+ All Categories
Home > Documents > bridge design using SAP

bridge design using SAP

Date post: 12-Apr-2016
Category:
Upload: sukhwinder-singh-gill
View: 48 times
Download: 7 times
Share this document with a friend
Description:
bridge design using SAP
77
Analysis and Design of Highway Super structure Bridge Advisor: Dr. Bilal El Ariss Name : ID : Awad Mahfoudh Ba Obaid 200501233 Hussain Mahmod Al braiki 200602670 Salim Ibrahim Ba Saeed 200608514 Salem Abdullah Fadaaq 200501514 Suhail Mohamed Al Amri 200416287 Graduation Projects Unit Graduation Project (II)
Transcript
Page 1: bridge design using SAP

Analysis and Design of Highway Super structure Bridge

Advisor: Dr. Bilal El Ariss

Name : ID :

Awad Mahfoudh Ba Obaid 200501233Hussain Mahmod Al braiki 200602670Salim Ibrahim Ba Saeed 200608514Salem Abdullah Fadaaq 200501514Suhail Mohamed Al Amri 200416287

Spring Semester 2011

Graduation Projects Unit

Graduation Project (II)

Page 2: bridge design using SAP

• Introduction

• Objectives

• Summary of GP (1)

• Background Theory

• Analysis & Design

• Economical , Environmental & Contemporary Issues

• Conclusion

Outline

Page 3: bridge design using SAP

Introduction

Development of Abu Dhabi has become a place full of shopping mall and luxury building, hotels.

Development increases the population of Abu Dhabi.

Population growth causes problems in the infrastructural.

Major infrastructural problem is the traffic jam.

The bridge is constructed to link many other major roads to the City of Abu Dhabi.

Problem Statemen

t

Page 4: bridge design using SAP

Objectives

• The main objective of this graduation project is to

recommend and present different bridge alternative

Bridges. Analysis will be conducted for the different bridge

alternatives. Then, those different bridge alternatives will

be designed according to our analysis.

Page 5: bridge design using SAP

Summary of GP1

Page 6: bridge design using SAP

The pier cap is a structural element that transfers

the loads carried by the superstructure elements to

the substructure elements, located at the junction of

two spans.

Literature ReviewPier Caps

Page 7: bridge design using SAP

Single column (Hammerhead).

Multi-column or pile bent.

Solid Wall.

There are different types of pier caps, the following are the most common types:

Literature ReviewPier Caps

Page 8: bridge design using SAP

The selection of the pier type depends on many factors,

such as :

1. Required load capacity.

2. Superstructure Geometry.

3. Site conditions.

4. Cost Consideration.

5. 5. Aesthetics.

Page 9: bridge design using SAP

Pier Cap Dead Load Analysis Process

Total Dead loads coming from girders have been

considered as point loads (concentrated loads on the pier

cap).

In this case, there have been a total of 9 concentrated

loads imposed on the cap (since we have 8 girders).

Page 10: bridge design using SAP

Dead Load Analysis

Page 11: bridge design using SAP

Dead Load Analysis

We will design on the Maximum Load from girder = 2380.03 kN

Support Load (kN)

1 827.6

2 2380.03

3 2023.05

4 2120.4

5 2087

6 2120.4

7 2023.05

8 2380.03

9 827.6

Page 12: bridge design using SAP

SAP2000 Dead Load Analysis

Next, take the maximum reactions. Then entered as point concentrated loads

Page 13: bridge design using SAP

SAP2000 Dead Load Analysis

Finally, Bending moments are determined for the maximum critical load effects

Page 14: bridge design using SAP

Live Load Configurations

Page 15: bridge design using SAP

Live Load Study Cases

Case (1): On the middle

P Pw

P = 284.7 KNW = 345.78 KN/m

According to the AASHTO standards, there are different live load scenarios that should be studied in order to obtain the maximum possible live load:

Page 16: bridge design using SAP

Case (2): Full Shift Left

Live Load Study Cases

Page 17: bridge design using SAP

Live Load Study Cases

Case (1): One on the middle• R1= 0• R2= 0• R3= 7.845 KN• R4= 838.7 KN• R5= 838.7 KN• R6= 7.845 KN• R7= 0• R8= 0

Page 18: bridge design using SAP

Live Load Study Cases

Case (2): Full Shift Left• R1= 1183.14 KN• R2= 1116.7 KN• R3= 1243.2 KN• R4= 1899 KN• R5= 1251.1 KN• R6= 1212.3 KN• R7= 760 KN• R8= 1636.6 KN

Page 19: bridge design using SAP

Live Load Cases Result

Load Cases G1 G2 G3 G4 G5 G6 G7 G8

1 1183.14

1116.7

1243.2

1899

1251.1

1212.3

759.718

1636.6

2 0 0 7.845

838.7

760.1 0 0 0

Max. Load (kN)

1183.14

1116.7

1243.2

1899

1251.1

1212.3

759.718

1636.6

Page 20: bridge design using SAP

Take the maximum reaction from cases. Then entered in the SAP2000 as concentrated load

Live Load

Finally, Bending moments are determined for the maximum critical live load effects

Page 21: bridge design using SAP

Ultimate Moment of Pier cap

Moment Location

Moment form Dead Load (KN.m)

Moment from Live Load (KN.m)

Ultimate Moment (KN.m)

Span 1 8041.71 4109.21 17243.255Middle Pier -13474.53 -7170.1 -29390.838

Span 2 8041.71 3989.76 17034.2175

Page 22: bridge design using SAP

Bridge component

Design

Page 23: bridge design using SAP

Bridge Girder

Frame 7Frame 1 Frame 6Frame 2 Frame 5Frame 3 Frame 4 Frame 8

Abutment 2Pier 1 Pier 6Pier 2 Pier 5Pier 3 Pier 4 Pier 7

Frame Positive Ultimate Moment (kN.m)

Pier cap Negative Ultimate Moment (kN.m)

1 15407.1 1 -192592 8723.79 2 -189083 11265.6 3 -135294 10604.7 4 -149765 10604.7 5 -135296 11265.6 6 -189087 8723.79 7 -192598 15407.1 Max -19259

Max 15407.09

• Girder ultimate negative moments values:

Analysis Data

Page 24: bridge design using SAP

Bridge Girder Design Concept

Main target is to determine the location of the neutral axis.

Two cases: Case 1:

N.A falls in the flange (a ≤ hf) Section above N.A is rectangular

b

N.A.

AS

hf

Page 25: bridge design using SAP

Bridge Girder Design Concept

Case 2:

N.A falls in the flange (a > hf) Compressed concrete above N.A is NOT

rectangular. Divide compressed concrete Above N.A into rectangular parts.

hf

b

N.A.

AS

Page 26: bridge design using SAP

Compare the values of Mu & Mflange if:

Mu < Mflange a < hf

Mu > Mflange a > hf

Where:

Mu = Moment from applied forces

Mflange = Moment carried by flange.

Bridge Girder Design Concept

Page 27: bridge design using SAP

R-Section

STEP 1: Assume bar size.

STEP 2: Assume cover.

STEP 3: Compute depth of steel reinforcement ( d ).

STEP 4: Determine ( ρ ) from Tables or ACI Equation.

STEP 5: Ensure that ρmin ≤ ρ ≤ ρmax.

STEP 6: Determine As.

Design procedure

Page 28: bridge design using SAP

Calculations

Girder Design Steps:

Bottom Steel Reinforcements.

Top Steel Reinforcements.

Girder Design

Page 29: bridge design using SAP

Reinforcement Calculations

mmdmmdmmC

MpafMpafc

b

s

c

y

431040

42035'

Assume Bar size # 43

mmdCoverhd

mmmm

ddCCover bsc

2428722500

725.71243

1040Cover

2

Bottom steel

Page 30: bridge design using SAP

Based on the above result case one procedure will be followed.

fflangeu

flange

flange

ffcflange

u

haMM

mkNmmNXM

M

hdbhfM

mKNM

.51533.508.10153.52

7502428*)1250*2500*35*85.0(

2*)85.0(

.09.54071

10

'

Reinforcement CalculationsBottom

steel

Page 31: bridge design using SAP

3231.22428*1250*9.01009.15407

2

6

2

XR

bdM

R

n

un

005766.0

35*85.0323.2*2

11420

35*85.0

'85.0

211

'85.0

CfnR

yfCf

Reinforcement CalculationsBottom

steel

Page 32: bridge design using SAP

0035.0

0035.0420*435

0033.0420

4.1

4

4.1

min

min

'min

ofGreater

ff

fofGreater

y

C

y

0035.0

0035.0420*435

0033.0420

4.1

4

4.1

min

min

'min

ofGreater

ff

fofGreater

y

C

y

815.035*007.006.1

30007.006.13085.0

1

''

'

1

MPafforfMPaffor

CC

C

025.0420600

600420

35*815.0*85.0)75.0(

60060085.0

)75.0('

1

Max

Max

yy

CMax ff

f

Reinforcement CalculationsBottom

steel

Page 33: bridge design using SAP

Max min

bars 31bars 1.121452

17499.523bar one of areasection cross

A bars ofNumber

17499.523

2428*1250*0035.0

..

s

2

mmA

A

dbA

S

S

S

Reinforcement CalculationsBottom

steel

So according to the area of steel obtained, we choose to take 13 bars # 43

Page 34: bridge design using SAP

• As =13 bars #43 for each meter ,

• From table bmin =1174mm < bactual =1250

mm.

• So, we need one layer.

Reinforcement CalculationsBottom

steel

Page 35: bridge design using SAP

Reinforcement CalculationsBottom

steel

Page 36: bridge design using SAP

Reinforcement CalculationsTopsteel

Page 37: bridge design using SAP

Girder reinforcement

Frame

Postive ultimate moment (kN.m)

Number of steel bars

Pier cap

Negative ultimate moment (kN.m)

Number of steel bars

1 15407.1 13# 43 1 -19259 16 # 43

2 8723.79 7 # 43 2 -18908 15 # 43

3 11265.6 9# 43 3 -13529 12 # 43

4 10604.7 9# 43 4 -14976 12 # 43

5 10604.7 9# 43 5 -13529 12 # 43

6 11265.6 9# 43 6 -18908 15 # 43

7 8723.79 7 # 43 7 -19259 16 # 43

8 15407.1 13# 43

Page 38: bridge design using SAP

Reinforcement

The failure of reinforced concrete beams in shear is

quite different from their failure in bending.

Shear failure occur suddenly with little or no advance

warning.

Girder Shear

Page 39: bridge design using SAP

ReinforcementGirder Shear

Page 40: bridge design using SAP

Vu= 1271 KN Ø for shear = 0.75 We found that ØVc/2 = 673.31 < Vu= 1271 KN < ØVc=1346.63

KN So we need minimum strips We choose stirrups number 16 with max allowed spacingSmax =smaller of: 600mm

or 0.5d=0.5 x 2428=1214mm or

Choose Smax=600mm=60cm

ReinforcementGirder Shear

Page 41: bridge design using SAP

Dead Load Analysis Process

Total Dead loads coming from girders have been

considered as point loads (concentrated loads on the

pier cap).

In this case, there have been a total of 9 concentrated

loads imposed on the cap (since we have 8 girders).

Pier caps

Page 42: bridge design using SAP

According to reinforcement concrete (RC)

design concept, the design of bridge pier

caps follows the rectangular section design

method which used in slab design.

Concept & theory Pier caps

Design

Page 43: bridge design using SAP

Pier cap design fc

’ = 35 MPa fy = 420 MPa Cc=50 mm

db=57 mm

ds= 10 mm According to the ACI codes:

ρ = 0.85 (fc’/ fy) x [1-(1-(2Rn / 0.85 fc

’)0.5]

Rn = Mu/φ bd2

As=ρbd

Page 44: bridge design using SAP

Reinforcement Calculations

Mu = 17243.255KN.m = 17243.255x 106 N.mm

Cover= Cc+db+ds= 50+57+10= 88.5 mm =90 mm

d=h-cover=2550-88.5= 2461.5 mm

Rn = 17243.255x106 / (0.9 x 1000 x 2461.5 2)= 3.166

ρ = 0.85 (35/ 420) x [1-(1-(2x3.066 / 0.85x 35)0.5] = 0.00798

Bottom steel

Page 45: bridge design using SAP

From ACI Table the ρmax= 0.0216, and ρmin 0.0035

Reinforcement CalculationsBottom

steel

Page 46: bridge design using SAP

since the ρ = 0.00719 is between the extremes

ρmax<ρ < ρmin , ok (ρ = 0.00719)

As=ρbd=0.00797 x 1000 x 2461.5 = 19651.67 mm2

Reinforcement CalculationsBottom

steel

Page 47: bridge design using SAP

Reinforcement CalculationsBottom

steel

Page 48: bridge design using SAP

Steel Reinforcement

Moment Location

Ultimate Moment (KN.m)

As (mm2)

No. of bars

Span 1 17243.255 19300 8#57Middle Pier -29390.838 34452.964 15 #57

Span 2 17034.2175 19050.328 8#57

Pier cap

Page 49: bridge design using SAP

  Negative shear Positive shear

span 1 -7587.37 -middle pier -12641.7 13840

span 2 - 7667.12

Shear Design Calculation Pier cap

We will design on the ultimate shear

=

Vu= 13840 KN

Page 50: bridge design using SAP

In our case we found that Vu ≥ ØVc , so we will need stirrups

So we will use

Shear Design Calculation Pier cap

Page 51: bridge design using SAP

Spacing limit :-

Shear Design Calculation Pier cap

Page 52: bridge design using SAP

Shear Design Calculation Pier cap

Page 53: bridge design using SAP

Alternative design

Present the second alternative design for the bridge, which is:

• I-Section Steel girder

Page 54: bridge design using SAP

Classification of LTB Cases:

• (1) if Lb ≤ Lp No LTB• (2) if Lp < Lb < Lr Inelastic LTB• (3) if Lb > Lr Elastic LTB

Where:

• Lb: laterally unsupported length of the compression flange.• Lp : limit for no LTB.• Lr : limit between elastic and inelastic LTB.

Lateral Torsional Buckling LTB

Page 55: bridge design using SAP

Moment vs. Lb curve

Page 56: bridge design using SAP

Design Concept

Mu ≤ øMp (Where ø = 0.9)

øMp = Zx * fy

Zx = øMp / fy ; Zx : is the plastic

section modulus

Page 57: bridge design using SAP

Moment on the Girder

Section

Frame Ultimate Moment (kips.ft)

Ultimate Moment (kips.ft) Zx Zx

1 11356.2 -14195 2725.5

-3406

.9

2 6430.12 -13937 1543.23

-3344.

9

3 8303.63 -9972.3 1992.87

-2393.

3

4 7816.53 -11038 1875.97

-2649

.2

5 7816.53 -11038 1875.97

-2649.

2

6 8303.63 -9972.3 1992.87

-2393.

3

7 6430.12 -13937 1543.23

-3344.

9

8 11356.2 -14195 2725.5

-3406

.9

Page 58: bridge design using SAP

Girder Front View

Section

Page 59: bridge design using SAP

Selection of the section

Zx= 3406.9 in3

Mu= 14195kips.ft

Page 60: bridge design using SAP

SAP2000

Page 61: bridge design using SAP

SAP2000

Page 62: bridge design using SAP

Ultimate Moment

Frame Ultimate Moment (kips-ft)

Ultimate Moment (kips-ft)

Zx Zx

1 6272.05 8525.27 1505.29 2046.072 2734.62 6238.21 656.309 1497.173 3536.51 8382.43 848.763 2011.784 3325.38 8382.43 798.092 2011.785 3325.38 6238.21 798.092 1497.176 3536.51 8525.27 848.763 2046.077 2734.62 8525.27 656.309 2046.078 6272.05 8525.27 1505.29 2046.07

Page 63: bridge design using SAP

Selection of the section

Zx= 2046.07 in3

Mu= 8525.27 kips.ftSection :

Page 64: bridge design using SAP

Laterally unsupported length of the compression flange (Lb)

Page 65: bridge design using SAP

Number of Segments

Case (1) Lb ≤ Lp No LTB

Lb = 24m

Lateral Bracing

Section Lp (ft) Lp (m) Lr

(ft) Lr (m) Lb (m) Lb/Lp

Segments

W40x503 13.1 3.99390

2 55.3 16.85976 21.6 5.40824

4 6

Page 66: bridge design using SAP

Final Section

Page 67: bridge design using SAP

Girder Front View

SectionW40x503

Page 68: bridge design using SAP

Economical Issues Detailed Cost

Cost of the Concrete Bridge Deck:

• The volume of the deck = 840 m x 22m x 0.25m = 4620 m3

• The volume of the parapets = [9.86 KN/m x (840 m x 2)] / 25 KN/m

=662.6 m3

• Cost of (1 m3) of concrete = 1500 AED

• The cost for deck and parapets = 4620 m3 + 662.6 m3 x 1500 AED/

m3 = 4.6 x106AED.

Page 69: bridge design using SAP

Economical Issues Detailed Cost

Cost of the Concrete Bridge Girders:

• The cost of the girders =Area x Length of Girder x Cost x Number of

girder

=2.625m2 x840mx1500AED/m3 x8=3.31x106AEDCost of the Steel Bridge Girders:

• Cost of (1 ton) of steel = 8000 AED/ton

• Cost of steel girders = weight of whole girders x cost of (1 ton)

steel

= 734.28 ton x 8000 = 5874240 AED

Page 70: bridge design using SAP

Economical Issues Detailed Cost

Cost of the Concrete Bridge Pier-caps:• Area of one pier cap =1000 x 2250 =2.25 x 106 mm2 =2.25 m2 • Volume of one pier cap = 2.25 x 22 = 49.5 m3 • Total cost of pier caps = 49.5 x 1500 x 7 = 519750 AED

Page 71: bridge design using SAP

Economical Issues AlternativeComparison

Total cost of : (AED)

Concrete bridge superstructure 8,429,750

Steel bridge superstructure 10,993,990

Page 72: bridge design using SAP

Economical Issues AlternativeComparison

• The initial material cost of reinforced concrete is less than

the equivalent steel required for construction.

• Less long term cost of materials used for repairing or

replacing the defected parts, since concrete does not

require high maintenance and protection coatings,

compared to steel.

Page 73: bridge design using SAP

In general, concrete bridge has lower environmental effects than a steel bridge :

• less influenced by excessive wearing from the moist surrounding atmosphere, because of its low chemical-active nature with moisture.

• Does not require a lot of protection layers, which contain harmful chemicals and highly toxic materials such as paints and protection coats, which means less consumption of material and less harming of the surrounding environment.

• Steel reinforcing steel bars (rebars) used in the bridge could be utilized, after the end of the serviceability, where it could be cleaned and reused, or recycled.

Concrete Bridge Environmental Issues

Page 74: bridge design using SAP

Environmental Issues

• On the other hand, the possibility of reusing and recycling the

materials is higher for the steel bridge.

• This means more reducing of the waste and its negative

impact on the environment.

SteelBridge

Page 75: bridge design using SAP

Contemporary Issues

• One of the most important issues regarding the design of the

bridge is having a positive social impact.

• This is achieved by considering the appropriate bridge design.

• This means fewer blockages of the bridge, more flow-ability,

and more convenience and comfort for the users.

Social Impact

Page 76: bridge design using SAP

Gant chart

Page 77: bridge design using SAP

Thank You For Listening …


Recommended