+ All Categories
Home > Documents > Bond behaviour of steel plate reinforced concrete beams

Bond behaviour of steel plate reinforced concrete beams

Date post: 14-Nov-2021
Category:
Upload: others
View: 6 times
Download: 0 times
Share this document with a friend
30
University of Wollongong University of Wollongong Research Online Research Online Faculty of Engineering and Information Sciences - Papers: Part B Faculty of Engineering and Information Sciences 2018 Bond behaviour of steel plate reinforced concrete beams Bond behaviour of steel plate reinforced concrete beams Mazin Mohammed Sarhan Sarhan University of Wollongong, [email protected] Muhammad N. S Hadi University of Wollongong, [email protected] Lip H. Teh University of Wollongong, [email protected] Follow this and additional works at: https://ro.uow.edu.au/eispapers1 Part of the Engineering Commons, and the Science and Technology Studies Commons Recommended Citation Recommended Citation Sarhan, Mazin Mohammed Sarhan; Hadi, Muhammad N. S; and Teh, Lip H., "Bond behaviour of steel plate reinforced concrete beams" (2018). Faculty of Engineering and Information Sciences - Papers: Part B. 1802. https://ro.uow.edu.au/eispapers1/1802 Research Online is the open access institutional repository for the University of Wollongong. For further information contact the UOW Library: [email protected]
Transcript
Page 1: Bond behaviour of steel plate reinforced concrete beams

University of Wollongong University of Wollongong

Research Online Research Online

Faculty of Engineering and Information Sciences - Papers: Part B

Faculty of Engineering and Information Sciences

2018

Bond behaviour of steel plate reinforced concrete beams Bond behaviour of steel plate reinforced concrete beams

Mazin Mohammed Sarhan Sarhan University of Wollongong, [email protected]

Muhammad N. S Hadi University of Wollongong, [email protected]

Lip H. Teh University of Wollongong, [email protected]

Follow this and additional works at: https://ro.uow.edu.au/eispapers1

Part of the Engineering Commons, and the Science and Technology Studies Commons

Recommended Citation Recommended Citation Sarhan, Mazin Mohammed Sarhan; Hadi, Muhammad N. S; and Teh, Lip H., "Bond behaviour of steel plate reinforced concrete beams" (2018). Faculty of Engineering and Information Sciences - Papers: Part B. 1802. https://ro.uow.edu.au/eispapers1/1802

Research Online is the open access institutional repository for the University of Wollongong. For further information contact the UOW Library: [email protected]

Page 2: Bond behaviour of steel plate reinforced concrete beams

Bond behaviour of steel plate reinforced concrete beams Bond behaviour of steel plate reinforced concrete beams

Abstract Abstract This technical note presents an experimental study on the bond behaviour of chequer steel plate reinforcements in concrete members based on the beam-end method. The effects of lozenges of the chequer steel plate, the use of steel bolts, and the thickness of the concrete cover on the bond behaviour are investigated. The experimental program includes five specimens designed as beam-end pullout members. Each specimen is 225 mmwide, 300 mmhigh and 600 mmlong. Stirrups with 80 mmcentre-to-centre spacing are used as confinement for all specimens. The first specimen is reinforced with a deformed steel bar whereas the remaining specimens are reinforced with steel plates. All specimens except for the one reinforced with a smooth steel plate failed by pullout accompanied by splitting crack. The lozenges of chequer steel plate increased the ultimate pullout failure load by 80% compared to that of the specimen reinforced with a smooth steel plate. It has also been found that the pullout failure load of a steel plate reinforced concrete member can be significantly affected by the thickness of the concrete cover. Two other significant findings are that the pre-ultimate slippage of a steel plate reinforced concrete member is much less than that of a deformed steel bar reinforced one, and that the post-ultimate behaviour of the former is much more ductile than the latter. Comparisons between the present test results and the earlier test results involving reinforced concrete beams subjected to four-point bending tests suggest that the beam-end method may not be an appropriate method for comparing the bond strength of a chequer steel plate against that of a reinforcing bar.

Disciplines Disciplines Engineering | Science and Technology Studies

Publication Details Publication Details Sarhan, M. M., Hadi, M. N. S. & Teh, L. H. (2018). Bond behaviour of steel plate reinforced concrete beams. Construction and Building Materials, 189 751-756.

This journal article is available at Research Online: https://ro.uow.edu.au/eispapers1/1802

Page 3: Bond behaviour of steel plate reinforced concrete beams

1

Bond Behaviour of Steel Plate Reinforced Concrete Beams 1

Mazin M. Sarhan1 2

1Ph.D. Candidate, School of Civil, Mining and Environmental Engineering, University of 3

Wollongong, Australia. E-mail: [email protected] 4

Muhammad N. S. Hadi2

5

2 Associate Professor, School of Civil, Mining and Environmental Engineering, University of 6

Wollongong, Australia (corresponding author). Email: [email protected] 7

Lip H. Teh3 8

3Associate Professor, School of Civil, Mining and Environmental Engineering, University of 9

Wollongong, Australia. E-mail: [email protected] 10

11

Abstract 12

This technical note presents an experimental study on the bond behaviour of chequer steel 13

plate reinforcements in concrete members based on the beam-end method. The effects of 14

lozenges of the chequer steel plate, the use of steel bolts, and the thickness of the concrete 15

cover on the bond behaviour are investigated. The experimental program includes five 16

specimens designed as beam-end pullout members. Each specimen is 225 mm wide, 300 mm 17

high and 600 mm long. Stirrups with 80 mm centre-to-centre spacing are used as confinement 18

for all specimens. The first specimen is reinforced with a deformed steel bar whereas the 19

remaining specimens are reinforced with steel plates. All specimens except for the one 20

reinforced with a smooth steel plate failed by pullout accompanied by splitting crack. The 21

lozenges of chequer steel plate increased the ultimate pullout failure load by 80% compared 22

Page 4: Bond behaviour of steel plate reinforced concrete beams

2

to that of the specimen reinforced with a smooth steel plate. It has also been found that the 23

pullout failure load of a steel plate reinforced concrete member can be significantly affected 24

by the thickness of the concrete cover. Two other significant findings are that the pre-ultimate 25

slippage of a steel plate reinforced concrete member is much less than that of a deformed 26

steel bar reinforced one, and that the post-ultimate behaviour of the former is much more 27

ductile than the latter. Comparisons between the present test results and the earlier test results 28

involving reinforced concrete beams subjected to four-point bending tests suggest that the 29

beam-end method may not be an appropriate method for comparing the bond strength of a 30

chequer steel plate against that of a reinforcing bar. 31

Keywords: beam-end test; concrete bond; chequer steel plate; reinforced concrete; 32

reinforcement slippage; reinforcement toughness; steel plate reinforcement. 33

34

1. Introduction 35

The bond strength between concrete and its steel reinforcement is a key factor for the 36

ultimate load-carrying capacity of a reinforced concrete member. It also influences some 37

serviceability design issues such as crack width, crack spacing and deflection of the member 38

[1-3]. According to ACI-408R-03 [4], the transfer of forces from a deformed reinforcement 39

bar to the surrounding concrete takes place by (a) chemical adhesion between the bar and the 40

concrete, which is controlled by the surface condition of the bar and the concrete type; (b) 41

frictional forces between the bar and the concrete, which depends on the interface’s 42

roughness, normal forces on the surface of the bar, and relative slippage between the bar and 43

the concrete; and (c) mechanical anchorage or bearing of the ribs against the concrete. 44

Page 5: Bond behaviour of steel plate reinforced concrete beams

3

There are five well-known methods to investigate the bond between concrete and steel 45

reinforcement bars. The first method is the direct pullout test recommended by RILEM-7-II-46

128 [5] and employed by Alavi-Fard and Marzouk [6], Chan et al. [7], Campione et al. [8], 47

Fang [9], Fang et al. [10], Bamonte and Gambarova [11], Cattaneo and Rosati [12], Tastani 48

and Pantazopoulou [13], Belarbi et al. [14], and Desnerck et al. [15]. The direct pullout 49

method uses a concrete cylinder with a known bonded length of the bar, and can be carried 50

out with either the concentric or eccentric position of the bar. There are several reasons for 51

selecting this method, including the ease of fabrication, the simplicity of the test, and the 52

ability to isolate the different parameters that have effects on the overall bond behaviour. 53

The second and third methods are the anchorage beam and the splice beam tests 54

recommended by ACI-408R-03 [4], depicted in Figures 1(a) and 1(b), respectively. The 55

anchorage beam method uses a concrete beam with a specified bonded length of the bar and 56

two flexural splits, tested under four-point bending [16]. The splice beam method uses a 57

concrete beam with a known bonded length of the bar and a known splice length of the bars 58

(the splice length exists in the constant moment zone). The splice beam specimen is relatively 59

easy to fabricate, and provides a similar bond strength to that obtained using the beam 60

anchorage method. The splice beam method has been used by several researchers, for 61

example Zuo and Darwin [17], Ichinose et al. [18], Mazaheripour et al. [19], Bandelt and 62

Billington [20], and Prince et al. [21]. 63

The fourth method is the beam-bending test introduced by RILEM-7-II-28D [22], depicted in 64

Figure 1(c). The specimen consists of two symmetrical blocks connected to each other by a 65

steel hinge at the top and by the reinforcement bar near the bottom. It is subjected to four-66

point bending during the test. It has been employed by Belarbi et al. [14], Desnerck et al. 67

Page 6: Bond behaviour of steel plate reinforced concrete beams

4

[23], Kotynia [24], Almeida Filho et al. [25], Chikh et al. [26], Mazaheripour et al. [19], and 68

Tutikian et al. [27]. 69

The fifth method is the beam-end test recommended by ASTM-A944−10 [28], which uses a 70

concrete beam with a known bonded length of the bar, as depicted in Figure 2. In order to 71

avoid conical surface failure of the specimen, a certain length of the bar close to the beam end 72

is unbonded by using plastic sleeves, as shown in Figure 2. The beam-end method has been 73

used by El-Hacha et al. [29], Sofi et al. [30], Sarker [31], Sarker [32], Hongwei and Yuxi [33] 74

and Moen and Sharp [34]. 75

The present study investigates the bond behaviour of beams reinforced with chequer steel 76

plates using the beam-end method recommended by ASTM-A944−10 [28]. It also provides 77

comparisons between the present test results and those obtained by the authors for plate and 78

bar reinforced concrete beam specimens subjected to four-point bending tests [35]. 79

80

2. Experimental program 81

2.1 Specimen configurations and preparation 82

A total of five chequer-plate reinforced concrete specimens, confined with stirrups of 10-mm 83

plain steel bars spaced at 80 mm from each other, were tested. Each concrete specimen was 84

225 mm wide, 300 mm high, and 600 mm long, embedding a 100 mm by 10 mm steel 85

chequer plate over 225 mm in the manner shown in Figure 2. The specimen designations are 86

shown in Table 1. 87

The first specimen (BE-N20) had a N20 steel bar (20-mm-diameter deformed steel bar of 500 88

MPa nominal yield stress), as shown in Figure 2(a). Each of the remaining four specimens 89

Page 7: Bond behaviour of steel plate reinforced concrete beams

5

(BE-HP, BE-HSP, BE-HBP, and BE-VP) had a chequer steel plate of a yield stress between 90

330 and 390 MPa. The steel plate was installed horizontally in Specimen BE-HP, as shown in 91

Figure 2(b). In Specimen BE-HSP, the steel plate had two smooth faces as the lozenges were 92

removed, as indicated in Figure 2(c). Specimen BE-HBP had a steel bolt of 20 mm diameter 93

and 100 mm length welded to the steel plate (on the smooth face) at the mid-distance of the 94

embedded length, as shown in Figure 2(d). The nominal yield stress of the steel bolt was 460 95

MPa. Specimen BE-VP had the same details as Specimen BE-HP except that the steel plate 96

was embedded vertically, as shown in Figure 2(e). 97

Figure 3 shows the geometry of the lozenges in the chequer steel plates used in the present 98

study. The plate had a regular pattern of raised lozenges on one of the two faces, the reverse 99

face was smooth (featureless face). Each lozenge was 5.5 mm wide, 26 mm long, and 1.5 mm 100

high. The perpendicular distance between any two parallel neighbouring lozenges was 22.5 101

mm, and the lozenges came in two right angle directions. 102

The lozenges of the chequer steel plate for Specimen BE-HSP were removed using a grinder, 103

resulting in a featureless surface as shown in Figure 4(a). The steel bolt in Specimen BE-HBP 104

was completely welded around its circumference to the smooth surface of the chequer steel 105

plate, as shown in Figure 4(b). 106

The steel bar and chequer steel plates were unbonded by using PVC pipes and PVC tapes, 107

respectively. Silicone glue was used at the ends (circumferences) of the unbonded areas to 108

prevent the encroachment of concrete. Steel wires were used to fasten the stirrups to the 109

longitudinal steel bars. Steel chairs having a height of 20 mm were placed under the stirrups 110

to provide the bottom cover for each specimen. Steel screws were placed on the bottom of the 111

formwork to prevent horizontal movement of the chequer steel plate during concrete casting. 112

Page 8: Bond behaviour of steel plate reinforced concrete beams

6

The interior surfaces of the formwork and the reinforcements were cleaned from dust using 113

compressed air prior to casting the concrete. A ready-mix concrete with a maximum 114

aggregate size of 10 mm was used. To remove air bubbles from the concrete, an electrical 115

vibrator was used for each specimen. The specimens were cured by keeping them wet using 116

Hessian rugs and plastic sheets for 28 days. 117

118

2.2 Material properties 119

For the purpose of determining the concrete compressive strength, concrete cylinders were 120

cast based on Australian Standards 1012.9-1999 [36], 100 mm in diameter and 200 mm in 121

height. The concrete cylinders were cured in a water tank until the respective days of the tests. 122

The compressive strengths, each as the average of three samples, were 32.6, 42.3, and 49.2 123

MPa at 7, 28, and 56 days, respectively. 124

In order to obtain the indirect tensile strength of concrete, concrete cylinders were cast 125

according to Australian Standards 1012.10-2000 [37], 150 mm in diameter and 300 mm in 126

height. The indirect tensile strength of concrete was found to be 3.5 MPa. 127

Three 500-mm long samples of both the plain (R10) and the deformed (N20) steel bars were 128

tested in tension according to Australian Standards 1391-2007 [38] using a 500-kN Instron 129

universal testing machine. The average yield stress of the plain bar was found to be 365 MPa, 130

and that of the deformed bar was 540 MPa. The corresponding tensile strengths were 490 131

MPa and 625 MPa, respectively. 132

Page 9: Bond behaviour of steel plate reinforced concrete beams

7

Five tension coupons of the chequer steel plates, each being 80 mm wide and 500 mm long, 133

were also tested according to Australian Standards 1391-2007 [38]. The average yield stress 134

was found to be 370 MPa and the tensile strength was 484 MPa. 135

136

2.3 Test procedure 137

The beam-end specimens were tested in the manner depicted in Figure 5. The tests were 138

carried out by using the 600 kN actuator. Each beam-end specimen was placed on a steel 139

beam and partially capped at the top with a 25-mm thick steel plate. The concrete beam-end 140

specimen was thus anchored to the steel beam by running two 28-mm steel threaded rods 141

through itself between the steel beam flange and the cap steel plate, secured with nuts. Two 142

supports were used to restrain the specimens in the horizontal direction, as indicated in Figure 143

5. 144

All the tests were carried out under a displacement controlled loading regime at the stroke 145

rate of 1 mm/minute. The applied axial tension load and the displacement were recorded 146

through an internal load cell. Each beam-end pullout specimen was loaded until the pullout 147

failure, which was observed as a decrease in the applied load with an increase in the 148

displacement. 149

150

3. Experimental results and discussions 151

Except for the specimen reinforced with a smooth steel plate (Specimen BE-HSP), the failure 152

mode involved pullout of the embedded steel plate or bar and splitting crack of the concrete 153

along the embedded length, as shown in Figure 6. The surface cracks were observed after the 154

Page 10: Bond behaviour of steel plate reinforced concrete beams

8

respective ultimate test loads were reached, starting from the anchorage end on the soffit side 155

and propagating towards the loaded end. For each of Specimens BE-HP, BE-HBP and BE-156

VP, a wedge formed between the soffit and one of the two adjoining sides. On the other hand, 157

no visible cracks were observed for Specimen BE-HSP, which failed by pullout of the plate 158

only. 159

A high level of confinement was provided in these beam-end specimens by the transverse 160

reinforcement. The confinement constrained the progress of splitting cracks, produced a 161

significant increase in the ultimate load, and affected the failure mode. The R10 stirrup bars 162

acted as shear reinforcements during crack propagation and therefore presented more ductile 163

behaviour of the specimens. No yield or rupture of the steel bar or chequer steel plate was 164

observed for any of the specimens. The behaviour of the present beam-end specimens was 165

consistent with that found by Zuo and Darwin [17] and El-Hacha et al. [29]. 166

Figure 7 shows the load-displacement graphs of the present beam-end specimens. The peak 167

pullout loads of Specimens BE-N20, BE-HP, BE-HSP, BE-HBP, and BE-VP were 176, 99, 168

55, 127, and 199 kN, respectively. It is interesting to note that, prior to the ultimate limit state, 169

the slippage of each of the plate reinforcements was much smaller than that of the deformed 170

bar reinforcement. The reason is that the bond area of each steel plate was much larger than 171

that of the steel bar. 172

It can also be seen from the results of Specimens BE-HP and BE-HSP that the lozenges of the 173

chequer steel plate increased the bond load by 80%, emphasising the benefit of using chequer 174

steel plates rather than plain steel plates for concrete reinforcement. 175

The result of Specimen BE-VP points to the very significant effect of the concrete cover’s 176

thickness on the bond strength. Further research is required to quantify such an effect in terms 177

of the cover thickness. 178

Page 11: Bond behaviour of steel plate reinforced concrete beams

9

A significant outcome of the present test results is that all the steel plate reinforcements 179

behaved in a significantly more ductile manner post the ultimate limit state than the steel bar 180

reinforcement. Their differences are quantified in terms of toughness, defined as the area 181

under the bond-slippage curve [20]. The toughness was calculated until 30 mm of slippage 182

for each specimen. Figure 8 shows the toughness values of the present specimens. 183

However, by comparing the peak pullout loads of the five specimens against the 184

corresponding yield loads of the steel reinforcements shown in Table 1, it can be seen that the 185

plate reinforced specimens failed at loads well below the latter, in contrast to the deformed 186

bar reinforced specimen. 187

It would therefore appear from the present beam-end tests that the chequer steel plates did not 188

have adequate bond strength to enable themselves to yield when used as horizontal 189

reinforcements in concrete beams. However, this apparent indication is inconsistent with the 190

test results of Hadi et al. [35] for steel plate reinforced concrete beams subjected to four-point 191

bending tests. The four-point bending tests demonstrated that, not only the chequer steel plate 192

reinforced beams attained similar yield moments to the deformed bar reinforced beam, but 193

also exhibited much more ductile post-ultimate behaviour. In the four-point bending tests 194

[35], the deformed steel bars had a similar yield load to that of the chequer steel plates. 195

196

5. Conclusions 197

This technical note has described an experimental study to investigate the bond behaviour of 198

steel plate reinforcements in concrete members. The following findings can be summarised: 199

Page 12: Bond behaviour of steel plate reinforced concrete beams

10

1. The general failure mode of beam-end specimens was pullout accompanied by splitting 200

crack. Only the specimen reinforced with a smooth steel plate had a simple pullout failure 201

without visible cracks. 202

2. The lozenges of chequer steel plate increased the pullout load by 80% compared with the 203

smooth steel plate. 204

3. The existence of steel bolt (welded to the chequer steel plate) increased the pullout load 205

by 28%. 206

4. The steel plate reinforced specimens had much less slippage prior to the ultimate limit 207

state compared to the deformed steel bar reinforced specimen. The steel plate reinforced 208

specimens had much better toughness than the deformed steel bar reinforced specimen. 209

The reason is that the bond area of each steel plate was much larger than that of the steel 210

bar. 211

5. The thickness of the concrete cover can have a significant effect on the pullout failure 212

load of the steel plate reinforced specimen. 213

6. The existing equations cannot be used to estimate the bond strength of the steel plate 214

reinforcements. 215

7. The pullout failure loads of the beam-end specimens with steel plate reinforcements were 216

much lower than the corresponding yield loads of the reinforcements, in contrast to the 217

case of the deformed steel bar specimen. 218

8. The beam-end method may not be an appropriate method for comparing the bond 219

performance between a chequer steel plate and a steel bar, used as tensile reinforcements 220

in a concrete beam subjected to bending. 221

222

Acknowledgements 223

Page 13: Bond behaviour of steel plate reinforced concrete beams

11

The authors wish to thank Messrs Cameron Neilson, Ritchie McClean, Fernando Escribano, 224

and Alan Grant for their help in conducting the experimental work. The first author would 225

also like to thank the Iraqi government for the financial support of his Ph.D scholarship. 226

227

References 228

[1] Z. P. Bazant, S. Sener, Size effect in pullout tests, ACI Materials Journal, 85 (1988) 347-229

351. 230

[2] Z. P. Bazant, Z. LI, M. Thoma, Identification of stress-slip law for bar or fiber pullout by 231

size effect tests, Journal of engineering mechanics, 121 (5) (1995) 620-625. 232

[3] J. Zuo, D. Darwin, Bond strength of high relative rib area reinforcing bars, Structural 233

Engineering and Engineering Materials SM Report No. 46, University of Kansas 234

Center for Research, Inc. (1998). 235

[4] ACI 408R-03, Bond and development of straight reinforcing bars in tension, American 236

Concrete Institute Committee 408, Farmington Hills, MI, US, 2003. 237

[5] RILEM 7-II-128, RC6: Bond test for reinforcing steel. 1. Pull-out test, RILEM technical 238

recommendations for the testing and use of construction materials, E & FN Spon, 239

London, UK, 1994. 240

[6] M. Alavi-Fard, H. Marzouk, Bond behavior of high strength concrete under reversed pull-241

out cyclic loading, Canadian Journal of Civil Engineering, 29 (2002) 191-200. 242

[7] Y.W. Chan, Y.S. Chen, Y.S. Liu, Development of bond strength of reinforcement steel in 243

self-consolidating concrete, Structural Journal, 100 (2003) 490-498. 244

Page 14: Bond behaviour of steel plate reinforced concrete beams

12

[8] G. Campione, C. Cucchiara, L. La Mendola, M. Papia, Steel–concrete bond in lightweight 245

fiber reinforced concrete under monotonic and cyclic actions, Engineering Structures, 246

27 (2005) 881-890. 247

[9] C. Fang, Bond strength of corroded reinforcement under cyclic loading, Magazine of 248

Concrete Research, 58 (2006) 437-446. 249

[10] C. Fang, K. Gylltoft, K. Lundgren, M. Plos, Effect of corrosion on bond in reinforced 250

concrete under cyclic loading, Cement and Concrete Research, 36 (2006) 548-555. 251

[11] P. F. Bamonte, and P. G. Gambarova, High-bond bars in NSC and HPC: study on size 252

effect and on the local bond stress-slip law, Journal of Structural Engineering, 133 (2) 253

(2007) 225-234. 254

[12] S. Cattaneo, and G. Rosati,. “Bond between steel and self-consolidating concrete: 255

experiments and modeling.” ACI Structural Journal, 106 (4) (2009) 540-550. 256

[13] S. P. Tastani, S. J. Pantazopoulou, Direct tension pullout bond test: experimental results, 257

Journal of Structural Engineering, 136 (6) (2009) 731-743. 258

[14] A. Belarbi, D. N. Richardson, M. K. Swenty, L. H. Taber, Effect of contamination on 259

reinforcing bar-concrete bond, Journal of Performance of Constructed Facilities, 24 (3) 260

(2010) 206-214. 261

[15] P. Desnerck, J. M. Lees, C. T. Morley, Bond behaviour of reinforcing bars in cracked 262

concrete, Construction and Building Materials, 94 (2015) 126-136. 263

[16] B. S. Hamad, A. Y. H. Ali, M. H. Harajli, Effect of fiber-reinforced polymer 264

confinement on bond strength of reinforcement in beam anchorage specimens, Journal 265

of Composites for Construction, 9 (1) (2005) 44-51. 266

Page 15: Bond behaviour of steel plate reinforced concrete beams

13

[17] J. Zuo, D. Darwin, Splice strength of conventional and high relative rib area bars in 267

normal and high-strength concrete, ACI Structural Journal, 97 (4) (2000) 630-641. 268

[18] T. Ichinose, Y. Kanayama, Y. Inoue, J. Bolander, Size effect on bond strength of 269

deformed bars, Construction and Building Materials, 18 (2004) 549-558. 270

[19] H. Mazaheripour, J. A. O. Barros, J. M. Sena-Cruz, M. Pepe, E. Martinelli, Experimental 271

study on bond performance of GFRP bars in self-compacting steel fiber reinforced 272

concrete, Composite Structures, 95 (2013) 202-212. 273

[20] M. J. Bandelt, S. L. Billington, Bond behavior of steel reinforcement in high-274

performance fiber-reinforced cementitious composite flexural members, Materials and 275

Structures, 49 (1-2) (2016) 71-86. 276

[21] M. J. R. Prince , G. Gaurav, B. Singh , Splice strength of deformed steel bars embedded 277

in recycled aggregate concrete, Structures, 10 (2017) 130-138. 278

[22] RILEM 7-II-28 D, RC5: Bond test for reinforcing steel. 1. Beam test, RILEM technical 279

recommendations for the testing and use of construction materials, E & FN Spon, 280

London, UK. 1994. 281

[23] P. Desnerck, G. De Schutter, L. Taerwe, Bond behaviour of reinforcing bars in self-282

compacting concrete: experimental determination by using beam tests, Materials and 283

Structures, 43 (1) (2010) 53-62. 284

[24] R. Kotynia, Bond between FRP and concrete in reinforced concrete beams strengthened 285

with near surface mounted and externally bonded reinforcement, Construction and 286

Building Materials, 32 (2012) 41-54. 287

Page 16: Bond behaviour of steel plate reinforced concrete beams

14

[25] F. M. Almeida Filho, M. K. El Debs, A.L.H.C. El Debs, Numerical approach of the bond 288

stress behavior of steel bars embedded in self-compacting concrete and in ordinary 289

concrete using beam models, Revista IBRACON de Estruturas e Materiais, 6 (3) 290

(2013), 499-512. 291

[26] N. Chikh, A. Merdas, A. Laraba, R. Benzaid, Study of the bond behavior of concrete 292

beam strengthened with NSM-CFRP, Proceedings of the World Congress on 293

Engineering, U.K., 3 (2013). 294

[27] B. F. Tutikian, T. Hilgert, J. J. Howland, Adherence comparison of concrete with 295

unprotected steel and hot galvanized steel, BRACON Structures and Materials Journal, 296

7 (2) (2014) 313-320. 297

[28] ASTM-A944−10, Standard test method for comparing bond strength of steel reinforcing 298

bars to concrete using beam-end specimens, American Society for Testing and 299

Materials , West Conshohocken, PA, US, 2015. 300

[29] R. El-Hacha, H. El-Agroudy, S. H. Rizkalla, Bond characteristics of high-strength steel 301

reinforcement, ACI Structural Journal, 103 (6) (2006) 771-781. 302

[30] M. Sofi, J. S. J. Van Deventer, P. A. Mendis, G. C. Lukey, Bond performance of 303

reinforcing bars in inorganic polymer concrete (IPC), Journal of Materials Science, 42 304

(9) (2007), 3107-3116. 305

[31] P. Sarker, Bond strengths of geopolymer and cement concretes, Advances in Science 306

and Technology, Trans Tech Publ, 69 (2010) 143-151. 307

[32] P. K. Sarker, Bond strength of reinforcing steel embedded in fly ash-based geopolymer 308

concrete, Materials and Structures, 44 (5) (2011), 1021-1030. 309

Page 17: Bond behaviour of steel plate reinforced concrete beams

15

[33] H. Lin, Y. Zhao, Experimental study on measuring the steel stress via FBG sensors, 310

Applied Mechanics and Materials, 548-549 (2014) 663-667. 311

[34] C. D. Moen, S. R. Sharp, Bond properties between concrete and corrosion- resistant 312

reinforcing steels, ACI Structural Journal, 113 (2) (2016), 383-392. 313

[35] M. N. S. Hadi, M. M. Sarhan, L. H. Teh, Behavior of concrete beams reinforced with 314

steel plates, Accepted for publication in the American Concrete Institute (ACI) 315

Structural Engineering Journal, (2018). 316

[36] AS 1012.9-1999, Determination of the compressive strength of concrete specimens, 317

Australian Standard, Sydney, NSW, Australia, 1999. 318

[37] AS 1012.10-2000, Determination of indirect tensile strength of concrete cylinders 319

(‘Brazil’ or splitting test), Australian Standard, Sydney, NSW, Australia, 2000. 320

[38] AS1391-2007, Metallic materials—tensile testing at ambient temperature, Australian 321

Standard, Sydney, NSW, Australia, 2007. 322

[39] AS/NZS-4671:2001, Steel reinforcing materials, Australian/New Zealand Standard, 323

Sydney, NSW, Australia, 2001. 324

[40] ACI 408.3-01/408.3R-01, Splice and development length of high relative rib area 325

reinforcing bars in tension (408.3-01) and Commentary (408.3R-01), American 326

Concrete Institute Committee 408, Farmington Hills, Mich., US, 2001. 327

Page 18: Bond behaviour of steel plate reinforced concrete beams

16

List of Tables

Table 1: Test matrix

Table 2: The pullout forces and bond strengths of specimens

Page 19: Bond behaviour of steel plate reinforced concrete beams

17

List of Figures

Figure 1: Bond test methods: (a) Anchorage beam [4]; (b) Splice beam [4]; and (c) Beam-

bending [22].

Figure 2: Beam-end specimens: (a) BE-N20; (b) BE-HP; (c) BE-HSP; (d) BE-HBP; (e) BE-

VP

Figure 3: Geometry of lozenges in chequer steel plates.

Figure 4: (a) Chequer steel plate with removed lozenges for Specimen BE-HSP; (b) Steel bolt

welded to chequer steel plate for Specimen BE-HBP

Figure 5: Test setup.

Figure 6: Failure modes of beam-end pullout specimens: (a) BE-N20; (b) BE-HP; (c) BE-

HSP; (d) BE-HBP; and (e) BE-VP

Figure 7: Load-slippage curves of beam-end pullout specimens

Figure 8: Toughness of beam-end pullout specimens

Figure 9: Definition of relative rib area of the steel bar reinforcement (Rr)

Page 20: Bond behaviour of steel plate reinforced concrete beams

18

Table 1: Test matrix

Test specimen Embedment

Yield load of

reinforcement

(kN)

Steel bolts

Diameter

(mm)

Length

(mm)

BE-N20 N20 170 ---

BE-HP

Horizontal chequer

steel plate

---

BE-HSPa

370 ---

BE-HBPb

20 100

BE-VP Vertical chequer steel

plate 370 ---

a The lozenges were removed.

bA steel bolt was welded to the chequer steel plate.

Page 21: Bond behaviour of steel plate reinforced concrete beams

19

Table 2: The pullout forces and bond strengths of specimens

Test specimen

Pull-out

force

(kN)

Measured

bond

strength

(MPa)

Calculated bond

strength by Zuo

and Darwin

(MPa)

Calculated bond

strength by ACI-

408R-03

(MPa)

BE-N20 176 12.4 11.4 11.2

BE-HP 99 2 5.2 5.2

BE-HSP 55 1.1 -- --

BE-HBP 127 2.6 -- --

BE-VP 199 4 5.2 5.2

Page 22: Bond behaviour of steel plate reinforced concrete beams

20

Figure 1: Bond test methods: (a) Anchorage beam [4]; (b) Splice beam [4]; and (c)

Beam-bending [22]

Splice length

Bar

Flexural splits

Hinge

Embedded length Plastic sleeve

Concrete

(c)

(a)

(b)

Page 23: Bond behaviour of steel plate reinforced concrete beams

21

PVC

600

300

100 225

00

100

(e)

R10@80

PVC

Figure 2: Beam-end specimens: (a) BE-N20; (b) BE-HP; (c) BE-HSP; (d) BE-HBP; (e) BE-VP

20

32

20

225

300

Steel bolt

(Diameter =20) 2R10

Chequer plate

100x10

20

32

20

225

300 Chequer plate

10x100

2R10

225

300 N20

2R10

20

32

20

20

32

20

225

300

Chequer plate

100x10 2R10

20

32

20

225

300

Plate 100x10

2R10

PVC

Embedded length

600

300

100 225

(a)

PVC

R10@80

Chequer face

Smooth face

600

300

100 225

(b)

R10@80 PVC

PVC

Face without Lozenge

Smooth face

600

300

100 225

(c)

PVC

PVC

R10@80

PVC

R10@80

600

300

100 225

(d)

112.5

PVC

100

Page 24: Bond behaviour of steel plate reinforced concrete beams

22

90o

Figure 3: Geometry of lozenges in chequer steel plates

Page 25: Bond behaviour of steel plate reinforced concrete beams

23

Figure 4: (a) Chequer steel plate with removed lozenges for Specimen BE-HSP; (b) Steel

bolt welded to chequer steel plate for Specimen BE-HBP

(a)

(b)

Lozenges

Smooth face

(No lozenges)

PVC

Steel bolt

Page 26: Bond behaviour of steel plate reinforced concrete beams

24

Figure 5: Test setup

Page 27: Bond behaviour of steel plate reinforced concrete beams

25

Figure 6: Failure modes of beam-end pullout specimens: (a) BE-N20; (b) BE-HP; (c) BE-HSP; (d) BE-HBP; and (e) BE-VP

(a) BE-N20 (b) BE-HP (d) BE-HBP (c) BE-HSP (e) BE-VP

Splitting cracks

Diagonal cracks on

the side face

Splitting cracks Splitting cracks

Diagonal cracks on

the side face

Diagonal cracks on

the side face

Page 28: Bond behaviour of steel plate reinforced concrete beams

26

0

50

100

150

200

0 10 20 30 40 50

BE-N20

BE-HP

BE-HSP

BE-HBP

BE-VP

Load

(kN

)

Slippage (mm)

Figure 7: Load-slippage curves of beam-end pullout specimens

Page 29: Bond behaviour of steel plate reinforced concrete beams

27

2626

1817

1324

2257

4001

0

1000

2000

3000

4000

5000

BE-N20

BE-HP

BE-HSP

BE-HBP

BE-VP

Toughnes

s (k

N.m

m)

Figure 8: Toughness of beam-end pullout specimens

Page 30: Bond behaviour of steel plate reinforced concrete beams

28

Figure 9: Definition of relative rib area of the steel bar reinforcement (Rr)

Shearing area, π db sr

Rib

angle

Sr hr

Bearing area, Ar

(Ar ≈ hr π db )

Gap

Rr = (bearing area/Shearing area) ≈ hr/Sr)


Recommended