Date post: | 14-Apr-2018 |
Category: |
Documents |
Upload: | norazuree-draman |
View: | 216 times |
Download: | 0 times |
of 32
7/30/2019 Case Study Hlt234- Final
1/32
i
TABLE OF CONTENT
1.0 INTRODUCTION........................................................................................................................... 11.1 Background ............................................................................................................................... 11.2 Problem Statement ................................................................................................................... 1
1.3 Objectives.................................................................................................................................. 22.0 LITERATURE REVIEW ................................................................................................................... 1
2.1 Sewage Treatment Plant ........................................................................................................... 12.1.1 Sewage Treatment Method .........................................................................................12.1.2 Classification of Sewage Treatment Plant.................................................................... 2
2.1.2.1 Attached Growth Processes.......................................................................... 22.1.2.2 Suspended Growth Processes ......................................................................32.1.2.3 Hybrid Processes - Attached Growth with Suspended Growth.................... 3
2.2 Technologies for Sewage Treatment ........................................................................................ 42.2.1 Oxidation Pond (OP)..................................................................................................... 42.2.2 Sequencing Batch Reactor (SBR) ......................................................................... ......... 52.2.3 Extended Aeration (EA)................................................................................................ 72.2.4 Oxidation Ditch (OD) .................................................................................................... 8
7/30/2019 Case Study Hlt234- Final
2/32
ii
2.2.5 Rotating Biological Contactor (RBC)............................................................................. 92.2.6 Membrane Bio Reactor (MBR) ..................................................................................... 9
2.3 Comparison of Sewage Treatment Technologies ................................................................... 102.4 Life Cycle Assessment ............................................................................................................. 11
3.0 METHODOLOGY ........................................................................................................................ 133.1 Site Visits ........................................ ......................................................................................... 133.2 Process Description................................................................................................................. 14
4.0 RESULTS AND DISCUSSION ........................................................................................................ 174.1 Design and Process Review..................................................................................................... 174.2 Collected Data of STP .............................................................................................................. 194.3 Kinetic Parameters .................................................................................................................. 19
4.3.1 Calculations .......................................................................................... ...................... 204.4 Analysis.............................................................................................. ...................................... 25
4.4.1 Actual Removal Efficiency .......................................................................................... 254.4.2 Operational Cost ........................................................................................................25
5.0 CONCLUSION............................................................................................................................. 276.0 REFERENCES.............................................................................................................................. 28
7/30/2019 Case Study Hlt234- Final
3/32
1
1.0 INTRODUCTION
A public Sewage Treatment Plant (STP) located in Cheras has been selected for the case study. This
STP which is serving for residential and commercial areas at Taman Segar Perdana, Cheras is operated and
maintained by Indah Water Konsortium Sdn Bhd (IWK).
1.1 Background
The process type of the selected STP is Sequencing Batch Reactor (SBR) system. The system
is designed to cater for 12,000 population equivalent (PE) which is equals to 2,700 m 3/ day of
average flow. Treated effluent from the STP is discharged into nearby monsoon drain which
eventually flows into Sungai Langat.
The STP is located at the upstream of Bukit Tampoi Water Intake Point, thus the effluent
must comply with Standard A of EQ(S)R 2009 Second Schedule. However, the STP is not designed to
include nutrient removal process since it was constructed before the gazette date of EQ(S)R 2009.
1.2 Problem Statement
Sewage, also known as domestic wastewater is one of the major contributors to river pollution.
Various systems are presented nowadays, which offer sophisticated technologies for high efficiency of
treatment.
Despite the availability of the high technology for sewage treatment, there had been numerous
occasions where water intake points and its treatment facilities had to cease operation as the river
water quality was very poor at intake point. The water treatment facilities were unable to treat it to the
required drinking water quality. This happens due to the fact that the environmental need is not given
precedence in selecting an appropriate sewage treatment system for a new development. In pursuit of
economic growth, cost has always been the number one factor considered in providing sewage
treatment systems to cater for new developments.
7/30/2019 Case Study Hlt234- Final
4/32
2
1.3 Objectives
The objectives of this study are;
i. To determine the efficiency of the selected STP in meeting the required effluentstandard as stipulated by EQA
ii. To review the physical design of selected STP and determine whether the design issufficient to accommodate daily flow connected to the STP.
iii. To compare the physical design of the selected STP to the requirements inGuidelines for Developers Volume IV Design of Sewage Treatment Plant.
iv. To assess whether the plant is operated in an efficient mannerv. To come out with a proposal to operate the plant efficiently, at a lower cost while
still achieving the stipulated standard
7/30/2019 Case Study Hlt234- Final
5/32
1
2.0 LITERATURE REVIEW
2.1
Sewage Treatment Plant
Sewage, also known as domestic or municipal wastewater is created by residential,
institutional, commercial and industrial establishment. In simple word, sewage is defined by human
waste. It includes household liquid waste from toilets, bathrooms, showers, kitchens, sinks and
laundry. In many areas, sewage also includes liquid wastes from industrial and commercial activities.
Sewage treatment is the process of removing physical, chemical and biological contaminants in
sewage prior to discharge into water bodies. It involves physical, chemical and biological process with
the objective to produce treated effluent (fluid) which is considered safe to be discharged to the
environment and also treated sludge (solid) which is suitable for disposal or reuse. Physical unit
operation includes screening, mixing, flocculation, sedimentation, filtration and floatation. In chemical
unit processes, removal or conversion of contaminants is achieved by means of chemical additions or
chemical reactions. This includes precipitation, adsorption and disinfection. Biological unit process is the
method where pollutants are removed through biological activity. Biodegradable organic substances are
converted into gases released to the atmosphere while the cell tissue is removed through settling
process.
2.1.1 Sewage Treatment Method
Sewage treatment method can be categorized into preliminary treatment, primary
treatment, secondary treatment and tertiary treatment.
Preliminary and/ or primary treatment refers to the physical unit process, is the first stage of
treatment which is applied to any sewage. Preliminary treatment includes screening and grinding to
remove debris and rags, grit removal by sedimentation and oil and grease removal by floatation.
Primary treatment removes some of the suspended solids and organic matter through screening and
sedimentation. Effluent from primary treatment still contains high organic constituent.
7/30/2019 Case Study Hlt234- Final
6/32
2
Secondary sewage treatment refers to biological and chemical unit processes.
Biodegradable organic and suspended solids are removed mainly using biological unit processes.
Some secondary sewage treatment also includes disinfection.
Tertiary sewage treatment refers to combination of physical, biological and chemical unit
processes. It includes removal of nutrients, toxic substances such as heavy metal, also further
removal of suspended solids and organics. Tertiary treatment produces effluent of high quality
which is suitable for reuse.
In Malaysia, the focus has been to provide a basic preliminary, primary and secondary
sewage treatment. However, current trend is moving towards providing tertiary sewage treatment
for removal of nutrients including ammonia and phosphorous since the new effluent standard for
sewage (gazetted in December 2009) has become more stringent. Thus, new sewage treatment
plant (STP) which is designed after December 2009 must include nutrient removal process.
2.1.2 Classification of Sewage Treatment PlantThe microorganisms in sewage treatment can be grown in a form of fixed film, suspension
or a combination of both. Hence, biological treatment processes for sewage treatment works can
be classified under one of the followings:
a) Attached Growth Processes
b) Suspended Growth Processes
c) Combined Processes (Hybrid)
2.1.2.1 Attached Growth ProcessesIn an attached growth process, the active microorganisms grow and attach on the
mobile or immobile medium (rock, gravel, slag, plastic or other synthetic materials) that is in
contact with sewage. The organic material and nutrients are removed from wastewater
flowing past the attached growth also known as biofilm. Attached growth process can be
operated as aerobic or anaerobic process. Types of attached growth processes include:
7/30/2019 Case Study Hlt234- Final
7/32
3
a) Trickling Filter (TF)b) Fluidised Bedc) Packed Bed Reactord) Rotating Biological Contactor (RBC)e) Submerged Biological Contactor (SBC)
2.1.2.2 Suspended Growth ProcessesIn a suspended growth process, active microorganisms responsible for treatment
remain in suspension in the sewage by appropriate mixing methods. Their concentration is
usually related to mixed liquor suspended solid (MLSS) or mixed liquor volatile suspended
solid (MLVSS). This system was developed as a result of studies that showed that if sewage is
aerated over a long period of time, the organics in the sewage are removed by the active
microorganisms grow during the process. The most common suspended growth process used
for municipal wastewater treatment is the activated sludge process.
Types of suspended growth processes include:
a) Waste Stabilisation Pond Systemb) Aerated Lagoonc) Conventional Activated Sludge (CAS)d) Extended Aeration (EA)
2.1.2.3 Hybrid Processes - Attached Growth with Suspended GrowthRecent technologies in sewage treatment include combination of attached growth
and suspended growth process in order to obtain best performance and most economical
treatment. Among advantages of Hybrid Process is; it combines the stability and capability to
handle shock loads of an attached growth process and the capability of suspended growth
system in producing high quality effluent.
7/30/2019 Case Study Hlt234- Final
8/32
4
Hybrid processes can be used to upgrade existing attached growth and suspended
growth process, especially in plants with high suspended solids in the final effluent due to
poor solids settlement in the final clarifier.
2.2 Technologies for Sewage Treatment
In Malaysia, primary treatment systems such as communal septic tanks and Imhoff tanks have
been widely used to treat sewage. Other common system is the unreliable low cost secondary system
like oxidation ponds. These systems only treat sewage partially, discharging treated effluent which is
still contains high organic constituent. This creates risk of public health and environmental problems,
especially in urban areas. 38% of public sewage treatment plants in Malaysia are mechanical plants.
Sewage breakdown is accelerated in mechanical plants, by means of mechanical equipments. Common
types of mechanical STP used in Malaysia are Extended Aeration, Sequencing Batch Reactor, Oxidation
Ditch and Conventional Activated Sludge.
2.2.1 Oxidation Pond (OP)
Oxidation Ponds (or Stabilization Ponds) are a popular sewage treatment method for small
communities because of their low construction and operating costs. New oxidation ponds can treat
sewage to Standard B effluent level but require maintenance and periodic desludging in order to
maintain this standard.
OPs may comprise one or more shallow ponds in a series. The natural processes of algal and
bacteria growth exist in a mutually dependent relationship. Oxygen is supplied from natural surface
aeration and by algal photosynthesis. Bacteria present in the wastewater use the oxygen to feed on
organic material, breaking it down into nutrients and carbon dioxide, which are used then by the
algae. Other microbes in the pond such as protozoa remove additional organic and nutrients to
polish the effluent.
Normally, at least two ponds are constructed. The first pond reduces the organic material
using aerobic digestion while the second pond polishes the effluent and reduces the pathogens
7/30/2019 Case Study Hlt234- Final
9/32
5
present in sewage. Sewage enters a large pond after passing through a settling and screening
chamber. After retention for several days, the flow is often passed into a second pond for further
treatment before it is discharged into a drain. Bacteria present in sewage acts to break down
organic matter, using oxygen from the surface of the pond. Oxidation ponds need to be desludged
periodically in order to work effectively. Depending on the design, OPs must be desludged
approximately every 10 years.
OPs require large amounts of land and the degree of treatment is weather dependent. They
are incapable of achieving a good standard of effluent consistently. Nowadays, application of this
treatment system for new developments are ceasing due to the variations of performance and vast
land area requirement.
2.2.2 Sequencing Batch Reactor (SBR)The Sequencing Batch Reactor is a sequential suspended growth (activated sludge)
process, in which all major steps take place in the same tank. SBR system has been successfully
used to treat both municipal and industrial wastewater. In addition to removing TSS and BOD,
SBR can be designed and operated to enhance removal of nitrogen, phosphorous and ammonia.
There are five basic sequences in a cycle, namely;
1) Fill
Fill stage consists of adding the waste and substrate for microbial activity. The fill
phase can include many phases of operation depends on various modes of
control, termed as Static Fill, Mixed Fill and React Fill. Static fill involves waste
introduction of influent without mixing or aeration. In some applications, static fill
will be accompanied by mixed fill stage so that microorganism is exposed
sufficient substrate. In a react fill stage, both mixing and aeration are provided.
2) React (Aeration)
The react stage completes the reactions initiated during fill stage. The react stage
may be comprised of mixing or aeration, or both. The length of react phase can be
controlled by timers, by liquid level controls in a multitank system, or when the
degree of treatment has been achieved.
7/30/2019 Case Study Hlt234- Final
10/32
6
3) Settle
- The separation of liquid-solid occurs during settle phase, which is similar to the
operation of a conventional final clarifier.
4) Decant
- Clarified effluent is decanted during this stage. Various apparatus are available for
decanting purpose. The most common are floating or adjustable weirs.
5) Idle
- Idle phase is the final phase and is only used in multi tanks applications. The time
spent in this phase depends on the time required for the preceding tank to
complete its fill cycle. Sludge wastage is normally done during this stage.
There are two major classifications of SBRs, the intermittently fill & intermittently
decant system and the continuous fill & intermittently decant system. The intermittently fill
system only accepts effluent at specified interval and in general, follow the five step sequence.
There are usually two IF units in parallel. Because this system is closed to influent flow during
the treatment cycle, two units may be operated in parallel, with one unit open for intake while
the other runs through the remainder of the cycles. In the continuous inflow SBR, influent flows
continuously during all phases of the treatment cycle. To reduce short-circuiting, a partition is
normally added to the tank to separate the turbulent aeration zone from the quiescent area.
Advantages and disadvantages of SBR system are summarized in Table below:
Advantages Disadvantages
Equalization, primary clarification (in most
cases), biological treatment, and secondaryclarification can be achieved in a single
reactor vessel.
A higher level of sophistication is required
(compared to conventional systems),especially for larger systems, of timing units
and controls.
7/30/2019 Case Study Hlt234- Final
11/32
7
Advantages Disadvantages
Operating flexibility and control. Higher level of maintenance (compared to
conventional systems) associated with more
sophisticated controls, automated switches,
and automated valves.
Minimal footprint. Potential of discharging floating or settled
sludge during the DRAW or decant phase with
some SBR configurations.
Potential capital cost savings by eliminating
clarifiers and other equipment.
Potential plugging of aeration devices during
selected operating cycles, depending on the
aeration system used by the manufacturer
Potential requirement for equalization after
the SBR, depending on the downstream
processes.
2.2.3 Extended Aeration (EA)
The extended aeration system is one of the modifications of activated sludge process. It is a
complete mix system and provides biological treatment for the removal of biodegradable organic
wastes under aerobic conditions. Air may be supplied by mechanical or diffused aeration to provide
the oxygen required to sustain the aerobic biological process. Mixing must be provided by aeration
to maintain the microbial organisms in contact with the dissolved organics.
Since there is complete stabilization occurs in the aeration tanks, there is no need for
separate sludge digester. Primary settling tank is also not required since the settleable organic solid
is allowed to settle in aeration tank due to long hour of retention time i.e. 18 to 24 hours.
EA is one of the most common systems used in municipal wastewater treatment in Malaysia
since it is easy to operate, capable to handle organic loading and flow fluctuation, also the system
have relatively low sludge yield due to long residence time and sludge age.
7/30/2019 Case Study Hlt234- Final
12/32
8
2.2.4 Oxidation Ditch (OD)
Oxidation ditch system is an extended aeration activated sludge process. It consists of a
"ring or oval shaped channel" equipped mechanical aeration devices, commonly brush aerators.
Screened wastewater enter the ditch is circulated through the channel and aerated. The tank
configuration and aeration and mixing devices promote unidirectional flow in channel, so that the
energy used for aeration is sufficient to provide mixing in a system, with relatively long hydraulic
retention time. High degree of nitrification can be achieved if the basin is sized using appropriate
SRT.
The ditch is built on the surface of the ground and is lined with an impermeable lining. This
allows the wastewater to have plenty of exposure to the open air for the diffusion of oxygen. The
liquid depth in the ditches is very shallow, 0.9 to 1.5 m, which helps to prevent anaerobic
conditions from occurring at the bottom of the ditch. The oxidation ditch effluent is clarified in a
secondary clarifier and the settled sludge is returned to maintain a desirable MLSS concentration.
As in the extended aeration system, OD system also produces low sludge volume due to
long residence time in the ditch. However, this system requires relatively larger land area than
other types of activated sludge process.
Advantages Disadvantages
Long hydraulic retention time and complete
mixing minimize the impact of a shock load or
hydraulic surge.
Effluent suspended solids concentrations are
relatively high compared to other
modifications of the activated sludge process.
Produces less sludge than other biological
treatment processes owing to extended
biological activity during the activated sludge
process.
Requires a larger land area than other
activated sludge treatment options. It makes
this system less feasible in urban areas where
land acquisition cost is relatively high.
Energy efficient operations result in reduced
energy costs compared with other biological
treatment processes.
7/30/2019 Case Study Hlt234- Final
13/32
9
2.2.5 Rotating Biological Contactor (RBC)
Rotating Biological Contactors (RBCs) are mechanical secondary treatment systems. The
system comprises of a series of closely spaced circular discs, normally made from plastic material.
The disks are partially submerged and slowly rotated in sewage. Organic pollutants are breakdown
and stabilized by the bacteria and microorganisms present in sewage that grows on the rotating
disks.
As the disks rotate, the micro-organisms obtain oxygen from the atmosphere. As the micro-
organisms grow, they build up on the media until they are strip off due to shear forces provided by
the rotating disks in sewage. Effluent from the RBC is then passed through final clarifiers, where the
micro-organisms in suspension settle as sludge. The sludge is withdrawn from the clarifier for
further treatment.
RBC units are suitable where land area is restricted. They are quite and consistently produce
a high quality effluent. Because they are modular they are also suitable for a staged development.
Operations and maintenance costs are lower than other forms of mechanical treatment.
2.2.6 Membrane Bio Reactor (MBR)
Membrane Bioreactors combine conventional biological treatment processes with
membrane filtration to provide an advanced level of organic and suspended solids removal. This
system can also provide an advanced level of nutrient removal when designed accordingly.
In MBR system, the membranes are submerged in an aerated biological reactor. The
porosities of the membranes range from 0.035 microns to 0.4 microns, depending on the
manufacturer. This level of filtration produces high quality of effluent to be drawn through the
membranes while eliminating the typically used sedimentation and filtration processes in other
types of system. Because the need of sedimentation is eliminated, the biological process can be
operated at a higher mixed liquor concentration. This significantly reduces the number and size of
tankage required, thus allowing many existing plant to be upgraded without adding new tanks.
7/30/2019 Case Study Hlt234- Final
14/32
10
The distinct advantages of MBR over EA and SBR system make the system a favourable
option especially where land area is limited and plant located in environmentally sensitive area.
However, due to high cost of equipments, it is not the appropriate technology for every
application.
Other benefits of MBRs include:
Hydraulic Retention Time (HRT) of 4-8 hours vs 16-24 hours Solids Retention Time (SRT) of 15-365 days, can vary based on flow without negative
process impact
MLSS of 10,000-15,000 mg/L Sludge Yield of 20-40% less than conventional Footprint of 25% Conventional Plant Modular expandability Highest quality effluent Capable of meeting new standards for nutrient removal Less susceptible to upsets due to flow variations Less odour Simple, yet sophisticated
2.3 Comparison of Sewage Treatment Technologies
Factors considered in selecting an appropriate system for a proposed new development are
capital cost, treatment efficiency, sizing of the system which is related to land area requirement, ease
of operation and maintenance, as well as the O&M cost.
7/30/2019 Case Study Hlt234- Final
15/32
11
Table 1 : Comparison of Technologies for the Wastewater
Average Removal Efficiency
Treatment System BOD
(%)
COD
(%)
SS
(%)
Ammonia
(%)
Total N
(%)
Total P
(%)
Oxidation Pond 75 - 85 65 - 80 70 - 80 < 50 < 60 < 35
Sequencing Batch
Reactor (SBR)
85 - 95 80 - 90 93 - 97 > 80 < 60 < 35
Extended aeration (EA) 90 - 97 83 - 93 87 - 93 > 80 < 60 < 35
Membrane Bio Reactor
(MBR)
99 99 99.9 99.2 99 96.6
Conventional Activated
Sludge (CAS)
85 - 93 80 - 90 87 - 93 > 80 < 60 < 35
Rotating Biological
Contactor (RBC)
88 - 95 83 - 90 87 - 93 65 - 85 < 60 < 35
High Rate Trickling Filter 80 - 90 70 - 87 87 - 93 < 50 < 60 < 35
2.4 Life Cycle Assessment
Life cycle assessment (LCA) is an appropriate methodology for assessing the sustainability of a
sewage treatment plant design. ISO 14040:2006 describes the principles and framework for life cycle
assessment (LCA). Environmental costs and benefits of different sewage treatment technologies and
standards can be compared quantitatively using the LCA method.
Factors considered in comparing the technologies are:
Potential Negative Impact Factors Contributing to the ImpactNonrenewable energy High sludge production, High energy consumption, Land use
Global warming impact High sludge production, CO2 produced (directly related to the energy
consumption)
Acidification NOx produced
Eutrophication NOx produced
7/30/2019 Case Study Hlt234- Final
16/32
12
High Medium Low
Sludge production CAS SBR MBR, EA, OD
Energy consumption MBR, CAS, EA SBR OP
Land use OP, OD, CAS EA MBR, SBR
CO2 produced MBR, CAS, EA SBR OP
NOx produced CAS, EA, OD SBR MBR
Potential Negative Impact Nonrenewable
energy
Global warming
impact
Acidification Eutrophication
Type of System
Oxidation Pond (OP) ++ +++ + +
Sequencing Batch Reactor
(SBR)
++ ++ ++ ++
Extended Aeration (EA) ++ + + +
Oxidation Ditch (OD) + + ++ ++
Membrane Bio Reactor
(MBR)
++ + +++ +++
Note:
+++ - Most favourable/ least negative impact
++ - Intermediate grade
+ - Least favourable/ most negative impact
7/30/2019 Case Study Hlt234- Final
17/32
13
3.0 METHODOLOGY3.1 Site Visits
Site visit has been conducted on 26th January 2011. During site visits, dimensions of key
process units from inlet pump stations to the SBR tank were measured. Layout plan of the SBR
plant is shown in drawing in Appendix A.
The plant has been designed to treat flow equivalent to 12,000PE and the current PE loading
is 11,305PE (94%). Based on MS1228, 1PE is equals to 0.225m3/day/capita, thus the plant receives
flow equivalent to 2,544m3/day at average. Peak flow is calculated using following equation from
MS1228:
Qpeak = PFF x Qave
Where PFF = 4.7 PE x (PE / 1000)-0.11
= 3.58
Thus, Qpeak = 3.58 x 2,700m3/day
= 9,655m3/day
Since the STP is located in water catchment area, the design was designed to meet Standard
A effluent based on Guidelines for Developers Volume IV (Sewage Treatment Plant). It is important
to note that the STP was designed in year 2002, before the gazette date of Environmental Quality
(Sewage) Regulation: 2009. Thus, design of this plant does not include for tertiary treatment to
remove nutrient and further removal of suspended solids and organics.
7/30/2019 Case Study Hlt234- Final
18/32
14
3.2 Process Description
Raw sewage from the last manhole of Taman Segar Perdana enters the inlet works via two (2)
mechanical coarse screen of 25mm clear opening to collect the rubbish. The primary screen is controlled
by one (1) unit of manual penstock. After screening process, the raw sewage flows into a pump sump
and periodically pumped by two (2) raw sewage pumps (1 duty, 1 standby). These pumps transfer the
raw sewage via 350mm DI pipe to the next process unit.
Before reaching the single grit removal chamber, the sewage will flow through the secondary
screen chamber which comprises of two (2) units of mechanical fine screens of 12mm bar spacing. The
collected rubbish is then transferred down to the collection bin via 500mm wide conveyor system.
Concurrently, sewage flows from the top level and undergoes aeration at the grit chamber. At selected
intervals, the airlift pump will pump up the settled grit to a collection sump. Then, the pre-treated
sewage flows out to the grease chamber whereby the floating grease is removed by the surface grease
scrapper conveyor. Finally, the pre-treated sewage flows into the distribution chamber at the head of
the reactor tanks. The flow of the pre-treated sewage into the reactor tanks is controlled by two (2)
numbers of motorised penstocks. Periodically, the flow will be released out into the SBR tank.
There are two (2) SBR tanks in this plant. SBR is an activated sludge system whereby the
biological reaction, solid-liquid removal and surface liquid (effluent) removal are all carried out in a
single tank by setting specific sequences. The SBR tanks operate in the following sequences:
1) Fill and aerate Sewage is intermittently filled in the tanks and aerated for two (2) hours2) Settle Aeration stops and suspended solids settle leaving a clear liquid at the top of the
sludge blanket
3) Decant Clear liquid (effluent) is decanted with a maximum of 30% of the total tankvolume. Decant depth for the reactors are 1.2 m from top water level.
4) Idle Sludge is pumped out at the end of the cycle
7/30/2019 Case Study Hlt234- Final
19/32
15
The above four (4) cycles are known as one (1) cycle which takes four hours (Fill & aerate - 2
hours, settle - 1 hour, decant & idle - 1 hour) to complete. Thus, six (6) cycles are performed in a reactor
tank per day. The waste activated sludge (WAS) pumped from the SBR tank is transferred into a circular
gravity sludge thickener tank. Sludge is expected to thicken to about 1% dry solid content in the gravity
thickener tank before it is transferred out to the drum thickener. Polymer is added prior to entering the
drum thickener to aid the flocculation of the sludge.
The dryness of the produced cake from drum thickener is typically from 8 10% and further
treated at the sludge drying beds. So far, the mechanical sludge facilities at this plant are not fully
utilized due to small amount of sludge generated by the SBR reactor. Thus, the WAS pumped out during
idle phase is bypassed to sludge drying bed and dried for 28 days. Filtrate from the drying beds is
returned to the inlet works for treatment. Every 28 days, the sludge drying beds will be cleared out and
the sludge cake is sent to an approved site for disposal as solid waste.
Meanwhile, effluent extracted from the SBR tanks is transferred to a disinfection chamber. A
flow measurement facility complete with a non-contact ultrasonic level meter is provided for the
effluent.
Flow diagram of the SBR plant is shown in Figure 1.
7/30/2019 Case Study Hlt234- Final
20/32
16
Figure 1 : Flow Diagram of SBR System
Inlet Pump
Station
Incoming Sewage
Secondary
Screen Chamber
Grit Removal
Chamber
Grease Removal
Chamber
Sludge Thickening
Tank
Mechanical Sludge
Dewatering
Sludge Drying
Bed
Final Effluent
Chamber
Treated Effluent
Screened Raw
Sewage
WAS WAS
Thickened
Sludge
Filtrate
Sludge Cake for
Disposal as Solid
Waste
Stabilized Sludge
SBRTank 1
SBRTank 2
7/30/2019 Case Study Hlt234- Final
21/32
17
4.0 RESULTS AND DISCUSSION
4.1 Design and Process Review
Design and process review are conducted in order to determine whether each of the key
process units at the plant has been designed sufficiently in order to meet the stipulated standard. Based
on the Guidelines for Developers Volume IV (Sewage Treatment Plant), the design influent and effluent
values adopted in the design of a Standard A plant are tabulated in Table below:
Table 2 : Design Influent and Effluent Values
Effluent Value (mg/l)Parameter Design Influent
Value (mg/l) Design Absolute**
Biochemical Oxygen Demand (BOD5) 250 10 20
Suspended Solids (SS) 300 20 50
Chemical Oxygen Demand (COD) 500 60 120
Ammoniacal Nitrogen (AMN) 30 5 50
Oil and Grease (O&G) 50 2 20
Total Nitrogen (TN) 50 n/a n/a
Total Phosphorous (TP) 10 n/a n/a
** Absolute value is the stipulated effluent standard that the plant must comply at all times.
Based on measurement and information provided by IWK, dimensions of main process units
are shown in Table 3.
7/30/2019 Case Study Hlt234- Final
22/32
18
Table 3 : Dimension of Main Process Units
Tank Nos Dimension Volume
(m3)
HRT @
Qave
HRT @
Qpeak
Limits in
Guidelines
a. Wet Well 1 6.5m (l) x 2.2m (w) x
4.3m (d)
*Effective depth = 0.9m
12.87 7 min - Max. 30min @
Qave
b. Grit Removal
Chamber
1 V1 + V2 + V3 = 9.53m3 +
10.72m3
+ 0.40m3
**
20.65 11 min 3 min Min. 3min @
Qpeak
c. Grease Removal
Chamber
2 5.0m (l) x 1.0m (w) x
2.2m (d)
22 12 min 3 min Min. 3min @
Qpeak
d. Reactor Tank 2 27.5m (l) x 10.7m (w) x
4.0m (d)
2,354 20.9 hr - 18 24 hr @ Qave
* Effective depth is the difference between start and stop level of pumps
** Grit removal chamber of rotary type as shown in figure below
From the table above, it is found that the provided tank volumes of key process units are sufficient to cater
for the hydraulic load at which the plant has been designed to.
V2
V1
V3
7/30/2019 Case Study Hlt234- Final
23/32
19
4.2 Collected Data of STP
Data collected during site visit to the STP are tabulated in Table 4 below.
Table 4 : Influent and Effluent Sampling Result
Parameter Concentration (mg/l)
BOD5in 159
BOD5eff 12
CODin 338
CODeff 36
SSin 138
SSeff 14
O&Gin 32
O&Geff 7
NH3Nin 30
NH3Neff 17
MLSS 3,300
MLVSS ~ 0.7 X 3,300 = 2,310
4.3 Kinetic Parameters
Equations used are:
aveQ
VHRT ====
XV
SQ=M/F
0
rw
cXQ
VX ====
d
c
K
1 ++++====
V
QS=V
0
L
7/30/2019 Case Study Hlt234- Final
24/32
20
Assumptions are made based typical value of kinetic coefficient for the activated sludge process from
Metcalf & Eddy, 1991, as per tabulated in Table 5.
Table 5 : Typical kinetic coefficients for activated sludge type of process for domestic wastewater
ValueCoefficient Basis
Range Typical
K d-1
2 - 10 5
Ks mg/L BOD5
mg/L COD
25 100
15 - 70
60
40
Y mg VSS/mg BOD5 0.4 - 0.8 0.6
kd d-1 0.025 0.075 0.06
fd unitless 0.06 0.20 0.12
Yn g VSS/ g NH4-N 0.10 0.15 0.12
kdn g VSS/ g VSS.d 0.05 0.15 0.08
4.3.1 Calculations
Calculation of HRT
Provided volume of aeration tank = 2,354 m3
Average Flow = 2,700m3/ day
hr21hr9.20day1
hr24
day/m2700
m2354HRT
3
3
========
Calculation of SRT
MLSS, X = 3,300 mg/l
Underflow concentration, Xr = 10,000 mg/l
Volume of Sludge Wastage, Qw = 43.2 m3/ day (based on WAS pump capacity, 8 l/s,
runs 15 minutes per cycle, thus 1.5 hour per day)
days18l/mg000,10day/m2.43
l/mg300,3m354,2
3
3
c ====
====
7/30/2019 Case Study Hlt234- Final
25/32
21
Calculation of sludge yield
Sludge wastage/ produced, Qw = 43.2m3/day
Sludge concentration, Xw = 10,0000 mg/l
kg Sludge Produced /day = 432 kg/ day
kg BOD Removed / day = day/kg6481000
day/m700,2l/mg)10250(3
====
Thus, Y = 67.0day/kg648
day/kg432==== kg sludge produced/ kg BOD5 removed
Calculation of oxygen requirement
Ro = Q (S0 S) 1.42 PX, VSS + 4.33 Q (NOx)
PX ,VSS =QY S0 S
1 + Kd SRT+
fd
kd QY S0 S SRT
1 + Kd SRT+
QYn NOx
1 + Kdn SRT
Assumefd = 0.15 g/ g
kd = 0.06 d-1
Yn = 0.12 g VSS/ g NH4-N
kdn = 0.08 g VSS/ g VSS.d
NOx = (30 5) mg/l = 25mg/l
PX,VSS = 208.73 + 33.81 + 3.32 = 245.85 kg/day
Thus,
Ro = [(2,700m3/day) (250 10)mg/l (1kg / 10
3g)] [1.42 (245.85kg/day)]
+ [4.33 Q (NOx)]
= (648 344.41 + 292. 28) kg O2/ day
= 595.87 kg O2/ day
Aeration tank/ tank
Aeration time / cycle = 2.0 hr
No. of cycles/ day = 6
7/30/2019 Case Study Hlt234- Final
26/32
22
Total aeration time = 12 hr/ day
Average oxygen transfer rate = hr/kg65.49=12hr/day
day/Okg595.872
Air weight = 1.201 kg/m3
% of oxygen = 0.232
O2 transfer efficiency of Unifflex diffuser = 0.15
Air volume required = 49.65 kg/hr / (1.201 kg/m3
x 0.232 x 0.15)
= 1,188 m3/ hr or 19.8 m3/min
Based on Guidelines for Developers Volume IV,
Oxygen requirement for SBR = Cycle TimeAeration Time 2.0kgO2 per kg BOD removed
BOD to remove = 648 kg/day
Air volume required = (4 hr / 2 hr) x (2.0 kg O2 x 648 kg/day)
= 2,592 kg/day or 108 kg/hr
= 108 kg/hr / (1.201 kg/m3 x 0.232 x 0.15)
= 2,584 m3/ hr or 43.07 m
3/min
Calculation of F/M ratio
1
3
30 day09.0
l/mg3300m354,2
l/mg250day/m700,2
XV
SQM/F
====
====
====
Calculation of specific growth rate
Assume kd = 0.06 d-1
11 d12.0=d06.0+days18
1=
Calculation of BOD volumetric loading
VL = day/m/kg29.0=)kg/g10)(day/m2354(
)l/mg250)(day/m700,2( 333
3
7/30/2019 Case Study Hlt234- Final
27/32
23
Calculation of Nutrient Requirement
BOD : N : P = 100 : 5 : 1
Based on Table 2,
BOD = 250 mg/l
TN = 50 mg/l
TP = 10 mg/l
Based on concentrations above, BOD : N : P is 25 : 5 : 1, which indicates that sufficient nutrient is
available in the influent
7/30/2019 Case Study Hlt234- Final
28/32
24
Table6:Comparisonof
HLT234toDesignGuidelines
Guidelines
M
etcalf&Eddy
HLT234
MLSS,mg/l
3,0004,5
00
2,0005,000
3,300mg/l
MLVSS,mg/l
-
-
0.7x3,300mg/l=
2,310mg/l
F/MR
atio,
kgBOD/kg
MLVSSd-1
0.050.3
0
0.040.10
0.09
BODvolumetricloading
kgBOD/m3.d
-
0.10.3
0.29
HRT,
hr
18-24
15-40
21
SRT,days
1030da
ys
1030days
18days
SludgeYield,
kgSludge/
Kg
BOD5
load
0.751.1
0
0.40.8
0.66
CycleTime,
hr
48hrs
-
4
Decantdepth,m
Max1.0
-
1.2m
Decanttime,
hr
-
-
1
DecantVolume,%
30%
30%
30%
OxygenVolumeRequire
d,
kg/hr
CycleTime
AerationTime
2.0
kgO2p
erkgBODremoved
=108kg/hr
Q(S0S)
1.42PX,VSS+4.33Q(NOx
)
=49.65kg/hr
n/a
OxygenVolumeRequire
d,
m3/min
43.06m3/m
in
19.8m3/min
45m3/min
7/30/2019 Case Study Hlt234- Final
29/32
25
4.4 Analysis
4.4.1
Actual Removal Efficiency
BOD removal = [(So - S) / So]*100%BOD removal = [(159 - 12)mg/l /159]*100%
= 92.4 %.
4.4.2 Operational Cost
Electricity cost is the highest contributor to the total O&M cost of a STP. Electricity
cost per month for HLT234 is estimated based on M&E equipments data as shown below in
Table 7.
Table 7 : List of Mechanical Equipments in HLT234
Equipments Nos Capacity Total
Capacity
Power
(kW)
Head
(m)
RSP 2 (1 duty, 1 standby) 117.5 l/s 117.5 l/s 14.0 10.0
Air Blower 4 (3 duty, 1 standby) 15.0 m3/min 45.0 m
3/min 15.0 n/a
WAS pump 2 (1 duty, 1 standby) 8.0 l/s 8.0 l/s 1.3 6.0
Primary Mechanical Screen 2 - 1.1 n/a
Secondary Mechanical
Screen
2 - 0.75 n/a
7/30/2019 Case Study Hlt234- Final
30/32
26
Calculation of Electricity Consumptions
i) Raw Sewage Pump1 unit x 14.0 kWh x 24hr x 30 day = 10,080 kW/ month
ii) Air Blower3 units x 15.0 kWh x 12 hr x 30 day = 16,200 kW/ month
iii) WAS Pump1 unit x 1.3 kWh x 1.5 hr x 30 day = 58.5 kW/ month
iv) Primary Mechanical Screen2 units x 1.1 kWh x 2hr x 30 day = 132 kW/ month
v) Secondary Mechanical Screen2 units x 0.75 kWh x 2hr x 30 day = 90 kW/ month
Total kW usage per month = 27,280.5 kW/ month
TNB Tariff = RM 0.366 (Industrial)
Total electricity cost = RM 9,984.66
7/30/2019 Case Study Hlt234- Final
31/32
27
5.0 CONCLUSION
It is concluded that the design of HLT234, a sequencing batch reactor plant at Taman Segar Perdana
is sufficient to treat sewage influent of 2,700 m3 per day to meet EQ(S)R. The plant is operated at an
operational cost of approximately RM 10,000 per month.
7/30/2019 Case Study Hlt234- Final
32/32
6.0 REFERENCESMetcalf & Eddy, Inc. Wastewater Engineering: Treatment, Disposal, Reuse. 3
rdedition. New York: McGraw
Hill.
U.S. EPA. EPA Design Manual, Summary Report. Sequencing Batch Reactors. EPA/625/8-86/011, August
1986.
U.S. EPA. Wastewater Technology Fact Sheet. Sequencing Batch Reactors. EPA 932-F-99-073 September
1999.
L. K. Wang, N. K. Shammas, and Y. T. Hung. Handbook of Environmental Engineering Volume 9:Advanced
Biological Treatment Processes. New York: Humana Press
Ministry of Housing and Local Government. Guidelines for Developers Volume IV : Sewage Treatment Plant
https://www.iwk.com.my