Board of Directors Agenda Report MEETING DATE: JANUARY 17, 2019 ITEM NUMBER: 9A
SUBJECT: Committee / Ad Hoc Committee / Liaison Reports DATE: January 11, 2019 FROM: Robert Ruiz, Board Chair PRESENTATION BY: Robert Ruiz, Board Chair ___________________________________________________________________ RECOMMENDATION Information item only. BACKGROUND To assure compliance with the Bagley-Keene Act, Committee reports are only for the purpose of the Committee chair, Ad Hoc Committee members or Liaison to provide a verbal update. Should the Board want to discuss any Committee work item not already on the agenda; those would need to be agendized for a future Board meeting.
i. Heroes Hall Veterans Foundation Board (Director La Belle, Chair; Vice Chair
Cervantes) ii. Financial Monitoring Committee (Director Pham, Committee Chair; Director
Mouet) iii. Legislative Monitoring Committee (Director Aitken; Committee Chair; Chair Ruiz) iv. Tenant Liaison Committee (Director Pham, Committee Chair; Vice Chair
Cervantes) v. Board of Directors Governing Policy Manual Review Ad Hoc Committee
(Director Bagneris, Committee Chair; Chair Ruiz) vi. Safety & Security Committee (Chair Ruiz, Committee Chair; Vice Chair
Cervantes)
Board of Directors Agenda Report MEETING DATE: JANUARY 17, 2019 ITEM NUMBER: 9B
SUBJECT: Update on Relocation of the A4 Skyhawk Aircraft from the County Facility in Santa Ana to the OC Fair & Event Center
DATE: January 11, 2019 FROM: Kathy Kramer, CEO PRESENTATION BY: Director La Belle & Ken Karns, VP Business Development ___________________________________________________________________ RECOMMENDATION Director LaBelle is recommending staff initiate a Letter of Understanding (LOU) with California Fairs Financing Authority (CFFA) to undertake all requirements and construction for the relocation of the A4 Skyhawk. To that end, Director Labelle requests that through staff CFFA engage the services of ATI Architects and Engineers to work with staff and CFFA on the development of the scope of work, bid process and construction review. Director LaBelle also recommends that staff set a ”not to exceed” budget of $20,000.00 to have that work carried out by ATI. BACKGROUND At the October 25, 2018 meeting, the Board of Directors approved moving forward with perusing the opportunity to relocate the A4 Skyhawk aircraft from the County Facility in Santa Ana to the OC Fair & Event Center and to enter into discussions with the County of Orange on a Memorandum of Understanding (MOU). At the December 13, 2018 meeting, the Board of Directors approved the Capital expenditure for this project with a budget of $100,000.00. Director Labelle and the Chair of the Heroes Hall Veterans Foundation, Nick Berardino, along with OCFEC staff attended a kick-off meeting with representatives from the County. Director Labelle will be providing a verbal update on the meeting and the status of the MOU.
Board of Directors Agenda Report MEETING DATE: JANUARY 17, 2019 ITEM NUMBER: 9C
SUBJECT: Discussion on District’s Request for Proposal (RFP) Process
DATE: January 11, 2019 FROM: Kathy Kramer, CEO PRESENTATION BY: Director La Belle & Kathy Kramer, CEO ___________________________________________________________________ RECOMMENDATION At the Board of Directors’ discretion. BACKGROUND At the December 13, 2018 Board of Directors meeting, Director La Belle requested a discussion on the District’s Request for Proposal (RFP) process.
Board of Directors Agenda Report MEETING DATE: JANUARY 17, 2019 ITEM NUMBER: 9D
SUBJECT: Storm Water Management Update DATE: January 11, 2019 FROM: Kathy Kramer, CEO PRESENTATION BY: Ken Karns, VP Operations ___________________________________________________________________ RECOMMENDATION Information item only. Please see the attached documentation on OC Fair & Event Center Storm Water Management. BACKGROUND In a previous Board of Directors meeting, staff provided verbal updates on Storm Water Management and made a commitment to bring back an Executive Summary. Attached you will find the following documents:
1. Storm Water Program, Executive Summary 2. Santa Ana Regional Water Quality Control Board, Notice of Violation (NOV) 3. OC Fair & Eventer Center, response to Water Quality Board NOV 4. OC Fair & Event Center, response to Water Quality Board NOV schematics
and photos At the December 13, 2018 meeting, the Board of Directors approved two Capital expenditures for Storm Water Management projects:
$300,000.00 for new infrastructure on the North side of the property $75,000.00 to replace the existing desilting basin located inside the
Equestrian Center footprint. OCFEC staff is currently working with Fuscoe Engineering, Inc. (FEI) to plan for the 2018–2019 annual reporting contract, as well as developing a scope of work for an enhanced storm water capture diversion plan.
OC Fair & Event Center • 32nd District Agricultural Association 88 Fair Drive, Costa Mesa, CA 92626 • (714) 708-1500 • ocfair.com
Storm Water Program ‐ Executive Summary Fuscoe Engineering, Inc. (FEI) has assisted in developing OC Fair and Event Center’s (OCFEC) Storm Water Program and their continued assistance in its implementation to maintain compliance. Prior to their involvement with OCFEC’s Storm Water Program, FEI has previously done hydrology and water quality technical work for the OC Fair Master Plan EIR in 2003. Thus, their firm’s referral to OCFEC was not just based on their consulting work with the Del Mar Fairgrounds and the Cities of Anaheim, Brea, Tustin, Los Alamitos, and Yorba Linda, but also from working directly with us in the past.
ProgramDevelopment
OCFEC contacted FEI to review the enforcement actions issued by the Regional Board in February 2016. Prior to this, we were managing our Storm Water Program since our enrollment in the Phase II MS4 Permit (Municipal Separate Storm Sewer System) in 2014, with some assistance from UC Davis Cooperative Extension. In November 2015, the Regional Board notified us of its intent to audit OCFEC’s Storm Water Program. Not submitting OCFEC’s 2014‐15 Annual Report by the October deadline likely contributed to this request. The site audit was conducted in December 2015 with OCFEC Staff and the NOV enforcement letters were issued two months later. The NOV (Notice of Violation) gave OCFEC 30 days to respond; otherwise the NOV would escalate to fines and civil penalties. Fines for similar non‐compliance issues are typically in the $100,000 range. Due to the need to prepare two Annual Reports and a Storm Water Management Plan (SWMP) in such a short compliance timeline, FEI was hired to provide these services. During this whole process, FEI proactively engaged the Regional Board to provide status updates to assure them that OCFEC would meet all the committed deadlines noted in the response letter to the NOV. By July 2016, less than 5 months after the NOV was issued, the SWMP was completed and submitted to the Regional Board. The SWMP guidance document included storm drain maps, inventories of infrastructure and facilities, inspection forms, and training materials for day‐to‐day use by OCFEC Staff. Also in July 2016, the 2014‐15 Annual Report was submitted to the Regional Board. Subsequently in September 2016, the 2015‐16 Annual Report was submitted to the Regional Board. By this time, we had met all NOV related obligations. No further enforcement action was taken by the Regional Board.
MaintainingCompliance
Considering the resources needed to administer our Storm Water Program, FEI has continued its relationship with us by providing technical support to augment OCFEC Staff. Day‐to‐day operations and program activities, such as inspections, continue to be carried out by our Facility Operations Staff, while FEI is called on to address program level and technical issues such as, compliance with Trash TMDLs, (Total Maximum Daily Load) coordinating with County of Orange for wet weather monitoring at three outfalls on the property, and preparing strategies/studies to resolve existing storm drain infrastructure
and runoff pollution issues at the request of our staff. For example, during the 2016-2017 fiscal year, FEI provided engineering support and participated in meetings with the City of Costa Mesa
OC Fair & Event Center • 32nd District Agricultural Association 88 Fair Drive, Costa Mesa, CA 92626 • (714) 708-1500 • ocfair.com
for the design of the Arlington Bioswale and street improvement project. During the 2017‐18 fiscal year, FEI has studied alternatives to replace the desilting sediment basin at the equestrian center. This study also included a feasibility study on diverting parking lot runoff to the newly built Arlington Bioswale to take advantage of its design as a storm water runoff treatment system for OCFEC. Currently, we are in compliance with the Phase II MS4 Permit and have met all permit obligations. We have periodically communicated with Regional Board staff to inform them of progress, since the Storm Water Program requires iterative improvement from year‐to‐year. The Regional Board had not expressed any issues or concerns since the NOV in 2016.
FutureActions
FEI is continuing to assist our Storm Water Program as it has for the past two years. They are confident in OCFEC’s leadership and staff to carry out much of the program’s compliance activities. Their role is to supplement our program by providing their technical expertise in program implementation when and where it is needed. For the 2018‐19 fiscal year this includes, but are not limited to, updating the SWMP as programs are iteratively improved, preparing the 2018‐19 Annual Report, providing audit/inspection support, assisting with the Trash TMDL implementation, and preparing additional studies for infrastructure/drainage solutions to minimize storm water runoff pollution from the property.
CurrentActivity
During the September Board meeting I reported we had an anonymous complaint of a nuisance run off. The Regional Water Board staff visited the OCFEC on July 26th and along with OCFEC staff and Fusco Engineering representative carried out a review of the area.
In anticipation of an official NOV being issued OCFEC and FEI started planning improvements. The main improvement being the install of a new storm sewer catch basin east of the Corporation yard.
On November 1st OCFEC did finally receive the anticipated NOV, 5 items are to be addressed relating to Housekeeping, Procedures, Inspections, Training, Minimization of hot spot discharge.
OCFEC staff along with FEI is diligently working on these items.
Violations of the permit may result in charges of up to $10,000 for each day of violation.
5 items addressed; Provision F.5.b.4 – The OCFEC does train on pollution prevention and good housekeeping however during Fair time, the staff and users on grounds is at its peak. The permanent staff is notified to be alert and observant for anything that may need to be addressed by management as well as remediate the current observed situation. In the New Hire Orientation pre Fair. The OCFEC will be presenting an overview of training on:
1. Pollution Prevention
2. Pressure washing do’s & Don’ts and approved locations
3. Implement IDDE training (Illicit Discharge Detection Elimination) for year round staff as well as
Fair time staff.
Staff will be providing signage in locations that have higher potential of illicit discharges as well as handing out brochures to all new vendors that come on grounds year round or Fair time.
OC Fair & Event Center • 32nd District Agricultural Association 88 Fair Drive, Costa Mesa, CA 92626 • (714) 708-1500 • ocfair.com
Provision F.5.d.3.i – We do have an IDDE manual and plan in place. We will be more conscious of all grounds surroundings and implementation of our processes. We will reiterate the empowering of our staff to address illicit discharges once seen and not leave it up to management. Provision F.5.f.3.i – The corporate yard has been made a hot spot and measure have been installed to make sure any water or illicit discharge coming from the yard or surrounding areas will be captured and diverted to the sewer. This work has been completed by installing a catch basin and lateral sewer line to the main sewer. We have spill kits at the corporation yard and the staff will be trained to implement any remediation efforts needed. Provision F.5.f.5.ii – The hiring of the new Health& Safety/Environmental Supervisor will assist with inspections required by the water board. Provision B.3 – The main mall pressure washing containment issue has been resolve by installing a catch basin to collect the water and disperse it to the sewer. The OCFEC is also in the process of obtaining full capture systems installed on storm water inlets to help contain debris. The OCFEC has been diligently working with FEI in determining the viability and capacity of the silt basin in the equestrian center; it currently works as designed however it was designed in the 70s when there was no testing and requirement for storm water and before the clean water act. The OCFEC is currently working with Fuscoe to plan for the 2018‐2019 Annual Reporting contract as well as developing a scope for an enhanced storm water capture and diversion plan.
Santa Ana Regional Water Quality Control Board
November 1, 2018
Jerry Eldridge CERTIFIED MAIL
. EDMUND G. B AOWN J A. GOVERNOR
~ M ATTHEW R ODAIOUEZ l """'-._ ~ SECRETARY FOR ~ ENVIRONMENTAL PROTECTION
OC Fair & Event Center 88 Fair Drive
RETURN RECEIPT REQUESTED
Costa Mesa, CA 92626
jeldridge@ocfair. com
NOTICE OF VIOLATION OF THE GENERAL PERMIT FOR WASTE DISCHARGE REQUIREMENTS (WDRS) FOR STORM WATER DISCHARGES FROM SMALL MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4), ORDER NO. 2013-0001-DWQ, NPDES PERMIT NO. CAS000004 (WDID 8 30M2000250)
Dear Mr. Eldridge:
Urban runoff is a major contributor of pollutants to surface and ocean waters within Southern California. To control the discharge of pollutants from Municipal Separate Storm Sewer Systems (MS4s), the 1987 amendments to the Clean Water Act established a framework for regulating pollutants in storm water runoff. Pursuant to these amendments, the State Water Resources Control Board (State Board) began regulating municipal storm water runoff through the General Permit for waste discharge requirements (WDRs) for storm water discharges from Small Municipal Separate Storm Sewer System (MS4s), NPDES Permit No. CAS000004 (Permit). The State Board renewed the Permit in 2013 through Order No. 2013-0001 -DWQ.
On July 26, 2018, Regional Board staff visited OC Fair & Event Center in response to a complaint of an unauthorized non-storm water discharge. Based on the information gathered during the inspection, Regional Board staff established the following:
• Sediment and small amounts of manure were observed in the street and concrete drainage swale south of the barns in the Equestrian Center Area;
• The drain inlet on the southeastern edge of the Equestrian Center Area was covered by a filter fabric held in place by sand bags;
• Water was observed pooling on the eastern side of the Equestrian Center Area;
• Several people on-site stated they had seen black colored discharge originating from the west of the Equestrian Center Area several times throughout the year. They described the water as "trashy and not clean looking";
• At the beginning of the inspection, Regional Board staff observed that the concrete drainage swale that runs through the middle of the Equestrian Center Area was stained dark grey, but no water was visible. At 11 :46 am, Regional Board staff observed dark
W ILLIAM RUH, CHAIR I H OPE A. S MYTHE, EXECUTIVE OFFICER
3737 Mam St, Suite 500, R1vers1de, CA 92501 I www.watertloards .ca gov/santaana
c) RECYCLED PAPER
OC Fair & Event Center - 2 - November 1, 2018
colored water in the concrete drainage swale to the west of the Equestrian Center Area. The water appeared to originate from the Corporate Yard Area;
• Waste bins were stored in the southern part of the Corporate Yard Area, approximately 20 feet away from the stained concrete drainage swale. Dark colored water was draining from the waste bins and hay was observed in the drainage swale. This appeared to be the source of the dark colored water observed to the west of the Equestrian Center Area. Manure, trash, and hay were contained in the waste bins;
• To the south of the waste bins, Regional Board staff observed a small covered barn area and several motor homes. Water was flowing from this area towards the waste bins, originating approximately 75 feet away. The source of the water was from the small barn. Manure and bedding were observed in the discharge within the barn. There were several hoses in this area, some connected to motor homes;
• A roll-off bin was observed in the Corporate Yard area immediately adjacent to the concrete drainage swale. Sediment and debris were observed under the roll-off bin;
• Standing water was observed in a ditch along the north of the site just south of Arlington Drive. Keith Holbrock stated that the water was most likely from wash water from the Main Mall Area that was not diverted into the sanitary sewer system; and,
• Howard Wen of Fuscoe Engineering stated he would identify the Corporate Yard Area as a hot spot. In addition, he stated that consideration is being given to replacing the sedimentation basin at the southeast corner of the Equestrian Center Area.
Based on the above information, Regional Board staff has concluded that OC Fair & Event Center has violated the following Sections of the Permit:
• Provision F .5. b.4 requires the Permittee to train employees on how to incorporate pollution prevention/good housekeeping techniques into Permittee Operations. The housekeeping issues observed in the Corporate Yard Area indicate this training is ineffective at reaching its intended audience;
• Provision F.5.d.3.i requires the Permittee to develop approaches to require non-storm water discharges suspected of being illicit discharges to be eliminated and to develop procedures to implement corrective actions. During the inspection, a dark colored nonstorm water discharge was observed originating from the small barn and the waste bins in the Corporate Yard Area. Procedures were not in place to prevent th is discharge or to implement corrective actions;
• Provision F.5.f.3.i requires the Permittee to conduct an inspection and assessment of pollutant discharge potential and pollutant hotspots. During the inspection, the housekeeping conditions at the Corporate Yard Area suggest that it could be a potential pollutant hotspot. Howard Wen of Fuscoe Engineering identified that the Corporate Yard Area should be designated a hot spot;
• Provision F.5.f.5.ii requires the Permittee to minimize the potential for pollutant discharge during hotspot inspections. The issues observed at the time of the inspection suggest these inspections have not been effective; and,
OC Fair & Event Center - 3 - November 1, 2018
• Provision B.3 effectively prohibits discharges through the MS4 of material other than storm water to waters of the U.S. The uncontrolled discharge of wash water that occurred earlier in the day from the Main Mall Area is not an authorized discharge listed in Provisions B.3. and is therefore a prohibited discharge. ·
Please be advised that violations of the Permit may result in the imposition of administrative civil liability in an amount of up to $10,000 for each day of violation and $10 per gallon for discharges above 1,000 gallons under Section 13385 of the California Water Code.
Please provide a response with an implementation timeline to this Notice by November 19, 2018. If you have any questions, please contact Barbara Barry via email at [email protected] or via phone at (951) 248-0375.
Sincerely,
/J<l /~ t'c," Michelle R. Beckwith, Chief Coastal Storm Water Unit
cc: Fuscoe Engineering - Howard Wen City of Costa Mesa, NPDES Coordinator - Kelly Dalton County of Orange Public Works - James Fortuna
U")
ru :r D'"'
CJ rn U")
CJ
ru CJ CJ CJ
CJ ..-'I D'"' CJ
..D
..-'I CJ ("-
U.S. Postal Service™ CERTIFIED MAIL® RECEIPT Domestic Mail Only
11•• • . ... . -, .... ..,. -
OFF I C I AL u Certified Mall Fee
$ Extra Services & Fees (check box, add fee as spproprtato) D Roturn Receipt (hardcopy) $ D Rotum Receipt (electronic) $ 0 Certified Mall Restrlctod Dol1V91)' $ D Adult Signature Required $
0 Adult Slgnatul9 Restrlctod Dollvory $
Postage
Jerry Eldridge OC Fair & Event Center 88 Fair Drive Costa Mesa, CA 92626
. . SE
Postmark Here
--------·----------------------------
PS Form 3800, April 2015 PSN 7530-02-000-9047 See Reverse for lnstruct,ons
P A G E | 1
November 14, 2018
Santa Ana Regional Water Quality Control Board
Attn: Michelle R. Beckwith, Chief
Coastal Storm Water Unit
3737 Main Street, Suite 500
Riverside, CA 92501-3348
RE: Response to Notice of Violation of the General Permit for Waste Discharge
Requirements (WDRs) for Storm Water Discharges from Small Municipal Separate Storm
Sewer System (MS4), Order No. 2013-0001-DWQ, NPDES Permit No. CAS000004 (WDID
8 30M2000250)
Dear Ms. Beckwith,
This letter has been written in response to Santa Ana Regional Water Quality Control Board’s
Notice of Violation of the General Permit for Waste Discharge Requirements (WDRs) for Storm
Water Discharges from Small Municipal Separate Storm Sewer Systems (MS4s), Order 2013-
0001-DWQ, NPDES Permit No. CAS000004, dated November 1, 2018. It serves to inform the
Regional Board staff of the actions taken to correct the noted concerns in the NOV.
COMMENTS AND RESPONSES
1. Comment: Sediment and small amounts of manure were observed in the street and
concrete drainage swale south of the barns in the Equestrian Center Area;
Response:
We hope that the Regional Board understands that the Equestrian Center is a
challenging facility to address, where the safety of horses is considered along with
storm water runoff pollution prevention. The dirt surfaces that are provided for
equestrian activities and safety happen to be the source of pollution onto the paved
street. Since the beginning of its operations, the equestrian center has implemented a
sediment basin to mitigate sediment from discharging off-site. In addition, OCFEC
staff has worked with the equestrian center operator to ensure sediment on the street
surface is minimized through regular sweeping. When necessary, written warnings
have been issued to address the condition of the street when it exceeds OCFEC policies
and expectations, as well as weekly reminders to keep the grounds clean. If OCFEC
OC FAIR & EVENT CENTER NOVEMBER 14, 2018
P A G E | 2
staff performs the repairs, the equestrian operator is back charged for the services as a
cost recovery mechanism.
Additionally, OCFEC initiated discussions earlier in the year to install sediment control
BMPs at the boundaries where the dirt transitions to asphalt. We are currently vetting
the options with the concern of minimizing trip hazards to the horses. In the
meantime, a more frequent street sweeping and cleaning schedule has been
implemented.
Implementation Timeline:
• Increased sweeping and cleaning – Completed.
• Sediment control BMP at pavement/dirt transitions – 02/2019
2. Comment: The drain inlet on the southeastern edge of the Equestrian Center Area was
covered by a filter fabric held in place by sand bags;
Response:
This catch basin sediment control is a temporary BMP implemented during dry
weather. It has been programmed into the regular maintenance of the street at the
Equestrian Center Area since before the OCFEC SWMP. OCFEC staff understands that
this BMP is not intended to be a permanent solution, and only serves to augment the
performance of the sediment basin until it is replaced or redesigned. In April 2018,
OCFEC conducted a study (with a cost-benefit analysis) to propose alternative
treatment control BMPs and drainage improvements to replace the sediment basin and
improve the catch basin design. Due to the significant costs associated with this
proposed capital improvement, it requires board approval and further studies to prove
the concepts. Currently, OCFEC has committed some funds in 2019 to implement part
of the improvements recommended by the study.
Implementation Timeline:
• Equestrian Center drainage improvements – 2019
3. Comment: Water was observed pooling on the eastern side of the Equestrian Center
Area;
Response:
The pooling water observed was due to a water line break. The area was coned to
identify the area of the break for repair crews. The break was fixed shortly after the
visit by the Regional Board. See attached Figure 1 of the repaired area.
Implementation Timeline:
• Repair water line break – Completed.
OC FAIR & EVENT CENTER NOVEMBER 14, 2018
P A G E | 3
4. Comment: Several people on-site stated they had seen black colored discharge
originating from the west of the Equestrian Center Area several times throughout the
year. They described the water as "trashy and not clean looking";
Response:
A drain is currently being installed to intercept and divert nuisance flows from the
Corporate Yard Area to the sewer (see Attachment 1 and Figures 2-5). The sewer
diversion will be plugged during rain events. Additionally, signage will be posted to
inform staff, contractors, and vendors of the diversion, along with delineating the areas
that drain to it. No activities that would generate nuisance runoff will be allowed
outside of the designated area.
Implementation Timeline:
• Sewer diversion construction – Completed.
• Signage and area delineation – 02/2019
5. Comment: At the beginning of the inspection, Regional Board staff observed that the
concrete drainage swale that runs through the middle of the Equestrian Center Area was
stained dark grey, but no water was visible. At 11 :46 am , Regional Board staff observed
dark colored water in the concrete drainage swale to the west of the Equestrian Center
Area. The water appeared to originate from the Corporate Yard Area;
Response:
See response to comment #4 and Figures 2-5.
6. Comment: Waste bins were stored in the southern part of the Corporate Yard Area,
approximately 20 feet away from the stained concrete drainage swale. Dark colored
water was draining from the waste bins and hay was observed in the drainage swale.
This appeared to be the source of the dark colored water observed to the west of the
Equestrian Center Area. Manure, trash, and hay were contained in the waste bins;
Response:
See response to comment #4. Additionally, waste bins will be moved into the
Corporate Yard Area for storage and management. Bins will not be allowed outside of
the designated areas that are tributary to the sewer diversion. Any waste bins found to
be leaking will be immediately repaired or retired. See Figures 6-7 for trash bin
location and newly constructed sewer diversion.
Implementation Timeline:
• Waste bin relocation and repair – Completed.
OC FAIR & EVENT CENTER NOVEMBER 14, 2018
P A G E | 4
7. Comment: To the south of the waste bins, Regional Board staff observed a small covered
barn area and several motor homes. Water was flowing from this area towards the waste
bins, originating approximately 75 feet away. The source of the water was from the small
barn. Manure and bedding were observed in the discharge within the barn. There were
several hoses in this area, some connected to motor homes;
Response:
The noted discharge was from the temporary barn to stable ponies during the OC Fair.
The discharge was likely due to incidental spilling from the filling of drinking water for
the ponies. It appeared that it was likely to evaporate and not believed to be a threat
for discharge into the storm drain system. See Figures 8-9 attached that represent the
frequent state of the small barn outside of fair operating times.
The noted hose in the Regional Board photo appears to be a water supply line to the
motor homes that use this area during the OC Fair.
Implementation Timeline:
• Small barn discharge cleanup – Completed.
8. Comment: A roll-off bin was observed in the Corporate Yard area immediately adjacent
to the concrete drainage swale. Sediment and debris were observed under the roll-off bin;
Response:
See response to comment #4 and Figure 10. The area around the roll-off bins will be
more frequently swept and maintained, in addition to the sewer diversion.
Implementation Timeline:
• Roll-off bin area housekeeping – Completed.
9. Comment: Standing water was observed in a ditch along the north of the site just south
of Arlington Drive. Keith Holbrook stated that the water was most likely from wash water
from the Main Mall Area that was not diverted into the sanitary sewer system; and,
Response:
The ditch along Arlington Drive is the new bioswale constructed by the City of Costa
Mesa as part of street and storm drain improvements on Arlington. The swale has
been designed with stub-outs to receive runoff from the OCFEC property in the future.
Having not been intimately involved with the Bioswale project Keith was not aware of
the current status; the property’s on-site storm drain is not connected to the bioswale
at Gate 5, where the Main Mall area may drain to. Therefore, it is unlikely that wash
water from the Main Mall Area discharged into the bioswale. The standing water may
be from irrigation of the swale for vegetation establishment.
OC FAIR & EVENT CENTER NOVEMBER 14, 2018
P A G E | 5
Under current practices, wash waters from the Main Mall Area is captured at the
surface and pumped to the sewer system. In order to further minimize unintentional
discharge of wash waters, OCFEC is in the process of designing and installing a 24”x24”
inlet diversion to a 3-stage baffle box separator for pre-treatment and then discharge
to the sewer. This would resolve any concerns regarding wash waters from this area.
See Attachment 2 for schematic of vault and sewer line addition.
Implementation Timeline:
• Main Mall sewer diversion and separator – 11/30/2018
10. Comment: Howard Wen of Fuscoe Engineering stated he would identify the Corporate
Yard Area as a hot spot. In addition, he stated that consideration is being given to
replacing the sedimentation basin at the southeast corner of the Equestrian Center Area.
Response:
As a result of annual facility inspections performed by OCFEC staff during the 2017-18
year, the Corporate Yard and Maintenance & Operations Yard were identified as hot
spots. Subsequently a SWPPP was prepared in August 2018. At the time of the
Regional Board inspection, the hot spot SWPPP was under development. Because of
the inspection, additional guidelines were added into the hot spot SWPPP to address
the commitments OCFEC made to the Regional Board, including the previously
mentioned sewer diversion. The SWPPP is available for review in SMARTS. See Figures
11-14 for current, cleaned state of the Corporate Yard Area.
In regards to the sedimentation basin, please see response to comment #2.
Implementation Timeline:
• Corporate Yard Hot Spot SWPPP – Completed.
• Sediment basin replacement – Feasibility studies are ongoing.
V IOLATIONS AND RESPONSES
11. Provision F .5. b.4 requires the Permittee to train employees on how to incorporate
pollution prevention/good housekeeping techniques into Permittee Operations. The
housekeeping issues observed in the Corporate Yard Area indicate this training is
ineffective at reaching its intended audience;
Response:
Training is provided to OCFEC staff on a bi-annual basis per the permit requirements.
Furthermore, housekeeping practices are discussed with vendors prior to the start of
the OC Fair. Due to the noted deficiencies by the Regional Board, OCFEC will now
provide training to staff on an annual basis. Educational materials will also be provided
OC FAIR & EVENT CENTER NOVEMBER 14, 2018
P A G E | 6
to vendors before the start of OC Fair, further reinforcing the policies and practices for
the Corporate Yard Area. New signage around the facility will also provide friendly
reminders of proper disposal of waste and identify designated areas draining to sewer.
Implementation Timeline:
• Pollution prevention/good housekeeping annual training – Early 2019.
• Pollution prevention signage – 02/2019.
12. Provision F.5.d.3.i requires the Permittee to develop approaches to require non-storm
water discharges suspected of being illicit discharges to be eliminated and to develop
procedures to implement corrective actions. During the inspection, a dark colored non-
stormwater discharge was observed originating from the small barn and the waste bins
in the Corporate Yard Area. Procedures were not in place to prevent this discharge or to
implement corrective actions;
Response:
The OCFEC has developed an Illicit Discharge Detection and Elimination Policies and
Procedures Manual (September 2016) that is currently employed. Bi-annual training
has been provided to staff, which will now be provided annually. Additional spill kits
will be strategically placed in the Corporate Yard Area for greater readiness.
It is worth noting that the OC Fair occurs for one month between July and August each
year, where significant resources are devoted to the operation of the OC Fair and
management of the vendors’ and visitors’ experience. During this challenging event,
certain “back of the house” activities may not get the attention they would normally
get as resources are stretched thin. Incidental discharges may be missed, as a result.
However once noticed or identified they will immediately be rectified and cleaned up.
For all other times during the year, the OCFEC property is not activated in this manner
and the detection and response to any and all discharges are immediate and effective.
Implementation Timeline:
• IDDE Program – In place since 2016.
• IDDE annual training – Early 2019.
13. Provision F.5.f.3.i requires the Permittee to conduct an inspection and assessment of
pollutant discharge potential and pollutant hotspots. During the inspection, the
housekeeping conditions at the Corporate Yard Area suggest that it could be a potential
pollutant hotspot. Howard Wen of Fuscoe Engineering identified that the Corporate Yard
Area should be designated a hot spot;
Response:
OC FAIR & EVENT CENTER NOVEMBER 14, 2018
P A G E | 7
It should be clarified that the Corporate Yard Area was already identified and
designated a hot spot by OCFEC staff earlier in the year. A hot spot SWPPP was
already under development by Fuscoe Engineering at the time of the Regional Board
inspection. The SWPPP has since been uploaded to SMARTS and is being
implemented by OCFEC staff. Also, see response to comment #12 regarding OC Fair.
Implementation Timeline:
• Corporate Yard hot spot designation – Completed.
14. Provision F.5.f.5.ii requires the Permittee to minimize the potential for pollutant discharge
during hotspot inspections. The issues observed at the time of the inspection suggest
these inspections have not been effective; and,
Response:
Hotspot inspections began in 2017-18 year and the flaw may have been that the
quarterly inspections were not performed during the time of the OC Fair, not because
the inspections were ineffective. As mentioned previously, the OCFEC property is
activated in this manner only one time during the year, over a 30-day period. For
future quarterly inspections, OCFEC will make sure that one quarterly inspection occurs
during the OC Fair each year.
Current issues will be addressed with the addition of the sewer inlet, increased training,
and additional signage around the site. Maintaining IDDE procedures and quarterly
inspections will help address future issues found in the hot spot areas.
Implementation Timeline:
• Adjustment to quarterly inspection scheduling – Completed.
15. Provision B.3 effectively prohibits discharges through the MS4 of material other than
storm water to waters of the U.S. The uncontrolled discharge of wash water that occurred
earlier in the day from the Main Mall Area is not an authorized discharge listed in
Provisions B.3. and is therefore a prohibited discharge.
Response:
It is not clear that the water in the bioswale was a result of uncontrolled discharge of
water from the Main Mall area, since drainage from this area is not connected to the
Bioswale. Standing water in the swale has been thought to be from irrigation runoff in
efforts to establish new vegetation. Nevertheless, discharge from the Main Mall Area
will be addressed with the diversion of wash water to a vault separator and sewer line
(see attached schematic). In addition, supplementary training and signage will serve as
reminders to employees and vendors of OCFEC’s washing practices and response to
any potential illicit discharges.
OC FAIR & EVENT CENTER NOVEMBER 14, 2018
P A G E | 8
Implementation Timeline:
• Main Mall sewer diversion and separator – 11/30/2018
If you have any questions regarding this response letter, please feel free to contact me.
Sincerely,
Jerry Eldridge
Director of Facilities
OC Fair & Event Center
(714) 474-5983
Enclosure
cc: Santa Ana RWQCB – Barbara Barry
OC Fair and Event Center – Ken Karns
ATTACHMENT 1
CORPORATE YARD SCHEMATIC
1 OF 1
GATE 8 TICKET BOOTH
AGR1 IN = 50 FT
2012 BASE LAYOUT
01-18-12
SHEET TITLE:
DATE:
PLOTTED BY:
SHEET NO.
REVISIONS DATE SCALE:
OC FAIR & EVENT CENTERCOSTA MESA, CA
GATE
GATE
GATE
GATE
PWBALER
COMPACTOR
OVATIONSKITCHEN
CORPORATIONYARD
FIREHYD
FIREHYD
FIREHYD
FIREHYD
GATE
2
1
MATERNITYBARN
GATE
Figure 1.
In response to Comment #3, the pooling water was due to a break in the water line. As seen in the photo above, the water line has been repaired and there is no water on the surface.
Figure 2.
Figure 3.
In response to Comment #4 and #5, new sewer connections in the Corporate Yard are currently being constructed to intercept and divert any nuisance flows.
Figure 4.
Figure 5.
In response to comment #4 and #5, newly constructed sewer inlets in the Corporate Yard will divert nuisance flows away from the existing concrete v-ditch to assure flows do not reach the catch basin in the Equestrian Center and leave the site. These drains will be plugged during rain events so stormwater can follow the natural path.
Figure 6.
Figure 7.
In response to comment #6, trash storage will remain north of the newly constructed sewer diversion. Bins will be checked for leaks and housekeeping practices will assure upkeep of trash bins.
Figure 8.
Figure 9.
In response to Comment #7, the small barn area is upkept to OCFEC standards. Incidental spilling during fair season was likely the cause to the observed water.
Figure 10.
In response to Comment #8, the stationary roll off bins are within the boundary of the newly constructed sewer diversion. More frequent sweeping will be implemented to upkeep the Corporate Yard to the state that is shown in the photo above.
ATTACHMENT 2
MAIN MALL SCHEMATIC
Additional photos below show the current state of the Corporate Yard during non-fair operating times. As noted in the response, fair time is a busy season, however, increased inspections and trainings will be implemented to ensure housekeeping practices are followed by OCFEC staff, vendors, and contractors.
Figure 11.
Figure 12.
Figure 13.
Figure 14.
Board of Directors Agenda Report MEETING DATE: JANUARY 17, 2019 ITEM NUMBER: 9E
SUBJECT: OCFEC Organizational Succession Plan Update DATE: January 11, 2019 FROM: Kathy Kramer, CEO PRESENTATION BY: Kathy Kramer, CEO ___________________________________________________________________ RECOMMENDATION Information Item only. BACKGROUND Over the past year, staff has been developing an Organizational Succession Plan for the District. With over fifty percent of OCFEC civil service workforce eligible for retirement within the next five years, the organization faces an unprecedented challenge. It is essential to build a comprehensive road map ensuring a continuous pool of talent. As such, the organization must provide training and development opportunities to ensure that as staff retires, their knowledge is transferred and the impact on the organization is minimal. Staff will present an overview of the Organizational Succession Plan process as part of this staff report. Attachment: PowerPoint presentation
Succession Planning
RightPeople RightSkills RightTime RightPlace
OC Fair & Event Center Succession Plan, 2019
Percent of Civil Service Employees Eligible for Retirement in Next 5 years at OCFEC
31% Eligible for Retirement
as of October 2018
54% Eligible for RetirementWithin Next 5
Years
15% Not Eligible forRetirement Within Next
5 Years
2
Succession Planning Framework
Step 1• Organizational
Review
Step 2
•Identify Critical Retirement Positions
Step 3
•Conduct Employee Succession Planning Survey
Step 4
•Conduct Job Analysis
3
Step 5
•Assess Internal Talent Pool
Step 6
•Transfer Knowledge
Step 7
•Legacy Retiree Workshop
Step 8
• Identify and Develop Internal Talent Pool
Step 9
•Measure, Monitor andEvaluate Success
SWOT analysis to identify internal and external challenges
Conduct a GAP analysis
Develop strategic goals for the Organizational Succession Plan supported by: Management Board of Directors
Step 1
Organizational Review
4
Create a Matrix from HR employee data Include key positions that may become
vacated, including roles that areperformed by one person and critical tothe operation
The purpose is to identify thosecandidates that are eligible forretirement within a 3 year window
Step 2
5
Identify Critical Retirement Positions:
Potential Retiree Matrix
6
Broad survey that lists all departments andcaptures respondents interest by departmentand position*
43% of OCFEC employees responded to survey
Step 3
Employee Succession Planning Survey
7
*This survey captures interest in all positions including potential retiree positions
Purpose of the Survey: To understand internal interest for futureretiree vacancies and gather in-depth information about the interestin the jobs and possible job skills outside the potential candidates’core duties.
Potential Retiree Position Inventory
(Transfer of personnel data from Potential Retiree Matrix and Employee Succession Planning Survey to create this form)
8
Review position’s current job description and remove any non-relevant tasks or add relevant job duties
HR works with incumbent and supervisor of that role to conduct job analysis
Roll previous job description and job analysis results to create a job description based on the job analysis results
Step 4
Conduct Job Analysis
9
Goal of Job Analysis: To analyze existing job descriptions and relevancy of current duties, consider future needs and skills of the position for all retiree positions.
Assess Internal Talent Pool:
Executive Team and HR reviews Potential Retiree Position Inventory to assess interested internal candidate pool. An internal candidate may be selected to move forward
- OR - The position may require external recruitment,
if no interest internally
Step 5
10
Transfer of Knowledge:
Begin process of creating a desk manual/ reference guide for each retiree position
Retiree to create a listing of key knowledge/ experience for their role and catalog it for future use. Could include key contacts, date driven functions, procedures on how to complete critical tasks
Step 6
11
Legacy Workshop:
Schedule legacy workshops with staff identified in potential retiree profile
Step 7
12
Goal of Legacy Workshop:• Provide organization an opportunity to connect emotionally
with retirees and their past accomplishments helping themcreate their legacy. What do they want to be known for andhow can they be part of passing on and continuing theirlegacy?
• Walk through succession plan process with retirees.Answer questions and clarify retirees’ role in the success ofthe plan
• Explain expectations of retiree when working side-by-sidewith potential successor
Legacy Workshop:
Provide educational resources for retirement
Organize & develop legacy celebration for retirees
Step 7
13
Identify and Develop Internal Talent Pool:
Internal staff that is interested in future retiree positions are provided an updated job description.
Internal Staff completes a self-evaluation accessing their skill set relative to the requirements of the retiree’s position
HR/Executive Team reviews all evaluations to determine best candidate to move forward with succession planning
Development Plan is then created for qualified applicant to begin the succession process with the retiree candidate
If more than one applicant was interested in position, candidates not selected will be interviewed and skills accessed to possibly determine other opportunities for them to pursue. Then a plan is developed to help them gain experience/education to prepare them for a future opportunity.
Step 8
14
Measure, Monitor, & Evaluate Progress and Outcomes:
Monitor progress of developmental plans quarterly Retiree, successor, supervisor and HR
Hold quarterly Succession Planning Meetings to review plan and check on training and development goals
Make adjustments as needed to the development plan
There will be fluctuations based on organizational demands and potential vacancies in key roles
Step 9
15
Measure, Monitor, & Evaluate Progress and Outcomes:
Next Steps:
HR team conducting roll-out meetings across the organization
Schedule legacy workshops for first quarter 2019
Finalize Organizational Succession Plan “play book” and distribute to leadership
Step 9
16