Date post: | 14-Apr-2018 |
Category: |
Documents |
Upload: | tiong-v-yen |
View: | 230 times |
Download: | 1 times |
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 1/22
Haymarket Court | Hinson Street
Birkenhead | Wirral | CH41 5BX
T 08444 120 888 | F 08444 120 333
W www.premierguarantee.co.uk
MD Insurance Services Ltd is the Scheme Administrator or the Premier
Guarantee range o structural warranties. MD Insurance Services Ltd is
authorised and regulated by the Financial Services Authority.
Bricklayers Handbook
Superstructures
1 : 1
0
1 0 mm
2 0
3 0
4 0
5 0
6 0
7 0
8 0
9 0
1 0 0
1 1 0
1 2 0
1 3
0
1 4 0
1 5 0
1 6 0
1 7 0
1 8 0
1 9 0
2 0 0
0
1 m
2
3
4
5
6
7
8
9
1 0
1 1
1 2
1 3
1 4
1 5
1 6
1 7
1 8
1 9
2 0
1 : 1 0 0
TS-PG582-1.00-010212
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 2/22
Introduction
The Bricklayers handbook gives guidance to site managers and
site sta on key issues aced during construction or traditional
masonry construction. For other types o construction, pleasereer to alternative guidance, British Standards or specialist
design inormation.
Geographical location can vary the design signicantly and
although this guide gives examples o the most commonly
occurring issues, Premier Guarantee recommend early contact
with our surveyors to help give guidance on how to avoid
particular circumstances on your site.
Please reer to the Premier Guarantee Technical Manual or the
Functional Requirements, Principal Perormance Standards /
Requirements or the design and construction o Housing units
using Premier Guarantee.
Please note there are ‘Statutory’ variations to the inormation
shown in this publication in respect to;
• EnglandandWales: TheBuildingRegulations2010and Approved Documents.
• Scotland: TheBuilding (Scotland) Regulations2004 (as
amended)andtherelevantTechnicalHandbooks.
• NorthernIreland:TheBuildingRegulations(NorthernIreland)
2000 (as amended) and the relevant Technical Booklets
please reer to your Premier Guarantee Site Audit Surveyor
or urther advice.
Your Premier Guarantee Site Audit Surveyor contact is
Contents
Superstructure
Construction o wallsMortar
Masonry durability
MasonryWalljunctions
Cavity walls
Cavity wall insulation
Movement in masonry
Preventing damp penetration at external openingsStructural Lintels & bearings
Parapets
Lateral restraint o walls by foors and roos
Wallplates
Chimney construction
Horizontal damp proo courses
1 2
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 3/22
Superstructure
Construction of walls
Set out walls using securely marked proles with•
reerence lines and datum levels.
Walllengthsmustbecheckedforsquareness. •
Cross check against diagonal measurements rom•
the Architect plans.
The position o openings must be anticipated to•
ensure correct and even bonding occurs both
horizontally and vertically.
Care should be taken to avoid overstressing mortar •
by a building rises o no more than 1.5 m in a day.
Both leaves o a cavity wall should be built at the•
same time to avoid incorrect coursing and potential
weakeningofanindividualleaf(ifleftunsupportedfor
anylengthoftime).
Wheremasonryistobeplasteredorrendered;raked•
outjointsapproximately15mmdeepshouldbe
provided as work proceeds, to give a good key.
Laying bricks and blocks
Good building practice must be ollowed
Lay bricks and blocks level, using a regular bond with•
anominal10mmhorizontalbedjointprovided(unless
otherwisespeciedbythedesigner).
Fillcrossjoints. •
Perpendjointsshouldnotbelessthan7mmwideand•
ully bed in mortar. The perpends should be kept
vertically aligned as the work proceeds.
Lay ‘rog’ bricks with ‘rog uppermost’ lled with mortar •
to ensure the wall is stronger and more resistant to
sound transmission.
Lay hollow blocks on shell bedding with the vertical•
jointslled.
Ensureaconsistentbond,especiallyatcorners. •
Walltiesmusthavenotlessthan50mmdepthof•
bedontothemortarjointafterallowingfortolerances.
Ensurethemortarjointsarecarefullystruckaswork•
proceeds to prevent the cavity and or insulation below
being lled with mortar droppings.
Case study
In the picture below the bonding is inconsistent resulting in
verticaljointstocoincideonconsecutivecourses.Thewall
ties are also not properly bedded into each lea o masonry
using the correct type and length.
3 4
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 4/22
Horizontal and vertical alignment o masonry walls
Dimension Permissible
Deviation
Straightness in any 5 m length + / - 10 mm
Verticality up to 2.5 m height + / - 10 mm
Verticality up to 7 m height + / - 20 mm
The above dimensions represent the level that can be reasonably
achieved or general brick and block work masonry.
Case study
The vertical alignment o the load bearing inner lea o block work
in this case was ound to exceed the above recommendations.
Chases in masonry leas
Do not;
cut chases into any block masonry which is less than•
75mminthickness.
cut horizontal or raking chases in solid walls to a•
depth greater than one-sixth o the thickness o the
lea.
cut vertical chases to a depth exceeding one-third the•
thickness o the single lea in solid walls.
cut chases in separating walls.•
Chasesoneithersideofawall(notaseparatingwall)mustbeoset by a distance at least equal to the wall thickness.
Case study
A horizontal chase to accommodate piping was ound more
than 30 mm depth, approximately a 600 mm above the foor
level. This exceeded the maximum allowed by nearly double.
Cracking in the block work was observed above and below thechase.
5 6
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 5/22
Buttressing walls and returns
Wallsshouldhaveappropriatestructuralreturnsandpiers
to give adequate stability that meets the current Building
Regulations.WallthatdonotmeetcurrentBuildingRegulations
guidance should be proven by structural calculations.
Mortar
General requirements
Masonry mortar should be selected according•
to exposure conditions o the masonry and the
specication o the masonry units
Calcium chloride, ethylene glycol, or admixtures•
containing these materials, should not be added to
mortars to provide protection against reezing, or or
any other purpose.
Do not use air, entraining or other admixtures•
unless specied by the designer and ollowing the
manuacturer’s recommendations.
Wheremortarstrengthisrequiredforstructural•
reasons careul consideration should be given to the
accommodation o movement.
Mortar must not be ‘knocked up’ when it has begun•
to set.
Mixing in cold weather
Do not mix mortar when the air temperature is at or below 2 °C
andfalling.Donotuseneaggregate(sand)orsemi-nishedmortar(lime-sandmixtures)containingiceparticles.
Hot weather working
Whereprolongedperiodsofhotweatherpersist,certainclay
bricks(whicharehighlyabsorbent),maybewettedtoassistin
reducingsuction.Wettingshouldnotbeundertakenonany
other type o brick, nor should saturating completed walls be
attempted.
Site batched mortar
Caution must be taken when mixing material on site. Gauging
volumes by the shovelul must not be relied on to give
suciently consistent mix proportions, particularly with saturated
materials(e.g.dampsand).Thiscanresultinvariations
between batches which may aect the strength & durability o
the mortar. It is recommended that site batched mortar mixing
should only be produced using a careully selected prescription
mix and a suitable mechanical mixer.
Additives
Plasticisers and other additives may be added to the mortar mix to improve workability. Only products that have been specically
designedasamortaradditiveshouldbeused.Washingup
liquid and similar products must not be used.
Pre-mixed mortar
The use o pre mixed or actory made mortar ensures
consistency throughout the build element. It may be produced
as complete or semi-nished mortar. The design teams
approved specication must be ollowed ensuring that the
mortarconformstoBSEN998–2.
Table o mortar mixes
The mixes in the table below are recommended or clay bricks
(unlessotherwiserecommendedbythebrickmanufactureror
theEngineer/designerfortheparticularsite)
Use Required
Exposure Recommended Proportion
by Volume
Mortar
designationto BS 5628
– 3 And
BS EN 1999
– 2 :2006
Cement
: Llme :
sand
Cement
: sand
with air
Masonry
cement :
Sand ***
Work below
or near
ground level
High
Durability1* : ½ : 4
to 4 ½
1* : 3 to 4 1* : 2 ½ to
3 ½
(ii ) **
Internal and
External
wall areas
above
DPC level
General use 1 : 1 : 5
to 6
1 : 5 to 6 1 : 4 to 5 (iii)
High
Durability –
Severe or
Very Severe
exposure
1 : ½ : 4 to
4 ½
1 : 3 to 4 1 : 2 ½ to
3 ½
(ii)**
Copings,
cappings
and sills
Low
permeability
jointing
1 : 0 to
¼ : 3
Use a type
S sand to
BS 1200
- - (i)**
Parapets
and
Chimneys
High
Durability1 : ½ : 4 to
4 ½
1 : 3 to 4 1 : 2 ½ to
3 ½
(ii)**
7 8
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 6/22
For Minimum Compressive strength of site mixed mortar at 28 days
– see Table 13 BS 5628 – 3
When referring to Tables 13 in BS 5628 - 3 see also BS EN 1996
– 2 :2006
Where Concrete or Calcium silicate bricks are used, the manufacturer’s
recommendations must be followed and a designation (ii) or (iii) mortar
may be required
* Where soil or ground water sulphate levels are present, use Sulphate
resisting Portland cement (to BS 4027)
** Where Potential High risk of saturation is likely, refer to Table 12 in BS
5628 - 3
*** For Masonry cement :sand with Lime ller - see Table 13 BS 5628 – 3
Masonry durability
Masonry can become saturated with water, the extent o which
depends on the level o exposure. High areas o risk include
Masonryaroundtheexternalgroundlevel(two•
courses above and below are the most vulnerable
areas).
Parapets; especially where it is not rendered and / or •
the parapet is not provided with an eective coping.
Unrendered chimneys.•
Cappings, copings and sills in areas where reezing•
conditions may occur.
Wallswithminimalroofoverhangs. •
Local climatic conditions or geographical locations•
where elevations are exposed to severe wind driven
rain.
Buildings within severe exposure areas are required to have
rost resistant brickwork.
TheBSEN771seriesspeciesthecharacteristicsand
perormance requirements or masonry units.
WhereConcreteblocksaretobeusedeitherbelowDPC
level or externally without a render nish, reerence to the
manuacturer’s specications including third party accreditation
is required to conrm adequacy.
Cold weather working
Do not:
Build masonry when the air temperature is at or •
below 3 °C and alling, or until it is no less than 1 °C
and rising.
Lay mortar on rozen suraces•
Use wet bricks or blocks when there is a danger o •
reezing
Do:
Ensurenewlybuiltworkisprotectedfromrain&frost•
with suitable waterproo sheeting
Recessed mortar joints
Recessedmortarjointsarenotrecommendedfor:
Externalwallsinclaybrickworkormasonrycavity•
walls in areas o severe or very severe categories o
exposure
Or
Cavity walls with ull ll cavity insulation.•
Masonry wall junctions
New dwellings next to existing dwellings
Whenextendingontoexistingpropertiesthereistheriskof:
dierential movement occurring.•
water penetration through to the internal nishes at•
thejunctionofthenewandexistingwalls,particularly
whereacavitywalljoinsasolidmasonrywallor
anothercavitywall(withoutcontinuationofthecavity).
Whereanewdwellingistobeconstructedabuttinganexisting
dwelling, the new home should be an independent structure
with a new wall constructed alongside the existing wall. The
wall should be supported on a new oundation, independent o
the existing building.
Internal masonry wall junctions (new dwellings)9 10
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 7/22
Whereamovementjointisnotrequired:
alternative courses should be toothed•
or
wheretheadjoiningblockwall(e.g.separatingwall)is•
adifferentdensity;abuttjointisrecommendedwith
suitableties(orsuitableequivalent)at225mmmax
vertical centres.
For sound insulation requirements ol low the design team’s
proposal careully.
Newbuildextensionsontoexistingbuildings(i.e.aspartofa
refurbishmentprojectwithnewextensions)
It is not sae to assume a proprietary connector will be
satisactory or all cases.
Older buildings tend to have shallow oundations which move
seasonally in clay soils without damage. Damage is likely to
occuratthejunctionofanoldermovingbuildingandanew
building with oundations meeting current standards.
Prior to starting work on extensions an assessment o the
ground conditions and the existing oundations are required to
determine:
the extent o oundation movement likely to occur and•
what remedial measures are required to strengthen
the existing building and oundations.
the type o connections required between the new•
andexistingstructures(e.g.atwalls,roofsbeams
etc.).
In all cases o extending onto existing buildings
theexistingwall(aswellasitsfoundations)mustbe•
proven to be structurally stable and able to take any
additional load imposed on it.
the orm o connection between the structures•
must be proven by a structural engineer to cater or
movement.
horizontal DPC’s rom the new build must link through•
totheexistingstructureDPC(ifnone,achemical
injectionDPCwillberequired)
the method o preventing water penetrating at the wall•
connections.(seerecommendeddetailsoverleaf)
in the situation that the existing wall becomes a•
separatingwall(e.g.apartments),thewallwillrequire
upgrading to achieve at least 1 hour re resistance
the separating wall must also meet sound insulation•
standards. Robust details do not exist or these
constructions.
Case study
Anewcavitywallextensionformedajunctionwithanexisting
solidwalledbuildingaspartofaconversionproject.
Aproprietaryjunctionplatejoinedthestructures•
without regard or the extent o movement likely to
occur.
The existing solid brick wall orms a direct path or •
dampness to bypass the cavity wall and reach the
internal nishes.
Thiswallwasrebuilt(duetopoorworkmanship)andan
independent lining provided to the existing gable and new inner
lea to ensure no damp penetration or cold bridging occurred.
New cavity wall to existing solid wall junction
11 12
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 8/22
(reurbishment projects)
New cavity wall to existing cavity wall junction
(reurbishment projects)
Cavity walls
Construct the cavity wall with the correct cavity width.•
Ensurethecorrecttypeandlengthofwalltieisused. •
Ensureexistingcavitywallshaveadequatewallties. •
Cleanoffanysurplusmortarfromjointsonthecavity•
aces as the work proceeds. Keep the cavity and wall
ties ree rom mortar and debris.
Draw battens should be used to keep the cavity clear •
o mortar and debris.
Cavities at the base o the wall should be kept clear.•
A minimum 50 mm clear cavity is required between•
partial ll insulation and the external lea.
Case study
Debris build up on cavity wall ties can result in damp
penetrating the inner ace o the wall.
Cavity wall ties
OnlywalltiesinaccordancewithBSEN845–1,•
must be used. Other types must be independently
third party accredited and submitted to the warranty
provider or approval beore use.
Stainless steel wall ties should always be used.•
The correct type o tie depends on; the structural•
requirements o the wall, the insulation to be used and
the resulting cavity width. The contractor must ollow
the Design team’s approved plans.
13 14
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 9/22
Thewalltiesmustbelaidtoensure:
Thecorrectspacingisachieved(seechartoverleaf). •
not less than 50 mm embedment o the wall tie onto•
each lea must be achieved.
the ‘drip’ is in the centre o any clear cavity.•
the two leaves o the wall must be coursed to ensure•
the wall tie slightly slopes down towards the outside
lea and the drip points downwards.i partial ll insulation is to be installed, the correct•
combination o wall tie and retaining disc must be
used and a 50mm clear retained cavity provided.
Wall tie specication
WalltiesshouldconformtoBSEN845–1
Unlled or fully lled cavities
50mm to 75mm wide Buttery
Double triangle
Vertical twist
Proprietary ties *
75mm to 100mm wide Double triangle *
Vertical twist
100mm to 150mm wide Vertical twist
Partial lled cavities
50mm to 75mm wide Double triangle with proprietary
retaining disc Double triangle
with integral retaining rod
Proprietary ties *
75mm to 150mm wide Vertical twist with proprietary
retaining disc
* Third party accreditation should be provided
Walltiesmustbebuiltinasworkprogresses.Walltiesmust
notbepushedintothemortarjoint.
Spacing o wall ties
TiesshouldbespacedtotherecommendationsinBSEN
1996-2:orfollowthestructuralengineersdesignifwallties
require more requency.
Be aware:
Walltiesmustnot be allowed to all backwards to the inner lea.
15 16
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 10/22
Insulation should wrap around corners and not be cut•
andjoined.
Do not leave gaps in the insulation. Butt the insulation
slabstogetheratbothhorizontalandverticaljoints
and at closures, and install them with staggered
verticaljoints.
Keepjointsbetweeninsulationslabscleanandfree•
rom mortar droppings. Do not place any small o-
cutswiththecutedgeagainstthewallsurface(i.e.
placedatrightangles).
Ensurehorizontaljointsofinsulationcorrespondwith•
horizontalrowsofties.Whereadditionalwalltiesare
required, cut insulation slabs neatly to accommodate
them.
Case study
Insulation batts were ound incorrectly pushed into the cavity
with cut edges acing the outer lea.
Blown or injected cavity ll
Blownorinjectedinsulationshouldbecarriedoutby
appropriately qualied personnel. The cavity must be inspected
priortotheinstallationtoensure:
mortarjointsareushwithinthecavityandtheinner•
aces o the masonry are clean.
the cavities are ree rom obstructions such as lumps•
o mortar and parts o bricks. Mortar droppings below
the horizontal DPC must be minimised.
all scaold holes are lled with mortar on removal.•
Be aware
Thecorrectlengthofwalltiemustbeusedappropriatefor:
the width o cavity.•
the type o insulation used.•
to ensure a minimum 50mm bed onto each•
lea is achieved.
•
•
Do not attempt to tie wall ties together to achieve the
correct length.
Cavity wall insulation
Full ll cavity insulation
May not be appropriate in area with high or severe•
weather exposure.
Should not be used with random sandstone walling or •
other irregular acing.
Recessedmortarjointstotheouterleafarenot•
recommended with ull ll insulation.
Only third party accredited insulation products should•
be used.
Insulation batts should be built into the cavity as work •
proceeds and not pushed in ater.
The insulation slabs are o a thickness appropriate to•
the cavity width so as to correctly ll the cavity.
17 18
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 11/22
recessedmortarjointstotheouterleafarenot•
recommended with ull ll cavity insulation.
Partial ll insulation
Third party accredited Insulation slabs must be used.•
A minimum 50mm clear cavity between partial ll•
insulation and the external lea is required.
The correct combination o wall tie and retaining disc•
must be used and installed in accordance with third
party accreditation recommendations.
Keep the tops o the insulation batts clean and ree•
rom mortar droppings beore the next batt is installed.
Case study
Partial ll insulation batts were poorly installed against the inner
lea, the remaining cavity was less than 50mm and bridged
by mortar droppings allowing a path or water to reach the
inner lea.
Movement in masonry
Movement joints
The design o masonry walls should include provision or
potential thermal movement ater construction. A structural
engineer must be consulted to provide a specication.
Verticalmovementjointsshouldrunthefullheightof•
the wall.
The type o compressible ller and sealant to be•
used must be able to accommodate expansion
and contraction movement whilst resisting water
penetration. The sealant should conorm to BS 6213.
Walltiesmustbeprovidedat300mmvertical•
spacingseithersideofthemovementjoint.
Theconstructionofmovementjointsshouldberobust•
tomeetrequirementsofBS5628-3:2005&BSEN
1996-2:2006.
Inexternalwallscontainingopenings,movementjointsmay
be needed at more requent intervals, or the masonry above
and below the opening may need to be reinorced in order to
restrain movement.
Atypicalmovementjointinanouterleafofbrickworkisshown
below:
19 20
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 12/22
Masonry type Maximum spacing of
movement joints
Clay brickwork 12m centres
Dissimilar clay and concrete units
e.g. feature panels where different
movement characteristics possible
The brick manufacturers
should be consulted as more
frequent spacing likely
Short returns in clay masonry If a return in the length of
clay masonry is less than
675mm and either adjoining
length of masonry exceeds
6m, the masonry should be
interrupted at the return to
prevent the development of a
‘mechanical couple’ and the
risk of cracking.
A vertical, compressible joint
or a “slide-by” detail should
be incorporated.
Calcium silicate masonry Should be designed as a
series of panels separated
by movement joints at 8m
intervals.
Aggregate and autoclaved concrete
masonry
Vertical joints to
accommodate horizontal
movement should beprovided at intervals of 6m
Natural stone masonry In the absence of specic
calculations, vertical joints
not less than 10mm wide
should be provided at
intervals specied by a
structural engineer and
located no more than 8m
from an external corner
Internal leafs of cavity wallsThe masonry block manufacturer must
be consulted
In rooms where any walllength exceeds 6.0m
Note: 3mm must be added to the above i the rame is
supportedoffasuspendedtimbergroundoor.Engineered
timber members oer a slight reduction in shrinkage or urther
advice reer to a structural engineer or advice.
In calculating the amount o movement allowance must also be
made or any compressible sealant used. The material used or
lling these gaps should be capable o easily compressing to50% o its original thickness. Guidance on the type o sealants
to use is given in BS 6213
Allowance or ventilation to the cavity will also be required.
Preventing damp penetration at
external openings
Typical section through a window reveal
(Lintelnotshownforclarity)
21 22
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 13/22
A Weepholesat450mmcentresmustbeprovidedwithat
least2(oneateachend)ofthecavitytray(excluding
rendernishes)
B Full height insulated cavity closure incorporating a
verticalDPC.
C ThecavitytrayshouldprojectbeyondtheverticalDPC
D SillDPC(ifprovided)mustturnupbehindtheverticalDPC
by at least 100mmE Stop ends must be provided to the cavity tray weep holes
Moisture penetrating through the outer lea o cavity walls
(fairfacedbrickworkorrenderedblockwork)willrundownthe
inner ace o the external lea.
Wherethecavityisbridgedbyabarrier,e.g.lintels,oorslabs,
concrete rame members or horizontal cavity re barriers, a
cavity tray and weep holes are necessary.
Weepholesmustnotbeblockedparticularlywherearender
external nish is applied to the wall.
Window / door reveal vertical DPC sheltered
to normal exposure
Severe to very severe exposure
Bay window opening
23 24
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 14/22
Recessed balcony opening
Cavity trays
Cavity trays are required to span over openings in the cavity
wall where door and window openings, meter boxes, ducts and
cavity barriers are constructed. They are also required where
roo structures abut external cavity walls. This is to avoid water
penetrating through the outer lea and reaching internal suraces
at lower levels e.g. bay window sots.
Over structural openings in external walls
25 26
Partial ll cavity insulation is shown in this example.
The cavity tray must be ully supported within the•
cavity and lapped onto the ull width o the inner lea.
The height o the cavity tray must be at least 150mm•
within the cavity.
Stop ends must be ormed at each end and weep•
holes provided in the outer lea to drain moisture out
o the cavity.
At pitched roo abutments
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 15/22
27 28
Detail o fashing construction where external
walls are rendered
Detail36:IrelandtechManualdetailbackgroundwillbe
removed keep text but see note ** below
Lean-to roo abutment cavity tray construction
Flat roo abutment cavity tray construction
The external render to the block outer lea is not
shown or clarity.
Partial ll cavity insulation is shown in this example
Structural Lintels and Bearings
Lintel bearings
Construct a ull masonry unit immediately below lintel•
ends. Do not use o-cuts o bricks or blocks.Ensurethelintelislevelandisbeddedinmortar. •
The length o lintel bearings should be not less than•
100 mm and not less than 150 mm or pressed steel
lintels.
Certain lintels may require to be propped until the mortar has
set under the bearings.
Whereprestressedandreinforcedconcretelintelsareused:
build in lintels with the correct side uppermost in•
relation to the position o reinorcement.
prop prestressed composite lintels at centres not•
exceeding 1.2 m during the construction o masonry
above.
when using composite lintels o prestressed concrete•
with masonry the masonry should be careully built
withsolidlylledjoints.Noholesforservicesorweep
holesshouldbemadenorshouldanything(e.g.cavity
tray)bebuiltintothemasonrywithinthecomposite
zone.
exposed aces o lintels must be provided with re•
protection.
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 16/22
Unless proven by a structural engineer point loads immediately
above a lintel must be avoided.
Case study
Wheretheundersideoflintelsareexposedaboveopenings
such as garage doors, the lintel must be adequately protected.
Pad stones
Pad stones must be built into the wall to receive the•
ends o the structural member.
The size and material to be used or the padstone•
must not be less than the structural engineer’s
specication.
Pad stones must not bridge the cavity o an external•
wall.
Parapets
The minimum thickness and maximum height o parapet walls
shouldbeasbelow:
Thickness (mm) Parapet height not to be more than (mm)
t1 + t2
equal or less than 200 600
t1 + t2
greater than 200 equal or
less than 250 860
ADPCunderthecopingandacavitytrayattheroofjunction
must be provided to prevent dampness reaching the inner lea
in the accommodation below. Cavity insulation not shown or
clarity.29 30
L t l t i t f ll b fl d f Timber foor / wall detail
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 17/22
Lateral restraint of walls by floors and roofs
Whereoorsandjoistsare“builtin”orsupportedbyhangersoff
thewall:
shrinkageofjoistsshouldbetakenintoaccount. •
members must be secure to prevent twisting.
whereappropriatejoistsshouldbeprotectedagainst•
moisture.
gaps ormed in the wall construction should be sealed•
with a compressible ller to ensure air tightness.
Thebearingsofalloors,joistsandroofmembersmustnotbe
lessthan90mmontoaloadbearingwall.
Wherewallsrequirelateralrestraintbytensionstrapsatoors
androofconstructionstheprovisionsinBSEN1996-2:2006
should be met as well as the requirements ound in current
Building Regulations.
It should be noted that lateral restraint straps are not only
required at foor and rater / fat roo member levels but may
alsoberequiredtobettedatceilingjoistlevelinapitchedroof
situation. Provision is necessary when the height o the wall
exceedsrecommendedvaluesfoundinBSEN1995-1-1:2004
and current Building Regulations.
Ensureallrestraintstrapsttightlyagainstthemasonryface
within the cavity.
Provision should be made or blocking to be used in the gap
betweenthejoist/rafterandtheparallelwallatalllateral
restraintstrappositions–aswellasinbetweenjoist/raftersfor
the length o strap required.
Lateral restraint straps at foor or roo level must not be retro
tted by plug and screwing the strap to the masonry.
Timber foor / wall detail
Suspended concrete beam and block foor / wall detail
Timber roo / gable wall detail
Whereroofsarerequiredtogivelateralrestrainttowalls,
referencetoBS5268–1–2005&BSEN1990:2002should
bemade.(Seepreviousnoteaboutprovisionatceilingtielevel).
Restraint straps must turn down the cavity by at least 100mm
and be tight against the ace o the wall.
31 32
Case studyRater / gable wall detail
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 18/22
Case study
Whereinllingisrequiredbetweentrussmembersasshown
belowawallplateshouldnotbeusedandthejoistsshouldbe
“builtin”oronsuitablehangers.
Block work has been incorrectly built o the timber wall plate
instead o the trusses being supported o the masonry by correctlyspeciedtruss/joisthangers.
Chimney constructions
Chimneysmustbeconstructedsothatitsheight(measured
fromthelevelofthehighestpointinlinewiththeroof)should
not be greater than our and a hal times its least width.
Thecorrectprovisionofashingsareprovided(seedetails).
33 34
Rater / gable wall detail
Case study
The lateral restraint straps were ound to be securely built
into the gable wall but were not mechanically xed to the roo
members.
Wall plates
Wallplatesmustbelaidlevelonabedofmortarandxed
down onto the wall to restrain the roo against displacement
with galvanised straps at no greater than 2m centres.
Flues and linings Horizontal Damp Proof Courses
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 19/22
Flues and linings
General
Fillalljointswithjointingandcaulkingmaterials•
in accordance with the manuacturer’s sitework
instructions.
Build socketed fue liners with the inner surace•
oftheliningsmoothatthejointsandsocketends
uppermost, i necessary.
Fill the void between brick chimneys and clay or •
concrete fue liners with lightweight concrete or weak
mortar.
Do not use cracked or broken liner sections. Form•
bends with purpose made ttings.
ExtendleadorproprietaryhorizontalDPCtraysthroughtheliner
intotheueandturnupwards(seefollowingdetail)
The construction o fashings is dictated by the type o roo tile
/cladding to be installed. Please reer to the roo tile /cladding
manuacturer’s details or specic fashing detailing.
35 36
Horizontal Damp Proof Courses
Installation o the DPC must ollow normal good practice or the
detailingofDPCs,assetoutinBSEN1996–2:2006,BS
8000-3:2001&BS8215.
EnsuretheDPMisturnedupatslabedgeandlapped•
under the DPC or the ull thickness o the inner lea to
formacontinuousbarrier(includingunderdoorsills).
The DPC should be laid on a smooth bed o resh•
mortar in a continuous length or the ull width o the
lea including any nishes e.g. external render.
Ensureatleasta100mmoverlapisprovidedatany•
jointorangle.
The DPC must not obstruct the cavity.•
EnsuretheexternaledgeoftheDPCisvisibleandnot•
bridged by mortar when completing pointing o the
mortarjoint.
ExternalrendermustnotbridgetheDPC. •
Ensuretheleanmixcavityllmaterialisatleast•
225mm below the DPC level.
DPCs must not be pierced by services or xings.•
Case study
Blue bricks should not be used as the sole means o preventing
damp. A proprietary DPC must always be provided.
(Note;Poordetailingoftheoorslabconstructionatthedoor
thresholdpositionhasalsoresultedinacoldbridgingissue)
Case study
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 20/22
37 38
Insert Photo 1
Stepped DPC
WhereaslopingsiteconditionexiststheDPCmayhavetobe
stepped.
The DPC must be stepped in the masonry coursing so that
at any point it is never less than 150mm above the nished
ground level.
Render / Horizontal DPC junctions
Render must not be taken below and bridge the horizontal
DPC. A proprietary render stop must be installed to terminate
the render above the DPC.
Ca y
NotonlyhasthehorizontalDPCbeenbridgedbytherender
it has also been damaged by the insertion o waste pipes. All
service penetrations should be neat and above DPC level.
Insert photo 2
Note:Surroundingaccesspathsmustnotbeconstructed
at the same level as the DPC. Disabled Access ramps andlandings should be kept 150mm away rom the wall.
DPC / Radon / Gas membrane cavity trays
Whereagasmembraneisinstalledacavitytraywillberequired
to be ormed across the external walls. Typically the gas
membranewillalsoformacavitytraydetailasfollows:
Case study Avoidance o mortar build in cavity trays applies at all levels;
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 21/22
39 40
y
The cavity tray must be at least 225mm in vertical height and
lap ully across each lea o masonry unlike the example below.
The correct type o membrane must be used and correctly
lapped with the DPC.
Case study
Care must be taken to avoid excessive debris building up in the
tray or allow the insulation to become dislodged and bridge the
cavity.Waterpenetrationandcoldbridgingtotheinnerleafis
likely to occur.
horizontalDPC/DPMjunctionsandatupperlevelswhere
lintels, re stopping and roo abutments occur.
Notes Notes
7/29/2019 Bricklayers Pocket Book
http://slidepdf.com/reader/full/bricklayers-pocket-book 22/22
41 42
Notes Notes