Line Item # 1 2 310 Planning $4,800.00
10.10 Staff Salaries $4,800.00
10.10.01 Project Management - Planning $4,307.00 Project Management - Transportation Planning
10.10.02 Survey
10.10.03 15% (Conceptual) Design $493.00 Transportation Planning - scoping
10.10.04 Program Planning
10.10.05 Environmental
10.10.06 Communication & Civic Engagement
10.15 Consultants $0.00
10.15.01 Project Management - Planning
10.15.02 Survey
10.15.03 15% (Conceptual) Design
10.15.04 Program Planning
10.15.05 Environmental
10.15.06 Communication & Civic Engagement
10.20 Miscellaneous $0.00
10.20.01 Miscellaneous
10.99 Contingency - Planning $0.00
10.99.99 Contingency
20 Architecture & Engineering $40,461.00
20.10 Staff Salaries $40,461.00
20.10.01 Project Management - Design
20.10.02 30% Design $20,000.00 Engineering Bureau - Design 30% (approx.)
20.10.03 60% Design $10,000.00 Engineering Bureau - Design 60% (approx.)
20.10.04 90% Design $10,000.00 Engineering Bureau - Design 90% (approx.)
20.10.05 100% Design $461.00
Engineering Bureau - Design 100%, Construction
Procurement
20.10.06 Construction Manager Review
20.10.07 Plan Review
20.10.08 Communication & Civic Engagement
20.15 Consultant $0.00
20.15.01 Project Management - Design
20.15.02 30% Design
20.15.03 60% Design
20.15.04 90% Design
20.15.05 100% Design
20.15.06 Architect / Engineer
20.15.07 Geo-Tech
20.15.08 Commissioning
20.15.09 Miscellaneous
20.15.10 Maintenance Capital 1
20.15.11 Maintenance Capital 2
20.15.12 Maintenance Capital 3
20.15.13 Maintenance Capital 4
20.15.14 Maintenance Capital 5
20.15.15 Maintenance Capital 6
20.15.16 Maintenance Capital 7
20.15.17 Maintenance Capital 8
20.15.18 Maintenance Capital 9
20.15.19 Maintenance Capital 10
20.20 Utilities $0.00
20.20.01 Utilities
20.25 Hazmat Survey $0.00
20.25.01 Hazmat Survey
20.99 Contingency - Architecture & Engineering $0.00
20.99.99 Contingency
30 Land Acquisition & Right of Way $0.00
30.10 Staff Salaries $0.00
30.10.01 Easement/ ROW Plat Preparation
30.10.02 Real Estate
30.10.03 County Attorney
30.15 Consultants $0.00
30.15.01 Easement/ ROW Plat Preparation
30.15.02 Real Estate
30.20 Land $0.00
30.20.01 Land
30.99 Contingency - Land Acquisition & Right of Way $0.00
39.99.99 Contingency
40 Construction $67,476.00
40.10 Staff Salaries $8,778.00
40.10.01 Project Management - Construction
40.10.02 As-Builts
40.10.03 Construction Stakeout
40.10.04 Construction Management $8,778.00
Engineering Bureau - includes stake-out & general
engineering support (from final estimate)
40.10.05 CA Services
40.15 Contracted Services $58,523.00
40.15.01 Project Management - Construction
40.15.02 As-Builts
40.15.03 Construction Stakeout
40.15.04 Construction Management
40.15.05 CA Services
40.15.06 Prime Contractor $58,523.00 Ardent Company (includes contingency)
40.15.07 Utilities
40.15.08 FF&E
Notes/Description
Budget Line Items Line Item
Budget Totals ($)
Line Item # 1 2 3 Notes/Description
Budget Line Items Line Item
Budget Totals ($)40.15.09 Security
40.15.10 Maintenance Capital 1
40.15.11 Maintenance Capital 2
40.15.12 Maintenance Capital 3
40.15.13 Maintenance Capital 4
40.15.14 Maintenance Capital 5
40.15.15 Maintenance Capital 6
40.15.16 Maintenance Capital 7
40.15.17 Maintenance Capital 8
40.15.18 Maintenance Capital 9
40.15.19 Maintenance Capital 10
40.20 Construction and Administration $0.00
40.20.01 Construction and Administration procurement
40.25 Permits & Fees $175.00
40.25.01 Permits & Fees $175.00 VDOT permit fees
40.30 Commissioning $0.00
40.30.01 Commissioning
40.35 3rd Party Inspection $0.00
40.35.01 3rd Party Inspection $0.00
40.40 Infrastructure Technology $0.00
40.40.01 Infrastructure Technology
40.45 Miscellaneous $0.00
40.45.01 Miscellaneous
40.99 Contingency - Construction $0.00
40.99.99 Contingency
50 Relocation and Temporary Facilities $0.00
50.10 Staff Salaries $0.00
50.10.01 Staff Salaries
50.15 Consultants $0.00
50.15.01 Consultants
50.20 Resident Relocation $0.00
50.20.01 Resident Relocation
50.25 Miscellaneous $0.00
50.25.01 Miscellaneous
50.99 Contingency $0.00
50.99.99 Contingency
60 Equipment, Furniture & Fixture $0.00
60.10 Staff Salaries $0.00
60.10.01 Staff Salaries
60.15 Consultants $0.00
60.15.01 Consultants
60.20 FF&E $0.00
60.20.01 FF&E
60.25 Infrastructure Technology $0.00
60.25.01 Infrastructure Technology
60.99 Contingency- Equipment, Furniture & Fixture $0.00
60.99.99 Contingency
70 Vehicles $0.00
70.10 Staff Salaries $0.00
70.10.01 Staff Salaries
70.15 Consultants $0.00
70.15.01 Consultants
70.20 Vehicles $0.00
70.20.01 Vehicles
70.99 Contingency - Vehicles $0.00
70.99.99 Contingency
80 Operating Costs Funded from TCF $0.00
80.10 Staff Salaries $0.00
80.10.01 Staff Salaries
80.15 Other $0.00
80.15.01 Other
$112,737.00
$146,000.00 from 4/20/16 CIP (WalkArlington)
$33,263.00Variance
Total Cost Estimate - Current
Total Cost Estimate - CIP
$0.00
$50,000.00
$100,000.00
$150,000.00
$200,000.00
Project Costs
PROJECT COSTS VS BUDGET
Total Cost Estimate - Current Total Cost Estimate - CIP