    RESIDENTIALINSPECTIONCHECKLISTS

    2009

    Visit the virtual information kiosk VIK at: cityofcarrollton.com/VIK

  • 8/3/2019 Carroll Ton Inspection Check List

    2/40

    Table of Contents

    SUBJECT INSPECTION

    Required Inspections by Permit Type

    Reference of AbbreviationsTemporary Electrical Pole/SWPPP......................................................................................1011

    Pool Electrical Bond ............................................................................................................1012

    Sewer....................................................................................................................................1021

    Water Service.......................................................................................................................1022

    Gas Wrap/Service ................................................................................................................1023

    Lawn Sprinkler.....................................................................................................................1024

    Pool P-Trap..........................................................................................................................1029

    Retaining Wall .....................................................................................................................1041

    Sidewalks and Approach......................................................................................................1056Ham Antenna .......................................................................................................................1072

    Fence....................................................................................................................................1090

    Foundation Only ..................................................................................................................2001

    Plumbing Rough/Energy......................................................................................................2020

    Gas Rough and Test.............................................................................................................3021

    Pre-Brick..............................................................................................................................3042

    Plumbing Top Out/HVAC Rough/Gas Test/Energy............................................................3065

    Electrical Rough/Frame/Building/Energy, Building and Electrical ....................................3066

    Insulation..............................................................................................................................3067

    Roof Final ............................................................................................................................4003

    Utility Release/Plumbing/HVAC/Energy Final...................................................................4005

    Pool Work Final...................................................................................................................4042

    Electrical/Building/Energy Final, Electrical and Building ..................................................4063

    Clean & Show/Construction Heat/Electric Service .............................................................6015

    Clean & Show/Construction Heat/Gas Service ...................................................................6020

    Clean & Show/Construction Heat/Gas & Electric Service..................................................6060

    General Check/Follow-up....................................................................................................7000

    BUILDING INSPECTION

    [email protected]

    1945 E. Jackson Road | Carrollton, Texas 75006 | P.O. Box 110535 | Carrollton, TX 75011-0535

    Phone: 972/466-3225 | Fax: 972/466-3220

  • 8/3/2019 Carroll Ton Inspection Check List

    3/40

    Required Inspections by Permit Type

    ELECTRICAL

    1011 - Temporary Electrical Pole/SWPPP

    3066 - Electrical Rough/Frame/Building/Energy, Building and Electrical

    4063 - Electrical/Building/Energy Final, Electrical and Building

    FENCE1090 Fence

    HAM ANTENNA1072 - Ham Antenna

    LAWN SPRINKLER1024 Lawn Sprinkler

    MECHANICAL

    3065 - Plumbing Top Out/HVAC Rough/Gas Test/Energy

    4005- Utility Release/Plumbing/HVAC/Energy Final

    PLUMBING

    1021 Sewer1022 - Water Service

    1023 - Gas Wrap/Service2020 Plumbing Rough/Energy

    3065 - Plumbing Top Out/HVAC Rough/Gas Test/Energy4005 - Utility Release/Plumbing/HVAC/Energy Final

    POOLS

    1012 Pool Electrical Bond

    1029 - Pool P Trap

    4042 - Pool Work Final

    RETAINING WALL1041 - Retaining Wall

    SINGLE FAMILY DWELLING

    2020 - Plumbing Rough/Energy

    2001 Foundation Only

    3065 - Plumbing Top Out/HVAC Rough/Gas Test/Energy3066 - Electrical Rough/Frame/Building/Energy, Building and Electrical

    3067 - Insulation

    4005 - Utility Release/Plumbing/HVAC/Energy Final

    4063 - Electrical/Building/Energy Final, Electrical and Building

  • 8/3/2019 Carroll Ton Inspection Check List

    4/40

    Reference of Abbreviations

    The following is a reference list of some abbreviations/symbols used in this handbook of

    inspection checklists. Abbreviations are to be read as singular/plural in context with

    material. Any reference to a code or ordinance is to be interpreted as the latest version

    available of that code or ordinance. Periods have been eliminated in abbreviations for ease in

    reading.

    A/C Air Conditioning

    Art Article

    CDO Carrollton Drainage Ordinance

    CFC Carrollton Fire Code

    cfm Cubic Feet per Minute

    Ch Chapter

    COG See Amendments in Ordinance No. 2024

    CSC Carrollton Sign Code

    CZO (Carrollton) Comprehensive Zoning Ordinance

    Dwg Drawing

    GDS General Design Standards

    Mfg Manufacturing

    NCTCOG North Central Texas Council of Governments

    NEC National Electric Code

    Ord Ordinance

    p Page

    pp Pages

    psi Pounds per Square Inch

    Sec Section

    Specs Specifications

    Std Standard

    Subdv Subdivision

    Tbl Table

    IMC International Mechanical Code

    IPC International Plumbing Code

  • 8/3/2019 Carroll Ton Inspection Check List

    5/40

    Temporary Electrical Pole/SWPPP

    1011

    Temporary Electrical Pole/SWPPP Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Panel grounded and bonded 2008 NEC

    250-28

    250-52&53

    Breaker/outlet requirements-sizing for outlets used 2008 NEC 210-19

    Wire sizes and insulation 2008 NEC 310-16

    No open holes / to remain water tight 2008 NEC 314-17

    Unused breaker openings filled 2008 NEC 408.7

    Clearances: 18 above traffic for overhead drop.

    Distance from public property R.O.W2008 NEC 225-18

    Raceway used and installed 2008 NEC230-50

    230-54

    Weather resistant receptacles 115-250 volt 2008 NEC 406.8

    GFCI Protection / in use covers for exposed outlets 2008 NEC 406.8

    Address 2006 IRC 505

    Bracing: 45 degrees to support pole Encore serviceguidelines

    600

    SWPPP Inspection Checklist

    A. Erosion controls are to be in place at the temporary electric pole inspection.B. Erosion control fencing or soil stabilization fabric must be installed in an approved

    manner and maintained throughout the construction project until the UtilityRelease/Plumbing/ HVAC final inspections.

    C. Large piles of dirt are required to be protected with erosion control fencing, NOT soilstabilization fabric.

    D. Erosion control protection should be proactively maintained at least once a week.E. Storm water inlet protectionF. 50 feet rock entryway on commercial projects.

  • 8/3/2019 Carroll Ton Inspection Check List

    6/40

    Pool Electrical Bond1012

    Pool Electrical Bond Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONGrounding with minimum #8 ground wire around deck

    with ground clamps and all metal with 52008 NEC 680-26

    Grounding of copper conduit for pool lights/fixtures 2008 NEC 680-23Position of plugs in relation to pool sides 2008 NEC 680-22Low voltage lighting / transformer ground run to

    equipment ground to panel2008 NEC 680.24

  • 8/3/2019 Carroll Ton Inspection Check List

    7/40

    Sewer Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Pipe materials2006 IRC

    2006 IPCTechnical

    Policy for SDR

    17 Trenchless

    pipe

    P3002

    702

    Pipe sizes 2006 IRC2006 IPC

    P3005

    710

    Grade of pipe 2006 IRC2006 IPC

    P3005

    Table 704.1

    Sewer

    1021

  • 8/3/2019 Carroll Ton Inspection Check List

    8/40

    Water Service Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONPipe materials

    NTCOG Amendment (no polybutylene pipe allowed)2006 IRC

    2006 IPCP2904

    605Pipe sizes 2006 IRC

    2006 IPC P2903604.10Pressure test 2006 IRC

    2006 IPC P2503107, 312

    Water Service

    1022

  • 8/3/2019 Carroll Ton Inspection Check List

    9/40

    Gas Wrap/Service Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Pipe materials2006 IRC

    2006 IFGCG2413

    403Pipe sizes 2006 IRC

    2006 IFGC G2413402Pressure test (gas) NTCOG Amendments 2006 IRC

    2006 IFGC G2417406Connections/Joints 2006 IRC

    2006 IFGC G2414Ch. 4Tracer wire for non-metallic piping 2006 IRC2006 IFGC G2415.14.3404.14.3Pipe depth NTCOG Amendments 2006 IRC

    2006 IFGCG2415.9

    404.9

    Gas risers 2006 IRC2006 IFGC G2414.6.1Ch. 4

    Gas pipes not to be bent or strained 2006 IRC2006 IFGC G2416405

    Separate ditch for gas piping CarrolltonPolicy

    Protection from corrosion 2006 IRC2006 IFGC G2414.8404.8

    Gas Wrap/Service

    1023

  • 8/3/2019 Carroll Ton Inspection Check List

    10/40

    Irrigation Inspection

    1024

    Irrigation Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Check that city approved plans are on site. House bill 1656

    Approved back flow prevention device required with y

    strainer installed before device. Full port ball type isolation

    valve between meter and back flow device. Test cocks on

    B/F device are to be plugged with threaded plugs. Installed

    min. 3 ft. from water service on customer side of property

    line.

    House bill 1656

    Master valve (if required) installed on discharge side of

    B/F device (full port ball type valve).House bill 1656

    Check location of controllers and sensors (rain/freeze);each controller must be labeled with installers name and

    company name, license number, telephone number and

    warranty period.

    House bill 1656

    Check location and water emission devices, valves (zone,

    master, and isolation).House bill 1656

    Check all underground wiring for UL burial rating and

    sizing to manufacturers specifications; all wire splices

    must be moisture proof. All wiring is buried min. 6 inches.

    House bill 1656

    Check PVC piping for sizing, rating, installation and depth

    (min. 6 inches).

    House bill 1656

    and 2006 IPCSection 605

    Pop up water emission devices must be installed a min. 4

    inches from hardscape and direct flow away.House bill 1656

    NOTE: Double check backflow prevention permitted in ground if protected by a box.

  • 8/3/2019 Carroll Ton Inspection Check List

    11/40

    Pool P-Trap Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    P-Trap for pools/spas with air breakCarrollton

    Policy

    1 " minimum backwash/drain pipe CarrolltonPolicy

    Pool P-Trap

    1029

  • 8/3/2019 Carroll Ton Inspection Check List

    12/40

    Retaining Wall Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONRetaining walls which do not require a permit are not

    inspected. If under 4 feet from the bottom of footing tothe top 2006 IRC R105.2Inspect based on engineered approved plans for

    retaining walls requiring permit 2006 IBC 1610.1

    Retaining Wall

    1041

  • 8/3/2019 Carroll Ton Inspection Check List

    13/40

    Sidewalks and Approach Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONSand cushion for leveling only 1 (sidewalks only) GDS 2007 P-17Concrete thickness: Sidewalks/ driveways GDS 2007 P-16, P-17Location of sidewalk with respect to street and other

    existing sidewalk GDS 2007 P-17Width of sidewalk is 4 or 5 GDS 2007 P-17

    Tooling joints spacing GDS 2007 P-17

    Construction joint requirements GDS 2007P-11, P-16,

    P-17

    Expansion joint spacing (no tear off strips allowed in

    the sidewalks)GDS 2007 P-12, P-17

    Expansion joint materials GDS 2007 P-16, P-17

    Five foot flare instead of radius and curb omission for

    approaches attached to alleysGDS 2007 P-16

    Reinforcing steel GDS 2007P-11, P-16,

    P-17

    Storm drain inlet and separation from approach GDS 2007 D-1

    Location of driveway from intersection

    30 Residential or Alley

    40 Collector / Industrial

    50 Residential Arterial

    Driveway OrdOrd 1604

    as amended

    Bollards for thin brick wall required? Note on this

    inspection if needed.GDS 2007 M-4

    Sidewalks and Approach

    1056

  • 8/3/2019 Carroll Ton Inspection Check List

    14/40

    Ham Antenna Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONAnchor tie and foundations per approved plans and

    specifications CZOArt XXVIII

    Sec D

    Location of antenna (allowed only behind the main

    building CZO Art XXVIIISec DLocation of antenna in the back yard CZO Art XXVIII

    Sec D

    Prohibited location of guy wire anchors CZOArt XXVIII

    Sec D

    Height of anchor points CZO Art XXVIIISec D

    Setback from property lines and right of way CZOArt XXVIII

    Sec D

    Maximum height CZOArt XXVIII

    Sec D

    Fence or anti-climb devices CZOArt XXVIII

    Sec D

    Attachments prohibited CZO Art XXVIIISec D

    NOTE: Lintels installation occurs after the pre-brick inspection and is the

    responsibility of the contractors.

    Ham Antenna

    1072

  • 8/3/2019 Carroll Ton Inspection Check List

    15/40

    Fence

    1090

    Fence Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Proper setback from drainage easements CZOXXV 11-12

    A-D

    Proper height restriction for front yards or certain

    corner lots (key lots) 3' front yards, 4' key lotsCZO XXVI-A

    Proper requirements for pool enclosure 2006 IRCCZO

    Appendix G

    XXVII.7

    Gates across driveways as a pool enclosureTechnical

    Policy

    Sec V UBC

    CAAB ruling

    Zero lot lines (check CZO) CZO Article VIIPages 88-90

    Gates across driveways (electric)Technical

    PolicySec V -UBC

    If electric need inspection / burial depth and conduits

    secured / gfci needed ?2008 NEC

    300.5

    Conduit type

    210.8

    Gates across driveways (manual)Technical

    PolicySec. I 49

    Proper location for visibility from streets & alleys Visibility Ord.Ord. 1325 as

    amended

    No metal, barbed wire, or electric fencing permitted.

    Exception: Wrought iron is allowed.

    CZO

    Ord. 2803

    Article XXV

    Sec 11

    Sec 92-10

    Note: CZO 3/16/04 version

  • 8/3/2019 Carroll Ton Inspection Check List

    16/40

    Foundation Only Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Inspect based on engineered plans:

    - Reinforcement size and spacing- Reinforcement supports (chairs)- Concrete thickness- Beam spacings and depth/width- Debris and mud and water on slab and beams

    Read permit for special notes such as minimum

    finished floor elevations.

    2006 IRC R109.1

    Wrap copper water lines 2006 IRC P2603

    Provide protection for any horizontal plumbing pipeembedded in concrete along the length of the beams 2006 IRC

    P2603.2.1

    TechnicalPolicy

    Driveway not allowed to street if alley exists CSO Article X

    Garage not allowed to face streets certain exceptions

    may be applicableOrd. 2402

    Driveway separation from intersections Driveway Ord.Ord. 1604

    as amended

    Has the lot grade been drastically changed by cuts, fill,or other obstruction which may alter subdivision

    drainage patterns from what was accepted by

    Carrollton Engineering Department?

    Carrollton

    Drainage Ord.

    Ord. 1964

    as amended

    NOTE: Effective May 1, 2003, all foundation inspections must have an engineers

    inspection letter of approval.

    Foundation Only

    2001

  • 8/3/2019 Carroll Ton Inspection Check List

    17/40

    Plumbing Rough/Energy p. 1 of 2

    2020

    Plumbing Rough/Energy Inspection Checklist

    p. 1 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Check for setback survey CZO Use Districts

    Drainage piping materials 2006 IRC P3002

    Drainage pipe installation 2006 IRC P3005.1

    Drainage pipe joints 2006 IRC P3003

    Drainage pipe slope 2006 IRC P3005.4.2

    Drainage system sizing 2006 IRC P3005.4

    Drainage prohibited items 2006 IRC P3003

    P3005.1.5

    P3005.2.11

    Drainage system clean outs 2006 IRC P3005.2.3

    P3005.2.10

    P3005.2.9

    P3005.2

    Backwater valves 2006 IRC P3008

    Fixtures stack vented 2006 IRC P3102

    P-trap installation requirements 2006 IRC P3201

    P-trap sizing 2006 IRC P3201.7

    Water distribution 2006 IRC P2903.6

    Water manifold sizing 2006 IRC P2903.8.1

    2 Hose bibs required on SFD ( front/side and rear) 1

    required on Town houses and Condo's (rear)

    COC Technical

    Policy

    Water piping materials

    Polybutylene Pipe not allowed ( COG Amend.)

    2006 IRC P2904

    Trenching, excavation, and backfill 2006 IRC P2604

    Back flow prevention 2006 IRC P2902

  • 8/3/2019 Carroll Ton Inspection Check List

    18/40

    Plumbing Rough/Energy Inspection Checklist

    p. 2 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    Plumbing Rough/Energy p. 2 of 2

    2020

    CODE ITEM CODE SECTION

    Cut-off valves 2006 IRC P2903.9

    P2903.9.1

    P2903.9.3

    P2903.9.2

    Testing and inspection 2006 IRC P2503

    Gas pipe sizing 2006 IRC G2413&17

    Gas pipe labeling 2006 IRC G2412.5

    Gas pipe materials 2006 IRC G2414

    Gas pipe system installation & Testing 2006 IRC G2415 &

    G2417

    Gas tracer wire 2006 IRC 2415.14.3

    Protection of piping 2006 IRC G2415.8

    G2415.8.2

    Insulate hot water lines 2006 IECC 504.5

  • 8/3/2019 Carroll Ton Inspection Check List

    19/40

    Gas Rough and Test Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Pipe materials2006 IRC

    2006 IFGC

    G2414

    403

    Pipe sizes 2006 IRC2006 IFGC

    G2413

    402

    Pressure test (gas) 2006 IRC2006 IFGC

    G2417

    404

    Connections/joints2006 IRC

    2006 IFGC

    G2414

    Ch. 4

    Tracer wire for non-metallic piping 2006 IRC2006 IFGC G2415.14.3404.14.3

    Pipe depth2006 IRC

    2006 IFGC

    G2415.9

    404.9

    COG

    Amendment

    Gas risers2006 IRC

    2006 IFGC

    G2414.6.1

    Ch. 4

    Gas pipes not to be bent or strained

    2006 IRC

    2006 IFGC

    G2416

    405

    Separate ditch for gas pipingCarrollton

    Policy

    Protection from corrosion2006 IRC

    2006 IFGC

    G2414.8

    404.8

    Gas Rough and Test

    3021

  • 8/3/2019 Carroll Ton Inspection Check List

    20/40

    Pre Brick Inspection Checklist

    p. 1 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Sheathing will be free of all holes 2006 IRC R703

    No framing shall be visible 2006 IRC R703

    The roofing process has been completed Tech Policy 6-21-99

    Exterior openings exposed to weather shall be flashed 2006 IRC R703

    Exterior veneer shall not be attached to wood frame

    construction at or point more than 30 in height2006 IRC Table R703.7

    When wall ties are installed: ties shall be spaced tosupport not more than 2.67 sq. ft. of wall; wall ties shall

    not be more than 24 on centers horizontally &

    vertically

    2006 IRC R703.7.4.1

    When anchored veneer is applied over 2x4 stud

    construction, stud spacing shall not exceed 16Tech. policy Sec. V 32-33c

    When anchored veneer is applied over 2x6 stud

    construction, stud spacing shall not exceed 24Tech. policy Sec. V 32-33c

    Flashing and counter flashing2006 IRC

    Tech Policy

    R703.7.5

    R703.7.8

    Sec v 32

    Brick

    Supported by

    Wood 9-93

    Veneer height and support limitations 30 max height

    to footing rafter size per 2006 IRC, then doubled

    2006 IRC

    Tech Policy

    703.7.2

    703.7.2.1

    703.7.2.2

    703.7.3

    Sec v 32

    BrickSupported by

    Wood 9-93

    Pre Brick p. 1 of 2

    3042

  • 8/3/2019 Carroll Ton Inspection Check List

    21/40

    Pre Brick Inspection Checklist

    p. 2 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    Pre Brick p. 2 of 2

    CODE ITEM CODE SECTION

    Brick on wood rafters

    3 2x8

    2006 IRC

    Tech Policy

    R703Sec V 32

    Brick

    Supported by

    Wood 9-93

    Wind sheer

    Scab 2x4 on side of each stud

    2006 IRC

    Tech Policy

    R703.4.1.2

    Sec v 32

    Brick

    Supported by

    Wood 9-93

    Wall bracing 2006 IRC

    R602.10

    Table

    R602.3.(1)

    Water resistance barrier

    Exterior wall envelope2006 IRC R703.2

    Seal exterior wall envelope 2006 IECC 402.4

    *NOTE:

    Lintel installation occurs after the pre-brick inspection and is the responsibility ofthe contractors.

    Lintel = the horizontal beam forming the upper member of a door or window framesupporting part of the structure above it.

    3042

  • 8/3/2019 Carroll Ton Inspection Check List

    22/40

    Plumbing Top Out/HVAC Rough/Gas Test/Energy p. 1 of 33065

    Plumbing Top Out/HVAC Rough/Gas Test/Energy Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONPlumbing vent termination with respect to openings 2006 IRC P3103

    Water heater vent location 2006 IRC M1804

    Gas pipe sizing and tests. CSST must be supported

    every 4ft. and a min. of 12" clearance from roof deckunless installed in a flexible metal sleeve must be

    bonded from manifold to breaker panel with min. # 6wire or equivalent. Tested 10lbs. on 20 lb. 3 1/2"

    diaphragm test gauge and 3lbs. on a 6lb. 3 1/2

    diaphragm test gauge on low side with currentcalibration sticker.

    2006 IRC &

    COC TechnicalPolicy

    G2413&17

    Ventilation 2006 IRC M1507

    Protection of piping (freeze or damage) 2006 IRC P2603.6

    Fixture drainage lines 2006 IRC P3005

    Tests and inspection (sanitary drainage and potable

    water2006 IRC P2503

    Required Hose bibs ( 2 on SFD front & rear) 1 on

    Town homes and Condo's

    COC Tech.

    Policy

    Showers (material, installation and testing)COG

    AmendmentP2708

    Island fixture venting 2006 IRC P3112

    Vent connection and grades 2006 IRC P3104

    Stack venting 2006 IRC P3102

    Wet venting limitations 2006 IRC P3108

    Trap arm and p-trap 2006 IRC P3201.5

    Prohibited traps 2006 IRC P3201.5

    Clothes washer trap and tail piece height requirement2006 IRC

    Table 3201.7

    P2706.2

  • 8/3/2019 Carroll Ton Inspection Check List

    23/40

    Plumbing Top Out/HVAC Rough/Gas Test/Energy Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    Plumbing Top Out/HVAC Rough/Gas Test/Energy p. 2 of 33065

    CODE ITEM CODE SECTION

    Piping support

    2006 IRC &

    COC TechnicalPolicy for

    CSST

    P2605

    Water heaters: Regulations and installation2006 IRC &

    COC Technical

    Policy

    P2801.5.1P2801.5

    Insulate hot water lines 2006 IECC 504.5

    Above ceiling pan and drain for water heater 2006 IRC P2801

    Combustion air 2006 IRC M1701

    Ducts (HVAC) 2006 IRC M1601.2

    Duct insulation2006 IRC

    2006 IECC

    1601.3.4

    C.O.G.Table.

    503.3.3.3

    Refrigerant piping insulation 2006 IECC 503.2.8 C.O.G

    Hot water pipe insulation 2006 IECC 504.5 C.O.G

    Plenums: Sealed & secure 2006 IECC 503.2.7

    HVAC equipment: access and service space 2006 IRC M1305.1

    Condensation 2006 IRC M1411

    Return air 2006 IRC M1602

    Exhaust fans: vent termination 2006 IRC M1507

    Clothes dryer duct

    2006 IRC

    COGAmendment

    M1502504.6

    Chimney & vents 2006 IRCChapter 10

    M1805

  • 8/3/2019 Carroll Ton Inspection Check List

    24/40

    Plumbing Top Out/HVAC Rough/Gas Test/Energy Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    Plumbing Top Out/HVAC Rough/Gas Test/Energy p. 3 of 33065

    CODE ITEM CODE SECTION

    Specific appliances (fireplace and fuel burning

    equipment)

    Specific

    appliances(fireplace and

    fuel burning

    equipment)

    2006 IRC

    M1901

    Water heaters 2006 IRC M2005

  • 8/3/2019 Carroll Ton Inspection Check List

    25/40

    Electrical Rough/Frame/Building/Energy

    Building Sheet p. 1 of 23066

    Electrical Rough/Frame/Building/Energy Inspection Checklist

    Building Sheet p. 1 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONWall heights/stud heights 2006 IRC R602.3.1

    Carrollton Tbl

    Safety glazing 2006 IRC R308.4

    Wind bracing 2006 IRCR602.10.3

    R602.10.6

    C.O.G.

    Amend.

    Struts and purlins 2006 IRC R802.5.1

    Brick supported by wood members 2006 IRCNCTCOG

    Policy

    Cutting, notching and boring 2006 IRC

    R502.8

    R502.8.1

    R502.8.2

    602.6.1

    Floor joist bearing 2006 IRC R502.6

    Bathroom and laundry room ventilation 2006 IRC R303.3

    Attic ventilation (This only for a reminder at this stage.

    Shall not cause inspection disapproval.)2006 IRC

    R806.1

    R806.2

    R806.3

    Rafter, joist, header construction 2006 IRC

    R802.3

    R502.4

    R602.7

    R804.3

    New additions or remodel, smoke detector

    requirements/wiring 2006 IRC R313.1.1

    Bottom plates anchor - bolts or shot 2006 IRC R403.1.6

    Perimeter bottom plates treated 2006 IRC R320.1

    Fire blocking - holes and openings in top plates 2006 IRC R602.8

  • 8/3/2019 Carroll Ton Inspection Check List

    26/40

    Electrical Rough/Frame/Building/Energy Inspection Checklist

    Building Sheet p. 2 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    Electrical Rough/Frame/Building/Energy

    Building Sheet p. 2 of 23066

    CODE ITEM CODE SECTIONDraft stop 2006 IRC R502.12

    Stairs: run, rise, width 2006 IRC R311.5

    Fireplace lintel support 2006 IRC R1003.7

    Windows / Skylights U-Factor, SHGC 2006 IECC

    N1102.1

    C.O.G.

    Amend.

    Proper lumber grade stamps 2006 IRCR802.1

    R320.1.1

    Roof and ceiling framing 2006 IRC R802

    Exterior wood protection/sheathing 2006 IRC R703

    Framing at skylights 2006 IRC R802.9

    Line up of floor and ceiling joists to studs 2006 IRC R602.3.3

    Size & location of emergency bedroom windows 2006 IRC R310.1

    Driveway not allowed to street if alley exists CZOOrd 1604 as

    amended

    Nailing Patterns on exterior sheathing 2006 IRC R 602.10

    No green board allowed in bathroom shower/tub areas 2006 IRC R702.3.8

  • 8/3/2019 Carroll Ton Inspection Check List

    27/40

    Electrical Rough/Frame/Building/Energy

    Electrical Sheet p. 1 of 23066

    Electrical Rough/Frame/Building/Energy Inspection Checklist

    Electrical Sheet p. 1 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM

    CODE

    SECTION

    Required outlet spacing / location2008 NEC 210.52

    210.63

    Required outlets/switches circuits

    Kitchen counter top spacing

    2008 NEC 210-52

    210.70

    Protection of wires run through framing/studs2008 NEC 300.4

    334

    Support of NM cables (staples) 2008 NEC 314.17334

    NM cable in wet locations / kitchen islands (not allowed)2008 NEC 334.12

    Grouping / bundling of cables ( no more than 4- #12 & #14 )2008 NEC 334.8

    Damaged, pinched or torn cables2008 NEC 110

    Sealing penetrations top plates and fire blocking 2008 NEC 300.21

    Recessed lighting fixtures clearances / energy2008 NEC 410

    Bonding of metal boxes / ground pigtails / grounding

    2008 NEC 250.148

    314.4

    404.9

    Ceiling fan rated boxes 2008 NEC 314.27

    Smoke / fire alarm locations IRC 2006 R313

  • 8/3/2019 Carroll Ton Inspection Check List

    28/40

    Electrical Rough/Frame/Building/Energy Inspection Checklist

    Electrical Sheet p. 2 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    Electrical Rough/Frame/Building/Energy

    Electrical Sheet p. 2 of 23066

    CODE ITEM CODE SECTION

    Atticspace requirements: switches , service outlet , a/c

    disconnect & exhaust fan controls

    2008 NEC 210.70

    210.63

    320.23

    Jacuzzi tub requirements: circuits, gfci, & bonding

    2008 NEC 680.71

    Through

    681.74

    Conductor fill for boxes / number or cables in box 2008 NEC 314.16

    Panel service conductor size2008 NEC 310.15

    Neutral identification (white tape)2008 NEC 200.6

    One neutral per termination point on bar/ buss

    Grounds may be doubled

    2008 NEC

    C.O.C

    408.41

    Sub- panel isolation / no bond at to neutral at sub-panel2008 NEC 250.24

    Coverage of panel during contruction2008 NEC 110.12

    Bonding / grounding : all metal enclosures / cold water

    bonding

    2008 NEC 250.28

    250.52

    250.53

    250.92

    Concrete encased electrode /other electrodes / access2008 NEC 250.32

    250.64

    Panel identification / marking phases /amps/ voltage2008 NEC 408.58

    Panel maximum 42 circuits 2008 NEC 408.54

  • 8/3/2019 Carroll Ton Inspection Check List

    29/40

    Insulation Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Insulation walls, ceilings, floors 2006 IECC102

    402502

    2006 C.O.G. Amendments 2006 IRC 1102.1Water resistance barrier on exterior wall envelope 2006 IRC R 703.2

    Insulation

    3067

  • 8/3/2019 Carroll Ton Inspection Check List

    30/40

    Roof Final Inspection

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    Minimum class C roof2006 IRC

    COGAmendment

    R902

    Minimum deck thickness 7/16 2006 IRC TableR503.2.1(1)

    Clearance from combustibles 2006 IRC M1306.1Note:

    Inspection shall be requested at the completion of the deck replacement process. The contractor is completely responsible for installing the roof in accordance

    with the manufacturers specifications.

    The final roof inspection is limited to materials and clearance fromcombustibles.

    Roof Final

    4003

  • 8/3/2019 Carroll Ton Inspection Check List

    31/40

    Utility Release/Plumbing, HVAC/Energy Final p. 1 of 2

    4005

    Utility Release/Plumbing, HVAC/Energy Final Inspection Checklist

    p. 1 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONGas hooked up to appliances 2006 IRC G2422All plumbing fixtures in place, connected and water on 2006 IRC P2503

    No leaks in fixture drains 2006 IRC P2503.5.2Gas shut-off valves and connectors 2006 IRC G2420

    Water heater temperature and pressure relief valve 2006 IRC P2803

    Water heater clearance (if installed) 2006 IRC M2005

    Service water heating 2006 IECC 504

    Furnace AFUE rating (seasonal) 2006 IECC Tbl.503.2

    Valve box at house 2006 IRC P2903.9.1

    Vacuum breakers/frost proof hose bibbs 2006 IRCP2903.8.7

    P2903.10

    Seal firebox where penetrated by gas log lighter Mfg Specs

    A/C pad 2006 IRC 1403.2

    Catwalk and working space for attic units 2006 IRC 1305.1

    Appliance venting (if installed) *Vent-A-Hood not

    included2006 IRC M1801

    Electrical safely capped (or fixture installed) 2008 NEC 410-5

    A/C overcurrent protection to manufacturers specs 2008 NEC 440.22

    Electric panel feeder size 2008 NEC 310.15

    Grounding electrode system 2008 NEC 250

    Jacuzzi motor 2008 NEC 680 & 681

    No unused openings in panel 2008 NEC 110.12

  • 8/3/2019 Carroll Ton Inspection Check List

    32/40

    Utility Release/Plumbing, HVAC/Energy Final Inspection Checklist

    p. 2 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    Utility Release/Plumbing, HVAC/Energy Final p. 2 of 2

    4005

    CODE ITEM CODE SECTIONCity clean out GDS S11

    Water meter can GDS W-7

    Controls / Temperature 2006 IECC 503.3.2.2

    Clearance from combustibles 2006 IRC M1306.1

    Termite certification 2006 IRC R320

    Bollards behind driveways for subdivision screening

    walls

    GDS M-4

  • 8/3/2019 Carroll Ton Inspection Check List

    33/40

    Pool Work Final

    4042

    Pool Work Final Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTION

    P-Trap2006 IPC

    CarrolltonPolicy

    802.1.4802.2.1

    GFCI for pool lights 2008 NEC 680GFCI location & testing 2008 NEC 680

    Grounding terminations 2008 NEC 680Fence enclosure, gates and latches 2006 IRC

    AG105.2

    AG105.2.4

    Backflow protection 2006 IPC 608

    Backwash/drain pipeCarrollton

    Policy

    Any gas line related items

    Lo pressure 3 lbs on 6 lb visibly certifiable diaphragm

    gauge

    High or med. 60 lbs on 100 lb visibly certifiable

    diaphragm gauge

    2006 IRC

    2006 IFGCApp. G

    Pool heaters ON-OFF switch 2006 IECC 504.3.1

    Pool cover for heated pools 2006 IECC 504.3.2

    Pool time clocks setting 2006 IECC 504.3.3

    DrainageCDO

    2006 IRC

    Ord. 1964

    R401.3

    Entrapment protection / svrs system in place 2006 IRCAppendix G

    AG 106

  • 8/3/2019 Carroll Ton Inspection Check List

    34/40

    Electrical/Building/Energy Final Inspection Checklist

    Building Sheet p. 1 of 2

    4063

    Electrical/Building/Energy Final Inspection Checklist

    Building Sheet p. 1 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONSafety glass and glazing 2006 IRC R308Attic access and appliance access 2006 IRC R807.1

    M1305

    Smoke detectors (with battery backup) 2006 IRC R313

    Front and rear address (minimum 4 inch numbers) Policy Fire Dept.

    Hearth size 2006 IRC R1001.10Combustibles clearance from fireplace opening 2006 IRC Tbl 1001.011001.11

    1003.18

    Separation between garage and house 2006 IRC R309.2

    Percentage of exterior brick(SF@70%) CZO Art. VII

    Water meter cans (boxes) 2007 GDS W-7

    City walks and approaches

    Subdv Ord

    GDS

    Art. X, Sec. G

    & X1sec B

    P-15, P-22P-26

    Sewer cleanouts, water valves, manholes; level and

    accessible2007 GDS

    Water &

    Sewer

    Chapters

    Any work done without permit such as fences

    exceeding 20 feet in length, lawn sprinkler, dish, pool,

    etc.

    General

    Brochure

    Attic ventilation*Includes Vent-A-Hood duct

    2006 IRC R806

    Exterior refrigerant piping 2006 IECC 402.4.1

    Blown-in insulation shall comply with IECC2006 IECC

    2006 IRC

    102.11,1101.4

    402.1.2

  • 8/3/2019 Carroll Ton Inspection Check List

    35/40

    Electrical/Building/Energy Final Inspection Checklist

    Building Sheet p. 2 of 2

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    Electrical/Building/Energy Final Inspection Checklist

    Building Sheet p. 2 of 2

    4063

    CODE ITEM CODE SECTIONSurface drainage shall be directed to swales to ensure

    drainage away from foundation.2006 IRC R401.3

    Stair and handrail requirements2006 IBC

    2006 IRC

    1009.1& 1012.4

    311.51

  • 8/3/2019 Carroll Ton Inspection Check List

    36/40

    Electrical/Building/Energy Final Inspection Checklist

    Electrical Sheet

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline

    CODE ITEM CODE SECTIONCovers, face plates & canopies

    a. Outlet boxesb. Snap switchesc. Receptaclesd. Damp locationse. Fixturesf. Closet fixtures

    2005 NEC314.25

    314.41

    GFCI locations

    a. Bathroomb. Garagec. Outdoord. Crawl spacee. Unfinished basementf. Kitcheng. Bar sink

    2005 NEC 210-8

    Appliance installation 2005 NEC 422Stair and handrail requirements

    2006 IBC

    2006 IRC

    1009.1& 1012.4

    311.51

    Electrical panel

    Grounding electrode system 2005 NEC250.50

    250-52

    310.16

    A/C disconnect, wire & fuse size

    2005 NEC 440-11

    440.12

    440.22

    Protection of wiring in attics 2005 NEC 320.23

    Electrical panel installation 2005 NEC

    110-26

    408

    Service conductor size 2005 NEC220

    310-16

    Other electrical conductor sizes 2005 NEC 310-16

    Electrical/Building/Energy Final Inspection Checklist

    Electrical Sheet

    4063

  • 8/3/2019 Carroll Ton Inspection Check List

    37/40

    Clean and Show/Construction Heat/Electric Service

    6015

    Clean and Show/Construction Heat/Electric Service Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONProper breaker size for heating unit 2008 NEC 424

    Panel cover installed 2008 NEC 408access to electrical equipment 2008 NEC 110No holes in panel or unused openings 2008 NEC

    408

    110-12

    Capping of all loose wires and installed outlet covers 2008 NEC 110.14

    Identification of panel service on meter base or

    disconnect 2008 NEC

    408

    110230

  • 8/3/2019 Carroll Ton Inspection Check List

    38/40

    Clean and Show/Construction Heat/Gas Service Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONPipe materials (gas) 2006 IFGC 403Pipe sizes (gas) 2006 IFGC 402Connections (gas) 2006 IFGC 403Pressure test (gas) 2006 IFGC 406

    Proper installation 2006 IFGC 305

    Venting of appliance 2006 IFGC Chapter 5

    Clean & Show/Const. Heat/Gas Service

    6020

  • 8/3/2019 Carroll Ton Inspection Check List

    39/40

    Clean and Show/Construction Heat/Gas and Electric Service Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONCombine 6015 & 6020 inspections

    Clean and Show/Construction Heat/Gas and Electric Service

    6060

  • 8/3/2019 Carroll Ton Inspection Check List

    40/40

    General Check/Follow-up Inspection Checklist

    This checklist is not to be construed as all-inclusive; it is only to be used as a guideline.

    CODE ITEM CODE SECTIONGeneral Check/Follow-up