Business Department
Session 6
• Exam Question– Draw Network diagram
– Identify Critical path
– Sketch Gantt Chart
– ‘Crash’ the project
• Reduce the project completion time
Business Department 3
Project Scheduling
• 86% of all projects that fail, fail due to poor project planning
• Only 16% of IT projects complete on budget and on time (Standish Group 2000)
• Project objectives inadequately defined• Project activities inadequately established• Project activities inadequately quantified• Poor overall project planning
Business Department 4
Project Scheduling
• Planning of timetables and establishment of dates of activities
• Reduce or eliminate uncertainty• To improve efficiency • Better understanding of the objectives• Provides a basis for monitoring and
controlling work
Business Department 5
Aim of Project Scheduling
• Establish at any given time the cost and time spent on the project
• Establish the additional cost of accelerating the project
• Establish the level of resources required for each activity
• Two methods of scheduling• Gantt Charts • Network analysis (CPM)
Business Department 8
Network Diagram
• Schematic display of the project activities and the logical relationships (dependencies) between them
Activity-on-node
L
KJ
G
FFinishStart
Business Department 9
Network Diagram
• Schematic display of the project activities and the logical relationships (dependencies) between them
Activity-on-arrow
1
5
43
2
Business Department 11
Activity-on-the-node
1
Add coffee to cup
Boil water
Heat milk
Add milk and water
to cup2
3
4
Business Department 12
Activity-on-the-arrow
1 2 3 4Add coffee to cup
Boil water
Heat milk
Add milk and water
to cup
Business Department 13
Network Analysis
A. Taxi to airport (1 hour)B. Wait at airport (2 hours)C. Fly to destination (3 hours)D. Coach to hotel (1 hour)
A B C 7
1 3 60
D
Business Department 14
Network Analysis
1.1 Furniture1.2 Equipment1.3 Carpets1.4 Paint1.5 F&F
1.0 Purchase6 weeks
2.1 Furniture2.2 Carpets2.3 F&F
2.0 Strip-out2 weeks
3.1 Walls3.2 Woodwork
3.0 Decoration4 weeks
4.1 Equipment4.2 Furniture4.3 F&F4.4 Carpet
4.0 Installation2 weeks
Office Refurbishment
Business Department 15
Network Analysis
Start Purchase
6 weeks
Decoration
4 weeks
Strip-out
2 weeks
Installation
2 weeks
Finish
14 weeks
Business Department 16
Logic Table
1.0 Purchase - 6 weeks
2.0 Strip-out - 2 weeks
3.0 Decoration 1.0, 2.0 4 weeks
4.0 Installation 1.0, 2.0, 3.0 2 weeks
WBS code
Description Dependency Duration
Business Department 17
Network Analysis
Start
Purchase
6 weeks
Decoration
4 weeks
Strip-out
2 weeks
Installation
2 weeks
Finish
12 weeks
Business Department 18
Critical Path
• Total project time = total duration of activities on critical path
• Critical Path = longest duration path through the network
• Activities that lie on the critical path have no slack time
• Delay on activities that lie on the critical path delay the project as a whole
Business Department 20
Fully Analysed Network
Earliest Start Time (EST)
Earliest Finish Time (EFT)
Latest Start Time (LST)
Latest Finish Time (LFT)
Float
Duration
Activity code & Name
Business Department 21
Logic Table
Activity Dependency Duration
A - 3
B A 2
C A 3
D B, C 5
E B 7
F D, E 5
Business Department 23
Forward pass
• Total Project time • Work from left to right through the network• Earliest start time for each activity (EST)• Earliest finish time for each activity (EFT)
– EFT = EST + Duration
Business Department 24
Forward Pass
Start
3
B
C D
E
F
FINISH
A
2
3 5
7
50 3
3 5
3 6 6 11
5 12
12 17
17
Business Department 25
Backward Pass
• Critical path• Work from right to left through the network• Latest finish time for each activity (LFT)• Latest start time for each activity (LST)
– LST = LFT – Duration
• Float (slack time) = LFT-EFT• Critical Path Activities
– EST = LST and EFT = LFT
Business Department 26
Backward Pass
Start
3
B
C D
E
F
FINISH
A
2
3 5
7
50 3
3 5
3 6 6 11
5 12
12 17
17
1712 0
125 0
127 174 1
53 0
30 0
Business Department 27
Fully Analysed Network
0Start
A3 30
0 0 3
B2 53
3 0 5
C3 63
4 1 7D5 116
7 1 12
E7 125
5 0 12
F5 1712
12 0 17
FINISH1717
17 17
Business Department 28
Weighted Average Technique
• Project evaluation and review technique (PERT)
• a = optimistic time: – Time required if execution goes extremely well
• b = pessimistic time:– Time required if execution goes badly
• m = most likely time:– Time required if execution is normal
Business Department 29
Weighted Average Technique
• Beta Distribution• Mean duration for each activity
= a + 4m + b6
Business Department 30
Final Logic Table
Activity
Depend
Optimistic
Most likely
Pessimistic
Mean (d)
A - 7 8 9
B A 2 5 8
C A 3 6 9
D C, B 1 2 3
E B 7 8 15
Business Department 31
Critical Path
• Mean time for each activity (u) = (a + 4m + b)
6
• Mean activity A = (7 + (4x8) + 9) /6 = 8
• Mean activity B = (2 + (4x5) + 8) /6 = 5
• Mean activity C = (3 + (4x6) + 9) /6 = 6
• Mean activity D = (1 + (4x2) + 3) /6= 2
• Mean activity E = (7 + (4x8) + 15) /6= 9
Business Department 32
Final Logic Table
Activity
Depend
Optimistic
Most likely
Pessimistic
Mean (d)
A - 7 8 9 8
B A 2 5 8 5
C A 3 6 9 6
D B , C 1 2 3 2
E D 7 8 15 9
Business Department 33
Fully Analysed Network
A8 80
0 0 8
B5 138
9 1 14
C6 148
8 0 14
D2 1214
14 0 12E9 2516
16 0 25