Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
C BUILDING FACADE CALCULATION METHODOLOGY
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
C. BUILDING FACADE CALCULATION METHODOLOGY
C.1 Calculation Principles
Noise data obtained during the documented survey period and presented herein will provide the basis against
which predicted internal noise levels can be calculated and compared against the referenced Australian Standard
AS2107:2000 criteria to assess internal noise amenity and compliance. The process of this evaluation assesses
the composite acoustic performance of each façade element (e.g. glazing/frame, building envelope, ventilation
opening etc) is calculated and the measured external sound field is said to impinge upon it as direct sound. As
all measured noise levels were recorded under ‘free-field’ conditions, a correction of 2.5dB is applied to linear
spectral noise levels when calculating façade performance to account for the façade incidence effect.
From the layouts and elevation drawings the building envelope there are typically two materials capable of
transmitting sound into the internal space; Concrete, masonry or other main building structure construction, and
a range of framed and sliding glazing elements. Airborne sound transmission through the building structural
element is less critical than sound transmission through glazed panels, therefore various acoustic performances of
glazing types and thicknesses will be assessed and adjusted in design calculation to effect the most cost-effective
design solution, whilst ensuring design compliance is demonstrated.
Corresponding internal noise levels are then predicted using these detailed sound transmission loss calculations
through the calculated composite façade performance, with resultant internal levels corrected for radiating
(exposed) façade area and internal energy ‘losses’ associated with transmitted sound undergoing absorption
from (proposed) internal room finishes. This assessment is generally conservative to allow for unforeseen
variation in eventual performance.
Each façade is also assessed for flanking transmission paths. This includes, but is not limited to, transmission
through junctions between structural elements, aperture seals, and transmission through inter-connected
elements such as mechanical systems.
In order that an acoustically-robust façade design is achieved, building façade assessment calculations are
undertaken using ‘worst case’ (i.e. highest measured) external noise levels, unless otherwise noted. Calculations
are carried out on the most sensitive internal spaces – generally those with the largest glazed area and a low
internal absorptive area. This methodology provides an efficient review ensuring all spaces meet or exceed the
required standard.
All façade ingress calculations are carried out in accordance with the relevant parts of British and European
Standard BS EN 12354:2000 Building Acoustics – Estimation of acoustic performance of buildings from the
performance of elements Part 3: Airborne sound insulation against outdoor sound, which is the most prevalent
calculation methodology in the absence of an equivalent Australian Standard.
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
D CALCULATION OF NOISE EMISSIONS LIMITS
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
D. CALCULATION OF NOISE EMISSIONS LIMITS
An Assigned Noise Level is calculated for each noise sensitive receiver using a combination of environmental
factors local to the receiver. A standard set of ANL’s exist to provide a base level of acoustic amenity, as shown
in the Table below. These levels are modified by an Influencing Factor (IF) to reflect noise sensitivity in the
specific environment relative to the subject development.
To calculate the additional Influencing Factor (IF), concentric circles are drawn around the nearest noise-sensitive
reception point; one at 450m radius and one at 100m radius. Percentages are calculated for the amount of land
area within the circles used for noise emitting purposes (e.g. industrial or commercial uses) which are compared
to the total area encompassed by the concentric circles.
Traffic volume is taken into account in order to reach an acceptable ANL, or noise reception level, appropriate for
the area in which the receiver is to be situated.
Part of Premises Receiving Noise
Time of Day
Assigned Level (dB)
LA10 LA1 LAmax
Noise sensitive premises at locations within 15m of a building directly associated with a noise sensitive use
0700 to 1900 hours Monday to Saturday
45 + influencing factor
55 + influencing factor
65 + influencing factor
0900 to 1900 hours Sundays and public holidays
40 + influencing factor
50 + influencing factor
65 + influencing factor
1900 to 2200 hours all days
40 + influencing factor
50 + influencing factor
55 + influencing factor
2200 hours on any day to 0700 hours Monday to Saturday and 0900 hours Sunday and public holidays
35 + influencing factor
45 + influencing factor
55 + influencing factor
Noise sensitive premises at locations further than 15m of a building directly associated with a noise sensitive use
All hours 60 75 80
Commercial premises
All hours 60 75 80
Industrial and Utility premises
All hours 65 80 90
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
D CALCULATION OF NOISE EMISSIONS LIMITS
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
Calculation of Influencing Factor (IF)
The Influencing Factor (IF) is calculated using the following equation:
Influencing Factor (IF) = I + C + TF
Where;
I = (% of industrial land usage within 100m + %industrial land usage within 450m) x 1 / 10
C = (% of commercial land usage within 100m + %commercial land usage within 450m) x 1 / 20
TF = +6 if there is a major road within 100m of the development
+2 if there is a major road within 450 m of the development
+ 2 if there is a secondary road within 100m of the development
The maximum value the transport factor (TF) can reach is 6;
A major road is defined as having Annual Average Weekday Traffic (AAWT) flows in excess of 15,000 vehicle
movements per day. A secondary road is defined as having Annual Average Weekday Traffic (AAWT) flows in
excess of 6,000 vehicle movements per day.
Identification of Land Use
The image below shows our calculation of Commercial (C) and Industrial (I) land use in inner (100 m) and outer
circle (450m) radii centred on nearest NSR, identified as the adjacent Lot 08, 1m from the property boundary,
15m south of the Stage 1 Lot 5 development facade. Commercial land use is shown light blue outer circle, and
dark blue in inner circle. Industrial land use is shown red in the outer circle. Yellow indicates “Secondary” road
transport infrastructure in the outer circle.
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
D CALCULATION OF NOISE EMISSIONS LIMITS
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
ASSIGNED NOISE LEVEL LIMTS – SUMMARY CALCULATION TABLE
Land Use Type & IF Calculation
Industrial "I"
% Area in Inner Circle 0%
+0
% Area in Outer Circle 0%
Commercial "C"
% Area in Inner Circle 34%
+3.16
% Area in Outer Circle 30%
Roads Location
Estimated vehicle
Movements per
day
Classification Result "TF"
North Lake Rd (N of Beeliar Drv) INNER CIRCLE 15,180 Major +6
6
Beeliar Drv (W of Kwinana
Freeway) OUTER CIRCLE 35,540 Major +2
Kwinana Freeway OUTER CIRCLE >100,000 Major +2
INFLUENCING FACTOR +9.16
The resultant IF therefore equals 9, determining the applicable Assigned Noise Level limits at the NSR.
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
E EQUIPMENT CALIBRATION CERTIFICATES
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
E. EQUIPMENT CALIBRATION CERTIFICATES
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
F NOISE DURING CONSTRUCTION PHASE
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
F. NOISE DURING CONSTRUCTION PHASE
F.1 Extract from Appendix D AS 2436 - Section 4.6
AS2436:2010 Appendix D
Section 4.6
In demolition work alongside occupied premises there should, if possible, be a break in solid connections, e.g. concrete paving, between the working area and the adjoining buildings. This will reduce the transmission of vibration and structure-borne noise. Care should be taken that any such break is of no structural significance in relation to the planned system of demolition. The break could result in premature collapse due to lack of continuity or restraint. Care should be taken not to drop materials from a height either into or out of trucks. The surfaces on to which the materials are being moved should be covered by some resilient material. Particular care should be taken during the loading and unloading of scaffolding. Where material cannot be lowered in skips or by other means, it is recommended that properly constructed and damped chutes be used. The effectiveness of noise enclosures and screens can be partially lost if they are used incorrectly. For example, the noise being enclosed should be directed into and not out of the enclosure. There should also be no reflecting surfaces opposite the open side.
4.5.5 Maintenance of equipment Increases in plant noise are often indicative of future mechanical failure. Regular and effective maintenance of plant and equipment including vehicles is essential and will do much to maintain noise levels near to that of new plant. Maintenance should be carried out only by trained persons. Where maintenance work has to be done at night, precautions may be necessary to minimize any nuisance. Vibration from machinery with rotating parts can be reduced by attention to proper balancing. Frictional noise from the cutting action of tools and saws may be reduced if the tools are kept sharp. Other noises caused by friction in machines, conveyor rollers and trolleys can be reduced by proper lubrication.
4.6 CONTROLLING THE SPREAD OF NOISE
4.6.1 General
If noisy processes cannot be avoided, then the amount of noise reaching the receiver should be minimized. Two ways of doing this are either to increase the distance between the noise source and the receiver or to introduce noise reduction measures such as screens. Physical methods to reduce the transmission of noise between the site works and residences, or other sensitive land uses, are generally suited to works where there is longer-term exposure to the noise. Practices that will reduce noise from the site include: (a) Increasing the distance between noise sources and sensitive receivers. (b) Reducing the line-of-sight noise transmission to residences or other sensitive land uses using temporary barriers (stockpiles, shipping containers and site office transportables can be effective barriers). (c) Constructing barriers that are part of the project design early in the project to afford mitigation against site noise. (d) Installing purpose built noise barriers, acoustic sheds and enclosures.
4.6.2 Distance
Increasing the distance is often the most effective method of controlling noise. This may not be possible where work takes place on fixed structures, e.g. railway tracks. The effect of distance on noise levels is explained in Appendix B. Stationary plant such as compressors and generators can be located away from the work area so as to avoid being close to any noise-sensitive area.
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
F NOISE DURING CONSTRUCTION PHASE
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
4.6.3 Screening
On sites where distance is limited, the screening of noise may be of benefit and this should be taken into account at the planning stages. Appendix B illustrates the effect of the screen in reducing the noise level and Appendix D describes the performance of different types of acoustic screens and enclosures and the materials they are made of. If structures such as stores, site offices and other temporary buildings are situated between the noisiest part of the site and the nearest dwellings, some of the noise emission from the site can be reduced. If these buildings are occupied, then sound insulation measures may be necessary to protect workers in them.
A hoarding that includes a site office on an elevated structure offers a superior noise reduction when compared with a standard (simple) hoarding. This performance is further enhanced when the hoarding is a continuous barrier. Storage of building materials or the placement of shipping containers between the noise source and any noise-sensitive area may also provide useful screening and the same is true of partially completed or demolished buildings.
Noisy stationary plant can be put in a basement, the shell of which has been completed, provided reverberant noise can be controlled. Where compressors or generators are used in closed areas, it is necessary to ensure that the exhaust gases are discharged directly to the outside air and that there is good cross-ventilation to prevent the build-up of poisonous carbon monoxide fumes and to allow an adequate air supply to maintain efficient running.
Where such noise barriers are not practicable, a worthwhile reduction in noise can be obtained by siting the plant behind and as close as possible to mounds of earth, which may effectively screen the plant from any noise-sensitive areas. These can often be designed into the construction schedule or site arrangement for future landscaping. Water pumps, fans and other plant and equipment that operate on a 24-hour basis may not be a source of noise nuisance by day but can create problems at night. They should therefore be effectively screened either by being sited behind a noise barrier or by being positioned in a trench or a hollow in the ground provided this does not generate reverberant noise. In such cases, however, adequate ventilation should also be ensured.
Long, temporary earth embankments can provide quite an effective noise screen for mobile equipment moving, for example, on a haulage road. When the earthworks are complete, the earth mounds should be removed if possible with smaller, quieter excavators. A noise barrier may be a more reliable method of noise control than the imposition of restrictions on throttle settings. In many cases it will not be practicable to screen earthmoving operations effectively, but it may be possible to partially shield construction plant or to build-in at the early stages protective features ultimately required to screen traffic noise. Where earth noise barriers are not a practical proposition because of lack of space, consideration should be given to the possibility of constructing temporary screens from wood or any of the materials suggested in Appendix D.
The usefulness of a noise barrier will depend upon its length, its height, its position relative to the source and to the listener, and the material from which it is made. A barrier designed to reduce noise from a moving source should extend beyond the last property to be protected to a distance of not less than ten times the shortest measurement from the property to the barrier. A barrier designed to reduce noise from a stationary source should, where possible, extend to a distance beyond the direct line between the noise source and the receiver to a distance equal to ten times the effective barrier height, which is the height above the direct line between source and receiver. If the works are predominately within nominally closed structures, careful consideration should be given to reducing noise breakout at any openings.
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
F NOISE DURING CONSTRUCTION PHASE
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
4.7 CONTROL OF NOISE AT THE RECEIVER
In cases where noise emissions cannot be adequately controlled at the source or by controlling the spread of noise, consideration should be given to control of noise received at nearby sensitive locations. Provision of treatments at the affected residence or other sensitive land use is normally only suited to addressing noise from longer term construction projects at a stationary site, or where the work site is relatively isolated, or where only a few residences or other sensitive land uses are affected.
Practices that will mitigate the impacts of noise include: (a) Providing localized noise barriers adjacent to the receiving location. (b) Providing acoustic insulation to reduce airborne noise entering buildings, for example, heavyweight glazing or double glazing. (c) Providing ventilation to enable windows and doors to remain closed. (d) Providing access to temporary relocation for noise-affected occupants for short periods, for example, when high noise levels from construction occur at night and there are no feasible and reasonable ways of reducing noise levels.
4.8 CONTROL OF VIBRATION
4.8.1 General
Vibration can be more difficult to control than noise, and there are few generalizations that can be made about its control. It should be kept in mind that vibration may cause disturbance by causing structures to vibrate and radiate noise in addition to perceptible movement. Impulsive vibration can, in some cases, provide a trigger mechanism that could result in the failure of some building component that had previously been in a stable state. It can also trigger annoyance being elevated into action by occupants of exposed buildings, and should therefore be included in planning of communication with impacted communities.
It should be remembered that failures, sometimes catastrophic, can occur as a result of conditions not directly connected with the transmission of vibrations, e.g. the removal of supports from retaining structures to facilitate site access. BS 7385-2 provides information on managing groundborne vibration and its potential effects on buildings.
Where site activities may affect existing structures, a thorough engineering appraisal should be made at the planning stage. General principles of seeking minimal vibration at receiving structures should be followed in the first instance. Predictions of vibration levels likely to occur at sensitive receivers is recommended when these are relatively close, depending on the magnitude of source of the vibration or the distance involved. Relatively simple prediction methods are available in texts, codes of practice or other standards, however it is preferable to measure and assess site transmission and propagation characteristics between source and receiver locations.
Comparison of predicted levels of vibration with preferred or regulatory levels will indicate when either more detailed predictions are required or mitigation of transmitted vibration is advisable or necessary. Guidance in measures available for mitigation of vibration transmitted can be sought in more detailed standards, such as BS 5228-2 or policy documents, such as the NSW DEC Assessing Vibration: A technical guideline.
Identifying the strategy best suited to controlling vibration follows a similar approach to that of noise—of avoidance, control at the source, control along the propagation path, control at the receiver, or a combination of these. It is noted that vibration sources can include stationary plant (pumps and compressors), portable plant (jackhammers and pavement vibrators), mobile plant, pile-drivers, tunnelling machines and activities, and blasting, amongst others. Unusual ground conditions, such as a high water-table, can also cause a difference to expected or predicted results, especially with piling.
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
G ACOUSTIC GLOSSARY
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
G. ACOUSTIC GLOSSARY
Acoustic Measurement Parameter Definitions
dB
Decibel: a logarithmic scale applied to acoustic units such as sound pressure and sound power. Decibels are
always the ratio between two numbers. Sound Pressure in Pascals becomes "Sound Pressure Level re 2x10 -5 Pa"
in decibels. Sound Power in watts becomes "Sound Power Level re 10-12 W" in decibels. It is
also used for sound reduction or sound insulation and is the ratio of the amount of sound energy incident upon a
partition and the proportion of that energy which passes through the partition. The result is stated as a "decibel
reduction".
dB(A)
A- weighting: This is an electronic filter which attenuates sound levels at some frequencies relative to the sound
levels at other frequencies. The weighting is designed to produce the relative response of a human ear to sound
at different frequencies. The A-weighted sound level is therefore a measure of the subjective loudness of sound
rather than physical amplitude. A- weighting is used extensively and is denoted by the subscript A as in LA10, LAeq
etc. (Levels given without the subscript A are linear sound levels without the A- weighting applied, e. g. L10, Leq
etc.).
LAeq,T
The “A” weighted equivalent continuous sound pressure level. This may be thought of as the "average" sound
level over a given time “T”. It is used for assessing noise from various sources: industrial and commercial
premises, construction sites, railways and other intermittent noises.
LA90,T
The “A” weighted sound pressure level that is exceeded for 90% of the time T. It reflects the quiet periods
during that time and is often referred to as the "background noise level". It is used for setting noise emission
limits for industrial and commercial premises.
LAmax
The maximum "A" weighted sound pressure level during a given time on fast or slow response.
LpA
The "A" weighted sound pressure Level. The sound pressure level is filtered through a standard frequency
weighting known as A-weighting. This filter copies the frequency response of the human ear, so that the
resulting sound level closely represents what people actually hear.
R
Is the sound reduction index of a construction element in octave or 1/3 octaves and can only be measured in a
laboratory. There must be no flanking transmission.
R'
Is the sound reduction index of a construction element in octave or 1/3 octaves measured on site, and normally
includes flanking transmission (ie where sound travels via paths other than straight through the element being
tested, such as columns, ducts, along external walls, etc).
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
G ACOUSTIC GLOSSARY
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
Rw
To get the weighted sound reduction index (Rw) of a construction, the R values are measured in octave or 1/3
octave bands covering the range of 100Hz to 3150Hz. The curve is adjusted so that the unfavourable deviation
(or shortfall of the actual measurements below this standard curve) averaged over all the octave or 1/3 octave
bands is not greater than 2dB. The value of the curve at 500Hz is the Rw.
R’w
The apparent sound reduction index, which is determined in exactly the same way as the Rw but on site where
there is likely to be some flanking transmission.
D
This is the "level difference". It is determined by placing a noise source in one room and measuring the noise
levels in that room (the "source room") and an adjacent room (the "receiver room"). The level difference is
calculated by simply deducting the "receiver" noise level (dB) from the "source" noise level (dB).
Dw
This is the weighted level difference. D is measured on site in octave or 1/3 octave bands covering the range of
100Hz to 3150Hz. The D values are compared to a standard weighting curve. The curve is adjusted so that the
"unfavourable deviation" (or shortfall of the actual measurements below this standard curve) averaged over all
the octave or 1/3 octave bands is not greater than 2dB. The Dw is then the value of the curve at 500Hz.
Dnw
This is the weighted normalised level difference. D is measured on site in octave or 1/3 octave bands covering the
range of 100Hz to 3150Hz. As the level difference is affected by the area of the common wall/ floor and the
volume of the receiving room, as well as the amount of absorption in the receiving room, in the case of the DnT,w,
the results are "normalised" by a mathematical correction to 10m2 of absorption (Dn). The same weighting curve
as for Dw is used to obtain the single figure: Dnw.
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
G ACOUSTIC GLOSSARY
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
Acoustic Performance Guide
DnT,w
This is the weighted standardised level difference. D is measured on site in octave or 1/3 octave bands covering
the range of 100Hz to 3150Hz. As the level difference is affected by the area of the common wall/ floor and the
volume of the receiving room, as well as the amount of absorption in the receiving room, in the case of the DnT,w,
the results are "standardised" by a mathematical correction a reverberation time, usually 0.5 seconds (DnT). The
same weighting curve as for Dw is used to obtain a single figure "DnT,w"
DnT(Tmf, max),w
This is the weighted BB93 standardised level difference corresponding to a Building Bulletin 93 reference value
reverberation time in a receiving room. It is measured on site in accordance with BS EN ISO 140- 4: 1998.
Dn,c
Suspended ceiling normalised level difference. This is the sound level difference between two rooms, separated
by a suspended ceiling, normalised to a reference value of absorption in the receiving room (10m2 for the
Laboratory as specified in ISO 140- 9 : 1985). It is measured in 1/3 octave or octave frequency bands.
Dn,c,w
Weighted suspended ceiling normalised level difference. This is a single number quantity representing the sound
reduction between two rooms separated a suspended ceiling. It is obtained by applying specified weightings to
the 1/3 octave band suspended ceiling normalised level differences in the frequency range 100Hz to 3150Hz.
Ctr
Spectrum adaptation term: Value, in decibels, to be added to a single- number rating (e. g. Rw) to take account
of the characteristics of particular sound spectra. Ctr is calculated using an A- weighted urban traffic noise
spectrum as defined in BS EN ISO 717- 1 : 1997.
NR
Stands for Noise Rating. (It is NOT noise reduction). It is (e. g. NR30, NR35 etc.) a single number, which
represents the sound level in a room and takes account of the frequency content of the noise. The lower the NR
value, the quieter the room will be. It is mainly used for assessing noise from mechanical services systems. In
leisure developments it is used as a standard for noise break- in to rooms from external noise sources such as
traffic.
NC
Stands for Noise Criteria. It is very similar to NR but (e.g. NC30, NC35 etc.) uses slightly different frequency
weightings.
NRC
Stands for Noise Reduction Coefficient. The noise reduction coefficient of a material is the average, to the
nearest multiple of 0.05, of the absorption coefficients at 250Hz, 500Hz, 1kHz and 2kHz.
Stage 01 Lot 05 Cockburn Central
Acoustics - Report for Development Approval
G ACOUSTIC GLOSSARY
© SEALHURST PTY LTD All Rights Reserved SEA-2014-060 RPT001_RevB [DA]
α
Stands for Absorption Coefficient, which represents the proportion of incident sound energy arriving from all
directions that is not reflected back into the room. It ranges between 0 and 1, where 0 is reflective and 1 is totally
absorptive.
αw
Stands for Weighted Absorption Coefficient. Single- number frequency dependent value which equals the value
of the reference curve at 500Hz after shifting it as specified in EN ISO 11654 :1997.
αp
Stands for practical absorption factor. It is a frequency dependent value of sound absorption coefficient which is
based on measurements in one- third- octave bands in accordance with ISO 354 and which is calculated in octave
bands in accordance with EN ISO 11654 : 1997. It is the arithmetic mean of the three 1/3 octave sound
absorption coefficients within the octave being considered. The mean value is calculated to the second decimal
place and rounded in steps of 0.05 up to a value of 1.0.
Class X
Stands for the Absorption Class between 250 and 4kHz, as defined by EN ISO 11654. Class A is the best
classification representing the highest level of absorption, and Class E offers to lowest classification.
RT or T60
Reverberation Time is a measure of the echoic nature of a room. It is normally measured in 1/3 octave or 1/1
octave bands by creating a loud noise and measuring the time it takes for that noise to decay by 60dB. The
longer the reverberation time, the more ‘echoey’ a room sounds. For dwellings, a reverberation time of 0.5
seconds or less is normal. Cinema auditoria will have reverberation times of 1.0 second or below when fitted out,
but up to 9 seconds at shell completion.
When designing acoustically sensitive areas such as concert halls or lecture theatres, it is necessary to design the
room finishes to achieve optimum reverberation times. These will vary depending on the type of activity in the
room and the room volume.
Tmf
Stands for the arithmetic average of the reverberation times in the 500Hz, 1kHz and 2kHz octave bands, for the
type of receiving room, as defined in UK Schools design manual, Building Bulletin 93.
Lot 5 Signal Terrace, Cockburn Central
Transport Assessment CW932300
Prepared for Fraser Property Australia
06 November 2015
Lot 5 Signal Terrace, Cockburn Central
Transport Assessment CW932300
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia ii
Document Information
Prepared for Fraser Property Australia
Project Name Transport Assessment
File Reference CW932300-TR-R001-B-TIA-V1MBM-RJC.docx
Job Reference CW932300
Date 06 November 2015
Contact Information
Cardno (WA) Pty Ltd
ABN 77 009 119 000
11 Harvest Terrace
PO Box 447
West Perth WA 6872
Telephone: 08 9273 3888
Facsimile: 08 9388 3831
International: +61 8 9273 3888
www.cardno.com.au
Document Control
Version Date Author Author Initials
Reviewer Reviewer Initials
A 05/11/2015 Mina Bayat Mokhtari MBM Ray Cook RJC
B 06/11/2015 Mina Bayat Mokhtari MBM Ray Cook RJC
© Cardno 2015. Copyright in the whole and every part of this document belongs to Cardno and may not be used, sold, transferred, copied or reproduced in whole or in part in any manner or form or in or on any media to any person other than by agreement with Cardno.
This document is produced by Cardno solely for the benefit and use by the client in accordance with the terms of the engagement. Cardno does not and shall not assume any responsibility or liability whatsoever to any third party arising out of any use or reliance by any third party on the content of this document.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia iii
Table of Contents
1 Introduction 1
1.1 Introduction 1
2 Existing Situation 2
2.1 Existing Site Context 2
2.2 Existing Road Network 3
2.3 Existing Intersections 5
2.4 Existing Site Traffic Generation and Land Uses 5
2.5 Existing Road Network Performance 6
2.6 Existing Pedestrian/Cycle Networks 6
2.7 Existing Public Transport Facilities 7
2.8 Crash Assessment 8
3 Proposed Redevelopment 9
3.1 Development Yields 9
3.2 Access Arrangements 9
3.3 Service Vehicle Provision 10
4 Analysis of Transport Network 11
4.1 Transport Assessment 11
4.2 Development Traffic Generation 11
4.3 Development Traffic Distribution and Assignment 12
4.4 Car Parking Provision 14
4.5 Bicycle Parking Provision 15
4.6 End of Trip Facilities 15
4.7 Car Park Layout 15
4.8 Proposed Pedestrian/Cycle Facilities 15
4.9 Proposed Public Transport Facilities 15
4.10 Intersection Performance 16
4.11 Safe Walk/Cycle to School 19
5 Site Specific Issues 20
5.1 Site Specific Transport Issues 20
5.2 Operation of Sleeper Lane 20
6 Conclusions 21
Tables
Existing mid-block traffic volumes (two-way) 6
Cockburn Central Bus Routes 7
ITE Trip Generation Rates 11
Generated traffic directional proportions 11
Trip Generation (Stage 1-4) 11
Modes used by Cockburn Central Residents for Home-based Work Trips 12
Car Parking Requirements 14
Proposed Land Uses and Parking Bays, Stage 1-4 14
Bicycle Parking Requirements 15
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia iv
Sleeper Lane / Junction Boulevard Intersection Performance for 2021 AM Peak Hour 16
Sleeper Lane / Junction Boulevard Intersection Performance for 2021 PM Peak Hour 17
Sleeper Lane / Signal Terrace Intersection Performance for 2021 AM Peak Hour 18
Sleeper Lane / Signal Terrace Intersection Performance for 2021 PM Peak Hour 18
Figures
The Site Locality 2
Land uses adjacent to the Site 2
The Close-up Image of the Development Site 3
The existing road network surrounding the Shopping Centre 4
Existing intersection of Junction Boulevard/Sleeper Lane 5
Existing intersection of Signal Terrace/ Sleeper Lane 5
Exisitng Pedestrian/Cycling Facilities in the Area Surrounding the Site 6
Existing Public Transport Services in the Area Surounding the Site 7
Access arrangements for the Site 9
Turning movement diagram for 2021- AM Peak Hour 13
Turning movement diagram for 2021- PM Peak Hour 13
SIDRA Layout for Sleeper Lane / Junction Boulevard Intersection 16
SIDRA Layout for Sleeper Lane / Signal Terrace Intersection 17
Appendices
Appendix A Concept Development Plans
Appendix B WAPC checklist
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 1
1 Introduction
1.1 Introduction
Cardno has been commissioned by Fraser Property Australia to prepare a Transport Assessment for the
proposed mixed used development located at lot 5 Signal Terrace, Cockburn Central Town Centre. The
development full build out is planned to be in 4 stages and this report will review the transport aspects of
the proposed development for the full build out but with special focus on Stage 1 which is the subject of the
current Development Application (DA).
The development plan is provided is enclosed in Appendix A.
This report has been prepared in accordance with the Western Australian Planning Commission (WAPC)
Transport Assessment Guidelines for Developments: Volume 4 – Individual Developments (2006) and the
related checklist is included at Appendix B.
This report will specifically focus on traffic access, circulation, and safety. Discussion regarding pedestrian,
cycle and public transport considerations is also provided.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 2
2 Existing Situation
2.1 Existing Site Context
The proposed development site (the Site) is located in Cockburn Central Town Centre and is bounded by
Junction Boulevard to the north, Midgegooroo Avenue to the west, Signal Terrace to the south and Sleeper
Lane to the east.
The location of the Site is illustrated in Figure 2-1.
The Site Locality
Source: Nearmap 2015
As shown in Figure 2-2, the surrounding area of the Site is also zoned as “Mixed Use”.
Land uses adjacent to the Site
Source: City of Cockburn Mapping Tool, October 2015
The Site
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 3
The Site is currently a vacant land. Apart from the developed land to the east and south of the Site the area to
the north and west of the Site is mainly undeveloped.
The close-up image of the site is shown in Figure 2-3 below
The Close-up Image of the Development Site
Source: Nearmap 2015
2.2 Existing Road Network
Figure 2-4 shows the layout and classification of the roads surrounding the Site.
Road classifications are defined in the Main Roads Functional Hierarchy as follows:
Primary Distributors (light blue): Form the regional and inter-regional grid of MRWA traffic routes and
carry large volumes of fast-moving traffic. Some are strategic freight routes, and all are National or State
roads. They are managed by Main Roads.
District Distributor A (green): These carry traffic between industrial, commercial and residential areas and
connect to Primary Distributors. These are likely to be truck routes and provide only limited access to adjoining
property. They are managed by Local Government.
District Distributor B (dark blue): Perform a similar function to District Distributor A but with reduced capacity
due to flow restrictions from access to and roadside parking alongside adjoining property. These are often
older roads with traffic demand in excess of that originally intended. District Distributor A and B roads run
between land-use cells and not through them, forming a grid that would ideally be around 1.5 kilometres apart.
They are managed by Local Government.
Local Distributors (orange): Carry traffic within a cell and link District Distributors at the boundary to access
roads. The route of the Local Distributor discourages through traffic so that the cell formed by the grid of District
Distributors only carries traffic belonging to or serving the area. These roads should accommodate buses but
discourage trucks. They are managed by Local government.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 4
Access Roads (grey): Provide access to abutting properties with amenity, safety and aesthetic aspects
having priority over the vehicle movement function. These roads are bicycle and pedestrian friendly. They are
managed by Local government.
The existing road network surrounding the Shopping Centre
Source: Main Roads Mapping Information Centre 2015
The characteristics of the surrounding road network are discussed as follows: > Midgegooroo Avenue: located on the western boundary of the Site. Consists of a four-lane two-way
median-divided carriageway. Midgegooroo Avenue connects to Junction Boulevard and Signal Terrace to
the north-west and south-west of the Site respectively. Midgegooroo Avenue is a District Distributor A in
the MRWA Metropolitan Functional Road Hierarchy (MFRH). Midgegooroo Avenue functions as
continuation to North Lakes Road that serves as the main connection between the residential areas to the
north-west and Cockburn Town Centre. Midgegooroo Avenue has a posted speed limit of 70 km/h, on-
street parking is currently not feasible along both sides of Midgegooroo Avenue adjacent to the Site.
> Signal Terrace: located on the southern boundary of the Site. Consists of a two-lane two-way median-
divided carriageway. Signal Terrace connects to Midgegooroo Avenue and Sleeper Lane to the south-west
and south-east of the Site respectively. Signal Terrace is an Access Road in the MFRH WA, with a posted
speed limit of 50 km/h. Indented parking is provided on both sides of Signal Terrace adjacent to the Site.
> Junction Boulevard: located on the northern boundary of the Development. Consists of a two-lane two-
way median-divided carriageway. Junction Boulevard connects to Midgegooroo Avenue and Sleeper Lane
to the north-west and north-east of the site, respectively. Junction Boulevard is an Access Road in the
MFRH WA, with a posted speed limit of 50 km/h. Indented parking is provided on both sides of junction
Boulevard adjacent to the Site.
> Sleeper Lane: located on the eastern side of the Site is an un-marked two-way carriageway. Sleeper Lane
connects to Signal Terrace and Junction Boulevard to the north east and south east of the Site respectively.
Sleeper Lane is an Access Road in the MFRH with a posted speed limit of 50 km/h, on-street parking is
currently not feasible along both sides of the Site. Sleeper Lane is currently about 6 m wide and also has a
mainly red asphalt pavement which combined with its narrowness will encourage drivers to drive slowly.
Therefore it is expected that its operation is as a lane way and the operational speed in Sleeper Lane will
be about 30 km/h.
The Site
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 5
2.3 Existing Intersections
Sleeper Lane / Junction Boulevard Intersection (Figure 2-5) located at the north eastern corner of the Site
is a full movement T-intersection.
Existing intersection of Junction Boulevard/Sleeper Lane
Source: Nearmap 2015
Signal Terrace/ Sleeper Lane (Figure 2-6) located at the south western corner of the site is a four-way priority
intersection.
Existing intersection of Signal Terrace/ Sleeper Lane
Source: Nearmap 2015
2.4 Existing Site Traffic Generation and Land Uses
Currently the Site is a vacant land and there is no trip to/from the Site.
Signal Terrace
Sleeper Lane
Sleeper Lane
Junction Boulevard
Junction Boulevard
Sleeper Lane
Signal Terrace
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 6
2.5 Existing Road Network Performance
Existing traffic volumes of the surrounding road network were sourced from traffic count data undertaken by
Cardno in November 2015. Details are summarised in Table 2-1.
Existing mid-block traffic volumes (two-way)
Average Two-way Weekday Traffic
Volumes
Date Vehicles per AM
Peak Hour
Vehicles per PM Peak Hour
Junction Boulevard November 2015 40 180
Signal Terrace November 2015 200 250
Sleeper Lane* November 2015 - -
*No data was recorded for existing traffic movements along Sleeper Lane as it was closed for the purpose of construction
2.6 Existing Pedestrian/Cycle Networks
According to the map provided by Department of Transport, there is a shared path along Midgegooroo Avenue
that continues to the north and south and connects to the shared path along Beeliar Drive, which continues
toward east and connects to the shared path along Kwinana Freeway. There is no other dedicated on-road
and limited off-road cyclist facilities in the close vicinity of the Site. Footpaths are provided on both sides of the
roads surrounding the Site, the majority of paths exceed the 2.0m minimum and are generally considered
suitable for slow-speed utility cycling access. Town Centre streets are also generally low speed, with capacity
for mixed-traffic cycling for more confident riders. This suggests that there are reasonable existing links
between the Site and the surrounding area.
The walk and cycle map is shown in Figure 2-7
Exisitng Pedestrian/Cycling Facilities in the Area Surrounding the Site
Source: Department of Transport, Walk & Cycle Information, July 2013
The Site
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 7
2.7 Existing Public Transport Facilities
Cockburn Central Train Station is located within 400m walkable catchment from the Site. Trains toward Mandurah/Perth stop at this station every 10 minutes. A number of buses provide services from this train station to the surrounding suburbs. The local bus frequencies and information about bus routes within the Site surrounding area are shown in Table 2-2 and Figure 2-8, respectively.
Cockburn Central Bus Routes
Route No. Route Description Frequency per day
Weekdays Saturday
514 Murdoch Stain - Cockburn Central Station every 20 – 60 minutes every 60 minutes
518 Murdock Station - Cockburn Central Station every 20 – 30 minutes every 60 minutes
525 & 526 Cockburn Central Station – Hammond Park every 10 – 30 minutes every 20 – 45 minutes
522 Cockburn Central Station - Spearwood 1 service per day No service
532 Cockburn Central Station- Fremantle Station every 10 – 30 minutes every 60 minutes
Access to Cockburn Central Train Station is supported by footpaths along both sides of the roads in the area
surrounding the Site.
Uncontrolled crossings are provided at all the intersections located between the Site and the train station to
support access to public transport.
Existing Public Transport Services in the Area Surounding the Site
Source: Public Transport Authority
It can be stated that due to its proximity to the station, this Site has very good public transport connectivity.
The Site
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 8
2.8 Crash Assessment
A search of the Main Roads WA Reporting Centre for traffic accident data was made. This search covered all
recorded accidents between 1 January 2010 and 31 December 2014 on the following sections of the roads:
Intersection of Signal Terrace/Midgegooroo Avenue
It is understood that this intersection was upgraded in 2014 and MRWA Reporting Centre only provides data
up to December 2014.
Records show that before the upgrade, ten crashes occurred at this intersection, of which nine happened
between 2010 and 2012 and one in 2013.
Intersection of Signal Terrace/Linkage Avenue
There is a record of 11 crashes occurred at this intersection. Right Angle crashes are the most common type
of crashes at this intersection. 4 of the recorded crashes required medical attention.
It should be noted that 9 of the crashes were occurred between March 2010 and November 2012, at this time
most of the roads and intersection in Cockburn Central Town Center were under construction.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 9
3 Proposed Redevelopment
3.1 Development Yields
As stated earlier the Site is a mixed used development and is planned to be developed in 4 different stages.
Stage 1-4 consists of the followings:
332 Multiple Dwellings
743 sq.m Commercial Units
307.5 sq.m Café
The proposed plans of the Site is provided in Appendix B.
3.2 Access Arrangements
As shown in Figure 3-1 the Site provides 2 access points (A and B) for cars and both are located on Sleeper
Lane.
Access arrangements for the Site
Source: Cameron Chisholm Nicol
Entry/exit to the Site for pedestrian is provided at 4 different locations. (Each Stage will provide a separate
access for residents).
A
A A
B
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 10
3.3 Service Vehicle Provision
As per information provided in the waste management plan prepared by Bowman Associates Pty Ltd, once
construction of all stages is complete, the waste collection will be from the ground floor. The truck will always
travel in forward direction.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 11
4 Analysis of Transport Network
4.1 Transport Assessment
Future traffic conditions have been analysed for the year 2021. The assessment quantifies the effect that the
Site (Stage 1-4) will have on the road network.
Given that currently much of the land in the area surrounding the Site is undeveloped, for the purpose of the
traffic analysis only the future scenario has been considered.
As per the information provided in the ABS website, the population growth in the City of Cockburn is about
4.5% per annum. As a conservative estimate, the existing background traffic was increased by 5% per annum
to project the background traffic for 2021.
Conservatively, for the purpose of this assessment, traffic generated by the undeveloped, planned,
developments in the area has also been added the existing background traffic and then increased by the
growth factor of 5% per annum.
4.2 Development Traffic Generation
Trip generation rates for the residential dwellings have been sourced from Institute of Transport Engineer’s
Trip Generation Handbook 7th Edition.
Trips to the Site for the Commercial area and the Café have been based on the number of car bays provided
on-site and trips made by the customers will be considered to be as part of the background growth.
Table 4-1 summaries the ITE rates for AM and PM peak periods.
ITE Trip Generation Rates
Land Use ITE Code Weekday Peak hours
AM Peak Hour PM Peak Hour
Mid-rise apartments 223 0.35 per dwelling 0.44 per dwelling
Commercial and Café - 1 per 1 car bay 1 per 1 car bay
Trip directionality proportions for the stated land uses have been also sourced from the ITE Trip Generation
Handbook 7th edition and are shown in Table 4-2.
Generated traffic directional proportions
Land Use AM Peak hour PM Peak Hour
IN OUT IN OUT
Mid-rise apartments 29% 71% 59% 41%
Commercial and Café 88% 12% 17% 83%
Table 4-3 shows the total number of trips estimated to be generated by the Site after the application of
above trip and direction rates.
Trip Generation (Stage 1-4)
Land Use AM Peak hour PM Peak Hour
IN OUT IN OUT
Mid-rise apartments 34 83 86 60
Commercial and Café 18 3 4 17
Due to the land uses, above trip generation are likely to be generated by vehicles such as private cars, mainly
by residents. It is noted that the trip generation is very conservative and it will most likely be much lower as
future residents will utilise the excellent public transport services.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 12
4.3 Development Traffic Distribution and Assignment
As a result of having a train station and high frequency bus services in the close vicinity of the Site, it is
expected that a high proportion of home-based work and home-based education trips will be by using public
transport services.
Cockburn Central Station is approximately 19.4km south of Perth CBD and the travel time by train to Perth
Station is approximately 20 minutes. The cost of parking in the City can be prohibitive and as such, travelling
by train is an attractive mode of transport for commuters traveling to the Perth CBD in peak periods. Travel
time on the train is significantly faster when compared to travelling via private vehicle in peak periods
The ABS Census data for 2011 has been used to allocate residential trips to work to different modes.
Information about the modes used by the residents of Cockburn Central, is summarised in Table 4-4.
Modes used by Cockburn Central Residents for Home-based Work Trips
Travel to work %
People who travelled to work by public transport 13.60
People who travelled to work by car as driver or passenger 67.80 Source: ABS Census Data, 2011
Shown in Table 4-4, approximately 14% of employed people living in the Cockburn Central travel to work by
use of public transport services. It is noted that this proportion has not been applied to the number of trips
generated by the Site in the intersection performance assessment presented in Section 4.10 and the
assessment is therefore considered a very conservative assessment.
A common behavioural assumption in the study of transport networks is that travellers will gradually choose
routes that they identify as being the shortest under the traffic conditions. For the purpose of this report, it has
therefore been assumed that when the Site opens, drivers may be more inclined to turn right at the intersection
of Sleeper Lane/Signal Terrace and then turn right or left at the intersection of Midgegooroo Avenue/Signal
Terrace, As drivers will gradually start to experience delays, especially if they want to merge into traffic in
Signal Terrace, due to the volume of the through movement on Signal Terrace, they will decide to reduce their
travel time by choosing a different route. As a result, a proportion of traffic intending to go north is therefore
expected to go via Sleeper Lane and then via Linkage Avenue. It is also expected that people intending to
access Kwinana Freeway, will turn left at the intersection of Sleeper Lane /Signal Terrace and go south via
Linkage Avenue, and will merge into Beeliar Drive through the left in, left out intersection of Linkage Avenue
and Beelliar Drive as they do not need to go through the signalised intersection at Midgegooroo Avenue and
Beeliar Drive.
The results of above assumptions are shown in Figure 4-1 and Figure 4-2.
Figure 4-1 and Figure 4-2 show the turning movements at the intersections of Sleeper Lane/Junction
Boulevard and Sleeper Lane/Signal Terrace in 2021 including background 2021 traffic and all traffic due to the
developments planned in the area including The Site.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 13
Turning movement diagram for 2021- AM Peak Hour
Source: Nearmap 2015
Turning movement diagram for 2021- PM Peak Hour
Source: Nearmap 2015
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 14
4.4 Car Parking Provision
The car parking provision required to service the proposed residential dwellings is set out in the Residential
Design Codes (R-Codes) and City of Cockburn Town Planning Scheme No.3. The applicable land uses and
their car parking requirements are set out in Table 4-5.
Car Parking Requirements
Use Car Parking Requirements
Multi-Unit Residential (Location A)*
1 car parking space per Less than 110m2 and/or 1 or 2 bedrooms
1.25 car parking space per 110m2 or greater and/or 3 or more bedrooms
0.25 visitor car parking space per residential dwelling unit (according to the agreement with the City of Cockburn, the number of visitor car parking bays can be limited to 10% of the total number of residential dwellings)
Commercial (Office) & Café **
1 per 50 sq.m GLA
Source: * R-Codes
Location A is within:
800m of a train station on a high frequency rail route, measured in a straight line from the pedestrian entry to the train
station platform to any part of a lot; or
250m of a high frequency bus route, measured in a straight line from along any part of the route to any part of a lot.
** City of Cockburn Town Planning Scheme No.3
Table 4-6 shows these requirements applied to the Site.
Proposed Land Uses and Parking Bays, Stage 1-4
Use Proposed No. of Car Bays Requirement Compliant
Multi-Unit Residential – 332 Units (42 x 3 bedrooms and the rest less than 3 bedrooms)
For residents 369 car bays for residents (see comment below)
343 Yes
For visitors 34 visitor spaces 34 (as per agreement with the
City)
Yes
Commercial (Office) and Café
for staff 21 car bays (including 1 ACROD bay)
21 Yes
It is noted that currently only Stage 1 of the 4 stages is part of this DA submission. As part of Stage 1, 121 car bays will be provided for 87 dwellings and 307.5 sq.m café and with following allocation:
98 car bays for residents (including 18 tandem bays)
6 car bays for commercial tenancies (including 1 ACROD)
17 car bays for visitors (8 bays will be allocated to Stage 2 )
The overall provision of visitor bays is subject to change as the plans for the other stages has not been finalised and Stage 1 provides sufficient visitor parking and also will provide extra visitor bays for the use of Stage 2 when it is developed.
As part of the agreement with the City of Cockburn some of the dwellings that are provided for affordable apartment living, will not have an allocated car parking bay and the Site will provide a motorcycle bay for each of these dwellings. Therefore, 29 motorcycle bays (5% of the total bays provided for residents) of which 16 will be provided as part of Stage 1 will provided on-site.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 15
4.5 Bicycle Parking Provision
The bicycle parking requirement for the proposed development is also provided in City of Cockburn Town Planning Scheme No.3. It is shown in Table 4-7 below.
Bicycle Parking Requirements
Use Bicycle Parking Requirements
Multi-Unit Residential – 332 Units*
1 bicycle rack per each 4 dwellings for residents
1 bicycle rack per each 16 dwellings for visitors
Commercial (Office) and Café **
1 bicycle rack per 200sq.m GLA for employees
1 bicycle rack per 750sq.m GLA for visitors
Source: * City of Cockburn Town Planning Scheme No.3
** According to the agreement with the City of Cockburn, the total number of bicycle racks can be limited to 10% of the total
number of commercial car parking bays provided
As per above requirement, 71 bike racks will be provided as part of Stage 1 and 108 as part of Stage 2,3 and 4.
4.6 End of Trip Facilities
A unisex shower and 2 lockers will be provided at the ground floor for the use of commercial staff.
4.7 Car Park Layout
The car park layout of Stage 1, including the dimension of car parking bays, circulation roadways, aisles and
sight line clearance at the access driveways, drawings No. A03-01 to A03-04 dated to 04/11/2015, have been
checked for compliance with AS 2890.1 requirements.
4.8 Proposed Pedestrian/Cycle Facilities
In the study undertaken by Cardno for the Department of Transport “Cycling and Walking Routes to Stations”,
December 2014, new connections and some improvement in the existing paths were suggested, including the
following:
Line marking and bicycle symbols for all existing shared paths
New Connection between the shared path along North Lake Road and the shared path along Kwinana
Freeway
Improvement in the exiting path at the intersection of Beeliar Drive and Midgegooroo Avenue
Improvement in the connectivity between the shared path along Kwinana Freeway and the Cockburn
Gateway Shopping Centre
It is also understood that City of Cockburn bike plan will also be updated in 2015-16 financial year.
4.9 Proposed Public Transport Facilities
According to the advice obtained from PTA, no major changes are proposed to the public transport services for the road network surrounding the Site.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 16
4.10 Intersection Performance
Analysis of the 2021 performance has been undertaken for the following access intersections:
> Sleeper Lane / Junction Boulevard
> Sleeper Lane / Signal Terrace
These identified intersections have been analysed for each scenario using the SIDRA v5.1 analysis program.
This program calculates the performance of intersections based on input parameters, including geometry and
traffic volumes. As an output SIDRA v5.1 provides values for the Degree of Saturation (DOS), queue lengths,
and delays. The generally accepted upper limits for the DOS (where it is considered that the operation of the
intersection is constrained) are:
> 0.80 for unsignalised intersections
> 0.85 for roundabouts
> 0.95 for signalised intersections
A DOS exceeding these values indicates that the intersection may exceed its practical capacity. Above these
values, users of the intersection are likely to experience unsatisfactory queuing and delays during peak hour
periods.
4.10.1 Sleeper Lane / Junction Boulevard Intersection
The analysis of the Sleeper Lane / Junction Boulevard intersection for the weekday peak hour is discussed
below. Figure 4-3 is a SIDRA layout representation of the intersection.
SIDRA Layout for Sleeper Lane / Junction Boulevard Intersection
Sleeper Lane / Junction Boulevard Intersection Performance for 2021 AM Peak Hour
Intersection Approach
Background 2021 without
Development Background 2021 with
Development
DOS
Delay (s)
LOS 95% Queue (m)
DOS Delay (s)
LOS 95% Queue (m)
Sleeper Lane (S) L 0.06 4 A 2 0.066 4 A 2
R 0.06 4 A 2 0.06 4 A 2
Junction Boulevard (E)
L 0.11 1 A 0 0.11 1 A 0
T 0.11 0 A 0 0.11 0 A 0
Junction Boulevard (W)
T 0.05 1 A 2 0.06 1 A 2
R 0.05 2 A 2 0.06 2 A 2
All vehicles 0.11 1 NA 2 0.11 1 NA 2
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 17
Sleeper Lane / Junction Boulevard Intersection Performance for 2021 PM Peak Hour
Intersection Approach
Background 2021 without
Development Background 2021 with
Development
DOS
Delay (s)
LOS 95% Queue (m)
DOS Delay (s)
LOS 95% Queue (m)
Sleeper Lane (S) L 0.01 4 A 0 0.05 6 A 1
R 0.01 4 A 0 0.05 6 A 1
Junction Boulevard (E)
L 0.07 1 A 0 0.11 1 A 0
T 0.07 0 A 0 0.11 0 A 0
Junction Boulevard (W)
T 0.08 1 A 3 0.16 1 A 7
R 0.08 2 A 3 0.16 2 A 7
All vehicles 0.08 0 NA 3 0.16 1 NA 7
As indicated in Table 4-8, the proposed intersection configuration has sufficient capacity for all approaches
under the background 2021 plus development.
The geometry of the existing intersection is considered sufficient for both operation and safety.
4.10.2 Sleeper Lane / Signal Terrace Intersection
The analysis of the Sleeper Lane / Signal Terrace intersection for the weekday peak hour is discussed
below. Figure 4-4 is a SIDRA layout representation of the intersection.
SIDRA Layout for Sleeper Lane / Signal Terrace Intersection
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 18
Sleeper Lane / Signal Terrace Intersection Performance for 2021 AM Peak Hour
Intersection Approach
Background 2021 without Development
Background 2021 with Development
DOS
Delay (s)
LOS 95% Queue (m)
DOS Delay (s)
LOS 95% Queue (m)
Sleeper Lane (S)
L 0.03 3 A 1 0.04 5 A 1
T 0.03 3 A 1 0.04 4 A 1
R 0.03 3 A 1 0.04 4 A 1
Signal Terrace (E)
L 0.05 3 A 2 0.08 3 A 5
T 0.05 1 A 2 0.08 2 A 5
R 0.05 3 A 2 0.08 3 A 5
Sleeper Lane (N)
L 0.05 5 A 1 0.20 8 A 6
T 0.05 5 A 1 0.20 7 A 6
R 0.05 5 A 1 0.20 8 A 6
Signal Terrace (W)
L 0.18 2 A 8 0.23 2 A 11
T 0.18 0 A 8 0.23 1 A 11
R 0.18 1 A 8 0.23 2 A 11
All vehicles 0.18 1 NA 8 0.23 2 NA 11
Sleeper Lane / Signal Terrace Intersection Performance for 2021 PM Peak Hour
Intersection Approach
Background 2021 without Development
Background 2021 with Development
DOS
Delay (s)
LOS 95% Queue (m)
DOS Delay (s)
LOS 95% Queue (m)
Sleeper Lane (S)
L 0.02 5 A 0 0.03 7 A 1
T 0.02 4 A 0 0.03 7 A 1
R 0.02 5 A 0 0.03 7 A 1
Signal Terrace (E)
L 0.10 2 A 5 0.11 3 A 7
T 0.10 1 A 5 0.11 2 A 7
R 0.10 2 A 5 0.11 3 A 7
Sleeper Lane (N)
L 0.06 5 A 2 0.21 7 A 6
T 0.06 4 A 2 0.21 7 A 6
R 0.06 5 A 2 0.21 7 A 6
Signal Terrace (W)
L 0.14 2 A 7 0.19 2 A 11
T 0.14 1 A 7 0.19 1 A 11
R 0.14 2 A 7 0.19 2 A 11
All vehicles 0.14 1 NA 7 0.21 2 NA 11
As indicated in Table 4-10, the existing intersection configuration has sufficient capacity for all the approaches
under the background 2021 plus development.
The geometry of the existing intersection is considered sufficient for both operation and safety.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 19
4.11 Safe Walk/Cycle to School
There is no school located within 800m radius of the Site and it is expected that students living in the area will
utilise public transport.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 20
5 Site Specific Issues
5.1 Site Specific Transport Issues
The Site is expected to have minimal adverse impact on the surrounding area in terms of traffic generation or
safety.
5.2 Operation of Sleeper Lane
Sleeper Lane is 6 m wide, quite narrow and will mainly serve as the access for lots 5 and 6. As defined in
Liveable Neighbourhoods a narrow local access street with the width of 6m located along the rear /side of the
property boundary that is provided for vehicular access to higher density or missed used developments,
operates as a laneway. Therefore, it is expected that Sleeper Lane will operate as a low speed environment
(30km/h) due to its appearance as a lane way.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 21
6 Conclusions
This Transport Assessment outlines the transport aspects of the proposed redevelopment focusing on traffic
operations, access, and car parking. Discussion regarding pedestrian, cycle parking and public transport
considerations are also provided.
This statement has been prepared in accordance with the WAPC Transport Assessment Guidelines
for Developments: Volume 4 – Individual Developments (2006) for lodgement with the development application
for the City of Cockburn.
The following conclusions have been made in regards to the proposed development:
All 4 Stages are expected to generate relatively low traffic volumes of approximately 137 vehicle trips in
the AM peak hour and 167 vehicle trips in the PM peak hour which will have minimal impact on the
surrounding road network
The surrounding area has good pedestrian and cyclist provision
The Site has excellent public transport connectivity due to its close proximity to the Cockburn Central
Station
Accordingly, it is considered that the proposed development will have minimal impact in transport terms.
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 22
APPENDIX A CONCEPT DEVELOPMENT PLANS
UP
UP
UP
UP
UP
UPUPUPUP UP
UP UP UP UP UP
5
4
3
2
1
5
4
3
2
1
5
4
3
2
1
5
4
3
2
1
5
4
3
2
1
2
1
5
4
3
2
1
1
2
3
4
5
6
7
8
9
101
2
3
4
5
6
1
2
3
4
5
6
1
2
3
4
5
6
1
2
3
4
5
6
1
2
3
4
5
6
1
2
3
4
5
6
7
8
1 2 3 4 5
A-06-03
1
A-06-02
1
19.9 m²
STAIR 334.7 m²
TOWNHOUSE 534.6 m²
TOWNHOUSE 234.6 m²
TOWNHOUSE 1
68.9 m²
COMMERCIALUNIT 3
129.4 m²
COMMERCIALUNIT 1
81.3 m²
RESIDENTIAL BINSTORE
34.6 m²
TOWNHOUSE 3
58.5 m²
MAIN ENTRANCELOBBY
SSL 28.950
27.6 m²
BIKE STORE 1
9.2
m²
SM
SB
7.6 m²
GAS
14.9 m²
WATER
WC WC
3.1
m²
CO
MM
ER
CIA
LS
TO
RE
1
BOOSTER
AIR LOCK
WC
34.6 m²
TOWNHOUSE 4
HIGH LEVEL FEATURE CANOPYTO LOBBY ENTRY
CANOPY TOCOMMERCIAL UNITSMIN 2700 AGL
PLANTERPLANTER
28.0 m²
DISTRICTSUB-STATION
20.5 m²
BULK STORE
MOTORCYCLEPARKING
SECTIONAL O/H DOOR
LIFT SHAFT
F.I.
P
ALF
RE
SC
O D
ININ
GA
RE
A
SITE BOUNDARY
SIGNAL TERRACE
VISITOR BAY
3No. BIKERACKS
ME
CH
CO
MM
SE
LEC
T
CAR STANDING AREA ROOM FOR 3 CARS
7No. BAYS
8
A-07-04
8
A-07-04
6
A-07-03
6
A-07-03
PV5PV6
PV3 PV2 PV1
M1
M2
M4
M3
M5
M6
M7
PC-DPC1PC4 PC3 PC2PC5
P9
P10
P6P7P8
PV4
P13
P12
P11
VISITOR BAYVISITOR BAY VISITOR BAY
1
A-07-01
1
A-07-01
BMSB
CANOPY TO COMMERCIAL UNITSMIN 2700 AGL
4.7 m²
STORE 24.7 m²
STORE 34.7 m²
STORE 4
LIN
E O
F V
OID
OV
ER
LOC
KE
RS
66.1 m²
CAR PARKENTRANCE
SSL 29.600 SSL 29.600 SSL 29.600
LIGHT WEIGHTCONSTRUCTION IN-FILL
SSL 29.600
5.7 m²
NBN ROOM
3.1
m²
CO
MM
ER
CIA
LS
TO
RE
3
16.1 m²
END OF TRIP
114.3 m²
COMMERCIALUNIT 2
5.8
m²
CO
MM
ER
CIA
LS
TO
RE
2
17.2
m²
ST
AIR
1
3
A-07-02
3
A-07-02
5
A-07-03
5
A-07-03
5
A-13-10
1
A-13-24
6
A-13-24
1
A-13-22
1
A-13-23
2
A-13-23
16
A-13-21
AA
EE
6
6
5
5
D D
C C
F F
B B
7
7
8
8
9
9
10
10
SSL 29.160
SSL 28.850
SSL 28.750
RL 29.160
SSL 29.160
15.5
m²
CO
MM
ER
CIA
L B
INS
TO
RE
ST
R 0
1
SSL 29.200
SSL 29.150
SSL 29.600
SSL 29.015
SSL 29.010SSL 28.954
FALL
SSL 29.025
SSL 29.025
SSL 28.895
SSL 29.025
SSL 28.850
SSL 28.750
SSL 28.850
SSL 28.895
SSL 28.915
SS
L 28
.850
SSL 28.950
SSL 29.030
SSL 29.110
70mm STEP
SSL 29.130
SSL 29.040
SSL 29.040
SSL 29.040
SSL 29.120
SSL 29.160
SSL 29.120
SS
L 29
.120
SSL 29.130
1:10
ST
EP
RA
MP
SSL 29.060
SSL 29.130RL 29.160
SSL 29.120
SSL 29.140
SSL 29.130
SSL 29.120
SSL 29.110
SSL 29.170
RL 29.150
RL 29.130
RL 29.130
RL 29.140
RL 29.160
RL 29.160
RL 29.160
RL 29.160
RL 28.650
SSL 28.600
SSL 28.625
100mm STEP
FLOOR CHANNEL DRAIN TO HYDRAULICENGINEER'S DETAIL
FLOOR CHANNEL DRAIN TO HYDRAULICENGINEER'S DETAIL
SSL 28.850
SS
L 27
.900
SSL 27.950
SSL 27.900
SSL 27.950SSL 27.950
SSL 28.750
SSL 27.950SSL 27.950
SSL 27.930 SSL 27.930
SSL 27.950
7
A-08-06
4
A-08-04
8
A-08-07
4
A-08-08
2
A-08-09
1
A-08-06
2
A-08-02
3
A-08-01
STAGE 2
BATHTILES
LDY LDY LDY LDY LDY
BATHTILES
BATHTILES
BATHTILES
BATHTILES
BED 1LAMINATE
BED 1LAMINATE
BED 1LAMINATE
BED 1LAMINATE
BED 1LAMINATE
FH
FH
2500
8188
4312
4312
8188
1:10 STEP RAMP 1:10 STEP RAMP
1:10 STEP RAMP
1:6 STEP RAMP
1:10 STEPRAMP
11
A-13-24
FH
FW
FW
FW
FW
FW
TH
ST
AIR
5
TH
ST
AIR
4
TH
ST
AIR
3
TH
ST
AIR
2
TH
ST
AIR
1
STAIR 6
STAIR 9
STAIR 5
ST
AIR
12
ST
AIR
13
ST
AIR
14
ST
AIR
15
ST
AIR
16
FHR
1
A-19-05
3
A-16-07
ELECTRICAL TRENCH
ELECTRICAL TRENCH
REFER TO ELECTRICAL ENGINEER'SDRAWING DE-002 FOR FURTHERDETAILS OF SUB STATION WORKS
1
A-16-03
1
1
4
4
4
A-07-02
4
A-07-02
23
23
3400 4565 4550 5219 8431 10800 10800 7000 3565
TILES TILES TILES TILES TILES
FW
FW
TILE
FW
LL 29.480LL 29.480
PLANTER
LL 29.480
PLANTER
LL 29.480
SSL 28.820SSL 28.740SSL 28.680SSL 28.660
RL 29.530
RL 29.530 RL 29.530
04-EX16
RL 29.530 RL 29.530 RL 29.530
PLANTER
LL 29.480
SSL 28.750
SSL 29.040
SSL 29.040
03-ST05
DP DP DP DP
FW
FWSSL 27.900
FW
FW
FW
FW
FW
FW FW
FW FW
FW
TILES TILES
FW FW
FW
FW
SSL 29.040
SSL 28.990
FW
1:10
ST
EP
RA
MP
1:10STEP RAMP
/FOR CONTINUATION REFER DRAWING A-03-02
FHR
29.110 m
SSL 29.125J
A-09-09
G13D14.2
G14D14.2
G15D14.4
G16D14.4
G31D03.1
G29D03.4
G32D03.1
G33D03.1
G37D02.1
G36D02.1
G35D02.1
G28D14.4
G27D03.4
G06D18
G08D18
G07D18
G18D01.3
G17D07
G11D03.1
G10D03.1
G09D14.1 G03
D03.4
G20D06.3
G21D06.1
G22D06.1
G01D03.4
G02D03.4
G19D06.1
G26D14.1
G57D01
G75D01
G69D01
G38D03.4
G12D14.4
G63D01
G39D03.5
G40D03.5
G51D01
G52D20
G56D12
G55D11
G64D20
G68D12
G67D11
G58D20
G62D12
G61D11
G70D20
G74D12
G73D11
G76D20
G80D12
G79D11
G05D03.1
G04D14.2
G30D14.1
G34D03.1
G77D34
G71D34
G65D34
G59D34
G53D34
G78D13.2
G72D13.2
G66D13.2
G60D13.2
G54D13.2
G43D14.2
G42D40
G45D12.3
G01
W01
G02
W01
G03
W01
G04
W01
G05
W01
CW10
CW08
CW07
CW06
CW05
1301
CW01
CW03
CW02
1312
CW16
CW04
CW11
CW09
PFE
PFE
PFE
LIFT 1
LIFT 2
FD1
FD1 FD1
FHR
FH
FD2
FD1
FD1
FD1
FD2FD2
FD2 FD2
FD2
FD2
WR WR WR WR WR
FH FH
WC / SHOWER
EXISTING WASHED AGGREGATE SLAB
SEE NOTE 1
EXISTING WASHEDAGGREGATE SLABEXISTING WASHED AGGREGATE SLAB
EXISTING WASHEDAGGREGATE SLAB
3006 241 11720 2373 934 11744 1153 5299 100 8606
2194 2665 7975
NEW WASHED AGGREGATESLAB - SEE NOTE A
NEW WASHED AGGREGATESLAB - SEE NOTE B
SSL 28.530
SSL 28.588
SSL 28.690SSL 28.750 SSL 28.910
SSL 28.970 SSL 29.070SSL 29.100
SSL 29.125
SSL 29.070
SSL 29.150
SSL 29.015
RL 28.985
SSL 29.050SSL 28.875
SSL 28.800SSL 28.750
SSL 28.675
SSL 28.620
SSL 28.491
SSL 28.545
SSL 28.745SSL 28.925
1471
SSL 28.960
SSL 28.990
SSL 28.823
SSL 28.930
3510
35
02-TI02
SEE NOTE 3
SLE
EP
ER
LAN
E
SE
E N
OTE
2
CABLE ROUTE ACCESS INTO BUILDING
TACTILES AT 600mm DEEP
EXISTING WASHED AGGREGATE SLABEXISTING WASHEDAGGREGATE SLAB
SEE NOTE 1SEE NOTE 1SEE NOTE 1
SEE NOTE 1
SEE NOTE 1 SEE NOTE 1 SEE NOTE 1
EXISTING WASHED AGGREGATE SLAB
DS DS DS DS
DSDP
DS
DS DP
DS
DP
DS DP
DP
DP
DP
DS
DS
DS
DP
TW 29.680 TW 29.680 TW 29.680 TW 29.680 TW 29.680
VISITOR BAYVISITOR BAY
COMMUNICATIONSACCESS PIT
POWERACCESS PIT
TILES
CARPET
DSDS
LINE MARKING
DS
DS
COL5x CORA CBR3B BIKE RAILS(GRADE 316 STAINLESS STEEL)
1235
1000
1000
1000
1000
1090
900
DS
STEEL BEAM
CONCRETE CONCRETE
CONCRETE
7
A-13-31
LEGEND AND GENERAL NOTES
- REFER TO ARCHITECTURAL DRAWINGS SHEET A-00-03 FORARCHTECTURAL LEGEND AND GENERAL NOTES
- REFER TO A50 SERIES DRAWINGS FOR DETAILED ELECTRICALAND CEILING INFORMATION
- REFER TO A13 SERIES DRAWINGS FOR DETAILED WET AREALAYOUTS
FRL - /60/30 SELF CLOSING FIRE DOOR
FRL - /120/30 SELF CLOSING FIRE DOOR
FIRE DOOR LEGEND
FD1
FD2
SMD SMOKE DOOR - HOT AND COLD SMOKE SEALS
SETOUT SYMBOLS LEGEND
MJ STRUCTURAL MOVEMENT JOINT LOCATION - INSTALLTO AFS PANEL MANUFACTURER'S SPECIFICATION
NOTE: INSTALL SURFACE JOINTS AS REQUIRED IN LINE WITH AFS PANEL MANUFACTURER'S RECOMMENDATION
101W01
101D01
TYPENUMBER
TYPENUMBER
WINDOW / CURTAIN WALL / LOUVRE TAG
DOOR / TEMPORY DOOR / GATE / LOUVRE DOORROLLER SHUTTER TAG
101W01 HIGH LEVEL
CR CARD READER
DR DOOR RELEASE
*RL 29.000
NOTE A
NOTE B
HARD LANDSCAPE NOTES
LEVELS MARKED WITH AN ASTERISK ARE LEVELS TAKEN FROM THE SURVEYDRAWINGS.
EXPOSED AGGREGATE SLAB LAID ON GROUND 100mm THICK (MIN.) WITH L11 TMREINFORCING MESH
FINISH TO EXPOSED AGGREGATE SLAB TO BE HOLCIM WATTLE 32MPAAGGREGATE - 100% QUARTZ 7mm - 10mmMAX SLUMP - 80mm
FOAM EXPANSION JOINT TO BE APPLIED BETWEEN WINDOW FRAME AND SLAB.CONTROL JOINT TO BE APPLIED BETWEEN NOW AND OLD SLABS.CONTROL JOINTS TO BE INSTALLED AT 4.0M CTS MAX.SEE DRAWINGS A03-01 FOR SET-OUT OF CONTROL JOINTS.
EXPOSED AGGREGATE SLAB LAID ON GROUND 100mm THICK (MIN.) WITH L11 TMREINFORCING MESH
FINISH TO EXPOSED AGGREGATE SLAB TO BE HOLCIM SPINIFEX 32MPA WITH CCSMUDPACKAGGREGATE - 100% QUARTZ 7mm - 10mmMAX SLUMP - 80mm
FOAM EXPANSION JOINT TO BE APPLIED BETWEEN WINDOW FRAME AND SLAB.CONTROL JOINT TO BE APPLIED BETWEEN NOW AND OLD SLABS.CONTROL JOINTS TO BE INSTALLED AT 4.0M CTS MAX.SEE DRAWINGS A03-01 FOR SET-OUT OF CONTROL JOINTS.
NOTE 1
NOTE 2
NOTE 3
REMOVE EXISTING AGGREGATE AND REPLACE WITH NEW.
ALL WORK ALONG SLEEPER LANE BETWEEN GRID LANES A & THE CAR PARKENTRANCES, & BETWEEN THE TWO CAR PARK ENTRANCES ARE NEW WORKS.
ALL WORKS ALONG SIGNAL TERRACE ARE WORKS TO EXISTING PAVEMENT.
HARD LANDSCAPE - LEGEND
EXPOSED WASHED AGGREGATE FINISHCOLOUR - WATTLE
EXPOSED WASHED AGGREGATE FINISHCOLOUR - SPINIFEX WITH CCS MUDPACK
CAMERON
CHISHOLM
NICOL
Copyright Cameron Chisholm & Nicol (WA) Pty Ltd
ARCHITECT
CLIENT
PROJECT
TITLE
DATE DRAWN:
DRAWN: CHECKED: APPROVED:
DO NOT SCALE FROM DRAWINGS VERIFY ALL DIMENSIONSON SITE BEFORE COMMENCING WORK.COPY OR THE REPRODUCTION OF THIS DRAWING ISSTRICTLY PROHIBITED WITHOUT THE CONSENT OFCAMERON CHISHOLM & NICOL (WA) PTY LTD
NOTES:
KEY PLAN
(A1)
©
Cameron Chisholm &Nicol (WA) Pty LtdABN 81053861948
Level 3, Sheffield House713 Hay StreetPerth, Western Australia6000
+61 (0)8 9322 1566 +61 (0)8 9481 0854
[email protected] CCNWA.COM.AU
T
F
W
E
Perth
1:200 (A3)
M
SCALE
1 2 3 4 5 6
NOT FOR CONSTRUCTION
PROJ N° STAGE ZONE DISC./ DWG N° REV
PLOT DATE: 5/11/2015 5:33:25 PM
As indicated
B
HL
P05161
TENDERDOCUMENTATION
RM Approver
COCKBURN CENTRAL - LOT 5 - STAGE 1
51 A-03-01
SIGNAL TERRACE, WA 6164
GENERAL ARRANGEMENT PLAN GROUNDFLOOR - PART 1
1 : 100A-06-01
GROUND LEVEL - GA PLAN - PART 11
Date No. Revision Description Drawn
31/07/2015 A ISSUE FOR REVIEW
30/09/2015 B ISSUE FOR REVIEW
PART 1
PART 2
STAGE 2
STAGE 4 STAGE 3
STAGE 1
VOIDVOID VOID VOID VOID
UP
UP
UP
UP
5
4
3
2
1
2
1
1234
12 13 14 15 16 17
1 2 3 4 5 6 7
A-06-04
1
8
A-07-04
8
A-07-04
6
A-07-03
6
A-07-03
1
A-07-01
1
A-07-01
2
A-07-01
2
A-07-01
3
A-07-02
3
A-07-02
5
A-07-03
5
A-07-03
7
A-07-04
7
A-07-04
BIKE STORE 1 SM
SB
7.6 m²
GAS
14.9 m²
WATER
SHADED AREA INDICATIVE OFPLANT UNDERCROFT TO INCLUDEFIRE PUMP SYSTEM & 2noHYDRANT WATER STORAGE TANKS
AIRLOCK
PLANT ACCESSSTAIRS
28.0 m²
DISTRICTSUB-STATION
BULK STORE
MOTORCYCLEPARKING
SECTIONAL O/H DOOR
SECTIONAL O/H DOOR
SIT
E B
OU
ND
AR
Y
UP
UP
28.800 m
RISER SHAFT
VISITORBAY
VISITOR BAY
VISITOR BAY
VISITOR BAY
VISITOR BAY
VISITOR BAY
VISITOR BAY
VISITOR BAY
VISITOR BAY
COMM BIKES
CAR STANDING AREAROOM FOR 3 CARS
CAR STANDING AREAROOM FOR 6 CARS
7No. BAYS
EDGE OF SLAB
RETAINING WALL UNDER
WALL UP TO U/SIDEOF SLAB OVER
STEP IN SLAB
EDGE OF SLAB
S1-PV3
S2-PV2
S2-PV8
S2-PV7
S2-PV5
S2-PV4
PV9
PV8
PV7
P1
PV5PV6
PV3 PV2 PV1
S2-PV1
S2-PV6
M1
M2
M4
M3
M5
M6
M7
P35
P36
PC-DPC1PC4 PC3 PC2PC5
P9
P10
P2P3
P34
P15
P14
PV4
P23
P24
P25
P28
P27
P26
P5
P29
P13
P12
P11
VISITORBAY
VISITORBAY
VISITORBAY
BMSB
4.7 m²
STORE 2031
4.7 m²
STORE 3032
4.7 m²
STORE 4033
LOC
KE
RS
CAR PARK ENTRANCEPASSAGE
5600
5000
16.1 m²
END OF TRIP
STAIR 2
EE
6
5
5
D D
C C
F F
78910
SSL 27.950 SSL 27.950SSL 27.950
SSL 27.920
SSL 27.940
SSL 27.940 SSL 28.355
SSL 27.950 SSL 28.355
SSL 27.940
STEP
SSL 27.800
P30
SSL 27.800
SSL 27.170SSL 27.170
P16
P17
P18
P19
P20
P21
P22
ST
EP
ST
EP
STEP
SSL 28.355
SSL 28.375
SSL 28.335
SSL 28.355
SSL 27.250
1:20
1:8
SSL 28.780
SSL 27.960SSL 27.960
1:1
3
SSL 27.250
1:13
1:3
41:2
4
SSL 28.355
SSL 28.355
SSL 28.730
SSL 28.730
SSL 28.375 SSL 28.750 SSL 28.750
SSL 28.730
SSL 28.750
SSL 28.730
SSL 28.750
SSL 28.695
SSL 28.730
SSL 28.710
SSL 28.730
SSL 28.710
SSL 28.730
SSL 28.750
SSL 28.750
SSL 28.730 SSL 28.730
SSL 28.730
P4
SSL 28.730
SSL 28.825
SSL 28.795
SSL 28.730
SSL 28.760
SSL 28.790
SSL 28.800
SSL 28.700
SSL 28.725
SSL 28.720
SSL 28.720
SSL 28.750SSL 28.740
SSL 28.750
SSL 28.790
SSL 28.740
SSL 28.730
SSL 28.730
SSL 28.730
SSL 28.730
SSL 28.730
SSL 28.700
1:1
1
SSL 28.650SSL 28.670
SSL 28.730
SSL 28.680
SSL 28.640
SSL 28.570
SSL 28.700
SSL 28.660
SSL 29.120
SSL 28.560
SSL 28.680
SSL 28.730
SSL 27.260
8
A-08-07
1
A-08-06
1
A-08-03
4
A-08-05
STORMTECH CELLS BELOW.REFER TO HYDRAULICCONSULTANT'S DETAILS.
STORMTECH CELLS BELOW.REFER TO HYDRAULICCONSULTANT'S DETAILS.
SOAKWELL. REFER TOHYDRAULIC CONSULTANT'SDETAILS.
ST
AG
E 2
STAGE 3
SOAKWELL. REFER TOHYDRAULIC CONSULTANT'SDETAILS.
SOAKWELL. REFER TOHYDRAULIC CONSULTANT'SDETAILS.
SOAKWELL. REFER TOHYDRAULIC CONSULTANT'SDETAILS.
SOAKWELL. REFER TOHYDRAULIC CONSULTANT'SDETAILS.
STORMTECH CELLS BELOW.REFER TO HYDRAULICCONSULTANT'S DETAILS.
FHFH
FH
FHR
FH
4312
4312
8188
4525
7500
7500
7500
8431 10800 10800 7000 3565
STAIR 9
STAIR 5
STAIR 4
FW
FW
FWFW
FW
FW
FW
FW
FW FW
FW
FW
FW
PAINTED LINE
SSL 27.940
ST
EP
SSL 27.800
SSL 28.375SSL 27.978
SSL 27.978
A-06-02
2
1
1
4
4
J
J
H
H
G
G
K
K
2
2
3
3
ACO ACCESS "URBAN FILL" CLASS B(CODE: GS99C) HATCH TO WATERSTORAGE TANKS BELOW. SIZE1030X1030 X 85mm. TO BE INSTALLEDIN STRICT ACCORDANCE WITHMANUFACTURERS DETAILS ANDINSTRUCTIONS
/FOR CONTINUATION REFER DRAWING A-03-01
G24D03.5
G23D03.5
G42D40
G44D40
FW
FW
FHR
FD1
FD1
NEW WASHED AGGREGATESLAB - SEE NOTE A
300700
02-TI02
SSL 28.793
SSL 28.893
RL 28.860
SSL 28.796
SSL 28.764
300700
SSL 28.665
02-TI02
TACTILES AT 600mm DEEP
TACTILES AT 600mm DEEP
SLE
EP
ER
LAN
E
SE
E N
OT
E 3
LINE MARKING
VISITORBAY
VISITORBAY
FA
LL
MODDEX TUFFRAIL TR20Y MODULAR GMSBALUSTRADE. INSTALLED IN STRICTACCORDANCE WITH MANUFACTURER'SDETAILS AND INSTRUCTIONS
MODDEX TUFFRAIL TR20Y MODULAR GMSBALUSTRADE. INSTALLED IN STRICTACCORDANCE WITH MANUFACTURER'SDETAILS AND INSTRUCTIONS
.
DP
DISABLEDBAY
BOLLARD
DSDP
DP
DS
DP
MODDEX TUFFRAIL TR20Y MODULAR GMSBALUSTRADE. INSTALLED IN STRICTACCORDANCE WITH MANUFACTURER'SDETAILS AND INSTRUCTIONS
TW 28.500
DP
SOAKWELL. REFER TOHYDRAULIC CONSULTANT'SDETAILS.
DS
P6P7P8
FW
FWSSL 27.930
SSL 27.930
DS
DP
SOAKWELL. REFER TOHYDRAULIC CONSULTANT'SDETAILS.
DPDS
DP
DP
DP
DP
DP
DP
DSDP
DP DS
POTABLE PUMPROOM
TANK 2TANK 1
RISER SHAFT OVER
UP
SSL 25.650
2no HYDRANT WATERSTORAGE TANKS
7
A-07-04
7
A-07-04
6
A-08-03
WATER BREAK TANK
ACCESSLADDER
SSL 25.650 SSL 25.650
STAIR 4
1
1
J
J
H
H
2
3
3
2
FW
FW
FW
FRL - /60/30 SELF CLOSING FIRE DOOR
FRL - /120/30 SELF CLOSING FIRE DOOR
FIRE DOOR LEGEND
FD1
FD2
SMD SMOKE DOOR - HOT AND COLD SMOKE SEALS
LEGEND AND GENERAL NOTES
- REFER TO ARCHITECTURAL DRAWINGS SHEET A-00-03 FORARCHTECTURAL LEGEND AND GENERAL NOTES
- REFER TO A50 SERIES DRAWINGS FOR DETAILED ELECTRICALAND CEILING INFORMATION
- REFER TO A13 SERIES DRAWINGS FOR DETAILED WET AREALAYOUTS
SETOUT SYMBOLS LEGEND
MJ STRUCTURAL MOVEMENT JOINT LOCATION - INSTALLTO AFS PANEL MANUFACTURER'S SPECIFICATION
NOTE: INSTALL SURFACE JOINTS AS REQUIRED IN LINE WITH AFS PANEL MANUFACTURER'S RECOMMENDATION
101W01
101D01
TYPENUMBER
TYPENUMBER
WINDOW / CURTAIN WALL / LOUVRE TAG
DOOR / TEMPORY DOOR / GATE / LOUVRE DOORROLLER SHUTTER TAG
101W01 HIGH LEVEL
CR CARD READER
DR DOOR RELEASE
HARD LANDSCAPE - LEGEND
EXPOSED WASHED AGGREGATE FINISHCOLOUR - WATTLE
EXPOSED WASHED AGGREGATE FINISHCOLOUR - SPINIFEX WITH CCS MUDPACK
*RL 29.000
NOTE A
NOTE 3
HARD LANDSCAPE NOTES
LEVELS MARKED WITH AN ASTERISK ARE LEVELS TAKEN FROM THE SURVEYDRAWINGS.
EXPOSED AGGREGATE SLAB LAID ON GROUND 100mm THICK (MIN.) WITH L11 TMREINFORCING MESH
FINISH TO EXPOSED AGGREGATE SLAB TO BE HOLCIM WATTLE 32MPAAGGREGATE - 100% QUARTZ 7mm - 10mmMAX SLUMP - 80mm
FOAM EXPANSION JOINT TO BE APPLIED BETWEEN WINDOW FRAME AND SLAB.CONTROL JOINT TO BE APPLIED BETWEEN NOW AND OLD SLABS.CONTROL JOINTS TO BE INSTALLED AT 4.0M CTS MAX.SEE DRAWINGS A03-01 FOR SET-OUT OF CONTROL JOINTS.
ALL WORK ALONG SLEEPER LANE BETWEEN GRID LANES A AND THE CAR PARKENTRANCES, AND BETWEEN THE TWO CAR PARK ENTRANCES ARE NEW WORKS.
CAMERON
CHISHOLM
NICOL
Copyright Cameron Chisholm & Nicol (WA) Pty Ltd
ARCHITECT
CLIENT
PROJECT
TITLE
DATE DRAWN:
DRAWN: CHECKED: APPROVED:
DO NOT SCALE FROM DRAWINGS VERIFY ALL DIMENSIONSON SITE BEFORE COMMENCING WORK.COPY OR THE REPRODUCTION OF THIS DRAWING ISSTRICTLY PROHIBITED WITHOUT THE CONSENT OFCAMERON CHISHOLM & NICOL (WA) PTY LTD
NOTES:
KEY PLAN
(A1)
©
Cameron Chisholm &Nicol (WA) Pty LtdABN 81053861948
Level 3, Sheffield House713 Hay StreetPerth, Western Australia6000
+61 (0)8 9322 1566 +61 (0)8 9481 0854
[email protected] CCNWA.COM.AU
T
F
W
E
Perth
M
SCALE
NOT FOR CONSTRUCTION
PROJ N° STAGE ZONE DISC./ DWG N° REV
PLOT DATE: 5/11/2015 5:34:44 PM
As indicated
B
HL
P05161
TENDERDOCUMENTATION
RM Approver
COCKBURN CENTRAL - LOT 5 - STAGE 1
A-03-02
SIGNAL TERRACE, WA 6164
GENERAL ARRANGEMENT PLAN GROUNDFLOOR - PART 2
1 : 100A-06-01
GROUND LEVEL - GA PLAN - PART 21
1 : 100A-07-04
LEVEL 0 - PLANT UNDERCROFT2
Date No. Revision Description Drawn
31/07/2015 A ISSUE FOR REVIEW
30/09/2015 B ISSUE FOR REVIEW
RAMP 1
PART 1
PART 2
STAGE 2
STAGE 4 STAGE 3
STAGE 1
UP
UP
UP
UP
54321
30
29
28
27
26
25
24
23
22
21
20
19
18
16
15
14
13
12
11
10
9
8
7
6
5
4
3
16
15
14
13
12
11
10
9
8
7
6
5
4
3
16
15
14
13
12
11
10
9
8
7
6
5
4
3
16
15
14
13
12
11
10
9
8
7
6
5
4
3
16
15
14
13
12
11
10
9
8
7
6
5
4
3
36
35
34
33
32
31
30
29
28
27
26
25
24
23
22
21
20
19
A-06-03
1
A-06-02
1
8
A-07-04
8
A-07-04
6
A-07-03
6
A-07-03
1
A-07-01
1
A-07-01
3
A-07-02
3
A-07-02
5
A-07-03
5
A-07-03
68.4 m²
APARTMENT 11
50.3 m²
APARTMENT 1252.5 m²
APARTMENT 13
10.8 m²
APT 10 BALCONY
51.1 m²
APARTMENT 98.9 m²
APT 9 BALCONY
LIFT SHAFT
53.5 m²
APARTMENT 10
7.1 m²
APT 12 BALCONY
6.7 m²
APT 13 BALCONY8.3 m²
TH 4 BALCONY8.3 m²
TH 3 BALCONY8.9 m²
TH 2 BALCONY8.3 m²
TH 1 BALCONY
7.6 m²
APT 11 BALCONY
MOTORCYCLE
PARKING
SITE BOUNDARY
COLORBOND FASCIA ANDCAPPING
HIGH LEVEL GLAZED FEATURE ENTRYAWNING
COLORBOND BOX GUTTER LAIDTO FALLS
COLORBOND FASCIA ANDCAPPING
COLORBOND BOX GUTTERLAID TO FALLS
53.9 m²
APARTMENT 8
VO
ID
GLAZED BALUSTRADE TOBALCONIES
ME
CH
CO
MM
SE
LEC
9No. BAYS
P56
P40P41P45P47P51 P49P53 P37
P52 P50P54
P55
M8
P63
P64
P58
P57
P59
P60P61P62
5.1
m²
ST
OR
E 1
9
4.3 m²
STORE 154.4 m²
STORE 12
33.5 m²
BIKE STORE 2
M15
M9
M14
M13
M12
M11
M10
P48 P46 P42 P39 P38
M16
1569
ACCESSRAMP 2
3.9 m²
STORE 5
4.3 m²
STORE 164.3 m²
STORE 174.3 m²
STORE 18
3.1 m²
STORE 203.1 m²
STORE 22
8.3 m²
TH 5 BALCONY
3.2 m²
STORE 214.1 m²
STORE 7
3.9 m²
STORE 233.9 m²
STORE 24
105.8 m²
CORRIDOR
15.7 m²
LEVEL 1 LOBBY
STAIR 1
13.2 m²
LOBBY
4.4 m²
STORE 14
4.2 m²
STORE 13
4.4 m²
STORE 114.4 m²
STORE 104.5 m²
STORE 9
4.5
m²
ST
OR
E 8
4.0 m²
STORE 6
450
AA
EE
6
6
5
5
D D
C C
F F
B B
7
7
8
8
9
9
10
10
F
A-09-06
G
A-09-07
6
A-08-07
5
A-08-04
3
A-08-09
12
A-08-06
3
A-08-02
5
A-08-01
1
A-08-07
FE
FE
FH
FH
FHR
FHR
STAGE 2
WCTILES
WCTILES
WCTILES
WCTILES
WCTILES
BATHTILES
BATHTILES
BATHTILES
BATHTILES
LIVINGLAMINATE
LIVINGLAMINATE
LIVINGLAMINATE
LIVINGLAMINATE
LIVINGLAMINATE
LIVINGLAMINATE
LIVINGLAMINATE
LIVINGLAMINATE
LIVINGLAMINATE
LIVINGLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
BED 1CARPET
BED 1CARPET
BED 1CARPET
BED 2CARPET
BED 1CARPET
BED 1CARPET
BATHTILES
FH
FH
LDY
LDY LDY
LDY
LDY
SSL 32.500
SSL 32.500
SSL 32.500 SSL 32.500
SSL 32.430SSL 32.430
SSL 32.430
SSL 32.500
SSL 32.500
SSL 32.500SSL 32.500SSL 32.500SSL 32.500SSL 32.500
SSL 31.700
SSL 32.500
SSL 31.325
SS
L 31
.700
SSL 32.500
SSL 32.500
SSL 32.500 SSL 32.040
SSL 32.500SSL 32.500
SSL 32.500 SSL 32.430
SSL 32.430
SSL 32.480SSL 32.480SSL 32.435 SSL 32.435 SSL 32.480
SSL 32.500
DINING DINING DINING DINING DINING
DIN
INGDINING
DINING
DIN
ING
DIN
ING
2500
8188
4312
4312
8188
3400 4565 4550 5219 8431 10800 10800 7000 3565
2
A-13-20
TH
ST
AIR
5
TH
ST
AIR
4
TH
ST
AIR
3
TH
ST
AIR
2
TH
ST
AIR
1
ST
AIR
7
STAIR 10
23.5 m²
STAIR 3
2°
2°
2°
STUDY
FE
FE
2
A-19-055
A-19-05
6
A-16-03
1
1
4
4
4
A-07-02
4
A-07-02
8
A-16-03
23
23
/FOR CONTINUATION REFER DRAWING A-03-04
FW FW FW FWFW
34.7 m²
TOWNHOUSE 534.6 m²
TOWNHOUSE 434.6 m²
TOWNHOUSE 334.6 m²
TOWNHOUSE 234.6 m²
TOWNHOUSE 1
FW
FW FW
FW
FW
FW
FW
FW
FW
FW
ACOCHANNELDRAIN
FW FW FW FW FW FW
FW
FW
FW
1001D14.4
1092D13.1
1086D13.1
1091D14.4
1078D13.1
1080D13.1
1083D12.11082
D12
1084D13.2
1077D14.4
1085D14.4
1040D14.4
1042D14.4
1043D12.2
1045D12.2
1044D14.4
1047D12.2
1046D14.4
1048D14.4
1049D12.2
1002D14.4
1003D14.4
1010D14.4
1014D13.1
1015D13.1
1022D13.4
1016D13.1
1017D13.1
1024D14.4 1025
D02.11026
D02.1
1029D14.4
1028D07
1027D01.3
1071D14.4
1072D13.1
1069D13.1
1068D14.4
1067D12
1066D11
1065D13.2
1063D13.1
1032D03.1
1041D12.2
1023D14.4
1064D36
1081D32
1079D32
1070D36
1093D34
1087D34
1073D35
1033D13.4
1074D13.2
1075D11
1076D12
1094D13.2
1095D11
1096D12
1088D13.2
1089D11
1090D12
1000D13.2
1038D11
1037D12
1097D14.4
101
W26
102
W26
103
W26
104
W26
124
W28
122
W28
119
W18
118
W16
120
W30
115
W03
114
W34
112
W25
105
W26117
W11.1
113
W8.1
111
W8.2
110
W8.2
123
W8.2
121
W8.2
116
W8.2
WR WR
WR WR
WR
WR
FD1
FD1
FD1 FD1 FD1 FD1
FD1 FD1
FD1 FD1
FD1 FD1
FD1
FD1
FD1
FD1
FH
FD1
FD1
SMD
SMD
LIFT 1
LIFT 2
FW
FEATURE ALUMINIUM FRAMES AROUNDWINDOW OPENINGS (TYP)
SLIP RESISTANT TILES
FWDP
SSL 34.114
DSDSDS
LYSAGHT STANDARD KLIP-LOCK 700 ROOFSHEETING WITH CONCEALED FIXINGS,FIXED TO PURLINS IN LINE WITHMANUFACTURER'S DETAILS & AS1562.1
NOTE:ROOF ACCESS BYSPECIALISTCONTRACTOR
SUMP WITH O/F POP SUMP WITH O/F POPSUMP WITH O/F POP
STEEL BEAM
CONC
TILE TILE TILE TILE TILE TILE
TILE
TILE
TILE
TILE
DS
DS
DS
DS
DS
DP
DS
CARPET
CONCRETE
DPTD
AC
DPTD
AC
DPTD
AC
DPTD
AC
DPTD
AC
DPTD
AC
DPTD
AC
DPTD
AC
DS SUMP WITH O/F POP
SUMP WITH O/F POP
DPTD
AC
DPTD
AC
DS
DS
DS
DS
DPDPDS
COL.
SETOUT SYMBOLS LEGEND
MJ STRUCTURAL MOVEMENT JOINT LOCATION - INSTALLTO AFS PANEL MANUFACTURER'S SPECIFICATION
NOTE: INSTALL SURFACE JOINTS AS REQUIRED IN LINE WITH AFS PANEL MANUFACTURER'S RECOMMENDATION
101W01
101D01
TYPENUMBER
TYPENUMBER
WINDOW / CURTAIN WALL / LOUVRE TAG
DOOR / TEMPORY DOOR / GATE / LOUVRE DOORROLLER SHUTTER TAG
101W01 HIGH LEVEL
CR CARD READER
DR DOOR RELEASE
LEGEND AND GENERAL NOTES
- REFER TO ARCHITECTURAL DRAWINGS SHEET A-00-03 FORARCHTECTURAL LEGEND AND GENERAL NOTES
- REFER TO A50 SERIES DRAWINGS FOR DETAILED ELECTRICALAND CEILING INFORMATION
- REFER TO A13 SERIES DRAWINGS FOR DETAILED WET AREALAYOUTS
FRL - /60/30 SELF CLOSING FIRE DOOR
FRL - /120/30 SELF CLOSING FIRE DOOR
FIRE DOOR LEGEND
FD1
FD2
SMD SMOKE DOOR - HOT AND COLD SMOKE SEALS
CAMERON
CHISHOLM
NICOL
Copyright Cameron Chisholm & Nicol (WA) Pty Ltd
ARCHITECT
CLIENT
PROJECT
TITLE
DATE DRAWN:
DRAWN: CHECKED: APPROVED:
DO NOT SCALE FROM DRAWINGS VERIFY ALL DIMENSIONSON SITE BEFORE COMMENCING WORK.COPY OR THE REPRODUCTION OF THIS DRAWING ISSTRICTLY PROHIBITED WITHOUT THE CONSENT OFCAMERON CHISHOLM & NICOL (WA) PTY LTD
NOTES:
KEY PLAN
(A1)
©
Cameron Chisholm &Nicol (WA) Pty LtdABN 81053861948
Level 3, Sheffield House713 Hay StreetPerth, Western Australia6000
+61 (0)8 9322 1566 +61 (0)8 9481 0854
[email protected] CCNWA.COM.AU
T
F
W
E
Perth
M
SCALE
NOT FOR CONSTRUCTION
PROJ N° STAGE ZONE DISC./ DWG N° REV
PLOT DATE: 5/11/2015 5:35:52 PM
As indicated
B
HL
P05161
TENDER
DOCUMENTATION
RM
COCKBURN CENTRAL - LOT 5 - STAGE 1
A-03-03
SIGNAL TERRACE, WA 6164
GENERAL ARRANGEMENT PLAN LEVEL 1 -PART 1
1 : 100A-06-01
LEVEL 1 - GA PLAN - PART 11
Date No. Revision Description Drawn
31/07/2015 A ISSUE FOR REVIEW
30/09/2015 B ISSUE FOR REVIEW
PART 1
PART 2
STAGE 2
STAGE 4 STAGE 3
STAGE 1
UP
UP
UP
UP
UP
3
2
1
333231302928272625242322
38 37 36 35 34
6
5
4
3
2
1
4321
UP
A-06-01
1
A-06-02
1
8
A-07-04
8
A-07-04
1
A-07-01
1
A-07-01
2
A-07-01
2
A-07-01
3
A-07-02
3
A-07-02
5
A-07-03
5
A-07-03
7
A-07-04
7
A-07-04
51.1 m²
APARTMENT 9
8.9 m²
APT 9 BALCONY
10.0 m²
APT 8 BALCONY
11.9 m²
LIFT SHAFT
53.5 m²
APARTMENT 10
SSL 32.023
50.9 m²
APARTMENT 7
51.3 m²
APARTMENT 6
6.4 m²
STAIR 2
4.8
m²
AP
T 7
BA
LCO
NY
APARTMENT FITOUT IN STAGE 3
MOTORCYCLE
PARKING
SIT
E B
OU
ND
AR
Y
4.6
m²
AP
T 6
BA
LCO
NY
53.9 m²
APARTMENT 8
TEMPORARY FENCE TO BE INSTALLED AND ONLY REMOVED ON COMPLETION OF STAGE 3.
ME
CH
CO
MM
SE
LEC
9No. BAYS
EDGE OF SLAB
WALL UP TO SLAB OVER
300 WIDE CONCRETEKERB TO SIDES OF RAMP.
6750
800
EDGE OF SLAB
P56
P101
P40P41P45P47P51 P49P53
P87
P37
P77
P76
P75
P79
P78
P82
P83
P84
P52 P50P54
P80
P81
P55
M8
P85
P86
P67
P66
P63
P64
P65
P58
P57
P59
P60P61P62
P88
P89
P93
P96
P97
P100
P99
P98
P43
P90
P91
P95
P94
1m TURNINGPOINT AT ENDOF LANE
5.1 m²
STORE 194.3 m²
STORE 154.4 m²
STORE 12
33.5 m²
BIKE STORE 2
M15
M9
M14
M13
M12
M11
M10
P48 P46
P44
P42 P39 P38
M16
ACCESSRAMP 2
4.3 m²
STORE 164.3 m²
STORE 174.3 m²
STORE 18
3.1 m²
STORE 203.1 m²
STORE 22
1394
3.2 m²
STORE 214.1 m²
STORE 7
3.9 m²
STORE 23
3.9 m²
STORE 24
15.7 m²
LEVEL 1 LOBBY
11.7 m²
STAIR 1
13.2 m²
LOBBY
4.4 m²
STORE 14
4.2 m²
STORE 13
4.4 m²
STORE 114.4 m²
STORE 104.5 m²
STORE 9
4.5 m²
STORE 8
4.0 m²
STORE 6
P92
EE
6
6
5
5
D D
F F
7
7
8
8
9
9
10
10
SSL 32.500
SSL 32.500
SSL 32.040
SSL 31.765
SSL 34.225
SSL 30.400
SSL 30.430
SSL 30.430SSL 30.430
SSL 30.430SSL 30.460
SSL 30.460
1:8
SSL 30.460 SSL 30.430 SSL 30.430 SSL 30.460
SSL 31.330 SSL 31.300 SSL 31.300
SSL 31.330
SSL 31.285
SSL 31.285
SSL 31.300 SSL 31.300
SSL 31.300SSL 31.300
SSL 31.300
SSL 31.330
SSL 31.310
SSL 31.330SSL 31.330
SSL 31.310SSL 31.310
SSL 31.300
SSL 31.330
1:1
6
SSL 31.725
SSL 31.765
SSL 31.765
SSL 32.040
SSL 32.000
SSL 31.330 SSL 32.040
SSL 31.330
SSL 31.330
SSL 31.330
SSL 31.330
SSL 31.330
SSL 31.870 SSL 32.040
1:271:27
SSL 32.040 SSL 32.040
27.2 m²
M/C PARKING
11
A-08-07
1
A-08-07
15
A-08-07
12
A-08-06
5
A-08-01
5
A-08-05
7
A-08-03
ST
AG
E 2
STAGE 3
FH
FHR
FHR
FH
FH
FH
FE
BATHTILES
BATHTILES
KITCHENLAMINATE
BED 1CARPET
BED 1CARPET
LIVINGLAMINATE
BED 1CARPET
BED 1CARPET
BED 1CARPET
BATHTILES
BATHTILES
BATHTILES
KITCHENLAMINATE
KITCHENLAMINATE
KITCHENLAMINATE
LIVINGLAMINATE
LDY
LDY
LDY
LDY
LIVINGLAMINATE
LIVINGLAMINATE
RA
MP
RA
MP
RAMP 1
LDY
RAMP
SSL 32.500
SSL 32.040
SSL 32.500
SSL 32.500
SSL 32.430
SSL 32.500
SSL 32.430
FW
SS
L 32
.480
SS
L 32
.480
SSL 32.500
SSL 32.500
SS
L 31
.619
DINING
DINING
SSL 32.040
7500
7500
7500
4525
8188
4312
BALUSTRADE TYPE 1 - GLASS PANELSWITH POWDERCOATED ALUMINIUMHANDRAIL AND PROPRIETARY FIXINGS
STAIR 7
STAIR 8
STAIR 11
FW
FW
FW
FW
TANDEM BAY
TANDEM BAY
VENTILATIONSHAFT
4
A-13-21
A-06-02
2
1
1
4
4
J
J
H
H
G
G
K
K
2
2
3
3
/FOR CONTINUATION REFER DRAWING A-03-03
3400 4565 4550 5219 8431 10800 10800 7000 3565
FW
FW
FW
FW
FW
FW
FW
FW
FW
IN-SITU CONCRETE RAMP TO STRUCTURALENGINEER'S DETAIL
WALL MOUNTED HANDRAIL TO COMPLYWITH AS1428.1
TACTILE INDICATOR (TGSI) TO COMPLYWITH AS 1428.4, REFER TO FINISHESSCHEDULE
1068D14.4
1067D12 1066
D11
1065D13.2
1063D13.1
1062D14.4
1056D14.4
1057D13.11060
D13.2
1059D11
1061D12
1055D12
1053D11
1051D13.1
1054D13.2
1050D14.4
1036D14.4
1039D14.4
1035D14.4
1034D14.4
1064D36
1058D32
1052D32
1033D13.4
112
W25
109
W25
108
W02
106
W02
107
W24
110
W8.2
100
W32
125
W7.1
126
W29
1002D14.4
WR
WR
WR
FD1
FD1
FD1
FD1FD1
FD1
FD1
FD1
FD1
FD1 FD1
FD1
FD1
MOVEMENT JOINT IN STRICT ACCORDANCEWITH STRUCTURAL ENGINEER'S DETAILSAND INSTRUCTIONS
CONCRETE
CONCRETE
CONCRETE
DP
DP
DP
DS DP
DS
DS
DP
DP
DP
DS
DP
DP
DP
DP
DPDS
DS
DS
DPAC
DPTD
TD
AC
AC
CONCRETE
TIL
E
TIL
E
LEGEND AND GENERAL NOTES
- REFER TO ARCHITECTURAL DRAWINGS SHEET A-00-03 FORARCHTECTURAL LEGEND AND GENERAL NOTES
- REFER TO A50 SERIES DRAWINGS FOR DETAILED ELECTRICALAND CEILING INFORMATION
- REFER TO A13 SERIES DRAWINGS FOR DETAILED WET AREALAYOUTS
CAMERON
CHISHOLM
NICOL
Copyright Cameron Chisholm & Nicol (WA) Pty Ltd
ARCHITECT
CLIENT
PROJECT
TITLE
DATE DRAWN:
DRAWN: CHECKED: APPROVED:
DO NOT SCALE FROM DRAWINGS VERIFY ALL DIMENSIONSON SITE BEFORE COMMENCING WORK.COPY OR THE REPRODUCTION OF THIS DRAWING ISSTRICTLY PROHIBITED WITHOUT THE CONSENT OFCAMERON CHISHOLM & NICOL (WA) PTY LTD
NOTES:
KEY PLAN
(A1)
©
Cameron Chisholm &Nicol (WA) Pty LtdABN 81053861948
Level 3, Sheffield House713 Hay StreetPerth, Western Australia6000
+61 (0)8 9322 1566 +61 (0)8 9481 0854
[email protected] CCNWA.COM.AU
T
F
W
E
Perth
M
SCALE
NOT FOR CONSTRUCTION
PROJ N° STAGE ZONE DISC./ DWG N° REV
PLOT DATE: 5/11/2015 5:37:35 PM
As indicated
B
HL
P05161
TENDERDOCUMENTATION
RM Approver
COCKBURN CENTRAL - LOT 5 - STAGE 1
A-03-04
SIGNAL TERRACE, WA 6164
GENERAL ARRANGEMENT PLAN LEVEL 1 -PART 2
1 : 100A-06-01
LEVEL 1 - GA PLAN - PART 21
Date No. Revision Description Drawn
31/07/2015 A ISSUE FOR REVIEW
30/09/2015 B ISSUE FOR REVIEW
PART 1
PART 2
STAGE 2
STAGE 4 STAGE 3
STAGE 1
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 23
Transport Assessment
APPENDIX B WAPC CHECKLIST
Lot 5 Signal Terrace, Cockburn Central Transport Assessment
CW932300 Cardno 06 November 2015 Prepared for Fraser Property Australia 24
Item Status Comments/Proposals
Proposed development
proposed land use Included Discussed in Section 3
existing land uses Included Discussed in Section 2
context with surrounds Included Discussed in Section 2.1
Vehicular access and parking
access arrangements Included Discussed in Section 3.2
public, private, disabled parking set down / pick up Included Discussed in Section 4.4
Service vehicles (non-residential)
access arrangements Included Discussed in Section 3.3
on/off-site loading facilities Included Discussed in Section 3.3
Service vehicles (residential)
Rubbish collection and emergency vehicle access N/A
Traffic volumes
daily or peak traffic volumes Included Discussed in Section 2.5
type of vehicles (e.g. cars, trucks) Included Discussed in Section 4.2
Traffic management on frontage streets Included Discussed in Sections 2.2 & 2.3
Public transport access
nearest bus/train routes Included Discussed in Sections 2.7
nearest bus stops/train stations Included Discussed in Sections 2.7
pedestrian/cycle links to bus stops/train station Included Discussed in Section 2.7
Pedestrian access/facilities
existing pedestrian facilities within the development (if any) Included Discussed in Section 2.6
proposed pedestrian facilities within development Included Discussed in Section 4.8
existing pedestrian facilities on surrounding roads Included Discussed in Section 2.6
proposals to improve pedestrian access Included Discussed in Section 5.1
Cycle access/facilities
existing cycle facilities within the development (if any) N/A
proposed cycle facilities within the development N/A
existing cycle facilities on surrounding roads Included Discussed in Section 2.6
proposals to improve cycle access N/A
Site specific issues
Safety issues
identify issues Included Discussed in Section 5.1
remedial measures N/A