Budgeting for Plant Maintenance 1) You can set the budget for a Maintenance order . 2) You have to create a dedicated cost centre for a Maintenance order . 3) So that everytime you create a maint order the cost is booked in that respective cost centre .
Transcript
Page 1: Budgetting for pm .

Budgeting for Plant Maintenance

1) You can set the budget for a Maintenance order .2) You have to create a dedicated cost centre for a Maintenance order .3) So that everytime you create a maint order the cost is booked in that respective cost centre .

Page 2: Budgetting for pm .

You have to create aBudgetting Profile

In SPRO

Page 3: Budgetting for pm .
Page 4: Budgetting for pm .

Here enter the time frame like how u want to set the Budget. Don't Put any decimal place .Put start filed as

(1) For a current year .

Save .

Page 5: Budgetting for pm .

Assign the created Budget profile ,And the cost centre in Which you will maintain the budget .

Page 6: Budgetting for pm .

Enter your budget Month wise or Yearly

For yearly budget

Page 7: Budgetting for pm .

Here you can put your Budget Anually.

Save it .

Page 8: Budgetting for pm .

Create a Maint orderand we will see the cost of

Spares,Activity cost, Planned Cost /Actual cost / Budget .

Page 9: Budgetting for pm .
Page 10: Budgetting for pm .

Enter all you r details for the maintOrder. Also very important is youEnter the cost centre in location

Tab above

Page 11: Budgetting for pm .

In operation Tab enter the activity done for the order Here also put the activity type .In which you decide the

Cost per hour of your Technician.

Page 12: Budgetting for pm .

In the component Tab put the spares used for the order.

Release and save the order youWill get the planned cost .

Page 13: Budgetting for pm .

Planned cost

Page 14: Budgetting for pm .

Now you do goods issue forthe spares and do the activity

confirmation .So that you capture the actual cost .T-code- Migo( For G/I)T-code- IW37 For optn

confirmation

Page 15: Budgetting for pm .

Post it

Page 16: Budgetting for pm .

T- code IW37operation confiramation

Page 17: Budgetting for pm .
Page 18: Budgetting for pm .

Select the operation and pess the tab Individual confirmation

Page 19: Budgetting for pm .

You can also do the collective confirmation .if incase your Activity is more .

Page 20: Budgetting for pm .

Enter the Actual time taken for Completing the activity and tick final

Confirmation .

Page 21: Budgetting for pm .

Now you had got the Actual cost .If you want to see the Plan/Actl press the tab above

Page 22: Budgetting for pm .
Page 23: Budgetting for pm .

For Budget / Actual.T- code –

S_ALR_87013648

Page 24: Budgetting for pm .

Enter the controlling area and execute the budget

Page 25: Budgetting for pm .

Here in cost centre 1703 work shop maint you Can see the budget /Allotted / Available