+ All Categories
Home > Documents > BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0...

BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0...

Date post: 31-May-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
20
2017 UNDERWATER BRIDGE INSPECTION REPORT BRIDGE # DISTRICT: COUNTY: CITY/TOWNSHIP: Date of Inspection: Equipment Used: Inspected By: Report Written By: Report Reviewed By: Final Report Date: 73540 10 ST S over MISS. RIVER; 1ST AVE S District 3 Stearns St Cloud 09/30/2016 Stuber, Cory Cory Stuber City or Municipal Highway Agency Owner: Minnesota STATE:
Transcript
Page 1: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

2017 UNDERWATER

BRIDGE INSPECTION REPORT

BRIDGE #

DISTRICT: COUNTY: CITY/TOWNSHIP:

Date of Inspection:

Equipment Used:

Inspected By:

Report Written By:

Report Reviewed By:

Final Report Date:

73540

10 ST S over MISS. RIVER; 1ST AVE S

District 3 Stearns St Cloud

09/30/2016

Stuber, Cory

Cory Stuber

City or Municipal Highway AgencyOwner:

MinnesotaSTATE:

Page 2: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

UNDERWATER SUMMARY 3

UNDERWATER INSPECTION 4

UNDERWATER INSPECTION PROCEDURES 6

STRUCTURE INVENTORY 7

ELEMENTS 8

PICTURES 13

DRAWINGS 17

TABLE OF CONTENTS

PAGE NUMBER

Page 3: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Contractor:

(A) Scour screening assessment indicates stable rating and the extent of foundation exposure has not increased since the previous inspection, therefore, presently it is only recommended to monitor the extent of scour and footing exposure during future inspections.

(B) Consider removal of the accumulated timber debris around the piers during routine bridge maintenance.

(C) Reinspect the submerged substructure units at the normal maximum recommended (NBIS) interval of sixty (60) months.

Collins Engineers Inc.

9687Contractor Job Number:

RECOMMENDATIONS

REPORT SUMMARY

UNDERWATER INSPECTION

The substructure units inspected at Bridge No. 73540, Piers 2, 3, 4 and 5, were found to be in good condition with no defects of structural significance observed. Minor deficiencies observed included, random areas of poor consolidation with ¼ inch maximum penetration. Footing exposure was observed at the upstream end of Piers 4 and 5. The extent of footing exposure was comparable to what was reported during the previous underwater inspection. A light to moderate accumulation of timber debris was observed around the entire perimeter of Piers 2 and 4, and at the upstream end of Pier 3. The channel bottom appeared stable with minor localized scour observed, with no appreciable changes since the previous inspection.

(A) The channel bottom material generally consisted of sandy gravel and random cobbles allowing a maximum probe rod penetration of 6 inches.

(B) The channel bottom material consisted of silt allowing a maximum probe rod penetration of 2 feet at the upstream end of Pier 5.

(C) Footing exposure was observed at the upstream end of Pier 4, extending approximately 8 feet downstream on the east and west sides of the pier with a maximum vertical face exposure of 2.5 feet at the upstream nose.

(D) Footing exposure was observed at the upstream end of Pier 5, extending approximately 15 feet downstream on both sides of the pier, with a maximum vertical face exposure of 3 feet at the upstream nose.

(E) A light accumulation of 8-inch-diameter and smaller timber debris was observed around the entire perimeter of Piers 2 and 4 extending from the channel bottom up 6 feet and up to 3 feet off the pier noses and faces.

(F) Minor scour depressions, typically 5 feet in radius and 2 to 3 feet deep, were observed around the upstream ends of Piers 3, 4, and 5, resulting in footing exposure at Piers 4 and 5.

(G) The submerged concrete of the piers and exposed footings was in sound condition with minor random areas of poor consolidation with 1/4 inch maximum penetration.

(H) A light accumulation of timber debris, consisting of up to 8-inch-diameter branches, was observed at the upstream nose of Pier 3 from the channel bottom up 2 feet. The debris was approximately 8 feet long (E/W) by 3 feet wide (N/S).

INSPECTION FINDINGS

Page 3 of 20

Page 4: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Bottom of the pier cap at the downstream end of Pier 5.Water Level Reference:

WATERLINE DATUM

Waterline Elevation (feet):

The waterline was approximately 28.7 feet below reference.Description:

980.4

4.

Piers 2 through 5.Substructure(s) Inspected:

SUBSTRUCTURE INSPECTION DATA

General Shape:

16.7Maximum Water Depth at Substructure(s) Inspected (feet):

Each of the piers consists of two flared columns which extend down to form a single oblong rectangular shaft, which is supported by a rectangular footing/seal combination founded on steel H-piles.

Code:Item 62: Culvert:

6

Y 48 09/2016Code:Item 92B: Underwater Inspection:

Code:

(Minnesota specific codes are used for 92B and 113)

NBIS CODING INFORMATION5.

Item 60: Substructure:

Item 61: Channel and Channel Protection:

7Code:

District 3District:

10 ST S

County:

The superstructure consists of seven spans of multiple prestressed concrete beams. The superstructure is supported by two reinforced concrete abutments and six reinforced concrete piers. The piers are numbered 1 through 6 starting from the west end of the bridge. The footings of all the substructure units are supported on steel H-piles.

Bridge Description:

073 - Stearns

Facility Carried:

BRIDGE DATA1.

UNDERWATER INSPECTION

Bridge #:

MISS. RIVER; 1ST AVE SFeature Intersected:

73540

Underwater Visibility (feet):

Cloudy, 60°FWeather Conditions:

2.0

3.

0.5Waterway Velocity (ft/sec):

09/30/2016

Professional Engineer/Team Leader:

INSPECTION DATA2.

Cory Stuber P.E.

Date of Underwater Inspection:

Garrett Owens P.E.Inspection Diver:

Page 4 of 20

Page 5: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Scour 1885 EA 1

220 Reinforced Concrete Footing 23 23LF

STRUCTURAL ELEMENT CONDITION RATING

Conditions

6.

N

Bridge is scour critical because abutment or pier foundation is rated as unstable due to observed scour at bridge site.

Item 113: Scour Critical Bridge: Code:

No (Mark your selection with an X)Yes X

205

CS3 CS4

Reinforced Concrete Column 88 EA

CS2ELEM # Unit CS1Element Description Quantity

Page 5 of 20

Page 6: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

The routine underwater inspection of Bridge 73540 (10th Street Bridge (MSAS No. 101) over the Mississippi River) was completed on September 30, 2016. The underwater inspection was conducted from a 21 foot boat. The inspection was conducted by a team consisting of a PE-Diver with a valid MnDOT Team Leader certification, a backup diver and a dive tender. The inspection utilized commercial dive equipment and techniques (SSA and/or SCUBA) in accordance with OSHA regulations. Profiles were taken along the upstream and downstream faces of the bridge and around the periphery of substructure units to determine the presence, location and area of scour.

The bridge elements inspected consisted of four reinforced concrete piers each with of two flared columns extending down to form a single oblong rectangular shaft. According to the bridge inventory, Piers 2 through 5 were supported on rectangular concrete footings founded on steel H-piles. Inspection procedures followed FHWA guidance and the MnDOT Bridge and Structure Inspection Program Manual with channel bottom probing to search for foundations. The routine underwater inspection frequency is recommended to remain at a maximum of 60 months based on those findings and risk factors. Also, inspection procedures should continue to follow the above approach and standard guidance with 100% Level I and 10% Level II intensity efforts.

INSPECTION PROCEDURES

UNDERWATER INSPECTION

Page 6 of 20

Page 7: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

F - Friction Hinge Spec. Feat.Pier Foundation (Material/Type)

1 - CONCCantilever ID

+ W A T E R W A Y +Number of Spans Historic Status

3 - FTG PILE

Underwater 60Culvert Type 3 - FTG PILE

Pinned Asbly.

09/30/2016

Barrel Length

1171.4 ft. Navigation Control

Waterway Opening (sf.) 14500Structure Length

ft. Year Painted

0 - No nav. control on waterwayDeck Width (Out-to-Out) 53.3

+ P A I N T +

APPR: 1 TOTAL:5 - Not eligible

MAIN: 7

Main Span Length 168.7 ft.Drainage Area (sq. mi.)

B R I D G E D A T A +Main Span Detail

0 - SUBSTANDARD+ M I S C.

Appr. Span Type 5 - Prestress or Precast Structure Flared

GR Termini N - NOT REQUIRED

Appr. Guardrail

Main Span Type 5 - Prestress or Precast Median Width On Bridge

ft. Bridge Railing 1 - MEETS STANDARDS

0 - SUBSTANDARD

Main Span Design 01 - Beam Span

ft. GR Transition

Skew 0

Y/N Freq Date

Abutment Foundation (Material/Type)

1 - CONC Frac. Critical

D E P T H I N S P. +Appr. Span Design

0 - No flare+ I N

Appr. Span Detail Field Conn. ID

07 - Box Girder Parallel Structure N - No parallel structure

Pier Protection

0 - Not Required

Rating Date 11/1/199245682 sq. ft. Traffic

ft. 50B. Rt 6.00Sidewalk Width 50A. Lt 6.00

Roadway Area (Curb-to-Curb)

Posted Load 0 - Not Required

PostingStructure Area (Out-to-Out) 62436 sq. ft.

DBL:VEH: SEMI:

Rt 28 ARail Type Lt 28 C N - N/AN - N/A B N - N/A

N - Not Applicable Overweight Permit CodesCurb Height Lt

ft. Horizontal 0 - Not Required

0.83 ft. Vertical0.83 ft. Rt

Wear Surf Install Year 1983

sq. ft. Nav. Vert. Lift Bridge Clear. (ft.)

N - STBL - LIM SCOUR

Year 1992Primer Type MN Scour Code

Painted Area

Unsound Paint % Nav. Clr. (ft.)

!

Deck Material 1 - Concrete Cast-in-Place 0.0Wear Surf Type 4 - Low Slump Concrete

Vert. 0.0 Horiz.

S I G N S +Operating Rating 2 - HS TRUCK

1 - Epoxy Coated Reinforcing + B R I D G E

Inventory Rating 2 - HS TRUCK 28.0

46.0Deck Rebars Install Year 1983

Deck Rebars

Finish TypeWear Course/Fill Depth 0.17 ft.

0 - None

Design Load 5 - HS 20

+ C A P A C I T Y R A T I N G S +Deck Membrane

45 ° 32

Inspector Name Stuber, Cory

Latitude Control Section (TH Only) Status' 56.15 ''

2 - 2-way traffic

Routine Inspection Frequency 24

Sect., Twp., Range

0.2 MI W OF JCT CSAH 8 Level of Service 1 - MAINLINE

- 28W Roadway Type13 - 124N

Detour Length 2.0 mi.R A T I N G S +

Custodian 04 - City or Municipal Highway Agency

Owner 04 - City or Municipal Highway Agency

Deck 7 Unsound Deck %

C O N D I T I O N° 8 '

A - Open

Longitude 94 001+00.590 + N B I 49.49 '' Reference Point

Crew

+ I N S P E C T I O N +

Agency Br. No. 197

District 03

Bridge Match ID (TIS) 1 Userkey

10 ST S over MISS. RIVER; 1ST AVE S

Minnesota Structure Inventory Report

Bridge ID: 73540

+ G E N E R A L + + R O A D W A Y +

Date: 01/23/2017

Sufficiency Rating 93.4Roadway Name or Description

101

City St Cloud

Routine Inspection Date 09/14/2015

Desc. Loc.

Township 10 ST S

Number

NRoadway O/U Key Route On StructureMaint. Area Structurally Deficient

NRoute Sys 05 - MSASCounty 073 - Stearns Functionally Obsolete

Lanes

Waterway Adequacy 9Max. Vert. Clear.

ft.Legislative District 15Bft.Potential ABC 2 - N/A ft.

ft.On - Off System Roadway Width 39.00 ft.

Vertical Clearance ft.1 - ON

Underclearances 4

Service On 5 - Highway-pedestrian Appr. Surface Width+ S A F E T Y F E A T U R E S +

6 - Highway - waterway Bridge Roadway Width 39.0

39.0 ft.

Service Under

ft.

38.9 ft. Approach Alignment 9Horizontal Clear.

ft.

ft.+ S T R U C T U R E + Lateral Clearance

HCADT ADTT7

Year Built 1983

MN Year Reconstructed Functional Class

%Channel 6

Substructure

2Superstructure 7

ON 2 UNDER

17900 YEAR 2003BMU Agreement ADT

Structure Evaluation 7If Divided

D I M E N S I O N S +Bridge Plan Location 1 - CENTRAL

9/1/1985Deck Geometry 5

NB-EB SB-WBDate Opened to Traffic

+ R D W Y

FHWA Year Reconstructed

MN Temporary Status

16 - Urban - Minor ArterialCulvert N

A P P R A I S A L R A T I N G S ++ N B I

Page 7 of 20

Page 8: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

County:

City:

Township:

Township:Section: Range:

Span Type:

NBI Deck: Super: Sub: Chan: Culv:

Appraisal Ratings - Approach: Waterway:

Required Bridge Signs - Load Posting:

Horizntal:

Traffic:

Vertical:

MN Scour Code:

Open, Posted, Closed:

Location:

Route:

Control Section:

Local Agency Bridge Nbr.:

Ref. Pt.:

Maint. Area:

Length:

Deck Width:

Rdwy. Area/ Pct. Unsnd:

Paint Area/ Pct. Unsnd:

Culvert:

Stearns

St Cloud

124N13 28W

5 - Prestressed Concrete 2 -Stringer/Multi-beam or Girder

7 7 7 6 N

9 9

0 - Not Required

0 - Not Required

0 - Not Required

N - Not Applicable

N - STBL - LIM SCOUR

0.2 MI W OF JCT CSAH 8

05 - MSAS 101 001+00.590

1171.4

53.3

45682 sq. ft. / %

sq. ft. / %

N/A

A - Open

ft.

ft.

Postings:List:

MINNESOTA BRIDGE INSPECTION REPORT

01/30/2017

BRIDGE 73540 10 ST S OVER MISS. RIVER; 1ST AVE S

Unofficial Structurally Deficient N

NUnofficial Functionally Obsolete

Unofficial Sufficiency Rating 93.4

ELEMNBR ELEMENT NAME INSP. DATE QUANTITY

QTYCS 1

QTYCS 2

QTYCS 3

QTYCS 4REPORT TYPE

Reinforced Concrete Deck 01/23/2017 62436 SF 61187 0 1249 012 Underwater

62436 SF 61187 0 1249 0Migrated Values

Notes: 2012 : Minor rust stains and spalls .2013 : Minor rust stains and spalls. Bird netting damage at pier 7.2015 : Minor rust, stains, delamination and spalls. All utility access covers (MH type covers) are deteriorated, are leaking and cause damage:delamination and loose concrete. All utility access covers need repair/maintenance work.

510 - Wearing Surfaces 45682 SF 44768 0 914 0

Notes: Low Slump Overlay with Epoxy Rebar Notes: [2010] Minor cracking.2012 : Minor cracking.2013 : Minor cracking sealed in 2012 by MnDOT Bridge Maintenance District 3. Condition stable.2015: Minor cracking. Crack sealing repair/maintenance work needed.

Underwater 01/23/2017

45682 SF 44768 0 914 0Migrated Values

Reinforced Concrete Slab 01/23/2017 62436 SF 61187 0 1249 038 Underwater

62436 SF 61187 0 1249 0Migrated Values

Notes: 2012 : Minor rust stains and spalls .2013 : Minor rust stains and spalls. Bird netting damage at pier 7.2015 : Minor rust, stains, delamination and spalls. All utility access covers (MH type covers) are deteriorated, are leaking and cause damage:delamination and loose concrete. All utility access covers need repair/maintenance work.

510 - Wearing Surfaces 45682 SF 44768 0 914 0

Notes: Cast-In-Place Concrete Voided Slab with Low Slump Overlay Notes: 2012: Minor cracking.2013: Minor cracking sealed in 2012 by MnDOT Bridge Maintenance District 3. Condition stable.2015 :Condition stable.

Underwater 01/23/2017

45682 SF 44768 0 914 0Migrated Values

Reinforced Concrete Closed Web/BoxGirder

01/23/2017 1892 LF 1375 517 0 0105 Underwater

1892 LF 1375 517 0 0Migrated Values

Notes: 2012: minor to moderate spalling, or delamination.2013: minor to moderate spalling, or delamination.2015: Minor to moderate spalling, or delamination.MnDOT Maintenance crews applied in 2012/2013 protective coating to some spalled areas(including spalled areas with exposed reinforcement).All drainage openings: area around drainage openings shows signs of delamination, spalling, reinforcement exposure, rust. All floor drainsconcrete areas need repair/maintenance work, and floor drains should have a drain extension installed.

Page 8 of 20

Page 9: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Prestressed Concrete OpenGirder/Beam

01/23/2017 8197 LF 8197 0 0 0109 Underwater

8197 LF 8197 0 0 0Migrated Values

Notes: Monitoring of cracks show no change since additional post tentioning was added in 1991 [2002] Continued measurements on cracksshow no change in 2002.[2007] Crack width monitoring shows no change again in 2007.2012 : Epoxy injected cracks stable.2013 : Epoxy injected cracks stable.2015: Epoxy injected cracks stable.All girder ends are rusting and need repair/maintenance work.

Reinforced Concrete Column 01/23/2017 42 EA 42 0 0 0205 Underwater

42 EA 42 0 0 0Migrated Values

Notes:2015: Minor deterioration. There may be minor cracking, but there is no exposure of steel reinforcement.

Reinforced Concrete Abutment 01/23/2017 147 LF 0 147 0 0215 Underwater

147 LF 0 147 0 0Migrated Values

Notes: [2016] Migrator added 40 LF to abutment quantity to account for wingwalls (CS1:0 CS2:40 CS3:0 CS4:0).

2012: Reinforced concrete element has minor to moderate deteoration- cracking, minor spalling.2013: Reinforced concrete element has minor to moderate deterioration- cracking, minor spalling.2015: Reinforced concrete element has minor to moderate deterioration- cracking, minor spalling.There are gaps - deteriorated, unsealed joints between the bridge walls and approach stairs causing soil erosion and soil loss. Soil lossevident. Repair/maintenance work needed - refer to 2013 DONLAR's proposal/recommendation for repair work.

Wingwall notes:2012: Reinforced concrete element has minor to moderate deterioration- cracking, minor spalling.2013: Reinforced concrete element has minor to moderate deterioration- cracking, minor spalling.2015: Reinforced concrete element has minor to moderate deterioration- cracking, minor spalling.There are gaps - deteriorated, unsealed joints between the bridge walls and approach stairs causing soil erosion and soil loss. Soil lossevident. Repair/maintenance work needed - refer to 2013 DONLAR's proposal/recommendation for repair work.

Reinforced Concrete Pile Cap/Footing 01/23/2017 23 LF 0 23 0 0220 Underwater

Notes: [2016] Underwater Inspection - Footing exposure was observed at the upstream end of Pier 4, extending 8 feet downstream on the eastand west sides of the pier with a maximum vertical face exposure of 2.5 feet at the upstream nose. Footing exposure was observed at theupstream end of Pier 5, extending 15 feet downstream on both sides of the pier, with a maximum vertical face exposure of 3 feet at theupstream nose. The concrete of the footings was generally in sound condition with minor random areas of poor consolidation with 1/4 inchmaximum penetration.

Reinforced Concrete Pier Cap 01/23/2017 746 LF 0 746 0 0234 Underwater

746 LF 0 746 0 0Migrated Values

Notes: [2007] Approx 1 SqFt area on western most pier cap has delaminated but repair deterioration still minimal.2012: Reinforced concrete element has minor to moderate deterioration- cracking, minor spalling, with exposure of steel reinforcement.2013: MnDOT plans to repair in October 2013 following spalled areas:Pier 2 cap 3sq.ft spalled areas east side; Pier 3 cap 15sq.ft spalled westside, 8sq.ft. spalled east side.Pier 5 cap south facia shear cracks stable, bearing seat stable.2015: Reinforced concrete element has minor to moderate deterioration- cracking, minor spalling, delamination, efflorescence, rust.Repair/ maintenance work needed in these areas.

Strip Seal Expansion Joint 01/23/2017 816 LF 0 816 0 0300 Underwater

816 LF 0 816 0 0Migrated Values

Notes: [2002] Work order issued to clean joints[2010] Work order issued to clean joints.2012: Joints have deteriorated, and are leaking. As part of 2012 bridge repair work, City plans to replace glands on all expansion joint devices:joint model Lenco Type W.2013: MnDOT Maintenance District 3 replaced joints in 2012 . Joint model Lenco Type W.2015: Condition stable.

ELEMNBR ELEMENT NAME INSP. DATE QUANTITY

QTYCS 1

QTYCS 2

QTYCS 3

QTYCS 4

BRIDGE 73540 10 ST S OVER MISS. RIVER; 1ST AVE S

REPORT TYPE

Page 9 of 20

Page 10: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Movable Bearing 01/23/2017 9 EA 9 0 0 0311 Underwater

9 EA 9 0 0 0Migrated Values

Notes:2012: Quantities adjusted to reflect the Plan quantity.2015: Good condition and functioning as intended.

Fixed Bearing 01/23/2017 5 EA 5 0 0 0313 Underwater

5 EA 5 0 0 0Migrated Values

Notes:2012 : Quantities adjusted to reflect the Plan quantity.2015: Good condition and functioning as intended.

Reinforced Concrete Approach Slab 01/23/2017 1560 SF 0 1560 0 0321 Underwater

1560 SF 0 1560 0 0Migrated Values

Notes: [2016] Migrator assumed an approach slab length of 20FT and used the inventory quantity of 39FT for the width.[2010] Cracking and settlement.2012: Minor deterioration - cracking. There is slight settlement, but traffic impact on the bridge has not been significantly increased.2013: Minor deterioration - cracking. Slight settlement, but traffic impact on the bridge has not been significantly increased.2015: Minor deterioration - cracking. Slight settlement, but traffic impact on the bridge has not been significantly increased.West approach slab: poured joint between the approach slab and the bituminous pavement deteriorated and needs repair/maintenance work.

Metal Bridge Railing 01/23/2017 2335 LF 2325 10 0 0330 Underwater

2335 LF 2325 10 0 0Migrated Values

Notes: [2016] Migrator assumed concrete/metal combination type rail.[2010] 10 LF of railing bent due to impact damage.2012 : Quantity adjustment to reflect the Plan Quantities2012 : 10 LF moved to State 2 - railing bent due to impact damage.2013: No new findings.2015: No new findings.

515 - Steel Protective Coating 999 SF 999 0 0 0

Notes: [2016] Migrator assumed CS1 and a quantity of 999 SF.

Underwater 01/23/2017

999 SF 999 0 0 0Migrated Values

Reinforced Concrete Bridge Railing 01/23/2017 2335 LF 2325 10 0 0331 Underwater

2335 LF 2325 10 0 0Migrated Values

Notes: [2016] Migrator assumed concrete/metal combination type rail.[2010] 10 LF of railing bent due to impact damage.2012 : Quantity adjustment to reflect the Plan Quantities2012 : 10 LF moved to State 2 - railing bent due to impact damage.2013: No new findings.2015: No new findings.

Critical Deficiencies or Safety Hazards 01/23/2017 1 EA 1 0 0 0800 Underwater

1 EA 1 0 0 0Migrated Values

Notes: NO CRITICAL FINDINGS OBSERVED DURING THE LAST INSPECTION.

Concrete Hinge Assembly 01/23/2017 122 EA 0 122 0 0851 Underwater

122 EA 0 122 0 0Migrated Values

Notes: 2012 : Concrete hinge assembly has minor deteriorations. Debris or corrosion may have resulted in slight restriction of movement; atpier 6 box girder west side cleaning and lubrication of bearings recommended.2013 : Concrete hinge assembly has minor deteriorations. Debris or corrosion may have resulted in slight restriction of movement. MnDOTBridge Maintenance District 3 in 2013 cleaned and lubricated bearings at pier 6 box girder west side.2015 : Concrete hinge assembly has minor deteriorations. Debris or corrosion may have resulted in slight restriction of movement. MnDOTBridge Maintenance District 3 in 2013 cleaned and lubricated bearings at pier 6 box girder west side.

Concrete Shear Cracking 01/23/2017 1 EA 1 0 0 0883 Underwater

1 EA 1 0 0 0Migrated Values

Notes: Use this element to monitor the presence of shear cracking on concrete elements. Pay particular attention to the concrete pier caps andprestressed concrete beams.

ELEMNBR ELEMENT NAME INSP. DATE QUANTITY

QTYCS 1

QTYCS 2

QTYCS 3

QTYCS 4

BRIDGE 73540 10 ST S OVER MISS. RIVER; 1ST AVE S

REPORT TYPE

Page 10 of 20

Page 11: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Scour 01/23/2017 1 EA 0 1 0 0885 Underwater

Notes: [2016] Underwater Inspection - Minor scour depressions, typically 5 feet in radius and 2 to 3 feet deep, were observed around theupstream ends of Piers 3, 4, and 5, resulting in footing exposure at Piers 4 and 5.

Slopes & Slope Protection 01/23/2017 1 EA 1 0 0 0892 Underwater

1 EA 1 0 0 0Migrated Values

Notes: Use this element to rate the condition of slopes and slope protection.

Deck & Approach Drainage 01/23/2017 1 EA 1 0 0 0894 Underwater

1 EA 1 0 0 0Migrated Values

Notes: Use this element to rate the condition, function, and adequacy of the drainage system.

Protected Species 01/23/2017 1 EA 1 0 0 0900 Underwater

1 EA 1 0 0 0Migrated Values

Notes: Use this element to track the presence of protected species living on this structure.

General Notes: [2010] Concrete voided slab element at W end, underside area. Isolated area of delamination and spalling, with reinforcementexposed. Repairs recommended: remove and replace loose concrete.

Maintenance work is scheduled for 2012, with the scope of work as in the attached BRIDGE 73540 MAINTENANCE REPORT.City plans to partner with MnDOT District 3 Bridge Maintenance Team to carry out the maintenance work. Cost estimates arebeing prepared by MnDOT and will be submitted to City for approval prior to starting the work.

2013: Maintenance work, as per the BRIDGE 73540 MAINTENANCE REPORT, did start 2012 with joint replacement, deckcrack sealing and some concrete repair.The work is to be completed 2013. Work is being done by MnDOT MaintenanceDistrict 3.Steps in approach areas to the University Bridge are scheduled for repair in 2014- see attached photos.

2015: Repair/Maintenance work discussed with the Program Administrator:1. Reinforced Concrete Box Girder: area around drainage openings shows signs of delamination, spalling, reinforcementexposure, rust. All floor drains concrete areas need repair/maintenance work, and floor drains should have a drain extensioninstalled in 2016.2. Prestressed Concrete Girder or Beam: All girder ends are rusting and need repair/maintenance work in 2016.3. Reinforced Concrete Abutment :There are gaps - deteriorated, unsealed joints between the bridge walls and approachstairs causing soil erosion and soil loss. Soil loss evident. Repair/maintenance work needed - refer to 2013 DONLAR'sproposal/recommendation for repair work.Task for 2016: Contact DONLAR and update their proposal and cost estimate for needed repairs.4. Approach Stairs: concrete has deteriorated in multiple locations, loss of concrete, unsafe walkingconditions.Repair/maintenance work needed - refer to 2013 DONLAR's proposal/recommendation for repair work.Task for 2016: Contact DONLAR and update their proposal and cost estimate for needed repairs.5. Concrete Approach Slab : West approach slab - poured joint between the approach slab and the bituminous pavementdeteriorated and needs repair/maintenance work in 2016.6. Underside of Concrete Deck: All utility access covers (MH type covers) are deteriorated, are leaking and cause damage:delamination and loose concrete. All utility access covers need repair/maintenance work in 2016.7. Concrete Deck: Minor cracking-crack sealing repair/maintenance work needed in 2016.8. Flush bridge deck and joints every year, and more frequently as needed.

58. Deck NBI:

36A. Brdg Railings NBI:

36B. Transitions NBI:

36C. Appr Guardrail NBI:

36D. Appr GuardrailTerminal NBI:

59. Superstructure NBI:

ELEMNBR ELEMENT NAME INSP. DATE QUANTITY

QTYCS 1

QTYCS 2

QTYCS 3

QTYCS 4

BRIDGE 73540 10 ST S OVER MISS. RIVER; 1ST AVE S

REPORT TYPE

Page 11 of 20

Page 12: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

ELEMNBR ELEMENT NAME INSP. DATE QUANTITY

QTYCS 1

QTYCS 2

QTYCS 3

QTYCS 4

BRIDGE 73540 10 ST S OVER MISS. RIVER; 1ST AVE S

REPORT TYPE

Inspector's Signature Reviewer's Signature

60. Substructure NBI:

61. Channel NBI:

62. Culvert NBI:

71. Waterway Adeq NBI:

72. Appr RoadwayAlignment NBI:

Page 12 of 20

Page 13: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Photo 1 - Upstream Elevation, Looking South.

Photo 2 - West Shoreline, Looking West.

Pictures

Page 13 of 20

Page 14: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Pictures

Photo 3 - Pier 2, Looking West.

Photo 4 - Pier 3, Looking West.

Page 14 of 20

Page 15: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Pictures

Photo 5 - Pier 4, Looking West.

Photo 6 - Pier 5, Looking East.

Page 15 of 20

Page 16: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Pictures

Photo 7 - East Shoreline, Looking East.

Photo 8 - View Downstream, Looking South.

Page 16 of 20

Page 17: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Page 17 of 20

Page 18: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Page 18 of 20

Page 19: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Page 19 of 20

Page 20: BRIDGE # 10 ST S over MISS. RIVER; 1ST AVE SMain Span Design 01 - Beam Span ft. GR Transition Skew 0 Y/N Freq Date Abutment Foundation (Material/Type) 1 - CONC Frac. Critical D E P

Page 20 of 20


Recommended