Risk Management
Project Risk
Staff Turnover - (Risk: Likely / Impact: Extreme / Manage as Emergency)
Would effect development of App
May take time to replace – hence project delayed
Prevention:
Tie down staff to Project Contract
Document while developing and within coding
Functionality - (Risk: Unlikely / Impact: Extreme / Manage as Proactively)
Too much functionality, not easy to navigate – could delay delivery date
Prevention:
Strip out functionality not required
Project Risk
Security - (Risk: Unlikely / Impact: Extreme/ Manage as Systematically)
Information can be taken, changed/deleted
Would damage BT’s image as provider of wifi and telephone services
Prevention:
Talk to BT and explain more time required, before launch
Poor Productivity - (Risk: Unlikely / Impact: Medium/ Manage as Proactively)
All it takes is one of the team members to produce poor work
Prevention:
Should have a back up plan/resources/quality control/document all steps/ QA
Business Risk
Content Suitable for Students & Corporate - (Risk: Medium / Impact: Medium / Manage as Strategically)
These are 2 different target markets, difficult to produce content for both
Prevention:
Talk to stakeholders and incorporate them into design process.
Monitor traffic once application is launched, Analytic tools.
50th Anniversary - (Risk: Medium / Impact: Medium / Manage as Strategically)
The focus of the Market Manager is through Linked In
Prevention:
Run a Google Ad Campaign
Facebook Page for BTYS
Business Risk
BT Resources - (Risk: Medium / Impact: Medium / Manage as Strategically)
After October 2012 BT will have to commit to resources for implementing the App
Prevention:
Team should be involved again at this stage
Year Round Exposure- (Risk: Medium / Impact: Medium / Manage as Strategically)
The App needs to change throughout the year to avoid becoming stale
Prevention:
Team need to be involved
Technical Risk
Scoping - (Risk: Unlikely / Impact: High / Manage as Systematically)
It’s not clear if the project was scoped out correctly at the start
Prevention:
Establish requirements and have BT sign off on them.
Testing/Debugging - (Risk: Likely / Impact: Medium / Manage as Systematically)
As this is a new App and functionality is changing this area is hard to estimate
Prevention:
Development & QA need more time
Compatibility - (Risk: Unlikely/ Impact: Medium / Manage as Proactively)
All Software features e.g. graphics need to be supported by IOS4&5 and HTML5
Prevention:
All features should be tested on the above platforms
Technical Risk
Synchronizing - (Risk: Likely / Impact: Medium / Manage as Systematically)
It’s not clear how BT systems will be integrated.
Prevention:
This will need to be tested and will be time consuming.
Security During the Event - (Risk: Unlikely / Impact: High / Manage as Extreme)
Can the systems handle the traffic
Prevention:
Needs to be fully tested over & over again.
Back Up Plan - (Risk: Unlikely / Impact: High / Manage as Emergency)
If App fails on the day what contingency plan is in place.
Prevention:
Need to discuss with BT.
Reputational & Political Risks
App Performance - (Risk: Unlikely / Impact: Extreme / Manage as Emergency)
Negative exposure for BT
BT will loose its year-round exposure
BT wouldn’t use Digital Skills Academy again
Prevention:
Test using large numbers e.g. students in Digital Hub
Identify critical path tasks
Negative Posts on Social Media Sites - (Risk: Likely / Impact: Medium / Manage Systematically)
Effects the event and sponsors in a negative manner
If not dealt with can escalate further
Prevention:
Embrace the negative comments
Make the relevant changes
Documentation/Training
Hand Over Document - (Risk: Unlikely / Impact: Extreme / Manage as Emergency)
It’s not clear if there is one
Training document required for BT staff
Prevention:
Document needs to be drawn up
Training plan needs to be put in place
Nature Risks
Disaster Recovery Plan - (Risk: Unlikely / Impact: Extreme / Manage as Emergency)
Fire
Flooding
Prevention:
Back up Off-Site
Daily, Weekly, Monthly.
Always use version control
Four Main Phases of BTYS Project App
Preparing for the Project• Deliverable – Specification/Scope stick to clients brief and sign off.• Delivery Date – October 2012 with LIVE DATE Jan 2013 doesn’t make sense• Budget – seems to be no budget or is there• Acceptance of Project – the Team seemed to change from the brief given.
Setting up the Project• Project Implementation Plan – Final delivery in October 2012• Technical Solution – kept changing, yet the technologies talked about are not new.• Any Contracts, Terms & Conditions – seems to be only to meet October deadline.
Implementing the Project• Risks Monitored – continuous monitoring• Manage Contract – contract seems to finish in October, 3 months before LIVE DAY• The deliverable date is October for the Team.
Review Project Implementation• Structured Review this is clearly something that the team cannot do• Requirements Met? How do they know if the requirements are 100% met, until LIVE DAY• Lesson’s Learned – if the team is not going to be around how will they be able to identify• What went wrong? – Only when the App goes LIVE will you ever know 100% what went
wrong
Conclusion
BTYS Digital Skills Academy Team
Main Risk is that Team is finished in Oct 2012