Date post: | 22-Oct-2015 |
Category: |
Documents |
Upload: | jinshad-uppukoden |
View: | 21 times |
Download: | 0 times |
Conceptual Bridge Engineering Report
Swanton to St. Johnsbury STP LVRT (1) Lamoille Valley Rail Trail from Swanton to St. Johnsbury
Prepared for: Vermont Association of Snow Travelers Prepared by: Vanasse Hangen Brustlin, Inc. Date: September 30, 2010
Lamoille Valley Rail Trail
Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\CONCEPTUAL BRIDGE ENGINEERING REPORT FINAL.doc
TABLE OF CONTENTS
BACKGROUND ....................................................................................................................................... 1
FIELD INSPECTION ................................................................................................................................. 2
DESIGN STANDARDS ............................................................................................................................. 2
REHABILITATION AND REPLACEMENT CONCEPT ALTERNATIVES ......................................................... 3
CONSTRUCTION COST ESTIMATING ..................................................................................................... 4
ATTACHMENTS :
BRIDGES 13, 17D, A27, 31, 34, 48, 49, 68, 77, AND 83
INSPECTION FINDINGS AND REHABILITATION/REPLACMENT ALTERNATIVES
PHOTOGRAPHS
CONSTRUCTION COST ESTIMATE SUMMARY
CONCEPT PLAN DRAWING
MINOR REHABILITATION
BRIDGE LIST
TYPICAL BRIDGE SECTIONS
Lamoille Valley Rail Trail
Swanton – St. Johnsbury STP LVRT (1)
\57294.00\reports\Bridge Reports\CONCEPTUAL BRIDGE ENGINEERING REPORT.doc 1
INTRODUCTION
BACKGROUND
The Lamoille Valley Rail Trail (LVRT) project consists of the investigation, design and construction of
a shared use recreational trail along the St. Johnsbury and Lamoille County Railroad (St J&LC) Right-
of-Way, which is presently a rail-banked, state owned corridor as delineated in the State of
Vermont’s lease to the Vermont Association of Snow Travelers (VAST). The corridor extends from
Station 55+20 near Mt. Vernon Street in St. Johnsbury to Station 4976+93 near Robin Hood Drive in
Swanton; a distance of approximately 93.2 miles. The railroad line was constructed between 1867
and 1877, and was abandoned between 10 and 20 years ago. The track and ties were removed by
the state in 2005, but many structures remain within the Right-of-Way.
This project is funded by the FHWA and administered by the State of Vermont Agency of
Transportation (VTrans) through the Local Transportation Facilities (LTF) Program. VAST retained
Vanasse Hangen Brustlin, Inc. (VHB) in July of 2008 to initially prepare the conceptual trail design,
structural repair/rehabilitation/reconstruction conceptual designs, and to develop environmental
documentation, all of which are currently nearing completion.
The purpose of this engineering report is to present recommendations, conceptual designs and
construction cost estimates for the bridges involved in the LVRT project. There are 52 structures
which have been classified as “bridges” on the Lamoille Valley Rail Trail (LVRT) system 10 of which
require a relatively significant amount of rehabilitation and/or replacement work. The other
bridges generally require only minor repairs, new decks and/or new railings. Six of the ten bridge
locations no longer have a structure in place (substructure components remain in some cases),
either because the existing structures were washed out and/or have been intentionally removed.
The other four bridges requiring significant rehabilitation require substructure rehabilitation as well
as replacement of some of their structural components. None of these ten structures are eligible
for the National Historic Register, and some require Right-of-Way acquisition.
This report contains the following for the 10 bridges requiring significant rehabilitation:
• Summary of inspection findings and rehabilitation/replacement alternatives
• Representative photographs
• Summary of conceptual construction cost estimate
• Concept Design drawing, including a plan, longitudinal section and typical section
This report also includes a list of the bridges which require minor rehabilitation and alterations and
typical bridge sections are provided for select bridge types illustrating the typical work to be done.
Lamoille Valley Rail Trail
Swanton – St. Johnsbury STP LVRT (1)
\57294.00\reports\Bridge Reports\CONCEPTUAL BRIDGE ENGINEERING REPORT.doc 2
A cost estimate for the rehabilitation of these bridges is also included. Bridge types not shown in
the typical sections will be addressed during final design.
FIELD INSPECTION
A team of engineers and technicians visited each of the ten bridges which require significant
rehabilitation during the week of August 24, 2009, and performed a cursory inspection of each site
and any remaining structural components. The following tasks were performed during the bridge
inspections:
• Photo logged visible site conditions and structural components
• Observed general site conditions in order to assess critical approach, roadway, and channel
geometric constraints
• Recorded existing utilities and other structures which may be impacted during construction
• Measured approximate site and bridge geometry, limited to aspects critical to the
development of conceptual plans
• Visually observed and recorded general condition bridge components
While in the field the team also visited a sampling of bridges which did not require significant
rehabilitation to determine the scope of work required for most bridges to adapt the bridges to
trail bridges.
DESIGN STANDARDS
The following is a list of pertinent design specifications, standards and guidelines which were
utilized to develop the conceptual bridge designs, and which will be required for final bridge
design.
• AASHTO LRFD Bridge Design Specifications (2007 edition with 2009 interims)
• AASHTO Guide Specifications for Design of Pedestrian Bridges (1997)
(Note: LRFD Pedestrian Bridge Design Specifications (2009) will be used in final design)
• AASHTO Roadside Design Guide (2002)
• VAOT Structures Manual (2004)
• VAOT Local Transportation Facilities (LTF) Guidebook for Municipally Managed Projects
(2009)
• Vermont State Design Standards (1997)
• VAOT Standard Specifications for Construction (2006)
• Vermont Pedestrian and Bicycle Facility Planning and Design Manual (2002)
Lamoille Valley Rail Trail
Swanton – St. Johnsbury STP LVRT (1)
\57294.00\reports\Bridge Reports\CONCEPTUAL BRIDGE ENGINEERING REPORT.doc 3
• VAST Guide for the Development of Snow Mobile Trails (2009)
• FHWA/USFS Equestrian Design Guidebook for Trails, Trailheads and Campgrounds (2007)
Specific note should be made of the following decisions with regard to geometric and structural
design criteria for the project.
• AASHTO H-10 Truck and Pedestrian Loads in accordance with the above applicable
specifications were established as the design loading for nine of the ten bridges with the
exception of Bridge No. 13. The H-10 Truck loading was selected based on Section 5.3.10
of the Vermont Pedestrian and Bicycle Facility Planning and Design Manual, and is
appropriate for the anticipated configuration of LVRT trail system maintenance vehicles.
However, the HS-20 Truck was selected for the design loading on Bridge No. 13, due to the
anticipated need for heavier trucks to cross this structure during the construction of the
trail system.
• A 10 ft minimum rail-to-rail clear width was selected for all bridges. Section 5.3.10 of the
Vermont Pedestrian and Bicycle Facility Planning and Design Manual states that a 12 ft rail-
to-rail width is the preferred minimum; however, this section permits a minimum width
equal to the approach width of 8 ft, plus a 1 ft shy distance on each side in “rare
instances.” VAST obtained conditional concurrence from VTrans that the LVRT bridges
meet the criteria for “rare instances” listed in this section of the manual, primarily in light
of the fact that the bridges are in rural and/or wilderness settings and the cost to widen
the substructures and superstructures would be prohibitive
• Since the LVRT system will be used in the wintertime, a minimum bridge railing height of
4’-6” was established, and is in accordance with Section 5.3.6 of the Vermont Pedestrian
and Bicycle Facility Planning and Design Manual. In addition, 4’-6” is recognized as the
minimum railing height for equestrian use, as stated in Chapter 3 of the FHWA/USFS
Equestrian Design Guidebook for Trails, Trailheads and Campgrounds.
REHABILITATION AND REPLACEMENT CONCEPT ALTERNATIVES
The steel girders and beams at each of the four bridges requiring significant rehabilitation with
remaining superstructures (Bridge Nos. 31, 68, 77 and 83) were found to be in generally good
condition. Based on engineering judgment, it is evident that the most economical alternative for
these structures is to retain the existing girders and beams, replace timber ties as required, and
install longitudinal wood decking and new bridge railing. The condition of substructure
components for these bridges ranges from poor to good. In each case, the most cost effective
alternative for rehabilitation or replacement of these substructure components was readily
apparent based on engineering judgment and rehabilitation has been recommended.
Lamoille Valley Rail Trail
Swanton – St. Johnsbury STP LVRT (1)
\57294.00\reports\Bridge Reports\CONCEPTUAL BRIDGE ENGINEERING REPORT.doc 4
The six bridge locations for bridges requiring significant rehabilitation where the superstructures
no longer exist have partial or complete substructure components remaining at four locations
(Bridge Nos. 13, 34, 48 and 49), while two locations (Bridge Nos. 17D and A27) have no remaining
substructure components. The proposed length of each of these structures is based on site
constraints, remaining substructure locations, or a combination of both. A cost evaluation was
performed for the two shorter spans (Bridge Nos. 13 and 34), comparing a prefabricated steel truss
alternative to a rolled steel beam alternative. In both cases, the truss alternative proved to be
more economical. As the lengths of pedestrian bridges increase, the disparity between the truss
and beam alternatives becomes greater in favor of the truss alternative. Therefore, the
recommended superstructure alternatives for all six bridges are prefabricated steel truss
superstructures.
Eight of the bridges requiring significant rehabilitation cross over waterways, for which the
elevations of Ordinary High Water (OHW) were estimated in the field where possible, based on the
limits of vegetation on the stream banks (shown on the attached Concept Plans where applicable).
In addition, approximate Q100 elevations are shown on the plans where possible, based on
channel profiles from available FEMA Flood Insurance Studies (FIS). It is anticipated that only two
bridges requiring significant rehabilitation may require more detailed hydraulic analyses during
final design in order to determine the minimum “low chord” elevation (Bridge No. 48) or the
appropriate span length (Bridge No. 49).
Considerations and constraints that factor into recommended alternatives are presented in the
Inspection Findings and Rehabilitation/Replacement Alternatives sheet for each bridge. The
recommended structure alternative and the general scope of work for each of the bridges requiring
significant rehabilitation are presented in the respective Concept Plan drawings.
Bridges requiring minor rehabilitation need substructure or superstructure repairs, the installation
of longitudinal wood decking, new bridge railing, and select replacement of timber ties.
CONSTRUCTION COST ESTIMATING
Conceptual construction cost estimates were developed through a variety of means, as follows:
• The costs of prefabricated steel truss bridges delivered (not including erection) to each site
were obtained from steel truss bridge fabricators.
• Material and construction items included in the VTrans Standard Specifications for
Construction (e.g. reinforced cast-in-place concrete, excavation, timber, etc.) were
estimated using VTrans’ Estimator database of average unit prices, and were increased to
account for small quantities or construction and access difficulties.
Lamoille Valley Rail Trail
Swanton – St. Johnsbury STP LVRT (1)
\57294.00\reports\Bridge Reports\CONCEPTUAL BRIDGE ENGINEERING REPORT.doc 5
• Construction activities that are not included in the VTrans Standard Specifications (e.g.
erection of the prefabricated steel truss superstructures) were estimated based on labor
costs given in the Means Catalog, as well as the use of engineering judgment based upon
past project experience.
• A contingency of 25% was added to each bridge construction cost estimate to account for
minor construction items, unforeseen materials and construction effort, and contractor
mark-up on the prefabricated steel trusses.
Order-of-magnitude construction cost estimates broken down into their major components are
provided within each bridge section of this report, and are summarized below. The total estimated
conceptual construction cost for all ten bridges requiring significant rehabilitation is approximately
$2.1 million as shown below and in the attached cost estimates.
Bridge No. Feature Crossing Location Conceptual Construction Cost Estimate
13 Mount Vernon St. St. Johnsbury $181,000
17D Whiteman Brook Danville $200,000
A27 VT Route 15 Walden $263,000
31 Bailey-Hazen Rd. Walden $181,000
34 Stannard Mtn. Rd. Walden $106,000
48 Lamoille River Wolcott $231,000
49 Wild Branch Wolcott $356,000
68 Lamoille River Cambridge $306,000
77 Black Creek Bakersfield $119,000
83 Black Creek Fairfield $113,000
Total Cost $2,056,000
The 42 bridges requiring minor rehabilitation are estimated to have a construction cost of $500,000
plus a 25% contingency to total of $625,000. The total construction cost estimate for bridges on the
project is $2.7 million.
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 13 inspection 8‐24‐09.doc
Bridge 13
Inspection Findings: • Date: August 24, 2009 • Location
o Station: 55+27.3 o St. Johnsbury o Over Mt. Vernon Street o Map sheet 2
• Superstructure o No superstructure remains
• Substructure o Masonry Abutment No. 2 remains o Abutment No. 1 removed. To be designed in coordination with D&K and the Three Rivers Trail o Abutment No. 2 appears to have settled slightly in the past and appears stable and retains batter o Northwest wingwall of Abutment No. 2 appears to have settled slightly in the past but appears stable o Bridge seat and backwall of Abutment No. 2 in poor condition
• Approaches/Site o Available vertical clearance sufficient to meet standards o Site distance is limited on the road o Horizontal clearance is nonstandard at west abutment o A concrete box culvert runs from south to north, under Mt. Vernon Street and west abutment. Culvert is
clear of debris and in good condition. Some scour and spalling of headwall at inlet. Some scour was observed on culvert outlet headwall.
o Guardrail on Mt. Vernon Street runs into northwest wingwall of Abutment No. 2 with unsafe transition o Overhead electrical and telephone utilities need to be raised for clearance over bridge o Retaining wall (supporting Mt. Vernon St.) north of bridge paralleling drive in good condition
Rehabilitation/Replacement Concepts: • New stub abutment and mechanically stabilized earth (MSE) wall for Abutment No. 1 with new Three Rivers Trail
(D&K)
• Consider stabilizing northwest wingwall and Abutment No. 2 with tie‐backs
• Reuse Abutment No. 2, construct new concrete bridge seat and backwall, and repoint masonry
• Evaluated prefabricated truss vs. steel beam superstructure with approx. 70’ span (truss determined more cost‐effective)
• Realign guardrail at northwest wingwall of Abutment No. 2 (local responsibility?)
• Telephone lines require permanent relocation. Electrical utilities may require temporary relocation for erection of bridge
Resource ID: • Not eligible for National Historic Register
Available Information/Data: • DuBois & King Three Rivers Trail Preliminary Plans
• Existing Plans of culvert construction
• Railroad Val Plan
Comments: • Use HS‐20 design loading for construction access
• Detour length approximately 6.0 miles
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 13.doc
BRIDGE 13 – OVER MOUNT VERNON STREET
Looking South on Mount Vernon Street
Abutment No. 2
Looking North on Mount Vernon Street
Abutment No. 1 Proposed Location
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 13 cost estimate.doc
BRIDGE 13 – OVER MOUNT VERNON STREET
A conceptual, order‐of‐magnitude cost estimate for the Bridge 13 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are based on year 2010 construction pricing.
Rehabilitation of existing substructure $ 35,000.00 Construction of new substructure $ 10,000.00 Construction and installation of new superstructure $ 90,000.00 Traffic control $ 10,000.00
Miscellaneous and Contingencies (25%) $ 36,000.00
Total $ 181,000.00
The estimated cost does not include the following: • Construction inspection, administration, and engineering • Three Rivers Trail Construction (MSE wall including excavation and backfill at
Abutment 2) • Potential tie‐backs for Abutment 1 (most likely not necessary)
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 17D inspection 8‐24‐09.doc
Bridge 17D
Inspection Findings: • Date: August 24, 2009
• Location o Station 314+53 o Danville o Over Whiteman Brook o Map sheet 12
• Superstructure o No superstructure remains
• Substructure o No substructure remains
• Approaches/Site o Steep washout of embankments o Approximately 83’ clear opening and 23’ deep (trail grade to stream invert) o Existing slopes East: 1:1, West: 1.2:1 o Heavy debris jamming channel up and down stream o Northeast, northwest, and southwest approach embankments have steep banks o Channel has poor alignment on approach from southwest o Stream flood elevations far below trail grade, based on existing channel geometry and FIRM
Rehabilitation/Replacement Concepts: • Recommend laying back abutment slopes 1.5:1 with heavy stone fill
• 1.5:1 slopes result in approximate 100’ superstructure. Prefabricated steel truss most cost‐effective alternative
Resource ID: • Not eligible for National Historic Register
Available Information/Data: • No FIS available – 1975 FIRM available
• Railroad Val Plan
Comments: • VAST Individual Bridge Feature sheet recommends a bridge which is removable if further erosion occurs
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 17D.doc
BRIDGE 17D – OVER WHITEMAN BROOK
East Slope
East Slope and Whiteman Brook
West Slope
Looking North Downstream
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 17D cost estimate.doc
BRIDGE 17D – OVER WHITEMAN BROOK
A conceptual, order‐of‐magnitude cost estimate for the Bridge 17D reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are based on year 2010 construction pricing.
Earthwork $ 40,000.00 Construction of new substructures $ 20,000.00 Construction and installation of new superstructure $ 100,000.00 Miscellaneous and Contingencies (25%) $ 40,000.00
Total $ 200,000.00
The estimated cost does not include the following:
• Construction inspection, administration, and engineering
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge A27 inspection 8‐24‐09.doc
Bridge A27
Inspection Findings: • Date: August 24, 2009 • Location
o Station 1029+23 o Walden o Over VT RT 15 o Map Sheet 36
• Superstructure o No superstructure remains
• Substructure o No substructure remains
• Approaches/Site o Existing RR ROW & VT RT 15 alignments require skewed bridge alignment to minimize ROW & slope
impacts, and for trail approach alignment to meet minimum groomer turning radius o Roadway clearance approximately 15’ below trail grade at south approach o South approach is relatively flat and north approach is sloped for several hundred feet before
meeting existing trail alignment o Speed limit is not posted (assumed 50 mph regulatory) o VT RT 15 is classified as minor arterial, based on online Vermont State Highway Map, with 2800 AADT
in Danville
Rehabilitation/Replacement Concepts: • Location of Abutment No. 2 should be at edge of required clear zone to minimize ROW taking and to
accommodate VAST groomer turning radius (see comments below), which requires full height abutment
• Location of Abutment No. 1 should be at edge of required clear zone to minimize slope impacts, easements, and to accommodate VAST groomer turning radius (see comments below)
• Prefabricated steel truss bridge span of 91’ +/‐ required to meet above geometric constraints
Resource ID: • Not eligible for National Historic Register
• ROW acquisition required (see comments below)
• Minor increases in sound levels to one residence to the west of the existing corridor
Available Information/Data: • ROW plans from prior VT RT 15 construction
• Railroad Val Plan Comments:
• Survey required to determine optimum location of bridge and ROW requirements
• Required clear zone to face of abutments for assumed design speed of 55 mph = 24’ (reference AASHTO Roadside Design Guide and VT State Standards)
• Confirm adequate sight distance with proposed Abutment No. 1 location in final design
• Assume minimum turning radius for VAST groomer = 40’
• Location and extent of proposed ROW taking and slope easements require discussion with VAST and VTrans
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge A27.doc
BRIDGE A27 – OVER VERMONT ROUTE 15
Looking North from South Embankment
Looking South from North Embankment
Looking South along Former Railroad Alignment
Looking North along Former Railroad Alignment
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge A27 cost estimate.doc
BRIDGE A27 – OVER VERMONT ROUTE 15
A conceptual, order‐of‐magnitude cost estimate for the Bridge A27 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are based on year 2010 construction pricing.
Earthwork $ 35,000.00 Construction of new substructures $ 70,000.00 Construction and installation of new superstructure $ 95,000.00 Traffic Control $ 10,000.00 Miscellaneous and Contingencies (25%) $ 53,000.00
Total $ 263,000.00
The estimated cost does not include the following:
• Construction inspection, administration, and engineering • ROW acquisition
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 31 inspection 8‐25‐09.doc
Bridge 31
Inspection Findings: • Date: August 25, 2009
• Location o Station 1232+78 o Walden o Over Bailey‐Hazen Road o Map sheet 44
• Superstructure o Rolled steel beam superstructure in good condition o Ties, deck, and railing significantly deteriorated ‐ in need of replacement
• Substructure o Abutments consist of timber pile bents and timber pile caps in fair condition with timber lagging
backwalls o Abutment No. 2 timber backwall in poor condition o Abutment No. 1 in fair condition below pile bent cap. Backwall above pile bent cap severely
deteriorated, allowing approach material to fall onto bridge seat o Piers consist of timber pile bents on concrete footings in fair condition
• Approaches/Site o Vertical clearance approximately 13’ over Bailey‐Hazen Road o Culvert runs from northeast of bridge under Ward Hill Road, then under north pier, then under
adjacent drive on northwest corner o Clear width of Bailey‐Hazen road is 21’ o Slopes under end spans are approximately 3:2 on north and 2:1 south
Rehabilitation/Replacement Concepts: • Reuse existing steel superstructure
• Additional horizontal and vertical clearance requested by Town; replace existing abutments, remove existing piers and raise existing superstructure
• Existing beams determined to have sufficient capacity to span entire bridge length
• New concrete abutments/bridge seats
• New decking and railing
• Fill and grade approaches to match new superstructure elevation
Resource ID: • Not eligible for National Historic Register
Available Information/Data: • Existing Steel Framing Plans
• Railroad Val Plan
Comments: • Detour approximately 5.0 miles
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 31.doc
BRIDGE 31 – OVER BAILEY‐HAZEN ROAD
Looking South on Bailey‐Hazen Road
South Pier to be Removed
Bridge Deck from South Approach
Abutment No. 2
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 31 cost estimate.doc
BRIDGE 31 – OVER BAILEY‐HAZEN ROAD
A conceptual, order‐of‐magnitude cost estimate for the Bridge 31 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and based on year 2010 construction pricing.
Earthwork and removal or existing substructures $ 50,000.00 Construction of new substructures $ 65,000.00 New deck and railing $ 20,000.00 Traffic Control $ 10,000.00 Miscellaneous Contingencies (25%) $ 36,000.00
Total $ 181,000.00
The estimated cost does not include the following:
• Construction inspection, administration, and engineering
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 34 inspection 8‐25‐09.doc
Bridge 34
Inspection Findings: • Date: August 25, 2009
• Location o Station 1421+65 o Walden o Over Stannard Mountain Road o Map Sheet 52
• Superstructure o No superstructure remaining
• Substructure o Both abutments are still in place o Abutment No. 2 bridge seat and backwall in poor condition, concrete scaling near bottom of
abutment o Abutment No. 1 has some scour under footing no more than 2 ft. and bridge seat in fair condition
• Approaches/Site o Roadway vertical clearance is less than 12’ from bridge seat elevations. Roadway also has a grade
from east to center of bridge of approximately 3% o Roadway masonry curb and retaining wall has one missing block which may have been intentionally
removed for roadway drainage. Some scour on north side o Horizontal clearance and horizontal site distance nonstandard o Span between existing backwalls 47’
Rehabilitation/Replacement Concepts: • Reuse abutments with new bridge seats and backwalls
• Repair spalling of abutments
• New prefabricated truss superstructure due to vertical clearance requirements
Resource ID: • Not eligible for National Historic Register
Available Information/Data: • Existing plans for bridge prior to removal
• Railroad Val Plan
Comments: • According to VAST, a small insurance settlement may be available to help pay for this structure • Detour approximately 6.0 miles
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 34.doc
BRIDGE 34 – OVER STANNARD MOUNTAIN ROAD
Looking South on Stannard Mountain Road
Abutment No. 1
Abutment No. 2
Looking North on Stannard Mountain Road
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 34 cost estimate updated.doc
BRIDGE 34 – OVER STANNARD MOUNTAIN ROAD
A conceptual, order‐of‐magnitude cost estimate for the Bridge 34 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are based on year 2010 construction pricing.
Rehabilitation of existing substructure $ 35,000.00 Construction and installation of new superstructure $ 40,000.00 Traffic Control $ 10,000.00 Miscellaneous and Contingencies (25%) $ 21,000.00
Total $ 106,000.00
The estimated cost does not include the following: • Construction inspection, administration, and engineering
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 48 inspection 8‐25‐09.doc
Bridge 48
Inspection Findings: • Date: August 25, 2009
• Location o Station 2183+54 o Wolcott o Over Lamoille River o Map sheet 81
• Superstructure o No superstructure remaining
• Substructure o Both abutments are still in place and in good condition, but both require clearing and removal of
brush o Abutment No. 2 has tree growing out of north side o Both abutments are concrete on masonry on ledge o Abutment No. 1 has small trees growing between masonry blocks but in good condition
• Approaches/Site o Abutment No. 2 access from adjacent property owners land (McArthur) o Abutment No. 1 is remote access from School Street or by boat from Abutment No. 2 o Span approximately 130’ o FIS Q100 approximately at existing bridge seat elevation o 2000 FIS Q100 WSE profile shows 1967 reconstruction (new girders and lowered bridge seats)
Rehabilitation/Replacement Concepts: • Reuse existing substructure with minor repairs and build seats up for Q100+1 desired freeboard
• New prefab truss superstructure based on span length
• Remove brush and trees from existing abutments
Resource ID: • Not eligible for National Historic Register
Available Information/Data: • 2000 FIS (FIRM with cross sections and floodway boundaries shown)
• Railroad Val plan
• Existing plans (prior to bridge removal)
Comments: • VAST lease states VTrans has responsibility for this bridge.
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 48.doc
BRIDGE 48 – OVER LAMOILLE RIVER
Abutment No. 1
Looking Downstream from Abutment No. 2
Abutment No. 2
Looking Upstream from Abutment No. 2
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 48 cost estimate updated.doc
BRIDGE 48 – OVER LAMOILLE RIVER
A conceptual, order‐of‐magnitude cost estimate for the Bridge 48 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are based on year 2010 construction pricing.
Rehabilitation of existing substructure $ 35,000.00 Construction and installation of new superstructure $ 150,000.00 Miscellaneous and Contingencies (25%) $ 46,000.00
Total $ 231,000.00
The estimated cost does not include the following:
• Construction inspection, administration, and engineering
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 49 inspection 8‐25‐09.doc
Bridge 49
Inspection Findings: • Date: August 25, 2009
• Location o Station 2249+26 o Wolcott o Over Wild River Branch o Map sheet 83
• Superstructure o No superstructure remaining
• Substructure o Abutment No. 2 removed and remnants of Abutment No. 1 still exists (not salvageable)
• Approaches/Site o ANR Stream Alterations Engineer requested 160’ span, which is shown for initial proposed concept o Floodplain restoration accomplished by VANR (after FEMA FIS) o Q100 5‐10’ below trail grade (more survey required)
Rehabilitation/Replacement Concepts: • New single span prefabricated truss due to required span length
• New abutments
Resource ID: • Not eligible for National Historic Register
Available Information/Data: • 2000 FIS (showing cross sections and flood boundaries)
• Railroad Val Plan
Comments:
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 49.doc
BRIDGE 49 – OVER WILD BRANCH
Abutment No. 1
Looking Upstream from Abutment No. 2 Site
Abutment No. 2 Proposed Site
Looking Downstream from Abutment No. 2 Site
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 49 cost estimate updated.doc
BRIDGE 49 – OVER WILD BRACH
A conceptual, order‐of‐magnitude cost estimate for the Bridge 49 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are base on year 2010 construction pricing.
Earthwork $ 10,000.00 Construction of new substructures $ 70,000.00 Construction and installation of new superstructure $ 205,000.00 Miscellaneous and Contingencies (25%) $ 71,000.00
Total $ 356,000.00
The estimated cost does not include the following:
• Construction inspection, administration, and engineering
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 68 inspection 8‐26‐09.doc
Bridge 68 Inspection Findings:
• Date: August 26, 2009
• Location o Station 3381+05 o Cambridge o Over Lamoille River o Map sheet 126
• Superstructure o Existing 5 spans, approximately 246’ long o 4 different girder types
Spans 1A and 1B rolled beam 30” deep Span 2 riveted plate girder 77” deep Span 3 riveted plate girder 103” deep Span 4 riveted plate girder 62” deep
o Steel in good condition Previous E&K inspection noted heavy corrosion at floor beam top flange and stringer‐floor
beam connections on Span 3 o Deck and railing in poor condition
• Substructure o Abutment No. 1 adequate condition for 10 year life o Abutment No. 1 has crack in south wingwall o Abutment No. 2 in good condition o Pier 1B timber piles in poor condition. Missing piles and 60‐100% loss on multiple piles o Pier 2 has significant debris accumulation o Pier 3 timber piles in poor condition
• Approaches/Site o Trail access by foot from south end (too overgrown for vehicles) o Q100 approximately 10’ below deepest girder – 1982 FIS
Rehabilitation/Replacement Concepts: • Reuse existing steel superstructure
• Minor abutment rehabilitation
• Remove Pier 1A. Span 1A and 1B continuous rolled beam determined to have sufficient capacity
• Replace Piers 1B and 3
• Repoint Pier 2 masonry and remove debris
• Install Pier protection
• New decking and railing
• Compare cost of Pier 3 replacement vs. cost of Pier 3 elimination and single span replacing Spans 3 and 4. Reuse of existing superstructure with Pier 3 replacement determined most cost‐effective
Resource ID: • Existing floodplain encroachment
• Not eligible for National Historic Register
(con’t)
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 68 inspection 8‐26‐09.doc
Available Information/Data:
• 1982 FIS (cross sections, flood boundaries, floodway map)
• Railroad Val Plan
• Existing plans of Spans 1A and 1B
Comments: • Follow up in‐depth inspection for development of design plans should include in‐depth steel inspection
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 68.doc
BRIDGE 68 – OVER LAMOILLE RIVER
Looking West at Pier 2 and Pier 3
Pier 1A
Abutment No. 1
Pier 1B
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 68 cost estimate updated.doc
BRIDGE 68 – OVER LAMOILLE RIVER
A conceptual, order‐of‐magnitude cost estimate for the bridge 68 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are based on year 2010 construction pricing.
Rehabilitation and removal of existing substructure $ 50,000.00 Construction of new substructure $ 95,000.00 New deck and railing $ 100,000.00 Miscellaneous and Contingencies (25%) $ 61,000.00
Total $ 306,000.00
The estimated cost does not include the following:
• Construction inspection, administration, and engineering
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 77 inspection 8‐26‐09.doc
BRIDGE 77 – OVER BLACK CREEK
Inspection Findings: • Date: August 26, 2009
• Location o Station 3829+75 o Bakersfield o Over Black Creek o Map sheet 143
• Superstructure o Steel salvaged from another structure in good condition o Decking in poor condition o Railing not present
• Substructure o Abutment No. 2: 6 back piles checked and hollow sounding, 4 interior front piles in good condition,
and 2 exterior front piles questionable o Abutment No. 1 piles good condition, but pile cap in poor condition o Timber lagging at Abutment No. 1 deteriorated, and condition at north abutment not determined
(requires coring)
• Approaches/Site o Bridge in middle of two pastures o Barbwire and electric fence present on all corners of bridge
Rehabilitation/Replacement Alternative: • Reuse existing steel superstructure
• Replace both timber pile bents with single steel H pile bent at north abutment
• New decking and railing and approach guardrail
• Replace pile cap and timber lagging at both abutments
Resource ID: • Not eligible for National Historic Registry
• Existing floodplain encroachment (according to 1985 FIRM – no FIS done)
Available Information/Data: • 1985 FIRM (no FIS available)
• Railroad Val Plan
Comments: • Corings of south abutment piles and north abutment lagging required
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 77.doc
BRIDGE 77 – OVER BLACK CREEK
Abutment No. 1
Abutment No. 2
Abutment No. 2 and Superstructure
Bridge Decking from North Approach
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 77 cost estimate.doc
BRIDGE 77 – OVER BLACK CREEK
A conceptual, order‐of‐magnitude cost estimate for the Bridge 77 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are based on year 2010 construction pricing.
Earthwork $ 10,000.00 Rehabilitation of existing substructures $ 40,000.00 Construction of new substructures $ 25,000.00 New deck and railing $ 20,000.00 Miscellaneous and Contingencies (25%) $ 24,000.00
Total $ 119,000.00
The estimated cost does not include the following: • Construction inspection, administration, and engineering
INSPECTION FINDINGS AND REHABILITATION/REPLACEMENT ALTERNATIVES January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Summary Sheets\Bridge 83 inspection 8‐26‐09.doc
Bridge 83
Inspection Findings: • Date: August 26, 2009
• Location o Station 3946+18 o Fairfield o Over Black Creek o Map sheet 147
• Superstructure o Steel in good condition o Two spans ‐ south span appears to have been salvaged from another bridge o Deck in poor condition (open deck with missing ties) o No railing present
• Substructure o Abutment No. 2 concrete in good condition o Pier is timber pile bent made up of 3 rows of 6; 11 piles > 60% section loss o Abutment No. 1 timber cribbing backwall in good condition with some tree and shrub growth, and
timber pile bents in good condition
• Approaches/Site o Floodplain includes overbank under south span
Rehabilitation/Replacement Alternatives: • Reuse existing steel superstructure
• Replace pier at midspan
• New deck and railing
Resource ID: • Not eligible for National Historic Register
• Existing floodplain encroachment (According to 1985 FIRM – no FIS done)
Additional Information/Data: • 1985 FIRM (no FIS available)
• Railroad Val Plan
Comments:
PHOTOGRAPHS Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\reports\Bridge Reports\report photos\bridge 83.doc
BRIDGE 83 – OVER BLACK CREEK
Span No. 2
Abutment No. 1 Timber Cribbing
Existing Timber Pile Pier
Abutment No. 1 Timber Piles
ORDER‐OF‐MAGNITUDE CONSTRUCTION COST ESTIMATE January 15, 2010 Lamoille Valley Rail Trail Swanton – St. Johnsbury STP LVRT (1)
\\Vtdata\Projects\57294.00\tech\Bridge Cost Estimates\bridge 83 cost estimate updated.doc
BRIDGE 83 – OVER BLACK CREEK
A conceptual, order‐of‐magnitude cost estimate for the Bridge 83 reconstruction is provided below. All costs are rounded to reflect the order‐of‐magnitude level of the estimate, and are based on year 2010 construction pricing.
Construction of new substructures $ 40,000.00 New deck and railing $ 50,000.00 Miscellaneous and Contingencies (25%) $ 23,000.00
Total $ 113,000.00
The estimated cost does not include the following: • Construction inspection, administration, and engineering
Bridges Requiring Minor Rehabilitation and Alterations
Lamoille Valley Rail Trail
Swanton – St. Johnsbury STP LVRT (1)
Structure
IDStation Bridge Type
Feature
Crossing
Structure
IDStation Bridge Type
Feature
Crossing
16L 257.51 Steel Truss VT 2B 55 2562.01Steel Through-
TrussLamoille River
17 288.58 Steel I-Beam Trestle Rd 56 2631.11 Steel I-BeamNeedless Eye
Rd.
18 385.4 Steel I-Beam None 57 2686.88 ConcreteCenterville
Brook
27 865.26Steel I-Beam, Pile
BentJoes Brook 59 2871.96
Steel Through-
TrussLamoille River
28 1044.71Steel I-Beam, Pile
BentWet-2008-143 63 3090.65
Steel Through-
PlateSmith Brook
29 1161.73 Stone Arch Morrill Brook 66 3169.22 Arch Pipe Wet-2008-386
35 1446.64Steel Beams,
Wood PilingLamoille River 67 3178.94 Boiler Section Wet-2008-389
36 1523.74 Steel I-Beam Greensboro Bk 67Q 3321.25 Wood Stringer 2008-TB260
38 1728.48 Steel Deck Plate Lamoille River 70 3606 Steel I-Beam Black Creek
40 1778.14Steel Through-
PlateLamoille River 71 3613.3 Steel Deck Plate Black Creek
41 1849.58Steel Through-
PlateLamoille River 73 3632.53
Steel I-Beam, Pile
BentBlack Creek
42 1938.77 Concrete 2008-TB149 76 3755.4Steel I-Beam, Pile
BentBlack Creek
F:\57294.00\reports\Bridge Reports\minor bridge list
Bent
43 1983.14 Concrete 2008-TB151 80 3886.15 Arch Pipe Black Creek
44 1990.73 Concrete Kates Brook 81 3891.69 Concrete 2008-TB279
45 2037.16Steel I-
Beam/Covered
Bridge
Lamoille River 82 3923.66 Stone Arch 2008-TB285
46 2066.12 Steel I-Beam Currier Brook 85 3966.18 Steel Deck Plate Elm Brook
47 2133.72Steel Through-
TrussLamoille River 87 4097.46
Steel I-Beam, Pile
BentFairfield River
51 2277.71 Steel I-Beam 2008-SC172 88 4151.53Steel I-Beam, Pile
BentBlack Creek
52 2310.88Steel Through-
TrussLamoille River 90 4260.76 Stone Arch 2008-TB303
53 2363.41 Steel I-BeamElmore Pond
Brook93 4415.51
Steel Through-
Truss
Mississquoi
River
54 2465 Stone Arch 2008-TB192 95 4465.71Steel I-Beam, Pile
BentMcgowan Brook
F:\57294.00\reports\Bridge Reports\minor bridge list