Getting the message across
Case study 10: Little Rays Nursery, Moira, County Armagh, McAvoy
Client: Little Rays Nursery Group
The projectLittle Rays Nursery Group is a multi-site day care operation, with progressive and ambitious owners keen to constantly innovate and expand their extremely successful company. Their strategy has seen the company grow from a single site nursery providing places for a few dozen children, to a multiple location organisation with over 250 child places and over 100 staff. The latest part of their investment strategy required the provision of a new building at their Moira site to accommodate additional places and demand for “after school” services.
The proprietors commissioned local architects Knox & Clayton to design a modern, contemporary building. The architects produced a design of high quality which would normally be constructed using traditional building methods.
Main drivers and constraints�� the most pressing project challenge was that the
Nursery is situated in a very busy location in terms of traffic movements
BenefitsTime: reduction in overall build time from an estimated nine months to just three months. An additional six months of income generationSustainability: 90 per cent reduction in material waste on siteHealth and safety: reduced number of deliveries to site
�� the need to have the facility operational in a very short time period in order to accommodate prospective pupils
�� to maximise the revenue potential. There was only a short window for construction and the building had to be fully operational in time for the busy summer period
�� the building had to be to a high standard of design to “fit” with the existing Grade II listed building and to comply with the strict guidelines set down by the Northern Ireland Environment & Heritage Service.
The solutionThe client’s key requirements were a commencement to completion programme of 14 weeks, zero disruption to the daily operation of the main nursery, a high quality finish both internally and externally, enhanced site safety, and a highly efficient and sustainable building with low running costs.
McAvoy proposed a two-storey steel framed structure with a “Tegral” Rainscreen cladding system on the first floor and stained hardwood timber on the ground floor,
Getting the message across
complemented by a PPC Aluminium framed glazing system and a “Kingspan” insulated roof system.
McAvoy was responsible for the turnkey package including mechanical, electrical and civil works, as well as compliance with statutory guidelines from Social Services.
Key facts�� the scheme was completed in just 12 weeks, reducing
the overall build programme by around six months�� 13 steel-framed modules – up to 14m long by 3.3m
wide and up to 12 tonnes in weight�� module craneage in one phase totalling one day.
Additional benefits of an off-site solution�� off-site construction helped to address the issues of
limited space for material and equipment storage on the site
�� the approach provided safer working conditions on the site
�� a reduction in material waste of around 90 per cent�� quality of design and construction�� fewer deliveries to site.
ContactOrla CorrThe McAvoy Group, 76 Ballynakilly Road, Dungannon, Northern Ireland BT71 6HDEmail: [email protected] (M): 07808 366955