Capacity Market DSR Testing Process June 2017 Electricity Market Reform DELIVERY BODY
Transcript

Capacity Market

DSR Testing Process

June 2017

Electricity Market Reform

DELIVERY BODY

Legal Disclaimer and Copyright

Disclaimer

This guidance document has been prepared by National Grid Electricity Transmission plc (NGET) and is provided voluntarily

and without charge. Whilst NGET has taken all reasonable care in preparing this document, no representation or warranty

either expressed or implied is made as to the accuracy or completeness of the information that it contains and parties using

information within the document should make their own enquiries as to its accuracy and suitability for the purpose for which

they use it. Neither NGET nor any other companies in the National Grid plc group, nor any directors or employees of any

such company shall be liable for any error or misstatement or opinion on which the recipient of this document relies or seeks

to rely other than fraudulent misstatement or fraudulent misrepresentation and does not accept any responsibility for any use

which is made of the information or the document or (to the extent permitted by law) for any damages or losses incurred.

In the event of any conflict or inconsistency between this document and the Capacity Market Rules, the Electricity Capacity

Regulations or the Auction Guidelines, the latter documents take precedence. Capitalised terms used in this document shall

have the same meanings given in the Capacity Market Rules.

Confidentiality

This guidance document, and its contents should be considered as confidential in nature, and document is supplied on this

basis. No part of this document may be reproduced in in any material form (including photocopying and restoring in any

medium or electronic means and whether or not transiently or incidentally) without the written permission of National Grid.

Copyright National Grid 2017, all rights reserved.

Electricity Market Reform

DELIVERY BODY

The icons below can be selected to access relevant sections of this guidance document: If you have any questions on any of the information contained in this guidance document, please contact the EMR team at [email protected].

DSR Tests: Contents

Electricity Market Reform

DELIVERY BODY

DSR Test example 1: Demand turn down

On average, over the 6 week baseline period, CMU

demand is 10MW. During the test, the CMU turns down

demand to 5MW. The DSR Test proves 5MW of DSR

capacity.

10MW average demand

compared to 5MW DSR Test demand proves 5MW

DSR capacity

What is a DSR Test? A DSR Test is taken by DSR providers to prove that a CMU can achieve its stated capacity. The date and Settlement Period of the DSR Test is chosen by the Capacity Provider. The demand / generation during the test period is compared to the average demand / generation of the CMU over a DSR baseline period to reach the DSR test result, as demonstrated in the two examples below:

1. What is a DSR Test?

Menu Electricity Market Reform

DELIVERY BODY

DSR Test example 2: DSR with onsite generation

On average, over the 6 week baseline period, CMU

demand is 5MW. During the test, the CMU uses on site

generation to export 5MW to the Grid. The DSR Test

proves 10MW of DSR capacity.

Average demand

over DSR baseline period1

-10 MW

Demand

during DSR Test period1

DSR Test result1

-5 MW

5 MW

Average demand

over DSR baseline period2

-5 MW

Generation

during DSR Test period2

DSR Test result2

+5 MW

10 MW 5MW average demand

compared to 5MW onsite generation proves 10MW

DSR capacity

0

0

2. The DSR Baseline Methodology

16 data points are used in calculating the DSR baseline: The first 6 data points are the same settlement period on the same day of the week as the test date for the last 6 weeks. The remaining 10 data points depend on whether the DSR Test takes place on a working, or non-working day. If the DSR Test takes place on a working day, the relevant data points are the last 10 working days. If the DSR Test takes place on a non-working day, the relevant data points are the last 10 non-working days, as shown in the examples below: N.B. Settlement periods where a Capacity Market Warning is in force are ignored.

Menu Electricity Market Reform

DELIVERY BODY

Eg 1: Working Day Tuesday 20th June 7am – 7.30am

1. 13th June 7am – 7.30am

2. 6th June 7am – 7.30am

3. 30th May 7am – 7.30am

4. 23rd May 7am – 7.30am

5. 16th May 7am – 7.30am

6. 9th May 7am – 7.30am

7. 19th June 7am – 7.30am

8. 16th June 7am – 7.30am

9. 15th June 7am – 7.30am

10. 14th June 7am – 7.30am

11. 13th June 7am – 7.30am

12. 12th June 7am – 7.30am

13. 9th June 7am – 7.30am

14. 8th June 7am – 7.30am

15. 7th June 7am – 7.30am

16. 6th June 7am – 7.30am

Eg 2: Non-working day Saturday 15th July 2pm – 2.30pm

1. 8th July 2pm – 2.30pm

2. 1st July 2pm – 2.30pm

3. 24th June 2pm – 2.30pm

4. 17th June 2pm – 2.30pm

5. 10th June 2pm – 2.30pm

6. 3rd June 2pm – 2.30pm

7. 9th July 2pm – 2.30pm

8. 8th July 2pm – 2.30pm

9. 2nd July 2pm – 2.30pm

10. 1st July 2pm – 2.30pm

11. 25th June 2pm – 2.30pm

12. 24th June 2pm – 2.30pm

13. 18th June 2pm – 2.30pm

14. 17th June 2pm – 2.30pm

15. 11th June 2pm – 2.30pm

16. 10th June 2pm – 2.30pm

Eg 3: Impact of Bank Holidays Monday 5th June 5.30pm – 6.00pm

1. 29th May Bank Holiday ignored

2. 22nd May 5.30pm – 6.00pm

3. 15th May 5.30pm – 6.00pm

4. 8th May 5.30pm – 6.00pm

5. 1st May Bank Holiday ignored

6. 24th April 5.30pm – 6.00pm

7. 2nd June 5.30pm – 6.00pm

8. 1st June 5.30pm – 6.00pm

9. 31st May 5.30pm – 6.00pm

10. 30th May 5.30pm – 6.00pm

11. 26th May (29th May is a non-work day)

12. 25th May 5.30pm – 6.00pm

13. 24th May 5.30pm – 6.00pm

14. 23rd May 5.30pm – 6.00pm

15. 22nd May 5.30pm – 6.00pm

16. 19th May 5.30pm – 6.00pm

Same day of

the week for the last 6

weeks

Last 10

work ing / non-work ing

days

Menu

3. The DSR Test Process for Unproven DSR CMUs

Electricity Market Reform

DELIVERY BODY

1. Request a DSR Test via the EMR

Delivery Body Portal, following the process steps outlined in this

guidance document. 2 Working days notice must be given.

2. Inform National Grid Control

Room and request metered data from EMR Settlements Body.

4. Send the metered data to Delivery Body within 5 working

days of receiving the request. The ‘clock’ stops if there are any issues with the data, or it has not been submitted by the

Capacity Provider.

5. Perform DSR Test analysis. Inform the

Capacity Provider of the outcome of the DSR Test via a DSR Letter within 5 working days

of receiving the data from EMRS.

7. Upload DSR certificate to

the EMR Portal, or arrange re-test with Capacity

Provider.

6. Confirm result or request new DSR Test

within 2 working days of receiving the DSR Letter. The result of a re-test will hold, even

if lower than the capacity proven in the first test.

3. Provisionally confirm whether DSR Test can take place. Under the Rules, the control room can cancel

DSR Tests at any time up to 4 hours ahead of the DSR Test. Preferred times to avoid: • Saturday and Sunday: 14:00 – 16:00

• Weekdays: 22:00 – 07:00

Electricity Market Reform

DELIVERY BODY

Step 1 – Decide the date and time of the DSR Test. • DSR Tests cannot be scheduled during the Prequalification Assessment Window.

• The DSR Test must take place at least one month prior to the start of the Delivery Year.

• It is advisable that the Metering Assessment and (if required) a Metering Test is completed before the

DSR Test.

Step 2 – Log on to the EMR Portal as Main Admin. • Log in here.

• If you have not yet registered onto the EMR Portal, or experience issues logging in, please contact the

EMR Team at [email protected].

Menu

Step 3 – Click on ‘My EMR’ then ‘My CMUs’. • This takes you to a list of all your CMUs. Find

the relevant CMU by entering the CMU ID into the search box at the bottom of the table.

3. The DSR Test Process for Unproven DSR CMUs

Electricity Market Reform

DELIVERY BODY

Step 4 – Click “EDIT AFTER PQRD DATA” and navigate to the DSR Test tab. Step 5 – Enter the date of the DSR Test into the “Settlement Date” field using the pop-up calendar. • DSR Tests cannot be scheduled during the Prequalification Assessment Window

Step 6 – Enter the Settlement Period of the test into the “Settlement Period” field.

Menu

3. The DSR Test Process for Unproven DSR CMUs

Electricity Market Reform

DELIVERY BODY

• The National Grid control room has advised that preferred times to avoid due to more acute operational difficulties with managing the system are:

• A DSR Test which takes place outside of these hours is less likely to be cancelled by the control room.

Weekdays Weekends

22:00 – 07:00 14:00-16:00

Menu

3. The DSR Test Process for Unproven DSR CMUs

Electricity Market Reform

DELIVERY BODY

Step 7 –“Other Info” • If the components / MPANs of the CMU have changed since Prequalification, please notify us of

the MPANs you would like to test here.

• If the CMU is a clone, please enter the relevant CMU ID(s) here also.

• Entering the location(s) of the CMU components(s) will be helpful for the control room and may increase the chance of the DSR Test being approved.

• Your location will not be shared with the control room without your consent so please state if you are happy for the Delivery Body to share this information with the control room.

• Please contact the EMR Team at [email protected] for more information.

Step 8– Click ‘Submit’.

• Clicking “Save” will not generate a notification to the Delivery Body, please ensure you select Submit.

Step 9 – Automatic system notification is generated. • Main Admin(s) of the relevant company and National Grid Delivery Body will receive notification

that a DSR Test request has been submitted (Reminder: the request must be submitted, not just saved for this notification to be sent.)

Actions taken by the Delivery Body and EMR Settlements Body (EMRS): • The Delivery Body will inform the National Grid control room of the test time and date. The control

room can cancel the test at any time up to 4 hours ahead of the test.

• The Delivery Body will request the relevant metered data from EMRS.

• EMRS provides data to Delivery Body within 5 Working Days. The ‘clock’ stops if there are any issues with the data, or it has not been submitted correctly.

• The Delivery Body will analyse the metered data and provide the Capacity Provider with a DSR Letter within 5 Working Days of receiving the data from EMRS.

Menu

3. The DSR Test Process for Unproven DSR CMUs

Electricity Market Reform

DELIVERY BODY

Electricity Market Reform

DELIVERY BODY

• The Capacity Provider has 2 working days from receiving the DSR Letter to request a re-test.

• Please notify the Delivery Body via telephone or email if you would like to re-test the CMU. The Delivery Body will then reject the active DSR Test request in the system and you will be able to re-submit the request.

• The outcome of a re-test will be conclusive, even if a lower capacity is proven.

• The Delivery Body will issue a DSR Test Certificate within 5 working days of issuing the DSR Letter, unless a re-test is requested.

• The DSR Test Certificate will be uploaded to the portal by the Delivery Body.

Menu

3. The DSR Test Process for Unproven DSR CMUs

Electricity Market Reform

DELIVERY BODY

4. Taking a DSR Test prior to Prequalification

Menu

To apply to the Capacity Market as a Proven DSR CMU: • A DSR Test can be requested via the EMR Portal as per Section 3 of this document.

• DSR Tests can be taken at any time of the year except during the Prequalification Window.

• Following the DSR Test, a DSR Test Certificate is issued to the Applicant. The capacity as shown on

the DSR Test Certificate will be the Proven DSR CMU capacity. • It is advisable that Proven DSR Applicants complete a Metering Assessment and (if required) a

Metering Test before requesting a DSR Test:

• Proven DSR CMUs can defer the Metering Assessment until after Prequalification, but if the CMU subsequently fails a Metering Test, it will no longer be classified as Proven. In this case, a new DSR Test would need to be undertaken.

• See our Metering Assessment guidance document for information, or contact the EMR team at

[email protected] if you would like to discuss taking a DSR Test prior to Prequalification. Prior to Prequalification only, the Capacity Provider or Applicant may provide historic information that identifies three Settlement Periods in which a DSR Baseline can be calculated and the CMU delivered a positive DSR volume. The Proven DSR capacity will be the lowest of the three DSR calculations. • Contact the EMR team at [email protected] for more information on this process.

Electricity Market Reform

DELIVERY BODY

5. Joint DSR Tests

Menu

A Capacity Provider may nominate more than one DSR CMU for a Joint DSR Test: • The CMUs must belong to the same Applicant or Capacity Provider.

• No Joint DSR Test may take place during the Prequalification Assessment Window.

• The deadline for taking a Joint DSR Test is one month before the relevant Delivery Year.

Follow the process steps outlined in Section 3 of this guidance document for each of the CMUs you wish to jointly test: • Ensure that the test date and time are the same in each submission.

• State that you would like to request a Joint Test in the “Other Info” box, and state which CMUs you

would like to jointly test.

Electricity Market Reform

DELIVERY BODY

6. Data used in DSR Test Assessment

The data used to assess CMUs for DSR Tests is the same metered volume data that has been submitted to EMRS by the Capacity Provider: If you have any queries, guidance on metered data can be found in WP195 or you can contact EMRS at [email protected].

Menu

Metering Data Pathway Comment

BMU This pathway should already be set up and be in operation. You are not required to take any further action to provide additional data.

HHDA This pathway should already be set up and be in operation. You are not required to take any further action to provide additional data. If the flows have not been set up, please contact your Supplier to ensure they have instructed their HHDA to report this data to EMRS. Please be mindful that EMRS usually receives this data 5 Working Days after the Settlement Date.

Self - submission Please make sure you have submitted the data for the DSR Test date and sufficient data for the 6 week DSR baseline.