+ All Categories
Home > Documents > BRIGADE MIXED USE DEVELOPMENT Brigade Residential...

BRIGADE MIXED USE DEVELOPMENT Brigade Residential...

Date post: 17-Apr-2020
Category:
Upload: others
View: 21 times
Download: 0 times
Share this document with a friend
37
Environment Clearance 1 | Page Address: 29 th & 30 th Floor, World Trade Centre, Brigade Gateway Campus, 26/1, Dr. Rajkumar Road, Malleswaram - Rajajinagar, Bengaluru - 560 055. Ph. 080-41379200, 9980141453 [email protected]; BRIGADE MIXED USE DEVELOPMENT At Sy. No. 171/1, 171/2, 171/3, 171/4, 172, 173/1, 173/2, 173/3, 183/2, 183/3, 183/6A, 183/6B, 183/7, 183/8, 183/9, 183/11 and 184/1(P) Varthur Village, Varthur Hobli, Bengaluru East Taluk, Bengaluru and Sy. No. 217/3, 227/1(P), 227/2, 227/3, 227/4, 228/1, 228/2, 229/1, 229/2, 229/3, 229/4, 229/5, 229/12, 230/1, 230/2, 230/3, 230/4, 270/1 and 270/3 of Gunjur Village, Varthur Hobli, Bengaluru East Taluk, Bengaluru Conceptual Plan, Form 1, Form 1A and Terms of Reference For Prior Environmental Clearance Project Proponent: M/s. Mysore Projects Private Limited Subsidiary of M/s. Brigade Enterprises Limited
Transcript

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 1 | P a g e

Address: 29th & 30th Floor, World Trade Centre, Brigade Gateway Campus, 26/1, Dr. Rajkumar Road, Malleswaram - Rajajinagar, Bengaluru - 560 055.

Ph. 080-41379200, 9980141453 [email protected];

BRIGADE MIXED USE DEVELOPMENT Brigade Residential Building

At Sy. No. 171/1, 171/2, 171/3, 171/4, 172, 173/1, 173/2, 173/3, 183/2,

183/3, 183/6A, 183/6B, 183/7, 183/8, 183/9, 183/11 and 184/1(P) Varthur Village, Varthur Hobli, Bengaluru East Taluk, Bengaluru and Sy. No. 217/3, 227/1(P), 227/2, 227/3, 227/4, 228/1, 228/2, 229/1, 229/2, 229/3, 229/4, 229/5, 229/12, 230/1, 230/2, 230/3, 230/4, 270/1 and

270/3 of Gunjur Village, Varthur Hobli, Bengaluru East Taluk, Bengaluru

Conceptual Plan, Form 1, Form 1A and Terms of Reference

For

Prior Environmental Clearance

Project Proponent: M/s. Mysore Projects Private Limited Subsidiary of M/s. Brigade Enterprises Limited

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 2 | P a g e

FOREWORD

Environmental Impact Assessment (EIA) is a planning tool generally accepted as an integral

component of sound decision-making. EIA is to give the environment its due place in the decision-

making process by clearly evaluating the environmental consequences of the proposed activity

before action is taken. Early identification and characterization of critical environmental impacts

allow the public and the government to form a view about the environmental acceptability of a

proposed developmental project and what conditions should apply to mitigate or reduce those risks

and impacts.

Environmental Impact Notification S.O.1533 (E), dt.14th September 2006, and amended thereafter,

issued under the provisions of Environment (Protection) Act 1986, has made it mandatory to obtain

prior environmental clearance for scheduled development projects. The notification has classified

projects under two categories 'A' & 'B'. Category ‘A’ projects (including expansion and modernization

of existing projects) require clearance from Ministry of Environment and Forest (MoEF), Govt. of

India (GoI) and for category B from State Environmental Impact Assessment Authority (SEIAA),

constituted by Government of India.

As per the above mentioned notification, it is mandatory to obtain environmental clearance if

construction projects falls under the below extract of the notification.

Project or Activity

Category with

threshold limit - B

Category

General Conditions

8 Building /Construction projects/Area Development projects and Townships

8(a)

Building and

Construction

Projects+++

>20000Sq.m. and

<1,50,000Sq.m. of

built-up area #

Any project or activity specified in Category 'B' will

be treated as Category 'A' if located in whole or in

part within 10 km from the boundary of: (i)

Protected areas notified under the Wildlife

(Protection) Act, 1972; (ii) Critically polluted areas

as identified by the Central Pollution Control Board

from time to time; (iii) Eco-sensitive areas as

notified under section 3 of the Environment

(Protection) Act, 1986, such as, Mahabaleswar,

Panchangi, Matheran, Pachmarhi, Dahanu, Doon

Valley and (iv) inter-state boundaries and

8(b)

Township and

Area

Development

Projects.

Covering an area

≥50ha and or built-

up area

≥1,50,000Sq.m ++

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 3 | P a g e

international boundaries.

Provided that the requirement regarding distance

of 10km of the inter-state boundaries can be

reduced or completely done away with by an

agreement between the respective states or U.Ts

sharing the common boundary in the case the

activity does not fall within 10 kilometers of the

areas mentioned at item (i), (ii) and (iii) above

#(built up area for covered construction; in the case of facilities open to the sky, it will be the activity

area)

++All projects under Item 8(b) shall be appraised as Category B1

+++All projects under item 8 (a) shall be appraised as Category B2

According to schedule category: 8 B, Sub-category B2 (Construction), M/s Brigade Enterprises

Limited GPA Holder for M/s. Cornerstone Bay East Developers Private Limited proposes to construct

“Brigade Mixed Use Development” at Sy. No. 171/1, 171/2, 171/3, 171/4, 172, 173/1, 173/2, 173/3,

183/2, 183/3, 183/6A, 183/6B, 183/7, 183/8, 183/9, 183/11 and 184/1(P) Varthur Village, Varthur

Hobli, Bengaluru East Taluk, Bengaluru and Sy. No. 217/3, 227/1(P), 227/2, 227/3, 227/4, 228/1,

228/2, 229/1, 229/2, 229/3, 229/4, 229/5, 229/12, 230/1, 230/2, 230/3, 230/4, 270/1 and 270/3 of

Gunjur Village, Varthur Hobli, Bengaluru East Taluk, Bengaluru with total Built-up area of

13,00,598Sq.m.

Brigade Group has entered into a Joint Venture agreement with M/s. Cornerstone Bay East

Developers Private Limited for development of land parcel covering an area of 3,09,665.97Sq.m (76

Acres 20.81 Guntas) located along the Varthur Sarjapur Main Road, Near Varthur. The application in

Form 1, Terms of Reference and Form 1A elaborates the proposed project and the plan to carry out

detailed Environment Impact Assessment (EIA).

The Terms of References are proposed by in-house team of Environmental Engineers, Planners,

Architects, Hydro-geologist, Ecologist, Traffic Management Experts, etc. The in-house EIA team is

headed by Mr. Anand Kumar A, having experience of over 12 years in Environmental Impact

Assessment, Sewage Handling & Treatment, Waste Handing & Treatment, Air Pollution Prevention &

Control, Sustainable Development, Green Buildings, etc.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 4 | P a g e

Mr. Anand Kumar A. has obtained an interim stay order against the MoEF Office Memorandum

mandating NABET accredited consultant organizations to carryout Environmental Impact

Assessment & Environmental Management Plan from the Honorable High Court of Bangalore. He

however, is a NABET accredited EIA co-ordinator (The Organization as a whole could not qualify for

accreditation). The team involved in designing Environmental Management Plan is vastly

experienced and are experts in their field of expertise.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 5 | P a g e

FORM 1

(I) Basic Information

Sl.

No. Item Details

1. Name of the project/s Brigade Mixed Use Development

2. Sl. No. in the schedule 8 (Construction) B1

3.

Proposed capacity / area / length / tonnage

to be handled / command area/lease

area/number of wells to be drilled

Total Built-up area = 13,00,598 Sq.m

4. New/Expansion/Modernization New

5. Existing Capacity/Area etc. Not Applicable

6. Category of Project i.e. ‘A’ or ‘B’ B1 (Construction > 1,50,000Sq.m of Built-up

area)

7. Does it attract the general condition? If

yes, please specify. No

8. Does it attract the specific condition? If yes,

please specify. No

9.

Location

Plot/Survey/Khatha No.

Village

Tehsil

District

State

Sy. No. 171/1, 171/2, 171/3, 171/4, 172, 173/1,

173/2, 173/3, 183/2, 183/3, 183/6A, 183/6B,

183/7, 183/8, 183/9, 183/11 and 184/1(P)

Varthur Village, Varthur Hobli, Bengaluru East

Taluk, Bengaluru and Sy. No. 217/3, 227/1(P),

227/2, 227/3, 227/4, 228/1, 228/2, 229/1,

229/2, 229/3, 229/4, 229/5, 229/12, 230/1,

230/2, 230/3, 230/4, 270/1 and 270/3 of Gunjur

Village, Varthur Hobli, Bengaluru East Taluk,

Bengaluru

10. Nearest railway station/airport along with

distance in kms.

Nearest Railway Station: Whitefield Railway

Station - 10Km

Carmelaram Railway Station - 6Km

Bengaluru City Railway Station: 25 km

Airport: 52 km (Kempegowda International

Airport)

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 6 | P a g e

11. Nearest Town, city, District Headquarters

along with distance in kms.

Bengaluru City - 25 km

Whitefield Town – 4 km

12.

Village Panchayats, Zilla Parishad,

Municipal corporation, Local body

complete postal addresses with telephone

nos. to be given)

Varthur Village & Gunjur Village, Varthur Hobli,

Bengaluru East, BBMP.

13. Name of the applicant M/s. Mysore Projects Private Limited

14. Registered Address

29th & 30th Floor, World Trade Center, Brigade

Gateway Campus, 26/1, Dr. Rajkumar Road,

Malleswaram - Rajajinagar, Bengaluru-560 055

15.

Address for correspondence: M/s. Mysore Projects Private Limited

Name Roshin Mathew

Designation (Owner/Partner/CEO) Director

Address

29th & 30th Floor, World Trade Center, Brigade

Gateway Campus, 26/1, Dr. Rajkumar

Road, Malleswaram - Rajajinagar, Bengaluru.

Pin Code 560055

E-mail [email protected]

Telephone No. 080-41379200; 9980141453

Fax No. 080-22210784

16.

Details of Alternative Sites examined, if

any.

Location of these sites should be shown on

a topo sheet.

Village-District-State

Not Applicable

17. Interlinked Projects Not Applicable

18. Whether separate application of

interlinked project has been submitted? Not Applicable

19. If yes, date of submission Not Applicable

20. If no, reason Not Applicable

21.

Whether the proposal involves

approval/clearance under: if yes, details of

the same and their status to be given.

(a) The Forest (Conservation) Act, 1980?

Not Applicable

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 7 | P a g e

(b) The Wildlife (Protection) Act, 1972?

(c) The C.R.Z Notification, 1991?

22. Whether there is any Government

Order/Policy relevant/relating to the site? No

23. Forest land involved (hectares) No

24.

Whether there is any litigation pending

against the project and/or land in which

the project is propose to be set up?

(a) Name of the Court

(b) Case No.

(c) Orders/directions of the Court, if any

and its relevance with the proposed

project.

No

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 8 | P a g e

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will

cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sl.

No. Information/Checklist confirmation

Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

1.1

Permanent or temporary change in

land use, land cover or topography

including increase in intensity of

land use (with respect to local land

use plan)

Yes

Proposed Mixed use Development on land

admeasuring 3,09,665.97Sq.m (76 Acres 20.81

Guntas). As per BDA Master Plan the existing

land use is Commercial and Residential. Mixed

use Residential and Commercial activities are

permitted in the proposed project site.

1.2 Clearance of existing land,

vegetation and buildings? No

The proposed project site is converted for

Residential and Commercial Purposes from

Agricultural Land use. Various Tree species

(Local / Native) exist at the project site. The

Trees shall be cut, retained or transplanted

depending on the age, economic and

environment value. Two tree saplings shall be

planted for every tree cut with the proposed

project site.

1.3 Creation of new land uses? No

The existing land-uses are Commercial and

Residential. Mixed Use Development is

permitted as per BDA / local bylaws.

1.4 Pre-construction investigations e.g.

bore houses, soil testing? Yes

Soil testing shall be carried out for structural

design

1.5 Construction works? Yes

The project will involve construction of Mixed

use buildings. (Residential and Commercial)

with total built-up area of 13,00,598Sq.m

1.6 Demolition works? No Not Applicable

1.7 Temporary sites used for

construction works or housing of Yes

Labor camp for about 500 - 800 workers will

be set-up near the proposed site

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 9 | P a g e

construction workers?

1.8

Above ground buildings, structures

or earthworks including linear

structures, cut and fill or excavations

Yes

The proposed project consists of 2 Basements

+ Ground + 3 Upper Floors to 30 Upper Floors.

Excavation will be for providing basement,

footings, sump tanks etc., and excavated earth

will be used for backfilling, leveling of earth,

internal roads, etc., Excavation of about

11,15,000cum is estimated for the project.

1.9 Underground works including

mining or tunneling? No Not Applicable

1.10 Reclamation works? No Not Applicable

1.11 Dredging? No Not Applicable

1.12 Offshore structures? No Not Applicable

1.13 Production and manufacturing

processes? No Not Applicable

1.14 Facilities for storage of goods or

materials? No Not Applicable

1.15 Facilities for treatment or disposal

of solid waste or liquid effluents? Yes

Municipal Solid waste of around 14,550kg/day

will be segregated at source into organic and

inorganic wastes. Around 8,250kg/day of

Organic Waste will be treated through

decentralized composting systems within the

development & 6,300kg/day of Inorganic

waste will be further segregated and sold to

local recyclers. Non-recyclable waste shall be

disposed to the BBMP authorized agencies.

Domestic sewage effluent of 3,526KLD

generated from the project shall be treated in

number of decentralized Sewage Treatment

Plants (STPs).

1.16 Facilities for long term housing of

operational workers? Yes

Temporary labour sheds for housing of

construction workers shall be provided near

the project site. 800 - 1000 workers are

expected during peak construction phase. All

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 10 | P a g e

required facilities viz., water, sanitary, power,

etc., shall be provided. The temporary sheds

shall be removed after completion of the

project. There shall be influx of people to the

project for housing, jobs, entertainment,

recreation, sports, etc. after completion of the

project.

1.17 New road, rail or sea traffic during

construction or operation? No Not Applicable

1.18

New road, rail, air waterborne or

other transport infrastructure

including new or altered routes and

stations, ports, airports etc?

No Existing and proposed transport infrastructure

will be used

1.19

Closure or diversion of existing

transport routes or infrastructure

leading to changes in traffic

movements?

No Not Applicable

1.20 New or diverted transmission lines

or pipelines? Yes New Water Supply and Electrical Supply lines

1.21

Impoundment, damming, culverting,

realignment or other changes to the

hydrology of watercourses or

aquifers?

Yes

Retaining walls along the Storm Water Drains

(Nalas) shall be constructed. However, there

shall not be any kind of obstruction in the flow

of water within the Nala.

1.22 Stream crossings? No Not Applicable

1.23 Abstraction or transfers of water

from ground or surface waters? No

Water will be drawn from Bangalore Water

Supply & Sewerage Board (BWSSB) and

Rooftop Rainwater

1.24

Changes in water bodies or the land

surface affecting drainage or run-

off?

No Not Applicable

1.25

Transport of personnel or materials

for construction, operation or

decommissioning?

Yes

Transportation of construction materials will

be made mainly through mechanized hi-tech

trucks covered with tarpaulin to avoid dust

release into the surrounding environment.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 11 | P a g e

Labor camp is proposed nearby the project

site.

1.26

Long-term dismantling or

decommissioning or restoration

works?

No Not Applicable

1.27

Ongoing activity during

decommissioning which could have

an impact on the environment?

No Not Applicable

1.28 Influx of people to an area in either

temporarily or permanently? Yes

There shall be influx of people to the project

for housing, jobs, entertainment, recreation,

sports, etc. after completion of the project.

1.29 Introduction of alien species? No Not Applicable

1.30 Loss of native species or genetic

diversity? No Not Applicable

1.31 Any other actions? No --

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 12 | P a g e

2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short supply):

Sl.

No.

Information/checklist

confirmation Yes/No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

2.1 Land especially undeveloped or

agricultural land (ha) No

The land-use of the proposed project site is

Residential and Commercial.

2.2 Water (expected source &

competing users) unit: KLD Yes

Water of about 3,915KLD will be sourced from

Bangalore Water Supply & Sewerage Board.

Rooftop Rainwater & Treated Water will also be

used

2.3 Minerals (MT) No Not Applicable

2.4

Construction material – stone,

aggregates, sand / soil

(expected source – MT)

Yes Appropriate for built-up area of 13,00,598Sq.m

from nearby sources.

2.5 Forests and timber (source –

MT) Yes

Timber for door/ window frames, etc., wherever

wood may be used

2.6

Energy including electricity and

fuels (source, competing users)

Unit: fuel (MT), energy (MW)

Yes

The total maximum power demand of 45 MVA for

the proposed project shall be sourced from

Bangalore Electricity Supply Company Limited

(BESCOM). Separate electrical rooms will be

constructed in the development as per the

requirement. It is proposed to install Dual Fuel

(Diesel and CNG) Sets as back-up power during

power cuts (2000 KVA x 9 Nos + 3000KVA x 5 Nos).

The installation of transformer, LT and HT panels

shall be as per the provision specified by the

concerned authorities.

The power requirement during construction of

about 500KVA for lighting tools and plant

equipment, pumps and others will be met from

BESCOM and back up DG sets enclosed type of

capacity 250KVA X 2Nos. is proposed.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 13 | P a g e

High Speed Diesel (HSD) with Sulphur content less

than 0.005% will be used for Diesel Generators in

case of power failure. Fire and safety measures

will be taken as per the guidelines from the

concerned authority.

2.7

Any other natural resources

(use appropriate standard

units)

No Not Applicable

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 14 | P a g e

3. Use, storage, transport, handling or production of substances or materials, which could be

harmful to human health or the environment or raise concerns about actual or perceived risks to

human health.

Sl.

No. Information/Checklist confirmation Yes/No

Details thereof (with approximate

quantities/rates, wherever possible)

with source of information data

3.1

Use of substances or materials, which are

hazardous (as per MSIHC rules) to human

health or the environment (flora, fauna,

and water supplies)

No Not Applicable

3.2

Changes in occurrence of disease or affect

disease vectors (e.g. insect or water borne

diseases)

No

Hygienic and sanitation systems shall

be scientifically designed. Pest &

Rodent, flies, control measures will be

done on a regular basis.

3.3 Affect the welfare of people e.g. by

changing living conditions? No

The standard of living of the nearby

locals will improve due to the

employment opportunities created by

the proposed mixed use development.

3.4

Vulnerable groups of people who could

be affected by the project e.g. hospital

patients, children, the elderly etc.,

No Not Applicable

3.5 Any other causes No Not Applicable

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 15 | P a g e

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sl.

No.

Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates, wherever possible) with source

of information data

4.1 Spoil, overburden or mine

wastes No Not Applicable

4.2 Municipal waste (domestic

and or commercial wastes) Yes

During Construction - Municipal solid waste of

about 100 kg/day from the labor camp and staff

will be segregated and disposed to municipal

authorities through local agencies.

During Operation - The Municipal solid waste

generation in the project will be of non-hazardous

in nature consisting of biodegradable and non-

biodegradable matter. This will comprise of solid

wastes from kitchens, garden, store rooms, wash

rooms, etc. The municipal solid waste from the

mixed use development after completion and full

occupancy is expected to be around 14,550kg/day.

The Municipal Solid wastes will be segregated into

biodegradable and non-biodegradable at source.

The biodegradable waste (8,250kg/day) will be

composted within the project site and the non-

biodegradable waste (6,300kg/day) will be handed

over to a local recyclers and BBMP for further

treatment and disposal.

4.3

The Hazardous (Waste

Management, Handling and

Trans-boundary Movement)

Rules

Yes

Waste oil from Dual Fuel Generator sets will be

stored in leak proof sealed barrels under covered

sheds and will be disposed off to KSPCB authorized

Re-processors.

4.4 Other industrial process

wastes No Not Applicable

4.5 Surplus product No Not Applicable

4.6 Sewage sludge or other Yes The Sewage Effluent generated from the entire

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 16 | P a g e

sludge from effluent

treatment

Mixed Use Development will be treated in number

of decentralized STPs. The treated water shall be

used for toilet flushing, air conditioning,

landscaping, etc. The Sludge shall be dewatered

and used as manure within the project campus

4.7 Construction or demolition

wastes Yes

The generation of waste material is inevitable at

different stages of construction process. 50kg/Sq.m

of built-up area is expected to be generated.

Measures shall be taken to reduce the construction

waste generation. Waste during construction

activity relates to excessive cement mix or concrete

left after work is over, rejection caused due to

change in design or wrong workmanship etc,

concrete appears in two forms in the waste.

Structural elements of building have reinforced

concrete, while foundations have mass non-

reinforced concrete. These materials are normally

reused as filler material at the same site after

completion of excavation work and for construction

of basement raft and internal road etc. Other

miscellaneous material during construction that

arise as waste includes, glass, plastic material,

general refuse, scrap metal, cardboard, plastics etc.

will be segregated and disposed to authorized

recyclers. Surplus construction waste shall be

disposed as per the Construction and Demolition

Waste Rules.

4.8 Redundant machinery or

equipment No Not Applicable

4.9 Contaminated soils or other

materials No Not Applicable

4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No Not Applicable

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 17 | P a g e

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sl.

No.

Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates, wherever possible) with source

of information data

5.1

Emissions from combustion of

fossil fuels from stationary or

mobile sources

Yes

Air emission comprising PM, NOX, un-burnt

hydrocarbon and SO2 will be from the operating

Dual Fuel Generator sets used as the standby power

source. Emission of the above pollutants will be

temporary (during power cuts) and will be further

minimized by the use of low Sulphur High Speed

Diesel (HSD) with Sulphur content <0.005%.

5.2 Emissions from production

processes No Not Applicable

5.3

Emissions from materials

handling including storage or

transport

No Not Applicable

5.4

Emissions from construction

activities including plant and

equipment

Yes

The potential ambient air quality impacts arising

from the proposed project would occur mainly

during project construction phase. Particulate

Matter would be predominant, pollutant generated

from construction activities. The gaseous emissions

such as SO2, NOX and un-burnt hydrocarbons would

be generated from the construction equipment and

vehicles.

The impact of such activities would be temporary

and restricted to the construction phase. The

impact will be confined within the project boundary

and is expected to be negligible outside the project

boundaries. Proper upkeep and maintenance of

vehicles, sprinkling of water on roads at

construction site, providing sufficient vegetation

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 18 | P a g e

etc, are some of the proposed measures that would

greatly reduce the impact on the air quality during

the construction phase of the project.

Excavation during windy days will be avoided to

reduce dust emissions.

5.5

Dust or odours from handling

of materials including

construction materials,

sewage and waste

Yes

Dust emission during construction phase will be

present and decreases gradually as project

progresses. Sewage during construction stage will

be treated in septic tank and soak pits and the

municipal waste will be handed over to local

disposal agencies on a daily basis through proper

records, thereby reducing the nuisance of odor and

minimizing the chances of spread of infectious

diseases. During operation phase, decentralized

sewage treatment plants shall be installed to treat

the sewage effluent and make them fix for reuse

and meet the discharge standards stipulated by

KSPCB / CPCB. The treated water shall be used for

landscaping, toilet flushing, air conditioning, etc.

5.6 Emissions from incineration of

waste No Not Applicable

5.7

Emissions from burning of

waste in open air (e.g. slash

materials, construction

debris)

No

Not Applicable. The In-organic waste generated

during the construction phase shall be properly

segregated and processed within the project.

5.8 Emissions from any other

sources No Not Applicable

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 19 | P a g e

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sl.

No.

Information/Checklist

confirmation Yes/No

Details thereof (with approximate quantities/rates,

wherever possible) with source of information data

with source of information data

6.1

From operation of

equipment e.g. engines,

ventilation plant, crushers

Yes

During the operation phase, noise will be generated

from the Generator sets, pump room, vehicles

movement, and general noise characteristics of the

occupants. The Generator set room and pump will be

isolated from the outside environment and proper

acoustic arrangements will be made to control the

noise generated from the rooms. Necessary mitigation

measures include installation of Vibration isolation

pads of suitable thickness commensurate to loading to

reduce the vibration, shall be provided under all

equipment’s provided. The noise levels outside the

room will be maintained within the stipulated norms

as per KSPCB Standards, both during the day and

night times.

6.2 From industrial or similar

processes No Not Applicable

6.3 From construction or

demolition Yes

Heavy construction traffic for loading and unloading,

fabrication and handling of equipment’s and

construction materials are likely to cause an increase

in the ambient noise levels. At peak of the

construction phase, minimal increase in noise levels is

expected to occur locally at construction site.

The peak noise levels from continuous construction

activity may vary between 80 to 85dB (A). However,

factors like air absorption, vegetal cover etc., would

result in significant attenuation of at least 20 to 25dB

(A) at 100 m distance. The resultant noise levels on

proposed project site at 100m distance at peak level

of construction are anticipated to be about 60 - 65dB

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 20 | P a g e

(A), which is well within the limits for Commercial

areas during the day time. Hence, the noise levels are

considered to have insignificant impact.

Further to minimize these potential impacts, major

construction activities would be scheduled during

normal daylight working hours and would be

implemented consistent with the applicable

standards. The construction contractor will use

equipment’s that are adapted to operate with

appropriate noise muffling devices resulting in the

least possible noise. Every effort would be taken to

minimize the noise levels including the mandatory use

of construction equipment’s with operable mufflers.

Overall, the impact of noise generated on the

environment is likely to be insignificant, reversible and

localized in nature and mainly confined to daytime

and construction period only.

6.4 From blasting or piling No Not Applicable

6.5 From construction or

operational traffic Yes

During Construction - Explained in 6.3

Operational Phase - From the project itself, there will

be separate Entry and Exit points, each 6.0 m wide.

The total width of the internal road (bi-directional) is

8m wide as per Fire regulations. The traffic circulates

around the property simultaneously providing ingress

& egress to the parking area. Hence, traffic noise is

not expected to be a major concern. Also, speed

breakers at regular intervals shall be put up to ensure

that vehicles do not over-speed within the property.

Sign boards indicating “No Horn”, “Drive Slowly” and

“Speed Limit” shall be put up at regular intervals to

guide the drivers for a safe drive. The Entry and Exit

will be manned by trained and experienced traffic

wardens/security. Stopping or parking near the

Entrance and Exit portals will be prohibited; The long

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 21 | P a g e

driveway leading to the Parking bays and areas will

ensure that vehicles do not get piled up. Bus bays are

proposed at strategic locations nearby to the

buildings, to ensure that the employees do not have to

walk for long distances to access them and thereby

effectively utilizing the public transport system.

6.6 From lighting or cooling

systems No

Noise, vibration, heat and intensity light will be

negligible from the lighting and cooling systems.

6.7 From any other sources No None other than the sources mentioned above.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 22 | P a g e

7. Risks of contamination of land or water from releases of pollutants into the ground or into

sewers, surface waters, groundwater, coastal waters or the sea:

Sl.

No.

Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates, wherever possible) with source

of information data

7.1 From handling, storage, use or

spillage of hazardous materials No

The hazardous material which includes used Oil,

diesel fuel, waste paints, varnishes, solvents,

fluorescent bulbs, batteries etc., will be handled

and stored in an environmentally sound manner.

Care shall be taken to avoid spillage of hazardous

oils onto land or water, thereby contaminating it.

7.2

From discharge of sewage or

other effluents to water or the

land (expected mode and place

of discharge)

Yes

The discharge of sewage during the operation

phase will be treated in the fully operational

decentralized STPs.

7.3

By deposition of pollutants

emitted to air into the land or

into water

No

Negligible impact due to air emissions from the

operation of generator sets onto land or water.

Height of stack for Dual Fuel Generator sets

during operation shall be designed as per the

formula, H = 14 Q 0.3, where, Q = Total SO2

emission from the Generator Set in kg/hr.

However, the above formula limits the maximum

height of the stack at 30m. Since the height of the

building is about 90m, it is decided to provide

stack height of 3.0m above roof level.

7.4 From any other sources No Not Applicable

7.5

Is there a risk of long term

build-up of pollutants in the

environment from these

sources?

No Not Applicable

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 23 | P a g e

8. Risk of accidents during construction or operation of the Project, which could affect human

health or the environment

Sl.

No.

Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

8.1

From explosions, spillages, fires

etc. from storage, handling, use or

production of hazardous

substances

No Not Applicable

8.2 From any other causes No

On site Personal Protective Equipment’s (PPE)

will be provided to all the laborers while on

duty. The Safety instructor at site will ensure

that all the labourers wear their PPE’s while

they enter the site and are on duty. Safety

training by a qualified Safety Instructor will be

given to all the laborers on a regular basis. The

construction equipment will be operated as per

the standard operating procedures of the

equipment’s and training for operating the

equipment’s shall be provided to the concerned

personnel by their authorized representatives.

8.3

Could the project be affected by

natural disasters causing

environmental damage (e.g.

floods, earthquakes, landslides,

cloudburst etc)?

Yes

The project area falls in Zone - II of Seismic

zoning map of India. The seismic factors have

been appropriately incorporated in the civil

designs for the proposed project.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 24 | P a g e

9. Factors which should be considered (such as consequential development) which could lead

to environmental effects or the potential for cumulative impacts with other existing or planned

activities in the locality

Sl.

No.

Information/Checklist

confirmation Yes/No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

9.1

Lead to development of

supporting.

facilities, ancillary development

or development stimulated by

the project which could have

impact on the environment e.g.:

• Supporting infrastructure

(roads, power supply, waste or

waste water treatment, etc.)

• housing development

• extractive industries

• supply industries

• other

No

The proposed project is a mixed use

development. The project will have its own

infrastructure in terms of power supply in the

form of Transformers, and Generator sets, which

will be operated only during power failure by

BESCOM. The project will create housing

infrastructure along with required amenities to

the persons who will be residing in the future

development.

9.2

Lead to after-use of the site,

which could have an impact on

the environment

No There is no impact on the environment post to

after-use of the site.

9.3 Set a precedent for later

developments No

Not possible to accurately project at the present

time

9.4

Have cumulative effects due to

proximity to other existing or

planned projects with similar

effects

No

The project area is fast developing. Number

residential and commercial developments are

planned and a few are under construction. The

connectivity of the project site to the IT hub ITPL,

EPIP, etc on one side and Electronic City, jigani,

etc on the other. Many best-in-the-class

education institutes have presence in the area.

Public and Private transport facilities is above

average. Overall the project is expected to

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 25 | P a g e

benefit the locals by providing them job

opportunities, housing, entertainment, sports,

etc.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 26 | P a g e

(III) Environmental Sensitivity

Sl. No. Areas Name/

Identity

Aerial distance (within 15 km.)

Proposed project location

boundary

1

Areas protected under international

conventions, national or local legislation

for their ecological, landscape, cultural or

other related value

No Not Applicable

2

Areas which are important or sensitive for

ecological reasons - Wetlands,

watercourses or other water bodies,

coastal zone, biospheres, mountains,

forests

No Not Applicable

3

Areas used by protected, important or

sensitive species of flora or fauna for

breeding, nesting, foraging, resting, over

wintering, migration

No Not Applicable

4 Inland, coastal, marine or underground

waters No Not Applicable

5 State, National boundaries No Not Applicable

6

Routes or facilities used by the public for

access to recreation or other tourist,

pilgrim areas

Yes

The abutting road connects

Whitefield to Sarjapur and Hosur

Road on one side and Old Madras

Road and Bengaluru International

Airport on the other.

7 Defence installations No Not Applicable

8 Densely populated or built-up area Yes Whitefield, Sarjapura,

Kundalahalli, Bengaluru City

9

Areas occupied by sensitive man-made

land uses (hospitals, schools, places of

worship, community facilities)

Yes Varthur Lake -0.5km, Gunjur Lake -

0.5km

10

Areas containing important, high quality

or scarce resources (ground water

resources, surface resources, forestry,

No Not Applicable

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 27 | P a g e

agriculture, fisheries, tourism, minerals)

11

Areas already subjected to pollution or

environmental damage. (those where

existing legal environmental standards

are exceeded)

No Not Applicable

12

Areas susceptible to natural hazard which

could cause the project to present

environmental problems (earthquakes,

subsidence, landslides, erosion, flooding

or extreme or adverse climatic

conditions)

No

The project area falls in Zone - II of

seismic zoning map of India. The

seismic factors have been

appropriately incorporated in the

civil designs for the proposed

project.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 28 | P a g e

(IV). Proposed Terms of Reference for EIA studies

Terms of References (TORs)

Introduction

M/s. Mysore Projects Private Limited is an Subsidiary of M/s Brigade Enterprises Limited an ISO 9001

– 2008, ISO 14001 – 2004 and OHSAS 18001 – 2007 certified company with more than twenty-nine

years of experience in the field engaged in construction and development of properties. Brigade

group has already constructed more than one hundred large commercial, residential, hospitality

properties and many more are under construction in and around Bengaluru city.

The World Class Mixed Use Development is proposed to be developed at Sy. No. 171/1, 171/2,

171/3, 171/4, 172, 173/1, 173/2, 173/3, 183/2, 183/3, 183/6A, 183/6B, 183/7, 183/8, 183/9, 183/11

and 184/1(P) Varthur Village, Varthur Hobli, Bengaluru East Taluk, Bengaluru and Sy. No. 217/3,

227/1(P), 227/2, 227/3, 227/4, 228/1, 228/2, 229/1, 229/2, 229/3, 229/4, 229/5, 229/12, 230/1,

230/2, 230/3, 230/4, 270/1 and 270/3 of Gunjur Village, Varthur Hobli, Bengaluru East Taluk,

Bengaluru.

Organizational Chart

Status of ownership of Land: M/s. Brigade Enterprises Limited through its Subsidiary M/s. Mysore

Projects Private Limited has entered into Joint Venture agreement with M/s. Cornerstone Bay East

Developers Private Limited for the development of property of 3,09,665.97Sq.m (76 Acres 20.81

Guntas). The property is converted for residential and commercial land-use. The project area is

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 29 | P a g e

compounded and protected by security group round the clock. The site was surveyed to verify the

land records with areas and was found to be legally correct.

Project Description

A unique development is planned with multiple facilities to cater to various needs of the people in

the vicinity and within the project campus. The proposed mixed use development would have

modern-day amenities/features such as Hotel: 200 Keys; Hospital: 50 Bedded, Retail Mall and

Multiplex, Auditorium, Food Courts, School, Offices, Clubs, Convention Centre, Art Centre, Cultural

Centre, Serviced Residents, Wellness Centre, Recreation Centre, Sports Centre, etc. apart from

Uninterrupted Power, Amphitheater, ATM, Efficient Security Team with security features such as

Baggage & Person Scanning, Vehicle Scanning prior to entry into the campus etc.

Objectives and significance of the project at local and regional level

The objective of the proposed project is to provide housing to about 24,000 occupants, 10,000 job

opportunity and world class amenities to the people in the vicinity and within the development. The

concept of mixed use development is well acceptable and sustainable worldwide. The social and

economic well-being is secured and ensures that the operation of mixed use development reduces

the pollution loads due reduced usage of natural resources by optimizing the design of various

functional elements. The proposed project shall have least influence on the surrounding

environment that is done by reducing the likely impacts from the project through Environmental

Impact Assessment and incorporating an Environmental Management Plan.

The proposed site is vacant / unused land converted for residential and commercial land-use. The

proposed site comes under Bruhat Bangalore Mahanagara Palike (BBMP) limits, and the source of

fresh water is Bangalore Water Supply & Sewerage Board (BWSSB). Power requirements will be met

from BESCOM.

Accessibility:

The proposed Commercial project is on Varthus - Sarjapur Main Road of 24m width. The project site

is about 20 km from Bengaluru City. It connects Whitefield on one side and Sarjapur on the other.

Due to the location of various residential & commercial establishments including shopping malls

within close vicinity, the project is best suited at the proposed site, reducing the travel time, traffic

congestion etc.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 30 | P a g e

Fig: Google Image of the Project Site

Contour Survey and Soil Investigation Report: Contour survey was carried out to find topography of

the site and for design purpose. It was observed from the topo map that a Storm Water Drain (Nala)

touches the project site at a few locations. Required buffer / setback shall be provided as per local

norms / byelaws.

Soil investigation study was conducted to find the soil stability, load bearings, etc. to determine the

structural loading and for designing the project. After the preliminary studies, it is proposed to

develop Mixed Use Development in 2 Basements + Ground + 3 Upper Floors to 30 Upper Floors.

Connectivity: The project site is located on Varthur - Sarjapur Main Road. The proposed project is

situated around 20 km from the Central Business area of the City, 45 km from the Kempegowda

International Airport, 6 km from Carmelaram Railway Station and about 20 km from Bengaluru City

Railway Station.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 31 | P a g e

Fig: Location Map

Generic Structure of EIA report

The generic structure of the EIA Report will be as per the MOEF EIA Notification dated 14th

September 2006 as described below: All documents will be properly referenced with index and page

numbers.

Chapter 1. Introduction (This chapter will describe the purpose of the report, Identification of

nature, size and location of the project (with latitude and longitude), Introduction of project

proponent, Description of site and surrounding environment, Location maps, Importance of project

to the country and region, and Scope of EIA study)

Chapter 2. Project Description (This chapter will describe the Type and Need of the project,

Magnitude of operation, Schedule for approval and implementation, Land requirement, Water

requirement and flow scheme, Technology and Process description, Site plan, Layout of project site

and boundary, Description of mitigation measures suggested to meet the environmental standards)

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 32 | P a g e

Chapter 3. Description of the existing Environment (This chapter will describe the study area, period

of EIA study, EIA components and methodology, Establishment of baseline data for valued

environmental components and base maps / description of relevant environmental component

(Meteorology, Air quality, Noise quality, Water quality, Land use, Soil quality, Ecology, Demography,

Occupational pattern and Socio-economics)

Chapter 4. Anticipated Environmental Impacts and Mitigation Measures. This chapter will describe

the investigated impacts due to project on surrounding location, credible accidents and

minimization, project design and impacts during construction and regular operation, measures

suggested for minimizing and / or offsetting adverse impacts, Irreversible and Irretrievable

commitments on environmental components, assessment of significance of impacts [including

criteria for determining significance, assigning significance.

Chapter 5. Environmental Monitoring Program (This chapter will include the various aspects of

monitoring the effectiveness of mitigation measures suggested including measurement

methodologies, frequency, location, data analysis, reporting schedules, emergency procedures)

Chapter 6. Additional Studies (This chapter will describe Risk Assessment, Emergency Management

Plan)

Chapter 7. Environmental Management and Monitoring Plan (This chapter will describe the

administrative aspects of ensuring that mitigation measures are implemented and their

effectiveness monitored after approval of the EIA).

Chapter 8. Summary and Conclusion (This chapter will describe the overall justification for

implementation of the project, and explain methods by which adverse effects of the proposed action

have been mitigated)

Chapter 9. Disclosure of Consultant Engaged (The name of the consultant engaged with brief

resume and nature of consultancy rendered will be provided in this chapter)

Proposed Terms of Reference

The purpose of Environmental Impact Assessment (EIA) is to determine as precisely as possible

within the present limits of knowledge and expertise, the likely environmental impacts of the

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 33 | P a g e

proposed project. The objective will be to establish a clean unit whose waste, if any, can be recycled

/ reused to the maximum extent feasible. Feasibility of reuse and disposal of liquid and solid wastes

generated from the project will be explored. The Terms of Reference proposed for this EIA is as

follows:

The study area will cover an area of 10 km radius around the proposed project site.

EIA procedure as given in the EIA Manual of MOEF will be followed.

Baseline environmental quality within 10 km radius of the project site will be assessed based

on secondary data collected from various sources supplemented by data generated at site.

Baseline data will be generated for non-monsoon season, for following environmental components:

Land Environment (land use, geology, seismology and soils):

The baseline data for land environment will include soil analysis for its fertility and to ascertain that

there is no polluting parameters in the soil. The soil sampling will be done by field study and will be

analyzed by NABET Accredited laboratories. The field study will also include identification of rare

vegetation, if any, and demarcation for its preservation. Soil will be analyzed for its load bearing

capacity, slope stability, level difference, particle size, etc.

Soil Sampling

Type and characteristics

Porosity and permeability

Sub-soil permeability

Inherent fertility

Water Environment

Identifying project activities including construction, which may affect surface water or groundwater.

Estimating water intake requirements and identifying the source of water to be used.

Air Environment (Air Quality)

The baseline data for air will include measurement / monitoring of Ambient Air. This is done by field

study to locate the Ambient Air Quality Monitoring Station (AAQMS) and samples collected are

analyzed by NABL approved / authorized laboratories. Baseline data of air pollutant parameters

extending an area of 500meters from the project shall be monitored at a number of locations.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 34 | P a g e

Description of baseline data of ambient air parameters namely RSPM, Nitrogen dioxide, Sulphur

dioxide, and Carbon monoxide shall be collected. Number and locations of Ambient Air quality

monitoring (AAQM) stations shall be decided based on the nature of project, meteorological

conditions, Topography, selected pollution pockets in the area and likely impact areas, using

Experimental judgement.

Ambient Air Monitoring is being done by Karnataka State Pollution Control Board at 10 Locations in

Bengaluru City which also includes Graphite India using manual equipment’s under National Ambient

Air Quality Monitoring Programme (NAMP) covering Industrial Area, Mixed Urban Area and Sensitive

Area. Six months Ambient Air Quality Monitoring results for Graphite India Station will be used as

baseline data. Also, AAQ data of the study area will be generated by following the guidelines for

ambient air quality monitoring published by CPCB (Guidelines for Ambient Air Quality Monitoring:

NAAQMS/25/2003-04-July 2003).

The parameters monitored are as follows.

Particulate Matter - (PM-10 & PM 2.5)

Oxides of Nitrogen (NOX)

Sulphur Di Oxide (SO2)

Carbon Monoxide (CO)

Ecological Environment (Terrestrial Ecology)

There will be no major impact on the terrestrial and aquatic environment of the surroundings or in

the region due to implementation of the project. Moreover, green-belting measures within the

campus will be undertaken to provide an aesthetically pleasing environment for the occupants of the

building. 33% of the project site is proposed for landscaping.

Flora and Fauna

The listing of flora and fauna will be carried out by referring to the published documents / recent

literature and observations recorded during the field visits.

Socio-Economic Environment (demography, socio-economic, public health)

Population, Sex ratio, Literacy rate, Socio-economic status etc., will be compiled through available

literature review. The Socio-Economic Environment in and around the project, pertains to the town

of Krishnarajapuram, and hence not a major consequence either as a source of nuisance to the

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 35 | P a g e

project, or for the project to have any adverse impact. Hence the Socio-Economic Environment has

not been studied or assessed in detail.

Topography

Topography of the project site will be given with contours drawings.

The impact of the project on the existing drainage pattern will be addressed and mitigation

measures will be suggested to counter the adverse impact on the existing drainage pattern.

Landscaping

Greenery development plan is prepared to enhance the aesthetic quality of the environment. The

plan also concentrates on measures that will be helpful in attenuating air and noise pollution levels

from the project. Local/Native fast growing tree species will be adopted in landscaping post

construction phase. 33% of the project area is reserved for development of greenbelt, landscaping

and gardens / lawns, etc.

Traffic Study

The existing traffic movement pattern and intensity on the Graphite India main road will be

monitored for one / two days. The impact of additional traffic due to the proposed project will be

assessed.

Rainwater Harvesting

Rainwater harvesting strategies which includes Roof top rainwater collection tank for harvesting

terrace water & re-charge pits for harvesting surface run-off within the project premises will be

implemented as a measure to augment the available groundwater resources of the area.

Environmental Management Plan

Environmental Management Plan (EMP) will be drawn up to maintain and enhance the

environmental quality in and around the project area. In case the quality of the environment is

expected to deteriorate beyond acceptable limits, additional strategies will be suggested and

implemented. Such strategies include air pollution mitigation measures, wastewater treatment and

reuse, noise reduction measures, etc.

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 36 | P a g e

The EMP will earmark specific staff, instruments and finances for routine environmental

management as well as collection, collation and examination of various environmental data. A post-

project monitoring plan will be suggested to monitor the changes in the environmental quality after

implementation of the project. All necessary administrative measures will be incorporated in the

EMP to achieve the following objectives:

Reduction of adverse environmental impacts

Improvement of environmental quality of the surrounding area

Waste minimization, re-use and resource recovery

Waste segregation to make the treatment and disposal cost-effective

Establish proper monitoring mechanism with adequate infrastructure

Risk assessment study

Risk assessment study will be undertaken and disaster management plan will be prepared to tackle

any accident that may occur due to the proposed activity.

Table: Environmental Attributes and Monitoring

Sl.

No. Attribute Parameter Source

Land Environment

1. Soil Soil Characteristics Field Study and Laboratory

Report

2. Seismology Seismic Hazard Literature Review

3. Topography Contours Field Study

Water Environment

4. Water Quality Physical & Chemical Parameters Field Study and Laboratory

Report

Air Environment

5. Ambient Air

Quality SPM, RSPM, SOX, and NOX

Field Study and Laboratory

Report

6. Meteorology Temperature, Relative Humidity,

Rainfall

Indian Meteorological

Department & Literature review

7. Traffic Study Traffic flow rate, PCUs, Road Width, Field Study and Literature review

Terms of Reference (TOR) Mysore Projects Private Limited

Environment Clearance 37 | P a g e

Carrying capacity of the road.

8. Socio-economic

aspects

Socio-economic characteristic of the

affected area Field Studies, Literature review

Declaration

“I hereby give an undertaking that the data and information given in the application and enclosures

are true to the best of my knowledge and belief and I am aware that if any part of the data and

information submitted is found to be false or misleading at any stage, the project will be rejected

and clearance given, if any, to the project will be revoked at our risk and cost.”

Date: 29-06-2017 ROSHIN MATHEW

Place: Bengaluru DIRECTOR


Recommended