+ All Categories

boqrd25

Date post: 03-Apr-2018
Category:
Upload: drganesh-kame
View: 220 times
Download: 0 times
Share this document with a friend

of 15

Transcript
  • 7/28/2019 boqrd25

    1/15

    United Nation Development ProgrammeProgramme of Assistance to the Palestinian People

    Rehabilitation of Road No.25

    PAL 10-00071488

    Bill of Quantity (BOQ)

  • 7/28/2019 boqrd25

    2/15

    Contractors signature and stamp Page 2

    PREAMBLE TO BILL OF QUANTITY (BOQ)

    1. GENERAL

    The nature of this contract is re-measured unit price contract and the Bill of Quantity

    (BOQ) shall reflect this fact.

    BOQ shall be read and construed in conjunction with other Contract Documents.

    General directions and description of work and material given in the Technical

    Specification are not necessarily repeated in the Bill of Quantity. The Technical

    Specification forms an integral part of the Bill of Quantity.

    The Tenderer is obliged to check the number of the pages of the Bill of Quantity and

    should any be found missing or duplicated or the figures of writing indistinct, the Tenderer

    must notify the Employer/Engineer at once and have the matter rectified before the Tender

    is submitted. No liability whatsoever will be accepted in respect of any claim for errors inthe Tenderers offer resulting from failure to comply with the fore-going.

    The Tenderer is deemed to have visited the site/s and fully acquainted himself as to the

    location of each of the items and works to be carried out and to all conditions which may

    affect the performance of the works, including but not limited to:

    Access for the storing dump site and UNDP crushing site as well as access torequired services

    Restrictions applicable to working in GAZA Strip area. All safety regulations and employer site safety procedures. All Palestinian regulations.

    The Tenderer is also deemed to have surveyed the actual condition of the site and buildings

    and made his own assessment of the type and extent of the works prior to submitting his

    offer.

    2. QUANTITIESAlthough practical care was exercised in preparing the BOQ, all quantities given herein

    shall be deemed to be estimated quantities of the work to be done. They are not to be takenas actual and correct quantities of the work to be executed and they do not absolve the

    contractor of his obligations under the Contract. At any time, the actual quantities increase

    or decrease, hence, it is understood that the actual quantities increase or decrease is

    expected risk and no claim whatsoever will be taken into consideration for extra cost in

    that respect by employer. Any claim whatsoever submitted for cost or extra expenses

    incurred from such increase or decrease will not be accepted by Employer/Engineer except

    where else stipulated in the Contract.

    3. MATERIALSAll materials used are to be of the best new available, subject to the Employer/Engineer

    approval, durable nature, guaranteed, not liable to any base exchange and manufactured

  • 7/28/2019 boqrd25

    3/15

    Contractors signature and stamp Page 3

    according to applicable BS, ASTM or DIN Standards. Execution also is subject to

    approval of Employer/Engineer and shall be in conformance of the best available common

    practice in engineering codes at the time of execution.

    Items that contain materials or products of special make with names of manufacturers are

    to be taken as samples of what will be required. Subject to the Employer/Engineerapproval, the Contractor may, at his discretion, offer similar products of other make if the

    equivalent quality of the specified materials is obtained. In this case, the Contractor shall

    submit a description and/or drawings showing all technical conditions, characteristics,

    make, type and address of Manufacturer, etc., of the materials offered as alternatives.

    4. PRICES AND CURRENCYThe prices given, by the Contract, hereunder in the BOQ shall be in United States Dollars

    orILS. Furthermore inflation and escalation or changes whatsoever shall not be subject of

    claim later on.

    The Unit Prices entered against the various items in the following Bill of Quantities

    include all operation costs for execution, completion and maintenance of the various items

    of the works finished completely in every respect till the final acceptance as specified or

    described in the Tender Documents, with or without modifications, either by way of

    additions or deductions, or alterations as may be offered in writing during the progress of

    the works, and include, without being limited to, all what is deemed necessary particularly

    referred to in the Tender Documents.

    The Unit Price shall cover all costs of every kind whatsoever including, without being

    limited to, all charges for additional site installations, relocation, supervision, labor,

    transportation and supply of materials; the provision, maintenance, use and efficient repair

    of all plant, equipment and appliance of every kind, the construction and maintenance of

    all temporary works, the performance of all services and the fulfillment of all obligations

    and responsibilities herein defined.

    The Tenderer shall be deemed to have fully considered all the conditions, obligations, and

    requirements of the Tender Documents before entering the respective unit price against the

    various items of the Bill of Quantities.

    The Unit Prices given hereunder the BOQ shall also include erection, installation, fixing,

    and re-fixing of all elements. These prices shall also include taxes, visa for labor, gate

    passes, accommodations for the Contractors staff and labors, all required insurance and

    work permits, guarantees, bonds, traffic plan requirements, safety procedures, etc. and all

    requirements necessary to have the work maintained until its final handing over.

    The Unit Prices given hereunder in the Bill of Quantity for this work shall also include

    overheads, risks, profit etc. and all other financial matters to have all these civil works

    completed.

  • 7/28/2019 boqrd25

    4/15

    Contractors signature and stamp Page 4

    The works, materials or activities listed in the following shall always be considered as

    supportive works to be included in the Unit Prices bid for any item in the Bill of

    Quantities:

    Any measurement for execution and payment of the works, including the provision ofmeasuring instruments, gauges, setting out marks, marking paint and relevant tools,labor, etc., the maintenance and preservation of gauges and setting-out marks during

    the execution of the works.

    Provision of small tackle tools or any other equipment required for the execution of theworks.

    Supply of consumable materials for the Contractors equipment. Removal of all contamination (refuse, debris, building rubbish and the like) arising

    from or in connection with the Contractors work to locations approved by the

    engineers Protection of the executed works and of the items made available for execution of the

    works from damage, fire, inclement weather, vandalism and theft etc., until the time of

    final acceptance.

    Transportation of all materials and structural components from the storage places onsite to the points of use and return transportation, if required.

    Submitting and transporting any samples required. Carrying out tests on materials and works, etc., that is required by the Engineer. Fuel and lubricants for operation of Contractors equipment. All safety precautions and measures for safeguarding labor as well as securing

    surrounding areas.

    Lighting of the work site. Maintenance , repair or reconstruct damaged infrastructure resulted by contractors

    activities

    5. RIGHTS OF EMPLOYERThe following rights are reserved to the Employer:

    To omit individual items mentioned in the Schedule of Prices if not required in theopinion of the Employer and/or to replace them should it be more advantageous to

    execute them in another way.

    To order execution of alternative or provisional items as if they were main items. To order execution of additional works as well as alternatives of works, always in

    conformity with the conditions outlined in the Contract.

    Any order and/or delivery of material or equipment by the Contractor for performance of

    the works may only be based on instructions and/or approved execution drawings by the

    Employer/Engineer.

  • 7/28/2019 boqrd25

    5/15

    Contractors signature and stamp Page 5

    All equipment and materials for installation and finishing works to be incorporated in this

    contract shall prior to ordering and/or delivery by the Contractor, be approved by the

    Employer/Engineer both in respect of quality and type as well as of quantity.

    6. SITE ACCESS AND STORAGEThe Tenderer shall visit all sites and ascertain the location of required access onto these

    sites and the location of allowance for complying with the requirements and for the

    reinstatement to original condition of all roads and areas used or disturbed by the

    Contractor to the satisfaction of the Engineer.

    7. SITE INSTALLATIONAll costs of labor, works, provisions, materials and equipment for Site Installations

    required by the Contractor and stipulated in the Tender Documents shall be included in the

    various unit prices of the Bill of Quantities. No extra payment will be allowed by the

    Employer for any of these activities.

    8. DURATIONThe total duration of the contract is Four (4) calendar months including weekends,

    holidays and official holidays. Official weekends are Fridays and Saturdays.

    9. OTHER CONTRACTORS OBLIGATIONS The Contractor has to submit Detailed Shop Drawings to be approved by the Engineer

    before commencement of the work, and all required materials should be supplied as

    specified and subject to the Engineer approval.

    The Contractor has to fix the underground services that may be damaged during hiswork.

    The Contractor has to maintain the Existing Open Channels flow during construction. All works has to be done according to the Engineer's instructions, Drawings and

    specification.

    The Contractor has to repair any damages of any services at full satisfaction ofrelevant Service Authority

    The contractor has to test on his own expenses, the sub-grade CBR beforecommencement of work, In case the CBR value less than 15%, then soil replacement

    should be applied.

    The contractor has to check the upper 30 cm below the top of the sub-grade to verifythat they are uniform, and any rubbish material or saturated /wet soil shall be removed

    and replaced with suitable material approved by the Engineer ,

    NO EXTRA COST SHALL BE PAID FOR SUCH REPLACEMENT

    The contractor has to Execute any required side slope according to specifications,drawings , and Engineers instructions

    Price will include costs of removing and/or relocating of all obstacles such as debris,garbage, trees and existing services in addition to the required materials necessary forwork completion according to engineer's instructions and specifications.

  • 7/28/2019 boqrd25

    6/15

    Contractors signature and stamp Page 6

    The contractor has to coordinate with Municipalities regarding garbage containerslocation.

    The contractor should include in his price the costs of cut and removal of trees roots,backfilling, watering, and compaction in layers with clean sand as specified and

    according to the Engineer instructions, the price will also include relocation of Power,

    Telephone poles and networks to sidewalk.

    Price will include costs of adjusting the levels of existing manholes (in any diameter)to suit the new situation. Replacing covers, frames, rings if defected and all materials

    and work required to complete the task.

    The contractor has to remove the existing base coarse during preparation works andtransport it wherever directed by the engineer to the related Municipality.

    The price will include costs of cutting and removing of the existing asphalt pavementlayer and transporting the removed material to a site approved by the Engineer

    Prices for excavation item shall include the removal of any buried structure not to bepart of the proposed roads, including transport of excavated, surplus material and

    buried structure (not to be part of the proposed roads) to a location approved by the

    engineer or his representative outside the site, workmanship and anywhere else,

    needed, all according to drawings, specifications, conditions and directed instructions

    by the Engineer or his representative.

    Quantities of excavation shall be measured according to the dimensions mentioned inthe drawings(engineering measurements in m2)

    Back-filling item should be in layers (25cm max. each & compaction test 97%). Pricesshall includes material supply, watering, compacting, transporting, testing and

    anywhere else, needed, all according to drawings, specifications, conditions and direct

    instructions by the Engineer or his representative.

    Suitable clean sand should be used for back-filling in layers (25cm max. each &compaction test 97%), selected from the approval excavated soil or imported. Prices

    shall includes supply, watering, compacting, transporting, testing and anywhere else,

    needed, all according to drawings, specifications, conditions and directed instructions

    by the Engineer or his representative.

    The contractor shall check and ascertain that the Benchmark used by him and itselevation is accurate and correct in all respects. The contractor shall check the

    surveying work. If correction is needed, the contractor has to redo the surveying work

    on his own.

  • 7/28/2019 boqrd25

    7/15

    Contractors signature and stamp Page 7

    Rehabilitation of Road No.25

    Bill No 1: Roads Works

    ItemNo.

    Description Unit Qty.UnitPrice(US$)

    Total(US$)

    1

    - The Contractor has to submit Detailed ShopDrawings to be approved by the Engineer before

    commencement of the work, and all required

    materials should be supplied as specified and subject

    to the Engineer approval.

    _All executed works must be documented in as Built

    Drawings, with connected By Total station in

    sample presented of GIS municipality department,

    also observe all existing points coordination. ( This

    mission will be finished by Approval Surveying

    office).

    - The Contractor has to fix the underground servicesthat may be damaged during his work.

    - The Contractor should include in his price the costs

    of sampling and testing as required and according to

    technical specifications and work requirement.

    - Price will include costs of removing and/or

    relocating of all obstacles such as debris, garbage,

    trees and existing services in addition to the required

    materials necessary for work completion according

    to engineer's instructions and specifications.

    - The Contractor should include in his price the costs

    of cut and removal of trees roots, backfilling,

    watering, and compaction in layers with clean sand

    as specified and according to the Engineer

    instructions, the price will also include relocation of

    Power, Telephone poles and networks to sidewalk.

    - Price will include costs of adjusting the levels of

    existing manholes (in any diameter) to suit the new

    situation. Replacing covers, frames, rings if defected

    and all materials and work required to complete the

    task.

    - The price will include costs of cutting andremoving of the Existing Asphalt pavement layer

    and transporting the removed material to a site

    approved by the Engineer

  • 7/28/2019 boqrd25

    8/15

    Contractors signature and stamp Page 8

    ItemNo.

    Description Unit Qty.UnitPrice(US$)

    Total(US$)

    1.1

    Clean, excavate, cut and fill carriageway, Median &

    sidewalks with clean dune sand from natural ground

    level to the bottom of the sub-base layer design

    level for carriageway and 26cm under the top faceof the curb stone for sidewalks including watering,

    compaction not less than 97% & CBR not less than

    15% ,all according to drawing and technical

    specifications . The work include remove crushed

    layer from the median. The price include dismantle

    existing curbstone if exist and receive to

    municipality stores & remove all existing block

    fences or others which objected the execution of

    works in carriageway or sidewalks., The work

    include observe septic tank .all according to drawing

    and technical specifications . All tests as perspecifications & Engineer Instructions.

    m2 17500

    1.2

    Transport and lay approved crushed stone base

    coarse 30 cm thick in two layers with CBR > 80%

    for the carriage way to the levels shown in the

    drawings. Price includes transporting crushed

    material, watering and compaction to reach 98 % of

    maximum dry density. Grader must be used in

    spreading and leveling of final layer. The work

    includes all tests as per specifications & Engineer

    Instructions.

    Note: Crushed materials to be transported fromUNDP crushing site west of Khanyounis (GAN-OR

    ex-settlement

    m2 6500

    1.3

    Level of existing crushed layer. The work include

    remove existing kurkar from the face of existing

    crushed then mix & grad existing crushed layer by

    using grader. The work include substitute any

    shortage of crushed to reach the design required

    levels as the drawings. Price includes watering and

    compaction to reach 98 % of maximum dry density.

    The work includes all tests as per specifications and

    Engineers instructions.

    Note: Crushed materials to be transported from

    UNDP crushing site west of Khanyounis (GAN-OR

    ex-settlement.

    m2 20000

    1.4

    Supply and lay approved sub-base material (

    Kurkar) of 15 cm thickness for the sidewalks in one

    layer with CBR.> 30%, watering and compaction up

    to 98% maximum dry density according to modified

    proctor test. the work includes all tests as per

    specifications & Engineer Instructions

    m2 10000

  • 7/28/2019 boqrd25

    9/15

    Contractors signature and stamp Page 9

    ItemNo.

    Description Unit Qty.UnitPrice(US$)

    Total(US$)

    1.5

    Construct reinforced concrete(80 Kg/m3) retaining

    walls, beams or any structural element as instructed

    by the Engineer including all necessary excavations

    & filling dune sand to the required level, B300concrete & expansion joint at 12m interval with

    selotex board all in accordance with the

    specification & drawings.

    M3 40

    1.6

    Supply & lay pre-cast concrete curbstones B300 for

    sidewalks (15x30x80 cm) including all necessary

    excavations, filling with dune sand & compaction to

    98% of MDD and compacted Kurkar (30x15 cm),

    B300 plain concrete foundation (27x10cm) under

    the curb and (12x21cm) behind, spreading 2 cm

    mortar under the curb, filling joints between curbs

    with cement mortar and painting with one primecoat and two finishing coats of approved brand

    name painting material ,expansion joint every 12 mr

    with selotex board and filling 3cm with seka flex

    ,all according to drawing and technical

    specifications.

    L.m 5500

    1.7

    Supply, install and compact of interlock tiles 8 cm

    thick, for carriageway The price include casting

    concrete beam with B300 (size 20x40 cm) at the

    ends of interlock, Also supply and spread dune sand

    5 cm thick under interlock, all the required tests,

    The work include connect the work with existingasphalt. all works are according to specifications,

    Drawings and Engineer instructions.

    m2 21500

    1.8

    Supply, install 250 mm outside diameter UPVC

    Pipes with wall thickness 7.3 mmfor crossing of theroad, each cross contain from 2 pipes in parallel.

    LM 250

    1.9

    Supply and cast concrete B250 for poles base

    Dimension (110x110x100 cm) the work include

    excavation , shuttering , supplying and installing hot

    galvanized steel pole base for 12 m poles, the work

    include supplying and fixing a 3" sharshori conduitswith a rope inside it in the base ,nuts , wishers and

    all required accessories required to complete the job,

    all according to drawings, specifications and

    engineer instructions.

    Unit 35

    1.10

    Supply and install 3" sharshori conduit with a rope

    inside it, the work include Excavation, backfilling

    on layers 20 cm thick of dune sand with compacting

    to 98 % MDD. The price including for any depth

    excavation( at least 1.0 m from the face of sidewalk

    pavement), laying and re-back filling with suitable

    Materials also included electrical warning tape.

    L.M 1200

    Total Roads Works

  • 7/28/2019 boqrd25

    10/15

    Contractors signature and stamp Page 10

    Bill No 2: Water works

    ItemNo.

    Description Unit Qty.UnitPrice(US$)

    Total(US$)

    2

    _All works must be coordinated with the waterdepartment at the Municipality and all testes need to be

    included.

    _ All executed works must be documented in as Built

    Drawings, connected By Total station with sample

    presented of GIS municipality department, also observe

    all existing points coordination. ( This mission will be

    finished by Approval Surveying office).

    _The price includes the cost of excavation to depth

    indicated in drawings using retaining shuttering, shoring

    according to instructions of Engineer, bedding of 20 cmclean dune sand under around and above the pipe with

    compaction, backfilling the rest of the trench up to

    design level with kurkar in layers 20cm thick each with

    compaction 98% MDD and all required tests.

    _The work includes removal of the surplus materials

    outside the site to places as instructed by the Engineer.

    _Supply and installation of elbows with any angles,

    Tees, Flanges, joints, metallic warning tap, and other

    accessories and thrust blocks according to details.

    The covers of manholes are made of cast iron with

    diameter 60 cm engraved by the word " Water " in

    English and Arabic. the ring is from cast iron squareshaped with 70*70 cm dimensions. the concrete which

    used around the ring is B350 and should have a Basalts

    layer of 2 cm above the concrete and around the cover

    rings. According to drawings, specifications and

    Engineers instruction.

    _Depth of trench is 1.4 m in carriage way and 1.1m in

    shoulders.

    _The price includes cutting the existing asphalt (if any)

    in suitable width using machine and reinstate the road to

    its original condition using two layers of base coarse 15

    cm each, supply and spread prime coat layer (MCO)

    under the new asphalt layer, and spread RC2 betweenthe new and the existing asphalt and the asphalt layer

    shall be 6 cm thick. In case the existing pavement is

    interlock tiling items should include removal and re-

    tiling interlock pavement to the original state including

    all required material to complete the pavement layers

    such as base coarse, interlock and sand ..etc.

    _ The price should include the connection of the new

    pipes to the existing pipes with all needed fitting and

    support to complete the work successfully.

    -The price Include Using Water tape above pipes.

  • 7/28/2019 boqrd25

    11/15

    Contractors signature and stamp Page 11

    ItemNo. Description Unit Qty.

    UnitPrice(US$)

    Total(US$)

    2.1

    Supply, install 110 mm outside diameter

    UPVC Pipes with wall thickness 4.2 mm waterpipes PN 10 . The price should include

    excavation of the trench 1 m from the design

    level of the sidewalk, the pipe should be

    bedded and covered with at least 20 cm of

    clean dune sand around and at the top and

    bottom of the pipe , The remaining depth of the

    trench will be filling with kurkar in layers not

    exceeding 20cm each, with compaction not

    less than 98 % , up to the design leveling of the

    road or sidewalk .All works are performed

    according to the drawings, specifications andEngineers instruction.

    L.M 150

    2.2

    Supply and install 100 cm internal diameter

    precast circular reinforced concrete water

    manholes, complete with B300 cast in place

    reinforced concrete base, cast iron cover (25ton

    Capacity), Frame, ring's , the concrete which is

    to be used around the ring is B350 for at least

    30cm width and depth, Basalt layer of 2 cm

    thick above the concrete and around the cover

    to fix the ring should be supplied and installed,

    cast iron steps @ 30cm maximum, excavationin any type of soil to any depth , backfilling

    with clean dune sand and compaction 98%

    MDD up to the design leveling of the roads,

    drainage opening with aggregate bed, two

    external hot bitumen coating (75/25). Price

    shall include all required tests. The price

    includes supply and install 4" Gate valve 16

    bar working pressure including all needed

    fittings, nibbles ,reducers and support to

    complete the works successfully. Price shall

    include all required tests and all work as perdrawings, specification and Engineer

    instruction

    Unit 2

    Total of Water works

  • 7/28/2019 boqrd25

    12/15

    Contractors signature and stamp Page 12

    Bill No 3: Sewage workstemNo. Description Unit Qty.

    UnitPrice(US$)

    Total(US$)

    3

    _The contractor has to submit detailed shopdrawings of the coming items for the approval by

    the Engineer before starting the work.

    _All executed works must be documented in as

    Built Drawings, connected By Total station with

    sample presented of GIS municipality

    department, also observe all existing points

    coordination. ( This mission will be finished by

    Approval Surveying office).

    _The price include observe the existing layers by

    removing & storing then relocating as layers

    constructed before._The price includes the cost of excavation to

    depth indicated in drawings using retaining

    shuttering, shoring according to instructions of

    Engineer, bedding of 20 cm clean dune sand

    under around and above the pipe with

    compaction, backfilling the rest of the trench up

    to design level with kurkar in layers 20cm thick

    each with compaction 98% MDD and all required

    tests.

    _The work includes removal of the surplus

    materials outside the site to places as instructedby the Engineer.

    _The work includes connection of the sewer line

    to the existing manhole All the sewage works

    have to be coordinated with Sewage Department

    at the municipality.

    _The price includes cutting the existing asphalt

    (if any) in suitable width using machine and

    reinstate the road to its original condition using

    two layers of base coarse 15 cm each, supply and

    spread prime coat layer (MCO) under the new

    asphalt layer, and spread RC2 between the newand the existing asphalt and the asphalt layer shall

    be 6 cm thick. In case the existing pavement is

    interlock tiling items should include removal and

    re-tiling interlock pavement to the original state

    including all required material to complete the

    pavement layers such as base coarse, interlock

    and sand ..etc. The measure of the diameter of the

    UPVC pipes is from the outside, where the

    diameter of manholes is from inside.

    _ The holes of the manholes have to be done

    using core machine and the manholes have to be

    coated by two external bitumen coating.

    _ The covers of manholes are made of cast iron

  • 7/28/2019 boqrd25

    13/15

    Contractors signature and stamp Page 13

    with diameter 60 cm engraved by the word "

    Sewage " in English and Arabic. the ring is from

    cast iron square shaped with 70*70 cm

    dimensions. the concrete which is to be used

    around the ring is B350 for at least 30cm width

    and depth, Basalt layer of 2 cm thick above the

    concrete and around the cover to fix the ringshould be supplied and installed, all according to

    drawings, specifications and Engineers

    ...instruction.

    3.1

    Supply, install 250 mm outside diameter UPVC

    Pipes with wall thickness 7.3 mm and join,

    UPVC pipes SN8 for the sewer networks with

    watertight and flexible joints sealed with

    approved gasket rubber ring including

    dewatering, excavation in any ground, shoring,

    shuttering, safety measures, testing, providing

    specified bedded and covered by 20 cm of cleandune sand at the bottom , above and around the

    pipes . Kurkar will be used for the rest of trench

    with layers not exceeding 20cm each , of 98 %

    MDD, leveling the road after backfilling .All

    according par drawings, specifications and

    Engineers instruction.

    L.M 1250

    3.2

    Ditto. But with 200 mm outside diameter UPVC

    Pipes with wall thickness 5.9 mm. The work

    include connect with branch manholes or any

    house connections.

    L.M 750

    3.3

    Ditto. But with 160 mm outside diameter UPVC

    Pipes with wall thickness 4.7 mm. The work

    include connect with branch manholes or any

    house connections.

    L.M 1000

    3.4

    Supply, install precast circular reinforced

    concrete Sewage manholes with internal dia.

    1.5 m(B350 kg/cm2) with cast iron steps @30cm

    spacing, cast iron manhole cover,(25 ton

    capacity), building in collector inlet, outlet pipes

    & future pipes ,connecting with end caps where

    shown or necessary. The price including twoexternal bitumen coating, shuttering, excavation

    in any ground, shoring, safety measures,

    formwork, excavation in any type of soil ,

    backfilling with kurkar in layers 20cm thick each

    and compaction 98% MDD , removing the

    surplus soil to the tip ..etc. the price include also

    supply and install 10cm concrete B200 under the

    bottom of the manhole and B200 plain concrete

    for benching the price includes also removing

    existing sewer network and manholes . All are as

    per drawings , specifications and the engineerinstructions.

    Unit 5

    3.5 Ditto. With internal dia. 1.2 m Unit 20

  • 7/28/2019 boqrd25

    14/15

    Contractors signature and stamp Page 14

    3.6 Ditto. With internal dia. 1.0 m Unit 20

    3.7 Ditto. With internal dia. 0.8 m Unit 8

    3.8

    Adjust level of existing Line or Manholes (Sewer,

    Water, Telephone, Storm water, etc.) to the

    required level. The work includes decreasing the

    height of manholes by demolishing the extra parts

    or increasing the height by supplying & installingprecast concrete ring B300, in cast the height

    more than 30 cm, otherwise casting of concrete

    may be used, also include( if need) cast iron

    cover 25 ton with the word sewer in English &

    Arabic) and all required materials. The work also

    includes cleaning of existing manholes & lines.

    Unit 20

    3.9 Ditto, but for Air Valve sewage manhole of

    pressure line which connect with treatment plant. Unit 1

    Total of sewage works(US$)

  • 7/28/2019 boqrd25

    15/15

    Contractors signature and stamp Page 15

    Rehabilitation of Road No.25PAL 10-00071488

    Summary

    Description Total (US$)

    Total Roads Works(US$)

    Total of Water works(US$)

    Total of sewage works(US$)

    Grand Total (US$) Not including Value Added Tax(VAT)

    Grand Total (in letters):-------------------------------------------------------------

    Contractors Name:------------------------------------------------------------------

    Signature and Stamp:----------------------------------------------------------------

    Date:-------------------------------------------------------------------------------------