+ All Categories
Home > Documents > Blowout and Kill Simulation Sample Report

Blowout and Kill Simulation Sample Report

Date post: 03-Apr-2018
Category:
Upload: meubro
View: 217 times
Download: 0 times
Share this document with a friend

of 34

Transcript
  • 7/28/2019 Blowout and Kill Simulation Sample Report

    1/34

    Well blowout and dynamic wellkill simulations

    Exploration well 5505/5-5 NewField North (PL 555)SampleCo E&P

    December 2010

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    2/34

    Customer:

    SampleCo

    Customer PO no.: Project:

    N/A Project nr. 2010-800070

    Document title: Doc. no.: WPA-DOC-2010-800070-00

    Well blowout and dynamic wellkill simulation of exploration well 5505/5-5 NewField North

    Conclusions:

    This report summarizes the blowout and dynamic well kill simulations done for exploration well 5505/5-5 NewField North in

    production license PL 555.

    The well is to be drilled as a slightly deviated exploration well to test hydrocarbon potential in the Res-1 and Not formations.

    Secondary targets include Res-1 and Res-2 formations. Based on client input, Res-1 and Res-2 are evaluated as potential producing

    formations. Res-1 and Res-2 are treated as two formations, with common properties for Res-1 and Res-2.

    The well is vertical down to last casing @ 3450 m TVD RKB. Top Res-1 is expected @ 3555 m TVD RKB. The formations are planned

    drilled with an 8 section to TD @ 4031m MD/3930m TVD RKB. The well design considered includes a 36 x 30 conductor set @

    475 m TVD RKB, 20 surface csg set @ 1350 m TVD RKB, 13 intermediate csg set @ 2380 m TVD RKB and a 9 reservoir csg set

    @ 3450 m TVD RKB.

    Sea depth at location is 364 m MSL. The expected fluid to be explored is gas/condensate.

    The well is assumed drilled by the semi-submersible drilling rig West Phoenix, with a 39 m RKB-MSL air gap.

    The scenarios investigated is (Section 3.2 for details)

    - Kick scenarios partly penetrated Res-1- Swab scenarios fully penetrated Res-1 and Res-2

    The worst case scenario is described by an open and unrestricted flowpath, and full penetration of Res-1 and Res-2 formations with

    maximum permeability estimates. In such an unlikely event, the maximum blowout potential is found to be 4445 Sm/day of gas

    condensate and 17.8 MSm3/day of gas. The risk weighted blowout potential is found to be 701 Sm/day of gas condensate and 2.80

    MSm/day of gas for a surface blowout and 706 Sm/day of gas condensate and 2.82 MSm/day of gas for a subsea blowout.

    Expected duration of a risk weighted blowout can be predicted based upon statistical data from the Sintef Offshore Blowout

    database and industry experience values, and is found to be 13.1 days for a surface release and 23.4 days for a subsea release.

    In case of a blowout that will have to be killed remotely via a dedicated relief well, simulations show that an unrestricted surface

    blowout from fully penetrated Res-1 and Res-2 formations, through an open/cased hole, will have the highest pumping

    requirements.

    The worst case scenario can be killed by one single relief well, pumping 10.000 LPM of 2.1 sg mud to a total of 200 m to stop HC

    influx. Total mud volume required during the operation, including 2 x bottom up circulation, is 693 m.

    Note that the high kill fluid densities needed in the worst case scenario might fracture the formation, and operational procedures

    should be prepared for circulation of lighter fluids to stabilize the well.

    Rev. Date Description Created by: Approved by :

    0 03.12.2010 First version V.Gruner T.Rinde

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    3/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:3 of 34

    Contents

    List of figures ............................................................................................................................................ 4

    List of tables ............................................................................................................................................. 4

    List of acronyms ........................................................................................................................................ 51 Background and Introduction ......................................................................................................... 6

    1.1 Introduction ............................................................................................................................ 6

    1.2 Objective of work .................................................................................................................... 6

    2 Data & Information Collection ........................................................................................................ 7

    2.1 Location and water depth ....................................................................................................... 7

    2.2 Drilling facilities ....................................................................................................................... 8

    2.3 Reservoir properties ............................................................................................................... 8

    2.4 Reservoir fluid information ..................................................................................................... 9

    2.5 Well design .............................................................................................................................. 9

    2.6 Inflow Performance Relationship ......................................................................................... 11

    2.7 Permeability sensitivity ......................................................................................................... 11

    2.7.1 Res-1 permeability sensitivity ...................................................................................... 122.8 Res-2 permeability sensitivity ............................................................................................... 12

    2.9 Water .................................................................................................................................... 13

    2.10 Drilling mud and kill fluid ...................................................................................................... 13

    3 Blowout Potentials and Duration .................................................................................................. 13

    3.1 Blowout scenarios in general ................................................................................................ 13

    3.2 Case scenario definitions ...................................................................................................... 14

    3.3 Distribution of flowpath probabilities ................................................................................... 16

    3.4 Blowout duration .................................................................................................................. 18

    3.5 Risk process and distributions............................................................................................... 20

    3.5.1 Permeability risking ...................................................................................................... 20

    3.5.2 Final blowout risk procedure ....................................................................................... 21

    3.6 Possibility for underground blowout .................................................................................... 23

    4 Killing Methods of Blowing Wells ................................................................................................. 23

    4.1 Design of the relief well ........................................................................................................ 24

    4.1.1 Relief well data ............................................................................................................. 25

    4.2 Dynamic wellkill through a relief well ................................................................................... 25

    4.2.1 Simulation and model assumptions ............................................................................. 26

    4.2.2 Simulation results Dynamic kill simulations .............................................................. 26

    4.3 Pump and kill mud considerations ........................................................................................ 28

    4.3.1 Possible kill sequence ................................................................................................... 28

    4.3.2 Minimum pumping requirements on relief well drilling rigs ....................................... 30

    4.4 Figures: Worst case gas-only kill scenario ............................................................................. 31

    5 References .................................................................................................................................... 32

    6 Appendix list ................................................................................................................................. 33

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    4/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:4 of 34

    List of figures

    Figure 1: Map showing location of PL 555 Source: www.arcticweb.com................................................ 7

    Figure 2: The semi-submersible drilling rig West Phoenix ....................................................................... 8

    Figure 3: Illustrative well schematics for the 5505/5-5 NewField North exploration well [6] ............... 10Figure 4: IPR relationships fully penetrated Res-1 and Res-2 .............................................................. 11

    Figure 5: IPR curves - Res-1 Permeability sensitivity ........................................................................... 12

    Figure 6: IPR curves Res-2 Permeability sensitivity .......................................................................... 12

    Figure 7: Possible blowout paths for the defined scenarios (Illustrative only). ..................................... 15

    Figure 8: Blowout duration data from the Sintef Database and the Scandpower report 2010 [2]. ....... 19

    Figure 9: NewField North Illustrative risk process for the surface release case. ................................. 21

    Figure 10: Relief well - pump power vs. pump discharge pressure ........................................................ 28

    Figure 11: Pump rate vs. BHP in possible kill sequence ......................................................................... 29

    Figure 12: Oil/gas and mud content in 5505/5-5 during kill sequence .................................................. 29

    Figure 13: Typical mud pump capacity ranges. ...................................................................................... 30

    Figure 14: Illustrative summary of blowout and killing of the worst case kill scenario. ......................... 31

    List of tables

    Table 1: Reservoir data for 5505/5-5 NewField North [4], [5]. ................................................................ 9

    Table 2: Fluid conditions for the expected fluid from exploration well 5505/5-5 [4], [5]. ....................... 9

    Table 3: Probability distribution of flow paths from 20 years of historical data Floaters. .................. 16

    Table 4: Risk criteria in duration distribution. ........................................................................................ 20

    Table 5: Permeability risk distribution.................................................................................................... 20

    Table 6: Permeability risking Kick scenario 5m reservoir exposure .................................................. 20

    Table 7: Swab scenario - Permeability risk distribution ......................................................................... 21

    Table 8: Permeability risking Swab scenario Full reservoir exposure ............................................... 21Table 9: Blowout rates and duration distributions for a potential surface release................................ 22

    Table 10: Blowout rates and duration distributions for a potential subsea release .............................. 22

    Table 11: Minimum bullheading rates in order to ensure displacement of gas. .................................... 24

    Table 12: Kill data - Worst-case scenario - Blowout through open hole ................................................ 27

    Table 13: Kill data - Blowout through drillpipe ....................................................................................... 27

    Table 14: Kill data - Blowout through annulus ....................................................................................... 28

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    5/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:5 of 34

    List of acronyms

    API American Petroleum Institute

    BHA Bottomhole assembly

    BHP Bottomhole pressure

    BOP Blowout preventerCGR Condensate gas ratio

    DHSV Down hole safety valve

    DP Drillpipe

    ECD Equivalent circulating density

    GOR Gas oil ratio

    ID Inner diameter

    IPR Inflow performance relationship

    LPM Liter per minute

    MD Measured depth

    MSL Mean sea level

    N/G Net/Gross

    OD Outer diameterOH Open hole

    OIM Offshore Installation Manager

    PWL Planned well location

    RKB Rotary kelly bushing

    sg. Specific gravity

    TD Total depth

    TVD True vertical depth

    WBM Water based mud

    WPA Wellpro Academica AS

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    6/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:6 of 34

    1 Background and Introduction

    1.1 Introduction

    This study is part of establishing input for required approval and contingency planning

    purposes as required in NORSOK D-010 in terms of estimating the expected blowout ratesand their duration, as well as checking the ability to kill potential blowouts based on defined

    scenarios and specified input for the well 5505/5-5 NewField North in PL 555.

    Wellpro Academica AS (WPA), an independent and specialized competence center for fluid

    modeling and simulation services, was contacted and asked to perform blowout and

    dynamic kill analysis for different possible case scenarios during drilling of the exploration

    well.

    Main objective of well 5505/5-5 is to test hydrocarbon potential in Garn sandstones.

    Secondary objective is Res-2 sandstones, Secondary-1 sandstones and Secondary-2

    sandstones.

    The well is to be drilled as a slightly deviated exploration well. The well is vertical down to

    last casing, then slightly deviates to stay parallel to the main bounding fault. TD will be 100m

    into the Secondary-2 sandstone. In case of success, the well will be a keeper.

    No contract is currently made for drilling rig. There is an option to use West Phoenix after

    drilling of NewField (SampleCo), and West Phoenix is used as default regarding rig related

    information in this report.

    The well design considered includes a 36 x 30 conductor set @ 475 m TVD RKB, 20

    surface csg set @ 1350 m TVD RKB, 13 3/8 intermediate csg set @ 2380 m TVD RKB and 9

    5/8 reservoir csg set @ 3450 m TVD RKB. A 8.5 section will then be drilled through the

    potential hydrocarbon carrier formations. Top Res-1 is expected @ 3555 m TVD RKB.

    The expected fluid to be explored is gas/condensate.

    1.2 Objective of work

    The objectives of this study are:

    Calculate and present an expected range of potential blowout rates for the well,

    including the worst case flow rates of oil and gas to surface.

    Perform a sensitivity analysis with respect to possible blowout scenarios and presentestimates for the blowout rates for the different scenarios.

    Estimate flow rate and duration distributions of the blowout rates based on updated

    historical data and reliable distribution statistics.

    Recommend needed kill fluid density and kill rates for one, or more, relief well(s) for

    worst case and expected scenarios.

    The flow rate and duration distributions will be estimated based on the Sintef Offshore

    Blowout Database [3] and the latest approved evaluation of the Sintef Database data from

    Scandpower Risk Management AS [2].

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    7/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:7 of 34

    WPA will perform dynamic kill simulations in order to document safe killing of a potentially

    blowing well, including discussion on the relief well(s) and pumping requirements involved

    in the blowout control operation as required in NORSOK D-010.

    The Software package OLGA 6.2.7, considered state of the art within dynamic simulation of

    multiphase flows, is utilized for the dynamic simulations. PVT is handled using PVTSim and

    tuned based on customer input ([Error! Reference source not found.] and [Error! Referencesource not found.]). Blowout cases have been simulated by use of Prosper and verified in

    OLGA in order to ensure correct estimates.

    In case of a real blowout developing, a more detailed relief well study is recommended in

    order to plan for reassessment of the planned relief well path and well intersection. From

    experience, extra restrictions such as broken drillpipes or other downhole objects, e.g. fishes

    etc., are often present in the flow path. The maximum blowout rates presented in this

    report might be reduced by such restrictions. Experience also shows that reductions of the

    near wellbore reservoir pressures tend to reduce the actual pumping requirements.

    2 Data & Information Collection

    2.1 Location and water depth

    The well 5505/5-5 NewField North analyzed in this report will be drilled as an exploration

    well in production license PL 555, west of Brnnysund. The water depth at location is 364

    m. Figure 1 shows the location of the PL 555 in the North Sea.

    Figure 1: Map showing location of PL 555Source: www.arcticweb.com

    http://www.arcticweb.com/http://www.arcticweb.com/
  • 7/28/2019 Blowout and Kill Simulation Sample Report

    8/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:8 of 34

    2.2 Drilling facilities

    Drilling rig contract has not yet been signed. There is a rig tender being reviewed with two

    contractors, Det Norske (Songa Delta) and Dolphin (Bredford Dolphin).The rig option is to

    continue to use the West Phoenix after OldField. Negotiations are ongoing to determine the

    best solution for the NewField North Rig. This report will assume West Phoenix as drilling rigfor 5505/5-5. The air gap of West Phoenix is (RKB-MSL) 39 m.

    Figure 2: The semi-submersible drilling rig West Phoenix

    2.3 Reservoir properties

    The well is to be drilled as a slightly deviated exploration well, penetrating the primary

    target Res-1 sandstones with the possible HC bearing formations. Top Res-1 is expected @

    3606 m MD/3555 m TVD RKB. Expected reservoir pressure and temperature are 470 bar and

    130oC, respectively.

    The secondary target is Res-2 sandstones with expected top @3860 m MD/ 3724 m TVD

    RKB. Expected reservoir pressure and temperature are 470 bar and 130oC, respectively.

    The formations are planned drilled with an 8 section to TD @ 4031 m TVD RKB.

    Table 1 shows the reservoir data used in the simulations for the well presented in this

    report. Res-1 and Res-2 formations are treated in common in this report, and reservoir

    properties are listed based on this.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    9/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:9 of 34

    Table 1: Reservoir data for 5505/5-5 NewField North [Error! Reference source not found.], [Error!

    Reference source not found.].Res-1 Res-2

    Top formation m TVD RKB 3555 3724

    Temperature @ res top C 130 130

    Pressure BarA 470 470

    FIT @ 20 csg sg 1.75 1.75FIT @ 9 5/8 csg sg 1.85 1.85

    Gross interval depth meter 52 56

    N/G ratio - 0.67 0.875

    Net interval depth meter 35 49

    Permeability mD 50-200 1-5

    Productivity Index, PI Sm/d/bar - -

    Skin - 0 0

    2.4 Reservoir fluid information

    The fluid properties expected to be explored are listed in Table 2. Res-1 and Res-2 are

    expected to hold the same reservoir fluid, namely a gas with a GCR of 4000 Sm/Sm. Fluid

    properties are based on customer input.

    Table 2: Fluid conditions for the expected fluid from exploration well 5505/5-5 [Error! Reference

    source not found.], [Error! Reference source not found.].Standard conditions Data

    Condensate density at std cond.* kg/Sm 800

    Condensate viscosity at std cond.* cP 0.328

    Gas density at std cond.* kg/Sm 0.856

    Gas viscosity at std cond.* cP 0.008

    Gas to Condensate Ratio (GCR) Sm/Sm 4000*std conditions defined as 15C/1.0135 BarAReservoir conditions Data

    Gas density at res cond.** kg/m 435

    Gas viscosity at res cond.** cP 0.064

    Bubblepoint pressure BarA 440Gas expansion factor, Bg Sm/Rm 0.0037**Reservoir conditions defined as 130C/470 BarA

    Fluid properties are represented by a black oil model for all simulations presented in this

    report, and tuned according to data listed in Table 2.

    2.5 Well design

    The well is to be drilled as a vertical exploration well with the following well design planned:

    - 36 x 30 conductor set @ 475 m TVD, 20 surface csg set @ 1350 m TVD RKB, 13

    3/8 intermediate csg set @ 2380 m TVD RKB and 9 reservoir csg set @ 3450 m

    TVD RKB. The well is vertical down to last casing.

    - A 8.5 section will be drilled through the potential hydrocarbon carrier formations

    to TD @ 4031 m MD/ 3939 m TVD RKB

    - OD for the DP used when calculating the blowout rates is 5

    Figure 3shows an illustration of the planned well.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    10/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:10 of 34

    Figure 3: Illustrative well schematics for the 5505/5-5 NewField North exploration well [Error!

    Reference source not found.]

    Alve North Well Diagram

    Formations MD TVD CASING / LITHOLOGY/ Hole Size Casing and Cement MudRKB m SS m EXPECTED PORE PRESS Data Aquisition

    Rotary Table 39Sea bed 403 364 36" x 42'' 36" x 30'' Conductor Pipe Seawater with high vis

    sweeps

    Class G 1.54sg Turned light XL 1.03sg

    Conductor Point 475 43626'' 20" Casing, X56, 133# Seawater with high vis

    sweeps

    Nordland 520 481 Class G Lead 1.3 sg, tail 1.5 sg 1.03 sg

    Casing Point 1350 1311

    Kai 1420 1381 17-1/2" 13 3/8'' Casing, P-110, 72# VT WBMFIT ~ 1.75 1.45-1.55 sg

    Hordaland 1699 1660 Class G Lead 1.3 sg, tail 1.5 sg

    Rogaland 1919 1880

    Springar 1996 1957

    Tech Casing Point 2380 2341

    12-1/4" 10-3/4" VM110, 65.7# VT OBM9 5/8" VM110, 53.5# VT 1.45-1.55 sg

    Class G 1.9sg

    Lysing 2832 2793

    BCU 3274 3235 Kick off point

    Prod Casing Point 3450 3411

    Garn + Not 3606 3540 OBM8-1/2" 1.40 SG

    Ile +Upper Ror 3665 3589 FIT ~ 1.85 One Core in reservoirPossibly 3 mini-DSTs

    Tofte + Lower Ror 3748 3660 Log reservoirs guaranteed

    Tilje 3790 3695 A 7" Liner may be run for future completionre 3908 3795TD 4031 3900

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    11/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:11 of 34

    2.6 Inflow Performance Relationship

    The productivity index is sensitive to parameters such as permeability, penetration length,

    N/G ratio, the productive height of the reservoir as well as mechanical skin, inflow

    turbulence or skew drainage due to limited penetration. The productivity index is also a

    transient parameter that tends to decline shortly after initiation of the production, or as inthis case, a blowout. This is caused by the reduction of the near wellbore reservoir

    pressures.

    When calculating the blowout potentials, the blowout rates for the different scenarios are

    strongly dependent on the permeability, pressure, fluid viscosity and the consecutive

    productivity index. Simulations are based on the most likely properties, as given in Table 1

    and Table 2.

    The IPR relationships for NewField North are given in Figure 4. The IPR relationships shown

    are for a fully penetration of Res-1 and Res-2 formations, with the maximum expected

    permeability estimates of 200 mD and 5 mD respectively. A blackoil gas model has beenused in the calculations.

    Figure 4: IPR relationships fully penetrated Res-1 and Res-2

    As Figure 4 shows, the total IPR, evaluated at 3555 m TVD RKB, has an absolute open flow(AOF) of just below 38 MSm/day/bar. Contributions from Res-2 are very small compared to

    the much more productive Res-1.

    2.7 Permeability sensitivity

    Both reservoir sections investigated in this study, Res-1 and Res-2, are subject to

    permeability uncertainties. A sensitivity analysis on reservoir permeability is performed and

    presented.

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    0 5000 10000 15000 20000 25000 30000 35000 40000

    Flowing

    wellborepressure

    [bara]

    Gas Rate

    [1000 Sm/day/bar]

    Total IPR

    Garn/Not

    Ile/Tilje

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    12/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:12 of 34

    2.7.1 Res-1 permeability sensitivity

    The Res-1 formations are modeled as one productive zone with common properties.

    Reservoir permeability is subject to uncertainty and a permeability range of 50-200 mD is

    used in the blowout evaluations in this report.

    IPR curves applicable for the Res-1 formations are shown in Figure 5.

    Figure 5: IPR curves - Res-1 Permeability sensitivity

    2.8 Res-2 permeability sensitivity

    The Res-2 formations are modeled as one productive zone with common properties.

    Reservoir permeability is subject to uncertainty and a permeability range of 1-5 mD is usedin the blowout evaluations in this report.

    IPR curves applicable for the Res-2 formations are shown in Figure 6.

    Figure 6: IPR curves Res-2 Permeability sensitivity

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    0 5000 10000 15000 20000 25000 30000 35000 40000

    Flowingwellborepressure

    [bara]

    Gas Rate

    [1000 Sm/day/bar]

    Garn+Not - 50 mD

    Garn+Not - 100 mD

    Garn+Not - 200 mD

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    0 500 1000 1500 2000 2500 3000

    Flowingwellborepressure

    [bara]

    Gas Rate

    [1000 Sm/day/bar]

    Ile+Tilje - 1 mD

    Ile+Tilje - 3 mD

    Ile+Tilje - 5 mD

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    13/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:13 of 34

    2.9 Water

    Expected depth of the gas/oil-water contact was not given. Conservatively the water

    fraction in the simulations is assumed equal to 0.0%, whilst condensed water is accounted

    for.

    2.10 Drilling mud and kill fluid

    No filter cake or formation damage, nor stimulation effects caused by the drilling fluids used,

    which might decrease or increase the formation productivity, has been discussed in this

    report.

    In situations where a relief well is needed to re-establish the well barriers, i.e. situations

    where connection to the well is lost or pumping cannot be done from the drilling rig for any

    reasons, the kill fluid should be blended for minimum viscosity in order to minimize the

    hydraulic resistance. Still, it is important that the density of the kill fluid is compatible with

    the formation fracture gradient or that operational measures are established in order to

    compensate for possible fluid loss situations after fulfillment of the killing.

    In all kill simulations performed in this study a kill fluid viscosity of 10.0 cP is used. This is

    assumed conservative with respect to the pumping requirements found.

    3 Blowout Potentials and Duration

    Blowout potentials are defined as the maximum expected blowout rates for various

    scenarios. Most likely expected parameters are to be used, or a weighted distribution of the

    same parameters. Whenever necessary, parameters and calculation results should be risked

    in order to establish the most reliable probability distributions for expected rates.

    The OLF Guidelines for estimation of blowout potentials [1] are used as basis for all flow

    rate calculations presented in this report. Distributions of possible flowpaths are given in

    accordance with data from the Sintef Offshore Blowout Database [3] and the latest

    evaluation of the Sintef Database data in the report from Scandpower Risk Management AS

    [2].

    3.1 Blowout scenarios in general

    A blowout is defined as an unwanted and uncontrolled flow from a subsurface formation

    which is released at surface, seabed or into a secondary formation, and cannot be closed by

    the predefined and installed barriers.

    Blowout potentials, i.e. the expected rates of oil, water and gas, are highly dependent on the

    scenario in which the blowout occurs. Lost pipe, junk or complex escape paths for the fluid

    will result in dramatically lower blowout rates than a fully open 9 casing all the way from

    formation to surface.

    For the NewField North exploration well, an unrestricted blowout through the 9 casing,

    with exposure to fully penetrated Res-1 and Res-2 formations, will result in a maximum

    blowout rate of 4445 Sm3/day of condensate and 17.8 MSm3/day of gas. This rate is related

    to the maximum permeability estimates of both Res-1 and Res-2, and is very unlikely to

    occur. The risk process in Section 3.5 present risked blowout rates based on an underlying

    risk process, where the permeability range presented in Table 1 is accounted for.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    14/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:14 of 34

    This unrestricted blowout scenario will in this well set up a drawdown onto the formation of

    more than 110 bars (11 MPa). This drawdown might induce a risk of collapse of the

    surrounding formation, or initiate production rates of sand, both consequences that can

    reduce the rate of fluids flowing from the well. Formation collapse might even kill the well

    and thereby stop the blowout entirely.

    3.2 Case scenario definitions

    Hypothetical blowout scenarios have been investigated in this study, all relevant for drilling

    operations. The analyzed case scenarios include blowouts through drill pipe, annulus and

    open hole to drill floor and to seabed, implying several blowout scenarios. The last case is a

    collective case for simulations of restricted flow.

    In order to limit the number of scenarios to analyze, two main categories of incidents are

    simulated and are intended to cover all possible scenarios conservatively. The two scenarios

    are Kick and Swab, which covers all kicks when entering a formation and all swab scenarios

    when pulling out of hole, respectively.

    Kick scenarios are represented by a partly penetrated reservoir, while swab scenarios are

    conservatively represented by a fully penetrated reservoir.

    The following principles in selection of scenarios have been used as basis for simulation

    cases:

    Blowout through casing/open hole, reservoir partly penetrated, kick scenarios

    Blowout through casing/open hole, reservoir fully penetrated, swab scenarios

    Blowout through drillpipe, reservoir partly penetrated, kick scenarios

    Blowout through drillpipe, reservoir fully penetrated, swab scenarios

    Blowout through annulus, reservoir partly penetrated, kick scenarios

    Blowout through annulus, reservoir fully penetrated, swab scenarios

    Restricted blowout through topside leak, 64/64'' choke

    All scenarios listed above have been investigated in this report.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    15/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:15 of 34

    Figure 7: Possible blowout paths for the defined scenarios (Illustrative only).

    A find in Res-1 and Res-2 is related such that a find in Res-2 is not possible with no find in

    Res-1. This result in the following possibilities:

    a) HC find in Res-1

    b) HC find in Res-1 and Res-2

    HC find in none is not evaluated in this report.

    Based on this, the following definition is made for simulations performed in this study.

    1) Kick scenarios are represented by a partly penetrated Res-1

    2) Swab scenarios are represented by fully penetrated Res-1 and Res-2.

    See Section 3.5.2 for illustration and results from final risk procedure.

    For cases involving a partly penetrated reservoir, i.e. the kick scenarios, a gross penetration

    pay of 5 meters is used. The N/G ratio is 1.0, which is considered conservative.

    Drilling

    BOP

    Sealevel

    Drilling

    BOP

    Sealevel

    Drilling

    BOP

    Sealevel

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    16/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:16 of 34

    3.3 Distribution of flowpath probabilities

    In order to establish the best possible statistical estimate for the well, a distribution

    between all investigated scenarios and the expected duration for these are to be calculated

    based upon the Guidelines from OLF [1]. The statistical values are found based on the Sintef

    Offshore Blowout Database [3] and the annual report from Scandpower[2], that are basedupon a more comprehensive analysis of the Sintef database. Hence, irrelevant cases are

    removed and probability distributions are adjusted according to observed trends.

    Furthermore the operational experience from the Acona Wellpro group of companies, with

    more than 25 years of relevant operations is implemented in the calculation of the

    probability distribution. These evaluations and their weighting are discussed in detail below.

    Table 3 summarizes relevant statistical findings from drilling-, completion and workover

    activities from the Scandpower report from January 2010 [2]. In addition to the incidents

    listed within drilling, incidents within both completion and workover activites are added to

    expand the statistical foundation. These activities are considered to have a similar type ofbarrier system, with drilling mud as the first barrier and the BOP as the second barrier.

    Table 3: Probability distribution of flow paths from 20 years of historical data Floaters.

    When implementing these data for calculation of flow path distribution the following

    assumptions and methodology have been used:

    The number of incidents is relatively low and small variations might cause relatively large

    alterations in the distribution coefficients, i.e. from one year to another as incidents older

    than the limitations set are removed from the statistical material. The statistical uncertainty

    will increase even more if some of the findings from the table above are considered

    irrelevant for the operation that is to be analyzed.

    In order to try predicting the probabilities for the different flow paths possible, a more

    detailed analysis is needed. A well operation with dead well, defined as operation where

    the fluid column itself is the primary barrier, includes the activities drilling operations,

    workover operations and completion operations. Loss of well control in these operations are

    initiated by, and limited to, formation kicks or losses caused by unexpected formation

    Full Restricted Full Restricted

    Outside casing 22.70 % 4.50 %

    Outer annulus 18.20 % 4.50 %

    Annulus 31.80 % 4.50 % 4.50 %

    Open hole 4.50 %

    Inside drillstring

    Inside test tubing 4.50 %Annulus 4.50 %

    Inside drillstring 4.50 % 40.90 %

    Inside prod tubing 4.50 % 45.50 %

    Outer annulus 27.00 %

    Annulus 27.00 %

    Inside drillstring 24.30 %

    Inside prod tubing 16.20 % 5.40 %

    Workover

    (7.4 incidents)

    Drilling

    (22 incidents)

    Completion

    (4.4 incidents)

    Data update: January 2009

    Distribution - Floaters

    Subsea Topside

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    17/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:17 of 34

    properties, lack of operational fluid control or swabbing of reservoir fluids from pulling out

    of holeactivities or lack of heave compensation.

    Since all these three incidents (kick or loss from/to reservoir, lack of fluid control and

    swabbing) also are possible from completion and workover operations and that the

    secondary barrier in these operations also includes the drilling BOP, the statistical data fromthese two groups are included in the statistical summary together with the data from drilling

    operations.

    In the final distribution used in this report, the outside casing and outer annulus flow paths

    are neglected. Such rejection is supported by the fact that kick procedures are to be

    established in order to minimize the risk of an underground blowout. Also, the modeling

    process would be too complicated, in terms of describing the flow paths. Hence, reliable

    modeling results are beyond reach.

    Similar the flow through production/test tubing is interpreted as flow through open

    hole/casing.

    When drilling production wells, i.e. in mature areas, the risk of running into unknowns are

    clearly lower than when drilling exploration wells, i.e. experiencing reservoirs with pore

    pressure higher than the corresponding ECD which might induce a formation kick. The

    formations pore pressures are provided through estimation for exploration wells. When a

    formation kick is observed, an operational procedure normally instructs the driller to stop

    further penetration and to close a secondary barrier in the drilling BOP. Furthermore the

    kick will be circulated out through the choke lines. In the risk and weighting process it is

    anticipated that such kick will be observed relatively shortly after penetrating the formation.

    In this report a penetration depth of 5 meters is used, similar to half a joint of drillpipe,

    assuming that the bit did not penetrate the formation when the drillpipe last was made up.5 meter penetration of top reservoir is assumed to be a conservative number.

    In reality, the choice of penetration length into the reservoir, i.e. 5 m, is not of importance

    when evaluating the probability distribution. In fact, it is the mechanisms leading to the

    blowout that is important. For the partly penetrated case, the occurrence of a blowout is

    due to a kick scenario in the well. For the fully penetrated case, a swab scenario leads to the

    possible blowout. The loss of primary barrier by swabbing of reservoir fluids when pulling

    out of hole can be caused by pulling to fast, insufficient compensation of the pumping rates

    or by a combination of these. Borehole collapse or partly collapse of some strings or

    formations might increase the risks of swabbing reservoir fluids. Theoretically such swabbing

    may not be discovered before the BHA is at surface.

    Accordingly, for this exploration well, the following probabilities are used between partly

    and fully penetrated reservoirs.

    Blowout initiated when the formation is partly penetrated 60 %

    Blowout initiated when the formation is fully penetrated 40 %

    For the kick scenarios, i.e. partly penetration, 5 m penetration is used, with a N/G ratio of

    1.0, which is considered conservative.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    18/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:18 of 34

    Note: It is worth to notice that the risk of flowing through OH, when penetrating top

    reservoir only, is assumed irrelevant and the probability of this is given a 0.0 % value. This is

    founded upon the fact that the top reservoir cannot be penetrated without having the DP

    and the bit in the hole.

    Therefore the flow path probabilities in the top penetration scenario, i.e. a kick scenario, aregiven the following values:

    Blowout through drill pipe has a probability of 25 %

    Blowout through annulus has a probability of 75 %

    Blowout through open hole to surface has a probability of 0 %

    Similar, the fully penetrated, i.e. swab scenario, are given the following probability

    distribution:

    Blowout through drill pipe has a probability of 21 %

    Blowout through annulus has a probability of 62 %

    Blowout through open hole to surface has a probability of 17 %

    In all drilling operations, and most other well operations as well, a Blowout Preventer (BOP)

    stack of valves and rams defines the secondary barrier against uncontrolled outflow of

    reservoir fluids. The BOP testing program and its procedures ensure that a BOP stack is

    experienced as extremely reliable equipment. This is further emphasized by the number of

    independent rams in the BOP and the requirement for accumulator capacity. Based on this,

    the risk of a total failure of the BOP is assumed to be very low.

    Once a blowout has occurred, the BOP has failed or has not been activated. Given such

    unlikely failures, and based on the OLF Guidelines for estimation of blowout potentials[1],

    the following distribution has been used for partly or full BOP failure:

    Restricted flow area has a probability of 70 %

    No restriction has a probability of 30 %

    The different consequences of a partial failure in the BOP are difficult to predict. In the OLF

    Guidelines for estimation of blowout potentials it is proposed to model a partly failure as

    95% reduction of the available fluid flow area. As restriction in available flow paths also can

    be caused by pipe in hole, fish/junk or collapse of the borehole itself, Wellpro Academica

    suggest that modeling of a partly failure is better described with a restriction similar to

    64/64 flow area for all scenarios. This is justified by the fact that the remaining flow area

    now is independent of the wellbore design or the size of the drillpipe used.

    3.4 Blowout duration

    A blowout may be stopped by several remedial actions. These are divided into the following

    categories:

    - Bridging, i.e. collapse of the near wellbore due to low pressure and/or high

    production rates.

    - Intervention from crew

    - Subsea or topside attempt requiring additional equipment

    - Drilling of relief well intersecting the blowing well

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    19/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:19 of 34

    If one or more relief wells are necessary to regain control of the well, the time needed for

    mobilization and drilling may vary. We can assume that the relief wells can be drilled with

    the same rate as the exploration well, but in addition ranging runs are required, e.g. with

    electromagnetic ranging tools. The time required to run such equipment must be taken into

    account. The time will depend upon drilling intersection depth, rig availability in general and

    in the specified area and weather conditions.

    For the 5505/5-5 NewField North well, drilling of one relief well is estimated as follows:

    Decision to drill the relief well: 3 days

    Termination of work, sail to location, anchoring and preparation : 12 days

    Drilling relief well to intersection: 45 days

    Homing in: 10 days

    Total time to kill well: 70 days

    Assumptions are made that the relief well will successfully kill the well after 70 days.

    In order to give best possible distribution estimate, the probability distribution for the

    different historical incidents must be found. The figure below is presented from the

    Scandpower reported data from 2010 and presents the probability that a blowout is still

    active after a certain number of days and several mechanisms may have been tried.

    Figure 8 describes the probability of killing a well after a number of days based on the use of

    one single kill mechanism.

    Figure 8: Blowout duration data from the Sintef Database and the Scandpower report 2010 [2].

    As can be seen from the figure above, multiple mechanisms may work together in order to

    stop the blowout. Scandpower reports that 77% of all blowouts can be stopped by bridging,

    70% can be stopped by intervention topside and 43% can be stopped by intervention

    subsea, if the mechanism evaluated is the only mechanism to stop the leak [2].

    Table 4 summarizes the risk criteria used in the distribution analysis in Chapter 3.5.

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0 5 10 15 20 25 30 35 40 45 50

    Percentage

    Days

    Wells still flowing after subsea attempts

    Wells still flowing after topside attempts

    Wells still flowing after natural bridging

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    20/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:20 of 34

    Table 4: Risk criteria in duration distribution.

    Risk of a blowout duration of 2 days P2The blowout could be controlled by measures

    performed from the existing rig

    Risk of a blowout duration of 15 days P15The blowout could be controlled by bringing

    in additional equipment

    Risk of a blowout duration of 70 days P70The blowout will have to be killed by drilling a

    dedicated relief well.

    3.5 Risk process and distributions

    From the detailed analysis presented in the previous section the probabilities for all relevant

    scenarios were found. According to the OLF Guidelines for estimation of blowout

    potentials all possible scenarios should be risked and blowout potentials shall be weighted

    respectively.

    Note: The overall probability of finding hydrocarbons in a well, which again introduces a

    certain risk for a blowout shall be included either in the environmental analysis or in the

    blowout analysis (this report). This value is neglected in this report and will have to be

    included in the environmental analysis.

    3.5.1 Permeability risking

    The formations to be investigated in this report are all presented with a permeability range.

    A log normal probability distribution gives highest probability for the low case, as shown in

    Table 5:Table 5: Permeability risk distribution

    Formation Low Medium HighRes-1 50 mD 100 mD 200 mD

    Res-2 1 mD 3 mD 5 mD

    Probability 50% 30% 20%

    All Kick scenarios are risked according to the input in Table 5. The risked rates presented in

    Table 6 and Table 7 (far right column) are used as input to the final risk process in Section

    3.5.2.

    Kick scenario 5m penetration of Res-1

    Table 6 and Table 7 list gas condensate rates for the specified scenarios. The far right column

    of the individual tables represents the risked rate of gas condensate for the range of

    permeability. Risking of flowpaths are introduced in Section 3.5.2.

    Table 6: Permeability risking Kick scenario 5m reservoir exposureUnrestricted Flowpath

    50 mD 100 mD 200 mD Risked

    [Sm/d] [Sm/d] [Sm/d] [Sm/d]

    OH 5 mSubsea 635 1232 2156 1118

    Surface 647 1243 2172 1131

    DP 5 mSubsea 475 655 788 592

    Surface 463 626 745 568

    ANN 5 mSubsea 571 926 1255 814

    Surface 576 933 1261 820

    Restricted Flowpath

    50 mD 100 mD 200 mD Risked

    Sm/d] [Sm/d] [Sm/d] [Sm/d]

    OH 5 mSubsea 424 543 621 499

    Surface 423 540 616 497

    DP 5 mSubsea 373 461 518 428

    Surface 363 447 500 415

    ANN 5 mSubsea 404 511 582 472

    Surface 403 508 577 469

    Note: The methodology for estimating most likely duration of a blowout are under

    revision and the methodology are likely to be changed or updated later in 2010.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    21/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:21 of 34

    Swab scenario Fully penetrated Res-1 and Res-2

    To simplify the model and restrict the number of scenarios, the reservoir permeability of

    Res-1 and Res-2 is modeled in a low, medium and high permeability scenario. I.e. all

    combinations of permeability are not simulated. This leads to the following permeability

    scenarios:

    Table 7: Swab scenario - Permeability risk distributionLow Medium High

    Res-1+Not / Ile+Tilje 50/1 mD 100/3 mD 200/5 mD

    Probability 50% 30% 20%

    Table 8: Permeability risking Swab scenario Full reservoir exposureUnrestricted Flowpath

    50/1 D 100/3 mD 200/5 mD Risked

    Sm/d] [Sm/d] [Sm/d] [Sm/d]

    OH FullSubsea 2562 3570 4420 3236

    Surface 2630 3649 4445 3299

    DP FullSubsea 847 905 936 882

    Surface 799 850 877 830

    ANN FullSubsea 1406 1597 1708 1523

    Surface 1411 1601 1712 1528

    Restricted Flowpath

    50/1 D 100/3mD 200/5 D Risked

    [Sm/d] [Sm/d] [Sm/d] [Sm/d]

    OH FullSubsea 651 681 696 669

    Surface 653 679 691 668

    DP FullSubsea 544 564 574 556

    Surface 525 545 555 537

    ANN FullSubsea 613 641 655 630

    Surface 609 634 647 624

    3.5.2 Final blowout risk procedure

    The process diagram in Figure 9 shows the risk process which is implemented in the analysis

    presented in this report, and the resulting weighted blowout rates of oil for a surface

    release.

    Surface release vs. subsea release

    When drilling from a floater, anchored or dynamically positioned, the OIM will try to pull the

    rig off from location shortly after an uncontrollable well integrity issue is unveiled and anysurface attempt to stop the flow has not succeeded or have been evaluated as unlikely to

    succeed. This leads to the two different duration estimates for a surface and a subsea

    release as presented in Table 9 and Table 10.

    Figure 9: NewField North Illustrative risk process for the surface release case.

    Step 5 Step 6

    Total Risk

    Oil blowout

    potential

    [%] [Sm/day]

    0.00 % 1131

    0.00 % 497

    13.50 % 82031.50 % 469

    4.50 % 568

    10.50 % 415

    2.04 % 3299

    4.76 % 668

    7.44 % 1528

    17.36 % 624

    2.52 % 830

    5.88 % 537

    100.00 % 701 Sm/day 2.80 MSm/day

    0.43

    0.08

    0.13

    0.00

    0.440.59

    0.10

    0.17

    0.27

    0.13

    0.45

    Step 7

    Risked oil

    blowout rate

    [Sm/day]

    0

    0

    111148

    26

    44

    67

    32

    114

    108

    21

    32

    Formation Penetration Flowpath

    Step 8

    Risked Gas

    blowout rate

    [MSm/day]

    0.00

    Step 1 Step 2 Step 3

    BOP Status

    Step 4

    Yes

    Kick - 5mGarn+Not

    Swab - FullGarn+NotIle+Tilje

    60%

    40%

    9 5/8"Csg

    Annulus

    Drillpipe

    9 5/8"Csg

    Annulus

    Drillpipe

    0%

    75%

    25%

    17%

    62%

    21%

    Restricted

    Open

    Restricted

    Open

    Restricted

    Open

    Restricted

    Open

    Restricted

    Open

    Restricted

    Open

    30%

    70%

    30%

    70%

    30%

    70%

    30%

    70%

    30%

    70%

    45%

    70%

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    22/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:22 of 34

    All values in Figure 9 above are repeated in the tables below for improved readability. The

    risked blowout rates and duration distributions are listed in the following tables; Table 9 for

    surface release, and Table 10 for subsea release.

    Table 9: Blowout rates and duration distributions for a potential surface release

    Table 10: Blowout rates and duration distributions for a potential subsea release

    The risk process illustrates the most likely expected blowout rates for an uncontrolled

    blowout from the 5505/5-5 NewField North well. These values are risk weighted; therefore

    both higher and lower rates may be experienced in a real blowout. The risked values arequalified numbers for likely volumes expected, and are to be used when evaluating the

    possible environmental impact from the well.

    As can be seen from Figure 9 and the tables above, the expected gas condensate blowout

    rate from the NewField North exploration well is 701 Sm/day for a surface release point and

    706 Sm3/day for a subsea release point. The corresponding risked blowout rates of gas are

    2.80 MSm3/day for a surface release point and 2.82 MSm3/day for a subsea release point.

    There is no significant difference in blowout rates between surface and seabed releases.

    The risked durations for surface and subsea release, are 13.1 days and 23.4 days,

    respectively.

    Note: The risked blowout rates shall not be used for evaluating possible kill methods or

    requirement.

    The worst case scenario is described by the scenario with an open and unrestricted flowpath

    and fully penetration of Res-1 and Res-2 formations with maximum permeability estimates.

    In such an unlikely event, the maximum blowout potential is found to be 4445 Sm/day of

    gas condensate and 17.8 MSm3/day of gas.

    Step 5 Step 6

    Total Risk

    Oil blowout

    potential

    P2

    t < 2 days

    P15

    t < 15 days

    P70

    t

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    23/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:23 of 34

    3.6 Possibility for underground blowout

    An underground blowout is defined as uncontrolled flow from one or more formations, into

    one or several formations. If the receiving formations are located above possible sealing

    rocks, such a blowout might develop into an uncontrolled release to seabed.

    In a well control situation, the formation below the last casing shoe could be exposed to

    pressures higher than the corresponding fracture pressures. Based on lightest possible fluid

    column from the reservoir to the casing shoe, an analysis is performed to evaluate possible

    pressure conditions at the last casing shoe.

    In the NewField North well, a 9 casing is planned set at 3450 m TVD RKB. At this casing

    shoe, the fracture gradient is estimated to 1.85 sg, equivalent to 626 Bara. The fracture

    gradient is estimated based on a provided FIT of 1.85 sg. This is considered conservative.

    Assuming shut in with light gas from the Res-1 and Res-2 formations, with the reservoirs

    expected pressurized to 470 Bara, the fracture pressure cannot be exceeded at the givencasing shoe depth.

    Hence, based upon the given fracture gradients and expected formation pore pressures,

    WPA has evaluated the risk of experiencing an underground blowout as less likely. Such

    blowout has been disregarded from this report.

    4 Killing Methods of Blowing Wells

    A blowout can be divided into four main categories with respect to the remedial action

    needed to re-control the well:

    - Interventions from the rig

    - Bridging

    - Drilling of relief well

    - Natural causes

    Interventions from the rig

    If the drilling rig is still intact and possible to work on, several remedial actions can be

    foreseen as possible methods for killing of a blowout. Possible solutions are:

    - Mechanical actions

    - Dynamic actions

    Mechanical actions can be installation of a new wellhead on top of the existing one,

    installation of additional, or replacement of valves or closure of already installed valves, like:

    - BOP valves

    - Swab, master or wing valve in the X-mas tree

    - DHSV

    Possible dynamical actions from the drilling rig could be circulation of fluids or cement into

    the well. High density fluid might kill the well hydrostatically, whilst high pumping rates

    might kill the well hydrodynamically. Bullheading intends to pump at sufficient pumpingrates to overcome the rising velocity of the gas bubbles in order to displace the well fluids

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    24/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:24 of 34

    with kill fluids. Kill fluid may be lubricated, circulated or bullheaded into the wellbore

    dependent on the actual status of the well. Table 11 shows necessary pumping rates needed

    in order to ensure that all gas found in the wellbore will move downwards as fluid is pumped

    into the same wellbore from topside connections. Table 11 is generic and for information

    only, and assumes completed well with installed X-mas tree.

    Table 11: Minimum bullheading rates in order to ensure displacement of gas.

    Needed bullheading rates toensure gas displacement

    Verticalwell

    Deviatedwell

    [LPM] [LPM]

    9 casing 1350 2300

    7 tubing 550 950

    5.5 tubing 300 550

    Bridging

    The majority of blowing wells are killed by themselves because of bridging. According to the

    Scandpower report approximately 77% of the historical blowouts could be stopped by

    bridging if no other mechanisms or manmade attempts were initiated. Bridging mechanisms

    might be:

    - Sand or rock accumulates inside the wellbore

    - Formation collapses due to high flowing rates and high drawdown pressure

    - Formation of hydrates blocking the flow paths

    Drilling of a relief well

    If the blowing well cannot be controlled otherwise, a dedicated relief well will have to be

    drilled. A relief well is to establish a secondary flow path directly into the blowing well,

    wherein kill fluid can be pumped. Such action is extremely time consuming and involves

    mobilizing of one, or more, new drilling rigs, anchoring, controlled survey and large volumes

    of kill fluids pumped at high pumping rates directly into the blowing well.

    Natural causes

    Other possible mechanisms stopping a blowing well could be:

    - Pressure depletion of the blowing reservoir

    - Stopping of gas lift, gas- or water injection

    - Coning of water or gas into the blowing well

    4.1 Design of the relief well

    Surface considerations

    According to regulations a minimum spud distance from the blowing well is suggested to be

    500 meter. Corporate regulations might be even more conservative, and the distance might

    also be increased for better logistics and/or improved access for emergency and oil spill

    vessels. Because of these elements, some companies recommend a minimum distance of

    1000 1500 meters. The spud location should take into account wind, sea current and rig

    anchoring. Normal caution procedures with respect to shallow gas, casing design and barrier

    philosophy shall imply. The relief well drilling rig shall not interfere with any subsea

    installations, pipelines or cables.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    25/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:25 of 34

    The location shall be selected so that smoke, fumes, hydrocarbons or toxic gases may not

    reach the relief well drilling rig. Therefore local wind and current patterns for the specific

    area and time of the year must be addressed.

    Normally, two relief well locations should be identified. In this report, 1000 meters are used

    as horizontal distance from 9 casing shoe to relief well rig.

    Relief Well design considerations

    Normal drill pipe and equipment should be planned for. In this evaluation, a well design

    similar to the main well is assumed.

    Wellpath considerations

    In order to minimize the blowout duration, the well path of the relief well should be as short

    as possible. This also reduces the hydraulic power needed to deliver the necessary kill rate.

    East-West direction is preferred, due to uncertainties in the survey tools. The well path

    should be suitable for wireline service. Hence, inclination should be less than 60-65.

    Pumping considerations

    Pumping through both drillpipe and annulus is not recommended, because of the

    importance of having control over the flowing bottomhole pressure. It is possible to utilize

    the drillpipe in the relief well as a downhole pressure gauge. Water will be pumped at a low

    rate and the topside pressure will be measured and the hydrostatic water gradient added.

    The total volume of kill fluid needed for a dynamic kill operation is the sum of:

    Volume of mud to fill the relief well

    Required pump rate times the time to stop inflow (FBHP > PRESERVOIR)

    Two hole volumes of the blowout well to ensure two proper bottom up

    circulations

    4.1.1 Relief well data

    A relief well design similar to the production well is assumed. A simplified survey was

    generated for the relief well, based on the below listed design.

    A 9 casing is assumed set as the last casing @ 3350 m TVD RKB, approximately 100

    meters prior to the intersection point, drilling a 8 OH into the blowing well just below the

    9 shoe of5505/5-5.

    4 kill and choke lines are assumed in the evaluated scenarios.

    5/5 OD drillpipe is used in the relief well with a 60 meter BHA of 6.5 OD.

    4.2 Dynamic wellkill through a relief well

    Dynamic simulations were performed in order to design a suitable relief well capable of safe

    killing of the maximum blowout rates from the well. Dynamic simulations are performed

    utilizing the OLGA 6.2.7 software package, considered state of the art within dynamic

    simulation of multiphase flows.

    Main objective was to identify the worst case scenarios and their respective kill

    requirements with respect to pumping rates and kill fluid density, assuming that the kill

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    26/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:26 of 34

    operation will have to be carried out through relief wells, intersecting the main well just

    below the last casing shoe.

    4.2.1 Simulation and model assumptions

    A discussion on simulation choices follows. The simulation results are summarized in tables.

    Several combinations of kill mud density and kill rates through the relief well are presented,

    as well as various number of relief wells.

    Reservoir fluids and their mobility

    Due to the sea water gradient and the pressure gradient in the blowing well in this specific

    case, the blowout rates for a surface release will be insignificantly higher than from a subsea

    release. However, killing of a blowout with a surface release is more challenging than a

    subsea release due to the higher pressure at the outlet of the blowing well in the subsea

    case.

    Therefore, the dynamic wellkill evaluations done in this report, where the blowout is killedthrough a relief well, is mainly performed for a blowout with surface release from a fully

    exposed Res-1 and Res-2 formations. Killing of worst case openhole scenario is also

    performed for blowout with subsea release due to the Subsea/Surface discussion performed

    in Section 3.5.2.

    The fluid column that will kill the well is generated between the last casing shoe and topside.

    Depletion

    In case of a real blowout developing, large volumes of reservoir fluids will be produced to

    surface and the near wellbore pressure will deplete accordingly. The simulations presented

    in this report do not include such depletion and will therefore be conservative compared tothe requirements at the time of the actual kill operation.

    4.2.2 Simulation results Dynamic kill simulations

    Blowout through openhole

    An unrestricted surface blowout through openhole represents the most difficult kill scenario

    evaluated in this report.

    Simulations show that a surface blowout from fully penetrated Res-1 and Res-2 formations,

    through an 8 openhole section and an open 9 casing set at 3450 m TVD RKB, can be

    killed by means of one single relief well only and 2.1 sg mud, pumping 10000 LPM to a totalof 200 m kill mud to stop hydrocarbon influx from the reservoir. Estimated total volume

    mud required during the operation, including 2 x bottoms up circulation, is 693 m of mud.

    Note that high kill fluid densities needed might fracture the formation and operational

    procedures should be prepared for circulation of lighter fluids to stabilize the well after

    hydrocarbon influx is stopped.

    The kill requirements found are presented in Table 12, and represent kill requirements for

    an unrestricted blowout through an open hole, from reservoir to the surface/subsea release

    point.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    27/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:27 of 34

    Variations of kill rate and relief well designs are presented in order to unveil the possibilities

    found to reduce the number of relief wells required to one single well. A variation in

    drillpipe OD and kill-/choke line ID is presented.

    Pump down through the inside of the relief well drill pipe can be done in order to increase

    the flow area even more and hereby further reduce the hydraulic resistance. Please notethat this procedure should be considered with care, as the pressure reading as described in

    Section 4.1 is lost. This option is reported used on the Montara blowout in 2009.

    Table 12: Kill data - Worst-case scenario - Blowout through open holeBlowout path Release

    point

    Relief well info Reservoir

    exposure

    Minimum

    Kill fluid

    Density

    Kill

    vol

    Total vol

    req.

    Min hp

    req

    Max

    topside

    press.

    Total rate

    req.

    #

    relief

    wells

    [sg] [m] [m] [hp] [bar] [lpm]

    9 csg @

    3450 m TVD

    RKB

    Surface9 csg, 5.5" DP,

    4" kill and choke lines

    Res-1

    Res-22.0 226 794 < 500 < 50 11000 2

    9 csg @

    3450 m TVD

    RKB

    Surface9 csg, 5" DP,

    4.5" kill and choke lines

    Res-1

    Res-22.0 226 794 < 500 < 50 11000 2

    9 csg @

    3450 m TVD

    RKB

    Surface9 csg, 5.5" DP,

    4" kill and choke lines

    Res-1

    Res-22.1 245 813 < 500 < 50 10000 2

    9 csg @

    3450 m TVD

    RKB

    Surface9 csg, 5.0" DP,

    4" kill and choke lines

    Res-1

    Res-22.1 200 693 7102 272 10000 1

    9 csg @

    3450 m TVD

    RKB

    Surface9 csg, 5.5" DP,

    4" kill and choke lines

    Res-1

    Res-22.2 342 835 7482 318 9000 1

    9 csg @

    3450 m TVD

    RKB

    Subsea9 csg, 5.5" DP,

    4" kill and choke lines

    Res-1

    Res-22.2 212 551 7482 318 9000 1

    9 csg @

    3450 m TVD

    RKB

    Subsea9 csg, 5.5" DP,

    4" kill and choke lines

    Res-1

    Res-22.2 234 573 5692 256 8500 1

    Blowout through drillpipeThis case is defined as a blowout through the in-hole drillpipe, and assumes closed BOP with

    no restrictions in drillpipe, or topside restrictions such as Kelly-cock or kick-stand, see Figure

    7 for an illustrative example.

    Killing of a blowout through the drillpipe does not require large kill rates or pit capacities.

    Successful killing is performed by moderate rates with 1.5 sg mud.

    Table 13: Kill data - Blowout through drillpipeBlowout path Release

    point

    Relief well info Reservoir

    exposure

    Minimum

    Kill fluid

    Kill vol Total vol

    req.

    Min hp req Max topside

    press.

    Total rate

    req.

    # relief

    wells

    [sg] [m] [m] [hp] [bar] [lpm]

    5.5" drillpipe@ 3450 m

    TVD RKB

    Surface 9 csg, 5.5"DP, 4" kill and

    choke lines

    Res-1Res-2

    1.5 46 225 < 500 < 50 2500 1

    Blowout through annulus

    This case describes a surface blowout through the annulus between the drillpipe and the 9

    casing. See Figure 7 for an illustrative example.

    Simulations show that blowout through the above specified annulus could be by moderate

    kill rates, pumping 1.7 sg mud @ 4000 LPM.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    28/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:28 of 34

    Table 14: Kill data - Blowout through annulus

    Blowout path

    Release

    point Relief well info

    Reservoir

    exposure

    Minimum

    Kill fluid Kill vol

    Total

    vol req.

    Min hp

    req

    Max topside

    press.

    Total

    rate req.

    # relief

    wells

    [sg] [m] [m] [hp] [bar] [lpm]

    9 5/8" csg @

    3450 m TVD

    RKB

    Surface

    9 5/8" csg, 5.5"

    DP, 4" kill and

    choke lines

    Res-1

    Res-21.7 180 567 < 500 < 50 4000 1

    9 5/8" csg @3450 m TVD

    RKB

    Surface9 5/8" csg, 5.5"DP, 4" kill and

    choke lines

    Res-1

    Res-21.8 112 499 < 500 < 50 4000 1

    4.3 Pump and kill mud considerations

    4.3.1 Possible kill sequence

    The dynamic kill operation requires large pump rates and heavy kill mud to overcome the

    reservoir pressure. The graph presented in Figure 10show pump rates vs. gauge pressure on

    the relief well mud pumps, in a possible kill sequence.

    The kill sequence presented utilizes heavy 2.1 sg. kill mud until BHP exceeds the reservoirpressure in Res-1 and influx from the reservoirs is stopped. A that point, kill mud density at

    the relief well rig is switched to 1.6 sg mud in order to prevent formation fracture.

    When the BHP exceeds the reservoir pressure, the relief well pump rate is reduced to 1000

    LPM during a circulation sequence to circulate all remaining hydrocarbons from the 5505/5-

    5 well.

    Figure 10 show pump discharge pressure and hydraulic power requirements during a kill

    operation of a worst case scenario, where a less dense kill mud is utilized during the

    circulation sequence, in order to prevent formation fracture.

    Figure 10: Relief well - pump power vs. pump discharge pressure

    Figure 11 represent the same sequence as for Figure 10, but show the pump rate and

    bottom hole pressure (BHP) at Res-1 (3555 m TVD RKB).

    0

    100

    200

    300

    400

    500

    600

    700

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    0 1 2 3 4 5

    Pumppressure

    [bara]

    Pumppower

    [hP]

    Time

    [hrs]

    Pump power

    Pump pressure

    BHP exceeds Pres of Garn/Not. Pump

    rate reduced during circulation

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    29/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:29 of 34

    Figure 11: Pump rate vs. BHP in possible kill sequence

    Figure 12 illustrates total oil/gas content and mud content in the 5505/5-5 well during the

    proposed kill sequence. Circulation of mud should continue until all hydrocarbons are

    evacuated from the well.

    Figure 12: Oil/gas and mud content in 5505/5-5 during kill sequence

    0

    100

    200

    300

    400

    500

    600

    700

    0

    2000

    4000

    6000

    8000

    10000

    0 1 2 3 4 5

    Pressure

    [bara]

    Pumprate

    [LPM]

    Time

    [hrs]

    Pump rate

    BHP - Garn/Not

    Reservoir Pressure

    0

    50

    100

    150

    200

    250

    0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

    Volume

    [m]

    Time

    [hrs]

    Oil and gas content in well

    Mud content in well

    BHP exceeds Pres. Switch to

    1.6sg mud at relief well rigBHP stabilizes at a pressure

    equivalent to a 1.6 sg mud gradient

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    30/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:30 of 34

    4.3.2 Minimum pumping requirements on relief well drilling rigs

    The engaged rig(s) to drill the relief well in order to kill the blowout scenarios evaluated for

    the NewField North exploration well will have to meet the following minimum capabilities,

    in order to ensure safe and reliable killing of a potential blowout:

    No of drilling rigs: 1

    Total pump capacity: 10.000 LPM @ 272 barg

    Minimum horsepower req.: 7102 HP

    Typical mud-pump setup: 4x2000 HP

    Minimum pit capacity pr rig: 700 m

    Kill and choke line dimensions: 4 ID

    Figure 13: Typical mud pump capacity ranges.

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    250 300 350 400 450 500

    Pumprate

    [LPM]

    Pressure

    [barg]

    Typical mud pump capacity ranges

    4 x 2200 HP mud pumps

    3 x 1600 HP mud pumps

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    31/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:31 of 34

    4.4 Figures: Worst case gas-only kill scenario

    Instalation: West Phoenix

    Well no: 6607/12-2

    Well type: Exploration

    Well status: Planned

    Date: 29/11/10

    Revision no: 01

    Prepared by: V.Grner

    Approved by: T.Rinde

    Killing of worst case

    blowout rate scenario

    Operation info

    Comments/Notes

    Worst Case ScenarioWell info

    Blowout Rate: 17.8 Sm/day

    9 " csg to seabed

    403 meter - 21" marine riser

    Totalt well & riser volume: 210m

    Relief well info

    9 " tapered csg in relief well

    8 OH to intersection (~100m)

    5.0" OD drillpipe

    60 meter BHA 6.5" OD

    2 x 4" ID kill / choke lines

    75 meter 8" fixed surface line (ID =7.2")

    Relief well length: 3731 m (Surface TD)

    Intersection point: 3450 m TVD RKB

    Pumping info

    Total pump rate: 10000 LPM Minimum kill fluid density: 2.1 sg

    Minimum kill volume: 200 m

    Total volume required: 693 m

    Minimum pump power pr rig: 7102 hP

    Minimum surface pressure: 272 BarG

    36" x 30" Conductor

    475 m TVD

    13 "csg

    2380 m TVD RKB

    Seabed 364 m MSL

    8 OH

    TD 4031 m TVD

    RKB-MSL 39 m

    Drilling

    BOP

    Sealevel

    Top Garn/Not 3555

    m TVD RKB

    Intersection

    3450 mTVD RKB

    20" csg1350 m TVD RKB

    9 " csg

    3450 m TVD

    RKB

    Top Ile/Tilje 3724

    m TVD RKB

    Pres 470 bara

    Pres 470 bara

    Figure 14: Illustrative summary of blowout and killing of the worst case kill scenario.

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    32/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:32 of 34

    5 References

    1. Nilsen, Thomas; OLF Retningslinjer for beregning av utblsningsrater og - varighet til

    bruk ved analyse av miljrisiko - Rev. nr. 02, 15. januar 2007.

    2. Blowout and Well Release Frequencies - Based on SINTEF Offshore Blowout Database,

    2009, Report, Scandpower Risk Management. Report no. 80.005.003/2010/R3,

    17.03.2010.

    3. Sintef Offshore Blowout Database

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    33/34

    Revision:

    0

    Date:

    03-12-2010

    Well blowout and dynamic wellkill simulation 5505/5-5 NewFieldNorth

    Page:33 of 34

    6 Appendix list

    1. About Wellpro Academica AS

  • 7/28/2019 Blowout and Kill Simulation Sample Report

    34/34

    Appendix 1: About Wellpro Academica ASWellpro Academica, established as a specialized competence center for fluid modeling and

    process control, employs specialists, mainly with PhD degree and extensive backgrounds

    from the industry. We have advanced software packages and simulation models available

    for our clients.

    Typical services provided by Wellpro Academica are:

    Flow assurance simulations and advice

    Computational Fluid Dynamics (CFD) simulations and advice

    Dynamic wellkill analyses

    Blowout analyses

    Well and flowline simulations and optimization

    Process simulations and de-bottlenecking

    Well and flowline allocation services

    Wellpro Academica personnel have a unique blend of competence. The company provides

    senior modeling services to a wide range of the industry from solar and renewables, via

    metallurgical, to the oil and gas industry. Our strength is the competence, the diversity and

    the ability to transfer this know-how.


Recommended