+ All Categories
Home > Documents > Capital Budget2

Capital Budget2

Date post: 04-Apr-2018
Category:
Upload: hilario-ponce-saplada
View: 221 times
Download: 0 times
Share this document with a friend

of 39

Transcript
  • 7/30/2019 Capital Budget2

    1/39

    1

    The Basics of

    Capital Budgeting

  • 7/30/2019 Capital Budget2

    2/39

    2

    Topics Overview

    Methods NPV IRR, MIRR

    Payback, discounted payback

  • 7/30/2019 Capital Budget2

    3/39

    3

    What is capital budgeting?A process for determining the

    profitability of a capital investment.

    Long-term decisions; involve largeexpenditures.

    Very important to firms future.

  • 7/30/2019 Capital Budget2

    4/39

    4

    Steps in Capital Budgeting Estimate cash flows (inflows &

    outflows).

    Assess risk of cash flows.

    Determine r = WACC for project.

    WACC = Weighted Avg. Cost of Capital

    Evaluate cash flows.

  • 7/30/2019 Capital Budget2

    5/39

  • 7/30/2019 Capital Budget2

    6/39

    6

    What does this represent?

    = n

    t = 0

    CFt

    (1 + r)t

  • 7/30/2019 Capital Budget2

    7/39

    7

    NPV: Sum of the PVs of all

    cash flows.

    Cost often is CF0 and is negative.

    NPV =n

    t = 0

    CFt

    (1 + r)t

    NPV =n

    t = 1

    CFt

    (1 + r)t- CF0

  • 7/30/2019 Capital Budget2

    8/39

    8

    Cash Flows for project L and

    project S

    10 8060

    0 1 2 310%

    Ls CFs:

    -100

    70 2050

    0 1 2 3

    10%Ss CFs:

    -100

  • 7/30/2019 Capital Budget2

    9/39

    9

    Whats project Ls NPV?

    10 8060

    0 1 2 310%

    Ls CFs:

    -100

    = NPVL

  • 7/30/2019 Capital Budget2

    10/39

    10

    Whats project Ls NPV?

    10 8060

    0 1 2 310%

    Ls CFs:

    -100

    9.09

    49.59

    60.11

    18.79 = NPVL NPVS = $19.98.

  • 7/30/2019 Capital Budget2

    11/39

    Which project should be chosen?

    11

    What if mutually exclusive? L or S?What if independent projects? L or S?

  • 7/30/2019 Capital Budget2

    12/39

    12

    Calculator Solution: Enter

    values in CF register for L.

    -100

    10

    60

    80

    10

    CF0

    CF1

    NPV

    CF2

    CF3

    I = 18.78 = NPVL

  • 7/30/2019 Capital Budget2

    13/39

    13

    Rationale for the NPV Method NPV = PV inflows Cost

    This is net gain in wealth, so acceptproject if NPV > 0.

    Choose between mutually exclusiveprojects on basis of higher NPV. Addsmost value.

  • 7/30/2019 Capital Budget2

    14/39

    14

    Using NPV method, which project(s)

    should be accepted? If project S and L are mutually

    exclusive, accept S because

    NPVs > NPVL .

    If S & L are independent, accept both;NPV > 0.

  • 7/30/2019 Capital Budget2

    15/39

    15

    Internal Rate of Return: IRR

    0 1 2 3

    CF0 CF1 CF2 CF3Cost Inflows

    IRR is the discount rate that forcesPV inflows = cost. This is the sameas forcing NPV = 0.

  • 7/30/2019 Capital Budget2

    16/39

    16

    NPV: Enter r, solve for NPV.

    IRR: Enter NPV = 0, solve for IRR.

    = NPVn

    t = 0

    CFt

    (1 + r)t

    .

    = 0n

    t = 0

    CFt

    (1 + IRR)t.

  • 7/30/2019 Capital Budget2

    17/39

    17

    Whats project Ls IRR?

    10 8060

    0 1 2 3IRR = ?

    -100

    PV3

    PV2

    PV1

    0 = NPV Enter Cash Flows in CF, thenpress IRR:

  • 7/30/2019 Capital Budget2

    18/39

    18

    Whats project Ls IRR?

    10 8060

    0 1 2 3IRR = ?

    -100

    PV3

    PV2

    PV1

    0 = NPV Enter Cash Flows in CF, thenpress IRR: IRRL = 18.13%.

    IRRS = 23.56%.

  • 7/30/2019 Capital Budget2

    19/39

    19

    40 4040

    0 1 2 3

    -100

    Find IRR if CFs are constant:

  • 7/30/2019 Capital Budget2

    20/39

    20

    40 4040

    0 1 2 3

    -100

    Or, with CF, enter CFs and pressIRR = 9.70%.

    3 -100 40

    9.70%

    N I/YR PV PMT

    INPUTS

    OUTPUT

    Find IRR if CFs are constant:

  • 7/30/2019 Capital Budget2

    21/39

    21

    Decisions on Projects S and Lper IRR

    IRRS = 18% IRRL = 23% WACC = 10%

    If S and L are independent, what to do?

    If S and L are mutually exclusive, whatto do?

  • 7/30/2019 Capital Budget2

    22/39

    22

    Rationale for the IRR Method

    If IRR > WACC, then the projects rateof return is greater than its cost-- some

    return is left over to boost stockholdersreturns.

    Example:WACC = 10%, IRR = 15%.

    So this project adds extra return toshareholders.

  • 7/30/2019 Capital Budget2

    23/39

    23

    Reinvestment RateAssumptions

    NPV assumes reinvest at r (opportunitycost of capital).

    IRR assumes reinvest CFs at IRR.

    Reinvest at opportunity cost, r, is morerealistic, so NPV method is best. NPV

    should be used to choose betweenmutually exclusive projects.

  • 7/30/2019 Capital Budget2

    24/39

    24

    Modified Internal Rate ofReturn (MIRR)

    MIRR is the discount rate which causesthe PV of a projects terminal value (TV)

    to equal the PV of costs. TV is found by compounding (FV)

    inflows at the WACC.

    Thus, MIRR assumes cash inflows arereinvested at the WACC.

  • 7/30/2019 Capital Budget2

    25/39

    25

    10.0 80.060.0

    0 1 2 3

    10%

    66.0

    12.1158.1

    -10010%

    10%

    TV inflows

    -100

    PV outflows

    MIRR for project L: First, findPV and TV (r = 10%)

  • 7/30/2019 Capital Budget2

    26/39

    26

    Second, find discount rate thatequates PV and TV

    MIRR = 16.5% 158.1

    0 1 2 3

    -100

    TV inflowsPV outflows

    MIRRL = 16.5%

    $100 = $158.1(1+MIRRL)

    3

  • 7/30/2019 Capital Budget2

    27/39

    27

    To find TV with calculator:Step 1, find PV of Inflows

    First, enter cash inflows in CF register:

    CF0 = 0, CF1 = 10, CF2 = 60, CF3 = 80

    Second, enter I = 10.

    Third, find PV of inflows: Press NPV = 118.78

  • 7/30/2019 Capital Budget2

    28/39

    28

    Step 2, find TV of inflows.

    Enter PV = -118.78, N = 3, I = 10

    CPT FV = 158.10 = FV of inflows.

  • 7/30/2019 Capital Budget2

    29/39

    29

    Step 3, find PV of outflows.

    For this problem, there is only oneoutflow, CF0 = -100, so the PV of

    outflows is -100.

  • 7/30/2019 Capital Budget2

    30/39

    30

    Step 4, find IRR of TV ofinflows and PV of outflows.

    Enter FV = 158.10, PV = -100, N = 3.

    CPT I = 16.50% = MIRR.

  • 7/30/2019 Capital Budget2

    31/39

    31

    Why use MIRR versus IRR?

    MIRR correctly assumes reinvestment atopportunity cost = WACC. MIRR also

    avoids the problem of multiple IRRs. Managers like rate of return

    comparisons, and MIRR is better for this

    than IRR.

  • 7/30/2019 Capital Budget2

    32/39

    32

    What is the payback period?

    The number of years required torecover a projects cost,

    or how long it takes to get thebusinesss money back.

  • 7/30/2019 Capital Budget2

    33/39

    What is the payback period?

    33

    50 5050

    0 1 2 3

    -100

  • 7/30/2019 Capital Budget2

    34/39

    What is the payback period?

    34

    40 4040

    0 1 2 3

    -100

  • 7/30/2019 Capital Budget2

    35/39

    35

    What are the payback periodsfor projects L and S?

    10 8060

    0 1 2 310%

    Ls CFs:

    -100

    70 2050

    0 1 2 3

    10%Ss CFs:

    -100

  • 7/30/2019 Capital Budget2

    36/39

    36

    Payback for project L

    10 8060

    0 1 2 3

    -100

    =

    CFtCumulative -100 -90 -30 50

    PaybackL 2 + 30/80 = 2.375 years

    0

    2.4

  • 7/30/2019 Capital Budget2

    37/39

    37

    Payback for project S

    70 2050

    0 1 2 3

    -100CFt

    Cumulative -100 -30 20 40

    PaybackS 1 + 30/50 = 1.6 years

    0

    1.6

    =

  • 7/30/2019 Capital Budget2

    38/39

    38

    Strengths and Weaknesses ofPayback

    Strengths:

    Provides an indication of a projects risk

    and liquidity. Easy to calculate and understand.

    Weaknesses:

    Ignores the TVM. Ignores CFs occurring after the payback

    period.

  • 7/30/2019 Capital Budget2

    39/39

    39

    10 8060

    0 1 2 3

    CFt

    Cumulative -100 -90.91 -41.32 18.79Discountedpayback 2 + 41.32/60.11 = 2.7 yrs

    PVCFt -100

    -100

    10%

    9.09 49.59 60.11

    =

    R i i 2 7

    Discounted Payback: Usesdiscounted rather than raw CFs.


Recommended