+ All Categories
Home > Documents > Case Studies - Distributed Wind Energy Association

Case Studies - Distributed Wind Energy Association

Date post: 11-Feb-2022
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
108
Transcript
Page 1: Case Studies - Distributed Wind Energy Association
Page 2: Case Studies - Distributed Wind Energy Association

Exemplary Distributed &

Community Wind Case Studies Moderator: Lisa Daniels, Windustry

Speakers: Scott Abbett, SED

Alan Axworthy, Northern Power Systems

Roger Dixon, Skylands Renewable Energy Corey Juhl, Juhl Wind

Aaron Morrow, HTWN

Charles Newcomb, Endurance Wind Power

John Pimental, Foundation Wind Power

Page 3: Case Studies - Distributed Wind Energy Association
Page 4: Case Studies - Distributed Wind Energy Association
Page 5: Case Studies - Distributed Wind Energy Association

HARBEC Inc.

Fuhrlander FL250 250kW

Installed in December of 2002

Page 6: Case Studies - Distributed Wind Energy Association

Northern Development LLC

Gamesa G58 850kW

Page 7: Case Studies - Distributed Wind Energy Association

Project / Turbine Stats

Gamesa G58 850kw

•~180 ft - Hub Height

•55m tower option

•~275 ft - Blade Tip Height

•~190 ft – Rotor Diameter

•~1,750,000kwh/year

Page 8: Case Studies - Distributed Wind Energy Association

Permitting Challenges

•Local Oversight – Ontario Planning and Zoning

•County Oversight – Wayne County Planning Board

•Federal Oversight – USACE

•Utility Oversight – Interconnection and Siting

Page 9: Case Studies - Distributed Wind Energy Association

Wetlands / Foundation

•Project required a Nationwide Permit from the USACE

•~600 yards of concrete

•Continuous pour, one truck every 10 minutes for 10 hours straight

Page 10: Case Studies - Distributed Wind Energy Association

Funding and Financing

•Project was fully debt financed by ESL Federal Credit Union

•ESL also provided short term line of credit for construction

finance

•First larger than 100kW turbine installed under the NYSERDA PON

2097 Program.

•$400,000 total.

•Federal 1603 funding

•~$700,000

Page 11: Case Studies - Distributed Wind Energy Association

Wayne Industrial

Sustainability Park •Wayne Industrial Sustainability Park = WISP

•How do you create an office park sharing electrical generation in lieu

of virtual net metering?

•Wayne County Industrial Development Authority

Page 12: Case Studies - Distributed Wind Energy Association

Final Unique Project Facts

Page 13: Case Studies - Distributed Wind Energy Association

Thank you For Your Time

Please Visit us on the Web at: www.sed-net.com

Page 14: Case Studies - Distributed Wind Energy Association
Page 15: Case Studies - Distributed Wind Energy Association

Distributed & Community Wind Case Studies

Off-grid Water Pumping in Hawaii

Alan Axworthy

Northern Power Systems

June 11, 2013

Page 16: Case Studies - Distributed Wind Energy Association

16

Page 17: Case Studies - Distributed Wind Energy Association

Traditional Land Divisions: Ahupua’a

“What this really aligns with is an ahupua’a system

where we’re not wasteful, we’re very cognizant of

utilizing the natural resources more efficiently…”

Leo Caires / Gen-X Energy Development

Page 18: Case Studies - Distributed Wind Energy Association

The Need: Water… Wai

Page 19: Case Studies - Distributed Wind Energy Association

Challenges: Remoteness

“One of the exciting aspects of our project is it

really addresses problems faced in remote

locations and that is bringing a new sense of

freedom that we can now deliver energy into

locations that normally would not be able to have

access to infrastructure or electricity power.”

Leo Caires / Gen-X Energy Development

Page 20: Case Studies - Distributed Wind Energy Association

Challenges: Grid Capacity Restrictions

Page 21: Case Studies - Distributed Wind Energy Association

Challenges : Intermittent Wind Resource

Page 22: Case Studies - Distributed Wind Energy Association

The Solution: Microgrid

Page 23: Case Studies - Distributed Wind Energy Association

Microgrid Proof-of-Concept

Page 24: Case Studies - Distributed Wind Energy Association

The Solution: Off-grid Farming Subdivision

Page 25: Case Studies - Distributed Wind Energy Association

Wind Resource

Page 26: Case Studies - Distributed Wind Energy Association

Benefits

“This turbine in this location is a kind of… symbol of what this

entire community is really all about—sustainability, reducing

carbon footprint, reducing greenhouse gas emissions, and

reducing our reliance on foreign oil.”

Fred Brown / Gen-X

Page 28: Case Studies - Distributed Wind Energy Association

Mahalo

Alan Axworthy

Northern Power Systems

http://www.northernpower.com

Page 29: Case Studies - Distributed Wind Energy Association
Page 30: Case Studies - Distributed Wind Energy Association

11 kW Gaia

Turbine

Grahamsville

Sullivan County

New York

Roger Dixon MREA Certified Wind Site Assessor

NABCEP Certified Level 3 Small Wind Installer

NYSERDA Certified Wind Turbine Installer

Skylands Renewable Energy, LLC

908.337.2057

[email protected] - www.skylandsre.com

Page 31: Case Studies - Distributed Wind Energy Association

The Process

• Qualify the Site via Wind Modeling Programs and Satellite

Imagery

• Meet with Client and Visually Inspect Site

• Complete NYSERDA Analysis/Discuss Client Expectations

• Paperwork and Contracts (Client, NYSERDA, Local Utility)

• Excavation, Underground Electric and Footing

• Construction and Electrical Inspections

• Delivery of Turbine and Tower

• Assembly and Erection

• Final Connections and Testing

• Final Inspections (Electrical, Construction, Utility and

NYSERDA) and Commissioning of Turbine

Page 32: Case Studies - Distributed Wind Energy Association

Qualify The Site Via Computer and

Satellite Imagery

Page 33: Case Studies - Distributed Wind Energy Association

HILLS and RIDGES

Page 34: Case Studies - Distributed Wind Energy Association

Wind Energy Site Assessment

• Qualify The Available Wind Resource At A Specific

Geographic Location

• Visually Inspect Area

• Quantify Site Obstructions And Height

• Evaluate Possible Locations For Tower

• Note Soil Condition

• Locate Existing Utilities

• Evaluate Crane Access

• Summarize Electrical Use

• Manage Client Expectations

Page 35: Case Studies - Distributed Wind Energy Association

Meet With Client and Visually Inspect Site

35

Page 36: Case Studies - Distributed Wind Energy Association

Mark Trees to Clear at Tower Location

36

Page 37: Case Studies - Distributed Wind Energy Association

Appropriate Tower Height

• Existing Ground Obstructions

• Rotor Length/Overall System Height

• FAA Regulations

• “Fall” Zones And Lot Line Setbacks

• Cost

• Type of Tower

• Lattice vs. Monopole

• Guyed vs. Freestanding

• Footings

• Local Zoning Regulations

37

Page 38: Case Studies - Distributed Wind Energy Association

Existing Electrical - Grid and Backup Generator

38

Page 39: Case Studies - Distributed Wind Energy Association

Site Specific

Report

NYSERDA

Analysis

Page 40: Case Studies - Distributed Wind Energy Association

Site

Specific

Report

NYSERDA

Analysis

Page 41: Case Studies - Distributed Wind Energy Association

Tower Footing in Process

41

Page 42: Case Studies - Distributed Wind Energy Association

Turbine Delivery

42

Page 43: Case Studies - Distributed Wind Energy Association

Unloading the Blade

43

Page 44: Case Studies - Distributed Wind Energy Association

Turbine Controller Installation

44

Page 45: Case Studies - Distributed Wind Energy Association

Revised Electrical System

45

Page 46: Case Studies - Distributed Wind Energy Association

Preparing for the Crane Lift

46

Page 47: Case Studies - Distributed Wind Energy Association

Setting Up the Crane

47

Page 48: Case Studies - Distributed Wind Energy Association

“The Pick” (Lower Part)

48

Page 49: Case Studies - Distributed Wind Energy Association

“The Pick” (Upper Part)

49

Page 50: Case Studies - Distributed Wind Energy Association

Tower Top View to the NW Tower Top View to the W

Page 51: Case Studies - Distributed Wind Energy Association

Tower Top View to the SW Tower Top View to the S

Page 52: Case Studies - Distributed Wind Energy Association

Tower Top View To The SE Tower Top View To The E

Page 53: Case Studies - Distributed Wind Energy Association

Tower Top View to the NE Tower Top View to the N

Page 54: Case Studies - Distributed Wind Energy Association

Satellite Image After Installation

Page 55: Case Studies - Distributed Wind Energy Association

Roger Dixon

MREA Certified Wind Site Assessor

NABCEP Certified Level 3 Small

Wind Installer

NYSERDA Certified Wind Turbine

Installer

Skylands Renewable Energy, LLC

908.337.2057

[email protected]

www.skylandsre.com

Page 56: Case Studies - Distributed Wind Energy Association
Page 57: Case Studies - Distributed Wind Energy Association

June 11th, 2013

DWEA - Small and Community Wind Conference and Exhibition

Adams Wind

20 MW - Community Wind Project

(Cosmos, MN)

Page 58: Case Studies - Distributed Wind Energy Association

Company Overview

58

The Adams Wind project (Adams Wind

Generations, LLC) is a community

owned and operated wind energy project

with a total nameplate capacity of 19.8

megawatts, utilizing twelve Alstom ECO-

86 1.65MW wind turbines. The project is

located approximately 70 miles west of

Minneapolis near the small town of

Cosmos, MN. The Adams Wind project is

a MN C-BED project which means at

least 51% of the gross electricity

revenues generated over the life of the

20-year power purchase agreement will

flow to the local owners. (The Adams

family.)

Introduction Adams Wind

PROJECT DETAILS

Project Size 19.8 MW

Project Location 2 miles West of Cosmos, MN

Turbine Equipment Alstom ECO-86 (1.65 MW)

Rotor Diameter 86 meters (282 ft.)

Structure Height 123 meters (403 ft.)

Local Owner Adams Family

Developer Juhl Wind Inc.

O&M Provider Alstom – Juhl Energy

Services

Balance of Plant Ryan Construction

Equity/Debt

Partner

JP Morgan Chase

Utility Off-taker Xcel Energy

Page 59: Case Studies - Distributed Wind Energy Association

Company Overview

59

The Adams Wind Project started as local land owner and farmer Doug Adams’

vision as he and his wife Karen explored ways to have the next generation of the

family (their four daughters and sons-in-law) involved in an Ag related business

together. Since none of his daughters decided to become (or marry) farmers, Doug

wanted to create a way for their family to have roots in the community long after he

retires from farming his land and the Adams Wind Project will allow them to do so

by “farming the wind” for the next 20 years. The project also helps to support the

local economy through land-lease payments to landowners, tax payments

benefiting the county and townships, and by creating new 6 new full-time jobs.

Project Overview Adams Wind

Page 60: Case Studies - Distributed Wind Energy Association

Company Overview

60

Conclusion Kenfield Wind

Thank you!

Page 61: Case Studies - Distributed Wind Energy Association
Page 62: Case Studies - Distributed Wind Energy Association

GREENSBURG HIGH SCHOOL CASE STUDY

June 11, 2013

Page 63: Case Studies - Distributed Wind Energy Association

Public School Finance 101 G

ener

al F

un

d

• Salaries

• Benefits

• Consumable Supplies

Cap

ital

Ou

tlay

Fu

nd

• Buildings

• Remodeling

• Renovations

• Non-Consumable Items

Page 64: Case Studies - Distributed Wind Energy Association

Project Overview

Turbine: Endurance E-3120 (50kW) 140ft Lattice

Annual Production: ~220,000 kWh

Demonstrated Annual Savings: $20k-$25k

Page 65: Case Studies - Distributed Wind Energy Association

Sales Process:

Customer Drivers

Development Process:

Interconnection

Permitting

Financing:

The Value to School Administrators!

Operation:

Endurance as a Partner

Value to School:

Superintendent’s Perspective

Project Details

Page 66: Case Studies - Distributed Wind Energy Association

Customer’s Perspective

Page 67: Case Studies - Distributed Wind Energy Association
Page 68: Case Studies - Distributed Wind Energy Association
Page 69: Case Studies - Distributed Wind Energy Association
Page 70: Case Studies - Distributed Wind Energy Association
Page 71: Case Studies - Distributed Wind Energy Association
Page 72: Case Studies - Distributed Wind Energy Association
Page 73: Case Studies - Distributed Wind Energy Association

endurancewindpower.co

m Confidential and Proprietary Information ©2013

Global Leaders in Distributed Energy Solutions BUILDING ON

SUCCESS

73

The Process: Picking Up the Pace

Problem/Opportunity

• UK FIT = Wide Funnel, Short Pipe

• Screening is time critical

Need

• GIS, shorthand AEP screening

• Requires tools/expertise not typical of DWT

Solution

• Partners (aggregators)

Page 74: Case Studies - Distributed Wind Energy Association
Page 75: Case Studies - Distributed Wind Energy Association
Page 76: Case Studies - Distributed Wind Energy Association
Page 77: Case Studies - Distributed Wind Energy Association
Page 78: Case Studies - Distributed Wind Energy Association
Page 79: Case Studies - Distributed Wind Energy Association
Page 80: Case Studies - Distributed Wind Energy Association
Page 81: Case Studies - Distributed Wind Energy Association
Page 82: Case Studies - Distributed Wind Energy Association
Page 83: Case Studies - Distributed Wind Energy Association
Page 84: Case Studies - Distributed Wind Energy Association
Page 85: Case Studies - Distributed Wind Energy Association

Distributed Wind Generation Overview June 2013

Page 86: Case Studies - Distributed Wind Energy Association

Foundation Windpower General Electric SLE 1.5MW wind turbine Vernalis, CA

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 86

Company Overview • Founded 2008 to pursue distributed wind projects • Industrial, commercial, municipal - energy niche • Design, develop, permit, finance, build, operate • Long-term power purchase agreement model • World-class equipment suppliers

11 sites 16 turbines 22 MW of generating capacity

Benefits to Customer • Energy cost savings and stabilization • Zero emissions • Small footprint (esp. compared to solar) • Visible symbol of environmental stewardship

Page 87: Case Studies - Distributed Wind Energy Association

Walmart 1.0 MW Red Bluff, CA

Safeway 2.0 MW Tracy, CA

Teichert 1.5MW Vernalis, CA

IEUA 1.0MW Rancho Cucamonga, CA

Anheuser Busch 1.5 MW Fairfield, CA

Cemex 1.0 MW Madison, CA

Robertson’s Ready Mix 2.0 MW Cabazon, CA Nestle Waters

3.2 MW Cabazon, CA

Cemex Black Mountain 3.2 MW Victorville, CA

Cemex River Plant 3.0 MW Victorville, CA

California Footprint, 22 MW (and growing)

Superior Farms 1.0 MW Dixon, CA

* Actual installed turbines in photos, if no photo, then project is in permitting phase

Page 88: Case Studies - Distributed Wind Energy Association

Distributed Wind Generation: Behind-The-Meter

Facility Site

Centralized Large Power Plant

Net Energy Metering

• Up to 1MW per Meter • At retail prices

Traditional Industrial Power Sales

• Long term PPA • Discount to retail rate

Wind Turbines

ON SITE

• Industrial retail rates • Inflexible monopoly

+ Transmission Expense Direct Sale

1-5 MW

Retail Sale

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 88

Page 89: Case Studies - Distributed Wind Energy Association

Benefits to Customer

• Cost savings (no capital expense) and cost predictability

• Creates “green jobs”

• Small footprint

• 1.0 MW of solar PV = 6 to 8 acres • 1.5 MW of wind = 50 sq. ft.

• Every 1500 MWh of renewable energy produced

• Could power 250 average sized homes • Equals planting almost 300 acres of trees • Eliminates over 2,600,000 lbs of CO2 • Saves over 2,000 barrels of oil

• A visible symbol of environmental stewardship

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 89

Solar PV – 1.0 MW Wind – 1.5 MW

= 5 to 7 acres = ~ 800 sq. ft.

Wind turbine

could fit in ½ of an end

zone

PV solar requires

~9 football

fields

Page 90: Case Studies - Distributed Wind Energy Association

PPA Based Model – No Risk Way to Reduce Costs

• Zero Payback Period (all cap ex and operating costs are paid by Foundation Windpower)

• Immediate cost savings of 5% to 20% (utility rates rise 5%-6% annually)

• Customers may save millions of dollars in energy costs

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 90

Page 91: Case Studies - Distributed Wind Energy Association

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 91

• Complex process

• 6 to 24 months

• High degree of uncertainty

• $50k to $500k for planning, permits, mitigation

Challenge #1 = CEQA

May result in no project and

total loss

Page 92: Case Studies - Distributed Wind Energy Association

6/15/2013

Challenge #2 = Community Acceptance

Foundation Windpower LLC – Confidential / Proprietary 92

Housecats kill 1000x more birds than wind turbines

Noise level = to your kitchen refridgerator

Page 93: Case Studies - Distributed Wind Energy Association

Challenge #3 = Window Is Closing

1. Federal tax incentives SUNSET -- concern regarding federal debt

• Wind tax credits (PTC/ITC) recently extended • Only valid for project starting construction before Dec. 31, 2013

2. Self Generation Incentive Program is FINITE and COMPETITIVE • No new funding past 2014

3. Tax equity and credit (esp. project finance) markets CHANGE • Not many firms active in tax equity – Foundation Windpower has strong relationship • Debt markets nervous and fickle

4. Equipment is available NOW at attractive prices and terms • Equipment often not available for one-turbine projects

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 93

This window will close… soon

Current market conditions enable Foundation Windpower to offer renewable energy at a small discount to traditional power

Page 94: Case Studies - Distributed Wind Energy Association

6/15/2013

Anheuser-Busch Budweiser Brewery (Fairfield, CA)

Foundation Windpower LLC – Confidential / Proprietary 94

August 2011-- Foundation work October 2011 -- Construction & Erection November 2011 -- Electrical & Interconnection November 2011 – Commissioned Adjacent to I-80

Page 95: Case Studies - Distributed Wind Energy Association

6/15/2013

Superior Packing, Ellensburg Lamb Co. (Dixon, CA)

Foundation Windpower LLC – Confidential / Proprietary 95

October 2012-- Foundation work November 2012 -- Construction & Erection December 2012 -- Electrical & Interconnection December 2012 – Commissioned Visible from I-80 near Davis, CA

Page 96: Case Studies - Distributed Wind Energy Association

6/15/2013

1.5 MW Teichert Materials (Vernalis, CA)

Foundation Windpower LLC – Confidential / Proprietary 96

March-April 2010 -- Foundation work May 2010 -- Construction & Erection Jun.-Aug. 2010 -- Electrical & Interconnection September 2010 – Commissioned Visible from I-580, I-205, Hwy 33

Page 97: Case Studies - Distributed Wind Energy Association

6/15/2013

2.0 MW Safeway Distribution Center (Tracy, CA)

Foundation Windpower LLC – Confidential / Proprietary 97

Feb 2011 - Foundation work April 2011 - Construction May 2011 - Electrical & Interconnection June 2011 – Commissioned Located adjacent to I-580

Page 98: Case Studies - Distributed Wind Energy Association

6/15/2013

1.0 MW Inland Empire Utility Agency (Rancho Cucamonga, CA)

Foundation Windpower LLC – Confidential / Proprietary 98

August 2011-- Foundation work October 2011 -- Construction & Erection November 2011 -- Electrical & Interconnection November 2011 – Commissioned Visible from I-10 and I-15

Page 99: Case Studies - Distributed Wind Energy Association

6/15/2013

1.0 MW Project Cemex (Madison, CA)

Foundation Windpower LLC – Confidential / Proprietary 99

May 2012-- Foundation work June 2012 -- Construction & Erection July 2012 -- Electrical & Interconnection August 2012 – Commissioning Visible from Hwy-505

Page 100: Case Studies - Distributed Wind Energy Association

6/15/2013

3.2 MW Cemex River Plant (Victorville, CA)

Foundation Windpower LLC – Confidential / Proprietary 100

September 2012-- Foundation work October 2012 -- Construction & Erection November 2012 -- Electrical & Interconnection December 2012 – Commissioning Adjacent to I-15 and Route 66

Page 101: Case Studies - Distributed Wind Energy Association

6/15/2013

3.2 MW Cemex Black Mountain Quarry (Apple Valley, CA)

Foundation Windpower LLC – Confidential / Proprietary 101

September 2012-- Foundation work October 2012 -- Construction & Erection November 2012 -- Electrical & Interconnection December 2012 – Commissioning Visible from I-15

Page 102: Case Studies - Distributed Wind Energy Association

6/15/2013

1.0 MW Walmart Distribution Center (Red Bluff, CA)

Foundation Windpower LLC – Confidential / Proprietary 102

May 2012-- Foundation work July 2012 -- Construction & Erection August 2012 -- Electrical & Interconnection September 2012 – Commissioning Visible from I-5

Page 103: Case Studies - Distributed Wind Energy Association

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 103

Walmart Erects Its First Megawatt Wind Turbine In California August 6, 2012 By Todd Woody

http://www.forbes.com/sites/toddwoody/2012/08/06/walmart-winds-up-wind-power-in-california/

As Walmart installed solar panels on its 100th California store in San Diego last week, a 265-foot-high wind turbine was rising

outside one of the retail giant’s distribution centers in the rural reaches of the Golden State. The 1-megawatt, General Electric

turbine in Red Bluff is Walmart’s first such installation and the next stage in the company’s efforts to eventually obtain 100% of

its energy from renewable sources.

“It looks like our renewable energy strategy is going to take a lot of tools,” says Greg Pool, a director of energy for Walmart.

“We are pursuing wind energy and renewable energy at a lot of different levels.” The company has installed micro-turbines a

top light poles at stores in California and Massachusetts that generate between 2 to 3 kilowatts of electricity but Red Bluff is

the first facility that will boast a full-sized wind turbine like those found on wind farms that generate hundreds of megawatts of

power.

The GE wind turbine is expected to supply between 15% and 20% of the Red Bluff distribution’s electricity demand. As with

Walmart’s solar installations, the retailer won’t own the turbine. In this case, Walmart will buy the electricity it generates under

a 15-year power purchase agreement with Foundation Windpower, a Silicon Valley company that installs large turbines for

businesses.

“We’re targeted to save money from day one of the project,” says David Ozment, Walmart’s senior director of energy.

Walmart operates more than 100 distribution centers across the U.S. and the company is looking at the suitability of the sites

for wind power, according to Pool. “Clearly there’s opportunities for us going down the road,” he says.

Just don’t expect to see giant wind turbines go up at your local Walmart. Besides the inevitable headaches that would come

from trying to obtain permits to install a 25-story machine with blades that stretch 250 feet, such a turbine would generate

more electricity than a typical store needs, Pool says. “One thing I would like to see, and this is kind of a missing link in the

wind industry in the U.S., is that there’s not enough medium size turbines in the 400 kilowatt to 800 kilowatt size.”

Page 104: Case Studies - Distributed Wind Energy Association

6/15/2013

2.0 MW Robertson’s Ready Mix / Mitsubishi Cement (Cabazon, CA)

Foundation Windpower LLC – Confidential / Proprietary 104

September 2012-- Foundation work October 2012 -- Construction & Erection November 2012 -- Electrical & Interconnection December 2012 – Commissioning Adjacent to I-10

Page 105: Case Studies - Distributed Wind Energy Association

6/15/2013

3.2 MW Nestle Water / Arrowhead (Cabazon, CA)

Foundation Windpower LLC – Confidential / Proprietary 105

June 2012-- Foundation work October 2012 -- Construction & Erection November 2012 -- Electrical & Interconnection December 2012 – Commissioning Adjacent to I-10

Page 106: Case Studies - Distributed Wind Energy Association

2013-14 Strategy

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 106

Behind the Meter Projects (double the fleet) • More of the same 1-10 MW projects • Expand to new regions

Acquire Medium-Size Development Assets • PURPA niche projects <20 MW • Late stage development

Deliver New Products to Existing Customers • Solar • Storage • Waste heat recovery

Page 107: Case Studies - Distributed Wind Energy Association

Contact Information

For Corporate Information: John Pimentel mobile: 650-269-8933 [email protected]

6/15/2013 Foundation Windpower LLC – Confidential / Proprietary 107

For Sales : Bob Lewis mobile: 415-515-3404 [email protected] www.foundationwindpower.com

Page 108: Case Studies - Distributed Wind Energy Association

Exemplary Distributed &

Community Wind Case Studies Moderator: Lisa Daniels, Windustry

Speakers: Scott Abbett, SED

Alan Axworthy, Northern Power Systems

Roger Dixon, Skylands Renewable Energy Corey Juhl, Juhl Wind

Aaron Morrow, HTWN

Charles Newcomb, Endurance Wind Power

John Pimental, Foundation Wind Power


Recommended