of 20
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
1/20
Internal Wall Insulation SystemDesign Guide
ResidentialReurbishment
March 2010
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
2/20
Walls 45%
Roof 20%
Ground floor 13%
Windows and doors 9%
Draughts 13%
Where heat is lost from a typical solid wall house
The importance o wall insulation in houses
Buildings account for 40% of our energy
consumption and in houses the majorityof this energy is lost through the walls.
Thereore insulation is one o the most cost
eective improvements that can be made
and there are various insulation options
depending on how the home is constructed.
In general, the walls in the home can be
categorised into two distinct types. Modern
style homes, usually built post-war (1945),
are constructed with cavity walls. Older style
homes are constructed with solid brick walls.
Around a third o the heat is lost in an
un-insulated house with cavity walls, which
account or a large majority o recently
built homes. Occupants can make savings
around 115 per year* and see a return
on investment within a couple o years by
insulating their cavities.
However, solid walls can lose even more
heat than cavity walls. Typically the totalheat loss rom an un-insulated house with
solid external walls account or 45% (see
pie chart). Insulating solid walls can be
more expensive than cavity wall insulation.
However, higher savings can be achieved
through internal or external insulation or
solid walls saving the occupant up to 400
a year* and internal wall insulation oers
a quicker payback than external wall
insulation.
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
3/203
Contents
The importance o wall insulation in houses...........................................2
Why insulate a solid wall property.......................................................3
Solid wall insulation options................................................................4
The IWI System..................................................................................6
Features and advantages o the
IWI System........................................................................................9
Avoiding dampness within the construction............................................10
Avoiding thermal bridging and
surace condensation..........................................................................11
Separating walls................................................................................12
Insulation continuity at oors................................................................13
Installation o the IWI System...............................................................15
Installation at window and door openings.............................................17
Accommodating fxtures and fttings..................................................... 19
Why insulate a solid wall property?
Over a quarter o the UKs CO2
emissions
are generated by our homes. O theestimated 25 million homes in the UK
approximately 36% have been labelled
as hard to treat, the majority o which
are solid walled properties. Insulating all
the solid wall properties in the UK would
provide signifcant reductions in the amount
o CO2
we emit and would also help to
reduce an occupants uel bills.
Save money on energy bills
Homes losing heat, lose money. A poorly
insulated home will be costing the occupant
signifcantly more in heating bills than a
ully insulated property. Insulation slows the
transer o heat, reducing the amount o
energy consumption in the home - keeping it
warm in winter and cool in summer.
Eradicate uel poverty
50 per cent o solid wall properties are
occupied by people living in uel poverty.
Fuel poverty is linked to multiple deprivation
and unaordable uel prices characterised
by inadequate insulation and inefcient
heating systems. Fuel poverty can be
seriously damaging to peoples quality o
lie and can be particularly uncomortable
or the older generation, children and the
disabled. Britain is said to have the highest
number o avoidable deaths due to winter
cold in Western Europe.
Help save the planet
Fight climate change by reducing CO2
emissions rom solid wall homes. Solid wall
homes will play an essential role in helping
to save the environment, it is estimated that
a properly insulated solid wall home could
save approximatly 2 tonnes o CO2per
year*. This would represent a signifcant
step on the road to making homes carbon
neutral.
Increase a homes valueInsulating a solid wall home properly
can add to a homes market value by
signifcantly improving its Energy Efciency
Rating. In the case o external wall insulation
it can improve the overall aesthetics
and internal wall insulation can improve
the interior dcor and appearance o a
property.
* Energy Saving Trust March 2010
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
4/20
External wall insulation or
internal wall insulation?Solid walls can be insulated externally or
internally. Each solution has its merits.
External Wall Insulation (EWI)
External wall insulation systems generally
comprise an insulation layer mechanically
or adhesively fxed to the existing wall
and covered with a render coat; or timber
boarding, concrete and clay tiles or metal
cladding can also be applied.
An external insulation system can radicallyalter the appearance o a property (unless
it is already rendered) and planning
permission as well as Building Regulations
compliance may well be required prior
to installation. Special attention will need
to be paid, or instance, to window sills,
rainwater downpipes and gutters, and
eaves. Relocation or changes to the
rooine may be required to accommodate
the thickness o the system. External wall
insulation systems can deliver high levelso thermal perormance, eliminate thermal
bridging and cause minimum disruption to
the occupants o buildings. External wall
insulation systems are usually installed by
specialist installers.
Internal Wall Insulation (IWI)
Internal wall insulation solutions usually
involve the installation o metal or timber
studs with insulation installed between
the studs and then overlaid with a vapour
control layer and plasterboard. Alterna-
tively, a thermal laminate board or rigid
insulation board plus plasterboard can
be mechanically fxed to the walls. These
systems should not be used to isolate or hide
moisture penetration or damp problems in
the existing structure. In accordance with
Building Regulations, solid walls should
prevent moisture ingress arising rom
exposure to rain and snow without moisture
penetrating to the inside and damaging the
building.
Insulating internally improves the thermal
perormance o the wall without aecting
the external appearance o the building.
However, there will be a small reduction in
the internal oor area and the installation
process may cause disruption to theoccupants o the building. Internal wall
insulation can be installed one room at
a time thereby minimising disruption to
occupants and providing exibility during the
reurbishment programme. In a large numbero cases, internal wall insulation could be
the preerred option because it costs less to
install and maintain than external insulation
systems, does not require scaolding during
the installation process, and the existing
appearance o the building is maintained.
Combination Installations
In many instances (especially mid terraced
houses), the optimum solution may be to
install a combination o both external and
internal wall insulation. An EWI system may
suit the back o a house where appearance
is less important or already compromised
by single storey extensions, outriggers, soil
stacks, rainwater downpipes and boiler ues.
The ront o the house can be insulated with
an IWI system, which maintains aesthetic
quality, while also delivering high levels o
thermal perormance and a exible
installation solution.
Solid wall insulation options
Illustration o external
wall insulation
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
5/205
Solid wall insulation options
Advantages o internal over
external wall insulationSolid external masonry walls can be
upgraded in two ways, either internally or
externally.
Internal insulation is the preerred solution or
upgrading solid masonry walls because:
It costs less to install than external
insulation
It is easier to maintain than external
insulation
No scaolding is required
The external appearance o the building
is maintained so it can be installed in
conservation areas
No specialist skills or equipment are
required to install the insulation
Materials are readily available
It can be installed on a room-by-room,
single aade or whole house basis, as
part o a ull reurbishment plan
Installation is not delayed by bad weather
Thermal comort
An internal wall insulation system enables
comortable room temperatures to be
achieved more quickly than with an external
wall insulation system. Heating time periods
can be reduced, particularly in intermittently
heated buildings such as dwellings.
Taking the opportunity
An ideal opportunity to install internal
insulation on a solid wall is when other
work is already required, e.g. when
existing plaster is crumbling and needs
replacement, when the decorative fnish
is being removed, or when rewiring or
installing central heating, or during total
reurbishment.
The existing wall should be examined
and any remedial work, e.g. the insertion
o a damp proo course or the repair o
overowing guttering, carried out beore the
insulation system is installed. It is important
that the internal insulation system is not usedto hide or isolate damp or wet walls.
Taking advantage o any opportunity to
improve the energy efciency o a dwellingand upgrading un-insulated external walls
provides a number o benefts including:
Reducing CO2 emissions
Reduced uel bills
Increased thermal comort or the
occupiers
Reduced risk o condensation and
mould growth
Reduction o abric damage and
maintenance costs
Illustration o internal
wall insulation
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
6/20
The system components
The IWI System is a brand new internal insulation system designed or
upgrading existing solid external walls.
It consists o thermally engineered insulated studs and insulation slabs,
which can be combined to provide greater thicknesses o thermal
insulation than achievable by using a single thickness. EcoStuds are
a composite o high perormance extruded polystyrene insulation and
Oriented Strand Board (OSB). The OSB is manuactured rom timber
supplied rom Forest Stewardship Council (FSC) certifed orests.
The IWI System has been designed to simpliy the process o upgrading
solid masonry walls while delivering high levels o thermal perormance.The system can be installed by any competent builder.
System components
EcoStud extruded polystyrene
bonded to Oriented Strand Board
(OSB).
Earthwool EcoBatt water
repellent glass mineral wool slab
Plasterboard fxings Knau
Drywall screws.
Sealant Knau multi purpose
sealant.
Vapour check plasterboard Knau Vapourshield (min 75MN.s/g)
Plasterboard Knau
Moistureshield, Wallboard
or Denseshield.
Fixing to masonry fxings
manuactured in accordance with
BS1210.
Wall plugs universal wall plugs
as manuactured by Fischer or
Rawlplug.
Vapour control layer
Polyethylene membrane with a
minimum vapour resistance o
260MN.s/g.
U-values (W/m2K) for 225mm solid masonry walls*
EcoStud (mm) U-value (W/m2K)
60 0.45
75 0.35
90 0.30
120* 0.26
150* 0.20
* Combination o two studs required toachieve this thickness
The Internal Wall Insulation System
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
7/207
Thermally engineered EcoStud, extrudedpolystyrene bonded to a 11mm strip oOriented Strand Board (OSB)
Earthwool EcoBatt, water repellent glassmineral wool slab
Separate vapour control layer (min260MN.s/g), i preerred
12.5mm vapour check plasterboard(min 75MN.s/g). Or standardplasterboard with a separate vapourcontrol layer)
Existing solid masonry external wall
Existing plaster fnish (i sound)
Joint sealed with Knau Multi PurposeSealant
Existing solid masonry external wall withexisting plaster
Thermal laminate board lining reveal
EcoStud (jamb stud lines with edge oexisting reveal)
Earthwool EcoBatt between EcoStuds
600mm dimension to centre o adjacentstud to suit
Earthwool EcoBatt
Thickness(mm)
Width(mm)
Length(mm)
Thermal conductivity(W/mK)
Thermal resistance(m2K/W)
60 555 1200 0.036 1.65
75 555 1200 0.033 2.25
90 555 1200 0.033 2.70
EcoStud
Thickness(mm)
Width(mm)
Length(mm)
Thermal conductivity(W/mK)
Thermal resistance(m2K/W)
60 50 2400 n/a 1.72
75 50 2400 n/a 2.22
90 50 2400 n/a 2.72
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
8/20
Features o IWI System A cost-eective, thermally efcient
solution
Quick and easy to install so rooms are
out o commission or the minimum
period
Can improve the acoustic perormance o
the existing external wall (see page 9)
Finished using a plaster skim coat or
dry lining techniques
No need to remove existing wall fnish,unless un-sound
System can accommodate wall
imperections
Easily adapted around openings such
as windows and doors
Can easily accommodate fxings or
fttings such as radiators, pictures and
shelving
Benets o IWI SystemThe use o EcoStud eliminates the thermal
bridging issue associated with systems
incorporating timber and metal studs.
EcoStuds, with their XPS backing, provide
a high level o thermal resistance, which
is comparable to that o the glass mineral
wool insulation ftted between the studs.
For example, the IWI System is almost
13% more thermally efcient than a timber
stud system o the same thickness.
Compared with other internal insulation
methods, the IWI System has the ollowing
additional advantages:
The system components are unaected
by moisture (should the external wall
become damp ater installation)
A minimum number o lightweight, easy
to handle, components are required
System thickness is comparable to
alternative solutions, but greater
thicknesses can be provided simply
by installing two studs, one on top
o the other.
Airtight solution enables maximum
thermal efciency to be achieved rom
the system
Incorporates highly sustainable glass
mineral wool insulation (see page 9)
The glass mineral wool infll has the
maximum Euroclass A1 fre rating to BS
EN 13501: Part 1.
Thermal perormance
A typical 225mm (nine inch) thick
un-insulated masonry external wall with
dense plaster internally will achieve a
U-value o approximately 2.00W/m2K.
The same wall insulated with the IWI
System, using 75mm thick studs, will
achieve a U-value o at least 0.35W/m2K,
an improvement in thermal perormance o
over 80%.
I a typical three bedroom semi-detached
house were to be upgraded in thismanner, it would reduce the carbon
emissions associated with the house by
approximately 2 tonnes per year.
The tables (on pages 6 and 7) give key
thermal perormance data or the system.
Three stud thicknesses are available, 60,
75 and 90mm, which can be combined to
give a variety o thickness solutions.
Double stud installation
Enhanced thermal perormance can beachieved by installing double layers o
EcoStuds. For instance, a combination
o two 75mm EcoStuds will achieve a
U-value o 0.20W/m2K. Ater securing
EcoStud in accordance with the
installation instructions on pages 15 - 18,
screw fx a second EcoStud to the frst
one. Both EcoStuds should be installed in
the vertical position.
When fxing the second EcoStud itis essential that the screws should be
sufcient to ensure a minimum 38mm
penetration into the frst EcoStud. Care
should be taken to ensure that the two sets
o screws are not installed in coincident
positions.
Earthwool EcoBatts and a vapour check
plasterboard are installed in the same
manner as a single stud application.
Features and advantages o the IWI System
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
9/209
Other key issues or the IWI System
Sustainability
The IWI System incorporates glass mineral
wool infll insulation, which has the
ollowing sustainability credentials:
It has the maximum A+ rating in the
BRE Green Guide to Specifcation
The basic raw materials are silica
sand, the earths most common mineral
and recycled glass bottles
It can be recycled at the end o the
buildings lie
Manuactured using ECOSE
Technology, a revolutionary, new,
ormaldehyde ree binder technology,
based on rapidly renewable materials
instead o petro-based chemicals.
It reduces embodied energy and
delivers superior environmental
sustainability.
Supakubecompression packaging
saves energy and delivers more
product per pack
Air leakage
Existing dwellings can suer rom excessive
air leakage which, i not treated, can lead
to high energy costs, occupant discomort
rom draughts and external noise, as well
as a reduction in indoor air quality.
To ensure that upgrading o external
walls is as eective as possible, it is
very important to prevent air leakage
through the structure or at least keep it to
an absolute minimum. Air leakage can
be between the interior and exterior, aswell as between dierent elements o the
building envelope.
Air leakage through the masonry wall
occurs through cracks, gaps where there
is poor adhesion between the mortar and
the masonry units, or diusion through
the masonry units themselves. Where the
plaster has been removed and air leakage
through the wall is thought to be excessive,
it should be tackled beore the IWI System
is installed by applying a parging coat to
the inner surace o the wall.
As the insulation component o the IWI
System is in intimate contact with the
plasterboard, air movement behind the
system should not be great. However, to
prevent unwanted air leakage all junctions
with other elements should be well sealed
with particular attention being paid to
the joints between the IWI System and
window rames. In addition, Knau MultiPurpose Sealant should be used to seal
electric sockets against the plasterboard,
as well as all gaps around plumbing
service penetrations. Any large gaps or
penetration through the dry lining system
can be sealed with expanding oam.
Acoustic perormance
Glass mineral wool is inherently good at
absorbing sound and allows sound energy
to be dissipated within the body o the
insulation. This helps to reduce anking
sound transmission across intermediate
oors and also provides sound insulation
rom external noise sources, especially as
the plasterboard lining provides additional
mass to the existing construction.
The airborne sound insulation
perormance o a solid masonry wall, bothto and rom the exterior, can be improved
signifcantly by installing the IWI System;
a typical improvement o up to 5dB could
be expected. However, to maximise the
improvement in acoustic perormance, it
is important that the installed system is as
airtight as possible (see above).
Thermal mass
Generally speaking the amount o
available thermal mass will not besignifcantly reduced by the installation
o an internal wall insulation system in
most house types. Whilst there are no
defnitive rules as to how much thermal
mass is required, a general rule o thumb
is that the surace area o the walls and
oors providing the mass should be at
least six times that o the area o glazing
in the room. The vast majority o existing
houses will have masonry separating and
partition walls, which provide sufcientthermal mass to help stabilise the internal
environment.
Thus, in a typical mid-terraced property,
where the IWI System is only installed on
the glazed elevations, the thermal mass o
the dwelling is not altered signifcantly by
its installation.
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
10/20
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
11/2011
Avoiding thermal bridging and surace condensation
Thermal bridging
Thermal bridging occurs when the
continuity o the insulation is broken
causing the inner surace o the wall at
that point to become much cooler than
the surace where the wall is insulated.
This typically occurs at the junction o an
external wall and a separating wall or
oor. Thermal bridging can cause
an increase in heat loss, surace
condensation and mould growth
and can be a particular problem in
terraced houses.
Surace condensation
Simply put, surace condensation occurs
when water vapour in the air cools and
condenses (reverts to liquid orm) when
it comes into contact with a cold surace.
Reducing the amount o water vapour
in the air by extracting moist air rom
kitchens and bathrooms and increasing
the surace temperature will prevent
condensation orming on the internal
surace o solid external walls. The
installation o the IWI System will raise
the surace temperature o the walls to
a level whereby condensation will not
orm under usual maximum humidity
conditions experienced in dwellings. As
can be seen rom Figure 2, the warm
surace temperature o the internal
walls (red colour) remains constant
across the EcoStuds, reducing the risk o
condensation orming on cooler suraces.
Figure 2 Thermal contours through the external wall and IWI System (Image generated usingHEAT 3 sotware)
Cold external surace
Warm internal surace
EcoStud Earthwool Ecobatt
Combustion appliances
It is imperative that ventilation
requirements or gas, oil or coal fred
combustion appliances are not
compromised by the installation o the
IWI System and the system does not
interere with the supply o air to the
appliance.
Recommendations, guidance and
compliance with the Building Regulations
or the ventilation o combustion
appliances can be ound in BuildingRegulations Approved Document J -
Combustion appliances and uel storage
systems.
Flues
Care must be taken to ensure that ues
and ventilation measures or gas, oil or
coal fred combustion appliances are
not blocked or adversely aected by the
installation o the IWI System.
Where a ue penetrates the IWI System,the ue can be completely surrounded
and encased by Earthwool EcoBatt which
is a non combustible glass mineral wool
product. The extruded polystyrene content
o EcoStud should not be subjected to
temperatures in excess o 70C.
The ue can be aced with a
non-combustible board, e.g. plasterboard
or cement based board, prior to the
installation o the IWI System. However,i in doubt regarding the surace
temperature o the ue, contact the
manuacturer o the appliance under
consideration.
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
12/20
The junction o the external wall and the
separating wall is the location with thegreatest risk o thermal bridging and
surace condensation. As well as insulating
the external wall, the recommendation is to
partially insulate the separating wall using
a 9.50/17.50mm thermal laminate board
(Polyoam Linerboard) or a distance o
400mm back rom the external wall. This
will prevent excessive heat loss and keep
the surace temperature high enough to
avoid the risk o surace condensation.
Neither external wall nor
separating wall insulated(Figure 3a)
Figure 3a shows the eect o the
separating wall bridging the external
wall. The internal corners are in the yellow
contour and are colder than the main
body o the external wall, increasing the
risk o condensation and mould growth
to occur and urther reducing the thermal
perormance o an already poorly
perorming wall.
External wall and separating
wall only insulated on one
side(Figure 3b)
Figure 3b demonstrates the dierence
between insulating and not insulating
at the separating wall junction with
the external wall. The heat loss
through the un-insulated external wall
is approximately 80% greater than that
through the insulated external wall.
External wall and separating
wall insulated on both sides(Figure 3c)
Figure 3c shows that when both the
external wall and separating wall are
insulated, there is an even temperature
distribution at the separating wall junction
with the external wall. As there are no
yellow or green areas at the surace o
the wall, the suraces are kept warm,minimising the risk o condensation and
mould growth.
External wall insulatedseparating wall un-insulated(Figure 3d)
Figure 3d shows the eect o not
insulating at the separating wall junction
there is signifcant additional heat ow
through the junction and potential or
surace condensation and mouldgrowth to occur.
Figure 3 Thermal contours at the
external wall/separating wall junction(Images generated using HEAT 3 sotware)
Separating walls
Figure 3b Party wall insulated onone side
Un-insulated external wall
Un-insulated separating wall
Both external wall andseparating wall insulated
Plan
Figure 3c Party wall insulated onboth sides
Both external wall andseparating wall insulated
Both external wall andseparating wall insulated
Plan
Figure 3a Party wall without insulation
Un-insulated separating wall
Un-insulated external wall
Plan
Figure 3d External wall insulatedeither side o uninsulatedparty wall
External wall insulatedon both sides
Plan
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
13/2013
Insulation continuity at foors
Suspended timber ground
foorsAn un-insulated suspended timber ground
oor typically accounts or 13% o the
heat loss rom a traditionally constructed
dwelling and should be insulated
whenever possible. Earthwool EcoBatt can
also be used or this application.
The insulation should be the same
depth as the oor joists and ully fll the
available space so as to be in contact
with the underside o the oor deck andtight against the sides o the joists. It
should be supported on netting stapled,
or nailed, to the underside o the joists.
The gap between the last joist and any
walls should also be insulated to maintain
continuity with the IWI System.
I there is a basement or there is a deep
enough sub oor void, the insulation
can be installed rom below and the
netting fxed to the underside o the joists.
Otherwise, the only practical way to
insulate the oor is to lit the oorboards,
orm a cradle by running the netting
over and between the joists and install the
insulation rom above.
To minimise air leakage, the joint between
the oor boarding and the wall should
be sealed using Knau Multi Purpose
Sealant, as should the joint between the
plasterboard and the oor and, fnally,
the skirting board and the oor (Figure 4,page 14). Gaps where radiator pipes and
electric cables penetrate the oorboards
should also be sealed, as should any
gaps between individual tongued and
grooved oorboards.
Where the joints between oorboards are
open, or square edged boards have been
used, a more efcient way o sealing the
oor is to lay hardboard sheets over the
complete oor area.
tIntermediate foors
Insulation continuity
When upgrading external walls, the
insulation layer should be as continuous
as possible across intermediate oors.
Failure to insulate the oor joist zone
results in a major thermal bridge across
the IWI System which signifcantly reduces
the overall thermal perormance o the
external wall.
For example, the eect on the ront
elevation o a typical mid terraced house
insulated with the IWI System would be to
reduce the U-value rom 0.35W/m2K with
the oor zone insulated, to an average o
0.41W/ m2K with an un-insulated oor
zone, equivalent to a 15% increase in
heat loss through the wall.
The loss o thermal perormance can be
avoided by flling the oor zone (i.e. the
ceiling void between the oor boarding
and the ceiling) with Earthwool EcoBattinsulation or a certain distance rom the
external wall, the extent depending on the
direction o the oor joists in relation to
the external wall or separating wall.
Joists parallel with separating wall
Insulation should be installed between
the last joist and the separating wall and
extend along the separating wall by at
least 400mm. Insulation should also be
installed between the joists that are built
into the external wall and extend into
the room by at least 300mm. (Figure 5,
page 14).
As can be seen rom the thermal contours
in Figure 6, page 14, insulating between
the joists o an intermediate oor and
the space between the last joist and the
separating wall (right o diagram) substan-
tially improves thermal perormance,
compared with the un-insulated oor zone
(let o diagram) both through the plainareas o the external wall and through the
separating wall junction.
Joists parallel with external wall
Insulation should be installed between the
last joist and the external wall and within
the frst joist space or the ull length o the
external wall (Figure 7, page 14).
Sealing to prevent air leakage
To ensure that the IWI System achieves its
intended perormance, it is important that
the perimeter joints at the oor and ceiling
are sealed with a continuous bead o
Knau Multi Purpose Sealant.
In particular, the gap between the ooring
and wall and the ceiling and wall should
be sealed, as well as the joint between the
skirting board and the ooring (Figure 8,
page 14). Failure to seal these joints could
result in cold air entering the building
and reducing the thermal and acoustic
perormance o the IWI System.
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
14/20
Figure 5 Floor zone insulation joistsparallel with separating wall
Insulation betweenjoist and wallextending back400mm
Separating wall
External wall
Plan
Figure 6 Thermal contours with and without oor zone insulated(Images generated using HEAT 3 sotware)
External wall
Un-insulated oor zone
Separating wall
Insulation between joistand wall extendingback 400mm
Insulation flling oorzone at least 300mminto the room
Plan
Figure 7 Floor zone insulation joistsparallel with external wall
Insulation betweenjoist and external wall
External wall
Separating wall
Plan
Figure 8 Detail at intermediate timber oor
Insulation ully fllingceiling void
Seal joint betweenooring and wall withKnau Multi PurposeSealant
Seal joint betweenooring andplasterboard/skirtingboard with KnauMulti Purpose Sealant
Insulation installedbetween last joist and wall
Seal joints with KnauMulti Purpose Sealant
Section
Figure 4 Detail at suspended timberground oor
Insulation supportedon mesh /netting
Seal joint betweenooring and wall withKnau Multi PurposeSealant
Seal joint betweenooring andplasterboard/skirtingboard with KnauMulti Purpose Sealant
Insulation installedbetween last joist andwall
Section
Insulation continuity at foors
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
15/2015
Installation o the IWI System
Beore installing the IWI System a
comprehensive property surveyshould be carried out to establish
the condition o the building, its
suitability to receive the system
and identiy any remedial work
needed prior to starting the
upgrade process. At this point
a decision can be made as to
whether an internal or external
wall insulation system is most
appropriate or the property under
survey.
1 Where plaster is sound, fx directly
through it, removing existing skirting
boards i required beore fxing the
EcoStuds (Figure 9). I not sound,
remove decayed plaster and, or
greatest airtightness, seal with a
parge coat. EcoStuds are to be
installed with the OSB acing into the
room.
2 Screw fx EcoStuds horizontally to
the oot o the existing wall as set
out in step 4. These studs should be
positioned so that, i the wall is bowed
or not vertical, the verticality o the IWI
System is maintained. The horizontal
studs should also be located to that the
OSB acing can provide a fxing point
or the new skirting board (Figure 10).
3 Screw fx EcoStuds horizontally at the
head o the wall ollowing the same
process as in step 2. Then, fx EcoStuds
vertically between the top and bottom
horizontal EcoStuds as indicated in step
Figure 11
Figure 9
Figure 10
75mm
600mm600mm600mm600mm
75mm
4, spacing them at 600mm horizontal
centres to coincide with plasterboarddimensions. Ensure that the vertical
studs are cut and installed so as to be
in close contact with the horizontal
studs at oor and ceiling level (Figure
11).
Alternatively, where the ceiling line is
irregular, cut EcoStuds to extend rom
the horizontal EcoStud at the oot o
the wall to tight under the ceiling and
fx as described in step 4. Once the
studs are fxed in position, adhesive
fx EcoStud noggins (using Knau Multi
Purpose Sealant) between the studs at
ceiling level to receive plasterboard
fxings. The adhesive sealant should be
applied to the back and both ends o
the noggins. Alternatively, screw fx the
noggins in position.
4 Fix all EcoStuds to the existing wall
using screws and suitable universal
wall plugs. A minimum fxingpenetration o 40mm is required into
the existing masonry wall (excluding
thickness o plaster). Five fxings per
stud are required but the number
can be increased as required, or as
dictated by site conditions. Position the
fxings at 600mm maximum centres
and 75mm rom the end o each stud
as shown below.
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
16/20
Installation o the IWI System
5 I there are irregularities in the wall
suraces, pack out the EcoStuds usingsuitable materials which are unaected
by moisture. (Figure 12).
6 Friction ft Earthwool EcoBatts (water
repellent glasswool insulation) between
the EcoStuds ensuring the insulation
zone is completely flled. There should
be no gaps between the slabs and they
should be installed so as to be tight to
the plasterboard and ully fll the space
between the studs. (Figure 13). Whereinsulation requires cutting, it should
be cut 5mm wider than the space it is
intended to fll (Figure 14).
7 Once the insulation has been
ftted, screw 12.5mm vapour check
plasterboard to the EcoStuds using
38mm drywall screws, or wood
screws, at nominal 300mm horizontal
and vertical centres, reducing to
200mm centres at corners (Figure 15).Alternatively, fx a separate vapour
control layer ollowed by standard
plasterboard.
Ensure that there is a 3 - 5mm gap
between the plasterboard and the
existing oor to allow space or
sealing, as in step 8. The plasterboard
sheets should be installed ull height
vertically.
8 Seal all joints at the perimeter o the
plasterboard using Knau Multi Purpose
Sealant to prevent air movement
behind the IWI System.
9 Mechanically fx the skirting boards
through the plasterboard to the
horizontal EcoStuds at the oot o
the wall, or fx them with a high
strength instant grab adhesive to the
plasterboard. Seal the skirting to the
oor with Knau Multi Purpose Sealantas a fnal precaution against air
leakage.
Figure 12
Figure 13
Figure 14
Figure 15
Footnote: The plasterboard selected should
be suitable or the activities to be undertakenwithin the space being upgraded. For
instance, where the walls may be subject
to mechanical damage, consider using an
impact-resistant plasterboard such as Knau
Denseshield (vapour check grade).
Pullout strengthPullout strength tests have confrmed that
EcoStud perorms equally to that o metal
or timber studs, 38mm drywall screws
or wood screws should be used when
securing plasterboard to EcoStuds.
Vapour check membraneEnsure all jonts, rips, tears and
penetrations through the vapour check
membrane are sealed prior to the
installation o the plasterboard.
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
17/2017
Wall openings
10 Around openings (windows, doors
etc), screw fx EcoStuds to the wall at
the edge o jambs, sills and heads as
determined by on site requirements
(Figure 16).
11 Line the openings with a thermal
laminate board, preerably, with
a minimum thermal resistance o
0.34m2K/W (e.g. 9.5/17.5mm
Polyoam Linerboard). I there are
thickness constraints due to the size othe window or door rame, install as
thick a thermal laminate board as is
practicable. The edge o the thermal
laminate board should fnish ush with
the ace o the EcoStuds (Figure 17).
12 The thermal laminate boards should be
fxed using adhesive or plaster dabs,
and additionally secured with localised
mechanical fxings. Complete continuity
o insulation should be achieved aroundthe opening at the junctions o heads,
jambs and sills by cutting back the
plasterboard at the edge o the laminate
board (Figure 18).
13 When setting out studs adjacent to
openings in relation to plasterboard
dimensions, make allowance or the act
that the plasterboard needs to extend
beyond the centre line o the jamb stud
to cover the thermal laminate board.For example, the dimension between
the centre lines o the jamb stud and the
next stud needs to be 600mm, less the
thermal laminate thickness (including
adhesive dabs), less 25mm (hal the
stud width) (Figure 19).
Figure 16
Figure 17
Figure 18
Figure 19
Installation at window and door openings
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
18/20
Installation at window and door openings
Figure 20
Figure 21
Stepped or check reveals
14 Install a new window rame towards
the outside o the wall and build out
head and jamb reveals with a suitably
sized timber infll piece to accommodate
the recommended thickness o thermal
laminate board, ensuring a strip o damp
proo membrane is fxed to the back
o the timber using galvanised nails or
stainless steel staples, i.e. between the
timber and the external wall (Figure 20).
15 Fix EcoStuds to the ace o the jambs
and ush with the timber infll piece
and orm a continuous insulated
lining around the opening with the
plasterboard cut back accordingly, as
step 12 (Figure 21).
Internal corner
Internal corners should be installed in
accordance with Figure 22 and the corner
void ully flled with Earthwool EcoBatt. Thecentre o the studs adjacent to the corner
studs should be adjusted to accommodate
the corner detail (Figure 22).
External corner
External corners should be installed in
accordance with fgure 23. In order to
provide additional rigidity at the junction
o the plasterboard linings a timber batten
(minimum 25mm x 25mm) should be
screwed fxed in position as indicated andthe corner void ully flled with Earthwool
EcoBatt. The centre o the studs adjacent
to the corner studs should be adjusted to
accommodate the corner detail (Figure 23).
Plasterboard nishing
techniquesTaping and jointing
In order to accommodate a taped and
jointed fnish, taper edged plasterboards
should be installed. Ater applying a primer
coat over the plasterboard and joints, a
reinorced tape and jointing compound
should be used to achieve a seamless
fnish. Knau Drywall provides a
comprehensive range o jointing
compounds and tapes.In all instances ollow the plasterboard
manuacturers instructions.
Skimming
A 2 to 5mm veneer coat o Knau
Multicover or Knau Universal Board
Finish can be applied to the ace o the
plasterboards. The board joints should be
reinorced with paper or fbre tape.
Decoration
Follow manuacturers instructions regarding
priming requirements prior to the installation
o wallpaper or specialist coverings.
Tiling
Face EcoStuds with Knau Moistureshield
or Aquapanel when installed in humid
or wet areas such as kitchens and
bathrooms. The weight o tiling (including
adhesive) fxed direct to plasterboard
(without plaster skim) should not
exceed 32kg/m2. Follow guidance
and recommendations rom tilingmanuacturers and BS5385 accordingly.
Figure 22
600mm
600mm
Figure 23
600mm
600mm
25x25mm (min)timber batten
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
19/2019
Electric cables
Electric cables give o heat when in use
and should be routed where they will not
be covered by thermal insulation, so the
heat can be dissipated. I cables need to
be located within insulation, they should
be run in conduit and possibly increased
in size. Advice on this should be sought
rom a suitably competent person, such as
a qualifed electrician.
PVC-insulated cables should be located
in suitable conduit to avoid being indirect contact with extruded polystyrene
insulation in order to prevent plasticiser
migration which can cause loss o
protection to the conductors.
Socket outlets
When socket outlets on the existing
external wall need to be repositioned on
the new EcoStud lining, it is likely that the
existing cables will need to be extended.
Extending cables in this manner is notclassifed as notifed work (according
to Approved Document P, 2006 Design
and installation o electrical installations)
and can be carried out by a suitably
competent person. All electrical work
should be carried out in accordance
with Approved Document P, the relevant
part o the current IEE Regulations and
associated Guidance.
Note: As with all electrical work, i at all in
doubt consult a suitably competent person such
as a qualifed electrician.
Socket and switch boxes
Socket and switch boxes should be fxed
into the plasterboard lining in accordance
with the manuacturers instructions.
Plasterboard and drywall socket and
switch boxes simply clip into place when
inserted into a pre-prepared opening.
When the ace plate is tightened onto
the socket box, the box grips against theplasterboard. Beore the ace plate is
fnally fxed, the boxes should be sealed
against the plasterboard using Knau Multi
Purpose Sealant to prevent air leakage(Figure 24).
Figure 24 A plasterboardsocket box
Heating radiators
Thermally upgrading the external wall in
a room may provide an opportunity to
have a smaller radiator and re-position
it on an internal wall. Alternatively, it
may be possible to replace wall hung
radiators with skirting radiators. Further
inormation should be obtained rom, or
instance, a heating engineer or radiator
manuacturer.
Fixing radiators
Do not fx radiators to plasterboard alone.
Sufcient support is provided only when
radiator brackets are fxed:
Through the plasterboard into the
EcoStuds
To horizontal timber battens, fxed
through the plasterboard to the
EcoStuds
To horizontal timber battens, fxed
between the EcoStuds and to the
masonry wall To Knau Drywall Fixing Channels,
screw fxed to the EcoStuds behind the
plasterboard
To the masonry wall using suitable
stand-o fxings.
Timber battens are suitable or loads up
to 75kg per metre run acting parallel to
the plasterboard and should be used or
heavier radiators.
Knau Drywall Fixing Channels aresuitable or loads up to 50kg per metre
run acting parallel to the plasterboard and
can be used or small radiators.
Picture rails and dado rails
Picture rails and dado rails should be
removed beore installing the IWI System
as they will prevent the EcoStuds being
fxed tightly against the wall. However,
picture rails and dado rails can be fxed
to the new plasterboard lining using an
instant grab adhesive ater installation o
the IWI System, or the rails can be fxed to
the EcoStuds using suitable screws.
Fixing to plasterboard
Light to medium weight items such as mirrors,
pictures, shelving and curtain poles can be
fxed in position using standard sel drilling,
winged or toggled plasterboard fxings and
fxings such as Knau Drywall anchors which
are suitable or loads up to 20kg acting
parallel to the plasterboard. For heavier
items, such as kitchen cupboards, specialist
heavy duty cavity anchor fxings should be
used. Universal wall plugs are also suitable
or use with shelving and cabinets. Heavier
items can also be secured by fxing back to
the masonry wall using proprietary stand-o
fxings or a suitably sized standard screw.
Alternatively, screw fxing a 10 - 18mm
plywood sheet to the ace o the EcoStuds
over the entire wall area (beore fxing the
vapour check plasterboard) provides a
solution to a wide range o fxing problems.
NB: I in any doubt as to the suitability o fxings,
consult the fxings manuacturer.
Accommodating xtures and ttings
7/31/2019 Brochure Internal Wall Insulation System Design Guide March 2010
20/20
RBB119909
Knau Insulation Ltd Customer Service (Sales) Technical Advisory Centre LiteraturePO Box 10 Tel: 0844 800 0135 Tel: 01744 766 666 Tel: 08700 668 660Staord Road Fax: 01744 612007 Fax: 01744 766 667 Fax: 0870 400 5797St Helens Email: [email protected] Email: [email protected] Email: [email protected] www.knaufnsulation.co.ukWA10 3NS
Knau Insulation LtdPO Box 10 Staord RoadSt HelensMerseysideWA10 3NS
www.knaufnsulation.co.uk
Email: [email protected]
Tel: 01744 766 600
This brochure is printedon 80% recycled paper
When you h ave finishe d withthis brochure please recycle it
80%
Knauf Insulation supports the
Great British Refurb Campaign.
www.greatbritishrefurb.co.uk