Date post: | 14-Dec-2015 |
Category: |
Documents |
Upload: | declan-gath |
View: | 215 times |
Download: | 0 times |
BoRit Superfund Site TimelineBoRit Superfund Site Timeline
•A Preliminary Assessment (PA) is
designed to determine whether a sites poses little or no threat to human
health and the environment or if it does pose a threat, whether the threat
requires further investigation.
•A Site Inspection (SI) identifies sites that enter the NPL listing
process and provides the data needed for Hazard Ranking System
(HRS) Scoring and documentation.
•A list of the most serious sites identified for possible long-term cleanup.
•A “removal action” is an action intended to stabilize or clean up an incident or site
which poses an immediate threat to human health or the
environment.
•If the release of hazardous
substances requires immediate or short-
term response actions, these are
addressed under the Emergency Response
program of Superfund.
•After a site is listed on the NPL, a
Remedial Investigation/Feasibility Study (RI/FS) is performed at the
site.
•The RI serves as the mechanism for collecting data to:characterize site
conditions;determine the
nature of the waste; and
assess risk to human health and the environment.
•Phase I: July 2008-June 2009 – Stabilization of stream banks so that asbestos-containing
material (ACM) does not enter the streams is
begun. In June 2009, EPA completed stream bank
stabilization at Wissahickon Creek.
•Phase II: July 2009-May 2010 - Stream bank
stabilization was completed at Rose Valley
Creek.
•Phase III: May 2010-June 2010 – Stabilization completed on the
reservoir berm parallel to the Wissahickon Creek.
•Phase IV: June 2010-July 2011 - Pile clearing and stabilization of Tannery
Run completed.
•Phase V: July 2011-September 2011 –
Stabilization completed at Wissahickon Creek from
the dam to its confluence with Tannery Run.
•In April 2006, an EPA Site
Assessment Team conducted
a baseline sampling event
at the BoRit Asbestos Site.
•Results from the sampling event
showed the presence of
asbestos in the air, soil, surface
water and sediments.
•Work began November 2009.
•Phase I of field work, which included surface water, sediment, soil, and waste sampling, completed January
2010.
•Phase II activities, which included community air
monitoring, installation of groundwater
monitoring wells, and additional onsite and
offsite (including residential) soil
sampling, began October 2010 and
completed November 2010.
• Activity based sampling occurred in summer/fall 2011.
•Proposed to the NPL September
2008.
•In April 2009, the site was listed on the NPL, making
the site eligible for federal cleanup
funding.
•EPA expects to complete the
RI/FS in approximately 3 years, depending on the needs of
the investigation.
Please Note: Time frames for site activities can vary depending on influences such as schedules, contracts and weather. Draft updated March 12, 2012
•The Feasibility Study (FS) is the mechanism for
the development, screening, and
detailed evaluation of alternative
remedial actions.
•The RI/FS is a multi-step process
including:Scoping
Site Characterization
Development and Screening of Alternatives
BoRit Superfund Site TimelineBoRit Superfund Site Timeline
•Preparation and
implementation of plans and
specifications for applying
site remedies.
•All new fund-financed
remedies are reviewed by the National
Priorities Panel.
•Ensures that Superfund
response actions provide for the
long-term protection of human health
and the environment.
•Included here are:
Long-Term Response Actions Operation and
MaintenanceInstitutional
Controls Five-Year
Reviews Remedy
Optimization
•Remedial Action (RA) follows the remedial
design phase and involves
the actual construction
or implementation phase of Superfund
site cleanup.
•The bulk of the cleanup
usually occurs
during this phase.
•Removes a site from the NPL once all
response actions are
complete and all cleanup goals have
been achieved.
Notes
•It is important to note that EPA
has NOT chosen a long-term
cleanup option for the site.
•EPA plans to work with the community to
keep them informed of our progress and of the options we’re considering for
the final cleanup.
•Once the RI/FS is completed, EPA will propose a final cleanup
option and will offer the
community a sixty day period to comment on the proposed
plan.
NotesNotes Notes
•EPA’s goal is to make sure that at every cleanup site, the Agency and its partners have an effective process
and the necessary tools and
information needed to fully explore future
uses, before the cleanup remedy is
implemented.
•This gives the Agency the best
chance of making it’s remedies
consistent with the likely future use of
the site. In turn, EPA gives
communities the best opportunity
to use sites following cleanup.
Please Note: Time frames for site activities can vary depending on influences such as schedules, contracts and weather. Draft updated March 12, 2012
•A ROD contains site history, site
description, site characteristics,
community participation, enforcement
activities, past and present activities,
contaminated media, the
contaminants present, scope
and role of response action and the remedy
selected for cleanup.
Notes