+ All Categories
Home > Documents > BRIEF DESCRIPTION OF ON GOING PROJ (AS ON 17-04-2013) GE ... · 03-01-2013 02-07-2013 85% 53.51% Wk...

BRIEF DESCRIPTION OF ON GOING PROJ (AS ON 17-04-2013) GE ... · 03-01-2013 02-07-2013 85% 53.51% Wk...

Date post: 17-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
3
C:\Users\Jahir\Desktop\Web Dev - MES\MES WEB SITE-DW&CE (Army)\CMES (A) Savar\Brief description of on going projects\GE (Army) Jessore\Brief description of on going Proj.doc Page -1 - BRIEF DESCRIPTION OF ON GOING PROJ (AS ON 17-04-2013) GE (ARMY) JESSORE Ser Job No, Name or Works & Admin Sac Tk CA No & Name of firm Date of Comm Date of Compl Progress Physical Financial Photo Rmk (a) (b) (c) (d) (e) (f) (g) 1. Constr of SM Bk Complex with CH/DH (5 Storied with 5 Storied fdn) for 30 BIR at Jessore Cantt 2nd phase completed. Job No. 65 Res Bldg of 2006-2007 Constr of SM BK Ground floor & Ist floor (Partialy) with CH/DH (Ground floor) (Ist Ph). Tk= 539.00 Lac Tk. 1034.41 Lac ( As per RPE). CEA/77 of 2006-07 M/S Kanta Engrs (Pvt) Ltd. Tk=3,64,47,042.00 Tk=3,64,86,342.84(Rev) 25-6-2007 04-01-2011 23-09-2012 21-04-2014 89% 68.94% CEA/17 of 2012-13 M/S. Ali Traders Tk=22,30.235/90 27-112012 26-05-2013 40% - Job No-147 Res Bldg of 2010-11 Construction of CH/DH Ist floor & 2nd floor (partialy) (3rd ph). Tk= 202.00 Lac. CEA/177 of 2010-11 M/S Kanta Engrs (Pvt) Ltd. Tk=1,78,60,791.02 06-7-2011 05-10-2012 04-12-2013 69% 60.56% Wk is in progress. Job No-65/Res Bldg of 2012-13 Construction of SM BK Complex (5 Storied foundation with RCC cast in situ pile) with CH/DH incl internal/external services & furniture for Newly raised 30 BIR at Jessore Cantt (4th/Last phase). Tk=1088.06 lac. CEA/102 of 2012-13 M/S Kanta Engrs (Pvt) Ltd. Tk=8,91,37,638.88 20-02-2013 19-02-2014 35% 23.85% Wk is in progress. 2 Job No-06/Others of 2012-2013 Improvement/extension of ext water supply line for Pump house-03 at Polash Residential area , Jessore Cantt Tk= 100.00 Lac. CEA/40 of 2012-13 M/S Khan Enterprise. Tk=93,44,356.00 03-01-2013 02-07-2013 85% 53.51% Wk is in progress. 3 Job No-14/ Others Bldg & Structure of 2012-2013 Supply & Installation of 2 x Under Ground Fuel tank (45,000 Ltr Capacity) and 1 x Fuel Dispensing unit with ancillary works for BSD at Jessore Cantt . Tk= 70.00 Lac. CEA/37 of 2012-13 M/S Nipun Nirman. Tk=59,99,993/25 03-01-2013 02-07-2013 75% 62.33% Wk is in progress. 01 of 03
Transcript
Page 1: BRIEF DESCRIPTION OF ON GOING PROJ (AS ON 17-04-2013) GE ... · 03-01-2013 02-07-2013 85% 53.51% Wk is in progress. 3 Job No-14/ Others Bldg & Structure of 2012-2013 Supply & Installation

C:\Users\Jahir\Desktop\Web Dev - MES\MES WEB SITE-DW&CE (Army)\CMES (A) Savar\Brief description of on going projects\GE (Army) Jessore\Brief description of on going Proj.doc Page -1 -

BRIEF DESCRIPTION OF ON GOING PROJ (AS ON 17-04-2013) GE (ARMY) JESSORE

Ser Job No, Name or Works & Admin Sac Tk

CA No & Name of firm Date of Comm Date of Compl

Progress Physical Financial

Photo Rmk

(a) (b) (c) (d) (e) (f) (g) 1. Constr of SM Bk Complex with

CH/DH (5 Storied with 5 Storied fdn) for 30 BIR at Jessore Cantt

2nd phase completed.

Job No. 65 Res Bldg of 2006-2007 Constr of SM BK Ground floor & Ist floor (Partialy) with CH/DH (Ground floor) (Ist Ph). Tk= 539.00 Lac Tk. 1034.41 Lac ( As per RPE).

CEA/77 of 2006-07 M/S Kanta Engrs (Pvt) Ltd. Tk=3,64,47,042.00 Tk=3,64,86,342.84(Rev)

25-6-2007 04-01-2011 23-09-2012 21-04-2014

89% 68.94%

CEA/17 of 2012-13 M/S. Ali Traders Tk=22,30.235/90

27-112012 26-05-2013

40% -

Job No-147 Res Bldg of 2010-11 Construction of CH/DH Ist floor & 2nd floor (partialy) (3rd ph). Tk= 202.00 Lac.

CEA/177 of 2010-11 M/S Kanta Engrs (Pvt) Ltd. Tk=1,78,60,791.02

06-7-2011 05-10-2012 04-12-2013

69% 60.56%

Wk is in progress.

Job No-65/Res Bldg of 2012-13 Construction of SM BK Complex (5 Storied foundation with RCC cast in situ pile) with CH/DH incl internal/external services & furniture for Newly raised 30 BIR at Jessore Cantt (4th/Last phase). Tk=1088.06 lac.

CEA/102 of 2012-13 M/S Kanta Engrs (Pvt) Ltd. Tk=8,91,37,638.88

20-02-2013 19-02-2014

35% 23.85%

Wk is in progress.

2 Job No-06/Others of 2012-2013 Improvement/extension of ext water supply line for Pump house-03 at Polash Residential area , Jessore Cantt Tk= 100.00 Lac.

CEA/40 of 2012-13 M/S Khan Enterprise. Tk=93,44,356.00

03-01-2013 02-07-2013

85% 53.51%

Wk is in progress.

3 Job No-14/ Others Bldg & Structure of 2012-2013 Supply & Installation of 2 x Under Ground Fuel tank (45,000 Ltr Capacity) and 1 x Fuel Dispensing unit with ancillary works for BSD at Jessore Cantt . Tk= 70.00 Lac.

CEA/37 of 2012-13 M/S Nipun Nirman. Tk=59,99,993/25

03-01-2013 02-07-2013

75% 62.33%

Wk is in progress.

01 of 03

Page 2: BRIEF DESCRIPTION OF ON GOING PROJ (AS ON 17-04-2013) GE ... · 03-01-2013 02-07-2013 85% 53.51% Wk is in progress. 3 Job No-14/ Others Bldg & Structure of 2012-2013 Supply & Installation

C:\Users\Jahir\Desktop\Web Dev - MES\MES WEB SITE-DW&CE (Army)\CMES (A) Savar\Brief description of on going projects\GE (Army) Jessore\Brief description of on going Proj.doc Page -2 -

Ser Job No, Name or Works &

Admin Sac Tk CA No & Name of firm Date of Comm

Date of Compl Progress

Physical Financial

Photo Rmk

(a) (b) (c) (d) (e) (f) (g) 4 Job No-15/ Others Bldg & Structure

of 2012-2013 Construction of 1 x Cow shed and 1 x Calf shed incl ancillary works for Military farm at Jessore Cantt . Tk= 160.00 Lac

CEA/86 of 2012-13 M/S Saidur Rahman Tk=1,36,16,557/70

06-02-2013 05-11-2013

26% 19.50%

Wk is in progress

5

Job No-31/Others Bldg & Structure of 2012-2013 Supply & Installation of 1 x 350 x 150 mm dia deep tube well (PVC pipe) incl ancillary works for STC & S area at Jessore Cantt . Tk= 26.29 Lac.

CEA/56 of 2012-13 M/S Babul Khan & Co Tk=24,49,834.00

20-01-2013 19-07-2013

65% 41.61%

Wk is in progress

Main Boring Completed.

6 Job No-41/Abnormal Rep of 12-13 Supply/Replacement/Maint of Control Panel including all Accessories for existing 1 x Patient type lift of Bldg No. PT-60 CMH at Jessore Cantt . Tk= 10.65 Lac.

SCA/95 of 2012-13 M/S Aziz & Co Tk=9,94,780.00

06-03-2013 03-06-2013

100% 00%

Work completed

02 of 03

Page 3: BRIEF DESCRIPTION OF ON GOING PROJ (AS ON 17-04-2013) GE ... · 03-01-2013 02-07-2013 85% 53.51% Wk is in progress. 3 Job No-14/ Others Bldg & Structure of 2012-2013 Supply & Installation

C:\Users\Jahir\Desktop\Web Dev - MES\MES WEB SITE-DW&CE (Army)\CMES (A) Savar\Brief description of on going projects\GE (Army) Jessore\Brief description of on going Proj.doc Page -3 -

Ser Job No, Name or Works &

Admin Sac Tk CA No & Name of firm Date of Comm

Date of Compl Progress

Physical Financial

Photo Rmk

(a) (b) (c) (d) (e) (f) (g) 7. Job No-96/Res Bldg of 2012-2013

Construction of 1st, 2nd, 3rd, 4th & 5th floor and Remaining Wks of Grd floor and CH/DH with recreation room (2 Storied foundation) incl internal/external services and furniture for under construction of SM BK (6 Storied foundation) for 145 Fd WKSP Coy EME at Jessore Cantt (Last phase). Tk=500.00 lac.

- - -

NOA not yet received.

8.

Job No-97/Others Bldg & Structure of 2012-2013 Constr of 1 x Div Multipurpose Auditorium with Internal/ External services and Furniture for Sta HQ Jessore Cantt (3rd Ph) Tk=480.00 lac

CEA/213 of 2012-13 M/S Alom & Associates Tk=4,48,96,142/70

-

-

NOA received but Contract not yet received.

9 Job No-E in C/02 of 2012-2013(DPP Project) Repair/Maint/Renovation and Improvement of various Wks at Jhenidah cadet college, Jhenidah. Tk= 225.03 Lac.

E-IN-C/29 of 2012-13 M/S Hunain Enterprise. Tk=78,15,119/52

06-03-2013 05-12-2013

07% 00%

Wk is in progress

E-IN-C/33 of 2012-13 M/S Salim & Brothers Tk=1,29,84,883.00

12-02-2013 11-08-2014

15% 00%

Wk is in progress

MD SHAH ALI Major GE (Army) Jessore