Ryan Jones and Glenn White
Dominion Engineering, Inc.
Industry-NRC 2012 Meeting BAC Testing Program
February 29, 2012
Boric Acid Corrosion: Implications Assessment of BAC Test Programs
2 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Contents
• Objective of Implications Assessment
• Summary of Modeling for Full-Scale Mockup Test Program (Task 4)
(Basis for Implication Assessment)
• Implications of Full-Scale Mockup Test Program on the Current Safety
Assessments and Inspection Requirements
3 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Objectives of Implications Assessment
• The objective is to address the implications of the BAC test program
(culminating in full-scale mockup testing) on the assumptions and
technical bases that were used to develop the MRP safety
assessments (i.e., MRP-110, MRP-117, MRP-167, and MRP-206)
supporting the current inspection requirements for the RPV top and
bottom heads (ASME Code Cases N-729-1 and N-722-1, respectively).
• Technical Concern Addressed by Safety Assessments – If a leaking
nozzle is not detected during an inspection, can wastage conditions
develop that result in structurally significant loss of material before the
next inspection opportunity and successful leak detection.
• The full-scale mockup results provide the best experimental simulations
of conditions expected to exist in an actual leaking nozzle.
– Confirm that the wastage rates observed in the full-scale mockup tests
support the assumptions used in the safety assessments
– Confirm the effectiveness of visual inspection to detect the existence of a
leak
4 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Summary of Modeling for Full-Scale
Mockup Test Program
5 © 2012 Electric Power Research Institute, Inc. All rights reserved.
• Application to Support Design of Full-Scale Mockups – For an assumed leak rate,
use PICEP (or alternative) to evaluate initial effluent conditions.
– Use Lockhart-Martinelli (LM) approach to quantify two-phase flow pressure profile (Tsat) along annulus.
– Iterate with thermal FEA models to determine effective dry-out area.
– Calculate concentration of boric acid.
– Calculate chemistry and resulting pHT.
– Estimate wastage.
Primary
Conditions
PICEP
x0
Lockhart-
Martinelli
Analysis
Tsat
P
Heat Transfer
Analysis
A
ANSYS
Twall
Dryout
x(z)
Chemistry
Calculation
Li(z)
B(z)
pHT(Li,B,T)
CR(pHT)
pHT(z)
CR(z)
Part 1
Part 2
Hydra
ulic
T
herm
al
BMN Model
Mockup Model
Chem
ical
Corr
osio
n
Implications Assessment of BAC Testing Modeling – Thermal-Hydraulic Analyses
6 © 2012 Electric Power Research Institute, Inc. All rights reserved.
• RVH Model Description: – Simulated a nozzle leak between
outer diameter of CRDM nozzle (above weld) and head bore using 1/8th symmetry model based on typical reactor vessel head geometry.
– Representative materials of construction and thermal boundary conditions.
RVH Thermal Model Mockup Thermal Model
Implications Assessment of BAC Testing Modeling – Thermal Analyses
7 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Modeling – Dry-Out Calculation
• Coupled heat transfer and two-phase hydraulic models are used to determine area vs. temperature curves.
• ANSYS independently generates data points for dry-out area vs. temperature.
• Intersection of thermal-hydraulic modeling and FEA analyses defines the dry-out area and temperature (two equations and two unknowns).
0.01
0.1
1
10
100
200 250 300 350 400 450 500 550 600
He
at T
ran
sfe
r A
rea
[in
2]
Average Wall Temperature on Dryout Region [°F]
10 mil gap (CR Model)
1 mil gap (CR Model)
10 mil gap (RVH ANSYS Model)
1 mil gap (RVH ANSYS Model)
10 mil gap (Mockup ANSYS Model)
1 mil gap (Mockup ANSYS Model)
Heat Transfer Area for Dryout0.01 gpm
4" diameter 5.5" length annulus ~ 69 in 2
8 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Modeling – Wastage Rate Estimates
• Calculate Concentration Factors in Annulus
– Slug of fluid entering the annulus through the orifice travels to the
top of the annulus without mixing with the fluid preceding or
following it.
– All chemical species are conserved in a particular slug.
– Differences in chemistry along the annulus result from differential
partitioning and concentration of species as the quality changes.
• Calculate pHT as a function of [Li], [B], and Temperature
– Compute the pHT of lithium/boric acid solutions per the method
described in the EPRI Primary Water Chemistry Guidelines.
– Model predictions expected to be more aggressive than conditions
which will actually develop during testing (e.g., does not include
precipitates and effect of corrosion products).
– Assumes only significant species in the annulus are Li, B, and
Water.
9 © 2012 Electric Power Research Institute, Inc. All rights reserved.
0.001
0.01
0.1
1
10
0 0.5 1 1.5 2 2.5 3
Co
rro
sio
n R
ate
[in
/ye
ar]
Distance from Injection Site [in]
1 mil Annulus
10 mil Annulus
Dryout
0.05 in3/year
0.07 in3/year
0.01 gpm
Implications Assessment of BAC Testing Modeling – Wastage Rate Estimates
10 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Modeling – CFD Simulations
• CFD Model used to simulate flow within mockup annulus (two-phase flow with heat
transfer from LAS).
• Confirmed correlation between cooled region and dominant attack which corresponds to
concentrating boric acid at edge of two-phase regions.
• Pre-machined flow channel
• Pre-machined cavity
• Attack is predominantly within the narrow annulus region just outside the pre-machined regions.
11 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Full-Scale BMN Mockups – Wastage Correlation with Cooling
• Interpolation of TC data confirms correlation between regions of annulus cooled by liquid and regions of attack within the annulus.
12 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications of Full-Scale Mockup Test
Program on the Current Safety
Assessments and Inspection
Requirements
13 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Wastage Rate Modeling in Safety Assessment – MRP 110
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.001 0.01 0.1 1. 10. 100.
Size of Wastage Cavity at Time of Detection (in3)
Cu
mu
lati
ve
Dis
trib
uti
on
Fu
nct
ion
, F
1.5 EFPY Fuel Cycles
2.0 EFPY Fuel Cycles
Bare metal visual (BMV) examinations
performed every refueling outage for a
plant with a head temperature of 605°F
The probability of the wastage cavity size exceeding
the allowable wastage volume of ~150 in3 is less than
1 10-4
for both 1.5 and 2.0 EFPY cycles.
Results of Probabilistic Wastage
Calculation used in MRP-110
• The MRP-110 model showed
high confidence that Code
allowable stresses (i.e.,
stress associated with a
wastage volume of ~150in3
as documented in Appendix
D of MRP-110) would not be
exceeded given a leaking
nozzle and periodic bare
metal visual examinations
performed at an appropriate
interval.
14 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Wastage Rate Modeling in Safety Assessment – MRP 110
0.00
0.50
1.00
1.50
2.00
2.50
3.00
1E-05 1E-04 1E-03 1E-02 1E-01 1E+00
Corr
oso
in R
ate
(in
/yr)
Leak Rate (gpm)
Exponential behavior assumed for
leak rates between LRlow and LRcrit:
CR = 0.069e35.8 LR
(LRcrit,CRcrit)
(LRlow,CRlow)
Upper shelf behavior assumed for leak
rates greater than LRcrit: CR = 2.5 in/yr
Linear behavior assumed for
leak rates less than LRlow:
CR = (LR/LRlow)CRlow
LRlow and LRcrit chosen
based on calculation of
extent of local cooling
as a function of leak rateLRlow = 0.001 gpm
LRcrit = 0.1 gpm
Linear Corrosion Rate used in MRP-110
• Linear corrosion rates (in/yr)
presented in MRP-110 were
intended to provide a
conservatively high estimate for
application to a large cooled
region of the RVH for an
extended period of time.
– LRlow and LRcrit were leak
rates required to produce
<10°F temperature drop and
produce Tavg = 212°F,
respectively, on the model
heat sink area.
– CRlow = 0.072in/yr and
CRcrit = 2.5in/yr were limiting
values for linear corrosion
rates documented in the
Boric Acid Corrosion
Guidebook, Rev. 1.
15 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Wastage Rate Modeling in Safety Assessment – MRP-167
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1E-05 1E-04 1E-03 1E-02 1E-01 1E+00
Corr
oso
in R
ate
(in
/yr)
Leak Rate (gpm)
Exponential behavior assumed for
leak rates between LRlow and LRcrit:
CR = 0.069e71.7 LR
(LRcrit,CRcrit)
(LRlow,CRlow)
Upper shelf behavior assumed for leak
rates greater than LRcrit: CR = 1.25 in/yr
Linear behavior assumed for
leak rates less than LRlow:
CR = (LR/LRlow)CRlow
LRlow and LRcrit chosen
based on calculation of
extent of local cooling
as a function of leak rateLRlow = 0.0005 gpm
LRcrit = 0.05 gpm
Linear Corrosion Rate used in MRP-167
• Linear corrosion rates (in/yr)
presented in MRP-167 were intended
to provide a conservatively high
estimate for the area of uncovered
cladding.
– Leak Rate Factor: LRlow and LRcrit were
reduced by a factor of two since target
surface temperatures were achieved in
the BMN with half the flow rate
required in the CRDM configuration.
– Linear Corrosion Rate Factor:
Accounts for the inverted BMN
geometry and also the spatially
averaged corrosion rate being less
than the local maximum corrosion rate,
considering that the potential for
pooling of concentrated boric acid
solution does not exist to the same
extent as for the top head.
– Linear corrosion rate curve was
multiplied by a reducing factor sampled
as triangular distribution with
Lower=0.3, Mode=0.5, and Upper=1.0.
(plot is shown with mode factor
applied).
16 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Comparison of Safety Assessment and Full-Scale Testing
• The following describes how wastage volumes were determined
from the safety assessment models and compared to the mockup
tests.
• Volume of Material used in Safety Assessment Models
– At the time of detection of a simulated leak during a regular
inspection, the modeled wastage volume is then compared to
structurally unacceptable volume (i.e., ~150 in3 for the top head
or equivalent volume required to uncover (3in)2 of cladding for
the bottom head).
– The values for CRSA and ASA are known as function of the time-
dependent leak rate which increases with time.
• Volumetric Wastage Rates Measured in Full-Scale Mockup Tests
– Total volume of material is measured at the end of the test and
divided by the test duration.
– In contrast to safety assessments, the values for CRFSM and
AFSM are unknown, but these values are expected to vary with
time despite the leak rate being a controlled constant for the
full-scale mockup tests.
0
inspectT
SA SA SAVol CR A dt
0
where test
FSMFSM
Test
T
FSM FSM FSM
VolWR
T
Vol CR A dt
17 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Comparison of Safety Assessment and Full-Scale Testing
• Comparison of safety assessments and full-scale mockup wastage rates
– Wastage rates provide most applicable comparison, but still not one-
to-one since the corrosion rates and area terms are not the same
between the mockup and model. Moreover, the full-scale mockup
quantities represent conservative early stages of the wastage
process whereas the safety assessments are intended to be applied
for all stages of the wastage process.
• Comparison of volumetric corrosion rates is most meaningful because:
– Maximum linear corrosion rates are rather localized and not
representative of structurally significant material loss
– Average linear corrosion rates are sensitive to estimates of the
affected areas, which are in practice uncertain
where ( ) and
both & ( )
SA SA SA
SA
SA
WR CR A
CR fn LR
LR A fn t
18 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Comparison of Wastage Rates – MRP-110
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.0001 0.001 0.01 0.1 1. 10. 100. 1000.
Cu
mu
lati
ve
Dis
trib
uti
on
Fu
nct
ion
, F
Volumetric Wastage Rate Applied in MRP-110 App. E Model (in3/yr)
MRP-110 App E at LR = 0.001 gpm
MRP-110 App E at LR = 0.01 gpm
MRP-110 App E at LR = 0.1 gpm
Mockup Data at LR = 0.001 gpm
Mockup Data at LR = 0.01 gpm
Mockup Data at LR = 0.1 gpm
Full-Scale Mockup Wastage Rate Compared to
Probabilistic Model used in MRP-110
• Used MRP-110 model to determine the
instantaneous wastage rate at the instant
the leak rate matched the nominal leak
rate of the full-scale CRDM tests.
• Cumulative distribution of instantaneous
volumetric wastage rates (WRSA)
compared to the time-averaged values
(WRFSM) from the full-scale mockup tests.
– The wastage rates observed during
the full-scale tests support the
wastage rates used in the safety
assessment.
– The wastage rates observed during
the full-scale tests are representative
of early stages with a restrictive
annulus. These wastage rates are
expected to be bounding and
decrease with time as: (1) the annulus
opens, (2) velocities are lower, and (3)
there is reduced back pressure to
promote moisture retention.
19 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Comparison of Wastage Rates – MRP-110
0.0001
0.001
0.01
0.1
1
10
100
1000
Vo
lum
etr
ic W
asta
ge
Ra
te [
in3/y
r]
0.0012 3 4 5 6 7 8
0.012 3 4 5 6 7 8
0.12 3 4 5 6 7 8
1
Volumetric Leak Rate [gpm]
CRDM Nozzle Mockups MRP-110 MC Code MRP-110 (Best Fit) MRP-110 (1%) MRP-110 (99%)
Comparison of CRDM Full-Scale Nozzle Mockups and MRP-110 (Top Head)
Volumetric Wastage Rate per MRP-110
Probabilistic Model Compared to Full-Scale
Mockup Results (Top Head)
• The MRP-110 model was
used to generate
instantaneous volumetric
wastage rates covering the
range of flow rates tested
with the full-scale mockups.
• The instantaneous wastage
rate vs. leak rate data was
then evaluated to determine
the mean and bounding
percentile (1st and 99th)
curves (non-parametric fit).
• The full-scale mockup results
are bounded by the statistical
variations of the model used
in the MRP-110 safety
analysis for top heads.
20 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Comparison of Wastage Rates – MRP-167
0.0001
0.001
0.01
0.1
1
10
100
1000
Vo
lum
etr
ic W
asta
ge
Ra
te [
in3/y
r]
0.0012 3 4 5 6 7 8
0.012 3 4 5 6 7 8
0.12 3 4 5 6 7 8
1
Volumetric Leak Rate [gpm]
Comparision of BMN Full-Scale Mockupsand MRP-167 (Bottom Head)
BMN Mockups MRP-167 MC Code MRP-167 (Best Fit) MRP-167 (1%) MRP-167 (99%)
Volumetric Wastage Rate implied by MRP-167
Probabilistic Model Compared to Full-Scale
Mockup Results (Bottom Head)
• The MRP-167 model was used to
generate instantaneous volumetric
wastage rates covering the full
range of flow rates tested with the
full-scale mockups.
– MRP-167 used corrosion length (ℓ) to
determine the area of unsupported
head cladding. BMN Mockup data
used to estimate a proportionality
function C(ℓ) in order to estimate
volume; V=[C(ℓ)][ℓ3].
• The wastage rate vs. leak rate data
was then evaluated to determine the
mean and bounding percentile (1st
and 99th) curves (non-parametric fit).
• The full-scale mockup results are
bounded by the statistical variations
of the model used in the MRP-167
safety analysis for bottom heads.
21 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Effectiveness of Visual Examinations – Modeled in Safety Assessments
0.1
1.
10.
100.
1,000.
10,000.
100,000.
1,000,000.
1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E+00
Leak Rate (gpm)
Vo
lum
e o
f B
ori
c A
cid
Dep
osi
ts
Rel
ease
d D
uri
ng
Fu
el C
ycl
e (i
n3)
18-month Fuel Cycle
24-month Fuel Cycle
Cycle average boron concentration of 750 ppm and
zero deposit porosity assumed. The density of boric
acid crystals is 1.44 g/cm3 (0.052 lb/in
3).
Assumed sensitivity of bare metal
visual (BMV) leak inspections:
10 in3 (½ lb) of boric acid deposits
5 in3 (¼ lb) lower bound
20 in3 (1 lb) upper bound
Volume of Boric Acid Deposits
for a Fuel Cycle versus Leak Rate
• The effectiveness of the visual
examination modeled in the safety
assessments is represented by a
probability of detection (POD) curve
that estimated the probability of
detecting a given volume of boric acid
deposits.
• The POD curve used in MRP-110
was represented by a triangular
distribution with lower, mode, and
upper values set to 5in3, 10in3, 20in3,
respectively.
• Models used in safety assessments
account for the possibility that a
substantial fraction of the boric acid
might be advected away from the
location of the leak with the liquid
phase of the effluent that has not
been vaporized.
22 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Effectiveness of Visual Examinations – Observations in Full-Scale Tests
• All full scale mockup tests (i.e., CRDM nozzle, Inverted CRDM nozzle, and BMN) had visual evidence
local to the exit of the annulus for all conditions tested including: (a) leak rates ranging from 0.001 gpm
to 0.1 gpm, (b) conforming and offset insulation configurations, and (c) varied ventilation conditions.
• Volume of Evidence – There was a positive correlation between the amount (both local to the annulus
exit and remote from the mockup) of evidence and the leak rate of the test.
• Type of Evidence – The Type of Evidence local to the annulus exit was dependent on ventilation and
insulation configuration, but the Volume of Evidence was relatively independent of testing parameters
other than leak rate. As leak rate increased, the Volume of Evidence local to the annulus exit shifted
from white boric acid deposits at low leak rates to tenacious corrosion products at intermediate to high
leak rates.
• Wastage Progression – The full-scale mockups were representative of early stages of the wastage
process and variations in test results suggested the possibility of wastage being initially concentrated
deep in the annulus. Regardless of the wastage progression, there was always evidence of a leak.
There was no evidence that a structurally significant subsurface cavity could develop in the absence of
evidence readily detectable by visual inspection.
• Based on the results of the full-scale mockup tests, the assumptions regarding effectiveness of visual
examinations used in the technical analyses of the MRP safety assessments are consistent with
detection for an actual leaking penetration.
23 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications Assessment of BAC Testing Conclusions Regarding Current Inspection Requirements
• Current inspection requirements for reactor vessel top and bottom head
nozzles are defined in ASME Code Cases N-729-1 (top head) and
N-722-1 (bottom head), which are made mandatory by NRC regulation
subject to specific conditions (10 CFR 50.55a(g)(6)(ii)(D) and (E))
• The technical assessments of these inspection requirements (MRP-
110, MRP-117, MRP-167, MRP-206) apply two key elements: (1)
wastage rate dependence on leak rate, and (2) ability to detect a leak
by visual examination.
– Based on the full-scale mockup tests, both the volumetric wastage rate and
effectiveness of visual examination to detect a leak have been shown to support the
modeling elements used in the technical analyses of the safety assessments.
• The current inspection requirements are conservative and adequate
such that a leaking nozzle would be detected and not result in
structurally significant wastage.
24 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity