C9: Wave & Tidal Business Forum
Transcript
Page 1: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

C9: Wave & Tidal

Business Forum

Page 2: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Lynne BrycelandInnovation Development Officer,

ScottishPower Renewables

Page 3: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Sound of Islay –

Supply Chain Opportunities

RenewableUK

Annual Conference

6 November 2013

Lynne Bryceland,

Innovation Development Officer

Page 4: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

4

Iberdrola

One of the largest global electricity companies

22 million supply points - over 40 countries

World’s No.1 wind operator

14,000 MW of installed wind capacity

More than 60,000 MW in development

ScottishPower Renewables

Largest UK wind operator - > 1300 MW

200 employees, growing rapidly

£1bn invested in UK over past 10 years

Diversifying into Offshore Wind & Marine

Iberdrola-ScottishPower Renewables

Page 5: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Sound of Islay Tidal Array

Project Update

Page 6: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

6

Islay Tidal Demonstration Array Project

• Developer: ScottishPower Renewables

• Technology: ANDRITZ HYDRO Hammerfest

and Alstom TGL

• Local Partner: Islay Energy Trust

• Size: 10MW

• Location: Sound of Islay, Argyll, UK

Page 7: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

7

Islay - Site Credentials

• Strong tidal flow

• Suitable depth

• Shelter from high wave and high winds

• Low environmental impact

• Grid capacity

Page 8: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

8

Islay - Project Status

• Planning consent secured

• Agreement for Lease secured

• Grid connection secured

• Flow surveys completed, tidal regime confirmed

• Seabed surveys completed

• Turbine layout optimised

Page 9: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

9

ANDRITZ HYDRO Hammerfest HS1000

• World’s 1st grid-connected tidal device

• Leading technology concept:

• Seabed-mounted

• Open-rotor

• Five year track record (>15,000hrs)

• Two successful installations

• Scottish base established

• First installed at EMEC Dec 2011

• Successful retrieval and thorough

inspection

• Reinstalled September 2013 for extended

reliability tests into 2014

Page 10: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

10

ALSTOM TGL DEEPGen IV.1

• 500kW 1st generation deployed and

tested at EMEC for over 2 years

• 1MW device now installed at EMEC and

in testing

• Participating in ETI ReDAPT

• Some significant design and operational

differences between TGL and AHH

• Key learning opportunities for SPR

Page 11: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Tidal Generation: Future Opportunities

Page 12: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

12

Supply Chain Opportunities

Engineering and Manufacture

• Fabrication

• Blade manufacture

• Assembly – drive train

• Component supply

O&M/Facilities

• Cabling & mooring works

• Installation, commissioning & testing

• Port & harbour facilities

• Onshore works – electrical & civil

• Vessels & barges

• Servicing & maintenance

Page 13: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

13

Supply Chain Opportunities....continued

Support and Consultancy

• Design – conceptual and detailed

• Site surveys

• Performance assessment

• Environmental assessment & monitoring

• Servicing & maintenance

Page 14: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

14

• SPR has developed strong working relationships with key stakeholders in

developing this project:

• Scottish Enterprise (SE)

• Highlands & Islands Enterprise (HIE)

• Scottish Development International

• Argyll & Bute Council

• Islay Energy Trust

• SPR and OEMs meet with both SE and HIE to discuss potential supply

chain opportunities the project could foster;

• Support of economic development partners is pivotal in identifying and

promoting involvement of local suppliers and infrastructure;

• Crucially, economic development partners are also working directly with

the supply chain to ensure potential firms have the infrastructure and

capabilities to offer services to future marine projects.

Capturing the Opportunities

Page 15: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

15

Involvement of local businesses

maximised:

Spend to date ~ £450k

Partnership with Islay Energy Trust

- Full time project officer on Islay

Local promotion of:

• Employment

• Skills

• Fisheries liaison

• Education

• Supply Chain

• Infrastructure

• Tourism

• Social Investment

Local Collaboration - Islay

Fiona MacGillivrayOrnithology

Susan CampbellArchaeology

Colin Campbell, Marine SurveysIslay Energy Trust

Direct local benefits valued at up to £0.75m

Page 16: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management
Page 17: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 17 David Ainsworth E HO TP BD&SD

ns AG 20XX All rights reserved. Answers for energy.

Anglesey Skerries Tidal Stream ArrayRenewable UK, NEC 6th November 2013

David Ainsworth, Business Development Director

Page 18: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 18 David Ainsworth E HO TP BD&SD

Project background

• 2006 identified flagship tidal current sites in Welsh

waters

Site selection

Key Milestones

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

EIA Scoping Physical &

env surveys

AFL

secured

Offshore EIA

completed

Marine licence

application submitted

SEI

submitted

Marine

Licence &

S36 awarded

Cable route

variation &

onshore planning

submitted

Pre-installation

env monitoring

started

Commissioned

Project history

All contracts

plavced

Page 19: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 19 David Ainsworth E HO TP BD&SD

Anglesey Skerries, Wales

Page 20: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 20 David Ainsworth E HO TP BD&SD

Leasing & Licensing

• Commercial Demonstration Type 3A

• Tenant - Sea Generation (Wales) Ltd

• Maximum capacity 10MW

Overview

• 2011 – AfL signed

• 2013 Feb - Marine License – WG, Marine Consents Unit

(MCU) (now NRW)

• 2013 March - Section 36 Electricity Act - DECC, MMO

• 2013 October - Town & Country planning – Isle of

Anglesey County Council (IACC)

Status

Page 21: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 21 David Ainsworth E HO TP BD&SD

Physical surveys

• Desk-top geotech completed in 2008

Geotech desk top

• Q2 2013 - Geotech Site Investigation

Geophys site investigation

• 2008 - Geophys completed

• 2013 - Additional geophys for L3 cable route

Geophys

Page 22: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 22 David Ainsworth E HO TP BD&SD

Cable routing

Original 2010 Concept Revised 2012

Page 23: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 23 David Ainsworth E HO TP BD&SD

Turbine

Sea Generation

(Wales) Ltd

Installation

BOP

Other

services

Construction

Manager

Other contractors & suppliers

Employer

Legend

Marine Current Turbines Ltd (MCT)

Proposed contractual set-up for Skerries – Sea Generation Wales

Others

Turbine

Services

Construction phase Operation phase

Page 24: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 24 David Ainsworth E HO TP BD&SD

SPC Contractual Set Up.

Abbreviations:

DNO = Distribution Network Operator

PPA = Power Purchase Agreement

MMO = Marine Management Organization

MCU = Marine Consents Unit of the Welsh Government

TCE = The Crown Estate

DECC = Department of Energy and Climate Change

BOP = Balance of Plant

Grid AccessContract

GrantAgreement

ConstructionManagementContract

O&MContract

MCT, Installation, Switchgear etc

Consents (Marine, Sect. 36, EPS…)

Land Lease Agreements

Installation, Turbine etc.

InsurancePolicy

Operator

Consultants

Procurement

Contracts

TCE / T&C /

Land Owner

PPAInvestors

Insurance

Company

MMO / MCU

DNO

DECCConstruction

Management

SPC

SeaGeneration

(Wales) Ltd

ShareholderAgreement

Services

Supplier

Turbine Services

Agreement

BOP Service

Supplier

BOP Services Agreement

Sea Generation (Wales) Ltd Activity

Page 24

Page 25: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 25 David Ainsworth E HO TP BD&SD

MCT Locations in Bristol

2012 –

Bristol & Bath

Science Park

Team currently 55+

Will grow to 70+

2013

St Philips

Assembly & Test Facility

25,000 square feet

Up to 25 jobs for initial production

Page 26: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 26 David Ainsworth E HO TP BD&SD

Quayside Assembly

Frequency

Converter

GearboxGenerator

Switchgear

Transformer

Contol System

Hydraulic Power

Pack

Pitch Actuators

Pitch System

Control

Hub Casting

Pitch BearingsCrossbeam

Foundation

Tower

Blades

Crane

MCT - Manufacture/Assembly Strategy for the turbine - Turbine

Page 27: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

2013-11-06

Restricted © Siemens AG 2013 All rights reserved.

Page 27 David Ainsworth E HO TP BD&SD

David Ainsworth

Business Development Director

E HO TP BD&SD

Marine Current Turbines Ltd

Bristol & Bath Science Park,

1st floor, Dirac Crescent,

Bristol, UK BS16 7FR

siemens.com/energy

Page 28: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management
Page 29: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Lewis Wave Power – delivering local benefitsMarc Murray, Aquamarine Power

Page 30: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Aquamarine Power – our goal is to create a

product called Oyster which produces

electricity from ocean wave energy…..

30

Page 31: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

…and sell the technology world wide

31

Page 32: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

The Lewis Wave Power Project

Page 33: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

The Project Site

Page 34: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Simple, Survivable, Shore based technology

Page 35: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

35

Onshore Site

• An onshore facility comprising hydroelectric

power equipment and a site office within a

compound of approximately 10,000m2

• Temporary construction area located

adjacent to the onshore hydroelectric facility

• Permanent access route from the A857

• Access track to the shoreline.

• Onshore pipelines will be laid out in

trenches or on the surface

Page 36: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

36

Offshore Site

• A 40MW wave energy array consisting of

between 40 and 50 Oysters attached to the

seabed.

• A spread of boats including a jack up barge,

a dive boat, a tug and a multicat will be

needed for offshore installation of pipelines

and piles.

• The Oysters will be winched into place by

mooring anchors and secured using rock

anchors.

• Pipelines to pump water from the Oysters to

the onshore hydroelectric power station

(these will be directionally drilled or surface

laid)

Page 37: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

37

How to get onto the Aquamarine Power Supply Chain

Key Considerations

• Although an Energy Company, we’re not Oil

and Gas

• This is the first Pre-Commercial array – getting

involved is an investment in a new industry

• We are looking to build relationships not one

off purchases

• Local is important, but it is a competitive

tendering process

Page 38: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

• Willing to work with the industry

• Willing to understand failures as a learning opportunity

• Willing to take some commercial risk

Suppliers

Rogues gallery:

“I don’t know what the problem is but it is definitely not our fault”

“No one else has ever had a problem with our product – it must be the way

you are using it”

“All our other customers are very happy and never complain”

“We’ve never had any failures before”

Page 39: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

• We want you to supply to this industry

• The long term opportunity is huge

• You need to treat this as an investment

• You do not know it all (and neither do we!)

My message to suppliers….

Page 40: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Average Breakdown of a 40MW Project

Engineering services (preparation)

1%

Component manufacturing

27%

Marine services8%

Assembly8%

Plate and steel fabrication

4%Concrete fabrication

1%

Fabrication of electrical

equipment4%

Cabling services and installation

4%

Onshore infrastructure

4%

Offshore infrastructure4%

Civil engineering8%

Control systems

4%

Electrical Services8%

Monitoring services1% Freight Transport

8%

Accommodation and personal support

services4%

Other/support services

4%

Page 41: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Employment Statistics

Aquamarine Power's study showed that their 40MW wave energy project in the

Western Isles could generate:

• 98 to 200 jobs in the Outer Hebrides and wider Highlands and Islands during

the construction phase - generating an estimated £4.49 million to £9 million

gross value added per year;

• 23 to 37 jobs during the 20 year operations and maintenance phase -

generating £1.3 million to £2.1 million per year.

• The calculation includes all direct employees and contractors used by

Aquamarine Power, indirect jobs such as shops, hotels and local services, and

induced jobs created by the increased overall activity in the area.

Page 42: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

What does it take to have a successful project?

Proven Technology

Supportive Government

Finance / Customer

Seabed / Resource

Permit for Plant

Harbours

Vessels

Grid

Community

Fabricators

Suppliers

Page 43: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

What is critical now?

Lewis Wave Farm

Proven Technology

Supportive Government

Finance / Customer

Seabed / Resource

Permit for Plant

Harbours

Vessels

Grid

Community

Fabricators

Suppliers

Page 44: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

What is critical now?

Proven Technology

Grid

Page 45: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Dependent on the Western Isles grid link; but current programme is:

• Component testing - 2014/15

• Oyster 801 (Lewis design) testing in EMEC – 2016

• Lewis Detailed Design – 2015/16

• On the ground works – 2016

• Energisation timescales:

o 3 -10 MW in 2018

o 10 – 20MW in 2020

o 10 - 20MW in 2021

Timescales

Page 46: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

• Scotland is a great place to be in the marine energy

business

• 95% of our supply chain is in Europe

• We have good government / regional and local support

• We have shown we can develop the supply chain

• Investment is our immediate challenge

– EU

– Government

– Supply chain

• This is a real economic opportunity

Conclusions

Page 47: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

What next?

47

To get onto the suppliers list, we require:

• Relevant contact details

• Brief description of the services you provide (capability statement)

• Send it to [email protected]

• Sending it anywhere else will mean it will probably get lost amongst a wider

range of suppliers details.

Page 48: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

48

Page 49: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Aquamarine Power

Elder House

24 Elder Street

Edinburgh

EH1 3DX

Tel: +44 (0) 131 524 1440

Fax: +44 (0) 131 524 1444

www.aquamarinepower.com

49

Contact us

Page 50: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management
Page 51: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Alstom TidalKen Street – Business Development Manager

6 November 2013

Heads down and keep going!

Page 52: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

ALSTOM © 2013. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Three main activities in four Sectors

Equipment & services for power generation

ALSTOM THERMAL POWER

Equipment & services for rail transport

Equipment & services for power transmission

ALSTOM TRANSPORT

ALSTOM GRIDALSTOM RENEWABLE POWER

Page 53: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

ALSTOM © 2013. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

1MW Turbine main features

Yaw for optimised

inflow and reduced

loads

Integrated

power

conversion

system

Pitching blades for

increased

performance and

reduced loads

Geared for low

weight

Remote

Docking

Buoyant Nacelle

to reduce O&M

costs

Page 54: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

ALSTOM © 2013. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

The story so far

Tripod drilling 2006

500kW

Concept2011

100MWh

Harbour deployment testing 2008 - 2009

2012

250MWh

Testing

Complete

1MW TurbineGrid connected Jan

2013

100MWh

October 2013

Aim to complete

testing 2014

06:00 09:00 12:00 15:00 18:00 21:00 00:00 03:00 06:000

100

200

300

400

500

600

D_TShortAveMeasuredPower

Page 55: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

ALSTOM © 2013. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

The immediate Tidal Market

• 65% of tidal resource is deeper than 30m. (Black & Veatch Consulting Ltd.,2005)

• Raz Blanchard, Fromveurand Pentland Firth, Islay is more than 35m depth.

• Need to be seabed mounted

Sound of Islay

Raz Blanchard

Page 56: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

ALSTOM © 2013. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Potential Tidal Market

Global Tidal Hot Spots – 80GW ?

Factory ?

Final

Assembly

O&M

• Factory where volume justifies

investment

• Final Assembly and O&M base close

to sites

Page 57: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

ALSTOM © 2013. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

O&M base creates local high skilled jobs

Farm

Turbines

Utility

Vessels

Retrieval Time

Deployment Time

Dockside

Local Dockside

Workshop

Minor

Unplanned

Events

Planned &

Unplanned

Primary

Removals/year

Minor Planned &

Unplanned

Events

Major

Planned & Unplanned

Events

Minor maintenance hours

Minor maintenance period

Per arising

Maintenance labour cost/hr

Minor maintenance hours

Minor maintenance period

Per arising

Maintenance labour cost/hr

Major maintenance hours

Major maintenance period

Per arising

Maintenance labour cost/hr

Turbine

StandsTurbine

Bays (2yr overhaul location)

Turbine O&M

Facility

Turbine

Bays (10yr overhaul

location)

Turbine

Transport

Distance

& Time

SPMT

Lorry

57

Page 58: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

ALSTOM © 2013. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

• Politics

• Cost of Energy

• Financial challenges

• UK content

• EMR

− strike price− ring fence marine

• Binding targets for 2030

− CO2 reduction of 40% (compared to 1990)

− 35% RE electricity (national targets) presently ends 2020

• Confidence

Factors to consider

Page 59: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

ALSTOM © 2013. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Head down and carry on!

Page 60: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

www.alstom.com

Page 61: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management
Page 62: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Building the Supply ChainAndrew ScottBusiness & Project

Development Manager

Page 63: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Pelamis – background

• Market leading offshore wave technology

• Over 15 years, has been long & tough road

• £85m funding including £23m revenues

• Meandering course due to short term investor

goals… straightening out track now!

• Total of 6 full scale grid connected machines

• P2 machines 9000+hours, operational

procedures demonstrated.

• ETI and utility funded project on CoE

reduction has led to ‘P2e’ machine spec.

• Current pipeline of 170MW of projects,

including demo site with grid connection.

• Supply chain evolved organically & stepwise.

• ‘Big names' now engaged through P2 – we

now have a solid base for initial pre-

commercial machines.

Page 64: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Pelamis – current supply chain

• PWP set up like “micro-OEM”.

• Design / verification / certification /

qualification / procurement /assembly /

commission / deployment / O&M in-house.

• Critical components co-developed with single

(or double) source suppliers.

• Balance of components outsourced mainly on

competitive basis.

• Strong relationships with suppliers, but no

formal exclusive partnerships [as yet].

Page 65: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

What do we need from the supply chain?

• Capability – new challenges need new solutions

or careful adaptation of existing systems.

• Collaboration – we need them to work with us to

deliver and ‘own the solutions’.

• Competitive/comparative advantages – so

we/they can retain the long-term benefits.

• Capacity – we need to work now with players

who can supply and stand behind commercial

volumes in due course.

• Cost reduction – 100% bought into principle that

to be successful we need to drive cost out

… and above all else …

• Commitment – this will be a long road to a fully

commercial sector, we need suppliers with staying

power and commitment.

65

Page 66: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Moving to volume scenarios

Page 67: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

Thank you!

Page 68: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management
Page 69: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2013 69

RenewableUK

6 November 2013

Dr Michael Ottaviano

Chief Executive Officer &Managing Director

Page 70: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2012 70

Carnegie Snapshot

• Owner and developer of “CETO” wave energy technology

• 26 engineering, commercial, administration staff

• ASX listed, based in Fremantle, Western Australia

• 100+ Patents or patents pending globally

• $70m spent to date on CETO

• EDF EN is a CETO licensee

• Current financials

o $11.7m cash (as at 30/9/2013)

o $15.5m undrawn grants (as at 30/9/2013)

1 year shareprice snapshot

Page 71: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2013 71

CETO Technology

• Fully submerged, point absorber

• Near-shore location or deepwater location

• Onshore or offshore power & water production

• Modular design largely using proven subsea components

Page 72: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2013 72

CETO 1 prototype

• Proof of Concept

• Fremantle

CETO 3 prototype

• 80kW unit

• Garden Island

CETO 2 prototype

• 3 x 1kW units pilot

• Fremantle

Concept Development

• Scale models and

wave tank testing.

<2004 2011- 20142004-2006 2006-2008 2010-20132009-2011

Technology Development Road Map

CETO 4 (independent test)

• 150kW unit.

• EDF on Reunion Island

Independent testing

• Wave tank test

• EDF & DCNS unit

CETO 5 (Plant demonstration)

• 240kW units, grid connected array project.

• Power & water production

• Garden Island, WA

2014-2016

CETO 6

• Design & location

tbd

Page 73: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2013 73

• World first multiple wave unit array

• 3 x 240kW CETO 5 units

• 100NB, 3000psi flexible pipeline 3.2km ashore

• Onshore power plant and grid connection

• Onshore reverse osmosis desalination pilot plant

• Design, approvals, off-take, funding complete

Perth Wave Energy Project

Page 74: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2013 74

Perth Wave Energy Project – Support

• $13.1m Australian Government grant funding for power generation

• $7.3m Western Australian State Government funding

• $1.25m Australian Government grant funding for desalinated water production

• Cooperation agreement with the WA Government water utility, Water Corporation

• Offtake with the Australian Department of Defence (HMAS Stirling)

Page 75: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2013 75

• Component manufacturing underway

• Onshore construction activities commenced

• First offshore activities is installation of foundations

in Q4, 2013

• Commissioning mid-2014

Perth Wave Energy Project – Status

Page 76: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2013 76

CETO 6 – Next Generation Design

• At least 2 x rated capacity versus CETO 5

• Locations: either EU/UK, Australia or Island nation

• Onshore or offshore power generation options,

subject to site characterisation.

• Design, location and funding to be finalised during

2014

• Collaboration partners to be finalised during 2014

• Commissioning in 2016

Page 77: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management

© Copyright Carnegie Wave Energy Limited 2013 77

Upcoming Milestones

• 2011/12:

Single unit test (CETO 3) at project site

$22m in Government grants secured

Power offtake with Dept of Defence

• 2013:

Detailed Design of Perth power project

Environmental & planning approvals

Start procurement & construction of Perth project

• 2014:

• Power and water production from Perth project

• Finalise CETO 6 project design and funding

• 2015/16:

• Construct & commission CETO 6 project

Page 78: C9: Wave & Tidal Business Forum · C9: Wave & Tidal Business Forum. Lynne Bryceland Innovation Development Officer, ScottishPower Renewables. ... MMO / MCU DNO DECC Construction Management