Date post: | 01-Jan-2016 |
Category: |
Documents |
Upload: | chase-lyons |
View: | 25 times |
Download: | 2 times |
Building for Learning ProjectPhoto Progress Report 5
December 2009 – February 2010
Project commencement 21st September 2009
Mid January – more minor demolition and framing
Fire services installed and stairway brickwork
Hooray - Admin completed!!!!!!
Former student work (maths and French) dating back to 1922 found in building cavities from demolition
1st Storey wall frames going up
Ground floor ceiling struts and power box installed
1st Storey Wall Framing – well underway
While the photos don’t show it – several days of +40c
Final part of old roof replaced with addition of new 1st Storey roof – February 2010
Finally the last of the timber singles!!!
With the final part of the roof replaced, the last big cleanup of all the 100+ years of accumulated dust, possum poo,
birds nests, etc from the classroom below
More scaffolding as the stairway and lift get built.
Sisalation being added, under black plastic is plaster boards ready for March construction.
Roof, spouts, drainage and sisalation February 2010
1st Floor data, electrical, phone installation Solar panels on roof - February 2010
Plumbing, air conditioning February 2010 Kos installing ducting.