Dear Resident WORKS IN YOUR AREA MONDAY 22 FEBRUARY TO MONDAY 7 MARCH 2016 The CityLink Tulla Widening project involves adding lanes and other measures to improve the flow of traffic across the 24 kilometre section of freeway from the CityLink tunnels to Melbourne Airport. The project will also provide travel time savings per trip between Melbourne Airport and the West Gate Freeway during peak periods. The project will deliver a safer, more reliable freeway. Generally, an additional lane is being added in each direction, as well as upgrades at key interchanges including Bell Street, Mount Alexander Road/Flemington Road and on the Bolte Bridge to West Gate Freeway entry ramp. CPB Contractors is the construction contractor for the Bulla Road to Power Street section of the project. Where we will be In the cul-de-sac of Waxman Parade next to the CityLink Tulla Freeway, as indicated in red on the map below.
Transcript

Dear Resident

WORKS IN YOUR AREA MONDAY 22 FEBRUARY TO MONDAY 7 MARCH 2016

The CityLink Tulla Widening project involves adding lanes and other measures to improve the flow of traffic across the 24 kilometre section of freeway from the CityLink tunnels to Melbourne Airport. The project will also provide travel time savings per trip between Melbourne Airport and the West Gate Freeway during peak periods.

The project will deliver a safer, more reliable freeway. Generally, an additional lane is being added in each direction, as well as upgrades at key interchanges including Bell Street, Mount Alexander Road/Flemington Road and on the Bolte Bridge to West Gate Freeway entry ramp.

CPB Contractors is the construction contractor for the Bulla Road to Power Street section of the project.

Where we will beIn the cul-de-sac of Waxman Parade next to the CityLink Tulla Freeway, as indicated in red on the map below.

When works will occurFrom 7am to 6pm Monday 22 February until Monday 7 March 2016.

CityLink

k

Yarrabin Street

Waxman Parade

What we are doingConnecting our site compound within CityLink land into existing utility services located in the area. This will involve:

Temporarily closing the cul-de-sac using traffic management signs and bollards Cutting holes in the road within the cul-de-sac using a specialised vacuum truck (non-

destructive digging) to safely uncover underground pipes and services Recording the location of pipes and services Connecting into the existing water, sewer and power services Reinstating our work areas.

What to expect A small team of construction personnel at work Noise from the non-destructive digging truck, excavator and site vehicles when in use Traffic management personnel will direct footpath pedestrians and garbage collection

services safely around the works Vegetation and a small tree will be removed as part of these works. These works will not impact your services or access to your property.

We are committed to keeping residents informed and minimising the inconvenience during construction, while keeping the community and our workers safe at all times. Managing and protecting the environment is also important to us and we are working with local and state government adhering to environmental laws to ensure the impact to the natural ecosystem is minimised.

This work may be rescheduled in the event of unsuitable weather or other unavoidable circumstances.

If you have any questions or concerns regarding this notification, please phone 1300 783 947 and select 1 or email us at [email protected]

131 450

Yours sincerely,

Community Relations TeamCPB ContractorsCityLink Tulla Widening: Bulla Road to Power Street

15/02/2016, Ref: 0053 F01