+ All Categories
Home > Documents > Brief Status of LHC Experimental Vacuum Project

Brief Status of LHC Experimental Vacuum Project

Date post: 10-Feb-2016
Category:
Upload: tauret
View: 32 times
Download: 3 times
Share this document with a friend
Description:
Brief Status of LHC Experimental Vacuum Project. Ray Veness CERN TE/VSC. Contents. Overview of the upgrade project Project work packages Recent changes to the project ‘environment’ Key activities in the 2012 shutdown Key activities in the 2016 shutdown Diameters of central beampipes - PowerPoint PPT Presentation
Popular Tags:
11
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC
Transcript
Page 1: Brief Status of LHC Experimental Vacuum Project

Brief Status of LHC Experimental Vacuum Project

Ray VenessCERN TE/VSC

Page 2: Brief Status of LHC Experimental Vacuum Project

Contents

o Overview of the upgrade projecto Project work packageso Recent changes to the project ‘environment’o Key activities in the 2012 shutdowno Key activities in the 2016 shutdown

o Diameters of central beampipeso New requests from the experimentso New data on beampipe alignmento Current issues under discussion

o Conclusions

LHC Experimental Vacuum LHCC Nov'10- R.Veness

Page 3: Brief Status of LHC Experimental Vacuum Project

Project Work Packageso Timescale

o Agreed May 2010o Covers period 2010-2015o Some modifications will not be complete

by the end of this periodo Volume of work

o 3 new beryllium chamberso 11 other new vacuum chamberso 8 other vacuum technology

developmentso Access procedures in activated

environmentso Development, design, construction,

installation, commissioningo Integrated project resources

o 27.4 person-years staff (~4.5 people average full-time)

o 6.5 person-years of visitorso 5982 kCHF of installed hardware and

2590 kCHF of VSC project costsLHC Experimental Vacuum LHCC Nov'10- R.Veness

Page 4: Brief Status of LHC Experimental Vacuum Project

Recent Changes to Project Environment

o Project now operatingo We have recruited 1 staff engineer, 1 staff technician, 1

fellow and 1 technical student for the project between July and October 2010

o Vacuum technology development and procurement of components is in progress

o ‘White Paper’changes to LHC scheduleo CERN White Paper ‘Provisional Planning for the LHC and

Injectors for the Next Decade’ in August 2010o 2014 shutdown becomes 2016 and 2018 shutdown becomes 2020-21

o ATLAS and CMS new PIXEL layer installation delayed to 2016o ALICE replacement central beryllium pipe comes forward to

2016 [not yet in work packages]o LHCb new vertex detector in 2016 [not yet in work

packages]LHC Experimental Vacuum LHCC Nov'10- R.Veness

Page 5: Brief Status of LHC Experimental Vacuum Project

2012 Shutdown: ATLAS

o 4 new vacuum chamberso No change in envelope (beam aperture)o Replace stainless with aluminium for

reasons of:o Access and ALARA during interventionso Detector background

o Requires detector opening and removal of 6 vacuum chambers

LHC Experimental Vacuum LHCC Nov'10- R.Veness

Half-length of the ATLAS beam vacuum sector

Page 6: Brief Status of LHC Experimental Vacuum Project

2012 Shutdown: LHCbo Install 1 new chamber

and 2 new support systemso Install a replacement UX85/3

conical beryllium chambero Required due to varnished leaks

in the existing chambero No change to layout or material

o Install and position new ‘spider’ supports for the UX85/2 and UX85/3 chambers

o Re-optimised for lower-Z with material changed from aluminium to beryllium

o Requires removal of 3 vacuum chambers and their supports

LHC Experimental Vacuum LHCC Nov'10- R.Veness

Cross-section of LHCb experiment

View inside magnet showing chambers and spider supports

Page 7: Brief Status of LHC Experimental Vacuum Project

2016 Shutdown: ATLAS and CMS

o ATLAS and CMS consolidate PIXEL detectorso Add another layer of pixel

o IBL project in ATLAS and 4-layer PIXEL in CMSo Make room for the detector by reducing the

central beampipe diameter from 58 to (50mm)

o Beam aperture for current and Phase-I upgrade optics (as per 2009) were studied

o Implications for CERN TE-VSCo Design and production of 2 new beryllium

chambers and supportso Full opening of both experiments and

removal of all vacuum chambers (16 in total)o Complex retro-fit procedure inside existing

ATLAS detectoro Full procedures for interventions in a

radioactive detectorLHC Experimental Vacuum LHCC Nov'10- R.Veness

Installation of CMS beryllium

ATLAS beryllium pipe in the PIXEL

Page 8: Brief Status of LHC Experimental Vacuum Project

Renewed Discussions on Central Beampipe Diameters

o Situation upto summer 2010o Working towards a reduction from 58mm to 50mm diameter for

ATLAS and CMS in 2014o Aperture and machine protection were check OK by machine expertso We were awaiting final layouts in ‘Z’ to verify vacuum, impedance and

collimationo Request to study sub-40mm chamber for ALICE in 2018

o ALICE had stated that a 50mm chamber would not give enough space for a useful PIXEL upgrade

o Situation as of Autumn 2010o Request for sub-40mm diameter chamber for ALICE for 2016

o Working towards a decision on an acceptable diameter for the end of 2011o Request for sub-50mm diameter chamber for CMS for 2016o Request for sub-50mm diameter chamber for ATLAS for 2012

shutdowno ATLAS would like an ‘urgent’ spare chamber compatible with the IBL

LHC Experimental Vacuum LHCC Nov'10- R.Veness

Page 9: Brief Status of LHC Experimental Vacuum Project

New Information on Beampipe Alignment

LHC Experimental Vacuum LHCC Nov'10- R.Veness

M.Nessi (ATLAS) in LEB meeting of 4/11/10

W.Riegler (ALICE) in LEB meeting of 4/11/10

Data collected during the 2010 run has given new insight into the actual position of the beampipe on the interaction plane with respect to beam and detectors

Page 10: Brief Status of LHC Experimental Vacuum Project

Open Issueso ‘Tomography’ data from ALICE, ATLAS and CMS

show good correlation with the originally installed positions of the chambers, however there are still open questions:o High-β optics may not be compatible with 50mm or less

diametero ATLAS and CMS confirm they do not see the need for high-β after 2016o Is this an issue for an ATLAS ‘spare’ for the 2012 shutdown?

o Does the beampipe move relative to the beam over a longer period?

o Data still being collected by ATLAS et al.o Has there been any movement of central beampipes away from

the interaction plane?o eg. tomography would not show ‘rotation’ of the chambers

o Other issues: Vacuum (stability, pressures), impedance and heating, collimation check require the length of the smaller diameter section

o Formal approval via Engineering Change Request and presentation to LHC Machine Committee will be required

LHC Experimental Vacuum LHCC Nov'10- R.Veness

Page 11: Brief Status of LHC Experimental Vacuum Project

Conclusionso Consolidation and upgrade project

o Project is approved, personnel have been recruited and is now in progresso Work is progressing as planned for the 2012 shutdown changeso Recent changes to the LHC schedule and new requests from the experiments

mean that the work packages and associated resources must be revisedo Diameters of upgrade chambers for ALICE, ATLAS and CMS

o Reduction of beampipe diameter to 50 mm has been verified for post-2016 operation for aperture, machine protection, mechanics and survey

o Missing longitudinal layouts for verification of vacuum, impedance and collimationo Data from the experiments collected during the 2010 physics run are starting

to give useful feedback as to the relative positions of beam, beampipe and detectors

o This may yield some additional margin for reducing beampipe diameterso Spare beryllium chamber for ATLAS

o The request for a sub-50mm spare beryllium chamber to be ready in time for a 2012 LHC shutdown is extremely challenging, from both technical and logistical points of view

LHC Experimental Vacuum LHCC Nov'10- R.Veness


Recommended