Workshop: Work Completion Process May 16, 2006
Transcript
Page 1: BlueprintSession4 PMWorkCompletionProcess

Workshop: Work Completion Process

May 16, 2006

Page 2: BlueprintSession4 PMWorkCompletionProcess

Project Goals

Implement SAP Plant Maintenance system

Provide integration with Finance, HR, and Materials Allow enhanced scheduling and planning for work assignments Provide work scheduling as well as management reporting tools Accommodate the use of mobile technology to reduce paperwork Accommodate the use of GIS with SAP Improve automated updates to customers about the status of work Implement a Preventive Maintenance system for buildings, areas, and

equipment Utilize standard SAP functionality to collect utility usage and cost

information for recharge calculations

Page 3: BlueprintSession4 PMWorkCompletionProcess

Agenda

Introduction

Discussion of Work Completion Process

Preview of Next Blueprinting Session

Other Discussion

Page 4: BlueprintSession4 PMWorkCompletionProcess

What is the SAP Work Completion Process?

Work Orders are “Technically Completed”

Notifications are closed with technical findings recorded

Notes may be recorded via an order confirmation

Page 5: BlueprintSession4 PMWorkCompletionProcess

How is an order “Technically Completed”?

Orders are usually Technically Completed (TECO) from a list:

Page 6: BlueprintSession4 PMWorkCompletionProcess

How is an order “Technically Completed”?

One or more orders are selected:

Page 7: BlueprintSession4 PMWorkCompletionProcess

How is an order “Technically Completed”?

The “checkered flag” icon is selected:

Page 8: BlueprintSession4 PMWorkCompletionProcess

How is an order “Technically Completed”?

SAP offers to complete the notifications at the same time. Since we are going to record technical results with the notification, “Complete Orders” is selected.

Page 9: BlueprintSession4 PMWorkCompletionProcess

How is an order “Technically Completed”?

SAP indicates which orders were processed with the check mark. If the “Refresh” icon is selected, these orders will drop from the list.

Page 10: BlueprintSession4 PMWorkCompletionProcess

How is an order “Technically Completed”?

Page 11: BlueprintSession4 PMWorkCompletionProcess

How is a notification closed?

A list is used to select the notifications which are in process:

Page 12: BlueprintSession4 PMWorkCompletionProcess

How is a notification closed?

A list of notifications in process is displayed:

Page 13: BlueprintSession4 PMWorkCompletionProcess

How is a notification closed?

A notification is chosen for processing:

Page 14: BlueprintSession4 PMWorkCompletionProcess

How is a notification closed?

A code may be entered and the “Checkered Flag” icon selected:

Page 15: BlueprintSession4 PMWorkCompletionProcess

How is a notification closed?

The date and time of completion are entered:

Page 16: BlueprintSession4 PMWorkCompletionProcess

How is a notification closed?

The processed notification is indicated by the check mark:

Page 17: BlueprintSession4 PMWorkCompletionProcess

How is a notification closed?

The display is refreshed and the notification is no longer listed:

Page 18: BlueprintSession4 PMWorkCompletionProcess

How is are comments attached to a Work Order?

The order confirmation transaction is used for this:

Page 19: BlueprintSession4 PMWorkCompletionProcess

How is are comments attached to a Work Order?

The top portion of this screen is for time entry when CATS is not used. The text is entered in the “Confirm Text” field. Long text may be used.

Page 20: BlueprintSession4 PMWorkCompletionProcess

Topics For Next Blueprinting Session

Determine Material Management Requirements Reservations from Orders Requisitions from Orders Goods Issues to Reservations Unplanned Goods Issues Material Availability Display

Page 21: BlueprintSession4 PMWorkCompletionProcess

The “Homework” List -Fill in the floor number (if you know it) for the spreadsheet with "Unknown" floor. -Develop a priority list (or lists) by notification type or order type for your area -Determine which fields should be eliminated or required on the notification screens -Develop a list of Damage, Cause of Damage, and Activity codes -Determine if additional (or fewer) order types are required for your area -Determine a list of "Maintenance Activity Types" for your area and decide which order types should have which Maintenance Activity Types

-Determine a list of "User Statuses" by Order Type for your area. (Different order types may have different statuses.) -Determine the criteria for the "Object Info Box" to pop up for repeated work on a room or equipment. 

-Determine which fields should be eliminated or required on the order screens