+ All Categories
Home > Education > Carnaby Street - Temporary Works case study for the commercial sector

Carnaby Street - Temporary Works case study for the commercial sector

Date post: 14-Jun-2015
Category:
Upload: deconstruct-uk
View: 831 times
Download: 1 times
Share this document with a friend
Description:
Deconstruct UK case study
Popular Tags:
5
Deconstruct UK case study for the commercial sector. Client: Shaftsbury PLC Location: Carnaby Street, London, W1 Contractor: Deconstruct UK Ltd Completion Date: December 2010 Sector: Commercial
Transcript
Page 1: Carnaby Street - Temporary Works case study for the commercial sector

Deconstruct UK case study for the commercial sector.

Client: Shaftsbury PLCLocation: Carnaby Street, London, W1

Contractor: Deconstruct UK LtdCompletion Date: December 2010

Sector: Commercial

Page 2: Carnaby Street - Temporary Works case study for the commercial sector

About the Project:

Carnaby Street redevelopment of 1950’s structure to provide new commercial and retail space to prime location.

This project on the busy pedestrianised Carnaby Street in London. This presented numerous logistical issues, not least of all supplying materials to and from site.

The site had suffered bomb damage during WW2 and required extensive underpinning and ‘King Post Walling’ to retain the roadway (Carnaby St).

Demolition works adjoined grade two listed structures with temporary support and therefore, had to be very versatile to accommodate the anomalies of structures from this era.

The works had to be coordinated into the bespoke restrictions working on the Carnaby Estate.

Page 3: Carnaby Street - Temporary Works case study for the commercial sector

Project Challenges:

Major challenges included designing temporary works to avoid permanent structures during early design stages which required fluid dialogue with the design team.

Demolishing structures on a very busy pedestrian street and considering the impactof noise and vibration for adjoining businesseswere key requirements for the client.

Ensuring the substructures were formed precisely for the construction phase of the project were also vitally important. Blenheim House followed us onto site and commented on the level of quality they inherited.

Page 4: Carnaby Street - Temporary Works case study for the commercial sector

Services provided by Deconstruct UK:

Our services:

Deconstruction Services ✓

Demolition Services ✓

Enabling Works ✓

Asbestos Removal Services ✓Asbestos Surveying Services ✓Ground Works Services ✓

Piling Services ✓

Steelwork Installations ✓

Builders Works ✓

Emergency Dangerous Structures

Temporary Works ✓

Page 5: Carnaby Street - Temporary Works case study for the commercial sector

Contact Details:

Deconstruct (UK) LimitedSilver House, 31-35 Beak StreetLondonW1F 9DPTel: 020 7734 6655Fax: 020 7734 6626

Email [email protected] Address www.deconstructuk.com

For more information about this case study, visit our case studies page here: www.deconstructuk.com