center for fluid
modeling and simulation services, was contacted and asked to perform blowout and
dynamic kill analysis for different possible case scenarios during drilling of the exploration
well.
Main objective of well 5505/5-5 is to test hydrocarbon potential in Garn sandstones.
Secondary objective is Res-2 sandstones, Secondary-1 sandstones and Secondary-2
sandstones.
The well is to be drilled as a slightly deviated exploration well. The well is vertical down to
last casing, then slightly deviates to stay parallel to the main bounding fault. TD will be 100m
into the Secondary-2 sandstone. In case of success, the well will be a keeper.
No contract is currently made for drilling rig. There is an option to use West Phoenix after
drilling of NewField (SampleCo), and West Phoenix is used as default regarding rig related
information in this report.
The well design considered includes a 36 x 30 conductor set @ 475 m TVD RKB, 20
surface csg set @ 1350 m TVD RKB, 13 3/8 intermediate csg set @ 2380 m TVD RKB and 9
5/8 reservoir csg set @ 3450 m TVD RKB. A 8.5 section will then be drilled through the
potential hydrocarbon carrier formations. Top Res-1 is expected @ 3555 m TVD RKB.
The expected fluid to be explored is gas/condensate.
1.2 Objective of work
The objectives of this study are:
Calculate and present an expected range of potential blowout rates for the well,
including the worst case flow rates of oil and gas to surface.
Perform a sensitivity analysis with respect to possible blowout scenarios and presentestimates for the blowout rates for the different scenarios.
Estimate flow rate and duration distributions of the blowout rates based on updated
historical data and reliable distribution statistics.
Recommend needed kill fluid density and kill rates for one, or more, relief well(s) for
worst case and expected scenarios.
The flow rate and duration distributions will be estimated based on the Sintef Offshore
Blowout Database [3] and the latest approved evaluation of the Sintef Database data from
Scandpower Risk Management AS [2].
7/28/2019 Blowout and Kill Simulation Sample Report
7/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:7 of 34
WPA will perform dynamic kill simulations in order to document safe killing of a potentially
blowing well, including discussion on the relief well(s) and pumping requirements involved
in the blowout control operation as required in NORSOK D-010.
The Software package OLGA 6.2.7, considered state of the art within dynamic simulation of
multiphase flows, is utilized for the dynamic simulations. PVT is handled using PVTSim and
tuned based on customer input ([Error! Reference source not found.] and [Error! Referencesource not found.]). Blowout cases have been simulated by use of Prosper and verified in
OLGA in order to ensure correct estimates.
In case of a real blowout developing, a more detailed relief well study is recommended in
order to plan for reassessment of the planned relief well path and well intersection. From
experience, extra restrictions such as broken drillpipes or other downhole objects, e.g. fishes
etc., are often present in the flow path. The maximum blowout rates presented in this
report might be reduced by such restrictions. Experience also shows that reductions of the
near wellbore reservoir pressures tend to reduce the actual pumping requirements.
2 Data & Information Collection
2.1 Location and water depth
The well 5505/5-5 NewField North analyzed in this report will be drilled as an exploration
well in production license PL 555, west of Brnnysund. The water depth at location is 364
m. Figure 1 shows the location of the PL 555 in the North Sea.
Figure 1: Map showing location of PL 555Source: www.arcticweb.com
http://www.arcticweb.com/http://www.arcticweb.com/7/28/2019 Blowout and Kill Simulation Sample Report
8/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:8 of 34
2.2 Drilling facilities
Drilling rig contract has not yet been signed. There is a rig tender being reviewed with two
contractors, Det Norske (Songa Delta) and Dolphin (Bredford Dolphin).The rig option is to
continue to use the West Phoenix after OldField. Negotiations are ongoing to determine the
best solution for the NewField North Rig. This report will assume West Phoenix as drilling rigfor 5505/5-5. The air gap of West Phoenix is (RKB-MSL) 39 m.
Figure 2: The semi-submersible drilling rig West Phoenix
2.3 Reservoir properties
The well is to be drilled as a slightly deviated exploration well, penetrating the primary
target Res-1 sandstones with the possible HC bearing formations. Top Res-1 is expected @
3606 m MD/3555 m TVD RKB. Expected reservoir pressure and temperature are 470 bar and
130oC, respectively.
The secondary target is Res-2 sandstones with expected top @3860 m MD/ 3724 m TVD
RKB. Expected reservoir pressure and temperature are 470 bar and 130oC, respectively.
The formations are planned drilled with an 8 section to TD @ 4031 m TVD RKB.
Table 1 shows the reservoir data used in the simulations for the well presented in this
report. Res-1 and Res-2 formations are treated in common in this report, and reservoir
properties are listed based on this.
7/28/2019 Blowout and Kill Simulation Sample Report
9/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:9 of 34
Table 1: Reservoir data for 5505/5-5 NewField North [Error! Reference source not found.], [Error!
Reference source not found.].Res-1 Res-2
Top formation m TVD RKB 3555 3724
Temperature @ res top C 130 130
Pressure BarA 470 470
FIT @ 20 csg sg 1.75 1.75FIT @ 9 5/8 csg sg 1.85 1.85
Gross interval depth meter 52 56
N/G ratio - 0.67 0.875
Net interval depth meter 35 49
Permeability mD 50-200 1-5
Productivity Index, PI Sm/d/bar - -
Skin - 0 0
2.4 Reservoir fluid information
The fluid properties expected to be explored are listed in Table 2. Res-1 and Res-2 are
expected to hold the same reservoir fluid, namely a gas with a GCR of 4000 Sm/Sm. Fluid
properties are based on customer input.
Table 2: Fluid conditions for the expected fluid from exploration well 5505/5-5 [Error! Reference
source not found.], [Error! Reference source not found.].Standard conditions Data
Condensate density at std cond.* kg/Sm 800
Condensate viscosity at std cond.* cP 0.328
Gas density at std cond.* kg/Sm 0.856
Gas viscosity at std cond.* cP 0.008
Gas to Condensate Ratio (GCR) Sm/Sm 4000*std conditions defined as 15C/1.0135 BarAReservoir conditions Data
Gas density at res cond.** kg/m 435
Gas viscosity at res cond.** cP 0.064
Bubblepoint pressure BarA 440Gas expansion factor, Bg Sm/Rm 0.0037**Reservoir conditions defined as 130C/470 BarA
Fluid properties are represented by a black oil model for all simulations presented in this
report, and tuned according to data listed in Table 2.
2.5 Well design
The well is to be drilled as a vertical exploration well with the following well design planned:
- 36 x 30 conductor set @ 475 m TVD, 20 surface csg set @ 1350 m TVD RKB, 13
3/8 intermediate csg set @ 2380 m TVD RKB and 9 reservoir csg set @ 3450 m
TVD RKB. The well is vertical down to last casing.
- A 8.5 section will be drilled through the potential hydrocarbon carrier formations
to TD @ 4031 m MD/ 3939 m TVD RKB
- OD for the DP used when calculating the blowout rates is 5
Figure 3shows an illustration of the planned well.
7/28/2019 Blowout and Kill Simulation Sample Report
10/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:10 of 34
Figure 3: Illustrative well schematics for the 5505/5-5 NewField North exploration well [Error!
Reference source not found.]
Alve North Well Diagram
Formations MD TVD CASING / LITHOLOGY/ Hole Size Casing and Cement MudRKB m SS m EXPECTED PORE PRESS Data Aquisition
Rotary Table 39Sea bed 403 364 36" x 42'' 36" x 30'' Conductor Pipe Seawater with high vis
sweeps
Class G 1.54sg Turned light XL 1.03sg
Conductor Point 475 43626'' 20" Casing, X56, 133# Seawater with high vis
sweeps
Nordland 520 481 Class G Lead 1.3 sg, tail 1.5 sg 1.03 sg
Casing Point 1350 1311
Kai 1420 1381 17-1/2" 13 3/8'' Casing, P-110, 72# VT WBMFIT ~ 1.75 1.45-1.55 sg
Hordaland 1699 1660 Class G Lead 1.3 sg, tail 1.5 sg
Rogaland 1919 1880
Springar 1996 1957
Tech Casing Point 2380 2341
12-1/4" 10-3/4" VM110, 65.7# VT OBM9 5/8" VM110, 53.5# VT 1.45-1.55 sg
Class G 1.9sg
Lysing 2832 2793
BCU 3274 3235 Kick off point
Prod Casing Point 3450 3411
Garn + Not 3606 3540 OBM8-1/2" 1.40 SG
Ile +Upper Ror 3665 3589 FIT ~ 1.85 One Core in reservoirPossibly 3 mini-DSTs
Tofte + Lower Ror 3748 3660 Log reservoirs guaranteed
Tilje 3790 3695 A 7" Liner may be run for future completionre 3908 3795TD 4031 3900
7/28/2019 Blowout and Kill Simulation Sample Report
11/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:11 of 34
2.6 Inflow Performance Relationship
The productivity index is sensitive to parameters such as permeability, penetration length,
N/G ratio, the productive height of the reservoir as well as mechanical skin, inflow
turbulence or skew drainage due to limited penetration. The productivity index is also a
transient parameter that tends to decline shortly after initiation of the production, or as inthis case, a blowout. This is caused by the reduction of the near wellbore reservoir
pressures.
When calculating the blowout potentials, the blowout rates for the different scenarios are
strongly dependent on the permeability, pressure, fluid viscosity and the consecutive
productivity index. Simulations are based on the most likely properties, as given in Table 1
and Table 2.
The IPR relationships for NewField North are given in Figure 4. The IPR relationships shown
are for a fully penetration of Res-1 and Res-2 formations, with the maximum expected
permeability estimates of 200 mD and 5 mD respectively. A blackoil gas model has beenused in the calculations.
Figure 4: IPR relationships fully penetrated Res-1 and Res-2
As Figure 4 shows, the total IPR, evaluated at 3555 m TVD RKB, has an absolute open flow(AOF) of just below 38 MSm/day/bar. Contributions from Res-2 are very small compared to
the much more productive Res-1.
2.7 Permeability sensitivity
Both reservoir sections investigated in this study, Res-1 and Res-2, are subject to
permeability uncertainties. A sensitivity analysis on reservoir permeability is performed and
presented.
0
50
100
150
200
250
300
350
400
450
500
0 5000 10000 15000 20000 25000 30000 35000 40000
Flowing
wellborepressure
[bara]
Gas Rate
[1000 Sm/day/bar]
Total IPR
Garn/Not
Ile/Tilje
7/28/2019 Blowout and Kill Simulation Sample Report
12/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:12 of 34
2.7.1 Res-1 permeability sensitivity
The Res-1 formations are modeled as one productive zone with common properties.
Reservoir permeability is subject to uncertainty and a permeability range of 50-200 mD is
used in the blowout evaluations in this report.
IPR curves applicable for the Res-1 formations are shown in Figure 5.
Figure 5: IPR curves - Res-1 Permeability sensitivity
2.8 Res-2 permeability sensitivity
The Res-2 formations are modeled as one productive zone with common properties.
Reservoir permeability is subject to uncertainty and a permeability range of 1-5 mD is usedin the blowout evaluations in this report.
IPR curves applicable for the Res-2 formations are shown in Figure 6.
Figure 6: IPR curves Res-2 Permeability sensitivity
0
50
100
150
200
250
300
350
400
450
500
0 5000 10000 15000 20000 25000 30000 35000 40000
Flowingwellborepressure
[bara]
Gas Rate
[1000 Sm/day/bar]
Garn+Not - 50 mD
Garn+Not - 100 mD
Garn+Not - 200 mD
0
50
100
150
200
250
300
350
400
450
500
0 500 1000 1500 2000 2500 3000
Flowingwellborepressure
[bara]
Gas Rate
[1000 Sm/day/bar]
Ile+Tilje - 1 mD
Ile+Tilje - 3 mD
Ile+Tilje - 5 mD
7/28/2019 Blowout and Kill Simulation Sample Report
13/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:13 of 34
2.9 Water
Expected depth of the gas/oil-water contact was not given. Conservatively the water
fraction in the simulations is assumed equal to 0.0%, whilst condensed water is accounted
for.
2.10 Drilling mud and kill fluid
No filter cake or formation damage, nor stimulation effects caused by the drilling fluids used,
which might decrease or increase the formation productivity, has been discussed in this
report.
In situations where a relief well is needed to re-establish the well barriers, i.e. situations
where connection to the well is lost or pumping cannot be done from the drilling rig for any
reasons, the kill fluid should be blended for minimum viscosity in order to minimize the
hydraulic resistance. Still, it is important that the density of the kill fluid is compatible with
the formation fracture gradient or that operational measures are established in order to
compensate for possible fluid loss situations after fulfillment of the killing.
In all kill simulations performed in this study a kill fluid viscosity of 10.0 cP is used. This is
assumed conservative with respect to the pumping requirements found.
3 Blowout Potentials and Duration
Blowout potentials are defined as the maximum expected blowout rates for various
scenarios. Most likely expected parameters are to be used, or a weighted distribution of the
same parameters. Whenever necessary, parameters and calculation results should be risked
in order to establish the most reliable probability distributions for expected rates.
The OLF Guidelines for estimation of blowout potentials [1] are used as basis for all flow
rate calculations presented in this report. Distributions of possible flowpaths are given in
accordance with data from the Sintef Offshore Blowout Database [3] and the latest
evaluation of the Sintef Database data in the report from Scandpower Risk Management AS
[2].
3.1 Blowout scenarios in general
A blowout is defined as an unwanted and uncontrolled flow from a subsurface formation
which is released at surface, seabed or into a secondary formation, and cannot be closed by
the predefined and installed barriers.
Blowout potentials, i.e. the expected rates of oil, water and gas, are highly dependent on the
scenario in which the blowout occurs. Lost pipe, junk or complex escape paths for the fluid
will result in dramatically lower blowout rates than a fully open 9 casing all the way from
formation to surface.
For the NewField North exploration well, an unrestricted blowout through the 9 casing,
with exposure to fully penetrated Res-1 and Res-2 formations, will result in a maximum
blowout rate of 4445 Sm3/day of condensate and 17.8 MSm3/day of gas. This rate is related
to the maximum permeability estimates of both Res-1 and Res-2, and is very unlikely to
occur. The risk process in Section 3.5 present risked blowout rates based on an underlying
risk process, where the permeability range presented in Table 1 is accounted for.
7/28/2019 Blowout and Kill Simulation Sample Report
14/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:14 of 34
This unrestricted blowout scenario will in this well set up a drawdown onto the formation of
more than 110 bars (11 MPa). This drawdown might induce a risk of collapse of the
surrounding formation, or initiate production rates of sand, both consequences that can
reduce the rate of fluids flowing from the well. Formation collapse might even kill the well
and thereby stop the blowout entirely.
3.2 Case scenario definitions
Hypothetical blowout scenarios have been investigated in this study, all relevant for drilling
operations. The analyzed case scenarios include blowouts through drill pipe, annulus and
open hole to drill floor and to seabed, implying several blowout scenarios. The last case is a
collective case for simulations of restricted flow.
In order to limit the number of scenarios to analyze, two main categories of incidents are
simulated and are intended to cover all possible scenarios conservatively. The two scenarios
are Kick and Swab, which covers all kicks when entering a formation and all swab scenarios
when pulling out of hole, respectively.
Kick scenarios are represented by a partly penetrated reservoir, while swab scenarios are
conservatively represented by a fully penetrated reservoir.
The following principles in selection of scenarios have been used as basis for simulation
cases:
Blowout through casing/open hole, reservoir partly penetrated, kick scenarios
Blowout through casing/open hole, reservoir fully penetrated, swab scenarios
Blowout through drillpipe, reservoir partly penetrated, kick scenarios
Blowout through drillpipe, reservoir fully penetrated, swab scenarios
Blowout through annulus, reservoir partly penetrated, kick scenarios
Blowout through annulus, reservoir fully penetrated, swab scenarios
Restricted blowout through topside leak, 64/64'' choke
All scenarios listed above have been investigated in this report.
7/28/2019 Blowout and Kill Simulation Sample Report
15/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:15 of 34
Figure 7: Possible blowout paths for the defined scenarios (Illustrative only).
A find in Res-1 and Res-2 is related such that a find in Res-2 is not possible with no find in
Res-1. This result in the following possibilities:
a) HC find in Res-1
b) HC find in Res-1 and Res-2
HC find in none is not evaluated in this report.
Based on this, the following definition is made for simulations performed in this study.
1) Kick scenarios are represented by a partly penetrated Res-1
2) Swab scenarios are represented by fully penetrated Res-1 and Res-2.
See Section 3.5.2 for illustration and results from final risk procedure.
For cases involving a partly penetrated reservoir, i.e. the kick scenarios, a gross penetration
pay of 5 meters is used. The N/G ratio is 1.0, which is considered conservative.
Drilling
BOP
Sealevel
Drilling
BOP
Sealevel
Drilling
BOP
Sealevel
7/28/2019 Blowout and Kill Simulation Sample Report
16/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:16 of 34
3.3 Distribution of flowpath probabilities
In order to establish the best possible statistical estimate for the well, a distribution
between all investigated scenarios and the expected duration for these are to be calculated
based upon the Guidelines from OLF [1]. The statistical values are found based on the Sintef
Offshore Blowout Database [3] and the annual report from Scandpower[2], that are basedupon a more comprehensive analysis of the Sintef database. Hence, irrelevant cases are
removed and probability distributions are adjusted according to observed trends.
Furthermore the operational experience from the Acona Wellpro group of companies, with
more than 25 years of relevant operations is implemented in the calculation of the
probability distribution. These evaluations and their weighting are discussed in detail below.
Table 3 summarizes relevant statistical findings from drilling-, completion and workover
activities from the Scandpower report from January 2010 [2]. In addition to the incidents
listed within drilling, incidents within both completion and workover activites are added to
expand the statistical foundation. These activities are considered to have a similar type ofbarrier system, with drilling mud as the first barrier and the BOP as the second barrier.
Table 3: Probability distribution of flow paths from 20 years of historical data Floaters.
When implementing these data for calculation of flow path distribution the following
assumptions and methodology have been used:
The number of incidents is relatively low and small variations might cause relatively large
alterations in the distribution coefficients, i.e. from one year to another as incidents older
than the limitations set are removed from the statistical material. The statistical uncertainty
will increase even more if some of the findings from the table above are considered
irrelevant for the operation that is to be analyzed.
In order to try predicting the probabilities for the different flow paths possible, a more
detailed analysis is needed. A well operation with dead well, defined as operation where
the fluid column itself is the primary barrier, includes the activities drilling operations,
workover operations and completion operations. Loss of well control in these operations are
initiated by, and limited to, formation kicks or losses caused by unexpected formation
Full Restricted Full Restricted
Outside casing 22.70 % 4.50 %
Outer annulus 18.20 % 4.50 %
Annulus 31.80 % 4.50 % 4.50 %
Open hole 4.50 %
Inside drillstring
Inside test tubing 4.50 %Annulus 4.50 %
Inside drillstring 4.50 % 40.90 %
Inside prod tubing 4.50 % 45.50 %
Outer annulus 27.00 %
Annulus 27.00 %
Inside drillstring 24.30 %
Inside prod tubing 16.20 % 5.40 %
Workover
(7.4 incidents)
Drilling
(22 incidents)
Completion
(4.4 incidents)
Data update: January 2009
Distribution - Floaters
Subsea Topside
7/28/2019 Blowout and Kill Simulation Sample Report
17/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:17 of 34
properties, lack of operational fluid control or swabbing of reservoir fluids from pulling out
of holeactivities or lack of heave compensation.
Since all these three incidents (kick or loss from/to reservoir, lack of fluid control and
swabbing) also are possible from completion and workover operations and that the
secondary barrier in these operations also includes the drilling BOP, the statistical data fromthese two groups are included in the statistical summary together with the data from drilling
operations.
In the final distribution used in this report, the outside casing and outer annulus flow paths
are neglected. Such rejection is supported by the fact that kick procedures are to be
established in order to minimize the risk of an underground blowout. Also, the modeling
process would be too complicated, in terms of describing the flow paths. Hence, reliable
modeling results are beyond reach.
Similar the flow through production/test tubing is interpreted as flow through open
hole/casing.
When drilling production wells, i.e. in mature areas, the risk of running into unknowns are
clearly lower than when drilling exploration wells, i.e. experiencing reservoirs with pore
pressure higher than the corresponding ECD which might induce a formation kick. The
formations pore pressures are provided through estimation for exploration wells. When a
formation kick is observed, an operational procedure normally instructs the driller to stop
further penetration and to close a secondary barrier in the drilling BOP. Furthermore the
kick will be circulated out through the choke lines. In the risk and weighting process it is
anticipated that such kick will be observed relatively shortly after penetrating the formation.
In this report a penetration depth of 5 meters is used, similar to half a joint of drillpipe,
assuming that the bit did not penetrate the formation when the drillpipe last was made up.5 meter penetration of top reservoir is assumed to be a conservative number.
In reality, the choice of penetration length into the reservoir, i.e. 5 m, is not of importance
when evaluating the probability distribution. In fact, it is the mechanisms leading to the
blowout that is important. For the partly penetrated case, the occurrence of a blowout is
due to a kick scenario in the well. For the fully penetrated case, a swab scenario leads to the
possible blowout. The loss of primary barrier by swabbing of reservoir fluids when pulling
out of hole can be caused by pulling to fast, insufficient compensation of the pumping rates
or by a combination of these. Borehole collapse or partly collapse of some strings or
formations might increase the risks of swabbing reservoir fluids. Theoretically such swabbing
may not be discovered before the BHA is at surface.
Accordingly, for this exploration well, the following probabilities are used between partly
and fully penetrated reservoirs.
Blowout initiated when the formation is partly penetrated 60 %
Blowout initiated when the formation is fully penetrated 40 %
For the kick scenarios, i.e. partly penetration, 5 m penetration is used, with a N/G ratio of
1.0, which is considered conservative.
7/28/2019 Blowout and Kill Simulation Sample Report
18/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:18 of 34
Note: It is worth to notice that the risk of flowing through OH, when penetrating top
reservoir only, is assumed irrelevant and the probability of this is given a 0.0 % value. This is
founded upon the fact that the top reservoir cannot be penetrated without having the DP
and the bit in the hole.
Therefore the flow path probabilities in the top penetration scenario, i.e. a kick scenario, aregiven the following values:
Blowout through drill pipe has a probability of 25 %
Blowout through annulus has a probability of 75 %
Blowout through open hole to surface has a probability of 0 %
Similar, the fully penetrated, i.e. swab scenario, are given the following probability
distribution:
Blowout through drill pipe has a probability of 21 %
Blowout through annulus has a probability of 62 %
Blowout through open hole to surface has a probability of 17 %
In all drilling operations, and most other well operations as well, a Blowout Preventer (BOP)
stack of valves and rams defines the secondary barrier against uncontrolled outflow of
reservoir fluids. The BOP testing program and its procedures ensure that a BOP stack is
experienced as extremely reliable equipment. This is further emphasized by the number of
independent rams in the BOP and the requirement for accumulator capacity. Based on this,
the risk of a total failure of the BOP is assumed to be very low.
Once a blowout has occurred, the BOP has failed or has not been activated. Given such
unlikely failures, and based on the OLF Guidelines for estimation of blowout potentials[1],
the following distribution has been used for partly or full BOP failure:
Restricted flow area has a probability of 70 %
No restriction has a probability of 30 %
The different consequences of a partial failure in the BOP are difficult to predict. In the OLF
Guidelines for estimation of blowout potentials it is proposed to model a partly failure as
95% reduction of the available fluid flow area. As restriction in available flow paths also can
be caused by pipe in hole, fish/junk or collapse of the borehole itself, Wellpro Academica
suggest that modeling of a partly failure is better described with a restriction similar to
64/64 flow area for all scenarios. This is justified by the fact that the remaining flow area
now is independent of the wellbore design or the size of the drillpipe used.
3.4 Blowout duration
A blowout may be stopped by several remedial actions. These are divided into the following
categories:
- Bridging, i.e. collapse of the near wellbore due to low pressure and/or high
production rates.
- Intervention from crew
- Subsea or topside attempt requiring additional equipment
- Drilling of relief well intersecting the blowing well
7/28/2019 Blowout and Kill Simulation Sample Report
19/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:19 of 34
If one or more relief wells are necessary to regain control of the well, the time needed for
mobilization and drilling may vary. We can assume that the relief wells can be drilled with
the same rate as the exploration well, but in addition ranging runs are required, e.g. with
electromagnetic ranging tools. The time required to run such equipment must be taken into
account. The time will depend upon drilling intersection depth, rig availability in general and
in the specified area and weather conditions.
For the 5505/5-5 NewField North well, drilling of one relief well is estimated as follows:
Decision to drill the relief well: 3 days
Termination of work, sail to location, anchoring and preparation : 12 days
Drilling relief well to intersection: 45 days
Homing in: 10 days
Total time to kill well: 70 days
Assumptions are made that the relief well will successfully kill the well after 70 days.
In order to give best possible distribution estimate, the probability distribution for the
different historical incidents must be found. The figure below is presented from the
Scandpower reported data from 2010 and presents the probability that a blowout is still
active after a certain number of days and several mechanisms may have been tried.
Figure 8 describes the probability of killing a well after a number of days based on the use of
one single kill mechanism.
Figure 8: Blowout duration data from the Sintef Database and the Scandpower report 2010 [2].
As can be seen from the figure above, multiple mechanisms may work together in order to
stop the blowout. Scandpower reports that 77% of all blowouts can be stopped by bridging,
70% can be stopped by intervention topside and 43% can be stopped by intervention
subsea, if the mechanism evaluated is the only mechanism to stop the leak [2].
Table 4 summarizes the risk criteria used in the distribution analysis in Chapter 3.5.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 5 10 15 20 25 30 35 40 45 50
Percentage
Days
Wells still flowing after subsea attempts
Wells still flowing after topside attempts
Wells still flowing after natural bridging
7/28/2019 Blowout and Kill Simulation Sample Report
20/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:20 of 34
Table 4: Risk criteria in duration distribution.
Risk of a blowout duration of 2 days P2The blowout could be controlled by measures
performed from the existing rig
Risk of a blowout duration of 15 days P15The blowout could be controlled by bringing
in additional equipment
Risk of a blowout duration of 70 days P70The blowout will have to be killed by drilling a
dedicated relief well.
3.5 Risk process and distributions
From the detailed analysis presented in the previous section the probabilities for all relevant
scenarios were found. According to the OLF Guidelines for estimation of blowout
potentials all possible scenarios should be risked and blowout potentials shall be weighted
respectively.
Note: The overall probability of finding hydrocarbons in a well, which again introduces a
certain risk for a blowout shall be included either in the environmental analysis or in the
blowout analysis (this report). This value is neglected in this report and will have to be
included in the environmental analysis.
3.5.1 Permeability risking
The formations to be investigated in this report are all presented with a permeability range.
A log normal probability distribution gives highest probability for the low case, as shown in
Table 5:Table 5: Permeability risk distribution
Formation Low Medium HighRes-1 50 mD 100 mD 200 mD
Res-2 1 mD 3 mD 5 mD
Probability 50% 30% 20%
All Kick scenarios are risked according to the input in Table 5. The risked rates presented in
Table 6 and Table 7 (far right column) are used as input to the final risk process in Section
3.5.2.
Kick scenario 5m penetration of Res-1
Table 6 and Table 7 list gas condensate rates for the specified scenarios. The far right column
of the individual tables represents the risked rate of gas condensate for the range of
permeability. Risking of flowpaths are introduced in Section 3.5.2.
Table 6: Permeability risking Kick scenario 5m reservoir exposureUnrestricted Flowpath
50 mD 100 mD 200 mD Risked
[Sm/d] [Sm/d] [Sm/d] [Sm/d]
OH 5 mSubsea 635 1232 2156 1118
Surface 647 1243 2172 1131
DP 5 mSubsea 475 655 788 592
Surface 463 626 745 568
ANN 5 mSubsea 571 926 1255 814
Surface 576 933 1261 820
Restricted Flowpath
50 mD 100 mD 200 mD Risked
Sm/d] [Sm/d] [Sm/d] [Sm/d]
OH 5 mSubsea 424 543 621 499
Surface 423 540 616 497
DP 5 mSubsea 373 461 518 428
Surface 363 447 500 415
ANN 5 mSubsea 404 511 582 472
Surface 403 508 577 469
Note: The methodology for estimating most likely duration of a blowout are under
revision and the methodology are likely to be changed or updated later in 2010.
7/28/2019 Blowout and Kill Simulation Sample Report
21/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:21 of 34
Swab scenario Fully penetrated Res-1 and Res-2
To simplify the model and restrict the number of scenarios, the reservoir permeability of
Res-1 and Res-2 is modeled in a low, medium and high permeability scenario. I.e. all
combinations of permeability are not simulated. This leads to the following permeability
scenarios:
Table 7: Swab scenario - Permeability risk distributionLow Medium High
Res-1+Not / Ile+Tilje 50/1 mD 100/3 mD 200/5 mD
Probability 50% 30% 20%
Table 8: Permeability risking Swab scenario Full reservoir exposureUnrestricted Flowpath
50/1 D 100/3 mD 200/5 mD Risked
Sm/d] [Sm/d] [Sm/d] [Sm/d]
OH FullSubsea 2562 3570 4420 3236
Surface 2630 3649 4445 3299
DP FullSubsea 847 905 936 882
Surface 799 850 877 830
ANN FullSubsea 1406 1597 1708 1523
Surface 1411 1601 1712 1528
Restricted Flowpath
50/1 D 100/3mD 200/5 D Risked
[Sm/d] [Sm/d] [Sm/d] [Sm/d]
OH FullSubsea 651 681 696 669
Surface 653 679 691 668
DP FullSubsea 544 564 574 556
Surface 525 545 555 537
ANN FullSubsea 613 641 655 630
Surface 609 634 647 624
3.5.2 Final blowout risk procedure
The process diagram in Figure 9 shows the risk process which is implemented in the analysis
presented in this report, and the resulting weighted blowout rates of oil for a surface
release.
Surface release vs. subsea release
When drilling from a floater, anchored or dynamically positioned, the OIM will try to pull the
rig off from location shortly after an uncontrollable well integrity issue is unveiled and anysurface attempt to stop the flow has not succeeded or have been evaluated as unlikely to
succeed. This leads to the two different duration estimates for a surface and a subsea
release as presented in Table 9 and Table 10.
Figure 9: NewField North Illustrative risk process for the surface release case.
Step 5 Step 6
Total Risk
Oil blowout
potential
[%] [Sm/day]
0.00 % 1131
0.00 % 497
13.50 % 82031.50 % 469
4.50 % 568
10.50 % 415
2.04 % 3299
4.76 % 668
7.44 % 1528
17.36 % 624
2.52 % 830
5.88 % 537
100.00 % 701 Sm/day 2.80 MSm/day
0.43
0.08
0.13
0.00
0.440.59
0.10
0.17
0.27
0.13
0.45
Step 7
Risked oil
blowout rate
[Sm/day]
0
0
111148
26
44
67
32
114
108
21
32
Formation Penetration Flowpath
Step 8
Risked Gas
blowout rate
[MSm/day]
0.00
Step 1 Step 2 Step 3
BOP Status
Step 4
Yes
Kick - 5mGarn+Not
Swab - FullGarn+NotIle+Tilje
60%
40%
9 5/8"Csg
Annulus
Drillpipe
9 5/8"Csg
Annulus
Drillpipe
0%
75%
25%
17%
62%
21%
Restricted
Open
Restricted
Open
Restricted
Open
Restricted
Open
Restricted
Open
Restricted
Open
30%
70%
30%
70%
30%
70%
30%
70%
30%
70%
45%
70%
7/28/2019 Blowout and Kill Simulation Sample Report
22/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:22 of 34
All values in Figure 9 above are repeated in the tables below for improved readability. The
risked blowout rates and duration distributions are listed in the following tables; Table 9 for
surface release, and Table 10 for subsea release.
Table 9: Blowout rates and duration distributions for a potential surface release
Table 10: Blowout rates and duration distributions for a potential subsea release
The risk process illustrates the most likely expected blowout rates for an uncontrolled
blowout from the 5505/5-5 NewField North well. These values are risk weighted; therefore
both higher and lower rates may be experienced in a real blowout. The risked values arequalified numbers for likely volumes expected, and are to be used when evaluating the
possible environmental impact from the well.
As can be seen from Figure 9 and the tables above, the expected gas condensate blowout
rate from the NewField North exploration well is 701 Sm/day for a surface release point and
706 Sm3/day for a subsea release point. The corresponding risked blowout rates of gas are
2.80 MSm3/day for a surface release point and 2.82 MSm3/day for a subsea release point.
There is no significant difference in blowout rates between surface and seabed releases.
The risked durations for surface and subsea release, are 13.1 days and 23.4 days,
respectively.
Note: The risked blowout rates shall not be used for evaluating possible kill methods or
requirement.
The worst case scenario is described by the scenario with an open and unrestricted flowpath
and fully penetration of Res-1 and Res-2 formations with maximum permeability estimates.
In such an unlikely event, the maximum blowout potential is found to be 4445 Sm/day of
gas condensate and 17.8 MSm3/day of gas.
Step 5 Step 6
Total Risk
Oil blowout
potential
P2
t < 2 days
P15
t < 15 days
P70
t
7/28/2019 Blowout and Kill Simulation Sample Report
23/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:23 of 34
3.6 Possibility for underground blowout
An underground blowout is defined as uncontrolled flow from one or more formations, into
one or several formations. If the receiving formations are located above possible sealing
rocks, such a blowout might develop into an uncontrolled release to seabed.
In a well control situation, the formation below the last casing shoe could be exposed to
pressures higher than the corresponding fracture pressures. Based on lightest possible fluid
column from the reservoir to the casing shoe, an analysis is performed to evaluate possible
pressure conditions at the last casing shoe.
In the NewField North well, a 9 casing is planned set at 3450 m TVD RKB. At this casing
shoe, the fracture gradient is estimated to 1.85 sg, equivalent to 626 Bara. The fracture
gradient is estimated based on a provided FIT of 1.85 sg. This is considered conservative.
Assuming shut in with light gas from the Res-1 and Res-2 formations, with the reservoirs
expected pressurized to 470 Bara, the fracture pressure cannot be exceeded at the givencasing shoe depth.
Hence, based upon the given fracture gradients and expected formation pore pressures,
WPA has evaluated the risk of experiencing an underground blowout as less likely. Such
blowout has been disregarded from this report.
4 Killing Methods of Blowing Wells
A blowout can be divided into four main categories with respect to the remedial action
needed to re-control the well:
- Interventions from the rig
- Bridging
- Drilling of relief well
- Natural causes
Interventions from the rig
If the drilling rig is still intact and possible to work on, several remedial actions can be
foreseen as possible methods for killing of a blowout. Possible solutions are:
- Mechanical actions
- Dynamic actions
Mechanical actions can be installation of a new wellhead on top of the existing one,
installation of additional, or replacement of valves or closure of already installed valves, like:
- BOP valves
- Swab, master or wing valve in the X-mas tree
- DHSV
Possible dynamical actions from the drilling rig could be circulation of fluids or cement into
the well. High density fluid might kill the well hydrostatically, whilst high pumping rates
might kill the well hydrodynamically. Bullheading intends to pump at sufficient pumpingrates to overcome the rising velocity of the gas bubbles in order to displace the well fluids
7/28/2019 Blowout and Kill Simulation Sample Report
24/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:24 of 34
with kill fluids. Kill fluid may be lubricated, circulated or bullheaded into the wellbore
dependent on the actual status of the well. Table 11 shows necessary pumping rates needed
in order to ensure that all gas found in the wellbore will move downwards as fluid is pumped
into the same wellbore from topside connections. Table 11 is generic and for information
only, and assumes completed well with installed X-mas tree.
Table 11: Minimum bullheading rates in order to ensure displacement of gas.
Needed bullheading rates toensure gas displacement
Verticalwell
Deviatedwell
[LPM] [LPM]
9 casing 1350 2300
7 tubing 550 950
5.5 tubing 300 550
Bridging
The majority of blowing wells are killed by themselves because of bridging. According to the
Scandpower report approximately 77% of the historical blowouts could be stopped by
bridging if no other mechanisms or manmade attempts were initiated. Bridging mechanisms
might be:
- Sand or rock accumulates inside the wellbore
- Formation collapses due to high flowing rates and high drawdown pressure
- Formation of hydrates blocking the flow paths
Drilling of a relief well
If the blowing well cannot be controlled otherwise, a dedicated relief well will have to be
drilled. A relief well is to establish a secondary flow path directly into the blowing well,
wherein kill fluid can be pumped. Such action is extremely time consuming and involves
mobilizing of one, or more, new drilling rigs, anchoring, controlled survey and large volumes
of kill fluids pumped at high pumping rates directly into the blowing well.
Natural causes
Other possible mechanisms stopping a blowing well could be:
- Pressure depletion of the blowing reservoir
- Stopping of gas lift, gas- or water injection
- Coning of water or gas into the blowing well
4.1 Design of the relief well
Surface considerations
According to regulations a minimum spud distance from the blowing well is suggested to be
500 meter. Corporate regulations might be even more conservative, and the distance might
also be increased for better logistics and/or improved access for emergency and oil spill
vessels. Because of these elements, some companies recommend a minimum distance of
1000 1500 meters. The spud location should take into account wind, sea current and rig
anchoring. Normal caution procedures with respect to shallow gas, casing design and barrier
philosophy shall imply. The relief well drilling rig shall not interfere with any subsea
installations, pipelines or cables.
7/28/2019 Blowout and Kill Simulation Sample Report
25/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:25 of 34
The location shall be selected so that smoke, fumes, hydrocarbons or toxic gases may not
reach the relief well drilling rig. Therefore local wind and current patterns for the specific
area and time of the year must be addressed.
Normally, two relief well locations should be identified. In this report, 1000 meters are used
as horizontal distance from 9 casing shoe to relief well rig.
Relief Well design considerations
Normal drill pipe and equipment should be planned for. In this evaluation, a well design
similar to the main well is assumed.
Wellpath considerations
In order to minimize the blowout duration, the well path of the relief well should be as short
as possible. This also reduces the hydraulic power needed to deliver the necessary kill rate.
East-West direction is preferred, due to uncertainties in the survey tools. The well path
should be suitable for wireline service. Hence, inclination should be less than 60-65.
Pumping considerations
Pumping through both drillpipe and annulus is not recommended, because of the
importance of having control over the flowing bottomhole pressure. It is possible to utilize
the drillpipe in the relief well as a downhole pressure gauge. Water will be pumped at a low
rate and the topside pressure will be measured and the hydrostatic water gradient added.
The total volume of kill fluid needed for a dynamic kill operation is the sum of:
Volume of mud to fill the relief well
Required pump rate times the time to stop inflow (FBHP > PRESERVOIR)
Two hole volumes of the blowout well to ensure two proper bottom up
circulations
4.1.1 Relief well data
A relief well design similar to the production well is assumed. A simplified survey was
generated for the relief well, based on the below listed design.
A 9 casing is assumed set as the last casing @ 3350 m TVD RKB, approximately 100
meters prior to the intersection point, drilling a 8 OH into the blowing well just below the
9 shoe of5505/5-5.
4 kill and choke lines are assumed in the evaluated scenarios.
5/5 OD drillpipe is used in the relief well with a 60 meter BHA of 6.5 OD.
4.2 Dynamic wellkill through a relief well
Dynamic simulations were performed in order to design a suitable relief well capable of safe
killing of the maximum blowout rates from the well. Dynamic simulations are performed
utilizing the OLGA 6.2.7 software package, considered state of the art within dynamic
simulation of multiphase flows.
Main objective was to identify the worst case scenarios and their respective kill
requirements with respect to pumping rates and kill fluid density, assuming that the kill
7/28/2019 Blowout and Kill Simulation Sample Report
26/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:26 of 34
operation will have to be carried out through relief wells, intersecting the main well just
below the last casing shoe.
4.2.1 Simulation and model assumptions
A discussion on simulation choices follows. The simulation results are summarized in tables.
Several combinations of kill mud density and kill rates through the relief well are presented,
as well as various number of relief wells.
Reservoir fluids and their mobility
Due to the sea water gradient and the pressure gradient in the blowing well in this specific
case, the blowout rates for a surface release will be insignificantly higher than from a subsea
release. However, killing of a blowout with a surface release is more challenging than a
subsea release due to the higher pressure at the outlet of the blowing well in the subsea
case.
Therefore, the dynamic wellkill evaluations done in this report, where the blowout is killedthrough a relief well, is mainly performed for a blowout with surface release from a fully
exposed Res-1 and Res-2 formations. Killing of worst case openhole scenario is also
performed for blowout with subsea release due to the Subsea/Surface discussion performed
in Section 3.5.2.
The fluid column that will kill the well is generated between the last casing shoe and topside.
Depletion
In case of a real blowout developing, large volumes of reservoir fluids will be produced to
surface and the near wellbore pressure will deplete accordingly. The simulations presented
in this report do not include such depletion and will therefore be conservative compared tothe requirements at the time of the actual kill operation.
4.2.2 Simulation results Dynamic kill simulations
Blowout through openhole
An unrestricted surface blowout through openhole represents the most difficult kill scenario
evaluated in this report.
Simulations show that a surface blowout from fully penetrated Res-1 and Res-2 formations,
through an 8 openhole section and an open 9 casing set at 3450 m TVD RKB, can be
killed by means of one single relief well only and 2.1 sg mud, pumping 10000 LPM to a totalof 200 m kill mud to stop hydrocarbon influx from the reservoir. Estimated total volume
mud required during the operation, including 2 x bottoms up circulation, is 693 m of mud.
Note that high kill fluid densities needed might fracture the formation and operational
procedures should be prepared for circulation of lighter fluids to stabilize the well after
hydrocarbon influx is stopped.
The kill requirements found are presented in Table 12, and represent kill requirements for
an unrestricted blowout through an open hole, from reservoir to the surface/subsea release
point.
7/28/2019 Blowout and Kill Simulation Sample Report
27/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:27 of 34
Variations of kill rate and relief well designs are presented in order to unveil the possibilities
found to reduce the number of relief wells required to one single well. A variation in
drillpipe OD and kill-/choke line ID is presented.
Pump down through the inside of the relief well drill pipe can be done in order to increase
the flow area even more and hereby further reduce the hydraulic resistance. Please notethat this procedure should be considered with care, as the pressure reading as described in
Section 4.1 is lost. This option is reported used on the Montara blowout in 2009.
Table 12: Kill data - Worst-case scenario - Blowout through open holeBlowout path Release
point
Relief well info Reservoir
exposure
Minimum
Kill fluid
Density
Kill
vol
Total vol
req.
Min hp
req
Max
topside
press.
Total rate
req.
#
relief
wells
[sg] [m] [m] [hp] [bar] [lpm]
9 csg @
3450 m TVD
RKB
Surface9 csg, 5.5" DP,
4" kill and choke lines
Res-1
Res-22.0 226 794 < 500 < 50 11000 2
9 csg @
3450 m TVD
RKB
Surface9 csg, 5" DP,
4.5" kill and choke lines
Res-1
Res-22.0 226 794 < 500 < 50 11000 2
9 csg @
3450 m TVD
RKB
Surface9 csg, 5.5" DP,
4" kill and choke lines
Res-1
Res-22.1 245 813 < 500 < 50 10000 2
9 csg @
3450 m TVD
RKB
Surface9 csg, 5.0" DP,
4" kill and choke lines
Res-1
Res-22.1 200 693 7102 272 10000 1
9 csg @
3450 m TVD
RKB
Surface9 csg, 5.5" DP,
4" kill and choke lines
Res-1
Res-22.2 342 835 7482 318 9000 1
9 csg @
3450 m TVD
RKB
Subsea9 csg, 5.5" DP,
4" kill and choke lines
Res-1
Res-22.2 212 551 7482 318 9000 1
9 csg @
3450 m TVD
RKB
Subsea9 csg, 5.5" DP,
4" kill and choke lines
Res-1
Res-22.2 234 573 5692 256 8500 1
Blowout through drillpipeThis case is defined as a blowout through the in-hole drillpipe, and assumes closed BOP with
no restrictions in drillpipe, or topside restrictions such as Kelly-cock or kick-stand, see Figure
7 for an illustrative example.
Killing of a blowout through the drillpipe does not require large kill rates or pit capacities.
Successful killing is performed by moderate rates with 1.5 sg mud.
Table 13: Kill data - Blowout through drillpipeBlowout path Release
point
Relief well info Reservoir
exposure
Minimum
Kill fluid
Kill vol Total vol
req.
Min hp req Max topside
press.
Total rate
req.
# relief
wells
[sg] [m] [m] [hp] [bar] [lpm]
5.5" drillpipe@ 3450 m
TVD RKB
Surface 9 csg, 5.5"DP, 4" kill and
choke lines
Res-1Res-2
1.5 46 225 < 500 < 50 2500 1
Blowout through annulus
This case describes a surface blowout through the annulus between the drillpipe and the 9
casing. See Figure 7 for an illustrative example.
Simulations show that blowout through the above specified annulus could be by moderate
kill rates, pumping 1.7 sg mud @ 4000 LPM.
7/28/2019 Blowout and Kill Simulation Sample Report
28/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:28 of 34
Table 14: Kill data - Blowout through annulus
Blowout path
Release
point Relief well info
Reservoir
exposure
Minimum
Kill fluid Kill vol
Total
vol req.
Min hp
req
Max topside
press.
Total
rate req.
# relief
wells
[sg] [m] [m] [hp] [bar] [lpm]
9 5/8" csg @
3450 m TVD
RKB
Surface
9 5/8" csg, 5.5"
DP, 4" kill and
choke lines
Res-1
Res-21.7 180 567 < 500 < 50 4000 1
9 5/8" csg @3450 m TVD
RKB
Surface9 5/8" csg, 5.5"DP, 4" kill and
choke lines
Res-1
Res-21.8 112 499 < 500 < 50 4000 1
4.3 Pump and kill mud considerations
4.3.1 Possible kill sequence
The dynamic kill operation requires large pump rates and heavy kill mud to overcome the
reservoir pressure. The graph presented in Figure 10show pump rates vs. gauge pressure on
the relief well mud pumps, in a possible kill sequence.
The kill sequence presented utilizes heavy 2.1 sg. kill mud until BHP exceeds the reservoirpressure in Res-1 and influx from the reservoirs is stopped. A that point, kill mud density at
the relief well rig is switched to 1.6 sg mud in order to prevent formation fracture.
When the BHP exceeds the reservoir pressure, the relief well pump rate is reduced to 1000
LPM during a circulation sequence to circulate all remaining hydrocarbons from the 5505/5-
5 well.
Figure 10 show pump discharge pressure and hydraulic power requirements during a kill
operation of a worst case scenario, where a less dense kill mud is utilized during the
circulation sequence, in order to prevent formation fracture.
Figure 10: Relief well - pump power vs. pump discharge pressure
Figure 11 represent the same sequence as for Figure 10, but show the pump rate and
bottom hole pressure (BHP) at Res-1 (3555 m TVD RKB).
0
100
200
300
400
500
600
700
0
1000
2000
3000
4000
5000
6000
7000
8000
0 1 2 3 4 5
Pumppressure
[bara]
Pumppower
[hP]
Time
[hrs]
Pump power
Pump pressure
BHP exceeds Pres of Garn/Not. Pump
rate reduced during circulation
7/28/2019 Blowout and Kill Simulation Sample Report
29/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:29 of 34
Figure 11: Pump rate vs. BHP in possible kill sequence
Figure 12 illustrates total oil/gas content and mud content in the 5505/5-5 well during the
proposed kill sequence. Circulation of mud should continue until all hydrocarbons are
evacuated from the well.
Figure 12: Oil/gas and mud content in 5505/5-5 during kill sequence
0
100
200
300
400
500
600
700
0
2000
4000
6000
8000
10000
0 1 2 3 4 5
Pressure
[bara]
Pumprate
[LPM]
Time
[hrs]
Pump rate
BHP - Garn/Not
Reservoir Pressure
0
50
100
150
200
250
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
Volume
[m]
Time
[hrs]
Oil and gas content in well
Mud content in well
BHP exceeds Pres. Switch to
1.6sg mud at relief well rigBHP stabilizes at a pressure
equivalent to a 1.6 sg mud gradient
7/28/2019 Blowout and Kill Simulation Sample Report
30/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:30 of 34
4.3.2 Minimum pumping requirements on relief well drilling rigs
The engaged rig(s) to drill the relief well in order to kill the blowout scenarios evaluated for
the NewField North exploration well will have to meet the following minimum capabilities,
in order to ensure safe and reliable killing of a potential blowout:
No of drilling rigs: 1
Total pump capacity: 10.000 LPM @ 272 barg
Minimum horsepower req.: 7102 HP
Typical mud-pump setup: 4x2000 HP
Minimum pit capacity pr rig: 700 m
Kill and choke line dimensions: 4 ID
Figure 13: Typical mud pump capacity ranges.
4000
6000
8000
10000
12000
14000
16000
250 300 350 400 450 500
Pumprate
[LPM]
Pressure
[barg]
Typical mud pump capacity ranges
4 x 2200 HP mud pumps
3 x 1600 HP mud pumps
7/28/2019 Blowout and Kill Simulation Sample Report
31/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:31 of 34
4.4 Figures: Worst case gas-only kill scenario
Instalation: West Phoenix
Well no: 6607/12-2
Well type: Exploration
Well status: Planned
Date: 29/11/10
Revision no: 01
Prepared by: V.Grner
Approved by: T.Rinde
Killing of worst case
blowout rate scenario
Operation info
Comments/Notes
Worst Case ScenarioWell info
Blowout Rate: 17.8 Sm/day
9 " csg to seabed
403 meter - 21" marine riser
Totalt well & riser volume: 210m
Relief well info
9 " tapered csg in relief well
8 OH to intersection (~100m)
5.0" OD drillpipe
60 meter BHA 6.5" OD
2 x 4" ID kill / choke lines
75 meter 8" fixed surface line (ID =7.2")
Relief well length: 3731 m (Surface TD)
Intersection point: 3450 m TVD RKB
Pumping info
Total pump rate: 10000 LPM Minimum kill fluid density: 2.1 sg
Minimum kill volume: 200 m
Total volume required: 693 m
Minimum pump power pr rig: 7102 hP
Minimum surface pressure: 272 BarG
36" x 30" Conductor
475 m TVD
13 "csg
2380 m TVD RKB
Seabed 364 m MSL
8 OH
TD 4031 m TVD
RKB-MSL 39 m
Drilling
BOP
Sealevel
Top Garn/Not 3555
m TVD RKB
Intersection
3450 mTVD RKB
20" csg1350 m TVD RKB
9 " csg
3450 m TVD
RKB
Top Ile/Tilje 3724
m TVD RKB
Pres 470 bara
Pres 470 bara
Figure 14: Illustrative summary of blowout and killing of the worst case kill scenario.
7/28/2019 Blowout and Kill Simulation Sample Report
32/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:32 of 34
5 References
1. Nilsen, Thomas; OLF Retningslinjer for beregning av utblsningsrater og - varighet til
bruk ved analyse av miljrisiko - Rev. nr. 02, 15. januar 2007.
2. Blowout and Well Release Frequencies - Based on SINTEF Offshore Blowout Database,
2009, Report, Scandpower Risk Management. Report no. 80.005.003/2010/R3,
17.03.2010.
3. Sintef Offshore Blowout Database
7/28/2019 Blowout and Kill Simulation Sample Report
33/34
Revision:
0
Date:
03-12-2010
Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth
Page:33 of 34
6 Appendix list
1. About Wellpro Academica AS
7/28/2019 Blowout and Kill Simulation Sample Report
34/34
Appendix 1: About Wellpro Academica ASWellpro Academica, established as a specialized competence center for fluid modeling and
process control, employs specialists, mainly with PhD degree and extensive backgrounds
from the industry. We have advanced software packages and simulation models available
for our clients.
Typical services provided by Wellpro Academica are:
Flow assurance simulations and advice
Computational Fluid Dynamics (CFD) simulations and advice
Dynamic wellkill analyses
Blowout analyses
Well and flowline simulations and optimization
Process simulations and de-bottlenecking
Well and flowline allocation services
Wellpro Academica personnel have a unique blend of competence. The company provides
senior modeling services to a wide range of the industry from solar and renewables, via
metallurgical, to the oil and gas industry. Our strength is the competence, the diversity and
the ability to transfer this know-how.