Date post: | 02-Jun-2018 |
Category: |
Documents |
Upload: | nay-win-shein |
View: | 214 times |
Download: | 0 times |
of 47
8/11/2019 BridgeWorks
1/47
MINISTRY OF CONSTRUCTION
PUBLIC WORKS
N LYSIS O F R TES
FOR
BRIDGE WORKS
GOVERNMENT OF TH E REPUBLIC OF THE UNION OF MY NM R
SECOND EDITION JUNE 2 13
8/11/2019 BridgeWorks
2/47
CONTENTS
SH NO
1O
2.0
3.0
4.0
5.0
6.0
NAME OF SUB HEAD
BRIDGES
SUB HEADS
Foundation W ork
P.C Girder
Steel Truss
Steel Plate Girder
Suspension and Cablestayed Bridge
Survey
Miscellaneous Notes
PAGE NO
8/11/2019 BridgeWorks
3/47
Standard Data for Working Out Rates Per Unit Quantity oflte m s of Work
ForemanCarpenter 1 st Grade)Carpenter 2nd Grade)
Worker
SrNo.
1
2.
3.
Particularsof Materials and Labour
X IX. RIDGESoundation orks
Labour For Driving 250 mm) Diameter TimberPiles inordinary Soil With 500 kg drop hammerfrom pulley winch and local trestle and manuallyoperated).Penetration average 6 m.Labour
PlantsPile driving frame 1)No
Sundries
Labour For Driving 250 mm)Diameter TimberPiles inordinary Soil With pile driving machine).Penetrationaverage 6 m.Labour
Operator
ForemanCarpenter I st Grade)Carpenter 2nd Grade)
WorkerFor Operation
H.S.DGrease
PlantsPile driving frame 1)No
Sundries
Labour for Pile Driving reinforced cement con-crete pile 350 x 350 mm x 12000 mm) inordinary soil with 12m dieselhammer).Penetrationaverage 12 m.Labour
ForemanPile driving machine operator
Pile driving machine AsstCrane operator
Worker
Unit
Man-DayMan-DayMan-DayMan-Day
HourL.S
Man-Day
Man-DayMan-DayMan-DayMan-Day
litre
kg
Hour
L.S
Man-DayMan-Day
Man-DayMan-DayMan-Day
Quantity
0 3
0 5
0 5
3
4
0 3
0 3
0 5
0.53
3
0.1
2.7
0 3
0 3
0 30 3
6
Remarks
Cost of Timber piles
accordingto varyingdia;
with all necessary fittings
is to be includedin the
main estimate.
Cost of Timber piles
accordingto varyingdia;
with all necessaryfittingsis to be included in the
main estimate.
8/11/2019 BridgeWorks
4/47
Stan dard Da ta for Working Out Rates Per Unit Quantity of Items of Work contd.
Particulars of Materials and Labour
001s Required12m)rail line trollies for transport of precast
bile.One crane for loading unloading erecting
and pitching of precast pile.Pile driving machine (1) No
;or OperationH.S.D for Pile Driving Machine
H.S.D for CraneEngine Oil
Sundries
.abour for Pile Driving reinforced cem ent con-rete pile (350 mmx 350 mm x 12000 mm n~rdinary oil Using drop hammerwith winch~perated y m achine).Penetration Average 12m ..abour
ForemanOperator
Workerdachine
Pile driving machine (1)No:or Operation
Diesel OilGrease OilSundries
Making of Stand Pipe rnrn thk; 12mm thk;
(800 to 1650 mm 0 ) (For 1 Sqm)Steel fixer
Worker
Driving Stand PipeDriving of Stand Pipe1350mm 0,1650mmwith Vibro Hamm er for 1200mm ,1500mm Bored Pile. For 1 m)
Stand pipeSteel fixer
Head WorkerWorker
Unit
HourHour
Hour
Man-Da:Man-Da:
Man-Dti
Remarks
Cost for R.C Piles to be
calculated according to
the reqd.Size and included in the main estimate.
Cost for R.C Piles to be
calculated accord ing to
the reqd.Size and inclu
ded in the main estimate.
8/11/2019 BridgeWorks
5/47
Standard Data for Working Out Rates Per Unit Quantity of Items o Work contd.
SrNo.
b)
7.
a)
b)
Particulars of Materials and Labour
Electric HelperOperator /Machine Driver
SundriesH.S.D
Driving of Stand Pipel950rnrn 0,2650 mm0with Vibro Hamm er for1800mm 0,2500mm 0Bored Pile. For 1 m )
Stand PipeSteel Fixer
Head Worker
WorkerElectric Helper
Operator /Machine DriverSundriesH.S.D
Removing Stand PipeRemoving of Stand Pipe1350mm 0,1650mm 0
with Vibro Hamm er for 1200 mm0 ,
1500mm0 Bored Pile. For 1 m )Stand PipeSteel Fixer
Head WorkerWorker
Electric HelperOperator M ac hi ne Driver
Sundries
Removing of Stand Pipe 1950mm02650 mm 0 with Vibro Hammer for1800mm02500mm 0 Bored Pile. For 1m
Stand PipeSteel Fixer
Head WorkerWorker
Electric HelperOperator /Machine Driver
SundriesH.S.D
Unit
Man-DayMan-Day
L.Slitre
NoMan-DayMan-Day
Man-DayMan-DayMan-Day
L.Slitre
NoMan-DayMan-DayMan-DayMan-DayMan-Day
L S
NoMan-DayMan-DayMan-DayMan-DayMan-Day
L.Slitre
Quantity
0.50.7
11
3.20.50.7
0.70.52
0.50.5
0.70.72.50.50.5
Remarks
8/11/2019 BridgeWorks
6/47
Standard Data for Working Out Rates Per Unit Quantity of Items of Work contd
Head W orkerWorker
Operator M ach ine DriverSundries
H.S.D
SrNo.
8
9
10.
1.
Remarksarticulars of M aterials and Labour
Fitting of Drilling Equipment to dig Bored Pile.1200rnm0 , 1500rnm0 ,1800mm 0
2500rnm 0. For 1 time )Head Worker
WorkerOperator /Machine D river
SundriesH.S.D
Dismantling of Drilling Equipment.For 1 time )
Drilling of 800mm 0 mini Bored Pile.Ground, Ordinary Soil) For1 m )
Head WorkerForemanWorker
Operator M ac hi ne DriverWater Pump Helper
SundriesH.S.D
Machinary hair Charges
Drilling of 800 mm @m ini Bored Pile.Ground , Weathered Soft Rock) For 1 m )
Head WorkerForemanWorker
Operator M ac hin e DriverWater Pump Helper
Sundries
H.S.DMachinary hair Charges
Unit
Man-DayMan-DayMan-Day
L.Slitre
Man-DayMan-DayMan-Day
L.Slitre
Man-DayMan-DayMan-DayMan-DayMan-Day
L.SlitreL.S
Man-DayMan-DayMan-DayMan-DayMan-Day
L.S
litreL.S
Quantity
27
0.8
70.8
0.70.5
2
0.30.3
1.314
0.70.7
8/11/2019 BridgeWorks
7/47
5
Standard Data for Working Out Rates Per Unit Quan tity of Items of Work contd.
SrNo.12.
13.
14.
15
Particulars of M aterials and Labour
Drilling of 800 rnm mini Bored Pile.W ater, Ordinary Soil) For 1 m )
Head WorkerForemanWorker
Operator /Machine DriverWater Pump Helper
SundriesH.S.D
Drilling of 800mm mini B ored Pile.
Water , Weathered Soft Rock) For1 m )Head W orker
ForemanWorker
Operator /Machine DriverWater Pump Helper
SundriesH.S.D
Drilling of 1200mm Bored PileOrdinary Soil) For 1 m )
Head W orkerForemanWorker
Operator /Machine DriverWater Pump Helper
Sundries
H.S.D
Drilling o f 1500mm Bored PileOrdinary Soil) For 1 m )
Head W orkerForemanWorker
Operator Mac hin e DriverW ater Pump H elper
SundriesH.S.D
Unit
Man-DayMan-DayMan-DayMan-DayMan-Day
L. Slitre
Man-DayMan-DayMan-DayMan-DayMan-Day
L.Slitre
Man-DayMan-DayMan-DayMan-DayMan-Day
L.S
litre
Man-DayMan-DayMan-DayMan-DayMan-Day
L.Slitre
Quantity
0.8
0 6
2.5
0.4
0 4
1.5
1.2
5
0.8
0 8
10 5
3
0.5
0 3
1.2
0.5
3.5
0.5
0 4
Remarks
8/11/2019 BridgeWorks
8/47
Standard ata for Working Out Rates Per Unit uantity of Items of Work contd.
Quantity
1 40 8
4 3
0 7
0 5
1 5
0 8
4 5
0 8
0 5
1 5
0 8
4 8
0 8
0 5
1 3
0 5
3 5
0 5
0 4
Unit
Man-DayMan-DayMan-DayMan-DayMan-Day
L.Slitre
Man-DayMan-DayMan-DayMan-DayMan-Day
L.Slitre
Man-DayMan-DayMan-DayMan-DayMan-Day
L.S
litre
Man-DayMan-DayMan-DayMan-Day
Man-DayL.Slitre
SrNo.16
17
18
19
RemarksParticulars of Materials and Labour
Drilling of 1500mm R.C.D Bored PileOrdinary Soil) For m )
Head WorkerForemanWorker
Operator M ac hin e DriverWater Pump Helper
SundriesH.S.D
Drilling of 1800mm , Bored PileOrdinary Soil) For m )
Head WorkerForemanWorker
Operator /Machine D riverWater Pump Helper
SundriesH.S.D
Drilling of 2500rnm , Bored PileOrdinary Soil) For 1 m )
Head WorkerForemanWorker
Operator /Machine DriverWater Pump H elper
Sundries
H.S.D
Drilling of 1200mm Bored Pile.Weathered Soft Rock Layer Only Based on Soil
Test Result ) For 1 m )Head Worker
ForemanWorker
Operator /Machine DriverWater Pump H elper
SundriesH.S.D
8/11/2019 BridgeWorks
9/47
Standard D ata for Working Out Rates Per Unit Quantiry of Items of W ork contd.
Particulars of Materials and Labour
lrilling of 1500mm Bored PileWeathered So ft Rock Layer Only Based on Soil
rest Result ) For 1 m )Head W orker
ForemanWorker
Operator Ma ch ine DriverW ater Pump Helper
SundriesH.S.D
lrilling of 1500rnrn R.C.D Bored PileWeathered soft rock L ayer only Based on soil
Testresult For mHead W orker
ForemanWorker
Operator Ma ch ine DriverW ater Pump Helper
SundriesH.S.D
lrilling of 1800m m Bored PileWeathered Soft Rock Layer Only Based on
Soil Test Result) For m )Head W orker
ForemanWorker
Operator /Machine DriverWater Pump Helper
SundriesH.S.D
Drilling of 2500m m Bored PileWeathered Soft Rock Layer Only based on
Soil Test Result ) For 1 m )Head W orker
ForemanWorker
Operator Ma ch ine Driver
Unit
Man-Da:Man-Da:Man-Da:
Man-Da:Man-Da:
L.Slitre
Man-D?Man-D?Man-D?Man-Da:
Remarks
8/11/2019 BridgeWorks
10/47
Standard Data for Working Out Rates Per Unit Quantity of hems of Work contd.
WorkerSundriesH.S.D
SrNo.
24.
25.
26
27.
28.
Particulars of Materials and Labour
Water Pump HelperSundries
H.S.D
Mixing of Betonite Solution. For 1 cum)WorkerSundriesH.S.D
After drilling Bored P ile and fitting tremie pipe topour concrete, Proving of Slime W ash with
Compressor, for cleaning to B ored hole.For 1 hole)
Hanging of Steel Cage for 800mm0,1000rnrn 0 ,1200mm to Bored Hole with C rane.For 12m length
Welding RodSteel Fixer
WorkerSundries
Hanging of Steel Cage for 1500mrn 0 ,1800 mm 0 ,2 5 0 0 mm to Bored Hole withCrane. For 12m length
Welding RodSteel Fixer
WorkerSundries
H.S.D
Pouring 1: ?4 3) Cem ent concrete by TremieMethod. 1 cum)
Head WorkerWorker
Operator /Machine DriverSundriesH.S.D
Unit
Man-DayL.S
litre
Man-DayL.Slitre
Man-DayL.Slitre
kgMan-DayMan-Day
L.S
kgMan-DayMan-Day
L.Slitre
Man-DayMan-DayMan-Day
L.Slitre
Quantity
0.7
0.8
-
2
8
0.50.80.1
Remarks
8/11/2019 BridgeWorks
11/47
Standard Data for Working Out Rates Per Unit Quantity of Items of Work contd.
Particulars of Materials and Labour
oining, D ismantling, Cleaning, Painting ofarth oil Grease of Trem ie Pipe to be ready.
For 1 m )Steel Fixer
HelperSundries
3reaking of Bored Pile Head. 1cum )Head Worker
Sundries
Well Foundation
Iiggingand sinking of 12 mrn spun pipeo get specifieddepth includingremoving soilmd water pumping. Ground, Ordinary soil)For 1 m)
WorkerCarpenter
Head WorkerOperator
Steel FixerSundries
Iigging and sinking of 12 mm spun pipeo get specified depth including removing soilmd water pum ping. Ground, Sand) For1 m)
WorkerCarpenter
Head WorkerOperator
Steel FixerSundries
Digging and sink ingof 12 mm spun pipeto get specified dep th including removing soilmd water pum ping. Ground , Weathered softrock) For 1 m)
WorkerCarpenter
Head Worker
Unit
vim-Dajvim Daj
Man-Da:Man-DqMan-Dq
L.S
Man-DqMan-Da,Man-Da
Remarks
8/11/2019 BridgeWorks
12/47
1
Standard ata for Working Out Rates Per Unit Quantity of Items of Work contd.
SrNo.
34.
35.
36.
37.
Particulars of Materials and Labour
OperatorSteel Fixer
Sundries
Diggingand sinkingof 1200mrn0spun pipeto get specifieddepth includingremoving soiland water pumping. Water, Ordinarysoil)For 1 m)
WorkerCarpenter
Head WorkerOperator
Steel FixerSundries
Digging and sinkingof 1200mm0spun pipeto get specifieddepth includingremoving soiland water pumping. Water, Sand) For 1 m)
Worker
CarpenterHead Worker
OperatorSteel FixerSundries
Digging and sinkingof 1200mm0spun pipeto get specifieddepth includingremoving soiland water pumping. Water, Weathered softrock) For 1 m)
WorkerCarpenter
Head WorkerOperator
Steel FixerSundries
Digging and sinkingof 2750mm0 cassionwellto get specifieddepth includingremoving soiland water pumping. Ground Ordinary soil)For 1 m)
Quantity
1.61.2
15.61.21.21
0.7
19.6
1.61.21.21
31.22.42.21.91.4
Unit
Man-DayMan-Day
L.S
Man-DayMan-DayMan-DayMan-DayMan-Day
L.S
Man-Day
Man-DayMan-DayMan-DayMan-Day
L.S
Man-DayMan-DayMan-DayMan-DayMan-Day
L,S
Remarks
8/11/2019 BridgeWorks
13/47
1 1
Standard Da ta for Working Out Rates Per Unit Quantity of Items of Work contd.
Quantity
2
63
0 5
10
3
6
6 5
10 5
3
2 5
78 8
0 6
12 5
3 8
7 5
8 1
11 3
13 1
3 8
4126
1
20
6
1213
18
Unit
Man-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-Day
L S
Man-DayMan-DayMan-DayMan-Day
Man-DayMan-DayMan-DayMan-DayMan-DayMan-Day
L S
Man-DayMan-DayMan-DayMan-DayMan-Day
Man-DayMan-DayMan-Day
SrNo.
38
39
Remarksarticularsof Materials and Labour
Head WorkerWorkerWelder
OperatorSteel FixerForeman
DiverHelperRigger
CarpenterSundries
Digging and sinkingof 2750mm0 cassion wellto get specifieddepth including removing soiland water pumping. Ground Sand)For 1 m)
Head WorkerWorkerWelder
OperatorSteel FixerForeman
DiverHelperRigger
CarpenterSundries
Digging and sinking of 2750rnm0 cassion wellto get specifieddepth including removing soiland water pumping. Ground, Weathered softrock) For 1 m)
Head WorkerWorkerWelder
OperatorSteel Fixer
ForemanDiverHelper
8/11/2019 BridgeWorks
14/47
12
Standard Data for Working Out Rates Per Unit Quantity of Items of Work contd.
Remarksr
No.
40.
41.
42.
Particularsof Materials and Labour
RiggerCarpenter
Sundries
Digging and sinking of 2750rnm0 cassion wellto get specifieddepth including removing soiland water pumping. Water Ordinary soil)
For 1 m)Head Worker
WorkerWelder
OperatorSteel FixerForeman
DiverHelperRigger
CarpenterSundries
Digging and sinking of 2750rnrn0 cassion wellto get specifieddepth including removing soiland water pumping. Water, Sand) For 1m
Head WorkerWorkerWelder
OperatorSteel FixerForeman
DiverHelperRigger
CarpenterSundries
Digging and sinking of 2750mm0 cassion well
to get specifieddepth including removingsoiland water pumping. Water, Weathered softrock) For 1 m)
Head Worker
Unit
Man-DayMan-Day
L.S
Man-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-Day
L.S
Man-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-DayMan-Day
L.S
Man-Day
Quantity
216
2.475.6
0.6
123.67.27.8
10.8
12.63.6
94.60.7
15
4.6
99.7
13.615.7
4.6
4.8
8/11/2019 BridgeWorks
15/47
3
Standard Data for Working Out Rates Per Unit Quantity of Items of Work contd.
echanic
orker
8/11/2019 BridgeWorks
16/47
Standard Data for Working Out Rates Per U nit Quan tity of Items of Work contd.
8/11/2019 BridgeWorks
17/47
5
Standard Da ta for Working Out Rates Per Unit Quantity of Items of Work contd.
SrNo.
4.
Particulars of Materials and Labour
Stressing for Post tension HT Wire to getcomplete strength 1 Tendon)
ErectorSteel Fixer
Operator Machine DriverMachine HelperElectric Helper
WorkerSundries
55 Plugging 1 : 1)Cem ent Concrete into the
Concrete cavity of the end-block. Girder 1 No)MasonWorkerSundries
56
58. ~ i x i n ~owering bar, jacking beam, hanger jack
Grouting high strength cement motor with Gro-uting machine to sheating pipe. Girder 1 No)
MechanicElectric Helper
Operator Machine D riverWorkerSundries
57.
ErectorWorker
Sundries
Fixing cycle trolley, launching rm and accesso-ries on the bailey girder. with crane and man)Including fixingbreak wedge and sway braces.1 pair)
ErectorWorkerSundries
Remarksnit
Man-DayMan-DayMan-DayMan-DayMan-DayMan-Day
L.S
Man-DayMan-Day
L.S
Man-DayMan-Day
Man-DayMan-Day
L.S
Man-DayMan-Day
L.S
Quantii
10.30.70.30.311
1
31
130
40
Man-Day 5Man-Day 35
L.S
8/11/2019 BridgeWorks
18/47
6
Standard Data for Working Out Rates Per U nit Quan tity ofItem s of W ork c ontd.
SrNo.59.
60.
61.
62.
63 .
64
Particulars of Materia ls and Labour
Side shifting P.C Girder from casting positionto Launghing position distancel m 1 time)
ErectorWorkerSundries
Making Jack up P.C Girder, timber crib.Tighting in hanging beam with steel cable ,removing crib, fixing to get right alignmentbetween two LaunchingArm 1 time)
Erector
CarpenterWorkerSundries
Pulling Steel cable from electric winch andfixing them top of the launchingArm. 1 time)
ErectorElectric Helper
Worker
Launching P.C Girder by electric winch.Launching 1 time)
MechanicElectric Helper
ErectorWorker
Making Jack Down Launched P.C Girderbracing strut not to fall down. 1 time)
ErectorCarpenterWorkerSundries
After making jack down dismantling launchingequipment from P.C Girder,Pushing Launching
rm
o the casting stagging. 1 time)ErectorMachine operator driver
Worker
Unit
Man-DayMan-Day
L.S
Man-Day
Man-DayMan-Day
L.S
Man-DayMan-DayMan-Day
Man-DayMan-DayMan-DayMan-Day
Man-DayMan-DayMan-Day
L.S
Man-DayMan-DayMan-Day
Quantity
520
2
5
2
13
4
2
20
4
4
4
2
Remarks
8/11/2019 BridgeWorks
19/47
SrJo.55
i6.
i7
58.
69
17
Slandard Data for Working Out Rates Per Unit Quantity of Items of Work contd.
Particulars of M aterials and Labour
Levelling and carving on the Cross Beam forfittingP C Girder,carving 1200mm x 254mmgrouting hole, fitting bearing plate. 1 sheet)
MasonErectorWorkerSundries
Fixing pretension frame with anchor bolt on theconcrete pretension bench according to therequired design. 10 Nos)
ErectorWorker
Putting H.T wire coil 3MT)to the Dispencerwith crane using man,fixing bolt nut.1 coil-3 ton)
ErectorWorkerSundries
Pulling H.T wire to D ispencer for requiredlength,cutting then with griding machine.60 Nos)
ErectorMechanic
Head WorkerWorker
Skill Electric)Sundries
Fixing repaired wires in p retension bench,anchorage frame systematically.26m 8 Nos)
ErectorHead Worker
WorkerSundries
18m 8 Nos)Erector
Unit
Aan-DajAan-DajAm-Daj
L.S
Aan-DajAan-Daj
Man-DaMan-DaMan-Da
L.S
Man-Da
Remarks
8/11/2019 BridgeWorks
20/47
Standard Data for Working Out Rates Per Unit Qu antig of Items of Work contd.
Erector
Remarksuantity
325
2
0.10.10.10.10.1
0.10.10.3
38321
Unit
Man-DayMan-Day
L.S
Man-Day
Man-DayMan-DayMan-DayMan-DayMan-Day
L.S
Man-DayMan-DayMan-Day
L S
Man-DayMan-DayMan-DayMan-DayMan-DayMan-Day
L S
SrNo.
70.
71.
72.
73.
74.
Particularsof Materialsand Labour
Head WorkerWorker
Sandries
Fixing end plate each end of the P.C Girdersystematically whille arrangingH.T wire.Girder 1 No)
Stressingfor pretensionH.t wire to get stressingforce3.45MPa. wire 1 No)
MechanicErector
Machine operatordriverWorker
Skill electric)Sundries
Stressingof 12mm r 13 rnm 7 strand wire
For No)Foreman
Steel FixerWorkerSundries
After fixing and checkingP.C wire and rein-forcement due to design, stressingH.T wire toget required design force and elongation.Wire 38 Nos)
ErectorWorker
Skill electric)Hard Worker
Operator Jack operator)Operator Hydraulicpump)
Sundries
Fixing accessorieson the P.C Girder as perdesign.a)Makingand fixinghook 2 points)
8/11/2019 BridgeWorks
21/47
9
Standard Data for Working Out Rates Per Unit Quantity of Items of Work contd
Remarksuantity
7
3
0.4
0.1
0.8
0.2
3
Unit
Man-DayL S
Man-Day
Man-DayL.S
Man-DayL.S
Man-DayL.S
Man-DayL.S
Man-DayL.S
Man-Day
SrNo,
75
76
77.
78.
79.
Particularsof Materials and Labour
ErectorSundries
@)Makingand fixing shoe plate 10 Points)Welder
c)fixingthrougt bolt nut 10 Nos)Erector
Sundries
Fixing of R.S.T Beam, H Beam, Angle,
M.S Flat Channel for casting bed only.For 10 kg)
Head WorkerSundries
Dismantlingof R.S.T Beam, H Beam, Angle,M.S Plate, M.S Flat Channel for casting bedonly. For 10 kg)
Head WorkerSundries
Fixing of L.S.T Par t , Bailey Part C.H Partssystem. ( For 10 kg)
Head WorkerSundries
Dismantlingof L.S.T Part , Bailey Part C.H
Parts system. For 10 kg)Head Worker
Sundries
Steel Truss
Labour for Launching of R.S.JS. over bridgesup ports Using two pulleys and winch fromthe other side) 5No x 13000rnrnx 610mrn x190mm)at 43.l)kg per RFT.Total Weight = 9.3 MTons)
LabourBridge Foreman
8/11/2019 BridgeWorks
22/47
2
Standard Data for Working Out Rates er Unit Quantity of Items o f W ork contd.
Total Kit oneOne hammer
Coir rope 25mm 61m)25000 Kg Jacks 2)No
Bridge Foreman
WorkerSundries
8/11/2019 BridgeWorks
23/47
Standard D ata for Working Out Rates Per Unit Quan tity of Items of W ork contd
Quantity
20150
1150
Unit
L S
Man-DayMan-DayMan-Day
L S
SrNo.
83.
Remarksarticulars of Materials and Labour
Tools RequiredTotal Kit one
One hammerCoir rope 25mrn 61m)
4000 Kg Hand Winch 2)NoBailey Roller 6)No
Jumper 10)NoWire Rope 16mm 228m)
One local JIBDouble pulley 2)NoSingle pulley 1)No
50000 kg Jacks 2)NoSundries
b) Labour for assemblingand launchingC.H.bridge 6.5m Road way)bolts and nuts for allsteel works complete 48m) span double depth.Total Weight 150 MTons) By Crane)
LabourBridge ForemanSkilled Worker
Unskilled WorkerTools Required
Total Kit oneOne hammer
Coir rope 25mm 61m)4000 Kg Hand Winch 2)No
Bailey Roller 6)No
Jumper 10)NoWire Rope 16mm 228m)
One local JIBDouble pulley 2)NoSingle pulley 1)No
50000 kg Jacks 2)NoSundries
Labour for assemblingand German bridge3.35m Road way) on scaffolding and lowering
down on supports or launching 18m)span.Total Weight 17.87 MTons)
8/11/2019 BridgeWorks
24/47
Standard Data for Working ut Rates Per Unit Quantity of Items of Work contd.
Bridge Forem an
Worker
Bridge ForemanSkilled workers
Unskilled workers
SrNo.
84.
85.
Particularsof Materialsand Labour
Labour
Tools RequiredBailey Jacks 2 NoBailey rollers 7 No
One spannerOne hammer
Sundries
Labour for assembling ofR.P.T bridgeonscaffoldingincluding rivettingand loweringdown on supports complete 30m).Span and5m) road way.Total Weight 64.2 MTons)
Labour
Tools Required4000 Kg hand winch
Wire rope 12rnm 457m)Wire rope 16mm 457m)Coir rope 25mm 152m)
ServiceboltsDouble pulley 2)NoSinglepulley 1)No
One BellowDollys 2)No
Rivetting guns 2)NoOne compressorwith 2)No. Hose pipe 152m)
Local JIB one No.One hammer
75000 Kg Jacks 2)NoSundries
Labour for assemblingand launchingof R.P.Tbridge after rivetting completefor all steelworks 3Om)span 5m) road way.Total Weight 64.2 MTons)
Unit
Man-Day
Man-Day
L.S
Man-DayMan-DayMan-Day
L.S
Quantity
8
80
30100420
Remarks
8/11/2019 BridgeWorks
25/47
3
Standard Datafor Working Out Rates Per Unit Quantity of Items of Work contd.
SrNo.
86.
87.
Particulars of Materials and Labour
LabourBridge Foreman
Skilled workersUnskilled workersTools Required
4000 Kg hand winchWire rope (12rnm 457m)Wire rope (16rnm 457m)Coir rope (25mm 152m)
Service boltsDouble pulley (2)No
Single pulley (1)NoOne BellowDollys (2)No
Rivetting guns (2)NoOne compressor with (2)No. H ose pipe (500 )
Local JIB one No.Bailey rollers (6)No
Jumpers (10)No75000 Kg Jacks (2)No
Sundries
Shifting Steel Truss and Bailey by Crane fromone place to ano ther (Including hooking ,removing, handling with man) (10 MTons)
ForemanHead Worker
WorkerSundries
Sorting arranging the steel truss systemati-cally, Laying out them for preassambling workssystematically. 10 MTons)
ForemanHead Worker
WorkerSundries
Unit
Man-Day
Man-DayMan-Day
L.S
Man-DayMan-Day
Man-DayL.S
Man-DayMan-DayMan-Day
L.S
Quantity
35
120400
11
5
114
Remarks
8/11/2019 BridgeWorks
26/47
Standard Da ta for Working Out Rates Per Unit Quantity ofltems of Work contd.
Steel FixerHead Worker
WorkerOperator /Machine Driver
Electric HelperSundries
Remarksuantity
2
1
20.50.5
2
1
14
10 5
40.5
0 8
0.53
0.5
Unit
Man-DayMan-DayMan-DayMan-DayMan-Day
L S
Man-DayMan-DayMan-DayMan-DayMan-Day
L.S
Man-DayMan-Day
Man-DayMan-DayMan-DayMan-Day
Man-DayMan-DayMan-DayMan-Day
SrNo.88.
89
90
Particulars of M aterialsand Labour
Checking the steel truss accord ing to the designfor preassembling works on the ground.
(1 000 kg)
(a) Erecting the preassembled steel truss frompier to pier with erection crane acco rding tothe design. (1000 kg)
Steel FixerHead Worker
WorkerOperator /Machine Driver
Electric HelperSundries
(b) Allowing 50 of the above expend iturefor dismentling.
(a) Installing Bo lts Nuts, Drift Pins Tigh-tenning according to the d esign while erectingsteel truss. (1000 Nos)
Steel FixerWorker
Tightening them with Electric Guns againbefore transfering the target place. (1000 Nos)
Steel FixerHead W orker
WorkerElectric Helper
(b) Removing Bolt Nu ts (1 000 Nos)Steel Fixer
Head WorkerWorker
Electric Helper
8/11/2019 BridgeWorks
27/47
5
Standard D ata for Working Out Rates Per Unit Quan tity of Items of Work contd.
SrNo.91.
92.
93
94.
Particularsof Materialsand Labour
Final Tightenningthe ready installed BoltsNuts accordingto theTightenningsequence( includingwith checkingthem whetherstandard or not ) 1000 Nos)
Steel FixerHead Worker
WorkerElectricHelper
Sundries
Checkinghigh tension Bolts Nuts with check
Wrench whether standard or not. 1 000 Nos)Steel fixerWorkerSundries
a)Fixingthe safetyNet to the upper lowersteel truss systematically. 100 m)
CarpenterHead Worker
WorkerSundries
b) Removing Safety nets from Steel trussSystemtically. 100 m)
CarpenterHead Worker
WorkerSundries
Fixing Sleeperon the top bottom Chordofthe Steel truss. 200 mm x 200 rnma) Carvingsleepers fixing on Top Chord.100 Nos)
CarpenterSundries
b) Drilling holes on the sleepers for hooking.
100 Nos)CarpenterSundries
Unit
Man-DayMan-DayMan-DayMan-Day
L S
Man-DayMan-Day
L.S
Man-DayMan-Day
Man-DayL.S
Man-DayMan-DayMan-Day
L.S
Man-DayL.S
Man-DayL.S
Quantity
216
1.5
1.5
4
6
50
23
25
4.5
2.4
Remarks
8/11/2019 BridgeWorks
28/47
Standard Da fa or Working Out Rates Per Unit Quantity of Items o f W ork contd.
rParticulars of Materials and Labour Unit Quantity Remarks
0
c) Shifting the sleepers within 30m with man
and arranging them Systemtically not more
than one time.) 100 Nos)Carpenter Man-Day 4
Sundries L.S -
d) Fixing the railway on the sleeper firmly on
the Top Chord of Installed steel truss.- fixing with the required G.Bolt, U.Bolt along
the rail length for UIS& DIS. 10 m)Steel Fixer Man-Day
Carpenter Man-Day 2
Head Worker Man-Day 1
Worker Man-Day 9
Operator /Machine Driver Man-Day 1
Electric Helper Man-Day 0.5
Sundries L.S
e) Fixing the railway on the the sleeper firmly
on the strainger of installed steel truss.fixing with the J.Bolt or Do g Sp ike for Up
Stream and Down S tream. 10 m)Steel Fixer Man-Day 1
Carpenter Man-Day 1
Head Worker Man-Day 1
Worker Man-Day 4 5
Sundries L.S
f) Disman tling the railway 50 of fixing)
95. Installing Erection Tower, Mast Crane Multi-purpose Crane on the Top Chord of the SteelTruss. 1000 kg)
a) With universal member
Steel Fixer Man-Day 5
Head Worker Man-Day 2
Worker Man-Day 13
Sundries L.S
8/11/2019 BridgeWorks
29/47
7
Standard Da ta for Working Out Rates Per Unit Quantity of Items of Work contd.
8/11/2019 BridgeWorks
30/47
Standard Data for Working ut Rates Per Unit Qu anti v of Items of Work contd.
Quantity
0.51
11
2020101002020
4
827
7
7
592
Unit
Man-DayMan-Day
Man-DayMan-Day
L.S
Man-DayMan-DayMan-DayMan-DayMan-DayMan-Day
L S
Man-Day
Man-DayMan-DayMan-DayMan-DayMan-Day
L.S
Man-DayMan-DayMan-Day
SrNo.
99
100.
Remarksarticulars of Materials and Labour
Steel FixerWorker
Operator /Machine DriverElectric Helper
Sundries
Shifting Erection Tower on the To p Chord fiomone span to another with winch, Pretension theSteel Cables Final tens ionwith 500 MT Jackand Checking Erection Tower. 1 Time)
ForemanSteel Fixer
Head WorkerWorker
Operator /Machine DriverElectric Helper
Sundries
While erecting steel truss fiom one Pier to
another for the required level, fixing with 100 MTon jack, 3001350 MT on jack,500 MTon jack,on the bearingof the piers.
After that, making jack up JackdownShifting horizontally longitudinallyOther components Work
a) 100 MTon Jack10 Nos per 1 Time)
Foreman
Steel FixerHead Worker
WorkerOperator /Mach ine Driver
Electric HelperSundries
b) 3001350 MTon Jack10 Nos per 1 Time)
ForemanSteel Fixer
Head Worker
8/11/2019 BridgeWorks
31/47
9
Standard Data for Working Out Rates Per Unit Quantity of Items of Work contd.
SrNo.
101.
102.
a)
b)
c)
103.
Particulars of Materials and Labour
WorkerOperator/Machine D river
Electric HelperSundries
c) 500 MTon Jack10 Nos per 1 Time)
ForemanSteel Fixer
Head WorkerWorker
Operator /Machine D riverElectric Helper
Sundries
Fixing of Bearing. 1000 kg)Steel Fixer
Head WorkerWorkerSundries
Cutting steel plate to get required size With gas)12mm thk: for 2500 mm
WelderOxygen gasPropane gas
16 mm to 20 rnm thk: for 2500 rnrnWelder
Oxygen gasPropane gas
25 mm to 30 rnrn thk: for 2500mm )Welder
Oxygen gasPropane gas
Welding work. one ply:)for 2500mm)
welding rod 5kglpkt)Welder
Unit
Man-DayMan-Day
Man-DayL.S
Man-DayMan-DayMan-DayMan-Day
Man-DayMan-Day
L.S
Man-DayMan-DayMan-Day
L.S
Man-Day
kgkg
Man-Day
kgkg
Man-Day
kgkg
PktMan-Day
Quantity
88
8
113
8.5
1010
229
14.51.5
1.5
51.5
26
1.5
0.21
Remarks
8/11/2019 BridgeWorks
32/47
Standard D ata for Working Out Rates er Unit Quanlily of Items of Work contd.
Remarks
Including Loading ,
Unloadtig and shifting
Quantio
2.53.3
1.5
0.8
111
0.1
Moving m ain cable coin
to cutting place by cran
Cleaning main cable
Levelling ground and
setting turn table for
cuttingmain cablewithwheel cutter chain
block to get specified
length.
Transferring cutted mai
cable
Unit
Man-DayMan-Day
L.S
Man-DayMan-Day
L. S
Man-DayMan-Day
L.S
Man-DayL.S
Man-DayL.S
Man-DayMan-DayMan-DayMan-Day
L S
;rJo.
04.
05.
06.
07.
,08.
109.
Particulars of Materials and Labour
Steel Plate GirderPreassembling of steel plate girder according
to design on the ground. 1000 kg)Skilled WorkerWorkerSundries
Fixing , nitial final tightenning of boltnuts and drip pins according to the design whileassembling steel plate girder . I000 Nos)
Skilled WorkerWorker
Sundries
Installation of preassembled steel plate girderby crane as per drawing from pier to p ier.1 000 kg)
Skilled WorkerWorkerSundries
Checking to final tightenned bolt nuts withchecking spanner whether standard or not.1000 Nos)
Skilled WorkerSundries
Placing bearing plateand fixing bolt nut.
Skilled WorkerSundries
Suspension and Cablestayed B ridgeCutting and cleaning main cable For 10m)
Skilled M anHead Worker
WorkerMachine D river/ Operator
Sundries
8/11/2019 BridgeWorks
33/47
Standa rd Data for Working ut Rates Per Unit Quantity ofl lems of Work confd.
SrNo.110.
111.
112.
113.
114.
Particulars of Materials and Labour
Taking out and cleaning running cable from
Cable Drum and placing them o n timber crib
For 1 0 m)
Skilled Man
Head Worker
Worker
Sundries
Fixing running cable on Winch Drum at
Up stream and Down stream For one winch)
Skilled Man
Head Worker
Sundries
Taking out and cleaning Pilot Cable from Cable
Drum and placing them on
timber Crib For 10 m)
Skilled Man
Head Worker
WorkerSundries
Fixing step by step steel wire rope Pilot C able
on each side of Anchor on high Level.
For lm)
Skilled Man
Head Worker
WorkerSundries
Fixing Travelling C age by safety belt on high
level of Tower with Pulley Travelly.
For 1 Cage)
Skilled Man
Helper for Skilled Man
Head WorkerElectrician
Sundries
Unit
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-DayMan-Day
Man-DayL.S
Man-Day
Man-Day
Man-DayL. S
Man-Day
Man-Day
Man-DayMan-Day
L.S
Quantity
0.1
0.1
0.1
3
4.5
0.30.2
0.4
0.3
0.2
0.1
13.5
7.5
1.50.8
Remarks
Including installationof
lock Bull Dog Grip
8/11/2019 BridgeWorks
34/47
Standard Data for Working Out Rates er nit Quantity of Items of Wo rk confd.
Alignment For one winch)
Skilled M anHelper for Skilled Man
Sundries
3rParticulars of Materials and Labour
qo.15. Fixing 5 Mton winch According Tower Anchor
Fixing Supporting Frame Anchor Plate system-tically according cable alignment behindAnchorage. For 1 Anchor Supporting Frame)
Skilled M anWelderWorkerSundries
After installation main cab le, dismantlingand cutting supporting Anchor F rame, extraAnchor Plate ( For 1 Anchor Supporting
Unit
Frame.)
Quantit
Skilled M anWelderWorkerSundries
Man-DayMan-Day
L.S
3
4.5
Man-DayMan-Day
Man-DayL.S
31.5
Man-DayMan-DayMan-Day
Welder
Operator of welding M /C
WorkerSundries
1
0.51.8
11 8. Fixing roller by welding o n high level of Towerwith safety belt. For 1 No)
Skilled M an
119. Making for Cable clam p systemmatically andmaking hole for Bolt Nut For Tower Tiltingwork. For Cable clamp1 set)
WelderHelper For Welder
Sundries
Man-Day
Man-DayMan-Day
L.S
0.5Man-DayMan-Day
Man-DayL.S
120. Fixing firmly Over lapping a t least 5MTon Chain
0.31.3
1.8
block, Steel Wire rope with Bull Dog Grip at
Remarks
Including timber support
and wedging according
inline of A nchor slab
Including temporary
welding work
8/11/2019 BridgeWorks
35/47
8/11/2019 BridgeWorks
36/47
Standard Data for Working Out Rates Per nit Quantity of Items of Work contd.
Head W orkerElectrician
Sundries
Head WorkerWorkerSundries
Remarks
Taking out cable from
Anc hor Plate of Ancho-
rageChecking Cable of Back
stay between Tow er and
Anchorage
Numbering cable by
layer and layer
Installation of M ain
Cable on high level over
water by life jacket and
safety belt
Joining heavy Cable
lamp to
Travelly by pulley and
chain block
Specified cable marking
on main cable
Doing difficulty on high
level of Main Cable
Fixing Suspender Rod
on main cab le with ing
shaft and safetypin
Transfering suspender
rod to working area
by Manpower
Quantity
14
34
0.30.1
0.4
7
2
0.5
Unit
Man-Day
Man-DayMan-Day
L.S
Man-DayMan-Day
L.S
Man-DayL.S
Man-Day
Man-DayMan-Day
L.S
SrNo.
125.
a)
b)
c)
126.
a)
Particulars of M aterials and Labour
Installation of C able Top Clamp.For Cable Clamp 1 set)
Skilled Man
Tightening Bolt Nut for one timeFor 10 Nos of Bolt)
Skilled ManElectricianSundries
Painting Enamel paint for cable Top Clam p onhigh level For 1 no of Top Clamp)
Skilled ManSundries
Installation Suspender RodFor Suspender Rod No)
Skilled an
8/11/2019 BridgeWorks
37/47
5
Standard Data for Working Out Rates Per Unit Quantity of Items o f W ork contd.
Skilled ManMechanic for GroutpumpElectrician
Head W orkerSundries
Remarksuantity
0.10.1
0.10.1
0.20.1
10.1
3 5
0.50.55
0.5
Unit
Man-DayMan-Day
L.S
Man-DayMan-Day
L.S
Man-DayMan-Day
L.S
Man-DayMan-Day
L.S
Man-DayMan-DayMan-DayMan-Day
L.S
Man-DayL.S
SrNo.
b)
c)
127.
128.
129.
130.
Particularsof Materialsand Labour
ThreadingSuspender U bolt ,painting grease,Checking Bolt Nut washer and SpecifingU Bolt marking
Skilled Ma nHead Worker
Sundries
PaintingEnamel paint for Suspenderrod bysafetybelt on high level
Skilled ManHead Worker
Sundries
AdjustingBack stayed for 1Om)Skilled Man
Head WorkerSundries
StressingMain Cable and SpecifingElongationwithin Anchor accordingspecified tension.For 1Om)
Skilled ManHead Worker
Sundries
GroutingCement motor for Cable Guide Tubewithin Anchor after stressing Main cable.For 1Om)
Releasingbinding cable Working length position
of Main Cable For Enclosing Blockafterstressing.
For 1 No of cable )Skilled Man
Sundries
8/11/2019 BridgeWorks
38/47
6
Standard Data for Working Out Rates Per Unit Quantity of Items of Work contd .
Skilled ManSundries
SrNo.131.
132.
133.
134.
135.
6
137.
Particularsof Materialsand Labour
Adjustingand cutting layer of cable toinstall Anchor Plate For Stressing.
For 1 No of cable)
Shiftingbailey or) Steel truss on ground forPreAssemblingwork. For 1000Kg)
Skilled ManHead Worker
Sundries
Preassemblingwork for bailey or) steel truss.For 1000Kg)
Skilled ManHead Worker
Sundries
Shiftingheavy bailey or) Steel Truss from
PreassembledYard to join cable car by CraneFor 1000Kg)
Skilled ManHead Worker
Sundries
Fixingpreassembledbailey or)Steel Truss onSuspenderRod of Main Cable.For 1000Kg)
Skilled ManHead Worker
Sundries
Fixing SafetyNet For 1m)Skilled Man
Sundries
RemovingsafetyNet For 1m)Skilled Man
Sundries
Unit
Man-DayL.S
Man-DayMan-Day
L.S
Man-DayMan-Day
L.
Man-DayMan-Day
L.S
Man-DayMan-Day
L.S
Man-DayL.S
Man-DayL.S
Quantity
0.1
1.51.5
50.5
0.8
7.5
10
0.5
0.2
Remarks
8/11/2019 BridgeWorks
39/47
7
Standard Data for Working Out Rates Per Unit Quantity ofItems of Work contd.
SrNo.138.
139.
140.
141.
142.
143.
144.
Particularsof Materials and Labour
Laying systematicallysmall Transon walk wayand Checking,Laying Decking BeamFor 1000 Kg)
Skilled ManSundries
Canying DeckingBeam and small Transondifficultyby man power on temporarywalkwayat high level of main bridge. For 1000Kg)
Skilled ManSundries
Puttingheavy Decking slab on main bridgeby crane For 1000Kg)
Skilled ManHead Worker
Sundries
Adjustingbailey or)Steel truss of main bridgeto get specifiedcamber by wing temporarycable and Cushion Block. For SuspenderHanger 1 Point)
Skilled ManSundries
JackingDown bailey or)Steel truss with rightalignmentto get final R.L by using 30 MTonJack Cushion Blockand M.S Plate. For one Pier)
Skilled ManSundries
Fixing Bearing Bolt to Bearing Mat and Baileyor)Steel truss Pin to Bearing Mat Baileyor)Steel truss. For one Pier)
Skilled ManSundries
Pouring High Strength Concrete to get requiredBearing Level For Bearing)
Skilled Man
Unit
Man-DayL.S
Man-DayL.S
Man-DayMan-Day
L.S
Man-DayL.S
Man-DayL.S
Man-Day
L.S
Man-Day
Quantity
9 5
2
0.81.3
3.5
13.5
12
Remarks
Include adjusting bottom
surface of Bearing Mat
to get specified R L
Including cushion
8/11/2019 BridgeWorks
40/47
8/11/2019 BridgeWorks
41/47
9
Standard Data for Working Out Rates Per Unit Quantity of Items of W ork contd.
Quantity
0.50.5
0.50.5
0 5
0.5
0.31
1
1
1
1
0.50.5
Unit
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
Man-Day
Man-Day
SrNo.152.
153.
154.
155.
156.
157.
158.
Remarksarticulars of M aterials and Labour
Reading and specifying the centre of the Boredpile when driving stand pipe from control point
by using theodolite. l Time)SurveyorHelper
Surveying and specifying concrete top level topour bored concrete. l Time)
SurveyorHelper
Checking Bored Pile position after pouringconcrete. 1 Time)
SurveyorHelper
Surveying and Chec king Bored Pile after pouringconcrete to know stable or unstable. 1 Time)
SurveyorHelper
Surveying and specifying Cap position ofAbutment or Pier. l Time)
Surveyor
Surveying and C hecking settlemen t of pier cap inwater. 1 Time)
Surveyor
Surveying and specifying Shaft position of Abu tment
159.
160.
or Pier. l Time)Surveyor
Surveying and spec ifling B earing position ofAbutment or Pier. 1 Time)
Surveyor
Specifling and Ch ecking Level tofix M.S Rod inPile Cap, Shaft Cross-beam. 1 Time)
SurveyorHelper
Man-Day
Man-Day
Man-DayMan-Day
8/11/2019 BridgeWorks
42/47
Standard Data for Working Out Rates Per Unit Quantity ofl tem s of W ork contd.
Particulars of Materials and Labour
Levelling Cap or) Shaft or) Cross Beam in theirform works before pouring concrete. 1 Time)
SurveyorHelper
Helper
162 Rechecking position of Pile or)C ap or) Shaft or)Cross Beam after concreting. 1 Time)
Surveyor
before pouring concrete for one pier. 1 Time)SurveyorHelper
163
Surveying Checking and specifying centre ofAbutment or) pier systematically. 1 Time)
SurveyorHelper
Surveying bearing hole d epth to get right depth
Surveying and Checking bottom ground of Pier inwater. 1 Time)
SurveyorHelper
Transfering and rechecking level M ark for specifiecplace from one bench Mark to another. 100 m)
Surveyor
Helper
Unit Quantity
Man-DayMan-Day
0.31
Man-Day
SurveyingEcho SoundingPier in water and waterlevel daily. 1 Time)
Surveyor
0 5
Man-Day 0 5
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
Man-Day
Man-Day
0 5
0 5
0 3
0 5
0 3
0 3
Man-Day
Remarks
0 5
Fixing bearing for one pier of main bridge or)Approach bridge Position or Grouting to ix bearinghole position Bearing.) 1 Time)Surveying Position
SurveyorHelper
Man-DajMan-Daj
8/11/2019 BridgeWorks
43/47
4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work contd.
Quantity
3
3
0.50.5
0.50.5
0.31
0.31
0.3
1
0.50.5
0.50.5
Unit
Man-Day
Man-Day
SrNo.
b)
169.
Remarksarticulars ofMaterialsand Labour
Recheckingposition.Surveyor
Helper
Fixing bearing for one pier of main bridge or)
a)
b)
170.
171.
a)
b)
172
173.
Approach bridge Positionor Groutingto ix bearinghole position Bearing.) 1 Time)Levelling
SurveyorHelper
RecheckinglevelSurveyorHelper
Surveyingand Rechecking 18m or)21m or)24m or)27m or)30m Girder for pouring concrete. 1 No)
SurveyorHelper
Surveyingfor erection of main truss to get specifiedlevel. 1 Time)
SurveyorHelper
Surveying Levelingand checkingfor erection ofmain truss to get specified level. 1 Time)
Surveyor
Helper
Surveyingand Checking Level for Laying Precastslab and finished level. 1 Time)
SurveyorHelper
Surveyingand specifjingCenter line for installationof Road Curb and Hand Rail. 1 Time)
SurveyorHelper
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
Man-Day
Man-Day
Man-DayMan-Day
Man-DayMan-Day
8/11/2019 BridgeWorks
44/47
Standard Data for Working Out Rates Per Unit Quantity ofItems of Work contd.
Road Curb and Hand Rail. 1 Time)
Surveyor
SrNo.174.
Helper
Particulars of Materials and Labour
Surveying and specifLing level for installation of
Man-DayMan-Day
Remarksnit
0.50.5
175.
176.
177.
178.
a)
@
179.
a)
Quantitj
0.5
0.5
0.3
0.3
0.50.5
0.50.5
0.50.5
Surveyingand specifling level for layingAC. l Time)SurveyorHelper
SurveyingOverlay, Road Curb, Hand Rail and AC
to get right alignment. 1 Time)SurveyorHelper
SurveyingPrecast Slab, Overlay, Road Curb,Hand Rail level. 1 Time)
SurveyorHelper
Surveyingposition of anywork before starting work
Excavationor Fixing Reinforcementand forrnwork
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
or Pouringconcreteor embeddedplate or Hand Railor Road Curb or P.C Girder or CollosionBarrier orDecking slab or Girder Overlayor AC or AnchorBox or Bored Pile or Stand Pipe or Keyline or CapSkirtingor Road or Drain or Box Culvert or SteelTruss or Pier Cap or shaft Cross-beam r Abutmentor RetainingWall or Rail Road or Vertical devia
tion.) 1 Time) SurveyorHelper
Man-DayMan-Day
Recheckingposition of anywork after working. l Time)SurveyorHelper
Man-DayMan-Day
Surveyingalignment Center Line)ofanyworkbefore
working. 1 Time)SurveyorHelper
Man-DayMan-Day
8/11/2019 BridgeWorks
45/47
4
Srandard Data for Working Out Rates er Unit Quantity oflte ms of Work contd
Quantity
0.50.5
0.50.5
0.50.5
0.50.5
0.50.3
0.50.3
0.50.5
0.51.5
4
Unitr
No.Remarksarticulars of Materials and Labour
b)
180.
a)
b)
181.
182
a)
b)
c)
183.
184.
Rechecking alignment Center Line)of anywork afterworking. 1 Time)
SurveyorHelper
Surveying and levelling anywork before working.1 Time)
SurveyorHelper
Man-DayMan-Day
Man-DayMan-Day
Rechecking level of anywork before working. l Time)SurveyorHelper
Surveying and checking settlement Main Bridge orApproach Bridge or Highway or Railway.) l Time)
SurveyorHelper
Man-DayMan-Day
Man-DayMan-Day
Checking for theodolite level and E.D.M instrumentwhich are used for surveying in bridge construction.Theodolite Calibration. 1 Time)
SurveyorHelper
Level Calib ration. 1 Time)SurveyorHelper
E.D.M Calibration. 1 Time)
SurveyorHelper
Determination o f Pier Position by E.D.M includingfinding distance between piers etc; other relevantor equivalent works. l Time)
SurveyorHelper
Level Net Survey Calculation Drawing. l Time)SurveyorHelper
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
Man-DayMan-Day
8/11/2019 BridgeWorks
46/47
44
Standard Dat afo r Working Out Rates Per Unit Quantity of Items of Work-contd.
SrNo.185.
a)
b)
c )
Particulars of Materials and Labour
Triangulation Net SurveyBasic Line Measurement(1 Time)
SurveyorHelper
Calculation Drawing. l Time)SurveyorHelper
Check Base Distance Measurement 1 Time)Surveyor
Helper
Unit
Man-DayMan-Day
Man-DayMan-Day
Man-Day
Man-Day
Quantity
4 5
24
0 5
0 5
Remarks
8/11/2019 BridgeWorks
47/47
45
Standa rd Data for Working Oui Rates Per Unit Quantity o f tems of Work contd.
SrNo.
1
Particulars of Materials and Labour
MISCELLANEOUS NOTES
For contractor s profit and overheadsTaxes afety charges managem ent etc.)
For Bridge M achinery WorkUse according to rateo analysis of MachanicalDepartment.)
Unit
L.S
L.S
Quantity
-
Remarks