PROJECT ID: GFS 1105
Boat House Design & Construction
An Major Qualifying Project Report
submitted to the Faculty of WORCESTER POLYTECHNIC INSTITUTE
in partial fulfillment of the requirements for the Degree of Bachelor of Science
By
Henry Moore
3/14/2011
Approved:
Guillermo Salazar, Advisor
Leonard Albano, Advisor
ii
Abstract: This project proposes a design for an addition to the rowing WPI facility in Shrewsbury MA. The scope of
this project includes a need assessment, review of local codes and ordinances, site analysis, preliminary
layout, structural design of the building foundations and building frame as well as cost estimates and
construction schedule. A 3D digital model of the facility is also developed.
iii
Capstone Design Experience It is a requirement of the Accreditation Board for Engineering and Technology (ABET) that all Civil
Engineering degrees include a Capstone Design Experience. The Capstone Design Experience must
incorporate prior coursework, engineering standards, and realistic constraints, and should address some
of the following concerns: environmental, sustainability, manufacturability, ethical, health and safety,
social, and political. The Boat House Design and Construction MQP proposed a design for an addition to
the rowing WPI facility in Shrewsbury MA. The scope of this project includes a need assessment, review
of local codes and ordinances, site analysis, preliminary layout, structural design of the building
foundations and building frame as well as cost estimates and construction schedule. A 3D digital model
of the facility is also developed.
One consideration that this MQP addressed was the environmental aspects of the Capstone Design
Experience through its adherence to restrictions by the Shoreline Protection Act. Attention was paid to
building code, making sure that the proposed building meets fire code, and would be safe to occupy.
This project addresses the several economic aspects. The first economic consideration was where to
place the proposed facility. A new lot on the lake, tearing down the existing rowing center, or making an
addition to the boat bays were all considered. It was decided that the most practical option was an
addition to current facilities, for the ease and use of the athletes. The cost estimate of the facility gave a
hypothetical cost for the facility. By addressing these and other concerns, this project satisfies the
Capstone Design Experience as stated by ABET.
iv
Acknowledgements I would like to thank Larry Noble, Larry Gluckman and Kevin McDermott for their cooperation and input
during the interview portion of this project. I would also like to thank Professor Salazar for his
continuing advice.
v
Table of Contents Abstract: ........................................................................................................................................................ ii
Capstone Design Experience ........................................................................................................................ iii
Acknowledgements ...................................................................................................................................... iv
Table of Contents .......................................................................................................................................... v
List of Figures ............................................................................................................................................... vi
List of Tables ............................................................................................................................................... vii
Chapter 1: Introduction: .............................................................................................................................. 1
Chapter 2: Background: ............................................................................................................................... 2
Chapter 3: Methodology .............................................................................................................................. 4
Chapter 4: Results: ....................................................................................................................................... 5
Section 4.1: Information from Interviews: ............................................................................................... 5
Section 4.2: Comparison of Facilities: ...................................................................................................... 5
Section 4.3: Alternative Facility Solutions and Locations ........................................................................ 6
Section 4.3.1: Land Purchase ............................................................................................................... 6
Section 4.3.2: Demolition of the Donahue Rowing Center .................................................................. 6
Section 4.4: Architectural Design ............................................................................................................. 7
Section 4.4.1: Design Requirements .................................................................................................... 7
Section 4.4.2: Facility Floor Plan .......................................................................................................... 8
Section 4.5: Foundation Design ............................................................................................................... 9
Section 4.6: Cost Analysis ....................................................................................................................... 10
Section 4.7: Financing ............................................................................................................................ 11
Section 4.8: Project Management.......................................................................................................... 12
Chapter 5: Conclusions .............................................................................................................................. 13
Bibliography: ............................................................................................................................................... 14
Appendices .................................................................................................................................................. 15
Appendix A: Availability of Land on Lake Quinsigamond ....................................................................... 15
Appendix B: Additional Views of Proposed Facility ............................................................................... 16
Appendix C: Foundation Designs ............................................................................................................ 17
Appendix D: Quantity Take off and Details of Cost Estimating .............................................................. 19
Appendix E: Calculations for Financial Options ..................................................................................... 28
Appendix F: Project Timeline Information ............................................................................................. 29
vi
List of Figures Figure 1: Overhead Picture of Facilities at Lake Quinsigamond ................................................................... 2
Figure 2: Floor Plan ....................................................................................................................................... 8
Figure 3: West Elevation ............................................................................................................................... 9
Figure 4: View of Meeting Room .................................................................................................................. 9
Figure 5: Cross Section of Foundation ........................................................................................................ 10
vii
List of Tables Table 1: Comparison of Boating Facilities ..................................................................................................... 6
Table 2: Summary of Cost Estimate ............................................................................................................ 11
Table 3: Finance Options ............................................................................................................................. 11
Chapter 1: Introduction:
Since Worcester Polytechnic Institute’s varsity crew teams were formed in 1999 the team has grown to
many times its original size. The original men’s varsity program consisted of 8 varsity athletes and a
handful of novice athletes. Now the team has almost 30 varsity athletes and over 30 novice athletes,
and has sent rowers to compete at World Championships, crew’s highest level. However, the crew
team still uses the original exercise room it was given, a 20 x 22 ft room on the third floor of Alumni
gymnasium. This room presents potential health hazards, since the large amount of dust can induce
coughing fits among athletes. As the team has grown, so has the amount of equipment. The boat
storage area in the boat house on Lake Quinsigamond has become over crowded, without sufficient
space to store the boats. In the winter time, when temperatures are below freezing and the lake is still
unfrozen, the crew team still practices outside on the lake. There is not sufficient inside space to warm
up and stretch down after these winter practices at the lake. With such a large team it is difficult to lift
weights at the existing WPI Fitness Center without monopolizing the weight room that is open to the
entire student body and faculty of WPI. A facility specifically designed for the crew team would rectify
all of these problems, as well as helping the crew team improve their performance by giving them access
to more space and equipment. Currently there is a new Sports and Recreation Center being constructed
at WPI. This new center will include a set of rowing tanks, which allow for simulation of an on-the-water
experience, and some area for ergometers. This center will be completed in one to two years, and
should help with some of the overcrowding issues in the weights area, but will not affect the amount of
space the crew team has to practice, or the issue of boat storage.
This project proposes a design for an addition to the rowing WPI facility in Shrewsbury MA. The scope of
this project includes a need assessment, review of local codes and ordinances, site analysis, preliminary
layout, structural design of the building foundations and building frame as well as cost estimates and
construction schedule. A 3D digital model of the facility is also developed.
In conducting this work there were several challenging parts of this project. The first related to the
architectural design of the building. To overcome this challenge, the personal experience of the author
has been used and similar facilities have been studied. Another challenge was the placement of the
building on the lot, since there is limited space, and setbacks that made it even more constrained. The
third challenge was related to the availability of another suitable lot in the area. There were only 18
available lots, and of those 18, only 4 are large enough. The average cost of those four lots is $650,000.
Considering the final predicted cost of the new construction is approximately $870,000, the cost of a lot
seems extremely high.
The final proposal calls for an addition to the current boat house facility on Lake Quinsigamond. This
would be most beneficial to the crew team in combining the current storage area with additional
storage area and indoor exercise area. Choosing to construct in addition instead of purchasing a lot
would also help to minimize costs.
2
Chapter 2: Background:
The WPI Men’s Crew team became a Varsity Program in the fall of 1999. The team started out with only
eight varsity rowers and a handful of novices recruited around campus. Over the years the team has
developed into a much larger program. Currently there are 28 varsity athletes, and 31 novice athletes
on the Men’s Crew team. The WPI Women’s Crew team has gone through a similar growth, and has
almost as many team members.
Currently the WPI teams launch and store boats at the Donahue Rowing Center on Lake Quinsigamond
in Worcester, MA. Below is an overhead picture of the current facilities, showing the Donahue Rowing
center and the boat bays.
Figure 1: Overhead Picture of Facilities at Lake Quinsigamond
Construction began on the Donahue Rowing Center in 1992. In the first stage of construction, six bays
were built, as well as the Donahue Rowing Center. The center is a facility built closer to the water, with
a large viewing room, a small office, a small kitchen, and women’s and men’s bathrooms. The second
stage of construction added four bays were added to the initial six. These facilities are shared by
Shrewsbury High School, Clark University, Worcester Academy, the Bancroft School, Assumption
College, Quinsigamond Rowing Association, St. John’s Prep, St. Mark’s School and WPI. WPI has control
of a full boat bay, and shares a boat bay with the College of the Holy Cross. These boat bays need to
provide storage for 8 eight person boats, 4 four person boats, 4 two person boats, and 4 one person
boats. Eight person boats are approximately 65 feet long, four person boats are 35 feet long, two
person boats are 25 feet long, and one person boats are 18 feet long. Boats with riggers attached are
approximately 6 feet wide. The facility provides storage for extra parts, tools, eight launches, eight sets
3
of oars (8 oars per set), miscellaneous supplies, and other exercise equipment. On campus the team has
an ergometer room on the third floor of Alumni Gymnasium. Ergometers are a machine that simulates
the rowing stroke and can measure the power output of each athlete. The room has space for 13
ergometers, and there are an additional five ergometers outside around the indoor track. For weight
lifting facilities the crew team uses the WPI Fitness Center in downstairs Alumni.
The new Sports and Recreation center that is being constructed above Alumni field will contain some
new facilities for the crew team. The building will contain a 16 person moving water rowing tanks, and
there will be room for 10 ergometers in the room. There will also be a new weight room in the building.
Once the new athletic facility is complete the existing Alumni Gymnasium will be renovated to offer
more academic space.
There are several issues with current facilities that prompt a change to help alleviate the issues. One
such issue is the lack of available space in Alumni Gymnasium. It is impossible for the Men’s or
Women’s Crew team to hold a practice for all of its members. There is not sufficient space for all of the
members. The space is also old, and some of the interior construction is rotting. There is also a large
amount of dust, which has induced asthma attacks in several athletes. The weight room also does not
have sufficient space for the team to hold a practice, and has limited hours. The boathouse has a limited
amount of space, and it is very difficult to maneuver and store boats. Several boats have to be stored
on the floor, and there is not room to work on boats inside. During inclement weather there is not room
for the team to stretch, warm up, and conduct workouts at the Donahue Rowing Center. Additional
space would help lighten the demands on other facilities. The new athletic facility does address some of
these needs, but a loss of space in Alumni Gymnasium does not help the current situation. The options
to alleviate the situation are renovating the current ergometer room, buying a lot on Lake
Quinsigamond and constructing a new building, tearing down the Donahue Rowing Center and
constructing a new facility, or constructing an addition to the current facilities on Lake Quinsigamond.
An addition to the Lake Quinsigamond boat house would be most convenient for the athletes, and
seems to be the most economical. Renovations to the current facility on campus are impractical
because there is not enough room for the proposed additions, and the area is already designated for
academic use. Buying a lot for new construction is not practical because the cost of a lot comes close to
doubling the cost of the proposed addition. It is inadvisable to tear down the Donahue Rowing Center
because it is still used by other teams who boat out of the same boat house. Therefore an addition to
the current facilities seems like the most logical solution.
4
Chapter 3: Methodology To develop the proposed boat house I have broken down the project into four phases. Phase 1 assessed
the necessities of the building, and researched local laws and building codes for waterfront buildings.
Interviews were conducted during phase 1 to better understand what comprises a facility of a
comparable program, what a team needs to give the team the best chance of success, and how the
current WPI facilities are used and how future facilities will be used. Phase 2 included designing the
building, including placement on the lot. It was important to make sure that the building design met all
requirements from the building code that was reviewed in phase 1, or else the building could not be
built. Phase 3 consisted of the structural design of foundations for the building, determined by the
expected loads of the building. The foundation designs were made using Allowable Stress design (ASD).
Phase 4 included cost estimating, developing a building timeline, and financing considerations.
5
Chapter 4: Results:
Section 4.1: Information from Interviews: Interviews were conducted with Lawrence Noble, head of WPI Rowing, Kevin McDermott, head of
Trinity Rowing, and Lawrence Gluckman, former national team coach. The purpose of the interview
with Lawrence Noble was to assess the current facilities available at WPI, what will become available
with the construction of the new athletic facility, and ascertain what facilities would be desired in the
future. The purpose of the interview with Kevin McDermott was to interview a coach at a similarly sized
Division III school which has recently built a new facility and to find out pros and cons of the facility
design. The purpose of the interview with Lawrence Gluckman was to find out what characteristics
were needed in a facility to allow a team to become successful at the most competitive levels of the
sport.
Lawrence Noble identifies the Donahue Rowing Center and the ergometer room in Alumni Gymnasium
as the main areas for boat storage and training facilities for the WPI crew team. The crew team has
limited access to weight lifting room in Alumni gymnasium. The new Sports and Recreation center will
provide rowing tanks that allow rowers to simulate water rowing while on land, and also provide some
exercising area. The construction of the new Sports and Recreation center also means renovations to
Alumni Gymnasium, and the crew team will lose its ergometer room. The ergometer room in Alumni
Gymnasium contains 13 ergometers that allow the athletes to practice the rowing motion. This is a
training tool used by the athletes every day, but is not as similar to rowing as the rowing tanks. There
are not enough ergometers for all of the athletes to use them at once, and there is not enough room for
additional ergometers. The new tank room will have room for approximately ten ergometers around its
perimeter.
The Trinity College Bliss Boat House was completed in 2005. The Bliss Boat House is located on the
Connecticut River in Hartford, Connecticut. The Trinity College crew team is similar in size to the WPI
crew team, with the men’s and women’s team each having between 40 and 60 athletes. The boat house
provides storage for all of Trinity’s boats, and provides exercise areas, meeting areas, and coaches’
offices. Kevin McDermott, the Trinity head coach, listed the pros of the facility as: having boat storage
and exercise facilities in the same location, available space for personal boat storage, finished space for
team functions, and amount of space and equipment for team workouts. The cons of the facility were
listed as: lack of parking, need of a system to hold exercise machines in place, upstairs floor surface
unsuitable for weight lifting, aluminum stud walls do not allow pull up bars, insufficient free area, and
lack of air conditioning upstairs.
Traits that Larry Gluckman identified as crucial to a facility are: sufficient space for whole team to
exercise to encourage team unity, sufficient bathroom and locker room area, kitchen facilities for
independence of athletes, sufficient boat storage area, and lounge areas for athletes.
Section 4.2: Comparison of Facilities: Due to the similarities between the WPI Crew team and Trinity Crew team, it seems practical to make a
comparison of the facilities.
6
Table 1: Comparison of Boating Facilities
Features Trinity College Current WPI Facilities
WPI Facilities w/ new athletic center
WPI Facilities w/ proposed addition and new athletic center
Sufficient Boat storage
Yes No No Yes
Tanks Yes No Yes Yes
Sufficient Locker Room facilities
Yes No No Yes
Ergometer Room w/ Sufficient Space
Yes No No Yes
Exercise Space Yes No No Yes
Dedicated Weight lifting facility
Yes No No Yes
Kitchen Yes Yes Yes Yes
Meeting Area Yes No No Yes
As is shown in the comparison, the new athletic facility does improve certain aspects of the facilities, but
does not address all of the areas of concern brought up by the interviewees. These areas include boat
storage, weight lifting area, ergometer area and meeting area.
Section 4.3: Alternative Facility Solutions and Locations There are three distinct options considered for the design and potential construction of the WPI Crew
facility. The options are: 1. buying land surrounding the lake and building a new facility, 2. tearing down
the existing boat house and building a new facility, 3. tearing down the Donahue Rowing Center building
and constructing a larger building combining the shared amenities with WPI facilities, or 4. make an
addition to the current Donahue Rowing Center boathouse bays.
Section 4.3.1: Land Purchase
When considering purchasing land around Lake Quinsigamond several problems became apparent.
There are very few lots available that are large enough to accommodate a facility and provide sufficient
parking. Out of 18 available lots, only four were large enough for the proposed facility (the list of lots
can be found in Appendix A). These lots are also very expensive. The average price of those four lots is
$650,000. Since the cost of the proposed facility is $870,000, the additional cost of a lot would increase
the cost of the project by 75%. Three out of four of the acceptable lots have existing structures.
Demolition costs come mostly from the waste disposal part of the project, and there could also be issues
with some of the older structures which contain lead paint and asbestos. Being so near to a body of
water demolition is very strictly regulated, and hazardous materials could make this a very difficult
process.
Section 4.3.2: Demolition of the Donahue Rowing Center
Tearing down the existing Donahue Rowing Center building is also very impractical. The building is one
of the only portions of the site that is open to the public, and since the facility to be constructed is
primarily for WPI Crew it is not practical to eliminate public space. The loss of the use of the rowing
7
center during construction would affect not only WPI, but the other schools who use the center. Since
there are races during the fall, spring and summer, there is no advantageous time for construction.
From a financial standpoint, it is very unreasonable to consider building anywhere besides the current
lot. Any lot would have the cost of the proposed building, but building on another lot would include the
cost of the lot, and any demolition costs. The average cost of an available lot on Lake Quinsigamond is
$525,475 (see Appendix A for table of lot prices and sizes). This amount itself is substantial, but of all of
these lots, only four are large enough for the proposed facility, observing the setbacks necessary in the
Shoreline Protection Act. Of those four the average cost is $650,000. Adding approximately $15,000 to
this cost for the demolition of the current structure, and the cost prior to construction of the facility is
over $665,000. When adding this cost to the $870,000 cost of the proposed facility, the total cost
comes to $1.535 million.
After considering the project it seems that the best option is to build an addition to the Donahue Rowing
Center boathouse bays. This is based on price, continuing availability of the facilities during
construction, and use in conjunction with the current boat bays. There is already plentiful parking, it is
in close proximity to the other existing WPI boat bays and can be used in conjunction with it. There is an
overhead picture of the boat bays and Donahue Rowing Center in Appendix B. There is a parking lot
behind the existing boat bays with approximately 50 spots and there is an adjacent town parking lot
with approximately 120 additional slots. There is a precedent for Shrewsbury allowing privately funded
construction on town owned property. The current boat house facilities were funded by the Donahue
family, and the land they on which this facility was built was and still is owned by the town. Since the
town owns the lot it is very reasonable to think that the town would be amenable to making an addition
to their current facility.
Section 4.4: Architectural Design
Section 4.4.1: Design Requirements
When designing the boat house facility, there are certain aspects of the International Building Code that
needed to be observed. Examples are:
25’ Setback from shoreline
60’ setback from other properties
Building is classified as A-3 so must comply with following guidelines
Maximum height 40’
Unlimited area
Must have automated sprinkler system
Maximum occupancy determined by 50 ft^2 per person, so 200 people
Walls minimum fire rating of 1 hour
Must be reasonable continuity to points of egress
No more than 7” height difference out of point of egress
Door width must be greater than 32”
Distance to nearest point of egress be no more than 250’
8
All of these requirements were considered and met by the proposed design.
Section 4.4.2: Facility Floor Plan
The major areas of the facility are the entrance lobby, coaching office, two locker rooms, exercise area,
meeting room, and boat storage area. These can be seen in photos and plans below, and more details
can be seen in Appendix B. The main entrance to the facility would be through the lobby. From the
lobby you can enter into the boat bay, coaches’ office, or exercise area. From the exercise area it is
possible to enter either of the two locker rooms, or the meeting area. The locker rooms occupy the end
of the building farthest from the lake, since their lack of windows would not provide a view. The
coaches’ office allows a view of the access to the boat bay, but also features windows viewing the
exercise room, to better supervise the athletes. The meeting room features windows viewing onto the
lake and access to the exercise room and boat bay. All of these features allow for athletes to progress
from one part of the facility to another, and also for coaches to supervise multiple areas of the facility at
once. The gross square footage of the building is 10,080 ft^2. All of the plan, elevation, and interior
views shown below are taken from a Revit Architectural model created to help show the design of the
facility.
Figure 2: Floor Plan
The figure below shows the west elevation, which faces the lake. The building is 72’ wide. It features
three windows in the meeting room facing the lake, and a door exiting the meeting room to the exterior.
There is also a door exiting the boat bay, and a large overhead door from where the boats would be
carried. The roof has a pitch of 4”/12”.
9
Figure 3: West Elevation
Figure 4: View of Meeting Room
Section 4.5: Foundation Design Foundation designs were conducted for the proposed structure. The foundations were designed to
fulfill the capstone design requirement of this project. The major calculations for the design included
the bearing capacity of the foundations, and the allowable settlement. The bearing capacity was
determined using Terzaghi’s equation. This equation accounts for the shape of the foundations, the
width, the density of the soil, the internal angle of friction of the soil, and the cohesive strength of the
soil. The equation gave an ultimate stress that was reduced by a factor of safety, giving the allowable
stress. Then the actual stress and allowable stress were compared, to make sure the allowable stress
was greater than the allowable stress. The allowable settlement was calculated for the soil using
Coduto’s equation for settlement. The equation gives a value for the settlement of the structure, which
10
must be less than the allowable settlement of the structure. In this case the allowable settlement was
1”, and the calculated settlement was 0.03255”. There were no available soil profiles of the site, so a
representative profile was assumed. This profile was assumed based on the author’s observations of
the banks surrounding the lake, which are very sandy. The values for the variables used in the equation
were taken from the Foundation Engineering Handbook. The full foundation calculations can be found
in Appendix C. The foundations are continuous strip footings, with a 2’ width. The walls are 1’ thick,
and have a height of 5’. #5 rebar reinforcement is in the walls and footings, and a keyway runs beneath
the wall. The foundations are under the exterior walls of the building, and also bisect the building
longitudinally. The figure below shows the cross section of the foundation walls, with the rebar and
keyway shown.
Figure 5: Cross Section of Foundation
Section 4.6: Cost Analysis Once the facility was designed, cost for the facility was estimated. This was done by conducting a
quantity take off, which quantifies all of the materials, labor, and equipment necessary for the project.
To ascertain the quantities to be estimated, a quantity take off was conducted using the dimensions
from the Revit model. This allowed wall, floor, ceiling, etc. areas to be calculated. These quantities
were then multiplied by an estimated unit cost from a 2011 copy of R.S. Means, a estimate guide with
national averages for construction materials and labor. The labor costs were based on the national
average, and were not adjusted to a specific area. Most portions of the projected were evaluated using
this method, but certain portions of the project were estimated using a lump sum, since there was not
enough information about them. The lump sum estimates were general conditions, plumbing, electrical,
and HVAC. To have a figure for these portions, I contacted a general contractor within the construction
industry. The contractor provided a cost estimate for each division, and provided an approximate
duration for the completion of each lump sum division. Below is a summary table containing the overall
cost for each division, and a total cost. The estimated total cost of the project is $868,940.83. The
detailed quantities from the takeoff can be found in Appendix D. These quantities are used in
11
combination with the unit prices from R.S. Means to create an item by item cost estimate, which can be
found in Appendix D.
Table 2: Summary of Cost Estimate
Division
Estimated Cost
Division 1: General Conditions
50,000.00
Division 2: Site Work
21,068.75
Division 3: Concrete
76,321.81
Division 4: Masonry
75,808.07
Division 6: Wood
24,944.00
Division 7: Dampproofing and Thermal Protection
74,163.56
Division 8: Openings
13,217.00
Division 9: Finishes
111,901.60
Division 10: Specialties
10,000.00
Division 15: Mechanical
80,000.00
Division 16: Electrical
35,000.00
Subtotal
572,424.79
Contingency
114,484.96
Overhead
103,036.46
Profit
78,994.62
Total
$868,940.83
Section 4.7: Financing The final cost of the project is projected as $868,940.83. This would most likely be funded by taking out
a loan, over a period ranging from the duration of construction, to 30 years. WPI would be the
institution taking out the loan, since the building would be WPI property. Hopefully WPI would be able
to partially fund the project through donors, to reduce costs. Reasons for a shorter or longer loan length
can be available funds, loan rates, cash flow, and other financial reasons. Some sample loan lengths are
listed in the table below, and sample calculations can be found in Appendix E. An interest rate of 4.5%
was assumed for all loans.
Table 3: Finance Options
Loan Length Interest Paid Total
6 month $19772.78 $888,713.61
1 year $39995.49 $908,936.32
3 year $125593.91 $994,534.74
5 year $219253.51 $1,088,194.34
7 year $321733.43 $1,190674.26
12
From the above table it is very obvious that the longer the length of the loan, the more interest costs
incurred. Therefor it is advisable to finance the project over as short a period as possible. It is not
always possible to pay a loan back over a short period of time due to cash flow difficulties, and
sometimes a longer loan period is necessary. As can be seen in the table, the longer then length of the
loan, the greater the cost of interest that is incurred. So it would be practical for WPI to try and raise
funds through alumni donations, or grants, to avoid incurring these interest costs.
Section 4.8: Project Management To give more detail about this project, a timeline was created using Microsoft Project. The duration for
each activity in the project was determined using productivity rates from 2011 R.S. Means. By
multiplying the estimate quantity by the productivity rate, it gives the duration of each activity. A Gantt
chart and list of activities are included in Appendix F. The table in Appendix F lists each of the individual
items taken off and estimated earlier in the project. The items are listed with their proposed duration,
start date, end date, and predecessors. The predecessors are used to establish a hierarchy of activities,
showing which activities must be completed before others can be started. The project is predicted to
take place between the dates of 5/9/11 and 10/14/11. The start date was chosen because it comes
after the completion of the collegiate racing season. This means that the majority of the use of the
facility will not begin again until the fall. These construction dates also avoid any periods of extremely
harsh weather, such as winter.
13
Chapter 5: Conclusions The goals of this project were to assess needs, review building code, analyze site possibilities, design
building, design foundations, takeoff quantities, estimate cost, discuss financing and determine the
project timeline. After interviewing various coaches, including the WPI coach, it was determined that
the main needs of the facility were additional boat storage, exercise area, ergometer area, and access to
weight lifting equipment. The new Sports and Recreation center does add additional weight lifting
equipment and rowing tanks, but additional renovations remove the current ergometer room. This
made it important to incorporate ergometer space and exercise area into the facility design. Review of
building code gave certain restrictions on facility size and fire suppression equipment for occupancy that
were incorporated in the design. After reviewing the possibilities for the location of a new facility, it was
decided that the most practical and cost effective solution would be to make an addition to the boat
house facilities on Lake Quinsigamond. Once a location was selected, a design of the building was made
using Revit Architectural. The foundations were designed using Terzaghi’s and Coduto’s equations for
allowable bearing stress and allowable settlement. The building model created in Revit was used to
takeoff material quantities needed for the project. These quantities were used with unit prices from R.S.
Means to estimate a cost of the proposed facility. Although there are numerous options for financing
the proposed facility, the key finding from the financial section was that the length of the loan should be
kept to as short as possible, and an attempt to raise money from donors should be made. The duration
of individual activities in the project were calculated using productivity rates from R.S. Means. These
activities were scheduled using a hierarchal system to create a timeline and order of activities leading to
the completion of the project.
In summary, all initial goals of the project were completed, and additional tables, plans, calculations,
and timelines can be seen in the appendices, as referenced earlier in the project.
14
Bibliography: 1. Day, Robert W. (2006). Foundation Engineering Handbook. McGraw-Hill. New York City, NY 2. (2010). Building Construction Cost Data. R.S. Means Company. Kingston, MA 3. (2009). 2009 International Building Code 4. Ching, Francis (2008). Building Construction Illustrated 4th Edition. Wiley. Hoboken, NJ 5. Dagostino, Francis; Peterson, Steven (2011). Estimating in Building Construction 7th Edition.
Pearson. Upper Saddle River, NJ
15
Appendices
Appendix A: Availability of Land on Lake Quinsigamond Below is a table showing the location, acreage, price, and status of any existing structure of any available
land on Lake Quinsigamond.
Table A1: Available Lots on Lake Quinsigamond
Address Acreage Price Existing Structure?
213 N Qunisig Ave
0.324 $675,900 Yes,house
15 Groveside Path
0.090 $269,900 Yes,house
Lot A N Quinsig Ave
0.268 $699,900 Yes, house
136 South Quinsig
0.082 $259,900 Yes, house
40 Huntington Ave
0.118 $126,00 Yes, house
252 South Quinsig Ave
0.340 $385,00 Yes, house
12 Old Faith Road 0.096 $224,700 Yes, house
20 Old Faith Road 0.349 $1,379,900 Yes, house
210 South Quinsig Ave
0.214 $489,000 Yes, house
208 A South Quinsig
0.178 $389,000 Yes, house
208 South Quinsig Ave
0.148 $289,000 Yes, house
Lot 1 South Quinsig Ave
0.785 $499,000 No
Lot 2 South Quinsig Ave
1.3 $625,000 No
77 Bay View Drive 0.198 $317,500 Yes, house
5 Smith Lane 0.251 $559,999 Yes, house
232 South Quinsig Ave
2.1 $1,050,000 Yes, condemned
128 South Quinsig Ave
0.178 $279,000 Yes, house
110 South Quinsig Ave
0.408 $399,900 Yes, house
Average 0.41261
$525,475
16
Appendix B: Additional Views of Proposed Facility The figures below show an additional elevation of the structure, a south-facing section of the building
showing the locker room, exercise room, and meeting area, as well as on overhead image of the boat
house and Donahue Rowing Center on Lake Quinsigamond.
Figure B1: South Elevation
Figure B2: Section A-A of Building
17
Appendix C: Foundation Designs Below are the scanned copies of the foundation calculations and design.
Figure C1: Foundation Calculations
19
Appendix D: Quantity Take off and Details of Cost Estimating The first 5 sheets are scanned copies of the quantity take off. Following that is a table using the take off
quantities and unit prices to determine the cost of each activity and division.
24
Table D1: Cost Estimating Spreadsheet
Price
Activity Quantity Unit
Material
Labor
Equip
Unit Price
Total Price
Production/Day
Duration (days)
Subtotal
Division 1
General Requirements
Lump sum - - - -
50,000 - -
Subtotal
50000
Division 2 Topsoil
Removal 428 bcy
0.58 1.21 1.79 766.1
2 865 0.5 Structural
Excavation 943 bcy
3.19 1.75 4.94 4658.
42 200 4.7
Backfill 1111 lcy
0.63 1.81 2.44 2710.
84 800 1.4 Haul away 21 lcy
1.91 2.19 4.1 86.1 144 0.1
6" Gravel 9730 sf 0.6 0.2 0.02 0.82
7978.6 8600 1.1
Fine Grading 1081 sy
0.61 0.52 1.13
1221.53 3000 0.4
Utility Excavation 131 bcy
3.19 1.75 4.94
647.14 205 0.6
Mobilization 3
each
500 500
1000 3000 3 1.0
Subtotal
21068.75
Division 3 Formwork
Footings 848 SFCA 1.63 2.7
4.33
3671.84 485 1.7
Walls 4240
SFCA 0.82 3.99
4.81
20394.4 505 8.4
Keyway 424 LF 0.18 0.65
0.83
351.92 530 0.8
Expansion Joints 432 LF 1.41 1.72
3.13
1352.16 200 2.2
Reinforcement
Footings 0.9 ton 855 740
1595
1435.5 2.1 0.4
25
Walls 1.8 ton 855 515
1370 2466 3 0.6
Slab 101 csf 21.5 26.5
48 4848 29 3.5 Concrete
Footings 31.5 CY 103 14.3 0.39
117.69
3707.235 120 0.3
Walls 78.5 CY 103
17.15 0.47
120.62
9468.67 100 0.8
Slab 187 CY 103 15.6 0.42
119.02
22256.74 130 1.4
Floor Finishing 9730 SF 0 0.39 0.04 0.43
4183.9 2400 4.1
Dampproofing 1420 SF 0.2 0.44
0.64 908.8 665 2.1
Vapor Barrier 101
Square 3.34 9.3
12.64
1276.64 37 2.7
Subtotal
76321.81
Division 4 12"
ConcreteBlock 6108 SF 4.29 7.5
11.79
72013.32 250 24.4
Mortar 293 CF 8.8 1.95
10.75
3149.75 143 2.0
Expansion Joints 250 LF 1.72 0.86
2.58 645 400 0.6
Subtotal
75808.07
Division 6
End Trusses 2 each 376 159
535 1070 20 0.1
Trusses 46
each 366 153
519 23874 30 1.5
Subtotal
24944
Division 7
Drip Edge 292 LF 0.46 0.86
1.32 385.4
4 400 0.7 Plywood
sheathing 21280 SF 0.7 0.53
1.23 26174
.4 1300 16.4 Asphalt
Shingles 213 Square 74 53
127 27051 27.5 7.7
Polyurethane Insulation 7308 SF 0.82 0.26 0.2 1.28
9354.24 3000 2.4
Fiberglass 6880 SF 0.7 0.77
1.47 10113 1350 5.1
26
Insulation (9 1/2" R30)
.6
Base Flashing 284 SF 1.57 2.25
3.82 1084.
88 130 2.2
Subtotal
74163.56
Division 8 Doors
Overhead 1 each 1700 460
2160 2160 1.5 0.7
Single Flush, Vision 5
each 435 40.5
475.5
2377.5 17 0.3
Double, Glass 2
each 640 86
726 1452 11 0.2
Single Glass 1
each 650 40.5
690.5 690.5 17 0.1
Single Flush 3
each 345
345 1035 17 0.2
Windows
0 0
Awning 10 each 335 129
464 4640 6 1.7
Fixed 2
each 315 116
431 862 6 0.3
Subtotal
13217
Division 9 Partition wall,
Metal Stud, Gypsum, tape and finish 6888 SF 0.86 1.97
2.83
19493.04 350 19.7
Base Board 829 LF 2.22 1.43
3.65
3025.85 240 3.5
Acoustic Ceiling 6880 SF 2.31 0.91
3.22
22153.6 380 18.1
Carpet 212 SY 51 4.31
55.31
11725.72 75 2.8
Tile 1536 SF 4.71 3.21
7.92
12165.12 180 8.5
Rubber Flooring 3168 SF 12.5 1.18
13.68
43338.24 275 11.5
Subtotal
111901.6
Division 10 Boat Storage
System 1 each 4000 6000
10000 10000
3.0
27
Subtotal
10000
Division 15 Plumbing and
Sprinkler System 1
each 15000
10000
25000 25000
22.0
HVAC 1
each 40000
15000
55000 55000
19.0
80000
Division 16
Electrical 1 each 20000
15000
35000 35000
21.0
Subtotal
35000
Subtotal
572424.8
Contingency (20%)
686909.7
Overhead (15%)
789946.2
Profit (10%)
868940.8
28
Appendix E: Calculations for Financial Options Below are a set of sample calculations used to determine interest and total cost based on an interest
rate and principal amount.
Financing Options: Equations used A=Pe^rt, I A=Total cost P=Principal r=rate t=time periods I=interest
costs
Sample Calculation: P=868,940.83, r=4.5% t=1 year
A=(868940.83)e^(.045*1)= 908936.32 I=888713.61-868.940= 39995.49
29
Appendix F: Project Timeline Information Below is a table containing information for the individual activities needed for the construction of the
project. Following that are images of the timeline extracted from Microsoft Project.
Table F1: List of Activities
Task Name Duration Start Finish Predecessors
Begin Project 0 days Mon 5/9/11 Mon 5/9/11
Excavation for foundation and footings
5 days Mon 5/9/11 Fri 5/13/11 1
Formwork for footings 2 days Mon 5/16/11 Tue 5/17/11 2
Install footing rebar 1 day Wed 5/18/11 Wed 5/18/11 3
Pour footings 1 day Thu 5/19/11 Thu 5/19/11 4
Formwork for walls 8 days Fri 5/20/11 Tue 5/31/11 5
Install wall rebar 1 day Wed 6/1/11 Wed 6/1/11 6
Pour walls 1 day Thu 6/2/11 Thu 6/2/11 7
Waterproof foundation 2 days Fri 6/3/11 Mon 6/6/11 8
Install perimeter drain 1 day Fri 6/3/11 Fri 6/3/11 8
Backfill around foundation 1 day Mon 6/6/11 Mon 6/6/11 10
Dig and run utilities from source
1 day Mon 5/9/11 Mon 5/9/11 1
Run under slab utilities 1 day Tue 5/10/11 Tue 5/10/11 12
Run under slab pipes 1 day Tue 5/10/11 Tue 5/10/11 12
Level and fine grade interior 1 day Wed 5/11/11 Wed 5/11/11 13,14
Install vapor barrier 1 day Thu 5/12/11 Thu 5/12/11 15
Install floor WWF 1 day Fri 5/13/11 Fri 5/13/11 16
Pour slab on grade 1 day Mon 5/16/11 Mon 5/16/11 17
Install base flashing 2 days Tue 6/7/11 Wed 6/8/11 11
Construct masonry walls 15 days Thu 6/9/11 Wed 6/29/11 19
Erect roof trusses 2 days Thu 6/30/11 Fri 7/1/11 20
Sheath roof 8 days Sat 7/2/11 Tue 7/12/11 21
Drip edge roof 1 day Thu 6/30/11 Thu 6/30/11 22
Shingle roof 8 days Fri 7/1/11 Tue 7/12/11 23
Install exterior doors 2 days Thu 6/30/11 Fri 7/1/11 20
Install exterior windows 2 days Thu 6/30/11 Fri 7/1/11 20
Enclosed structure 0 days Tue 7/12/11 Tue 7/12/11 24,25,26
Install metal studs 9 days Wed 7/13/11 Mon 7/25/11 20,22
Insulate building 8 days Tue 7/26/11 Thu 8/4/11 28,22,20
Rough in electric 14 days Tue 7/26/11 Fri 8/12/11 28
Rough in plumbing 13 days Tue 7/26/11 Thu 8/11/11 28
Rough in HVAC 16 days Tue 7/26/11 Tue 8/16/11 28
Install sheetrock 7 days Wed 8/17/11 Thu 8/25/11 30,31,32
Install suspended ceiling 18 days Fri 8/26/11 Tue 9/20/11 33
30
Install interior doors 2 days Wed 9/21/11 Thu 9/22/11 33
Install counters and cabinets
2 days Wed 9/21/11 Thu 9/22/11 33
Paint walls 4 days Fri 9/23/11 Wed 9/28/11 33,35
Install baseboard 3 days Wed 9/21/11 Fri 9/23/11 37
Install carpet 3 days Mon 9/26/11 Wed 9/28/11 38
Install tile floors 9 days Mon 9/26/11 Thu 10/6/11 38
Install rubber flooring 12 days Mon 9/26/11 Tue 10/11/11 38
Finish electric 9 days Wed 9/21/11 Mon 10/3/11 37
Finish plumbing 8 days Wed 9/21/11 Fri 9/30/11 37
Finish grade exterior 1 day Wed 7/13/11 Thu 7/14/11 24
Substantial completion 0 days Tue 10/11/11 Tue 10/11/11 44,38,39,40,41,42,43
Punch List 3 days Wed 10/12/11 Fri 10/14/11 45
Final Completion 0 days Fri 10/14/11 Fri 10/14/11 46
Figure F1: Gantt Chart Part 1