Canterbury Primary Response Earthquakes Sept/Feb/June. Dr Phil Schroeder Primary Care Coordinator Canterbury Primary Response Group Kelly Robertson Nurse Leader Canterbury Primary Response Group. Pre-historic Lessons. Managing It. Emergency Planning: Whole of Health Response. - PowerPoint PPT Presentation
Popular Tags:
77
Canterbury Primary Response Earthquakes Sept/Feb/June Dr Phil Schroeder Primary Care Coordinator Canterbury Primary Response Group Kelly Robertson Nurse Leader Canterbury Primary Response Group
Transcript
Page 1: Canterbury Primary Response Earthquakes Sept/Feb/June

Canterbury Primary ResponseEarthquakes Sept/Feb/June

Dr Phil SchroederPrimary Care Coordinator

Canterbury Primary Response Group

Kelly RobertsonNurse Leader

Canterbury Primary Response Group

Page 2: Canterbury Primary Response Earthquakes Sept/Feb/June

Pre-historic Lessons

Page 3: Canterbury Primary Response Earthquakes Sept/Feb/June

Managing It

Page 4: Canterbury Primary Response Earthquakes Sept/Feb/June

Emergency Planning: Whole of Health Response

CDHB Operations Team

Primary Care: Canterbury

Primary Response Group

Community and Public Health Secondary Care St John

Page 5: Canterbury Primary Response Earthquakes Sept/Feb/June

Canterbury Primary Response Group

Agencies and Funders

• Ministry of Health• Canterbury District Health Board• Hospital & Secondary Care • Community and Public Health • St John• City Council & Civil Defence• Aid Agencies e.g. Red Cross• Mental Health NGOs• Private Hospitals • Hotels• Media & Communications

Primary

• Primary Health Organisations• General Practice• 24HS & After Hours Clinics• Pharmacy• District Nursing + Home Care • Plunket• Maori Community Health• Allied Health Workers• Rest Homes• Radiology & Laboratories

Page 6: Canterbury Primary Response Earthquakes Sept/Feb/June

Canterbury: the safest of havens.

Page 7: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 8: Canterbury Primary Response Earthquakes Sept/Feb/June

Canterbury and NZ 2010 and NZ 2009

Rates Of Inf luenza-like Illness In Canterbury And New Zealand to 30 September 2010

0

50

100

150

200

250

300

7/01

/201

0

7/02

/201

0

7/03

/201

0

7/04

/201

0

7/05

/201

0

7/06

/201

0

7/07

/201

0

7/08

/201

0

7/09

/201

0

7/10

/201

0

7/11

/201

0

7/12

/201

0

Rat

e pe

r 100

,000

pra

ctic

e po

pula

tion Canterbury

NZ 2009NZ 2010

high

moderate to low

Page 9: Canterbury Primary Response Earthquakes Sept/Feb/June

September 4th 2010: Magnitude 7.1

• Mass casualties/injuries but no fatalities.

• Building damage Selwyn, Kaiapoi, ChCh and CBD.

• Liquefaction Kaiapoi and ChCh.

• Power out for up to one week.

• Water, Sewage out for several days – months.

Page 10: Canterbury Primary Response Earthquakes Sept/Feb/June

Hope for the Best

Plan for the Worst

Lessons September 4th 2010 “7.1” Selwyn Quake

LUCKY?

Page 11: Canterbury Primary Response Earthquakes Sept/Feb/June

Emergency Planning

Risk Reductio

n

Readiness

Response

Recovery Relationships

Page 12: Canterbury Primary Response Earthquakes Sept/Feb/June

Emergency Planning: Mandate Given 17th February

Health Emergency

Influenza Pandemic

Infectious Outbreak eg. SARS

Non Health Emergency Earthquake Flood or

TsunamiRugby

World Cup

Health Non-Emergency

Measles Outbreak

Noro-virus Community

Outbreak

Page 13: Canterbury Primary Response Earthquakes Sept/Feb/June

12:51 22ND FEBRUARY 2011

Page 14: Canterbury Primary Response Earthquakes Sept/Feb/June

February 22nd 2011: Magnitude 6.3

• Vertical acceleration quake among highest ever recorded.

• Mass casualties with 181 fatalities.

• Building damage ChCh and in particular CBD with monumental collapse.

• Liquefaction ChCh.

• Power out for up to two months plus.

• Water, Sewage out for months.

Page 15: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 16: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 17: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 18: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 19: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 20: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 21: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 22: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 23: Canterbury Primary Response Earthquakes Sept/Feb/June

Pegasus Health 24Hr Surgery– Staff safety– Patient safety– Building safety– Continuity of services

The Response Phase - Immediate

Page 24: Canterbury Primary Response Earthquakes Sept/Feb/June

General Practice– Staff safety– Patient safety– Building safety– Continuity/cessation

of services

The Response Phase - Immediate cont:

Page 25: Canterbury Primary Response Earthquakes Sept/Feb/June

Incident Centre coordination

Assessment of GPs and Pharmacy’s ability to provide service

Support for affected services

Staff and practice welfare

The Coordinated Primary Care Response

Page 26: Canterbury Primary Response Earthquakes Sept/Feb/June

Response StatusLevel 1 Level 2 Level 3

Score = 4 Score = 2 Score = 0

Building (the building they are working from (rather than their normal place of business

Moderate structural damage to premises, e.g. yellow sticker, co-located with another business or significantly comprised workflow

Minor structural damage to premise that have some impact of workflow

No structural damage – may have cosmetic damage that does not materially impact on business delivery

Services (water, sewer, power, telephone or fax)

One or more services not available for more than 1 business day in the last week

One or more service not available for any part of a business day in the last week

All services available with no interruption to any services in the last week

Staff (both in their employed roles and personal situation

One of more members of the business team significantly impacted by quake (physical injury, loss of family member or friend, displaced form home, significant financial hardship). Staff redundancies likely or made

One of more members of the business team are coping with moderate impact by the quake (significant damage to home, partner redundancy, difficulty maintaining staffing levels, etc)

Members of the business team have been impacted in a limited way by the quake

Income (rest home closure, medical practice relocated, retail sales, reduce consult/script numbers (depopulation)

One or more income streams significantly impacted by the quake (e.g. greater than 20% reduction in income)

One or more income streams moderately impacted by the quake (e.g. 5% to 19% reduction in income)

Income streams impacted in a limited way by the quake (less than 5%)

Practice and Pharmacy Status Definition

Page 27: Canterbury Primary Response Earthquakes Sept/Feb/June

Total score across the 4 categories:

Status Score

Green 0 - 1

Amber 2 - 9

Red 10 or more

Practice and Pharmacy Status

Page 28: Canterbury Primary Response Earthquakes Sept/Feb/June

Affect on Staff– Personally affected but

continued to work– Affected services

struggling with limited resources

• The clean up• Lack of essential services• Safety of vaccines

Providing Care

Page 29: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 30: Canterbury Primary Response Earthquakes Sept/Feb/June

– Decreased ability to perform at peak – “earthquake brain”

– Increased risk of misdiagnosis– Coping with own stress with aftershocks in the

work environment – Loss of business due to patients relocating

Providing Care cont…

Page 31: Canterbury Primary Response Earthquakes Sept/Feb/June

Affect on Patients– Access to service– Less people presenting but longer consultations

required– Health not priority due to disruption of homes and

livelihood– Relocating – loss of continuity of care

Providing Care cont…

Page 32: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 33: Canterbury Primary Response Earthquakes Sept/Feb/June

Ongoing………..– Funding options to support patient care– HR support/Pastoral care– Counseling support for staff– Regular communication to General Practice and

Pharmacies– Buddy system– Locum relief

Staff Support

Page 34: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 35: Canterbury Primary Response Earthquakes Sept/Feb/June

• Co-location

• Relocation

• Insurance Limitations

Issues for Pharmacy - Business Continuity

Page 36: Canterbury Primary Response Earthquakes Sept/Feb/June

Issues for Pharmacy - Business Continuity

Page 37: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 38: Canterbury Primary Response Earthquakes Sept/Feb/June

Wk 1 Wk 2 Wk 30

10

20

30

40

50

60

70

80

90

100

Pharmacies Scripts % comparison 3 weeks post-Quake Green Zone Status

Green 1Green 2Green 3Green 4Green 5Green 6

Issues for Pharmacy - Business Continuity

Page 39: Canterbury Primary Response Earthquakes Sept/Feb/June

Wk 1 Wk 2 Wk 30

10

20

30

40

50

60

70

80

90

100

Pharmacies Scripts % comparison 3 weeks post-Quake Rural

Rural 1Rural 2Rural 3Rural 4Rural 5Rural 6Rural 7

Issues for Pharmacy - Business Continuity

Page 40: Canterbury Primary Response Earthquakes Sept/Feb/June

Wk 1 Wk 2 Wk 3-100

-80

-60

-40

-20

0

20

Pharmacies Scripts % comparison 3 weeks post-Quake Red Zone Status

Red 1Red 2Red 3Red 4Red 5Red 6

Issues for Pharmacy - Business Continuity

Page 41: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 42: Canterbury Primary Response Earthquakes Sept/Feb/June

Critical Issues February 2011

General Practice

Comms Building

Pharmacy Comms Building

Day One

District Nursing Building

Primary Coord

Comms Building

Power Computers

Power Stock

Day Three

Cordon Access

Comms Building

Portaloos

Portaloos Stock

Day Six

Cordon Access

Comms

Page 43: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 44: Canterbury Primary Response Earthquakes Sept/Feb/June

Critical Issues February 2011

General Practice

Comms Building

Pharmacy Comms Building

Day One

District Nursing Building

Primary Coord

Comms Building

Power Computers

Power Stock

Day Three

Cordon Access

Comms Building

Portaloos

Portaloos Stock

Day Six

Cordon Access

Comms

Portaloos

Portaloos

Day Ten

Fuel Staffing

Roles

Page 45: Canterbury Primary Response Earthquakes Sept/Feb/June

Critical Issues February 2011

Rural CanterburyDay Three

Situation: Survey 100%

Open.

Problems: 1) Rising numbers displaced

patients and consult rates.

2) Fuel needing

farming coop.3) Resupply medication and courier

issues.

Rural Canterbury

Day OneSituation:

Some Minor Building

Damage. NO Loss Power,

Water, Sewage

Action: Practice

Survey 100% Rural

Practices Open.

Rural Canterbury

Day Six

Situation: Survey 100%

Open.

Problems: 1) Huge

numbers displaced

patients and unprecedented consult rates.

Rural Canterbury

Day Ten

Situation: Survey 100%

Open.

Problems: 1) Ongoing

huge numbers displaced

patients and ongoing high consult rates.

Page 46: Canterbury Primary Response Earthquakes Sept/Feb/June

Earthquake Response February 2011

General Practice 33%

Pharmacy 21%

Day One

79%

80%

Day Three

85%

83%

Day Six

96%

94%

Day Ten

Page 47: Canterbury Primary Response Earthquakes Sept/Feb/June

Earthquake Response February 2011

Red Practices:

Major Issues

Amber Practices:

Serious Issues

Green Practices:Minor or no issues

7%

34%

59%

Day 15:

103 Open = 96%

1 Relocating

2 Closed

Page 48: Canterbury Primary Response Earthquakes Sept/Feb/June

Earthquake Response February 2011

3%

31%

66%

Week 8:

105 Open = 99%

8 Relocated

1 Closed

7%

34%

59%

Day 15 Week 8

Page 49: Canterbury Primary Response Earthquakes Sept/Feb/June

Earthquake Response February 2011

17%

34%

49%

Week 83%

31%

66%

General Practice Pharmacy

Page 50: Canterbury Primary Response Earthquakes Sept/Feb/June

Canterbury Quakes: Sept, Feb, June

Page 51: Canterbury Primary Response Earthquakes Sept/Feb/June

June 13th 2011: Magnitude 5.7 & 6.3

• Some casualties but no fatalities.

• Building damage ChCh & CBD again.

• Liquefaction ChCh.

• Power out for one week plus.

• Water, Sewage out again.

Page 52: Canterbury Primary Response Earthquakes Sept/Feb/June

The Gap

Page 53: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 54: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 55: Canterbury Primary Response Earthquakes Sept/Feb/June

What Lessons Are We Learning?

Page 56: Canterbury Primary Response Earthquakes Sept/Feb/June

Lesson One:Overall Coordination

Page 57: Canterbury Primary Response Earthquakes Sept/Feb/June

Emergency Response

• CIMS – Coordinated Incident Management System

• EOC – Emergency Operations Centre

Page 58: Canterbury Primary Response Earthquakes Sept/Feb/June

Emergency Planning: Whole of Health Response

CDHB Operations Team

Primary Care:

Canterbury Primary

Response Group

Community and Public

HealthSecondary

Care St John

Page 59: Canterbury Primary Response Earthquakes Sept/Feb/June

Primary Emergency Operations Centre (EOC)

Primary Care Coordinator(s)

CommunicationsPrimary Care Reps :Rural Health Pharmacy

District Nursing EOC Manager

Logistics IntelligenceSector Coordinators Support Human

Resources Finance

Page 60: Canterbury Primary Response Earthquakes Sept/Feb/June

Lesson Two:Emergency Timelines

Page 61: Canterbury Primary Response Earthquakes Sept/Feb/June

Earthquake Response February 2011Preparing for Further Emergency

First 24 Hours• Institute local response• Contact EOC and provide status

Week One• Centralize Response and deploy resources to greatest

need• Survey Practices/Pharmacies to provide logistic support

Week Two Plus• Recognize areas most needing ongoing intensive input• Design ongoing work-streams or projects

Month Three Plus• Recovery mode: business viability, service viability.

Page 62: Canterbury Primary Response Earthquakes Sept/Feb/June

Earthquake Response February 2011

General Practice & Pharmacy

Eastern Suburbs Project

Gastroenteritis Project

Vaccination Project

Practice and Pharmacy

Relocation Project

Practice and Pharmacy Viability

Project

Practice and Pharmacy

Development Project

Human Resource Project

Future PlanningMental Health and

Psycho-social ResponsePreparing for

Further Emergency

Page 63: Canterbury Primary Response Earthquakes Sept/Feb/June

Emergency Planning

Response

RecoveryReadiness

Page 64: Canterbury Primary Response Earthquakes Sept/Feb/June

Lesson Three:Local Cooperation

Page 65: Canterbury Primary Response Earthquakes Sept/Feb/June

Notes:

City Ward Boundaries(Also used by CDEM)

An Example. . . . . .

Page 66: Canterbury Primary Response Earthquakes Sept/Feb/June

City Ward

Sectors, Legs and Coordinators

Primary EOC

Page 67: Canterbury Primary Response Earthquakes Sept/Feb/June

LEGLEG

LEG

LEG

LEG

City Ward

LEG

Sector Coordinator

Primary EOC

Page 68: Canterbury Primary Response Earthquakes Sept/Feb/June

Emergency Planning: Whole of Health Response

Rural Canterbury: 5

Districts

Hospitals & Secondary

Care

Page 69: Canterbury Primary Response Earthquakes Sept/Feb/June

Lesson Four:Business Continuity

Page 70: Canterbury Primary Response Earthquakes Sept/Feb/June

Business Continuity

Emergency Planning

Page 71: Canterbury Primary Response Earthquakes Sept/Feb/June

May 2011 Survey Findings

1) Appreciation for DHB supported free consults and prescriptions.

2) Keen for up to date information and consistent communications.

3) Frustration in achieving and maintaining power, water, sewage services and sense of DHB stockpile required eg. Generators.

4) Remarkable ability to continue to provide care when under duress.

5) Universally felt that everyone would like to be better prepared.

Page 72: Canterbury Primary Response Earthquakes Sept/Feb/June

Business Continuity Continuity of Care

Emergency Planning

Page 73: Canterbury Primary Response Earthquakes Sept/Feb/June

Lesson Summary:The Circle of Life and

Emergencies

Page 74: Canterbury Primary Response Earthquakes Sept/Feb/June

Emergency Planning: Whole of Health Response

(1) Overall

Response

(2) Timeline Progression

(3) Local Response

(4) Business

Continuity

(5) Continuity

of Care

Page 75: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 76: Canterbury Primary Response Earthquakes Sept/Feb/June
Page 77: Canterbury Primary Response Earthquakes Sept/Feb/June

Summary: Whole of Health Response

Canterbury Primary Response Website:www.primaryhealthresponse.org.nz

Logon: Primary Password: Response

Contact Email: [email protected]


Recommended