+ All Categories
Home > Documents > Building Control Regulations (Amendment) 2014 · 2014-01-27 · Building Control Regulations...

Building Control Regulations (Amendment) 2014 · 2014-01-27 · Building Control Regulations...

Date post: 18-Jun-2018
Category:
Upload: lethuan
View: 224 times
Download: 0 times
Share this document with a friend
58
Building Control Regulations (Amendment) 2014 Engineers Ireland Fire Safety Division 22 nd January 2014 Calum McMillan [email protected]
Transcript

Building Control Regulations (Amendment) 2014

Engineers Ireland

Fire Safety Division

22nd January 2014

Calum McMillan

[email protected]

2

Building Control Regulations | Overview

Building Control Regulations | Overview

1 - Recent Events and updates

- What’s been happening lately

- When does the new system begin

2 - A look back at the old system

- The requirements

- Certification

3 - Where we’re going:

- Building Control (Amendment) Regulations 2014.

- Key Reforms

- The Code of Practice

- Roles and responsibilities

3

Building Control Regulations | Overview

Building Control Regulations | Overview

4 – The Challenges

- What does the future hold?

- Will the system work?

- How do we compare with elsewhere?

5 – Summary and Open Forum

Recent Events and Updates

5

1 - Recent Events and Update

SI 80 signed into law March 2013

Significant Error (s) in this SI

Allowed 2nd Round of consultations

SI 80 to be revoked and replaced with SI 9

6

1- Recent Events and Update

- Text stated they applied to dwellings under 40sqm

- The wording of the certificates had altered and were considered unworkable i.e. Gave a 100% guarantee

SI 80 signed into law March 2013

Significant Error (s) in this SI

Allowed 2nd Round of consultations

SI 80 to be revoked and replaced with SI

9

7

1 - Recent Events and Update

- Triggered the opportunity for renewed consultations

- RIAI, CIF, IEI, ACEI and RICS

- Senior Council

- Negotiations from July to November with close meeting in December

SI 80 signed into law March 2013

Significant Error (s) in this SI

Allowed 2nd Round of consultations

SI 80 to be revoked and replaced with SI

9

8

1- Recent Events and Update

- Changes have been made to both the code of practice and the Regulations

- New SI 9 Signed off by minister and expected to be published this week.

SI 80 signed into law March 2013

Significant Error (s) in this SI

Allowed 2nd Round of consultations

SI 80 to be revoked and replaced with SI

9

9

1 - Recent Events and Updates

- New SI to be formally published (expected later this week) – hot of the press,

- The Code of Practice is still in draft format

- There is no agreed wording for ancillary certificates

- The National E – Lodgement & Registration System is being implemented in phases

- These Regulations apply to all projects if the commencement notice is lodged on or after 1st March 2014!

10

The New Building Control Regulations shall be applied to:

- The design and construction of a new dwelling

- The extension to a dwelling involving a total floor area greater than 40sqm

- Works to which part III applies i.e. require a fire safety certificate *

11

Building Control Regulations (Amendment) 2014

2 -A look back at the current system

Building Control Acts

1990 & 2007

Building Regulations Building Control

Regulations 1997-2009

Technical Guidance

Documents

Commencement notices

Fire Safety Certificates

Disability Access

Certificates

7 day notices

Lodgement of Plans

Design Certificates

Notices of Assignment

Undertaken certificates

Completion Certificates

Validation by BCA

Site Inspection Plan

Public Register

CODE OF PRACTICE

(Inspection and Certifying)

2 -A look back at the old system...

"Those who cannot learn from history are doomed to repeat

it." George Santayana

13

Typical Project Plan – The Old System

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

Fire Engineer appointed

Lodgement and award of FSC

Application

Review design development?

Review tender specs?

Typical

Only

optional Site Role? Witnessing and

commissioning?

Certification?

2 -A look back at the current system

14

Standard Opinions of compliance (SE 9101)

- Quite often based on visual (non evasive) inspection and substantial compliance

- Could be qualified based on scope and appointment

- Reliant on other certificates outlined in the schedule

- SE 9101 Conditions clause – average frequent of site visits is “normally fortnightly

2 -A look back at the current system

15

Was the old system working?

- Property boom led to some poorly designed and constructed buildings*

- Opinions of substantial compliance issued can be qualified – little accountability and nobody to sue.

- Huge amount of public pressure

- “A rolling set of guarantees” “Traceability” “accountability”*

2 -A look back at the current system

3 - Where we’re going...

17

3 - Where we’re going… Overview:

- Typical project plan and the implications

- Major reforms

- Roles and responsibilities

- The Code of Practice

18

Typical Project Plan – Where we’re going

3 –Where we’re going

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

19

Typical Project Plan – Where we’re going

3 –Where we’re going

Appoint team

Ensure team is

competent and will

adequate resources are

made available to

design, construct, certify

and inspect the building

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

20

Typical Project Plan – Where we’re going

3 –Where we’re going

FSC Application

Commencement

notice

GA plans, sections and

elevations

Assessment of proposed

approach to comply with BR’s

via online management system

Preliminary inspection plan

Schedule of plans and

specifications

Certificate of design and

notices of undertakings

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

21

Typical Project Plan – Where we’re going

3 –Where we’re going

Implementation of inspection

plan

Identify and inspect at agreed

milestones including testing

Ensure records of inspection

and close out non compliances

FSC Application

Commencement

notice

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

22

Typical Project Plan – Where we’re going

3 –Where we’re going

Submission of Certificates of

completion

Submission of amended plans,

specs etc

Submission of implemented

inspection plan

BCA Validation before building

can be occupied

FSC Application

Commencement

notice

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

23

Typical Project Plan – Where we’re going

Fire Engineer appointed

Lodgement and award of FSC

Application

Review design development?

Review tender specs?

Site Role? Witnessing and

commissioning?

Certification?

3 –Where we’re going

Typical

Only

optional

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

24

Typical Project Plan – Where we’re going

Fire Engineer appointed

Lodgement and award of FSC

Application

Review design development?

Review tender specs?

Site Role? Witnessing and

commissioning?

Certification?

3 –Where we’re going

Typical

Only

optional

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

25

Typical Project Plan – Where we’re going

Project Kick off

Concept to Scheme Design

Design Development

Tender

Construction

Completion

Fire Engineer or person

responsible for that Part B

3 –Where we’re going

26 Major Reforms

2. Submission of

plans &

documentation

1. Mandatory

Certification

3. Mandatory

Inspection 4. Role of Building

Control

27

1. Mandatory Certification

and undertakings

28

Commencement/

Design stage

Lead Design

Certifier

Ancillary Design certifiers

Completion

Stage

Site inspection plan

Assigned Certifier

Ancillary completion certifiers

Ancillary Design Certificate

Builder undertaking

Building Owner undertaking

Ancillary Certifier

undertaking

Building Certificate of compliance

Construction

29

Design Certificate

Mandatory Certificates of Compliance

Designer:

Design Certificate

- This will certify the design for all parts of Building Regulations (Parts A-M).

- The will rely on ancillary certification (back to back).

- It will be a single named person – on behalf of company

30 Mandatory Certificates of Compliance

Assigned Certifier:

Undertaken to inspect

and certify

- Undertaking in compliance with the code of practice

31 Mandatory Certificates of Compliance

Assigner Certifier:

Completion Certificate

of Compliance

- Confirmation or undertaking in compliance with the code of practice

32

Who is qualified to sign a design certificate or act as an assigned certifier?

- Registered Architect

- Chartered Engineer

- Registered Building Surveyor

- Must be a Competent Person

- There is no qualtification requirement for ancillary certifiers

- There is currently no template of the certificate in the Regs of CoP.

Mandatory Certificates of Compliance

33 Submission of plans and documentation

2. Submission of plans &

documentation

34

Submission of Plans and design documentation

At Commencement: - GA’s

- A Schedule of design documents currently prepared or to be prepared,

- An online assessment plan of the proposed approach to comply with Building Regulations A-M via the BCMS,

- The preliminary Inspection plan

- Certificates as noted previously

- No general requirement for detailed specifications, structural drawings or calculations omitted but must keep a record of these

Submission of plans and documentation

35

Lodging of Plans and design documentation

At Completion

- Plans, specifications and particulars, for any amendments from

those submitted at commencement stage or during the course of the works, are submitted by the assigned certifier,

- The inspection plan as implemented,

- Certificates of compliance as noted previously

Submission of plans and documentation

36 Mandatory inspection

3. Mandatory Inspection

37

Mandatory Inspection

- Assigned Certifier must inspect and coordinate the inspection by other sub certifiers

- The role is not to supervise the builder

- Assigned Certifier may be independent from designer

- Assigner Certifier must develop:

- Site Inspection Plan of appropriate intensity and frequency

- Agree a Inspection Notification Framework with Client and Builder - Identify items or stages of work for notification - Identify Ancillary certifier stages

Mandatory inspection

38 Mandatory Inspection

- The inspection plan will be dependent on a risk assessment and professional judgement relating to items such as:

- Type of building, construction, expertise of builder, - The complexity of the construction method, - Based on experience on non compliance issues - The impracticality or impossibility of subsequent inspection of

closed up work - Related to serious consequences

- Must include inspection of (amongst others): - Elements and components, the failure of which would, be

significant, - Work relating to fire safety, - Any work if not verified would be serious detrimental to the

fundamental purposes of the BR’s

Mandatory Inspection

39 Mandatory Inspection

- Inspection frequency - Scope and frequency formally written into the plan - Include critical milestones, not just periodic visits - This is a “live” document – constantly reviewed.

- Inspection Notification Framework (INF) - Agreement between AC, Building owner and builder before

commencement - Identify stages of work where notification is needed for

inspection and tests - Prepared in conjunction with designer and ancillary certifiers

- Closing out of non conformances

- Maintain Records as evidence of Inspection

Mandatory Inspection

40 The Role of Building Control

4. The Role of Building

Control

41

The Role of the Building Control Authority

- Validation of commencement notices and associated documentation

- No obligation but have the powers to carry out a technical

assessment at commencement or completion - Assessment should be based on risk and random selection

- Validation of completions certificates,

- It is not appropriate for the BCA to carry out a technical

assessment at this stage - Checking certs signed and completed, - No unresolved issues

The Role of Building Control

42

The Role of the Building Control Authority

- BCA’s are expected to carry out a certain level of assessment and inspection – 15%

- Inspections to include at least 4 key milestones

- Inspections based on risk assessment

- Responsibility remains with AC, Builders, Designers and Builder Owners

- To determine disputes referred by Ancillary Certifier

The Role of Building Control

43

Challenges for Building Control Authority

- A Frameworks for BCA’s is in draft to establish roles and Duties

- Risk assessment approaches to be adopted

- Consistency and standardisation

- Inspection and reporting systems to be implemented.

- Resources.

The Role of Building Control

44

Roles and Responsibilities Roles Responsibilities Certificates

Building

Owner

- Appoint relevant and competent persons (designer,

builder and AC)

- Ensure adequate resources

- Commencement

notice

- Declaration of

appointment

Lead Designer - Design their element and provide documentation

- Coordination of ancillary designers and associated

certificates

- Advice relating to proposed inspection regime plan

- Maintain records of design and inspection

- Design Certificate

- Collate Ancillary

Design Certs

Assigned

Certifier

- Inspect and certify works (Maybe)

- Identify all sub certificates and specialists required

- Coordinate all ancillary certifiers

- Plan and oversee inspection plan

- Single point of contact for BCA

- Undertaken

certificate

- Completion

certificate

- Collate Ancillary certs

Builder - Build in accordance with submitted plans and

specifications

- Appoint competent persons to oversee works

- Facilitate inspection plan

- Undertaken

certificate

- Completion

certificate

BCA - Validate the documentation submitted

- Inspections based on risk assessment

- None

How do I ensure compliance with the new system?

- Under Article 20 (g) of BCR’s the Code of Practice this shall, prima facie, indicate compliance with the requirement of these BC Regulations

- Similar status to TGD’s

- Still in Draft with a number of changes made since original

- Subjective and open to interpretation.

What does the future hold and will the new system work?

48

Will it be successful and are we doing enough?

- Only time will tell, but……

- It’s still self certification but with mandatory requirements

- It will undoubtedly lead to better practice and support a “culture of compliance”

- Who will take on the relevant roles?

- Can the Market absorb the additional cost?

- Does it achieve the Ministers goals?

- Consumer protection?

- Will still require costly and drawn out litigation,

- Latent defects insurance

- In terms of fire safety, is it enough?

- Fire Risk Assessments – mandatory

49

What the Future holds for Ireland

- Mandatory Registration of builders (code of conduct, oversight insurance, entry standards, sanctions)

- Approved inspectors from private sector (med – long term)

- Third Party Impartial certification or peer reviews

- Latent Defects Insurance - cover against defective design, materials or workmanship that are only discovered after construction of a building is complete

- Regular Review of the new system

50

How do we compare with other countries?

51

England and Wales

- AHJ – Building Control (or Approved Inspector in England) Fire Service for non-compliant or fire fighting items

- Fire Strategy Report is typically submitted to AHJ at scheme design stage for ‘in principle approval’

- Works can commence without this

- Fire Engineer does not have a role on siteto comply with legislation

- AHJ must be invited to visit the site but don’t need to go

- Building control or Approved inspector may issue completion of works

- Legal liability generally lies with the Builder

52

Scotland

- AHJ – Building Control Fire Service for non-compliant items

- Fire Strategy Report is typically submitted to obtain building warrant before commencement

- Fire Engineer does not need to have a role on site (site inspection) to comply with legislation

- AHJ typically do visit the site

- Applicants does submit Cert of Completion which is accepted or rejected by AHJ (typically contractor)

53

UAE

- AHJ – Fire Service in UAE known as Civil Defence

- Fire Strategy submitted and approved by House of Expertise (Third Party) and then AHJ prior to construction stage and additionally, prior to handover.

- Fire Engineer/Architect of Record have a formal role on site in UAE (incl. inspection and testing).

- AHJ typically do visit the site prior to h/over

- Generally 3 stage approach: Fire Engineer/Architect of Record,

House of Expertise (third party) and the AHJ Certify the works.

54

Australia

- AHJ – Accredited Certifier (generally private certifier)

- Fire Engineering Report (produced only if non-compliant items) must be submitted to AHJ at detailed design stage for approval

- Fire Engineer does not have a role on site to comply with legislation (except NSW); however AHJ typically request this regardless

- AHJ certify the work is complete in accordance with the regulations; AHJ issue Occupation Certificate (OC)

- AHJ do visit the site regularly; the Fire Service will typically visit the site at completion

- Building does need OC from AHJ prior to h/over

55

USA

- AHJ – Fire Service and Building Control

- Full construction documents must be submitted to AHJ for approval and permit prior to commencement

- Fire Engineer does have a role on site to comply with legislation

- The designer of a particular system certifies the work is complete in accordance with the regulations, plans, specs and codes

- AHJ do visit the site; the Fire Service typically at the end of construction stage for final testing

- A Certificate of Occupancy (CO) is normally required prior to occupancy provided by AHJ.

- AHJ rely on Certs from contractors and designers - in providing CO.

56

Summary

• The new system is a game changer for the industry (a lot of these should be getting done in the current system)

• The system will be in place for any commencement notice lodged on or after 1st March 2014,

• SI 9, 2014 has been signed off but other critical parts are incomplete

• Your scope will need to change accordingly

• Still Self certification but with a clear line of accountability

Thank You for Your Time

Questions?

58

Disclaimer

This presentation is for educational purposes only. It is designed to provide

general information and is not intended to be a complete or exhaustive narrative

of the Building Control Regulations. Recipients should not rely on the content

and we accept no responsibility for such use. These slides may not be used or

copied without the express written consent of Arup.


Recommended