Date post: | 05-Apr-2018 |
Category: |
Documents |
Upload: | mynoo-samal |
View: | 225 times |
Download: | 0 times |
of 36
7/31/2019 Bms Check List
1/36
3]DVR REMOTE ACCESS CLIENT SOFTWARE REQUIRED
4]AUTO IRIS CAMERA REQUIRED
5]ENTRY AND EXIT NPR CAMERA REUIRED WITH AUTO WHITE BALANCING WITH NIGHT M
6]OUT SITE ALL CMOUNT CAMERA CLEARITY REQUIRED WITH NIGHT VISION
7]ALL CAMERA SMPS CENTRALLY REQUIRED WITHOUT POWER DROPE
1]MIC REQUIRED
2]KEYBOARD/MOUSE REQUIRED INDIVIAL DVR
7/31/2019 Bms Check List
2/36
10]DVR BACKUP REQUIRED MIN 30 DAYS
11]EPABX SYSTEM CABLING REQUIRED FOR CLIENT SITE.
12]TELEPHONE INSTUMENT REQIRED FOR CLIENT RECEPTION.
8]LIFT CAMERA CABLING PROBLEM WHEN LIFT MOVE CAMERA UPS BACKUP REQUIRED
9]LIFT INTERCOM PROPER SYSTEM REQUIRED CENTRALLY
7/31/2019 Bms Check List
3/36
13]AS PER DRAWING CABLING NOT DONE SO PROPERLY QWALITY TESTING REQUIRED.
14]WATER LEVAL SENSORS REQUIRED FLEXIBAL POSIBLE TO REOMVE AND INSTALL NOW PSENSORS IF ANY ONE SENSORS FAULTY SO WE HAVE TO CHANGE ENTIRE 4 SENSORS UNNE
15]WATER LEVAL CERTIFICATE.
16]WATER LEVAL SLD REQUIRED
7/31/2019 Bms Check List
4/36
22]LIFT CLEARITY REQUIRED
23]DG YARD SPEAKER REQUIRED WITH PARKING AREA
24]ALL WATER TANK SENSORS CERTIFICATE REQUIRED
17]ALL FLOOR CR /CT REQUIRED FOR CLIENT FAS INTRIGATION
18]MCP REQUIRED AT ALL STAIRCASE
19]LIFT CAMERA FLUCTUATING
20]LIFT CAMERA SIGANAL NOISE
21]MCP BRACKET REQUIRED
7/31/2019 Bms Check List
5/36
25]STAIRCASE PRESARISIATION INTRIGATION REQUIRED
26]LIFT FIRE INTRIGATION REQUIRED
27]LIFT RCB JOB REQUIRED FOR TAKING INPUTS ON EBI SERVER [WITHOUT LIFT RCB JOB
28]ENTRY AND EXIT CAMERA REQUIRED WITH NPR WHITE BALANCE IRDA FOR CAPTURINUNDER NIGHT MODE.
7/31/2019 Bms Check List
6/36
34]CENTRAL INTERCOM REQUIRED.
29]VANTILATION FAN REQUIRED INDIVIAL STATUS FOR EBI FOR GETTING AT ACTUAL CON
30]LG1/LG2 STAIRCASE PRESARISATION REQUIRED
31]DG PANEL INTRIGATION REQUIRED
32]POINTS TESTING OF PFC
33]BATTARY BACKUP REQUIRED FOR FAS
7/31/2019 Bms Check List
7/36
35]AS PER BUIT DRAWING AND AS PER WORK DONE AT SITE NOT MATCH.
36]FAS SDU MASTER FILE WORK SHOULD REQUIRED
37]GRAFICS LINKING PROBLEM
38]MCP UNPROGRAM SO REQUIRED PROGRAM
7/31/2019 Bms Check List
8/36
39]WHENEVER HANDOVER START FIRST BRIFING REQUIRED WHAT IS AS PER BUILD AND WBRIFING ABOUT HOW SYSTEM ZONEING DONE AT SITE.
39]HVAC SYSTEM CONNECTION REQUIRED PROPER AS PER DESIGNED
7/31/2019 Bms Check List
9/36
40]WHENEVER CABLING WORK DONE AT SITE SO NOT MORE THAN THREE VENDORS ALS WHENEVER THERE IS CABLING PROBLEM WE WILL EASYLY TRACK VENDOR
41]FAS CABLE PATCHING OR JOINTS NOT REQUIRED ONLY LOOP VISED DETAILS REQUIRED
42]EXTRA EPABX CARD EXTENTION REQUIRED.
43]NETWORK SLD REQUIED
7/31/2019 Bms Check List
10/36
BELOW HANDOVER DOCUMENT REQUIRED
1]AS PER BUILT DRAWING OF FAS/CCTV/PA
2]BOQ REUIRED
3]CAUSE & EFFECT EXCEL
44]ALL PTZ CAMERA SETTING REQUIRED
4]CCTV/PA/FAS CHECKLIST
5]INSTALLATION REPORT
5]MATERIALS RECONCILATION
6]SOP REQUIRED
7]COMMISIONING REPORT
8]PASSWORD OF FAS AND DVR
45]
7/31/2019 Bms Check List
11/36
15]ALL SYSTEM HARD AND SOFT COPY REQUIRED
16]PRODUCT SERIAL NUMBER LIST REQUIRED
9]WARRANTY CERTIFICATE
10]SERVICE ESCALLATION MATRIX
11]PROJECT CLOSEOUT DOCUMENT
12]USER AND OPRATIONAL MANUAL AS PROVIDED SYSTEM
13]TESTING CERTIFICATE REQUIRED
14]FAS BACKUP REQUIRED.
7/31/2019 Bms Check List
12/36
1 Armored FRLS cables not used2 Cable not laid properly3 In case of fir e Lift, Staircase pressur4 PFC contract was not provided for a5 As Built Drawing not proper.
HVAC
1 Cable terminations not done proper
2 PFC contacts were not provided in3 Points Linking in EBI for most panels4 DG Status connections were not ma
Water management
1 Sensors were not laid properly.2 Most of the sensors dint had proper3 Points Linking in EBI for most Tanks
FASBelow points received from Honeywell
7/31/2019 Bms Check List
13/36
DE.
To ckeck announcement of PA system
Separate keyboard/mouse reqired for indivisual operation
To free from manual operation and technical upgradation
iris is an adjustable control the amount of light coming through the l
is opened, the more light it lets in and the brighter the scene.
Because this two are considered the most security zone-ENTRY & EXI
DAY/NIGHT camera is the best option than normal
SMPS is the DC power supply unit
7/31/2019 Bms Check List
14/36
Building intercome must be at reception
wireless camera should be used in Lift with networking through wifi,sfails/cutdown ,a contineous recording wil be in process.
By setting the proper resolution mode or by putting network strorage
ok,updated RCP or as build required
7/31/2019 Bms Check List
15/36
ROBLEM WITH POD B THEY FIXSSESORY
AS build drawing required if cabling not as per specified drawing
Single line diagram required with separate system wise-FIRE,PA,CCTV,
7/31/2019 Bms Check List
16/36
ok
MCP required at the most accessable area.
Proper flexibility in cabling required
Cable for camera not to be interfere with high tension electrical cablefield generate,while crossing over & the genetared emf produce nois
But bracket should not be lockable
PA system should be in common area for general announcement
7/31/2019 Bms Check List
17/36
E CANT GET DATA IN PUTS.
NUMBER PLATE ALSO WORK
ok
lift calling should be operated through fire calling
7/31/2019 Bms Check List
18/36
ITION
7/31/2019 Bms Check List
19/36
7/31/2019 Bms Check List
20/36
HAT IS CURRENT SENERIO ALSO
7/31/2019 Bms Check List
21/36
WORK AND ZONE DEFINED SO
7/31/2019 Bms Check List
22/36
7/31/2019 Bms Check List
23/36
7/31/2019 Bms Check List
24/36
ization fans were not connected.ctivation of Fans
ly for most of electrical panels.
any of electrical panels.were not done properly.
de.
cable terminations.were not done properly.
7/31/2019 Bms Check List
25/36
ens. The more the iris
7/31/2019 Bms Check List
26/36
o that if cabling
card on server
7/31/2019 Bms Check List
27/36
,AUTOMATION,BMS
7/31/2019 Bms Check List
28/36
,because a mangneticor humming effect.
7/31/2019 Bms Check List
29/36
7/31/2019 Bms Check List
30/36
7/31/2019 Bms Check List
31/36
7/31/2019 Bms Check List
32/36
7/31/2019 Bms Check List
33/36
7/31/2019 Bms Check List
34/36
7/31/2019 Bms Check List
35/36
7/31/2019 Bms Check List
36/36