+ All Categories
Home > Health & Medicine > Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Date post: 11-Jan-2017
Category:
Upload: interphex-events
View: 119 times
Download: 1 times
Share this document with a friend
59
Transcript
Page 1: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability
Page 2: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

PRESENTERS

BRIAN LIPKO, PE Senior Project Manager Hargrove Life Sciences

BRIAN TERMINE, PE Maintenance Engineering Manager GlaxoSmithKline

STEVE WALTER, CPIP Process Systems Technology Hargrove Life Sciences

Page 3: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

ACKNOWLEDGMENTS

RANDY MINTO, PE, Program Manager, GlaxoSmithKline

DAN D’AQUILA, PE, Director of Engineering & Validation, GlaxoSmithKline

ED STEVENS, Engineering Manager, GlaxoSmithKline

ALEX TANJUTCO, Validation Project Manager, GlaxoSmithKline

TED DOMBROWSKI, Senior Project Engineer, Arcadis (on behalf of GSK)

ROBERT HOEPPNER, Project Executive, Henderson Constructors, Inc.

MIKE BILLUPS, Project Manager, Henderson Constructors, Inc.

Page 4: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Introduction

AGENDA

Execution Results

Background Objectives Challenges

Benefits Lessons Learned

Summary

Design Construction Qualification

Page 5: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Introduction

INTRODUCTION

Execution Results

Background Objectives Challenges

Benefits Lessons Learned

Summary

Design Construction Qualification

Page 6: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

6

CTM (Clinical Trial Materials)

Facility

Manufactures purified drug substances for

clinical trials worldwide

INTRODUCTION: BACKGROUND

Page 7: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

7

INTRODUCTION: BACKGROUND

Existing HPW & WFI systems obsolete

Parts no longer available

Insufficient capacity for future expansion or production increase

Costly systems not energy efficient

Increased plant downtime risk due

to insufficient equipment reliability

Page 8: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

8

INTRODUCTION: BACKGROUND

Project Scope

REPLACE 2 OBSOLETE WATER SYSTEMS

HPW High Purity Water

WFI Water for Injection

New Reliable System Design

Supply HPW to Biopharm Development Pilot Plant

Change System Configuration from 3 to 2 Pumps

Replace WFI Control Panel Install Redundant VC Stills

Page 9: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

INTRODUCTION: OBJECTIVES

DELIVER SUSTAINABILITY

REDUCE WATER & ENERGY USAGE

REPLACE OBSOLETE EQUIPMENT

PROVIDE RELIABILITY THROUGH REDUNDANCY

NO IMPACT TO ON-GOING OPERATIONS

INCREASE SUPPLY &

STORAGE CAPACITY

Page 10: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

INTRODUCTION: OBJECTIVES RELIABILITY THROUGH REDUNDANCY

10

re·dun·dant serving as a

duplicate for preventing

failure of an entire system

HPW WFI Multi-Media Filters Softeners Carbon Filters RO/CDI Skid Tank Nitrogen

Filters Distribution Pumps

Vapor Compression Stills

Tank Vent Filters Distribution

Pumps

No Unplanned Downtime

Page 11: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

11

INTRODUCTION: OBJECTIVES

Generation and Storage Capacity

Insufficient during Maintenance Activities

Need to be Adept & Flexible

Accommodate Emerging Technologies in Manufacturing

Generation Capacity Bottlenecked

Required Daily Water Usage Planning Activities

CLINICAL TRIALS

HPW

WFI

INCREASE SUPPLY & STORAGE CAPACITY

Page 12: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Reverse Osmosis Pre-Treatment System

(Built c.1987)

12

FRP High Purity Water Storage Tank

2000 Gallon (Built c.1987)

INTRODUCTION: OBJECTIVES OBSOLETE EQUIPMENT

Page 13: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

13

Multi-Effect WFI Still (5 MEF)

(Built c. 1987)

(3) WFI Distribution Pumps One pump on each floor (Spares in Warehouse)

INTRODUCTION: OBJECTIVES OBSOLETE EQUIPMENT

Page 14: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Softener Regeneration

Brine Tank

14

Softener Regeneration Salt Pellets Palletized 40 lb bags

Consumed 400-800 lb/day

INTRODUCTION: OBJECTIVES OBSOLETE EQUIPMENT

Page 15: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

1

INTRODUCTION: OBJECTIVES

SC Microbial Microbial Fermentation Media Prep Microbial Purification Buffer Prep

Building 5 Building 38

Biopharm GMP Clinical Trial Production

Manufacturing

Building 4

Biopharm Development

Pilot Plant

NO IMPACT TO ON-GOING OPERATIONS

Safety Assessment

Manufacturing

Page 16: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

16

INTRODUCTION: CHALLENGES

WFI CONTROL

PANEL CHANGE

OUT

IMPACT TO ON-GOING

OPERATIONS: PHASED

APPROACH

VENDOR COMMITMENT

FOR EQUIPMENT DELIVERY

INSTALL WINDOW

& AVAILABLE DOWNTIME LIMITED

SPACE

Page 17: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

17

INTRODUCTION: CHALLENGES

Generation Equipment

Access

Utilities

BUILDING 38

EXISTING MECHANICAL

ROOM

Page 18: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Introduction

INTRODUCTION

Execution Results

Background Objectives Challenges

Benefits Lessons Learned

Summary

Design Construction Qualification

Page 19: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

SUSTAINABILITY EVALUATION

PROJECT LOCATIONS & CONSTRAINTS EQUIPMENT

EVALUATION

VISIT OTHER GSK SITES

19

EXECUTION: DESIGN

Page 20: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Site 1: Christ System

20

Site 2: Siemens: PreVUE®

Other Site Tours (Gemba)

EXECUTION: DESIGN

Page 21: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

21

Options Decision

HPW

Single Pass vs. Double Pass RO Single Pass

Polisher vs. None Install Polisher

Carbon vs. Bi-sulfite vs. UV Light Filtration Carbon Filtration

Service Type vs. Back Washable Carbon Filters Back Washable

Hot Water vs. Chemical Sanitization Hot Water Sanitization

FRP vs. SS HPW Storage Tank SS Tank

High Recovery RO vs. None High Recovery RO

Nitrogen Blanket on Storage Tank vs. None Nitrogen Blanket

Bulk Brine vs. Day Tank Both

Redundant vs. Single Storage Tank Filters Redundant Filters

EQUIPMENT EVALUATION

EXECUTION: DESIGN

Page 22: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

22

Options Decision

WFI

Vapor Compression vs. Multi Effect Vapor Compression

Separate Pump per Floor vs. Redundant Pumps Redundant Pumps

Redundant vs. Single Storage Tank Filters Redundant Filters

EQUIPMENT EVALUATION

EXECUTION: DESIGN

Page 23: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

23

SUSTAINABILITY EVALUATION

Systems Design

Evaluations

Operating Cost

Comparisons

Wastewater Volume

Reduction

EXECUTION: DESIGN

Page 24: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Only Feasible Solution:

Utilize existing Courtyard between B5 & B38 (14’ W x 110’ L)

24

Project Locations Limited

PROJECT LOCATIONS & CONSTRAINTS

EXECUTION: DESIGN

Page 25: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Top of Courtyard Looking NORTH

25

Bottom of Courtyard Looking SOUTH

EXECUTION: DESIGN PROJECT LOCATIONS & CONSTRAINTS

Page 26: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

26

2-STORY MECHANICAL ROOM DESIGN

EXECUTION: DESIGN

Page 27: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

27

EXECUTION: DESIGN 2-STORY MECHANICAL ROOM DESIGN

Page 28: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

28

Construct Addition

& Install

HPW System

Install WFI Pumps

& Control Panel

Demo Old HPW System

Install WFI VC

Stills

Demo Old Still

Phased Construction/ Qualification

Approach

PHASE 1 PHASE 1A PHASE 2

NO IMPACT TO ON-GOING OPERATIONS

EXECUTION: DESIGN

Page 29: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Construct 2-Story Addition for HPW

29

Between 2 Buildings Limited Access Adjacent GMP Operations

EXECUTION: DESIGN PHASE 1

Page 30: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

30

EXECUTION: DESIGN PHASE 1

Construct 2-Story Addition for HPW

Between 2 Buildings Limited Access Adjacent GMP Operations

Page 31: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

31

EXECUTION: DESIGN SYSTEM CONSIDERATIONS

Choose Vendor that Supplies Customizable PLC Controllers: Normalized Differential Pressure to determine cleaning interval Softener Regeneration is based on Hardness Softener Regeneration Rinse is based on Conductivity

Bulk Brine Tank System

Energy Efficiency

S3 Technology & Pump VFDs

Reduce Water Usage

S3 Technology & High Recovery RO

WFI: Pump Schemes

Fathom Software Complexity of Flows – Multiple Floors

Online TOC, Conductivity &

Microbial Detection

Page 32: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

32

EXECUTION: DESIGN PHASE 1A - WFI

No Redundancy

Difficult to Control Flow

Maintenance requires

Shutdown

Single Pump affected Tank Temp and other

Floor Availability

OLD SYSTEM

Page 33: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

33

EXECUTION: DESIGN PHASE 1A - WFI

Generated from Fathom Modeling

NEW SYSTEM

Redundancy

Control From Worst Case

Pump Maintenance = No downtime

VFD’s to manage fluctuations

Individual Loops can be Isolated

Page 34: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

34

EXECUTION: DESIGN WFI CONTROL PANEL

Desktop Simulation

Only

20 Year Old

System

No ‘Plan B’

Instruments = 86 I/O Points = 106 GREATEST RISK

Extensive Pre-planning

Page 35: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

35

EXECUTION: DESIGN HPW GENERATION SUMMARY

Page 36: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

36

EXECUTION: CONSTRUCTION TIMELINE

Week 1 25 33 41 49 57 65 73 81 89 97

Phase 2 Begins Shut Down & Phase 1 End

4/21/14

Shut Down Begins

12/16/13

Construction Begins

4/1/13

PHASE 2

PHASE 1A 7 WK

CONSTRUCTION AWARD

DESIGN 24 WEEKS

PHASE 1

9 105 17

Construction Complete

6/16/14 Design KO 6/4/12

CM Award 11/5/12

8 WKS

PROCUREMENT & DOCUMENTS 29 WEEKS

44 WEEKS

CONSTRUCTION

9/3/12 POs

Page 37: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

37

EXECUTION: CONSTRUCTION Existing

Courtyard

Stone & Soil Excavation

1st Floor Slab Installation

PHASE 1

Page 38: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Maintain Building Integrity during Removal of Building Façade

38

EXECUTION: CONSTRUCTION TEMPORARY PROTECTION

Removal of the façade exposed Utilities above occupied space inside

Installed Temporary Partition Walls in Active Areas & Issued Change Control

Updated Qualified Flow Drawings Continually During Construction

Page 39: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

39

EXECUTION: CONSTRUCTION

Large Crane due to Limited Access

Building Structure Construction

PHASE 1

Page 40: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

40

EXECUTION: CONSTRUCTION

Installation of HPW Equipment

PHASE 1

Page 41: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

41

EXECUTION: CONSTRUCTION

Outdoor Bulk Brine Tank 2nd Floor HPW

PHASE 1

Page 42: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

42

EXECUTION: CONSTRUCTION

2nd Floor Dual Softeners & Multi-Media Filters

2nd Floor Dual Carbon Filters

PHASE 1

Page 43: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

43

EXECUTION: CONSTRUCTION

1st Floor Dual RO Skids

1st Floor HPW Tanks & Pumps

PHASE 1

Page 44: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

44

EXECUTION: CONSTRUCTION

B38 Mechanical Room New WFI Pumps

B38 Mechanical Room Existing WFI Pumps to Demo

PHASE 1A

Page 45: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

45

EXECUTION: CONSTRUCTION

B38 Mechanical Room HPW System to Demo

Access Doors to B38 Mechanical Room

PHASE 2

6’6”

8’8”

Page 46: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

46

EXECUTION: CONSTRUCTION

New WFI Stills in B38 Mechanical Room

New WFI Stills at FAT Sugarland, TX

PHASE 2

Page 47: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

47

EXECUTION: CONSTRUCTION LEVERAGED QUALIFICATION APPROACH

Vendor Qualification Documents Reformatted to GSK Standards PRIOR to Factory Acceptance Test (FAT)

PEOPLE

Qualification Team: Validation Engineering Facilities QA

EQUIPMENT CHECK

Resolve issues prior to shipment Equipment Still at Factory

DURATION

Reduced Document Development Time by 3 weeks Duplicated FAT during SAT

Page 48: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

48

EXECUTION: CHALLENGES CONSTRUCTION

Constrained Area within the Middle of Operating Buildings

Delivery of High Purity Equipment

S3 Design Not Turn-Key

Polisher Tank Delivery

Sartorius Filter Housings

Installation of High Purity Equipment

DI Tank Filters

Failure of PQ1 Testing (Plan B)

Page 49: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

49

EXECUTION: QUALIFICATION VALIDATION DOCUMENTATION

1 Validation Master Plan (HPW/WFI) including 3 Validation Interim Reports

5 User Requirement Specs

14 Change Controls

27 Installation Operation Qualification Documents

10 Standard Operating Procedure Updates

22 Functional Design Specifications

3 Factory Acceptance Test / Site Acceptance Test

2 Design Qualifications

EXT

EN

SIV

E D

OC

UM

EN

T M

AN

AG

EM

EN

T

Page 50: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

Introduction

INTRODUCTION

Execution Results

Background Objectives Challenges

Benefits Lessons Learned

Summary

Design Construction Qualification

Page 51: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

51

RESULTS: BENEFITS

INCREASED SUPPLY

& CAPACITY

IMPROVED RELIABILITY

& DELIVERED

SUSTAINABILITY

LOWER OPERATING

EXPENSE

Page 52: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

52

IMPROVED SUPPLY TO CLINICAL OPERATIONS

RESULTS: BENEFITS

Increased Capacity & Reliability

Redundant HPW & WFI B38 B5 B4

Page 53: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

RESULTS: BENEFITS Reduced ~11,000 gallons per day / ~4,050,000 gallons per year Cost savings of ~$32K per year (Water & Sewer) Supports GSK’s strategic goal to reduce Water Consumption

Annual carbon emissions reduction of 348 TONNES CO2 Supports GSK’s strategic goal to reduce Carbon Footprint

New System supplying HPW to Biopharm Development Pilot Plant Eliminated Building 5 Resin Bed Train Service New Bulk Brine & Online Microbial Detection Systems Cost Savings of ~$170,000 per year

Water Consumption

Electrical Energy

Carbon Emissions

Operations

Pumping operations reduced by 88% Cost Savings of ~$28k per year

53

Page 54: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

OPERATING SAVINGS

RESULTS: BENEFITS Online Microbial Detection System

Synchronized Optical

Monitoring

Particulate Size

Microbial Fluorescence

Reduces Regulatory Sampling

Doesn’t Eliminate

Bioburden/Endotoxin 20%

(96) samples/yr

4th System Installed in US

Page 55: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

55

RESULTS: LESSONS LEARNED

Full Control

Replacement: Demo Simulation of Functionality

Integration of

Automation Contractor

Selection of Construction Contractor

WHAT WENT WELL

Procurement Management

WFI Batcher Orifices

WFI Still & Clean

Steam Supply Pressure

PQ1 Failure / ‘Plan B’

COULD HAVE DONE BETTER

Page 56: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

56

SUCCESS!

RESULTS: SUMMARY

CONSTRUCTED & VALIDATED IN LESS THAN 1

YEAR

TWO VALIDATED SYSTEMS

& NEW GENERATION EQUIPMENT

MINIMAL IMPACT TO ON-GOING OPERATIONS

Page 57: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

57

RESULTS: SUMMARY

MINIMIZED DOWNTIME

DELIVERED SUSTAINABILITY

LOWER OPERATING

EXPENSE

INCREASED RELIABILITY

OBJECTIVES EXCEEDED!

Page 58: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

58

RESULTS: SUMMARY OBJECTIVES EXCEEDED!

We kept the Trains on the Tracks

Page 59: Case Study: New High Purity Water System Technologies Deliver Reliability & Sustainability

59

QUESTIONS


Recommended