BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249
Transcript
Page 1: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

BME/CompE/EE/ME 297 Senior Design Seminar

Contracts & Contract Management

Andrew W. DozierFGH 249

Page 2: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

System Life Cycle

• In order to discuss contracts and contract management, it is necessary to understand where in the system life cycle contracting is used

• Typically, project engineers get involved at various phases of a system development– Front end studies

• System Engineering

– Development

– Production

– Fielded systems• Logistics, maintenance and support

Page 3: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Front End Studies

• Typically, the customer has an existing system that they want to advance to current state of the art

• A significant amount of work is required to define and refine the requirements for the new system

• The only deliverable is a paper study, with no delivery or performance requirement– This requires a different contract type from later system

development phases• Time and Material

Page 4: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Later Phases

• As system development proceeds the number of “unknown unknowns” diminishes– This implies that the risk of performance on the

contract diminishes with each advancing phase

• As before, the contract type changes– Cost reimbursable

– Fixed price

– Time and material (again)

Page 5: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contract Life Cycle

• Each phase of development typically is competed and awarded incrementally– This allows the customer to deal with differences in

implementation risk via the contract type used

• Typical phases– Requirements Development– Prototype/breadboard development– First article production– Low rate initial production– Production– Life cycle support

• Each development phase goes through the same process

Page 6: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contract Development

• Request for Proposal– Includes contract type, or form

• Proposal development– Cost/Schedule– Technical– Data/deliverables

• Factfinding• Negotiations• Best and Final Offer (BAFO)• Award• Performance• Closeout

Page 7: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Estimating

• Estimating takes place at the time of the proposal for each phase, and includes an estimate of the following:– Time phased cost:

• Direct labor• Direct material

– Overhead– General and Administrative Expenses– The sum of cost and G&A equals your cost through G&A

• The above defines your “breakeven point”• Please note that this is based on your cost estimate, not

what you end up spending on a project– Actual cost can vary significantly from the estimate

Page 8: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contract Negotiations

• The customer spends a lot of time understanding what is contained in the proposal, also known as “factfinding”

• After factfinding, a final iteration of the contract cost and fee is generated– The idea is to define the “cost” and the “fee” for the entire project– The “price” of the contract equals cost plus fee

• Based on the final submittal by all competitors, an award is granted

• There are a variety of incentives available to the customer based on the type of contract

• Cost reimbursable• Fixed price• Time and Material

Page 9: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Direct Material and Labor

• The term “Direct” implies that both the labor hours expended and the material utilized in accomplishing the project is incorporated into the deliverable product– Consider a building/construction project

• Direct Material and Labor do not include the cost of the contractor’s facilities, rent, utilities, etc.– These items are included in the “Overhead” that is applied to the

cost of Direct Material and Labor

• The cost of direct material and labor does include employee benefits, the cost of buyer labor to procure material, etc.

Page 10: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Typical Overhead Items

• Direct Labor would include:– Vacation pay

– Sick pay

– Insurance

– FICA

• Direct Material would include– Cost of shipping

– Buyers to purchase the material and their overhead

Page 11: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

How are Overhead Rates Calculated?

• By an accounting methodology that conforms to the Federal Accounting Standards Board (FASB) for government contracts, and generally acceptable accounting practices for commercial companies

• The approach may vary from Company to Company

• Overhead does not include “Wheat Tax” or the cost of non-direct labor– Supervisors, department heads, executives, etc.

– Also referred to as “Indirect” cost

• Overhead does include the “Cost of Doing Business”

Page 12: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Overhead Rate Calculation Example

Page 13: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Methods for Apportioning Overhead

Page 14: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Application of O/H, G & A, and Profit

Page 15: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Definition of a Contract

• A “bilateral” agreement between two business entities to do something in the future for “Consideration”– The giving party is the “Customer” (or Buyer, or Client)– Receiving party is the “Contractor” (or Seller)

• The contractor can subcontract work to other companies and individuals– However, the contractor is still responsible for contract performance– Typically, this decision is made by going through a “make vs. buy”

analysis

• All contracts are governed by the Uniform Commercial Code of the United States– A body of law

Page 16: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contractual Relationships

• Interactions between business entities are based on Common Law

• Ultimately, contracts are administered by the Federal and State Government if a dispute arises– Court of Claims

• Settlement of Contract Disputes

– Court of Patent Appeals• Settlement of Intellectual Property Disputes

Page 17: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Consideration

• Consideration is provided to the contractor upon successful completion of the contract terms

• Consider the following scenario:– Contractor builds a building, pays for all labor, subcontractors, and

material suppliers

– Contractor delivers the finished building with a perfect title.

– Owner gives the contractor money as consideration

• All contracts and changes to contracts have consideration

• Consideration can take forms other than money, such as schedule relief, technical performance relief, etc.

Page 18: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Requirements for the Creation of a Contract

• In order to establish a contract, a mutual understanding as to what each business entity will give and receive must be defined– Consideration

• Cost and fee

– Deliverable items and data– Technical performance of deliverables– Schedule– Tasks (work) to be performed

• If you don’t have all of the above items defined, you do not have an executable contract

Page 19: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Requirements for the Creation of a Contract (cont’d)

• The contractor makes an offer to the customer (Proposal)– Can be a written or verbal offer, or an offer created by other acts of

communication by responsible officers of the seller• Fax, email?

– Contractor defines the period within which the proposal will be honored

• Customer enters into negotiations by issuing a letter of acceptance• The offer must be revoked in writing if something happens that

requires withdrawal of the offer prior to expiration

– The offer defines all cost, schedule, and technical requirements

• Factfinding then takes place with the customer team • Negotiations are then held to clarify items in the proposal,

and to state the customer’s perception of the “should cost”

Page 20: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Requirements for the Creation of a Contract (cont’d)

• The customer then counteroffers to the seller to converge differences in understanding– This can take multiple iterations

• Customer then generates a “Best and Final Offer,” or BAFO • This is then either accepted by the performer (seller) or the

seller “takes a hike”• If the offer is accepted, a contract is generated which

incorporates all of the final changes, and everyone signs it– The signators must be able to legally obligate the business– Typically, signators would be officers of the company with a

delegated signature authority greater than the value of the contract• This could be many $100 Million

Page 21: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Requirements for the Creation of a Contract (cont’d)

• Upon everyone’s signature, the project starts– The seller is “under contract” to perform in accordance

with the final negotiated document

Page 22: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contract Changes

• Things happen during the course of the project that change either the amount of work ($$$$), or the schedule

• A formal change process is incorporated into all contracts– Unilateral Change

• Imposed by the Customer on the Contractor without concurrance

– Constructive Change• Failure by the Customer to meet contractual requirement, ie. “Breach

of Contract”

– Bilateral Change• Mutually agreed to change between the Customer and Contractor

• Unilateral and Constructive Changes generally result in a “Dispute”

Page 23: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Disputes and Breaches

• Unilateral changes are typically not acceptable to the Contractor– Consideration is insufficient

• Need more money to do the additional work

– Impossible to perform to changed schedule, performance, etc.

• A breach of contract occurs when the Customer or the Contractor fail to meet the requirements of the contract– Failure to provide Customer Furnished Equipment, Facilities, etc.

– Failure to deliver on time

Page 24: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Dispute Resolution

• Negotiations are required by all parties to resolve disputes• Contract letters and supporting documentation are very

important in order to document the situation and position of both parties– Getting ready to go to trial– Lawyers get involved– Generally very unproductive and expensive– Not worth the effort for less than $10K on a large job

• Disputes must eventually adjudicated by the Court of Claims, which requires a legal trial– This is a very expensive process

Page 25: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Termination

• Contract Termination is possible under certain pre-negotiated conditions– “Termination for Convenience of the Government”

• Termination is also possible for failure to meet Contract requirements– Cost, Schedule, or Technical Performance

– Termination for “Cause”

– Termination for Default

• Termination clauses are always included as a part of the original Contract

Page 26: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Termination (cont’d)

• Termination for cause allows the customer to re-procure the item at the expense of the original contractor!– This is extremely serious and can bankrupt a company

• Termination for convenience requires a “Termination Proposal,” which is then negotiated like a new contract– Material purchased is packaged and turned over to the customer

– Subcontracts must also be terminated

– Costs associated with early termination of employees are included• Layoff notification, etc.

Page 27: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contract Concepts

• Different contract types are available• The contract type selected must be based upon a mutual

understanding of the risk of success of the project– If the customer is incorrect with regard to their perception of risk,

than there should be no bidders on the contract– Success is defined as the achievement of all contract objectives

Cost, Schedule, Performance– Improper utilization of a contract type can, and does frequently result

in project failure

• All contracts provide a concept of “Profit” or “Fee”– Related to consideration– Generally, the fee equals funds left over at contract completion, and

after closeout

Page 28: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contract Concepts (cont’d)

– Residual materials or equipment are not included in the final profit

• Sold as surplus and credited to overhead

• Delivered to Customer

– Profit percentage varies with the type of contract, ie. cost reimbursable or fixed price

The residual funds can be negative!!

Page 29: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Types of Contracts

• Fixed Price• Cost Reimburseable• Time and Material

Page 30: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Fixed Price Contracts

• Highest risk to Seller. Used for low risk procurements.

• Three Types– Fixed Fee (FFP)

– Incentive Fee (FPIF)

– Fixed Price with Redertimination (FPR)

Page 31: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Firm Fixed Price Contracts (FFP)

• Fixed profit, no ceiling price• Exceptions

– Constructive Changes

– Unilateral Changes

• Definition of “Change” subject to interpretation– Generally used as negotiating tool

– Customer has upper hand by withholding of funds

• Can overrun! Can also have costs disallowed.

Page 32: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Fixed Price Incentive Fee (FPIF)

• Lower Risk to Seller, fee determined by targets• Ceiling Price• Cost/Profit Sharing

– Incentive Curve• 30/70 Share for Underrunns

• 70/30 Share for Overruns

• Still subject to Changes Clause• Can receive minimal or no profit and overrun!• Customer can also disallow costs.

Page 33: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Fixed Price with Redetermination (FPR)

• Two types: Prospective and Retroactive

• Prospective FPR negotiates prices to be paid in a prospective period– Similar to two FFP arrangements negotiated at stated times during

contract performance period

• Retroactive FPR provides for adjusting price after performance– Essentially like FPIF

• Maximizes Project Managers attention on happines of Customer

Page 34: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Cost Reimbursable Contracts

• Lower Risk to Seller than Fixed Price Contracts• Used for higher risk procurements

– Uncertainty of performance goals, etc.

• Three Types– Fixed Fee (CPFF)

– Incentive Fee (CPIF)

– Award Fee (CPAF)

Page 35: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Cost Plus Fixed Fee (CPFF)

• Fixed profit, no renegotiation of contract allowed

• No ceiling price

• Exceptions– Constructive Changes

– Unilateral Changes

• Definition of “Change” subject to interpretation– Generally used as negotiating tool

– Customer has upper hand by withholding of funds

• All “Costs” are paid– Subject to interpretation as to “Allowable” cost

Page 36: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Cost Plus Fixed Fee (cont’d)

• If project overruns at cost, no increase in fee (lower profit margin)

• If project underruns at cost, higher profit margin achieved

• Can overrun, but will always make a profit

Page 37: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Cost Plus Incentive Fee (CPIF)

• Lower Risk to Seller• Established Targets (Cost, Schedule, Performance)• Cost/Profit Sharing

– Incentive Curve• 30/70 Share for Underrunns

• 70/30 Share for Overruns

• Still subject to Changes Clause• Can overrun and still make a profit subject to the

Incentive Curve

Page 38: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Cost Plus Award Fee (CPAF)

• Fee determined by Customer via award criteria– No rules regarding Award Criteria

• Typical targets established– “Responsiveness to Customer”

– Cost/Schedule Controls, etc.

• Completely dependent on “Grade” of Customer.

• Can receive $0 profit, but will always be reimbursed for costs

• Maximizes Project Manager’s attention on happiness of Customer

Page 39: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Time and Material Contracts

• Lowest risk to Seller. Generally used for studies with indeterminate outcome, or support, operational or maintenance contracts.

• Not to Exceed Contract for labor and material• Task orders from Customer are negotiated with

Seller– Defines effort for small tasks

– Minimizes any cost uncertainty

Page 40: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Cost/Fee Examples

• FFP• FPIF• CPFF• CPIF

Note: In the following slides, the “price” to the customer equals the sum of the profit and cost.

Page 41: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Firm Fixed Price (FFP)

Page 42: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Fixed Price Incentive Firm Target (FPIF)

Page 43: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Cost Plus Fixed Fee (CPFF)

Page 44: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Cost Plus Incentive Fee (CPIF)

Page 45: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Elements of a Contract

• Contract Form• Schedule• Statement of Work (SOW)

– Deliverables

– Contract Data Requirements

– Contract Data Requirements List

– Specifications

Page 46: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contract Form

• Document which provides all “contractual” details– Type of Contract

– Total Cost

– Deliverables/Services and Prices

– Packaging and Marking

– Inspection and Acceptance

– Contract Clauses and Administration Data

– List of Documents, Exhibits

– Representations and Certifications

Page 47: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Contract Form (cont’d)

• Technically, Schedule and SOW are part of Contract– Generally referenced in body of Contract Form

• No Schedule or Technical Information. Cost only!

Page 48: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Schedule

• Time phased tasks and deliverables which are detailed in SOW, Supplies List, and CDRL

• Generally identical to the proposed schedule, with modifications resulting from negotiations

• No Cost or Technical Information. Schedule only!

Page 49: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Statement of Work

• Details all tasks and activities to be accomplished on Contract

• References the following documents– Contract Data Requirements

– Contract Data Requirements List (CDRL)

– Deliverable Items

– Specifications

• Defines all design activities, documentation, etc.

• No Cost or Schedule Information. Technical Only!

Page 50: BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249.

Other Topics of Interest

• Government Acquisition Regulations– DARS/FARS

• Government Contracting vs. Commercial Contracting

• Estimating/Scheduling Methodology• Work Planning• Specification Development and System