WELCOME TO THE NEW TRENTON CENTRAL HIGH SCHOOL 400 CHAMBERS STREET TRENTON, NJ 08609 Presented by: Dwayne Mosley, Facilities Administrator June 17, 2019 1 BUILDINGS AND GROUNDS DEPARTMENT Mission Statement: All Students will graduate with a vision for their future, motivated to learn continually and prepared to succeed in their choice of college or career
Transcript
Page 1: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

WELCOME TO THE NEW TRENTON CENTRAL HIGH SCHOOL

400 CHAMBERS STREET

TRENTON, NJ 08609

Presented by:

Dwayne Mosley, Facilities Administrator

June 17, 2019

1

BUILDINGS AND GROUNDS DEPARTMENT

Mission Statement:

All Students will graduate with a vision for their future, motivated to learn continually and prepared to succeed in their choice of college or career

Page 2: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

2

Design-Build ConstructionThe new Trenton Central High School will be a 350,000 square-foot school designed to educate 1,850 students in grades levels 10 through 12. The estimate cost to construct the school was $155 million dollars.

Current ActivitiesThe following activities are currently underway:• Submissions to the Department of Community Affairs for final plumbing and electrical approvals.• Contractors are continuing to address construction and final punch-list items.

Key Dates• Construction NTP (Project Start-up) – Complete (10/14/16)• Substantial Completion (TCO)– Pending (7/15/19)• School Opening – September 2019

STATUS UPDATE

Page 3: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

THE NEW TRENTON CENTRTAL HIGH SCHOOL

Summer Activities

3

➢ June➢ Boxes to be distributed➢ School Closing - Districtwide➢ Summer Movers Begin

➢ July➢ Relocation of curriculum items from various school locations➢ Building Systems & Equipment Trainings (Mechanics, Custodians, & some

School Staff).

➢ August➢ Terminate lease with Catholic Diocese (520 & 544 Chestnut Avenue and 171

Division Street).➢ Scheduled site walk-through(s) of The New TCHS facility (TBOE Board,

Administration, Community Stakeholders and interested public).

➢ September

➢ Grand Opening – The New Trenton Central High School

NOTE - Ribbon-Cutting Ceremony (TBD) by the NJSDA

Page 4: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

THE NEW TRENTON CENTRAL HIGH SCHOOL

PROGRESS

6

From The Old TCHS

Page 5: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

5

To The New TCHS

Page 6: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

6

CLASSROOMS

Page 7: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

7

COSMETOLOGY

Page 8: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

THE NEW TRENTON CENTRAL HIGH SCHOOL

8

Culinary Kitchen

Page 9: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

9

THE NEW TRENTON CENTRAL HIGH SCHOOL

Auditorium

Page 10: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

10

THE GYNASIUM

Page 11: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

11

Auxiliary Gymnasium

THE NEW TRENTON CENTRTAL HIGH SCHOOL

Page 12: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

12

The Outside Amphitheatre

Page 13: BUILDINGS AND GROUNDS DEPARTMENT Presentation on New...2019/06/17  · • Construction NTP (Project Start-up) –Complete (10/14/16) • Substantial Completion (TCO)–Pending (7/15/19)

Q & A