  • II 1264418-R8SDMS

    Butte Priority Soils Operable Unit R E M E D I A T I O N

    Bulletin #19 July 11, 2013

    Montana Department of ENVIRONMENTAL QUALITY

    Cleanup activities for the Butte Priority Soils Operable Unit (BPSOU) began in 1987. These actions (Time-Critical Removal Actions and Expedited Response [Non-Time Critical Response] Actions) were taken to address immediate and significant human health and environmental risks. EPA did not want to delay this cleanup work until the Remedial Investigation/Feasibility Study and Record of Decision (ROD) was completed. After these actions were taken the ROD was approved in 2006. Major components of remediation have been completed in the BPSOU since the ROD was issued. The following discussion and tables illustrate what has been completed, what is ongoing, and an estimated time of completion for each.

    Cleanup Activi t ies Completed Prior to the ROD Approximately 422 acres of land were addressed using the expedited Superfund removal process. The early response actions were designed and constructed in a manner consistent with the final remedy.

    Time-Critical Removal Actions • Walkerville (1988) - Addressed certain waste dumps and residential soil areas

    with contaminated lead and/or mercury • Timber Butte Mill (1989) - Removed and consolidated contaminated soils • Butte Priority Soils (1990 and 1991) - Addressed risks from certain mine waste

    dumps, a concentrate spill, and seven residential yards in Butte and Walkerville • Colorado Smelter (1992) - Removed and consolidated onsite contaminated soils • Anselmo Mine Yard and Late Acquisition/Silver Hill (1992) - Addressed a mine

    yard and several mine dumps in Butte • Walkerville II (1994) - Addressed four additional dump areas with elevated soil lead levels • Storm Water (started in 1995) - Partially addressed storm water issues in Butte, including removal of

    mercury contaminated soils and diversion of contaminated storm water • Railroad Beds (started in 1999) - Addressed contaminated

    railroad beds and adjacent residential yards that contain elevated concentrations of metals

    • Walkerville (2000/2001) - Addressed additional residential dumps with elevated metals levels

    Expedited Response (Non-Time Critical Response) Actions • Lower Area One -and incorporated into the ROD - Removed

    accessible mine tailings and contaminated soils from the Silver Bow Creek floodplain at the Colorado Tailing and Butte Reduction Works areas and installed a groundwater interception and treatment system

    • BPSOU (1994-and incorporated into the ROD) - Started to address certain residential areas with soil-lead concentrations above the residential action levels as part of the Residential Metals Abatement Program

    • Lower Area One Manganese Removal (1992) - Removed manganese ore stockpiles located within the flood plain of Silver Bow Creek

    • Old Butte Landfill/Clark Tailings (1998) - Completed Resource Conservation Recovery Act (RCRA) corrective action at the landfill in combination with Superfund removal actions

  • Status of Cleanup Activities Included in the ROD Residential Contamination Activities The Residential Metals Abatement Program (RMAP) aims to reduce risk from exposure to high metals. The RMAP includes comprehensive procedures for sampling, remediation, medical monitoring, community outreach, and overall property characterization and remedial status tracking.

    Activity Description Complete Ongoing Estimated

    Completion

    Final Multi-Pathway RMAP Plan X

    RMAP assessments X 2019

    RMAP cleanups including attic dust X 2029

    Community outreach and education X Ongoing

    Health studies and medical monitoring X Ongoing

    Long term tracking methods (database) X Ongoing

    Anaconda Sampling Worksite 137 X

    PA012Dump Site 113 X

    33 West Missoula X

    Non-Residential Solid Media Contamination Activities Contaminated solid media located in non-residential areas at the BPSOU site include waste rock piles, smelter wastes, milling wastes, and contaminated soils. Concentrations of metals in solid media in non-residential areas (commercial areas, open areas, and non-active mining areas) may exceed action levels. These areas may also pose a threat to the environment as a result of storm water runoff.

    Activity Description Complete Ongoing Estimated

    Completion

    Source areas that were recently reclaimed due to exceedances of arsenic and/or lead action level(s)

    Goldsmith Dump Site 161 X

    Arctic Site 1530 X

    Wake Up Jim Site 161 - moved to Granite Mountain Area and will not be reclaimed X

    Small waste areas surrounding Clark Mill Tailings repository X

    Caledonia Street X

    Moose Dump Site 12 X Source areas not exceeding arsenic and/or lead action level(s) but impacting surface water quality that were or will be reclaimed Back Fill 007 Site 65 X

    Unnamed Dump Site 148 X

    New and Mahoney Street X

    413 Boardman Street X

    Jenny Dell Site 33 X

    Kelly Mine yard entrance X

    North Wyoming Street X

    800 North Main 2013

    North Corner of Granite and Arizona X

    Green Mountain Shaft X

    Streambanks, sediment, and over bank deposits from the Blacktail Creek/Metro Storm Drain confluence area to Lower Area One

    X

    424 North Washington Street X

    131 West Copper Street X

    20 additional sites identified in 2010 X

    Other sites

    Sites within the Granite Mountain Memorial Area X

    Syndicate Pit X

    Butte mine waste repository X Sites not granted a "conditional and limited no further action" status in the Response Action Summary Document Colorado Smelter X

    Lower railroad yard site 1 X

    Other activities Maintain non-residential solid media sites to Butte Reclamation Evaluation System standards

    X Ongoing

  • Groundwater Activities To prevent contaminated groundwater from entering adjacent surface water sources and to prohibit domestic use of groundwater influenced by mining related wastes, a wide range of studies and remedial actions have been performed at the BPSOU.

    Activity Description Complete Ongoing Estimated

    Completion

    Metro Storm Drain (MSD) sub drain installation X Wetland demonstration area X 2014 Irrigation controls and monitoring at the Parrett Tailings X Ongoing Localized groundwater study X 2013 Perform MSD groundwater flow monitoring X Ongoing

    Butte Reduction Works (BRW) East End Grading and MSD/BRW Upgrades work plans X

    Culvert removals in Silver Bow Creek X BRW groundwater and surface water monitoring X Ongoing Conduct abandoned aqueduct study X 2014 Implement abandoned aqueduct study recommendations 2014 Prepare MSD sub drain groundwater management report X 2013 Implementation of selected MSD improvement action after reviewing MSD sub drain groundwater management report X 2013

    Implementation of the revised groundwater monitoring program X 2013

    Surface Water Activities The Selected Remedy for surface water is directed at achieving the primary objectives of meeting applicable or relevant and appropriate requirements, returning Silver Bow Creek to its beneficial uses, and protecting downstream receptors from releases of contamination from BPSOU. Recent remedial design and action efforts have been focused on improving the quality of storm water that discharges from the BPSOU into receiving streams.

    Activity Description Complete Ongoing Estimated

    Completion

    Upfront storm water best management practices (BMPs) Cleanout and maintenance of the Butte Silver Bow's storm water system X Ongoing

    Addressing illicit sewer connections X Ongoing

    Implementation of curb and gutter program X 2013

    Installation of storm water catch basin in Buffalo Gulch X To be determined Capping and vegetation of waste dumps contributing to storm water contamination

    X Ongoing

    Installation of hydrodynamic devices Anaconda Road/Butte Brewery X Lower Buffalo Gulch X Texas Avenue X

    Warren Avenue X Montana Street X Other activities Sediment removal from Blacktail Creek and Silver Bow Creek channels X To be determined

    Surface water management for base flow remediation X To be determined

    In-stream flow of augmentation X To be determined

    Further BMP evaluation, selection, and implementation X To be determined

    • _ g L̂ Bk—....

    Installation of hydrodynamic devices

  • Lower Area One (LAO) Groundwater Treatment Facility The Selected Remedy for the groundwater treatment facility includes retention, upgrades, and continued operations of the lagoon system for treating captured and routed groundwater prior to discharge to Silver Bow Creek. Recent design and remedial action work included multiple upgrades to the existing Butte Treatment

    Activity Description Complete Ongoing Estimated

    Completion

    Phase 1 Upgrade West Camp pump station X

    Upgrade of treatment lagoons outlet structures X 2013

    Replace existing automatic sampling building and effluent station X 2013

    Construct new influent pump station X 2013

    Phase II

    Improvements at BTL X 2013

    Upgrade existing chemical addition system X 2013

    Improve BTL access roads X 2013

    Construct new operations building X 2013

    Revegetation of BTL construction areas X 2014

    Long-term plans

    Water management plan X 2013

    Sludge management plan X

    Instrumentation, controls, and monitoring plan X

    Construction reports for MSD vault upgrades X

    Monitoring and Compliance Requirements The Selected Remedy for groundwater, surface water, and storm water requires an aggressive monitoring program for the entire groundwater alluvial aquifer and for the surface water sources. All monitoring data collected under the monitoring programs are periodically reviewed to determine whether the Selected Remedy remains effective.

    Activity Description Complete Ongoing Estimated

    Completion

    Surface Water

    Implement a revised interim surface water monitoring plan X Ongoing

    Perform wet weather sampling - automatic and opportunistic sampling X Ongoing

    Review surface water data summary reports and final surface water monitoring plan

    X Ongoing

    Groundwater

    Implement the revised interim groundwater monitoring plan X Ongoing

    Provide operations and maintenance of groundwater wells X Ongoing

    Review groundwater data summary reports X Ongoing

    Institutional Controls Requirements The institutional controls (IC) in the Selected Remedy are non-engineering tools that serve to protect the response actions (past and future) from degradations. The four basic IC categories used are: governmental, proprietary, informational, and enforcement/permitting. The specific Selected Remedy IC tools and the status of

    Activity Description Complete Ongoing Estimated

    Completion

    Establish controlled groundwater area and other controls for the alluvial aquifer in the technically impracticability zone to prevent domestic use

    X

    Implementation of BSB's zoning, ordinance, and permit requirements for storm water controls, protection of capped mine materials, and removal and disposal of contaminated soils

    X Ongoing

    Implement deed notices under Montana state law for capped and waste left in place areas

    X Ongoing

    Install fences and signage to prevent remedy disruption X Ongoing

    Operations and Maintenance (O&M) Activities The Selected Remedy requires the development of long-term and integrated comprehensive monitoring and O&M plans for all aspects of the Selected Remedy within the BPSOU.

    Activity Description Complete Ongoing Estimated

    Completion

    Implementation of the Active and Inactive Railroad O&M plans X Ongoing

    Implementation of the BTL O&M plans X Ongoing

    Implementation of the West Camp O&M plan X Ongoing

    Implementation of the MSD groundwater capture system O&M plan X Ongoing

    Implementation of the Repository O&M Plan X Ongoing

    Implementation of the storm water catch basins, hydrodynamic devices, and other O&M plans

    X Ongoing

  • US EPA Federal Building #339 400 N Main Street Butte, Montana 59701

    Do You Need More Information? U.S. Environmental Protection Agency:

    Sara Sparks, Remedial Project Manager, 406-782-7415

    Jean Cannada, Senior Environmental Employee, 406-782-3264

    Nikia Greene, Remedial Project Manager, 406-457-5019

    Butte Silver Bow Health Department:

    Eric Hassler, Residential Metals Abatement Program Manager, 406-497-5042

    Michele Bay, Community Outreach Coordinator, 406-497-5045

    Montana Department of Environmental Quality:

    Joe Griffin, Project Officer, 406-560-6060


Recommended